Community Finance Manual-5.18.11
Community Finance Manual-5.18.11
Community Finance Manual-5.18.11
ACRONYMS
CHAPTER 1: INTRODUCTION
5
6
7
8
8
9
10
1.1
1.2
1.3
1.4
1.5
1.6
Sub-project Conceptualization
Technical Assistance Fund
Sub-project Preparation and Development
Sub-project Consultation and Approval
Transactions
Payments
Processing and Flow of Documents
Withholding Taxes
Supporting Documents
Cash Disbursement Internal Control Guidelines
Recording and Filing
11
12
13
17
18
19
23
24
24
27
28
29
30
38
39
39
40
41
43
44
44
45
47
54
61
62
Classification
In Kind Contributions
Valuation and Costing
Recording and Filing
64
65
65
66
66
67
69
70
70
71
73
75
76
77
78
80
81
81
82
84
85
88
89
93
101
101
103
104
105
105
107
108
108
109
ACRONYMS
AC
ACPP
ACT
AIC
AR
BA
BAC
BDC
BIR
BLGU
BSPMC
CBIS
CEAC
CERS
CF
CO
COA
CPA
CPS
CSW
DAC
DOD
DSWD
DV
EWT
ExeCom
FM
FMS
FO
GMP
GOCC
IGP
KALAHI-CIDSS
KC
LBP
LCC
LCE
LGU
MCT
MDC
Area Coordinator
Actual Community Procurement Packaging
Area Coordinating Team
Audit and Inventory Committee
Acknowledgment Receipt
Barangay Assembly
Bids and Awards Committee
Barangay Development Council
Bureau of Internal Revenue
Barangay Local Government Unit
Barangay Sub-Project Management Committee
Capacity Building and Implementation Support
Community Empowerment Activity Cycle
Community Employment Record Sheet
Community Facilitator
Central Office
Commission on Audit
Certified Public Accountant
Community Process Specialist
Criteria Setting Workshop
Deputy Area Coordinator
Deed of Donation
Department of Social Welfare and Development
Disbursement Voucher
Expanded Withholding Tax
Executive Committee
Financial Management
Financial Management System
Field Office
Government Money Payments
Government-Owned and Controlled Corporations
Income Generating Project
Kapitbisig Laban sa Kahirapan-Comprehensive and
Integrated Delivery of Social Services
KALAHI-CIDSS
Land Bank of the Philippines
Local Counterpart Contribution
Local Chief Executive
Local Government Unit
Municipal Coordinating Team
Municipal Development Council
ME
MFA
MIAC
MIBF
MIT
MLGU
MOA
MTA
NGA
NGO
NOL
NPMO
NPMT
O&M
OR
PCF
PCPP
PCV
PIT
PO
PO
POW
PPT
PRA
PT
RCIS
RER
RFA
RFFP
RFR
RPD
RPM
RPMO
RPMT
SPA
SPI
TAF
TIN
TOR
TWG
VAT
VLCC
Municipal Engineer
Municipal Financial Analyst
Municipal Inter-Agency Committee
Municipal Inter-Barangay Forum
Monitoring and Inspection Team
Municipal Local Government Unit
Memorandum of Agreement
Municipal Trust Account
National Government Agency
Non-Government Organization
No Objection Letter
National Project Management Office
National Project Management Team
Operation and Maintenance
Official Receipt
Petty Cash Fund
Planned Community Procurement Packaging
Petty Cash Voucher
Project Implementation Team
People's Organization
Purchase Order
Program of Work
Project Preparation Team
Participatory Resource Allocation
Procurement Team
Regional Community Infrastructure Specialist
Reimbursement Expense Receipt
Regional Financial Analyst
Regional Finance Focal Person
Request for Fund Release
Regional Project Director
Regional Project Manager
Regional Project Management Office
Regional Project Management Team
Sub-Project Agreement
Sub-Project Implementation
Technical Assistance Fund
Tax Identification Number
Terms of Reference
Technical Working Group
Value-Added Tax
Voucher for Local Counterpart Contribution
CHAPTER 1
INTRODUCTION
Key Project Principles
Project Goals and Objectives
Project Components
Sub-projects eligible for financing
Sub-projects not eligible for financing
Utilization of Community Grants
Demand-driven
Communities are encouraged to prioritize their own needs, design their
own projects and decide on how resources are used.
Simple
All procedures and components of the project are kept simple to enable
all players to easily understand and become fully involved in the Project.
Sustainable
All barangay projects shall have viable long-term plans for operations and
maintenance and sustainability.
1. 3 Project Components
The Project is comprised of the following components: Capability Building
and Implementation Support, Community Grants, Monitoring and
Evaluation, which are discussed in detail below:
Capability Building and Implementation Support
Social Mobilization and Community Organizing.
KALAHI-CIDSS mobilizes local communities to participate in the
Project through provision of technical assistance by facilitators and
community organizations.
Capacity Building and Technical Support.
KALAHI-CIDSS strengthens the capacity of local communities and
local government units to initiate, plan and implement, manage and
supervise barangay sub-projects, through the provision of technical
assistance, training and workshops.
Community Grants
The Project carries out community development sub-projects,
including investment in economic and social infrastructure,
environmental conservation measures and capacity building, through
the provision of grants to barangays.
The Project also carries out audits of the records, accounts and
financial statements of expenditures relating to the implementation
of community development sub-projects.
Monitoring and Evaluation
The Project strengthens the capacity of the National Project
Management Office and local communities to monitor and evaluate
implementation of the Project and barangay sub-projects,
respectively through the development of baseline data and
computerized management information system.
11.
12.
Travel;
13.
14.
15.
10
CHAPTER 2
FINANCIAL MANAGEMENT STRUCTURE
AND FUNCTIONS
Project Financial Management Structure and Functions
Financial Management Role of the Coordinating Teams
Barangay Sub-project Management Structure
Financial Management Role of the Community
Financial Management Functions
11
2.1 Project
Functions
Financial
Management
Structure
and
Finance
Service
Regional Office
Regional
Project
Management
Office
Manage
ment
Division
Area
Coordinating
Team
Municipal
Coordinating
Team
Municipal InterBarangay
Forum
(MIBF)
Barangay
Assembly and
Sub-project
Implementation
12
13
14
15
RFFP Coordinator
Assume full responsibility of Regional Financial Analyst in monitoring all
financial transactions of on-going sub-projects in phase out areas.
Render technical assistance to all designated RFFP to ensure validity
and accuracy of community fund disbursements.
Review the accuracy, completeness and validity of the RFR and the
accompanying documents of phase out areas with the assistance of the
RFA. He/She shall also review accuracy, completeness and validity of
the RFR and the accompanying documents of current areas in the
absence of RFA.
Certify correctness of the financial aspect of the RFR by signing the
Reviewed by portion.
Responsible in timely submission of all RFRs and financial reports to
the Central Office.
Coordinate with the RPMT all issues/concerns raised by the respective
RFFPs in the area.
RFFP
Replace the MM as co-signatory of the community bank account of all
on-going sub-projects where MMs contract is already terminated. As
such, to protect Project funds, he/she shall ensure that all
disbursement vouchers are reviewed by the Municipal Financial Analyst
before signing the checks.
Coordinate with the RFFP Coordinator to ensure validity and accuracy
of claims before approving payment.
Establish systems/strategies to facilitate disbursement of funds at the
community level to ensure that sub-project implementation is not
delayed.
Ensure that communities and MFA complies with the financial
reportorial requirements of the Project and in the submission of
original paid Disbursement Vouchers and its supporting documents to
the RPMT.
Ensure that community accounts are closed when sub-projects are
completed.
Provide timely feedback to the RFFP Coordinator.
16
Barangay
Development
Council
PSA
Volunteers
Project
Preparation
Team (PPT)
Barangay
Representation
Team (BRT)
Sub-Project
Management
Committee
Bids &
Awards
Committee
Audit and
Inventory
Team
O&M
Committee
Secretary
Treasurer
Bookkeeper
Procurement
Team
Project Implementation
Team
Monitoring and
Inspection Team
Unlike the rest of the teams, the functions of these two teams ceases
when sub-project implementation commences:
1) Participatory Situation Analysis (PSA) Volunteers, formed to lead
in the conduct of participatory situational analysis, from data gathering
to community validation. These volunteers are either elected or chosen
during the first barangay assembly. In a typical KC barangay, about
two to three persons from each purok are chosen to serve as a PSA
volunteer. In large barangays, this is a sizable group.
2) Project Preparation Team (PPT). These are community residents
chosen to assist in the preparation of community proposals which will
be recommended by the barangays for prioritization during the MIBFPRA. There are no limits to the number of people who can be chosen to
serve in this team. They can be as few as three people or as many as
required by more complex sub-projects.
The Barangay Representation Team (BRT) is a committee formed to
represent the barangay in Municipal Inter-Barangay Forums. They can
also be chosen or elected by the Barangay Assembly during the 1st BA
meeting, or can be elected during the 2nd BA, prior to the CSW.
17
18
19
20
21
22
CHAPTER 3
FINANCIAL MANAGEMENT ROLE IN
SUB-PROJECT CONCEPTUALIZATION
AND APPROVAL
Sub-project Conceptualization
Technical Assistance Fund
Sub-project Preparation and Development
Sub-project Consultation and Approval
23
the PPT Head can request for Technical Assistance Fund (TAF) to engage
qualified service provider to conduct studies and prepare plans.
24
National
current
average
charged
25
26
27
c. Before signing for final approval, the BSPMC Chairperson should ensure
that all comments and agreements during the 3rd BA were integrated in
the POW.
d. Then, the Procurement Team prepares the Planned Community
Procurement Packaging (BSPMC Form No. 4).
