Lesson F: Project Schedule Risk Analysis
Presented by
David T. Hulett, Ph.D.
Hulett & Associates, LLC
[email protected]www.projectrisk.com
IPMC 2002 Fall Conference
Professional Education Program
2002 Hulett & Associates
Defining Risk
Project risk is an uncertain event or condition that, if it
occurs, has a positive or negative effect on a project
objective.*
*Guide to the Project Management Body of Knowledge
(PMBOK Guide), 2000 Project Management Institute
2002 Hulett & Associates
Opportunities and Threats
Most
Likely
Estimate
Optimistic
Estimate
Opportunities
Threats
2002 Hulett & Associates
Why Manage Risk?
Ignoring
Ignoringthe
therisk
riskdoes
doesnot
notmake
makeititgo
goaway
away
Our
Ourobjective
objectiveisistototurn
turnvague
vagueuncertainty
uncertaintyinto
into
identified,
identified,quantified
quantifiedrisk
risk
2002 Hulett & Associates
Iron Triangle of Project Objectives
Main three project objectives (a.k.a. Triple Constraint
of project management)
Technical
Technical
Cost
Cost
Schedule
Schedule
Environmental compliance, Safety, Being a good
corporate citizen
2002 Hulett & Associates
Which Objective Defines the Project?
The objectives are interdependent
When one is unmovable, the others need to be flexible
Any pressure on one will be transmitted to the others
Cost
Time
Technical
2002 Hulett & Associates
Performance Objective Traditionally
Comes First
Projects are usually defined by technical, performance,
quality or reliability specifications
The obvious question for a project management
professional:
How much will such a project cost?
How long will it take?
Cost
Time
2002 Hulett & Associates
Technical
But, Schedule May be the Main Goal
If the time factor is crucial
The project may be de-scoped
=> problem with
customer
Resources may be added => cost more to finish on
time
Cost
Time
2002 Hulett & Associates
Technical
Or, Cost May Be the Limiting Factor
Limits on cost will impact both schedule and
performance
Performance may be relaxed or reduced to limit cost
May use less-capable labor, less overtime => takes
longer
Cost
Time
2002 Hulett & Associates
Technical
The Objectives are Interrelated
Pressures from one objective will impinge on others
Pressures also impact on quality and business goals
Cost
Time
Technical
2002 Hulett & Associates
10
Establish Priority of
Project Objectives: Example
Cost
Technical
Performance
Schedule
Must
Have
Nice to
Have
Accept
Result
2002 Hulett & Associates
11
Measuring Objectives
Technical vs. Cost and Time
Cost is denominated in dollars, time in days
Technical objectives No common unit of measurement
Weight
Speed, range, capacity, climbing rate
Software function points, lines of code
Reliability Mean time between failure
Quality measures, costs
2002 Hulett & Associates
12
Using Technical Objectives Measurements
Technical objectives are not comparable
A dollar is a dollar, a day is a day
In Reliability Analysis (Fault Tree)
Each failure mode has a probability of failure there is one
measure of success
Otherwise:How do you trade off climbing rate with
carrying capacity or reliability?
2002 Hulett & Associates
13
Risk Management Processes
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
Source: Guide to the Project Management Body of Knowledge,
(PMBOK Guide, 2000 Project Management Institute
2002 Hulett & Associates
14
Risk Management Plan
Plan your approach to risk management on THIS
PROJECT
Who will manage the risk management process?
Determine approach: quantitative, qualitative, narrative
How frequently will the risk analysis cycle be done?
Budget for the risk management activities
Reference: Project Risk Analysis and Management (PRAM) Guide,
Association for Project Management, 1997
2002 Hulett & Associates
15
Risk Management Processes
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
Source: Guide to the Project Management Body of Knowledge
(PMBOK Guide), 2000 Project Management Institute
2002 Hulett & Associates
16
Risk Breakdown Structure
2002 Hulett & Associates
17
Technical Risk Examples
Major state-of-the-art advance may be needed
Requirements are not stable or are complex and may
be difficult to meet
Operating environment is difficult, and may pose
problems
Logistical challenges in getting equipment to site -- may
be more difficult than anticipated
2002 Hulett & Associates
18
Technical Risk (continued)
Integration requires interfaces between project sections
that may be complex
Reliability / maintainability standards may be
challenging
The design is incomplete or our approach may not work
Concurrency (overlapping of phases) may result in
confusion, missteps and rework
2002 Hulett & Associates
19
Technical Risk (continued)
Test and Evaluation program may not be capable of
assessing performance
Modeling and Simulation may not be adequate to
support the program through all phases
Production capabilities may not be adequate for the
demanding configuration
2002 Hulett & Associates
20
Technical Risk (continued)
The developer may not be capable to design and
manufacture the system
Budget resources may be insufficient
Customer and Contractor management teams may not
be sufficient or adequate
Time available may be insufficient
Source: Risk Management Guide for DoD Acquisition, Defense Acquisition
University, January 2000
2002 Hulett & Associates
21
SEI Categories for Software
Development Risk
Examine risks in several areas
Technical aspects of engineering software products
Environment within which the development takes place
Constraints to successful software development
Software Engineering Institute at Carnegie Mellon
University
www.sei.cmu.edu
2002 Hulett & Associates
22
Technical Risk - Top Ten Checklist of
Software Risks - Barry Boehm
Barry Boehm has written several articles that are
included in his edited volume: Software Risk
Management, IEEE Computer Society Press, 1989
(out of print).
