Garu Bridge Site
Garu Bridge Site
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
Geotechnical Report
Page i
1.0
1.1
Introduction
Foundation investigation has been carried out at proposed River site found in the
Upper East Region.
1.2
Fieldwork
The fieldwork was carried out between 23rd January and 25th January,
2010. To facilitate the attainment of the requirement of the fieldwork, and also
ensure compliance with the requirements of soil sample recovery and
performance of specified field tests such as standard penetration tests and
recovery of undisturbed clayey/compressible soils, a 1-ton mobile cable
percussion boring rig was used to undertake subsoil investigation.
1.3
Percussion drilling in soft ground involved the drilling of two (2No.) boreholes at
Garu. One borehole was drilled at each approach.
The various depths attained in soft ground and decomposed rock are shown in
Table 1 of Appendix A. Sampling and in-situ testing were carried out in the
boreholes in accordance with project specifications.
All boreholes in soft ground were deemed to have attained refusal when a total
of 50 blows have been applied during any one of the three 0.15m (6-ins)
sampler advancement during SPT. The final depths of the boreholes ranged
from 9.6m in BH 1 to 10.0m in BH 2. . Duration for chiseling in each borehole
averaged two (2) hours.
Geotechnical Report
Page 1
Borehole
(Percussion
Drilling)
Depth in Rock
(Chiselling with
California Hammer)
Total
Depth
B1
8.6m
1.0m
9.6m
B2
9.6m
0.4m
10.0m
2.0
Subsurface Conditions
2.1
Introduction
This section present the results of the field activities and samples recovered as
part of the investigations.
2.2
Surficial Soil Profile
The boreholes sunk at the site revealed the following ground
conditions;
Thickness
Average SPT N
11
sandy CLAY
Very loose, moist, greyish/ brown 3.0m 8.6m
15
silty
sandy
refusal
GRAVEL
(Weathered Granite)
Geotechnical Report
Page 2
2.3
Country Rock
Bedrock of weathered Granite belonging to the Middle Precambrian granitic
rocks, with minor belts of Birrimian rocks was encountered in all locations
drilled. It was chiselled at all borehole locations. The geological map indicates
that granite was to be expected along the project corridor. At Garu the material
actually chiseled is greyish, dark brown weathered rock.
2.4
Groundwater Conditions
Groundwater was encountered in all boreholes drilled at the site and it occurred
at depths range of between 2.7m in BH1 and 1.7m in BH2.
At the project corridor, the major rainy season occurs from mid August to
October. Groundwater levels are normally expected to peak at mid September
to mid October and be at lowest in mid December to mid April. Seasonal
fluctuation in groundwater level is dependent on several factors notable are;
geology, rainfall amount, topography, catchment area size, groundwater
abstraction and recharge rates, surface drainage and land-use characteristics.
Geotechnical Report
Page 3
3.0
3.1
The results obtained for N may be used to estimate bearing capacity for
granular soils of weathered granite formations. This is done in conjunction with
estimated width (B) of footing, and this is read off in the relationship established
by Terzargi and Peck curve for soils, ultimate bearing pressure in kN/m
Qult
2
N
B 0.3
B
0.08
The detailed results of allowable bearing capacity have been given in Table 3
of Appendix A.
4.0
At the Garu bridge site, a foundation depth range of between 8.6m 10.0m
should be adopted, this depth will be mainly in the competent weathered
rock horizon.
It is therefore recommended that a design bearing capacity of 500
750KN/m2 be used and footings placed at least between 8.6.0m 9.6m. At
that footing depth, either piles or caissons is to be used.
Geotechnical Report
Page 4
APPENDIX A
Geotechnical Report
Page 5
BOREHOLE LOG
PROJECT:
GARU
LOCATION:
BORING METHOD: Percussion Drilling
ds1
ds2
48
52
30
94
10
90
17
82
89
10
87
13
34
17
56
pH Value
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
8
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
9
9.1
9.2
9.3
9.4
(%)
Chemical
Tests
Cl- (mgl-1)
Type
Shear
Test
Cu (kN/m2)
Level*
(m)
N-value
Soil/Rock Description
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
In-situ
Test
Gravel (%)
Symbol
Soil Profile
SO42- (mgl-1)
Borehole No.: 1
spt1
- Ground water
N=8
59
26
spt2
N=11
56
24
spt3
N=17
32
15
N=5
17
spt4
non- plastic
spt5
N=4
spt6
N=5
spt7
N=17
19
85
N=>50
31
12
85
non- plastic
93
spt8
CPT
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
SO42- - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 2hours advancing 0.6m
Cone Test Performed at 9.3m. There was no penetration after 70 blows.
Geotechnical Report
Page 6
BOREHOLE LOG
PROJECT:
GARU
LOCATION:
BORING METHOD: Percussion Drilling
(%)
pH Value
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
8
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
9
9.1
9.2
9.3
9.4
9.5
9.6
9.7
9.8
9.9
10
Soil/Rock Description
Chemical
Tests
Cl- (mgl-1)
Type
Shear
Test
Cu (kN/m2)
Level*
(m)
N-value
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
In-situ
Test
Gravel (%)
Symbol
Soil Profile
SO42- (mgl-1)
Borehole No.: 2
spt1
42
16
39
61
- Ground water
N=11
37
21
34
66
N=5
21
88
44
56
spt2
spt3
N=3
non-plastic
Very loose wet brown coarse grained
SAND with silt
spt4
N=5
spt5
N=5
spt6
N=12
non-plastic
94
non-plastic
87
50
47
88
10
56
42
95
34
15
spt7
25
12
35
19
27
13
N=13
spt8
N=52
ds2
End of borehole
CPT
N=>67
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
SO42- - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 2hours advancing 0.65m
Cone test performed at 10m. Penetration after 67 blows was 0.05m
Geotechnical Report
Page 7
APPENDIX B
Geotechnical Report
Page 8
Table 3:
Location
BH 1
Foundation Soil
Soil Thickness
Proposed Foundation
Allowable Bearing
Depth
Pressure
Pressure
9.6m
8.6m
1056kN/m
352 KN/m
10.0m
8.6m
1056kN/m
352 KN/m
Geotechnical Report
Page 9
APPENDIX C
SITE PHOTOGRAPHS
Geotechnical Report
Page 10
Geotechnical Report
Page 11
Drilling at Borehole 1
Drilling at Borehole 2
Geotechnical Report
Page 12