28
CHAPTER 4
FUND RECEIPTS
DSWD Grant Funds
Local Cash Counterpart Contribution
Interest Earnings
Other Forms of Cash Receipts
Cash Receipts Internal Control Guidelines
Recording and Filing
29
CENTRAL
REGIONAL
MUNICIPAL
BARANGAY
DSWD
Central
Office
DSWD
Regional
Office
MIBF/ACT
BSPMC
Approve RFR;
prepare DV and
check and submit
to Servicing Bank
Servicing
Bank
Review and
endorse RFR to
DSWD-RPMO
Local
Branch
DISBURSEMENT
30
i.
ii.
iv.
v.
31
Requirements:
In accordance with the Memorandum of Agreement between the
DSWD and the LBP (Attachment 1), the following shall be required
from the communities to open a current/checking bank account:
1. MIBF Resolution approving the Sub-project
2. Barangay Council Resolution authorizing the BSPMC
Chairperson, Treasurer of the LGU Barangay and DSWD Area
Coordinator as signatories
3. Initial P1,000 deposit
4. Two (2) valid identifications of each authorized signatory
Secure
certification
from
the
branch
manager
that
a
current/checking bank account has been opened indicating the bank
account number. (See BSPMC Form No. 06)
Special Provision:
On the basis of the MOA between the DSWD and LBP, the bank shall
suspend any release from the account of the community beneficiary
found by DSWD to have violated the project principles. DSWD may
also request the LBP to apply other appropriate sanctions against
the said community account.
c. Complete the Tripartite SPA (See Attachment 3).
d. Treasurer to apply for additional bond premium.
Bond Requirement:
The Treasurer shall apply for additional bond premium to the
National Treasury in case premium paid is insufficient to cover
current maximum accountability determined by computing either of
the following:
32
e. Prepare and submit Request for Fund Release (RFR) (BSPMC Form
No. 7) together with the requirements to the RPMO through the
ACT.
4.1.1.1 Processing the Request for Fund Release
BSPMC Level
a. The BSPMC shall submit the RFR and its accompanying documents to
the ACT within ten (10) working days after the MIBF-PRA.
ACT Level
a. The ACT reviews the RFR and its accompanying documents submitted
by the BSPMC and submit the same to the RPMO within five (5)
working days.
b. Members of the ACT who reviewed the accompanying documents to
the RFR shall sign in the Reviewed by and Date portions of the RFR
Review Sheet (Annex 10) corresponding to the document specified in
the sheet.
RPMO Level
a. The RPMO through the Regional Community Infrastructure Specialist
(RCIS), Regional Financial Analyst (RFA) and Community Process
Specialist (CPS) reviews the accuracy, completeness and validity of the
RFR and its accompanying documents. They shall issue certification
that they have conducted thorough review of the Sub-project
documents and that the Sub-project is technically feasible and
economically acceptable using the Cost Effectiveness Ratio. The RFA
signs the Reviewed by portion of the RFR and a fax copy, with the
accompanying documents, shall be sent to the National Project
Management Office (NPMO) within five (5) working days.
b. In the absence of the RFA, it shall be the RFFP Coordinator who will
review and sign the RFR.
c. All other pertinent documents submitted by the BSPMC shall be
retained at the RPMO for safekeeping which shall thereafter be
transmitted to the DSWD Resident Auditor within ten (10) days of the
following month together with the photocopy of the documents
previously transmitted to the NPMO.
d. RPMO staffs who reviewed the accompanying documents to the RFR
shall sign in the Reviewed by and Date portions of the RFR Review
33
4.1.2
a.
The Treasurer prepares RFR when grant fund balance is only 10% of
the previous fund release and the Sub-project physical
accomplishment has reached the required progress depending on the
tranching availed by the community for the 2nd tranche and 90% for
the 3rd /final tranche. In case the grant fund balance is more than
10% of the previous fund release therefore not eligible to request for
the next tranche but said balance is not enough to pay current
obligation, the BSPMC shall submit justification stating the need for
the release of the next tranche. The justification which will be
34
endorsed by the ACT shall be attached to the RFR with a copy of the
Approved Purchase Order as proof of the obligation.
b.
c.
d.
e.
f.
g.
35
The community grant funds shall be released in three tranches with the
following requirements:
1st tranche RFR
RPMO level
Barangay Council Resolutions
Sub-project Agreement
Local Counterpart Contribution Plan
Certifications on local contributions
Bond Premium of Treasurer
Notarized Deed of Lot Donation for titled lot or Quit Claim for nontitled lots
Proposals/Feasibility Study for Public Good Sub-projects
Hydraulic Analysis for water system Sub-project
NPMO level
Request for Fund Release
MIBF Resolution
Sub-project proposal for Enterprise and Human Resource
Development Sub-projects
Program of Works following the prescribed cost sharing and with
detailed estimates (with signature of Municipal Mayor and Barangay
Captain to conform LCC commitments)
Planned Community Procurement Packaging and Schedule of Inkind LCC
Procurement Action Plan
Local Counterpart Contribution for Sub-project Implementation
Monitoring Report
Bank Certification indicating the community current account number
or Bank Statement/Snapshot
Certificate of Review by the RCIS, RFA and CPS
Photographs of the proposed site (at least three). For water system,
source, reservoir and pipeline right-of-way; roads, photo covering
starting stations projected towards the mid-section or the whole
road right-of-way, if possible and photo projected from the end
station towards mid-sections
(For succeeding cycles) Certification from the Regional Director that
the
following
financial
requirements
pertaining
to
the
implementation of previous Sub-projects were duly complied with:
a) all Disbursement Vouchers together with the supporting
documents have been duly submitted, b) Established Petty Cash
Fund fully liquidated and c) Community funds fully utilized and/or
community bank accounts duly closed.
Operation and Maintenance Action Plan
RFR Review Sheet (Annex 10a)
36
37
In all cases, the required physical progress for the release of the 3rd and
final tranche shall be 90%.
4.2.1
These are contributions which do not become part of the value of the
Sub-project but are intended to facilitate the conduct of activities of the
Project. Examples are cash expenses incurred during the conduct of
Community Empowerment Activity Cycle (CEAC). For this component,
donations are directly deposited to the Municipal Trust Account (MTA)
that is specifically opened to support the implementation of KALAHICIDSS Project in the municipality.
38
4.2.2
These are cash contributions that form part of the investment cost or
value of the sub-project. The minimum LCC cash for sub-project
implementation is fifteen percent (15%) of the grant component.
Said cash LCC shall be deposited in the community account prior to the
request of grant funds. If not deposited in full, delivery shall follow the
RFR tranching used for Grant Funds.
Cash donations are given to the community through the BSPMC and
deposited by the Treasurer to the same bank account as the grant. The
Treasurer shall issue a pre-numbered Acknowledgement Receipt (BSPMC
Form No. 21) for all cash donations. As proof that donations are deposited
to the community bank account, a copy of the validated Deposit Slip will
be provided to the Donor. However, in case where LCC cash is available
even prior to sub-project implementation or opening of communities
accounts, the Donor may deposit said cash in the Municipal Trust Account
opened by the MLGU for the Project. The Municipal Treasurer shall issue
an Official Receipt to acknowledge receipt. The cash shall be immediately
transferred to recipient communities as soon as respective accounts have
been opened.
These are cash received by the Treasurer as proceeds from sale of bidding
documents. The Treasurer shall issue a pre-numbered Acknowledgement
Receipt to interested bidders for the cash received and record it in the
logbook. These shall be used to pay or reimburse reproduction cost of
bidding documents and other expenses incurred during bidding activities.
39
4.4.2
Bid Security
4.4.3
Performance Security
40
Recording
41
Counterpart Contribution (VLCC) (BSPMC Form No. 10) for each eligible
paid Disbursement Voucher charged against the MTA. On a monthly basis,
the MFA will record in the Municipal Local Counterpart Contribution
Journal for Capability Building and Implementation Support (Annex 8) all
VLCCs issued for the period.
LCC for SPI
On the basis of the Acknowledgement Receipt with attached validated
deposit slip issued by the Treasurer to the donors, the Bookkeeper will
record receipt of funds in the same Cash Book used for DSWD Grant
Funds.
D. Other forms of Cash Receipts (Bid and Performance Securities)
On the basis of the Acknowledgement Receipt issued by the Treasurer,
the Bookkeeper shall record cash receipts in the Cash Book. However,
these receipts must be earmarked as funds not available for use.
4.6.2
Filing
The Treasurer shall file all photocopies of RFRs and its supporting
documents in a folder and, together with the other financial documents,
shall file it in a secured cabinet. On the other hand, the MFA will
chronologically file all VLCCs and its supporting documents in a folder and
will keep it also in a secured filing cabinet.
42
CHAPTER 5
FUND DISBURSEMENTS
Transactions
Payments
Processing and Flow of Documents
Withholding Taxes
Supporting Documents
Cash Disbursement Internal Control Guidelines
Recording and Filing
43
5.1 Transactions
Funds of the community may be used for the following:
5.2 Payments
5.2.1
5.2.2
44
Treasurer
Treasurer
Committee
members and
laborers
2.
3.
4.
45
Responsible
Unit/Person
Project Implementation
Team & Treasurer
Execom
Project Implementation
Team or Creditor
Treasurer
Procedures/Activities
5.
Responsible
Unit/Person
Treasurer
money
(for
6.
46
BSPMC Chairperson
Procedures/Activities
7.