This list is from his presentation to the Southern
California Risk Management Symposium, Sept.
2002
2002 Hulett & Associates
23
The Top Ten Software Risk Items Barry Boehm
Risk Item
Risk Management Techniques
1. Personnel Shortfalls
Staffing with top talent; key personnel
agreements; incentives; team-building; training;
tailoring process to skill mix; peer reviews
2. Unrealistic schedules
and budgets
Business case analysis; design to cost; incremental
development; software reuse; requirements descoping;
adding more budget and schedule
3. COTS; external components
Qualification testing; benchmarking; prototyping;
reference checking; compatibility analysis; vendor
analysis; evolution support analysis
4. Requirements mismatch;
gold plating
Stakeholder win-win negotiation; business case
analysis; mission analysis; ops-concept formulation;
user surveys; prototyping; early users manual;
design/develop to cost
5. User interface mismatch
Prototyping; scenarios; user characterization
(functionality, style, workload)
2002 Hulett & Associates
24
The Top Ten Software Risk Items Barry
Boehm (Continued)
Risk Item
Risk Management Techniques
6. Architecture, performance,
quality
Architecture tradeoff analysis and review boards;
simulation; benchmarking; modeling; prototyping;
instrumentation; tuning
7. Requirements changes
High change threshold; information
hiding; incremental development (defer
changes to later increments)
8. Legacy software
Design recovery; phaseout options analysis;
wrappers/mediators; restructuring
9. Externally-performed
tasks
Reference checking; pre-award audits;
award-fee contracts; competitive design
or prototyping; team-building
10. Straining Computer
Science capabilities
Technical analysis; cost-benefit analysis;
prototyping; reference checking
2002 Hulett & Associates
25
Common Colds of the Software World:
Capers Jones
Creeping user requirements
Excessive schedule pressure
Poor quality
Inaccurate estimation of costs
Inaccurate metrics and measurement
Management malpractice
Silver bullet syndrome
Source: Capers Jones, Assessment and Control of Software Risks,
Prentice Hall, Yourdon Press, 1994
2002 Hulett & Associates
26
Checklist Example
Project Risk Checklist
Project Name
Project Manager
Risk Type
Risk Area
Technology
Design
Organizational
Objectives
Resources
Customer
Regulatory
Expectations
Interface
Funding
Permit Required
Description of
Uncertainty
Resolution
(Action,
Evaluation of Risk
(present, importance) responsible)
Complexity
State-of-the-Art
Integration
Unclear
Changing
Compete w/ other proj.
Inexperienced
Unrealistic
Vague, changing
Not timely
Intermittant
Uncertain requirements
Uncertain timing
2002 Hulett & Associates
27
Risk Identification Tools: Brainstorming
Have the right people in the room
Expose the people to the project
Have them prepare for the session
Get them off-site to concentrate
Use the checklist developed on other projects
Lessons Learned files
Synergy among the participants
2002 Hulett & Associates
28
Sources of Data on Technical Risk
Comparison with similar systems
Relevant lessons learned
Experience
Results from tests and prototype development
Data from engineering and other models
Specialist and expert judgment
Analysis of plans and related documents
Modeling and simulation
Source: Risk Management Guide for DoD Acquisition, Defense Acquisition
University, January 2000
2002 Hulett & Associates
29
Risk Management Processes
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
Source: Guide to the Project Management Body of Knowledge
(PMBOK Guide), 2000 Project Management Institute
2002 Hulett & Associates
30
Willoughby Templates
In early 1980s, W. J. Willoughby, Jr was chairman of the
Defense Science Board
DSB developed a way to look at risk in Defense
Acquisition programs using a simple template approach
What is the problem?
