BMS T&C Manual
BMS T&C Manual
[customer name]
PROJECT:
[project name]
BY:
[DDC Control Company Name]
[ date ]
Table of Contents
Testing & Commissioning Manual
1.
BASE OVERVIEW
Page:
1.1 T&C Organization Chart............................................. 1
1.2 Basewide Network Overview ..................................... 2
1.3 BMS Execution Flowchart .......................................... 3
1.4 DDC Panel Test Flowchart ........................................ 4
1.5 BMS Test Flowchart................................................... 5
1.6 Basewide I/O Point Summary .................................... 6
2.
3.
APPENDIX
A.
1.1
1.2
1.3
1.4
1.5
1.6
PROJECT: XX-XXX
DDC Controllers
Commissioning & Testing Flowchart
Electrical Mechanical
Static Test
Pre-Commissioning
Power-Up Test
DDC Points
Test
DDC Panel
Functional
Test Report
VAV
Functional
Test Report
BMS
Commissioning & Testing Flowchart
BMS Network
Test
BMS
Functional
Test Reports
Final
BMS Tests
Project Manager
Client / Project
Contractor:
Client Name
Project Name
Company Name
Contractor Name
BMS SYSTEM
ELECTRICAL-MECHANICAL STATIC TEST
CONTRACT : ____________
Building : ________________
Panel
Level :
Room No.
________________
ITEM
: _______________________
CHECKED
COMMENTS
Signed
___________________
___________________
Name
___________________
___________________
Company
[Controls Company]
[Witness]
Date
___________________
___________________
: _____________________
Project Manager
Client / Project
Client Name
Project Name
Company Name
Contractor:
Company Name
BMS SYSTEM
PRE-COMMISIONING ELECTRICAL POWER UP TEST
CONTRACT : ____________
Building : ________________
Panel
Level :
CKT
: ______________________
________________
ZONE
NO.
NO.
ROOM NO
TYPE OF DEVICE
COMMENTS
Signed
___________________
___________________
Name
___________________
___________________
Company
[Controls Company]
[Witness]
Date
___________________
___________________
IDCHECKED TAGGED
TESTED
YES / NO
Bldg: _________
Level: _________
Panel: _________
AHU: _________
Performed by:
Date:
Witness by:
Date:
Performed by:
Date:
1 of 3
Witness by:
Date:
Bldg: _________
Level: _________
Panel: _________
AHU: _________
Performed by:
Date:
Witness by:
Date:
Performed by:
Date:
Witness by:
Date:
Performed by:
Date:
Witness by:
Date:
Performed by:
Date:
2 of 3
Witness by:
Date:
Bldg: _________
Level: _________
Panel: _________
AHU: _________
Performed by:
Date:
Witness by:
Date:
ZONE CONTROL:
When the fan is on a PID loop will modulate the zone dampers to maintain the zone space temperature at setpoint.
(AH8_SaFanStatus, AH8_Zone1Dmpr, AH8_Zone1RmTemp, AH8_Zone1RmTempSp)
Performed by:
Date:
3 of 3
Witness by:
Date:
Bldg: _________
Level: _________
Panel: _________
CH: _________
Performed by:
Date:
Witness by:
Date:
LEAD/LAG:
(Control Strategy CH_LeadLag)
When the lead chiller/pump set has 300 hours (adj.) run time logged, the lag set (CH-2) will be designated as lead.
Both units shall be rotated equally. Rotation shall not occur during peak operating hours.
(1080_CHRunTime)
Performed by:
Date:
Witness by:
Date:
Performed by:
Date:
Witness by:
1 of 1
Date:
Bldg: _________
Level: _________
AHU: _________
GENERAL:
The appropriate VAV AHU shall be running at static setpoint.
Occupied/Unoccupied CONTROL:
During occupied hours the VAV boxes shall be commanded to Occupied mode.
(AHU5_VAVOcc)
Performed by:
Date:
Witness by:
Date:
ZONE TEMPERATURE:
Verify the zone temperature using a temperature meter. Verify correct T-Stat height and location. Verify that the TStat is not exposed to false temperatures (ie, Xerox machine, coffee pot, direct sunlight).
Performed by:
Date:
Witness by:
Date:
DAMPER LEAK:
With the AHU running, command the VAV box to Unoccupied mode (damper closed). Verify damper leakage per
box size and BMS specification.
Performed by:
Date:
Witness by:
Date:
COOLING-MODE:
Modify the zone setpoint 20F below the room temperature. Verify: 1) cooling mode, 2) register discharge
temperature, 3) maximum cooling airflow.
Performed by:
Date:
Witness by:
Date:
HEATING-MODE:
Modify the zone setpoint 20F above the room temperature. Verify: 1) heating mode, 2) register discharge
temperature, 3) maximum heating airflow.
Performed by:
Date:
Witness by:
1 of 1
Date:
3.0 BMS
Test & Commissioning
1.1
1.2
1.3
Project Manager
Client / Project
Contractor:
Client Name
Project Name
Company Name
Contractor Name
BMS SYSTEM
NETWORK TEST
CONTRACT : ___________
Building : ________________
Panel
Level :
: ______________________
________________
ITEM
CHECKED
Server(s) installed
Workstation(s) installed
Switches installed
PAD/BBMD installed
Firewall installed
10
INSPECTION DATE
Signed
___________________
___________________
Name
___________________
___________________
[Witness]
Date
___________________
___________________
COMMENTS
PROJECT MANAGER
Company Name
CLIENT / PROJECT
CONTRACTOR
Client Name
Project Name
Contractor Name
Bldg. No:
Room No:
YES
NO
N/A
Performed By:
Witnessed by:
[DDC Control Engineer]
[Witness Engineer]
[QA/QC Engineer]
PROJECT MANAGER
Company Name
CLIENT / PROJECT
CONTRACTOR
Client Name
Project Name
Contractor Name
Bldg. No:
Room No:
Performed By:
YES
NO
N/A
Witnessed by:
[DDC Controls Engineer]
[Witness Engineer]
[QA/QC Engineer]