Responsible
Unit/Person
Treasurer
47
Description
Income payments to prime contractors/subcontractors Individual
Income payments to prime contractors/subcontractors Corporate
Income payments made by the government to
its local/resident suppliers of goods Individual
Income payments made by the government to
its local/resident suppliers of goods - Corporate
Professionals (lawyers, CPAs, engineers, etc.),
talent fees paid to individuals - If the current
years gross income is P720,000 and below
Professionals (lawyers, CPAs, engineers, etc.),
talent fees paid to individuals - If the current
years gross income exceeds P 720,000
Tax
Rate
2%
2%
1%
1%
10%
15%
48
BIR Form
No.
1600
f.
Description
Persons exempt from VAT under Section 109v
(final)
Tax
Rate
3%
Description
VAT Withholding of Purchase of Goods
VAT Withholding of Purchase of Services
which
the
Tax
Rate
5%
5%
assessment
or
49
ILLUSTRATIONS:
a) Payment of Goods
An invoice in the amount of PhP 100,000.00 was presented to the
Treasurer for payment of materials delivered by ABC Company.
Upon review of the documents supporting the claim, the Treasurer
found it complete and compliant to the Project policies and
guidelines.
Question 1: How much should the Treasurer pay assuming ABC Company
is a VAT-registered supplier? How much is the withholding tax?
Question 2: How much should the Treasurer pay assuming ABC Company
is a NON-VAT registered supplier? How much is the withholding tax?
Solution to Question 1: VAT Supplier
Step 1 Compute for the Tax Base
Tax Base
PhP 100,000.00
(5,357.14)
PhP 94,642.86
Therefore:
i) Total amount of check payable to ABC Company
PhP94,642.86.
ii) Total amount of check payable to BIR is PhP5,357.14.
Solution to Question 2: NON-VAT Supplier
Step 1 Compute for the Tax Base
Tax Base
PhP 100,000
50
is
PhP 100,000.00
(4,000.00)
PhP 96,000.00
Therefore:
i) Total amount of check payable to ABC Company
PhP96,000.00.
ii) Total amount of check payable to BIR is PhP4,000.00.
is
b) Payment to Contractors
Recoupment of Mobilization Fee
The contractor may be allowed to collect Mobilization Fee of up to 15% of
total contract cost. In such case, the amount collected must be
deducted/recouped from the progress billings computed based on the
physical accomplishment indicated in the billing. The Mobilization Fee,
however, shall be fully recouped upon reaching 80% physical
accomplishment.
Deduction of Withholding Tax
The corresponding Withholding Taxes shall also be deducted from the
total billing using the rates aforementioned. Payment for cash advance is
not subject to Withholding Tax.
Deduction of Retention Fee
Retention fee refers to the 10% amount retained from all progress billings
to cover uncorrected discovered defects and third party liabilities. This is
mandatory for all contracts with PhP 1M or more in addition to
performance security. For contracts with less than PhP 1M, retention fee
is only deducted from progress billings when there is no performance
security posted. The retention fee, if not called, shall be refunded to the
contractor after the expiration of the warranty period. The refund shall
not be subjected to Withholding Tax.
In case where closing of community account is mandated by the Project,
the community shall require the Contractor to convert this Retention Fee
to Bank Guarantee or Managers check or Cashiers check from a
reputable bank. Upon receipt of the Bank Guarantee, the Treasurer shall
51
Contract Cost
Mobilization Fee (15%)
500,000
75,000
150,000
(22,500)
(15,000)
(2,679)
(6,696)
(46,875)
Net Billing*
103,125
500,000
75,000
400,000
(150,000)
250,000
75,000
(22,500)
(52,500)
(25,000)
(4,464)
(11,161)
(93,125)
156,875
52
500,000
75,000
500,000
(400,000)
100,000
(10,000)
(1,786)
(4,464)
(16,250)
83,750
PhP 54,542.85
53
PhP 54,542.85
(7,090.57)
PhP 47,452.28
Therefore,
i) Total amount of check payable to Service Provider is
P47,452.28.
ii) Total amount of check payable to BIR is P7,090.57.
Evidence
Evidence
Evidence
Evidence
of
of
of
of
expenditure or liability
receipt of goods and services
payment
receipt of payment
54
6. Purchase Order
7. Sales/Charge Invoice and/or Delivery Receipt
8. Certification of Acceptance and Inspection (certification can also
be indicated in the PO)
9. Disbursement Voucher with photocopy of check
10. Official Receipt
iii. Reimbursement of Transportation Expenses of Service Provider
1. Special Order issued by the PPT, approved by the AC or DAC and
concurred by the Municipal Engineer
2. Approved Itinerary (details of travel)
3. Certification from the AC or DAC, PPT and Municipal Engineer on
the actual accomplishments of the Service Provider
4. Reimbursement Expense Receipt
iv. Payment for the training on operation and management plans for
income-generating sub-projects or those with cost recovery scheme
Refer to Chapter 5.5 Section E for list of supporting documents.
It is reiterated that in no case shall payments to service providers be
made without the acceptance of the concerned PPT. In case payments are
made to any incomplete or incorrect outputs, those who authorized the
payment shall be made responsible in ensuring that the outputs are
corrected and/or liable to repay the amount paid to the service provider.
B. Daily Rate Basis Laborers
1. Daily Time Record
2. Employment Record Sheet
3. Disbursement Voucher with photocopy of check
C. Direct Contracting of Labor or Pakyaw
1. Contract of Agreement
2. Composition of Pakyaw Group with corresponding
percentage of share
3. Statement of Work Accomplished
4. Employment Record Sheet
5. Disbursement Voucher with photocopy of check
rates
or
55
1.
2.
3.
4.
5.
BA Resolution
Accomplishment Report from each payee
Time Sheets
Employment Record Sheet
Disbursement Voucher with photocopy of check
E. Training Expenses
1. Approved Training Design and Budget
2. Minutes of Pre-Procurement
3. Canvass Forms
4. Minutes of Opening
5. Minutes of Evaluation
6. Abstract of Canvass
7. Notice of Award
8. Notarized Contract with the trainers
9. Training Completion Report with attached Attendance Sheet
10. Disbursement Voucher with photocopy of check
11. Official Receipt or Acknowledgement Receipt
F. Establishment of Petty Cash Fund
1. Minutes of Execom Meeting approving the amount of Petty Cash Fund
2. Disbursement Voucher with photocopy of check
G. Replenishment of Petty Cash Fund
1. Petty Cash Vouchers with Supporting Documents
2. Petty Cash Liquidation Summary
3. Disbursement Voucher with photocopy of check
H. Payment of Goods to Non-Registered Suppliers
a) Thru Reimbursement
For disbursements where payee is not a business entity required by
the BIR to issue OR and the money used to pay is advanced or paid
first by the official concerned and the expenses are authorized by the
BSPMC.
1.
2.
3.
4.
5.
6.
7.
Minutes of Pre-Procurement
Canvass Forms
Minutes of Opening of Canvass
Minutes of Evaluation of Canvass
Abstract of Canvass
Approved Purchase Order
Certificate of Inspection and Acceptance (certification can also be
indicated in the Purchase Order)
8. Disbursement Receipt with photocopy of check
9. Reimbursement Expense Receipt (BSPMC Form No. 23)
56
57
58
59
8. Purchase Order
9. Sales/Charge Invoice and/or Delivery Receipt
10. Certificate of Inspection and Acceptance (certification can also be
indicated in the Purchase Order)
11. Disbursement Voucher with photocopy of check
12. Official Receipt
M. Local Shopping for Goods
1. Approved Program of Works
2. Planned Community Procurement Packaging
3. Minutes of Pre-Procurement Conference
4. Canvass form
5. Minutes of Opening of Canvass
6. Minutes of Evaluation of Canvass
7. Abstract of Canvass
8. No Objection Letter (RPMT), if applicable
9. Purchase Order
10. Sales/Charge Invoice and/or Delivery Receipt
11. Certification of Acceptance and Inspection (certification can also be
indicated in the PO)
12. Disbursement Voucher with photocopy of check
13. Official Receipt
N. Local Bidding for Goods
1. Approved Program of Works
2. Planned Community Procurement Packaging
3. Minutes of Pre-Procurement Conference
4. Invitation To Bid
5. Minutes of Pre-Bid Conference
6. Minutes of Bid Opening
7. Forms of Bid
8. Bid Security
9. Certificate of Business Registration
10. Minutes of Evaluation of Bids
11. Abstract of Bid
12. Post qualification Report
13. Resolution to Award
14. No Objection Letter (NPMT)
15. Notice of Award
16. Performance Security
17. Purchase Order
18. Sales/Charge Invoice or Statement of Accounts and/or Delivery
Receipt
19. Certificate of Inspection and Acceptance (certification can also be
indicated in the Purchase Order)
20. Disbursement Voucher with photocopy of check
21. Official Receipt
60
61
Recording
PAID
By: ________________________
Date : ______________________
Then transmit to the Bookkeeper for recording. The Treasurer must
transmit DVs for recording on a regular basis, if possible daily.
b. Upon receipt of the Disbursement Vouchers and its supporting
documents, the Bookkeeper records the disbursement in the Cash
Book and return said documents to the Treasurer for filing.
62
5.7.2 Filing
The Treasurer files the documents in a folder (one folder by month). This
should be arranged by Disbursement Voucher Number, with the latest
number on top of the file and kept in a locked drawer or cabinet in the
BSPMC office. One set of photocopies of the documents should also be
kept as a precaution if something happens with the original set of
documents. The original set of documents shall be submitted to the
DSWD Field Office thru the AC or DAC for submission to the COA on or
before the 10th day of the following month. Said documents, while still at
the community level, shall be under the custody and control of the
Treasurer. The Treasurer shall be fully responsible and accountable for the
documents pertaining to financial transactions of the Project while still
under their custody. The Treasurer shall ensure that submission of these
documents is evidenced by a transmittal letter duly acknowledged by the
AC. At the end of Sub-project implementation, all financial documents
must be turned-over to the BLGU for safekeeping.