How can it be addressed?
When in the project life cycle should risk mitigation take
place
Represents Lessons Learned
2002 Hulett & Associates
31
Defense Science Boards
Findings and Recommendations
Most new weapon systems are less than satisfactory
and require burdensome maintenance and logistics
requires additional equipment in order to meet the
needs..
programs cannot succeed for technical reasons
A poorly designed produce cannot be tested efficiently,
produced or deployed.
Manufacturing problems will overwhelm production
schedules and costs
2002 Hulett & Associates
32
Defense Science Boards
Findings and Recommendations (continued)
Corrective measures by the DoD have focused on
establishing a series of management checkpoints and
review activities
this approach has been responsible for adding
numerous layers of management and has tended to
compartmentalize, matrixize and polarize the major
areas of the acquisition process: design, test and
productionthey do not describe the industrial process
2002 Hulett & Associates
33
Defense Science Boards
Findings and Recommendations (continued)
The probable cause (of the problems facing acquisition
programs) is inadequate engineering and manufacturing
disciplines combined with improperly defined and
implemented logistics programs.
Identify and establish critical engineering process and
their control methods
Transition from Development to
Production, Solving the Risk Equation
DoD 4246.7-M, January 1984
2002 Hulett & Associates
34
Overriding Attributes of the Defense
Science Boards Recommendations
Assurance of design maturity
Assessment of contractors design policy
Measurement of test stability
Near absence of failures in development testing of a
stable design
Certification of manufacturing processes
Design for production and proof of process
2002 Hulett & Associates
35
Willoughby Templates Top Level
Top Level of the Willoughby Templates
2002 Hulett & Associates
36
Willoughby Templates Detail
2002 Hulett & Associates
37
Willoughby Templates Detail (continue)
2002 Hulett & Associates
38
Willoughby Templates Detail (continue)
2002 Hulett & Associates
39
Example Template: Design Requirements
Area of Risk
Accurate and complete specification of the design
reference mission profile is required
Sometimes the profile does not correspond to the
ultimate service use
Often the profile is left to the contractors discretion
2002 Hulett & Associates
40
Example Template:
Design Requirements (continued)
Outline for Reducing Risk
Functional mission profile shows all functions on a time
scale prepared by the government customer
Environmental mission profile showing the surroundings
affecting the system
Contractor prepares profiles based on the governments
and become the design requirements
Timeline
During concept phase (JMSNS phase)
2002 Hulett & Associates
41
Qualitative Ranking of Risks
Group the risks into categories for appropriate action
This may be enough to manage risk effectively
Risk Ranking
High Risk
Risk Management Action
Stop Light Condition
RED
Resolve or mitigate in baseline plan
Moderate Risk
YELLOW
Resolve or develop a contingency plan
Low Risk
GREEN
Leave resolution to project team
2002 Hulett & Associates
42
Maxwell Risk Driver Assessment Matrix
Maxwell Risk Driver Assessment Framework
Risk Level
Very Low
Low
Medium
Minor Modifications Major
RequiredTechnical
1
Nothing New
Advancement
Only
Modifications
Currently in
Under
2 Tech;nology Status
Prototype Exists
Use
Development
Somewhat
Moderately
3 Complexity
Simple
Complex
Complex
Independent of Dependent on One Dependent on
Interaction /
Two Additional
Additional Risk
Other Risk
4
Dependencies
Risk Drivers
Driver
Drivers
Risk Driver Category
5 Process Controls
Manufacturing
Precision
High
State of the Art
In Design
Highly Complex
Dependent on
Three Additional
Risk Drivers
Very High
Beyond State of the
Art
Concept Stage
Highly Complex with
Uncertainties
Dependent on more
than Three Additional
Risk Drivers
Statistical
Documented
Limited
Process
Controls (No SPC) Controls
Controls (SPC)
Inadequate
Controls
No Known Controls
High
Known but
Inadequate
Unknown
Adequate
Limited Margins
2002 Hulett & Associates
43
Maxwell Risk Driver Assessment Matrix
(continued)
Maxwell Risk Driver Assessment Framework
Risk Driver Category
Risk Level
Medium
High
Very Low
Low
Reliability
Historically
High
Average
Producibility
Established
Demonstrated
Criticality to
Mission
Nonessential
Minimum Impact
Cost
Established
Known History or
Close Analogies
Schedule
Demonstrated Historical Similarity
Very High
Known Limited Serious Problems
Infeasible
Problems
of Unknown Scope
Feasible
Known
Alternatives
Available
Predicted by
Calibrated
Model
Known Difficulties Infeasible
Validated
Analysis
