Method Statement: Approval
Method Statement: Approval
Method Statement: Approval
CONTRACT NO:
REV:0
DATE ISSUED:
FOR
APPROVAL
FOR
CONSTRUCTION
FOR
REVIEW
APPROVAL
PREPARED BY:
RECEIVED BY:
APPROVED BY:
DATE:
DATE:
DATE:
REMARK:
METHOD
STATEMENT
CONTENT
1.0
General Description
2.0
Scope
3.0
4.0
Construction Preparation
5.0
6.0
7.0
2.0 Scope
This document does not only describe the procedures and method of bored
piling works and Grout column to support potential development of the specified
project ,but also contains the method of pile test,Quality Work ItemQWI&Quality
1
QTY.
PILE DIA.(mm)
ZONE A
ZONE P
750 A
10 Nos
10 Nos
750
0 Nos
51 Nos
900
0 Nos
22Nos
1050
9 Nos
43 Nos
1200
2 Nos
36 Nos
1350
22 Nos
46 Nos
1500
71 Nos
16 Nos
1800
47 Nos
0 Nos
2000
29 Nos
0 Nos
SUM QTY.
190 Nos
224 Nos
No.
Name
Quantity
Purpose
Drilling
Drilling
Drilling
Goods-Hanging
Goods-Hanging
Generator Set
Power
Ground-Flatting,Soil-Excavating
Welding Set
Metal-Welding
Rebar Cutter
Bar-Cutting
10
Bending machine
Bar-Bending
11
Steel Plate
70
Temporary Road
12
Sport light
Illumination
13
Water Pump
Dry site
14
Air compressor
15
Desander
Slurry Make
16
Slurry Pump
Slurry Make
17
Loader
Delivered Materials.etc
from the center of the pile. Excavation of the soil inside the casing will be carried out
using the rotary rig auger/bucket. Its position and verticality will be checked prior to
commencing excavation and regularly during excavation.
The verticality will be checked by placing a spirit level against the casing;
adjustments can be made by the hydraulic vibrators to keep the vertical alignment and
plan location within the allowable limits.
The checks shall be repeated in cases where major underground obstructions are
encountered. If the location of the excavation is so much outside the required tolerance
that it cannot be corrected, the hole will be back filled and the temporary casing will
be extracted. The excavation procedure will be repeated again in order to satisfy the
particular requirement.
Prior to the termination of each bored pile,the proposed length,boring record and
pile length design calculation sheet shall be submitted by Consultants Geotechnical
Engineer to RE or Consultants office(HQ)for approval. The Clients Representative
shall also verify the final toe level of the pile prior to the installation of the reinforcing
cage.Backfill of the bore hole with the suitable excavated material,and the unsuitable
excavated material for incorporation into the works will be removed off site by lorry.
(3) Cleaning of Pile Base
Following the completion of the excavation, the bored hole will be thoroughly
cleaned of the sediment. Cleanliness of the bored hole will be monitored by dipping
the base of the excavation .Airlifting will continue until clean water or negligible
debris in suspension is detected. Desanding to be carried out prior to the airlifting
work.
(4) Installation Of Reinforcement Cage
The reinforcement cage for the pile will be prefabricated on site in 12m lengths
or other length in accordance with the details( the amount,type and reinforced bar size)
shown on the contract drawings & specifications together with a top section of
appropriate length for each pile.
In addition to the main bars and binders shown on the drawings stiffening rings
will be fixed outside or inside the main bars at appropriate center to act as stiffeners to
prevent distortion of the prefabricated cages during handling. The stiffeners will be
8
spot welded to the main reinforcement with approval from the Engineers. For avoiding
the permanent deformations,the cage will be securely fixed using manually tied
galvanized wire and subsequently tack welded at predetermined junctures.
water into the pipe and therefore segregation of the concrete. Concrete will then be
introduced into the hopper of the tremie pipe in 6 cu m batches by use of a skip. As
successive batches of concrete are installed into the tremie pipe the level of the
concrete in the pile will be checked and a continuous record kept by means of
weighted tapes.
As the level of the concrete in the pile reaches a suitable level, the tremie pipe
will be withdrawn in section in such a way that a minimum immersion of 2m of the
tremie pipe into the concrete is maintained at all times.