63
CHAPTER 6
PETTY CASH FUND
Expenses Covered by Petty Cash Fund
Establishment of Petty Cash Fund
Disbursement from Petty Cash Fund
Replenishment of Petty Cash Fund
Final Liquidation of Petty Cash Fund
64
65
Responsible
Unit/Person
Treasurer
BSPMC Chairperson
Area Coordinator
Treasurer
Treasurer
Bookkeeper
Treasurer
66
Responsible
Unit/Person
Committee or Team
member needing
petty cash
Treasurer
Person making the
request
BSPMC Chairperson
or Project
Implementation
Team Head
Treasurer
Treasurer
Person who made
the request
Treasurer
Treasurer
Responsible
Unit/Person
Treasurer
Treasurer
Treasurer
Audit and Inventory
Committee
BSPMC Chairperson
Treasurer
BSPMC Chairperson
Area Coordinator
Treasurer
67
Responsible
Unit/Person
Count the petty cash fund, if there is still Treasurer
remaining balance.
Prepare PCF Liquidation Summary.
Treasurer
Gather and attach PCVs and supporting Treasurer
documents to the Summary Report and submit
them to the BSBSPMC Chairperson for approval.
Review and sign the Summary Report.
BSPMC Chairperson
If there is still petty cash fund on hand, deposit Treasurer
to the communitys bank account and attach the
validated deposit slip to the liquidation
summary.
Procedures/Activities
1.
2.
3.
4.
5.
68
CHAPTER 7
LOCAL COUNTERPART CONTRIBUTION
Classification
In-Kind Contributions
Valuation and Costing
Recording and Filing
69
7.1 Classification
7.1.1 Local Counterpart Contribution for Capability Building and
Implementation Support (LCC for CBIS)
As discussed in Chapter 4.2.1, these are contributions which do not
become part of the value of the Sub-project but are intended to facilitate
the conduct of activities of the Project. Aside from the LCC Cash intended
for the conduct of Community Empowerment Activity Cycle (CEAC), there
is LCC In-Kind under this component. Examples are the LGUs provision of
an office space and facilities for the ACT and IT equipment.
Tracking and recording of these contributions which will be handled by the
Municipal Financial Analyst, are based on the approved LCC Delivery Plan.
This plan is a document that outlines the breakdown and schedule of
delivery of local counterpart contributions by the municipal LGU. It is
planned by the MLGU, approved by the DSWD and concurred by the
Sangguniang Bayan, through a budget ordinance.
7.1.2
These are contributions that form part of the investment cost or value of
the Sub-project. It is intended to shoulder portions of either the direct or
indirect costs of the Sub-project. As discussed in Chapter 4.2.2, cash
counterpart of this type is directly deposited to the community account.
In Kind contributions of this type are materials, labor, equipment and
other direct or indirect costs committed by the LGUs, communities and
other donors which commitments are reflected in the Program of Works
approved by the MIBF.
70
7.3
Basis of Cash
Valuation
20% of monthly basic
salary
Source Document
Special Order of the
MLGU staff indicating
specific designation to
KC Project
IT equipment
(Computer, Printer, etc)
71
Actual Cost
Equivalent cost of
rental of vehicles
based on actual
number of hours used
Actual cost of food and
supplies and equivalent
rental rate of
venues/sound system
Technical services of
professional individuals
(e.g.
Draftsman/Engineer)
Services of government
personnel (e.g.
Draftsman/Engineer)
Services rendered by
BSPMC members in
implementing the Subproject
72
Approved and
Acknowledged Request
and Issue Slip
Approved Trip Tickets
Certificate of Training
indicating date, venue
and number of
participants from the
LCE and Barangay
Captain for municipal
and barangay levels
respectively;
Attendance Sheet;
Minutes
Acknowledgment
Receipt
Employment Record
Sheet (ERS)
Logbook/Individual
Timesheet
Completed output of
the services rendered
(e.g. detailed cost
estimates)
Logbook/Individual
Timesheet
Use of Heavy
Equipment
Lot/land or other real
property donation
Use of warehouse
7.4
Construction Logbook
7.4.1
Recording
73
7.4.2
Filing
74
CHAPTER 8
BOOKKEEPING AND PREPARATION OF
REPORTS
Cash Book
LCC In-Kind Journal
Status of Sub-project Fund Utilization Report
75
There are only two books namely: Cash Book and LCC Journal that the
BSPMC, particularly Bookkeeper should maintain during Sub-project
implementation. It shall be updated daily or on a weekly basis at the very
least. These books should be kept in a safe place and should be available
for review by any member of the community at all times. At the end of
Sub-project implementation, these books together with the other financial
documents should be turned-over to the BLGU for safekeeping.
REF
PARTICULARS
Apr 1
Deposit
Slip
Initial Deposit
AMOUNT
1,000.00
GRANTS
(LP)
LCC
(Cash)
1,000.00
76
REF
PARTICULARS
Apr 7
Notice
of Fund
Transfer
50%
Grant
Releases
GRANTS
(LP)
AMOUNT
LCC
(Cash)
195,000.00
c. April 23, 2010 - Aling Mingming, the Treasurer went to San Francisco
City to pay Super-337 Hardware for the construction materials purchased.
She gave the check amounting to P165,750.
DATE
Apr 23
REF
DV#
001
Lot-
AMOUNT
165,750.00
FUND
SOURCE
Grant
DIRECT COST
MATERIALS LABOR
165,750.00
To ensure that cash balance in the Cash Book tallies with the cash
available in the Bank account, the Bookkeeper shall prepare a monthly
Bank Reconciliation Statement.
77
DATE
May 8
VLCC
No.
Lot01
DONOR
PARTICULARS
MLGU
Donation of
Materials for
the completion
of Sub-project
DIRECT COSTS
MATERIALS
EQPT
LABOR
28,000.00
At the end of the month, the total in-kind LCC reflected in the book should
tally with the total of all VLCCs prepared for the month.
PARTICULARS
Cash
LP
a
Cash Balance, Beginning
In-kind
d (b+c)
-
e (a+b)
-
DV No.
-
Total
195,000.00
195,000.00
-
PLGU
28,000.00
MLGU
BLGU
1,000.00
Community/Others
Total Funds Available
195,000.00
1,000.00
28,000.00
Materials
195,000.00
28,000.00
165,750.00
Labor
Equipment
Lot
Contract of Works
Material Testing
Supervision
Pre-Engineering
Bond Premium
Administrative Expenses
78
165,750.00
29,250.00
28,000.00
1,000.00
165,750.00
29,250.00
Amount
CHAPTER 9
UNUTILIZED COMMUNITY GRANT
FUNDS
Kinds of Unutilized Grant Funds
Mechanics for the Utilization of Surplus, Left-Over and
Excess Funds
Mechanics for the Utilization of Savings
Procedures in Determining Excess Funds
Procedures in Determining Existence of Savings
Use of Contingency Fund
79
unutilized
grant
funds
and
the
Surplus Fund
It refers to the remaining amount from the municipal allocation after all
proposed Sub-projects are funded. This may happen when the total cost
of all proposed Sub-projects is well within the allocated amount for the
municipality and there are no Sub-projects left unfunded.
Left-over
It refers to the remaining amount from the municipal allocation after
some of the prioritized Sub-projects have been funded. This happens
when one or more Sub-projects remain unfunded and the remaining grant
amount is insufficient for the next runner-up proposal.
Excess
It refers to the remaining 10% final tranche of the community grant fund
when the Sub-project may be completed even without it. This happens
when conditions during actual Sub-project implementation lead to a
reduction on cost. In cases where only a portion of the 10% final tranche
will be requested to fully complete the Sub-project, the balance will
remain as excess fund.
Savings
It refers to the remaining funds in the community bank account after the
100% completion of the Sub-project with all valid financial obligations
settled. In this case, it is possible that barangays may generate savings
from the community grant funds due to varying site conditions during
implementation which the Project recognizes - may not be totally
anticipated at the time of planning.
Contingency
It refers to that item indicated in the Program of Works intended for
unforeseen expenses.
80
81
82
9.4.3 If the AC finds there is potential excess fund, i.e. money in the
bank is sufficient to carry out Sub-project requirements minus valid
payables, the AC shall inform the BSPMC in writing and request for
comments. If the AC finds that there is no excess fund, the RFR
documents may be forwarded to the RPMT for appropriate action.
9.4.4 The BSPMC, upon receipt of the ACs findings that there is potential
excess fund, may either concur or justify the need for the 3rd
tranche.
9.4.5 In case of concurrence, the AC shall notify the RPMT of the excess
fund and the Central Office shall retain the 3rd tranche. The BSPMC,
on the other hand, shall inform the BA of the ACs findings, continue
Sub-project implementation and submit the required 100%
completion reports in due time.
9.4.6 If, within 5 days from BSPMCs receipt of ACs findings, no reply is
received, the AC shall consider it as concurrence by the BSPMC.
9.4.7 The BSPMC may also provide justification/ explanation, in writing,
for the release of the 3rd tranche under the following possible
circumstances:
a. Discovery during Sub-project implementation of additional
works needed related to the approved Sub-project. A brief
supplemental explanation should be indicated in the Subproject physical progress report stating the additional works
required. The actual percentage physical progress of the Subproject, incorporating the additional works, should be
reflected. Documentation of the variation orders/extra works
are assumed kept on file by the BSPMC for reference during
inspection or audit.
b. Actual local counterpart contribution mobilized by the
community is greater than the amount committed. The
BSPMC should indicate in the physical progress report the
fact about its over-delivered LCC and how it was realized.
c.The community incurred legitimate savings during Sub-project
implementation. The BSPMC should indicate in the physical
progress report how the savings was realized.