Inadequate
Analysis
2002 Hulett & Associates
Possible
"Show Stopper"
Alternatives Exist
Out of Range of
Experience
Unknown or
Unsupported
Estimate
Unknown or
Unsupported
Estimate
44
Probability and Impact Define Risk
Risk is defined by two dimensions of a possible event
Probability that the event will occur
Impact on the project objectives (cost, time,
performance) if it does occur
Discussions about risk rely on these two dimensions
The two attributes of probability and impact must be
considered separately
Impact
Impactisisindependent
independentofofhow
howlikely
likelythe
theevent
eventisis
2002 Hulett & Associates
45
Qualitative Assessment of
Probability from Technology Maturity
Technology Maturity
Scientific research ongoing
Concept design formulated for performance and
qualifications
Concept design tested for performance and qualification
concerns at bench scale
Critical functions / characteristics demonstrated at pilot
scale
Full-scale prototype hardware passed qualification tests
with ACWA feedstocks
More than one full scale facility operational and deployed
2002 Hulett & Associates
Probability
Very High
High
Moderate
Moderate
Low
Very Low
46
Probability of Risk from
Process Complexity
Process Complexity Risk
Five or more processes/technologies including complicated
interfaces or complex operations
Two to four processes/technologies with complicated interfaces
and complex operations
Two processes/technologies with either complicated interfaces or
complex operations
Two processes/technologies in a single processing train, and
standard interfaces with routine operations
One process/technology and standard interfaces with routine
operations
Probabilty
Very High
High
Moderate
Low
Very Low
Complicated interfaces: multiphase streams, extreme conditions beyond industrial norms
Complex operations: multiple interactive and interrelated activities beyond industrial norms
2002 Hulett & Associates
47
Probability of Risk from
Process Difficulty
Process Difficulty Risk
No comparable process is operating on an industrial
scale, and more than one of: C, T, TP, or PC is expected
to exceed state of the art
No comparable process is operating on an industrial
scale, and at least one of the requirements for C, T, TP,
or PC are expected to exceed state of the art
Integrated process is combination of standard industrial
processes and C, T, TP, or PC exceed norm for these
processes
Integrated process is a combination of standard
industrial processes and C, T, PC or TP are within the
norm for these processes
Standard industrial process meets C, T, TP, and PC
requirements
C = Conversion efficiency, T = Tolerance or precision
TP = Throughput, PC = Process controls
2002 Hulett & Associates
Probability
Very High
High
Moderate
Low
Very Low
48
Qualitative Assessment of
Impact on Performance
Impact of Risk on Performance Objective
Impact
System requirement not achieved, safety and
environmental objectives jeopardized
System requirement not achieved, safety and
environmental objectives satisfied
Degradation of system performance eliminates all margins
Degradation of subsystem performance, decrease in
system performance (still above requirement)
Potential degradation of subsystem performance, but
system level not affected
No effect on subsystem or system performance (includes
producibility and support)
2002 Hulett & Associates
Very High
High
Moderate
Moderate
Low
Very Low
49
Qualitative Assessment of P & I
Emphasis on Impact
Qualitative Risk Analysis: Probability - Impact Approach to Project Risk Analysis
Probability
Very high
Mod
Mod
High
High
High
High
Low
Mod
Mod
High
High
Moderate
Low
Mod
Mod
High
High
Low
Low
Low
Mod
Mod
High
Very low
Low
Low
Low
Mod
Mod
Very Low
Low
Moderate
High
Very High
Impact on Project Objective
2002 Hulett & Associates
50
Probability and Impact by the Numbers
Assessing probability and impact verbally is too vague,
easy to make mistakes
On purpose
By design
Because of inattention
Defining the levels by objective criteria helps
Applying numbers to risk probability and impact seems
to improve concentration, increase discipline
2002 Hulett & Associates
51
Probability by the Numbers:
Technology Maturity (natural)
Technology Maturity
Scientific research ongoing
Concept design formulated for performance and
qualifications
Concept design tested for performance and qualification
concerns at bench scale
Critical functions / characteristics demonstrated at pilot
scale
Full-scale prototype hardware passed qualification tests
with ACWA feedstocks
More than one full scale facility operational and deployed
2002 Hulett & Associates
Probability
0.9
0.8
0.6
0.4
0.3
0.1
52
Impact by the Numbers: Performance
Objective (more problematic)
Many people feel comfortable assigning numbers to the