The concrete level will be brought to a level of minimum 750mm above cut off
level, then backfilling the space between the temporary and permanent liners with
sand will take place. If necessary, steel stabilizers will be used to fix the gap between
10
the permanent casing and temporary casing at the top level prior to concreting to
ensure the stability and verticality of the pile during concreting. The temporary liner
will be removed using a hydraulic casing hydraulic vibrators section by section, during
which further backfilling between the casings will be carried out as necessary.
5.4 Sequence of Pile Construction
The sequence of construction of the piles will be chosen in such a manner that no
damage can be caused to nearby piles still under construction or recently completed
(24 hours). The piling sequence will be submitted for Engineers approval. The piles
shall be bored and cast on the same day and min.distance of piles bored on the same
day (less than 24 hours )shall be more than 5 times diameter of the larger pile size
diameter.
This approach is to ensure minimum soil disturbance to occur at every boring
point, in order to prevent over break of the pile concrete which could happen due to
soil collapse in the bored hole. The adjacent point to the installed pile will only be
done on the next day.
Full records of the construction of the pile will be submitted to the Engineer after
the completion of each pile.
5.5 Testing of piles
(1) Testing of concrete
The quality of concrete will be tested on the site by measuring the slump and
11
(temperature of concreting) at the time of discharge into the pile borehole recorded on
a Concrete Delivery record. In addition to the site test, laboratory tests will be carried
out in order to check the strength of the placed concrete in accordance with the
requirements of the specifications. The appropriate strength requirement shall be
considered to be satisfied if,for the cubes tested at the specified age,none of the
strengths is below the required strength at the age tested;and the difference between
their strength is not more than 15% of the average.(All concrete cube test comply the
BS 5328: 1990)
For each batch or delivery of concrete,a slump test shall be carried out.Concrete
slump required to be 17525cm.
pile should select the representative one.The number of test piles which was similar
geological condition or same type and construction conditions should not be less than
5% of the total pile number.Designer and consultant shall decide to increase the
number of test pile when it was the complicated engineering geological condition, or
have questions about the construction quality of pile foundation.
The pile top must be handled before the PDA test,and the concrete strength shall
be same as bore pile concrete C40. The top of the pile should be above the ground and
the length from ground to the pile top shall be 1.5-2 times of the pile diameter. There
is a cushion between hammer and pile top .The sensor must be in compliance with
specification requirements and testing instruments must be in the standard state.
(3) Maintained Load Test
The kentledge reaction system consists of hydraulic jack sitting on the top of the
13
pile head. Upon testing, it is jacked against the main beam which carries a series of
secondary beams acted on by a set of concrete blocks, H-section steel beams or
combination of both. The weight of the concrete blocks should be arranged in a system
aligned with the center of gravity of the test pile as close as possible. The total dead
load shall be a least 10% higher than the maximum test load.
Figure5.9 MLT
The pole head of the test pile shall be casted above ground level, it has to provide
a horizontal platform so as to receive the test load evenly. The ground surface shall be
laid with steel plates as to ensure even distribution of load to the ground so as to
minimize differential settlement due to soft ground condition, if any. A general layout
of the kentledge system is needed.
The loads will be jacked in accordance to the specified load cycle. For each stage
of loading, the increment of load should be applied as smoothly and expeditiously as
14
possible. A set of readings for time and settlement should be taken before each loading
commences. When the load for each stage is reached, time and settlement observations
should be made and record again.
Figure5.10 MLT
All the test equipment such as the survey level, hydraulic jack and pressure
gauges are to be in sound condition. Pressure gauge must be accompanied with an
approved test certificate from an approved laboratory and a copy will be given to the
engineer-in-charge.
The load settlement of the test pile shall be measured by 4 nos. Of dial gauges
and counter checked sing an optical survey level.The average settlement of the pile is
taken from the average of 4nos. of dial gauges. The dial gauges are placed equally at
the sides of the test pile and fixed firmly on the reference frame by means of welding
or using a magnetic base.
15
A scale rule is secured firmly on the pile head or the side of the hydraulic jack, as
another mean to measure the pile settlement. Two external scale rules, to be erected on
the ground. These bench marks are usually set up at an angle 90 degrees to the
leveling instrument. The survey level is to be secured firmly on the ground.
(3) PIT Test
The PIT Test used to detect the pile has defects or not,degree of defect and its
position.Hit the pile top with a small hammer, and receive stress wave signal from the
pile by the sensor bonding at the the top of the pile.Using the stress wave theory to
research the dynamic response of the pile soil system, analyse the measured speed
signal, frequency signal,and obtaining the conclusion of pile integrity.
70 dB(A)
85 dB(A)
18
19