9.4.8 Should the AC find the BSPMCs explanation sufficient, the RFR
documents shall be forwarded to the RPMT together with the ACs
findings and the BSPMCs justification.
9.4.9 In cases where the BSPMC and the AC is in disagreement over
existence of excess fund, the AC and CF concerned shall discuss this
with the BA. If there is no agreement with the BA, the AC shall
elevate the matter to the RPMT. A representative of the RPMT shall
83
then conduct a field visit and desk review and provide the RPM with
recommendation. The RPMT, through the RPM, shall decide on the
issue.
9.4.10 If it is concluded/decided that there is indeed excess fund, DSWD
shall retain the last tranche and shall no longer entertain request for
its release.
84
85
86
LCC following the actual cost sharing ratio of the approved Subproject.
9.6.5 The amount to be released shall be the actual amount needed as
indicated in the required certifications or the amount of contingency
cost indicated in the POW, whichever is lower.
87
CHAPTER 10
FINANCIAL MONITORING SYSTEM
Financial Monitoring Activities
Monitoring Checklist
88
b.
c.
d.
The committee shall discuss and approve the above reports. In cases
where there are unresolved issues or big variance between plan and
actual progress, the Chairperson shall immediately coordinate with
the corresponding ACT member for technical assistance.
e.
Then the committee shall prepare work plan and disbursement target
for the succeeding weeks activities.
89
f.
90
91
b. Spearheaded by the RFA and RCIS, the results of the activity should
provide them bases to recommend sanctions to communities confirmed
to have irregular transactions and to assess performance of the ACT in
terms of job coaching and safeguarding of funds.
c. It shall be participated by all MFAs and DACs of both ACTs and MCTs
and shall be conducted on a monthly basis on or before the 9th day of
the following month in time for the submission of documents to the
COA.
d. Procedures in the conduct of Regional Fiduciary Workshop.
d.1 After the preliminary activities (e.g. opening prayer, roll call,
welcome message), the RFA shall give a very detailed orientation
regarding auditing procedures thru a power point presentation.
The participants should be encouraged to interact during and after
the lecture. This shall only be done on the first RFW. However, a
follow-through must be done depending on the results of the
workshops.
d.2 Then the MFAs are called to submit, for review purposes, all paid
disbursement vouchers (DVs), cash book, LCC journal, vouchers
for local counterpart contribution for sub-project implementation,
program of works, status of sub-project fund utilization report,
bank snapshot, and bank reconciliation statement. The RFA shall
make inventory of these financial documents and reports and
should see to it that all, especially DVs are accounted for.
d.4 The RFA will then interchangeably distribute the submitted financial
documents and reports together with the audit forms (i.e. working
paper and matrix of findings and recommendations) to each team
for the workshop proper.
d.5 Then the MFA or DAC will present their findings/observations and
recommendations. The auditee shall take note of them and may
immediately give their rejoinder.
The RFA and RCIS shall act as panelists. They will respond to the
queries and issues raised by the participants regarding the
findings/observations and provide inputs on the recommendations.
g. After all has presented, DVs and reports that have no findings shall be
submitted to the COA. Otherwise, it shall be returned to the concerned
MFA for immediate compliance except for DVs with adverse findings
where it shall be retained at the RPMT level for further review and
92
II. Reporting
III. Fund
Disbursement
93
MONITORING AGENDA
a. Check completeness
and correctness of
records in the Cash
Book.
b. Check whether all
deliveries and utilization
of LCC In Kind are
recorded in the LCC
Journal.
a. Validate figures in the
Annex 11 against the
Cash Book and LCC
Journal.
b. Check whether Annex
11s are completely
signed.
c. Verify whether BT and
CB submit reports on
time.
a. Check whether payee is
in the name of the
establishment or of the
proprietor.
b. Verify whether person
who signed the
Received by portion
MEANS OF
VERIFICATION
*Updated Cash Book
*Updated LCC
Journal
*Reconciled Annex
11 with Cash Book
and LCC Journal
*Signed Annex 11
*Transmittal Letters
*Disbursement
Vouchers and
Supporting
Documents
REMARKS
c.
d.
e.
f.
a.
b.
V. Local
Counterpart
Contribution
Delivery
a.
b.
c.
94
of the Disbursement
Voucher and who
received the Check is
the right payee. If not,
check whether he/she
is authorized.
Check whether
payment to
suppliers/laborers is
made within ten (10)
working days.
Check whether Official
Receipt is attached to
paid DVs and that
amount is consistent
with the OR.
For payroll payment,
check whether recipient
of cash is the right
laborer. If not, check
whether person who
received is authorized.
For payroll payment,
check whether cash is
fully disbursed. If not,
check whether
unreleased cash is
deposited back to the
account.
Check whether RFR is
submitted to the ACT
within ten (10) working
days after MIBF-PRA.
For succeeding
tranches, check
whether RFR is
submitted within five
(5) working days upon
reaching the financial
and physical
accomplishment
requirements.
Check whether LCC are
delivered on time. If
not, verify how this
affected sub-project
implementation and
what actions have been
undertaken to address
the problem.
Ascertain whether all
LCC delivered have
been accounted for.
Check correctness of
valuations of In-Kind
LCC and completeness
of its supporting
*RFR Logbook
*Transmittal Letter
VI. Materials
Inventory
Management
VII. Filing of
Financial
Documents
documents/proof of
delivery.
a. Check whether
materials delivered are
received, properly
stored, and accounted
by the MIT.
a. Check completeness,
filing, and safekeeping
of all financial
documents.
*Logbook
*Updated and signed
MRS
b. Municipal Level
The RFA is expected to know the financial aspect of implementation of
each approved subproject. Hence, he/she is required to visit each
community at least once during sub-project implementation to meet and
talk with the community volunteers. Equally important is the monitoring
of the performance of the MFA assigned in the municipality. Using the
following monitoring checklist, the RFA should be able to assess the
performance of the MFA and render appropriate technical assistance
thereof.
AREAS OF
ACTIVITIES
CONCERN
I. ACT Work a. Check whether
and Financial
WFP is within cost
Plan
parameters and
timelines.
MEANS OF
VERIFICATION
*ACT WFP initialed by
MFA
II. Job
Coaching
*Cash Book
*LCC IK Journal
*Bank Reconciliation
*Annex 11
*Narrative Report
*Minutes of Meeting
*Documentation of FM
Trainings
III. Request
for Fund
Release
95
a. Conduct spot
checking by
examining
community books
and DVs.
b. Validate thru
interview with
Community
Volunteers
whether job
coaching is being
done
c. Attend monthly
MFW.
a. Require MFA to
attach list of
findings in RFR
folder
b. FA I to initial
before RFA or AC
in the RFR.
c. Check whether
ACT review of
RFRs is within the
*Checklist of findings
*RFR tracking tool
(where number of
days of review and
compliance to BTS
RFRs is specified)
TIMEFRAME
Ten (10)
working days
upon receipt
of WFP from
FO
Monthly
(during Subproject
Implementati
on)
During
Monthly FM
Meeting (for
RFR
submitted
during the
month)
REMARKS
allotted 5 days.
d. In case of RFRs
with findings,
check whether
concerned
BSPMCs are
immediately
informed of its
findings and
recommendations.
IV.
a. Assess result of
Disbursemen
the MFW and
t of Funds
regional fiduciary
workshops.
V. FM
Reports
a. Set deadline on
the submission of
report at ACT
level
b. Check whether
municipal
consolidated
reports are
reconciled with
community
reports.
VI. Monitor
a. Review MFA
and Validate
monitoring tool
Financial
and journal
Status of
Sub-projects
VII. Inputs
a. Check minutes of
PDW
on Program
b. Check accuracy of
and Work
POWs.
(Indirect
Costs)
VIII.
a. Attend
Community
community
Finance
finance training
Training
to ensure that
MFA delivers
correctly.
IX. Provide
a. Review minutes
updates to
of MIAC
different
meetings or any
stakeholders
other meetings
with
stakeholders
X.
a. Check minutes of
Installation
O&M training
of FMS
b. Review financial
particularly
books and reports
on IGPs
of O&M group.
XI. Filing
Check the existence
system
of filing cabinet &
96
*Inventory of DVs
*Minutes of Fiduciary
Workshop
*Working
Papers/Matrix of
Findings
*FM Reports
*Narrative Reports
Monthly
during Subproject
Implementati
on
Monthly (FO
shall
establish its
own
deadline)
Monthly
*Minutes of
meetings/trainings
*POWs
Project
Development
Stage
*Narrative Report
Once in a
cycle
*Minutes of Meeting
Monthly
*Minutes of Trainings
SP almost
completed
During
Monthly FM
completeness of
financial files and
documents
Meeting
c. Regional Level
Monitoring of the performance of the region in its implementation of the
Projects financial management system is the responsibility of the Central
Office finance staff. On community finance, the monitoring will focus on
whether the region, specifically the Regional Financial Analyst has
ensured that the internal control measures put in place for the
economical, efficient, and effective implementation of communityapproved sub-projects remain in place and working. At the minimum,
monitoring assessment shall be done semi-annually to each region. The
following monitoring checklist shall be used to assess the performance of
the region.