impacts
Numbers imply cardinality meaning that the relation
between the numbers means something
An impact rated .6 is 3 times as bad as one rated .2
DoD recommends avoiding cardinal numbers in favor
of ordinal rankings (one is worse than the lower one)
E.g. Impacts rated A / B / C / D / E
2002 Hulett & Associates
53
Compare Impact Neutral
and Impact Aversion
Example of Different Impact Scales Reflecting
Organizational Preferences
Linear, Impact
Non Linear, Impact
Risk Impact Level
Neutral
Averse
Very High
High
Moderate
Low
Very Low
0.9
0.7
0.5
0.3
0.1
2002 Hulett & Associates
3.2
1.6
0.8
0.4
0.2
54
Impact on Performance by the Numbers
Impact of Risk on Performance Objective
Impact
System requirement not achieved, safety and
environmental objectives jeopardized
System requirement not achieved, safety and
environmental objectives satisfied
Degradation of system performance eliminates all margins
Degradation of subsystem performance, decrease in
system performance (still above requirement)
Potential degradation of subsystem performance, but
system level not affected
No effect on subsystem or system performance (includes
producibility and support)
2002 Hulett & Associates
3.2
1.6
0.8
0.4
0.2
0.1
55
Computing the Technical Risk Score
The Risk Score can be computed by multiplying
probability times impact
Prob. of .4 and impact of .7 yields a score of .28
The organization can determine the cutoff for each level
of Risk Score
Risk Ranking
High Risk
Moderate Risk
Low Risk
Stop Light Condition Cut-Off for Risk Score
RED
.30 < X
YELLOW
.15 < X < .30
GREEN
X < .15
2002 Hulett & Associates
56
Computing the Risk Score
Probability and Impact Risk Scores
Risk = P x I
Probability
0.9
0.18 0.36 0.72 1.44
0.7
0.14 0.28 0.56 1.12
0.5
0.10 0.20 0.40 0.80
0.3
0.06 0.12 0.24 0.48
0.1
0.02 0.04 0.08 0.16
0.2
0.4
0.8
1.6
2.88
2.24
1.60
0.96
0.32
3.2
Impact (Ratio Scale)
2002 Hulett & Associates
57
DoD Generally Recommends Against
Using Cardinal Values for Impact
This (use of numbers to calculate risk such as P x I)
may be suitable if both likelihood and consequences
have been quantified using compatible cardinal scales
or calibrated ordinal scales (e.g. using Analytic
Hierarchy Process). In such a case mathematical
manipulation of values may be meaningful
Source: Risk Management Guide for DoD Acquisition, DAU,
January 2000
2002 Hulett & Associates
58
DoD Generally Recommends Against Using
Cardinal Values for Impact (continued)
In many cases, however, risk scales are actually just
raw (uncalibrated) ordinal scales, reflecting only relative
standing between scale levels and not actual numerical
differences.
Any mathematical operations performed on results
from uncalibrated ordinal scales can provide
information that will at best be misleading, if not
completely meaningless
2002 Hulett & Associates
59
Risk Management Processes
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
Source: Guide to the Project Management Body of Knowledge,
2000 Project Management Institute
2002 Hulett & Associates
60
Decision Tree Analysis
Making Decisions with Uncertainty
Decision analysis helps structure the problem
Disciplined approach
Decisions to be made
Events that can happen, likelihood and impact
Costs and benefits of making some decisions, having
some events happen
2002 Hulett & Associates
62
Completed Simple Tree with Decisions,
Events, Costs, Rewards and Probabilities
35%
High
500
350
Market Demand
Greenfield
-150
65%
Low
300
150
Plant Decision
35%
High
400
365
Market Demand
Retrofit
-35
65%
Low
200
165
35%
High
300
300
Market Demand
None
0
Low
2002 Hulett & Associates
65%
150
150
63
Folding Back To Solve the Tree
Value of $235 moves from right to left
35%
High
500
350
Market Demand
Greenfield
-150
220
65%
Low
300
150
Plant Decision
235
35%
High
400
365
Market Demand
Retrofit
-35
235
65%
Low
200
165
35%
High
300
300
Market Demand
None
0
2002 Hulett & Associates
Low
202.5
65%
150
64
150
Changing Costs may Change Results and
Value
35%
High
500
350
Market Demand
Greenfield
-150
220
65%
Low
300
150
Plant Decision
220
35%
High
400
335
Market Demand
Retrofit
-65
205
65%
Low
200
135
35%
High
300
300
Market Demand
None
0
Low
2002 Hulett & Associates
202.5
65%
150
150
65
System Reliability:
System Failure Analysis
Purposes of a System Failure Analysis
Analyze the possible ways a facility, product or system
might fail
Understand how to build a more fault-tolerant facility
Discover what happened if it failed (e.g. plane crash)
Determine design that is efficient use of funds to keep
the facility running
Evaluate different competing designs from the failure
perspective
2002 Hulett & Associates
67
Simple Failure Analysis Model
What makes the room go dark in the evening?