AREAS OF
CONCERN
I. Pre-municipal
engagement
II. Provision of
technical
assistance
97
ACTIVITIES
a. Check whether LCC
plans met minimum
requirements of the
Project and that costs
are within the
established
parameters.
a. Check whether RFA
hold regular fiduciary
workshops.
b. Review minutes of
RPMT meetings and
results of fiduciary
workshops and assess
appropriateness of
rendered TA.
c. Check whether RFA
has visited each subproject at least once
during sub-project
implementation.
d. Review monthly feed
back reports of MFA
and the results of the
community level
monitoring checklist
and evaluate how RFA
respond to the
financial issues and
concerns raised
therein by checking
his/her TA agenda and
travel/accomplishment
reports.
e. Validate thru interview
DOCUMENTS TO
REVIEW
*LCC Plan
*Minutes of RPMT
meetings
*Minutes of fiduciary
workshops
*RFA travel and
accomplishment
reports
*MFA feed back
reports
*Community level
monitoring checklist
REMARKS
f.
g.
a.
b.
IV. Reports
a.
b.
c.
V. Financerelated
Grievances
a.
b.
98
*Grievance Reports
with status of actions
taken
VI. COA
Coordination
VII. Audit
Findings
99
*COA AOMs/Aide
Mem/Co Finance
Feed back reports
*Management
Letters
*COA Rejoinders
CHAPTER 11
FINANCIAL MANAGEMENT SYSTEM FOR
KALAHI-CIDSS OPERATION AND
MAINTENANCE
GROUPS/ASSOCIATIONS
Organizational Structure and FM Roles of Officers
Cash Receipts/Collection
Cash Disbursements/Payments
Recording and Filing
Determining Non-Cash Transactions
Preparation of Financial Reports
Particular
Amount
AR/OR
No.
Particular
Prepared by:
Verified by:
Recorded by:
Amount
OR/AR
Collector/Cashier
Bookkeeper
Treasurer
d. The Treasurer shall verify the cash collection received from the
Collector/Cashier versus the List of Collection.
e. The Treasurer also retains original copy of List of Collection and records
the same in
the Treasurers Journal which contains the following
after which he/she shall keep the cash in the Cash box for deposit the
next banking day.
Date
Refer
ence
Particular
Receipt
Disbursement
Cumulative
Balance
f. The Bookkeeper receives the duplicate copy of the List of Collection and
records the transactions in the Cash Book (The format is the same as
what is used in the Sub-project implementation.). He /she then file the
copy of the List of Collection.
Receivable
and
Accounts
Payable
(Non-cash
b3. Deduct the total expenses from the total revenues. The result
represents the Net Income or Net Loss for the period.
For monitoring purposes, it is most ideal to prepare Financial Report/
Income Statement every two weeks. This should, however, be decided
upon by the Association.
Other suggested Fund Management Procedures for Income Generating
Sub-projects are provided in the KC Manual for Project Sustainability
(Operations and Maintenance).
CHAPTER 12
BSPMC FORMS AND ANNEXES
BSPMC Forms
Annexes
Attachments
12.2 Annexes
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
11.3 Attachments
1. Memorandum of Agreement with LBP
2. Tripartite Sub Project Agreement
3. Revised Schedule of Premium Rates (Fidelity Bond)
Municipality
Province:
Region:
A. GENERAL INFORMATION
Name of proposed sub-project:
Category:
Public Goods
Enterprise
Cost parameter:
Php
Direct Cost
Indirect Cost
Total
% total
Total population
Male
Female
% to total
Yes
LGU Ownd
No
others specify
EMP Only
E. SP SUSTAINABILITY
Is there an existing O&M group or still to be organized?
Is the community willing to pay for Tariff and by How much?
Other sources of funds for the operation and maintenance activities?
Identified capability building requirements for O&M group?
How do we plan to maintain the completed sub-project?
Prepared by:
Brgy. Chairperson
Area Coordinator
BSPMC Chairperson
MIAC Representative
Sub-Project Duration
Equipment Needed
Technical Personnel
Unit of
%
Quantity
measure
Wt.
Scope of Work
(Direct Cost)
Item No.
Unit Price
Total
Other Source
Total Cost
Total
Breakdown Estimated
Project Cost
Sources of Fund
KALAHICIDSS Grant
Community
Local Gov't.Units
A. Direct Cost
Materials Cost
Equipment Rental
Labor Cost:
a. Skilled
b. Unskilled
Sub-Total A
B. Indirect Cost
Pre-Engineering
Supervision
Contractor's Profit
Taxes
Hand Tools
Material Testing
Admin and Overhead
Sub-Total B
TOTAL (A+B)
ADD: Contingency
%
Total Estimated Cost
ADD: O&M (Other amenities)
Grand Total
Prepared by:
Approved by:
Sevice Provider/ACT-DAC
BSPMC Chairperson
Reviewed by:
Concurred by:
Barangay Chairperson
Recommending Approval:
Municipal Mayor
Municipal Engineer
Noted:
Regional Infrastructure Engineer
Note:
Unit used
No. of
Units
Per Unit
Cost
Pro-posed
Amount of
Grant
Target Date of
Delivery of LCC
other
Amount
If exact
Office Supplies
fund
date can
Transportation Expenses
sources
not be
Committee Meetings
projected
Barangay Assemblies
just
write
projected
Honorarium
month
Approved by:
Barangay Treasurer
BSPMC Chairperson
Estimated Cost:
KC Cost:______________
LCC: _________________
In-kind : ___________
Cash: _____________
BY CONTRACT
PROPOSED
IMPLEMENTATION
SCHEDULE
QTY.
UNIT
TOTAL
PROC.
METHOD
st
1 Tranche
Grant
LCCCash
nd
2 Tranche
Grant
LCCCash
rd
3 Tranche
Grant
LCCCash
MONTH
Total
Grant
Package 2
Package 1
PACKAGES
TOTAL
Reviewed by:
Submitted by:
____________________
Procurement Team Head
_________________________
DAC/Municipal Engineer
____________________
BSPMC Chairperson
LCCCash
Estimated Cost:
KC Cost:______________
LCC: _________________
In-kind : ___________
Cash: _____________
BY CONTRACT
PROPOSED
IMPLEMENTATION
SCHEDULE
QTY.
UNIT
TOTAL
PROC.
METHOD
st
nd
nd
1 Tranche
2 Tranche
3 Tranche
In-Kind
In-Kind
In-Kind
MONTH
TOTAL
1
Package 2
Package 1
PACKAGES
TOTAL
Reviewed by:
Submitted by:
____________________
Procurement Team Head
_________________________
DAC/Municipal Engineer
____________________
BSPMC Chairperson
Fund Releases/Tranches
First
Second
Third
Total
Amount
Prepared by:
Approved by:
Barangay Treasurer
BSPMC Chairperson
Note:
If the Request for Fund Release being submitted is not in accordance with the projected
schedule, a revised schedule should be submitted with accompanying explanation or justification
to the Area Coordinating Team Leader.
Date:
This is to certify that Barangay ____________________ has opened the KALAHI-CIDSS Brgy.
_______________________ (name of Barangay) current account with the Land Bank of the
Philippines with the following details:
LBP Branch:
Complete Address:
Telephone No.
Fax No.
_________________________________________________________
_________________________________________________________
________________________
________________________
__________________________
Authorized Signatories:
NAME
DESIGNATION
SPECIMEN SIGNATURE
1.
2.
3.
By:
Region
Date (mm/dd/yy)
Province
Sub-Project ID No.
Municipality
Total Sub-Proj
Cost
LCC
Grant Funds
Barangay
Sub-Project Title:
May we request for the transfer of funds to the following LBP Bank Account for the implementation of
the Kalahi-CIDSS approved Sub-Project stated above.
LBP Branch:
Address:
Account Name:
Amount of
No. of this Tranche
this Request
Previous
Amounts
Released
Cumulative
Total
including
this Request
Kalahi-CIDSS:
Requested by:
__________________________________
_________________________________
Barangay Sub-Project Management Committee
Punong Barangay
Chairperson
Reviewed as to completeness of requirements:
_____________________________
________________________________
Area Coordinator
Mun. LGU Local Poverty Reduction Action Officer
Date
Date
Regional Project Management Office:
National Project Management Office
Reviewed by:
_____________________________
Regional Financial Analyst
Recommended by:
________________________________
Regional Project Director
________________________________
Date
Approved by:
_______________________________________
National Project Director
_____________________________
Date
DV No. _____________
(must be pre-numbered)
DISBURSEMENT VOUCHER
Payee:
Complete Address:
Date: ______________
PARTICULARS
AMOUNT
Write full description of the transaction to be paid. For example, if several items were
Purchased, each item should be enumerated with the corresponding no. of units and unit
Price.
ACCOUNT TITLE
The Treasurer should fill this up using the chart of Accounts.
Received the amount of ___________________________________________ (P_________________)
in full payment of the account described above.
Date
Received by:
PRINT FULL NAME OF THE PERSON RECEIVING THE PAYMENT. WRITE CLEARLY.
Signature over Printed Name
Prepared by:
Approved:
Barangay Treasurer
Reviewed by:
Municipal Financial Analyst
BSPMC Chairperson
KALAHI-CIDSS PROJECT
Barangay Sub-Project Management Committee
Barangay ________________________
Municipality _______________________
Province of __________________________
WEEKLY SCHEDULE OF DISBURSEMENTS
FOR THE WEEK ENDING ______________________________
Name of Payee
Particulars
Amount
Due
Date Due
Action Taken
(indicate if
Approved or not)
This authorizes the Barangay Treasurer to process the payments for the approved payables listed above. Actual payment shall be subject to the submission by
the payee of complete and correct documents.
Certified true and correct (All BSPMC Executive Committee Members present).
(Signature over Printed Name)
Date: _____________
PARTICULARS
AMOUNT
ACCOUNT TITLE
Note: attach to this voucher, photocopy or duplicate copy of the source document.
Prepared by:
Concurred:
Approved:
________________________
(Write name of person preparing
the voucher)
_______________________
Write name of donor
BSPMC Chairperson
______________________________________________________
PARTICULARS
PCV No.