We have two lamps, desk and floor
Specify the objective
To have a conversation, we need at least one light and
Failure means that both lights go out (BOTH .. AND)
To read by, we need both lights and failure means one
light goes out (EITHER .. OR)
2002 Hulett & Associates
68
Quantitative Analysis of the
Two
-Element Fault Tree
Two-Element
Suppose that the failure rates are as follows:
Floor lamp fails 4% of the time over a month
Desk lamp fails 5% of the time over a month
What is the likelihood that the room will be completely
dark in the evening, over the month?
An And Gate requires:
Both
Boththe
theFloor
FloorLamp
Lampand
andthe
theDesk
DeskLamp
Lampmust
mustFail
Fail
These are redundant
systems,
failure is unlikely
2002 Hulett
& Associates
69
AND Gate
-- Only 0.2% Likelihood
Gate-of a Completely Dark Room
Fault Tree Analysis
State of Being
Floor On, Desk On
Floor On, Desk Off
Floor Off, Desk On
Floor Off, Desk Off
Likelihood
Floor Lamp Desk Lamp
95.0%
96.0%
96.0%
5.0%
4.0%
95.0%
4.0%
5.0%
Total Likelihood
2002 Hulett & Associates
Joint Likelihood
of Occurrence
91.2%
4.8%
3.8%
0.2%
100.0%
70
Complete Darkness? Simple AND Gate
in Software
The likelihood is shown on the solved fault tree
Result
And Gate
Likelihood
of Failure
2002 Hulett & Associates
71
Suppose Bright Light and
Both Lamps are Necessary?
This is an OR GATE
The condition of Bright Light fails if:
Either
Eitherthe
theFloor
FloorLamp
Lampor
orthe
theDesk
DeskLamp
LampFails
Fails
This is a more common occurrence
These are not redundant systems any more
2002 Hulett & Associates
72
OR Gate 8.8% Likely That At Least One
Lamp Fails
Likelihood of failure increases to 8.8%
Fault Tree Analysis
State of Being
Floor On, Desk On
Floor On, Desk Off
Floor Off, Desk On
Floor Off, Desk Off
Likelihood
Floor Lamp Desk Lamp
95.0%
96.0%
96.0%
5.0%
4.0%
95.0%
4.0%
5.0%
Total Likelihood
2002 Hulett & Associates
Joint Likelihood
of Occurrence
91.2%
4.8%
3.8%
0.2%
100.0%
73
Fault Tree for Room Relatively
Dark, with Probabilities -- OR Gate
The likelihood that either / or failure occurs is 8.8%
Result
Or Gate
Likelihood
of &Failure
2002 Hulett
Associates
74
Risk Management Processes
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
Source: Guide to the Project Management Body of Knowledge
2000 Project Management Institute
2002 Hulett & Associates
75
Project Life Cycle, Risk and Risk
Management
Total Project Life Cycle
INCREASING RISK
CONCEPT
Execute
DEVELOPMENT
Opportunity and Risk
IMPLEMENTATION
TERMINATION
EFFECT OF RISK
MANAGEMENT
INCREASING VALUE
Plan
Amount at Stake
TIME
2002 Hulett & Associates
76
Evaluate a
Risk Response (Handling) Option
Can it be feasibly implemented?
What is its expected effectiveness?
Is it affordable?
Is time available to develop the option? What is its
impact on the schedule?
What effect does it have on the systems technical
performance
Source: Risk Management Guide for Acquisition, DAU 2000
2002 Hulett & Associates
77
Risk Avoidance
Eliminating the risk event
Relax the project objective
Severing the link to the project objective
Any risk for which the Triple Constraint can be relaxed
2002 Hulett & Associates
78
Risk Mitigation (Handling)
Design Immaturity Risk
Fall back to a less demanding design
Extend the time of the design phase to get it right
Rapid prototyping of the user interface
Design Uncertainty Risk
Parallel development
This is an expensive risk response strategy
2002 Hulett & Associates
79
Risk Mitigation (Handling)
Process Immaturity Risk
Test components
Test the integrated system at a scale factor
Semi-works tests at a larger scale
May need to test some components at full-scale
2002 Hulett & Associates
80
Some other Handling Options
Trade Studies Arrive at a balance of engineering
requirements
Incremental Development Design for later upgrade
Technology Maturation Plan to replace current
technology with preferred technology on Unit 2
Robust Design Use advanced design and
manufacturing techniques to promote quality, may be
costly
2002 Hulett & Associates
81
Some other Handling Options
Design of Experiments I.D. critical design factors and
focus on those
Open Systems Carefully selected commercial
specifications and standards
Use Standard Items / Software reuse
Modeling / simulation of the system
Manufacturing screening to identify deficient
manufacturing processes
Source: Risk Management Guide for Acquisition, DAU 2000
2002 Hulett & Associates
82
Software Risks: Capers Jones
Creeping User Requirements
New and unanticipated user requirements added after the
project is initiated and estimated
User requirements creep at about 1% per month
Mitigation
Prototyping can reduce the severity and volume of this
2002 Hulett & Associates
83
Software Risks: Capers Jones
Poor Quality
Mitigation
Result of technical and cultural issues
Not use effective defect prevention, removal therapies
Corporate culture not committed to quality
Test planning
Requirements analysis up front
Formal inspection
Beta testing with many users
Formal defect prevention
2002 Hulett & Associates
84
Software Risks: Capers Jones
Inaccurate Metrics
Proven as early as 1978 that lines of code cannot safely
be used to size projects, especially when multiple
languages exist.
Impact is poor measurement of productivity, cost and
schedule estimation and project planning
Mitigation
Jones promotes the use of function points as accurate
metrics
2002 Hulett & Associates
85
Software Risks: Capers Jones
Management Malpractice
Managers not trained for their jobs, not rewarded for good project
management skills
Culture lacks awareness of good practices
No training or good curriculum in schools
Mitigation
Understand what is needed
Allocate training resources, acquire courses
Elevate project management status in company
Establish best in class culture of professionalism
2002 Hulett & Associates
86
Checklist of Software Risk Items:
Barry Boehm
Developing the wrong software functions
Risk management techniques
Organization analysis
Mission analysis
Ops-concept formulation
User surveys
Prototyping
Early users manuals
2002 Hulett & Associates
87
Checklist of Software Risk Items:
Barry Boehm
Developing the wrong user interface
Risk management techniques
Prototyping
Scenarios
Task analysis
User characterization (functionality, style, workload)
2002 Hulett & Associates
88
Checklist of Software Risk Items:
Barry Boehm
Gold plating
Risk management techniques
Requirements scrubbing
Prototyping
Cost-benefit analysis
Design to Cost
2002 Hulett & Associates
89
Risk Transfer
Key for large projects
Contract provisions include conditions for customer or
supplier paying
Type of contract may deflect from customer to contractor or
vice versa
Fixed price contracts may limit customers cost exposure
It may increase cost if there are engineering change orders
2002 Hulett & Associates
90
Risk Deflection Between Customer
and Contractor / Supplier by Contract
Contractor and Customer Risk
80
60
40
20
1
Cost Plus
9 10
Relative Risk
100
Contractor Risk
Customer Risk
Fixed Price
2002 Hulett & Associates
91
Contingency Planning
Plan B is the contingency if the baseline plan does not
work out
Plan B will be developed, then kept for emergency
Identify the events that might trigger the need for Plan B
Identify the value or characteristics of the trigger events
that would initiate Plan B
Monitor those trigger points in Risk Monitoring and
Control
2002 Hulett & Associates
92
Risk Acceptance:
Set a Dollar Contingency Reserve
The best way is to:
Quantify risks and perform a Monte Carlo simulation
Agree on the organizations risk tolerance and pick the
point on the cumulative distribution
A short cut that may be helpful -- use the averages with
Method of Moments
2002 Hulett & Associates
93
Risk Acceptance:
Take the Right Risks
Accepting the Right Risks and Setting Contingency Amounts