(Must be pre-numbered)
Date
AMOUNT
TOTAL
Requested by:
Approved by:
Received By:
Payee
Particulars
Office Supplies
(inc photocopying)
Transportation
Expense
Others
(Specify)
Meals
Write
Other
expense
items
TOTAL
BSPMC
Prepared by:
Barangay Treasurer
Approved by:
BSPMC Chairperson
TOTAL
Municipality: __________________
GENDER
NAME
Male
Female
AGE
Nature of Work
(e.g. Laborer,
Foreman, etc.)
TYPE:
Skilled
NO. OF
WORKING
Rate Per
Unskilled
Hour
Province: ______________
Day
Hours
Days
TOTAL
Labor
PLAN PAYMENT
Cash
Bayanihan
ACTUAL PAYMENT
(accum.)
Cash
Bayanihan
1
2
3
4
5
6
7
8
9
10
TOTAL
NOTE:
Rate - Is the rate per day or per hour of the community worker (cash plus "bayanihan" monitized)
Cash - Is the cash amount to be paid to community members for labor
Bayanihan- Cost of Labor not to be paid (Community Equity)
Prepared by:
Noted by:
__________________________
Head, Procurement Team
_____________________________
Head, Project Implementation Team
Approved by:
_______________________
Brgy. Treasurer
______________________
BSPMC Chairperson
Signature
CERTIFICATION
THIS IS TO CERTIFY that ________________________________ and
(Name of Brgy. Chairman)
_________________________________ assure the KALAHI-CIDSS Project
(Name of BSPMC Chairman)
that we will provide in-kind equity in the form of materials for our proposed subproject , __________________________________________.
(Name of sub-project)
Description of the
materials
Quantity
Prevailing Unit
Price
Estimated Cost
__________________________
Signature of BSPMC Chairperson
___________________________
Signature of Brgy.Chairperson
Concurred by:
__________________________
Municipal Engineer
___________________________
Deputy Area Coordinator
CERTIFICATION
THIS IS TO CERTIFY that ________________________________ and
(Name of the Municipality)
_________________________________ assure the KALAHI-CIDSS Project
(Name of BSPMC Chairman)
that we will provide in-kind equity in the form of equipment for our proposed
sub-project , __________________________________________.
(Name of sub-project)
Description of the
Equipment
No. of
Unit
Prevailing
Rental Rate
No. of days
committed
Estimated Cost
___________________________
Signature of BSPMC Chairperson
Concurred by:
__________________________
Municipal Engineer
___________________________
Deputy Area Coordinator
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Work
Accomplishment/Activity
Work
Location
Rate/Day or
Rate/Month
_________
P
X
Total No. of
Days worked
_________
=
Total Amount
of compensation ________
Total Hours
working time for this period.
Approved by:
BSPMC Chairperson
Date
BSPMCFormNo.16
CONSTRUCTIONLOGBOOK
Nameofsubproject:___________________________________________________________________
PhysicalTarget:__________________________TotalApprovedCost:__________________________
Location:_____________________________________________________________________________
Date:___________________Day:__________________Weather:_______________________
LaborForceAvailable:
SkilledMen:Foreman_____________
UnskilledMen :_______________
Carpenter_____________
UnskilledWomen:________________
Mason_____________
SkilledWomen(Specify):__________
Plumber_____________
Welder _____________
H.E.Operator____________
L.E.Operator____________
Equipment/Toolspresentatsite:(specifyandnumber)
___________________
____________________
____________________
___________________
____________________
____________________
___________________
____________________
____________________
Activitiesundertaken:
Output/softheday
______________________________________________
__________________________
______________________________________________
__________________________
______________________________________________
__________________________
______________________________________________
__________________________
______________________________________________
__________________________
Problemsencountered&actiontaken:
______________________________________________
__________________________
______________________________________________
__________________________
______________________________________________
__________________________
______________________________________________
__________________________
BSPMC/ProjectStaff/Visitors:
___________________
____________________
_____________________
___________________
____________________
_____________________
___________________
____________________
_____________________
___________________
____________________
_____________________
Comments/Observations/Recommendations:
______________________________________________
__________________________
______________________________________________
__________________________
______________________________________________
__________________________
______________________________________________
__________________________
______________________________________________
__________________________
Labor
Generated
Total
Ave.
Rate/Day
No. of Days
Male
Female
Male
Unskilled
Female
TOTAL
Skilled
ITEM No.
QTY
UNIT
WEIGHT
(%)
AMOUNT
Physical Previous
Target
Cumm.
DURATION
Month 1
Month 2
Month 3
Month 4
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
TOTAL
% PROGRESS (PLANNED)
PHYSICAL
% PROGRESS (ACTUAL)
IV.
Recommendations
Prepared by:
Concurred by:
_____________________________________
MCT-Deputy Area Coordinator and/or Service Provider
Approved by:
Noted:
____________________________
BSPMC Chairperson
Municipal Engineer
Note: Attach Material Records Sheet if physical accomplishment lags behind financial disbursements.
Sub-Project Component
Activities
Municipality
Barangay Sub-Project ID No.
Unit/Performance
Indicator
Work
Target (No.
of Units)
Accomplishment
As of Previous
Period
For the
Current
Period
Total
Percent of
Work Target
Remarks
Prepared by:
Verified by:
Approved by:
BSPMC Chairperson
Area Coordinator
Estimated Cost:
KC Cost:______________
LCC: _________________
In-kind : ___________
Cash: _____________
BY CONTRACT
PROPOSED
IMPLEMENTATION
SCHEDULE
QTY.
UNIT
TOTAL
PROC.
METHOD
st
1 Tranche
Grant
LCCCash
nd
2 Tranche
Grant
LCCCash
rd
3 Tranche
Grant
LCCCash
MONTH
Total
Grant
Package 2
Package 1
PACKAGES
TOTAL
Reviewed by:
Submitted by:
____________________
Procurement Team Head
_________________________
DAC/Municipal Engineer
____________________
BSPMC Chairperson
LCCCash
DV No.
Payee
Particulars
Grants
LCC
Write
Source
of cash
contri.
TOTAL
Office Communi
Sub-Total
Supplies
cation
Cash Disbursements
Travel
Materials
Others
Write
other
expense
items
Sub-Total
Balance
ACKNOWLEDGMENT RECEIPT
AR# __________
Date __________
Cash/Check No.
Date
Amount
:
:
:
_____________
_____________
_____________
Prepared by:
_________________________
(Signature Over Printed Name)
Received by
_________________________
(Signature Over Printed Name)
Date/Time Received:
_________________________
NO
Date ______________________
MEMORANDUM
For
FROM
SUBJECT
In compliance with the provisions of KCKKB Operations and Finance Joint Guideline No. 1,
we have reviewed/validated the identified project of Barangay (or Cluster of Barangays, as
the case may be) _________________ to determine their eligibility to the 3% Technical
Assistance Fund (TAF) and have found that on the basis of the above information, Barangay
(or cluster) ________________ is eligible to avail of said Technical Assistance Fund.
I certify further that all the information supplied herein are true and correct to the best of my
knowledge.
Signed: Area Coordinator or Deputy Area Coordinator
xxxx
PCV No.
Particulars
Amount
xxxx
xxxx
xxxx
xxxx
xxxx
xxxx
xxxx
xxxx
xxxx
Total Expenses
Ending Balance
xxxx
xxxx
Cash Count
Denomination
No. of Pieces
Amount
P1,000
'500
'200
'100
'50
'20
'10
'5
'0.25
'0.10
'0.05
Total
Cash Count conducted by:
____________________________
Audit & Inventory Committee Head
_________________
Barangay Treasurer
ANNEX4
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
REGIONAL CONSOLIDATED STATUS OF SUBPROJECT FUND UTILIZATION REPORT
FOR THE QUARTER ____________
REGION:
MUNICIPALITY
TOTAL PLANNED:
TOTAL ACTUAL:
CASH:
CASH:
INKIND:
INKIND:
UTILIZATION
NO. OF
APPROVED
SUBPROJECT
KC GRANT
LCC
TOTAL
e (c+d)
GRANTS
PREVIOUS
MONTH
f
LCC
THIS MONTH
TOTAL
h (f+g)
PREVIOUS
MONTH
i
TOTAL
CUMULATIVE
TOTAL
BALANCE
THIS MONTH
j
k (i+j)
l(h+j)
m (e-l)
Prepared By:
Certified Correct:
Noted by:
Financial Analyst
DSWD-Regional Director/ARD
Sources:
Status of Subproject Fund Utilization Report (Annex 11)
Municipal Consolidated Status of Subproject Fund Utilization Report (Annex 6)
ANNEX 5
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
FIELD OFFICE ___
REGIONAL CONSOLIDATED STATUS OF LOCAL COUNTERPART CONTRIBUTION
FOR THE QUARTER _________
ACTIVITIES
Planned
PLGU
Actual
Balance
Planned
MLGU
Actual
Balance
Planned
BLGU
Actual
Balance
COMMUNITY/OTHERS
Planned
Actual
Balance
CEAC:
Social Preparation
Project Identification/Selection
Project Approval
Technical Trainings for Volunteers
Implementation Support
Monitoring and Evaluation
MIAC Meetings
CBIS:
Trainings
Personnel Services
Admin Cost
M&E
Sub-Total
SPI
Sub-Total
TOTAL
Prepared By:
Certified Correct:
Noted by:
Financial Analyst
DSWD-Regional Director/ARD
Sources:
LCC Delivery Plan
Subproject Fund Utilization Report (Annex 11)
Municipal LCC Journal for CBIS (Annex 8)
Municipal LCC (Annex 7)
Planned
TOTAL
Actual
Balance
ANNEX6
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
MUNICIPAL CONSOLIDATED STATUS OF SUBPROJECT FUND UTILIZATION REPORT
AS OF ____________
REGION:
TOTAL PLANNED:
TOTAL ACTUAL:
PROVINCE:
CASH:
CASH:
MUNICIPALITY:
INKIND:
INKIND:
BARANGAY
UTILIZATION
SUBPROJECT
TITLE
GRANTS
KC GRANT
LCC
TOTAL
e (c+d)
PREVIOUS
MONTH
f
LCC
THIS MONTH
TOTAL
h (f+g)
PREVIOUS
MONTH
i
TOTAL
CUMULATIVE
TOTAL
BALANCE
THIS MONTH
j
k (i+j)
l(h+j)
m (e-l)
Prepared By:
Reviewed by:
Certified Correct:
Noted by:
Financial Analyst
Municipal Accountant
DSWD-Regional Director/ARD
ANNEX7
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
MUNICIPAL CONSOLIDATED STATUS OF LOCAL COUNTERPART CONTRIBUTION
AS OF ____________
PROVINCE:
KC GRANT:
TOTAL PLANNED:
TOTAL ACTUAL:
MUNICIPALITY:
LCC:
CASH:
CASH:
INKIND:
INKIND:
No. of Barangays:
MLGU
CATEGORY
CBIS
ACTIVITIES
Planned
Actual
BLGU
Balance
Planned
Actual
Planned
Actual
Balance
TOTAL
Planned
CEAC:
Social Preparation
Project Identification/Selection
Project Approval
Technical Trainings for Volunteers
Implementation Support
Monitoring and Evaluation
MIAC Meetings
Trainings
Personnel Services
Admin Cost
Sub-Total
M&E
SPI
Subproject Implementation
Sub-Total
TOTAL
PREPARED BY:
APPROVED BY:
REVIEWED BY:
NOTED BY:
MUNICIPAL ACCOUNTANT
MUNICIPAL MAYOR
DSWD- RD/RPM
Sources:
Actual
Balance
ANNEX 8
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
MUNICIPAL LOCAL COUNTERPART CONTRIBUTION JOURNAL
for CAPABILITY BUILDING AND IMPLEMENTATION SUPPORT
For the Month of ____________________
MUNICIPALITY:
DATE
Source:
VLCC NO.