Risk Accepted
Subcontractor late
Likelihood Impact
a
40%
b
250
Expected
Mitigation Strategy
Value
c=axb
100 Use Old Subcontractor
Mitigation
Expected Savings
Cost
d
250
d-c
150
Expected value of the risk is less than mitigation costs
Take the right risks
2002 Hulett & Associates
94
But Establish
a Contingency Reserve
Risk Accepted
Subcontractor late
Part not pass the test
Design assumption faulty
Likelihood
Impact
Expected
Value
a
40%
30%
20%
b
250
350
650
c=axb
100
105
130
Total
335
Set the right contingency reserve
Set at the expected value if have enough risks
2002 Hulett & Associates
95
Content of the Risk Register
Date risk latest revised
Name
Description
Responsibility for monitoring, mitigating, reporting
Risk before further risk mitigation described in the Risk
Register
2002 Hulett & Associates
96
Content of the Risk Register (continued)
Risk mitigation options chosen
Timing of the action -- now, later, contingent
Fallback plans if action fails
Amount of risk expected to remain after risk
management
2002 Hulett & Associates
97
Risk Management Processes
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
Source: Guide to the Project Management Body of Knowledge,
2000 Project Management Institute
2002 Hulett & Associates
98
Risk Monitoring and Control
Risk Analysis is a continuing requirement
Cycle through identification, assessment, quantification
and response planning
Keep track of the identified risks (watch list)
Identify residual risks
Assure the execution of risk plans or if new plans should
be developed
2002 Hulett & Associates
99
Risk Monitoring and Control (continued)
Test and Evaluation (T&E) monitoring the performance of
selected risk handling options and developing new risk
assessments
Test-Analyze-and-Fix (TAAF) use a period of dedicated testing
to identify and correct deficiencies
Demonstration Events points in the program where technology
and risk abatement are demonstrated
Program metrics measure how well the system is achieving its
objectives, monitor corrective action
Source: Risk Management Guide for Acquisition, DAU 2000
2002 Hulett & Associates
100
Earned Value Analysis
Earned Value Management System (EVMS)
Helps forecast the budget and schedule at completion
Augments quantitative risk analysis
Based on data from the project itself, in an early stage
Earned Value has exhibited a reliable ability to predict
results at completion early in the project (e.g. at 20%
complete)
2002 Hulett & Associates
101
Picture of a Troubled Project
Earned Value Management System
120
80
60
40
Over Cost
Behind Schedule
Plan
Earned Value
Actual
20
19
17
15
13
11
0
1
Dollars
100
Project Months
2002 Hulett & Associates
102
Earned Value Forecast of a Troubled
Project
160
Status at Planned
Completion
140
100
Plan
Time Now
80
Earned Value
Actual
60
40
Projected EV
Projected Actual
20
22
19
16
13
10
0
1
Dollars
120
Project Months
2002 Hulett & Associates
103
Technical Performance Measurement
Technical Performance Measurement (TPM)
Identify key technical goals or targets to be made
through the project
Set the targets in the schedule, usually at key milestones
Measure technical achievements
Compare measured achievements to the technical
baseline
Variances between actual achievements and the
baseline lead to warnings of technical risk of completion
2002 Hulett & Associates
104
satisfaction
Technical Performance Measurement
(continued)
Targets should have meaning for technical risks
Technical targets all support the successful completion
of the project
These targets should have predictive value
If they are not met, you are in trouble
Identifying and scheduling the technical performance is
key
2002 Hulett & Associates
105
Technical Performance Measurement
(continued)
Variances from the technical baseline early in the
project are hard to make up later
Variances are accompanied with schedule and budget
implications
Some projects go on with only partial completion of
technical requirements at milestones
These projects may be in trouble
Catching up may be difficult and / or costly and / or take
more time
2002 Hulett & Associates
106
Technical Performance
Starts Well, Falls Behind
Technical Performance Measurement
Technical Metric
100
80
Technical
Plan
Technical Shortfall
60
40
Technical
Performance
To-Date
20
0
0
10
15
20
Project Months
2002 Hulett & Associates
107
Technical Performance Metric
of a Troubled Project
Status at Revised
Time Now
Completion
100
Technical Plan
80
60
Technical
Performance ToDate
Technical To-Go
40
20
25
22
19
16
13
10
0
1
Performance Metric
Forecasting
Technical Risk with TPM
Project Months
2002 Hulett & Associates
108
Project Closeout
Data gathering
Lessons Learned data base
Help future projects
Make it possible for future project managers to access
the data easily, learn the lessons clearly
2002 Hulett & Associates
109
Project Schedule Risk Analysis
CPM-500 Principles of Technical Management
Presented by
David T. Hulett, Ph.D.
Hulett & Associates, LLC
[email protected]www.projectrisk.com
2002 Hulett & Associates
110