DONOR
PARTICULARS
AMOUNT
ANNEX 9
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
LIST OF CHECKS ISSUED
For the Period ___________________
Region:
Province:
Date
Municipality:
Barangay:
Check
Number
Fund
Source
Payee
Particulars
Remarks
Amount
*submittedtoCOA,
FOorstillatthe
Community
RECAPITULATION:
PARTICULARS
Preparedby:
Approvedby:
MATERIALS
LABOR
EQUIPT
____________________________
BarangayTreasurer
___________________________
BSPMCChairperson
Supplies
Indirect Cost
Total
FUNDS UTILIZED
GRANT
LCC
TOTAL
ANNEX 10-A
(First Tranche)
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
REQUEST FOR FUND RELEASE (RFR) REVIEW SHEET
Region:
Province:
Municipality:
Barangay:
Sub-Project Title:
Date:
DOCUMENT
RPMO level
Barangay Council Resolutions
Sub-project Agreement
Local Counterpart Contribution Plan
Certifications on local contributions
Bond Premium of Treasurer
Notarized Deed of Lot Donation for titled lot or
Quit Claim for non-titled lots
Hydraulic Analysis for water system Sub-project
Proposals/Feasibility Study for Public Good
Sub-projects
NPMO level
Request for Fund Release
MIBF Resolution
SP proposal for Enterprise and HRD subprojects
Program of Works following the prescribed cost
sharing and with detailed estimates (with
signature of Municipal Mayor and Barangay
Captain to conform LCC commitments)
Planned Community Procurement Packaging
with Schedule of In-kind LCC
LCC for SPI Monitoring Report
Procurement Action Plan
Bank Certification indicating the community
current account number or Bank
Statement/Snapshot
Certificate of Review by the RCIS, RFA and
CPS
Photographs of the proposed site (at least
three). For water system, source, reservoir and
pipeline right-of-way; roads, photo covering
starting stations projected towards the midsection or the whole road right-of-way, if
possible and photo projected from the end
station towards mid-sections
(For succeeding cycles) Certification from the
Regional Director that the following financial
requirements pertaining to the implementation of
previous Sub-projects were duly complied with:
a) all Disbursement Vouchers together with the
supporting documents have been duly
submitted, b) Established Petty Cash Fund fully
liquidated and c) Community funds fully utilized
and/or community bank accounts duly closed.
Operation and Maintenance Action Plan
REVIEWER
REVIEWED DATE
REMARKS
SIGNATURE
ANNEX 10-B
(Second Tranche)
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
REQUEST FOR FUND RELEASE (RFR) REVIEW SHEET
Region:
Province:
Municipality:
Barangay:
Sub-Project Title:
Date:
DOCUMENT
RPMO level
Narrative Report (if there is a big variance in
physical & financial accomplishment)
Actual Community Procurement Packaging
Minutes of Barangay Assembly Meeting
Photographs of Sub-project progress
Registered Deed of Lot Donation for titles lots
NPMO level
Request for Fund Release
Status of Sub-project Fund Utilization Report
List of Checks Issued (Annex 9)
LCC for SPI Monitoring Report
Physical Progress Report signed by the Municipal
Engineer and the DAC and Regional Community
Infrastructure Specialist
Bank Statement/Snapshot
Operation and Maintenance Final Plan with
notarized Mutual Partnership Agreement
Certification from the Regional Director that the
requirement of monthly submission of all DVs as of
immediately preceding month to the FO/COA, has
been fully complied with
REVIEWER
REVIEWED DATE
REMARKS
SIGNATURE
ANNEX 10-C
(Third Tranche)
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
REQUEST FOR FUND RELEASE (RFR) REVIEW SHEET
Region:
Province:
Municipality:
Barangay:
Sub-Project Title:
Date:
DOCUMENT
RPMO level
Narrative Report (if there is a big variance in
physical & financial accomplishment)
Actual Community Procurement Packaging
Minutes of Barangay Assembly Meeting
Photographs of Sub-project progress
Proof of pending financial obligations e.g. Delivery
Receipts, Billings as attachment to Certification
NPMO level
Request for Fund Release
Status of Sub-project Fund Utilization Report
List of Checks Issued (Annex 9)
LCC for SPI Monitoring Report
Physical Progress Report signed by the Municipal
Engineer and the DAC and Regional Community
Infrastructure Specialist
Bank Statement/Snapshot
Certification indicating the total cost of remaining
materials to be procured and total cost of labor and
other related expenditures to be incurred to
complete the Sub-project signed by the Chairs of
the PT and the BSPMC and noted by the DAC
Certification of any pending financial obligations
e.g. unpaid delivered materials, services rendered
but not yet paid (wages/ payroll) and other incurred
but unpaid related expenditures signed by the
Treasurer, BSPMC Chair and noted by the DAC
Barangay Assembly resolutions confirming the
certifications
Joint Inspection Report
Certification from the Regional Director that the
requirement of monthly submission of all DVs as of
immediately preceding month to the FO/COA has
been fully complied with
REVIEWER
REVIEWED DATE
REMARKS
SIGNATURE
ANNEX 10-D
(Technical Assistance Fund)
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
REQUEST FOR FUND RELEASE (RFR) REVIEW SHEET
Region:
Province:
Municipality:
Barangay:
Sub-Project Title:
Date:
DOCUMENT
Request for Fund Release
MIBF Resolution availing of the TAF for their
prioritized sub-projects
MIBF Resolution that designates a representative
barangay who shall be the contracting party of the
service provider/s to be engaged (for clustered
barangays
Bank Certification indicating the community current
account number or Bank Statement/Snapshot
Bond Premium of Treasurer
Copy of notarized contract of service provider,
TOR specifying the expected deliverables, time of
submission and mode of payments
Matrix of barangays availing of the TAF with the
sub-project type and the name of corresponding
service providerr
Accomplished TAF Eligibility Checklist for each
barangay availing of the TAF
REVIEWER
REVIEWED DATE
REMARKS
SIGNATURE
ANNEX 11
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
STATUS OF SUBPROJECT FUND UTILIZATION
For the period ____________________
Barangay:
Municipality:
Province:
Name of Subproject:
GRANT FUNDS
PARTICULARS
LP
Cash
In-kind
Total
d (b+c)
e (a+b)
Approved by:
Reviewed by:
Community Bookkeeper
BSPMC Chairperson
Noted by:
Sources:
Amount
ANNEX12
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
CASH BOOK
Barangay:
Municipality:
Province:
Name of Subproject:
Bank Account No.
DATE
Sources:
REF
CASH IN (RECEIVED)
GRANTS
LCC
PARTICUL
ARS
AMOUNT
(LP)
(Cash)
Cash Receipts -
Payments -
AMOUNT
INDRECT COST
OTHERS
TRAVEL
RECAPITULATION:
PARTICULARS
MATERIALS
LABOR
EQUIPT
Supplies
Indirect Cost
Total
GRANT
CUM
BALANCE
FUNDS UTILIZED
LCC
TOTAL
ANNEX 13
DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI-CIDSS PROJECT
LOCAL COUNTERPART IN-KIND CONTRIBUTION JOURNAL
Barangay:
Municipality:
Province:
Name of Subproject:
DATE
DONOR
PARTICULARS
TOTAL
Source: Vouchers for Local Counterpart Contribution for SPI
MATERIALS
DIRECT COSTS
EQPT
LABOR
SUPPLIES
INDIRECT COST
TRAVEL
OTHERS (Specify)
TOTAL