What Is Post Implementation Review
What Is Post Implementation Review
As its name suggests, the post-implementation review focuses on learning how well
the change was deployed. It asks the team the following questions:
• Was the change implemented as per approved schedule?
• Was the change implemented successfully?
• Were there any impacts during implementation?
• Was there any last minute change of plans or activities?
• If change was backed out, what was the reason and were the business informed?
The change manager identifies2 who attends each post-implementation review.
Among those who typically attend are:
Change initiator
Change implementer
1 Operations and change team monitor the service for any incidents caused after
implementation or for any unknown impact.
2 Optionally the Service Level Manager, can also be part of the Post Implementation Review
team.
IT Change Management
Post Implementation Review Document
Operations manager
Change manager
Representatives from CAB (These members are notified during the CAB meetings,
they do not need to be present during the post implementation review)
The change review is the last set of activities for the change management process. If
the post-implementation review judges the change to be successful, the RFC is closed
and responsibility is transferred to the Operating and Supporting Quadrants.
The following figure is a flow chart that illustrates four possible outcomes of the post-
implementation review:
Change meets original objectives
Change needs to be backed out
Change needs additional changes to support goals
Change does not meet original goals, but does not need to be backed out and does
not require further changes
IT Change Management
Post Implementation Review Document
Change
Implemented
CM moves RFC to
monitoring state
Post
Implementation
Review Survey
Questionaire
Yes
Yes
1. Observation
The Change Manager moves the RFC from “Implemented” to “Monitoring and
Review” stage. The RFC will be kept in this stage for a defined period to monitor if
any incidents or other unknown impacts arise due to the implementation.
2. Survey (Questionnaire)
Once the monitoring phase is over, the Change Manager categorizes the
implemented change with help of implementer and other responsible staff. The
Change Manager publishes a set of questionnaire which is required to be answered
by the Change Implementer. These answers are reviewed by a group of nominees
and categories are labeled to the RFC.
Completed with no Impact
Backed out change
Minor Incidents occurred
Significant impact due to implementation
Labeling the RFC (Status = Completed and Rating = A, B, C, D, E)
Based on the submitted answers, the Change Manager labels the RFC into 5 type3
If the Change is successfully implemented and does not result in any new
Incidents the RFC is labeled as completed and given an “A” rating.
If the Change is completed with minor/major deviations resulting in minor
incidents, the RFC is termed completed once the solutions are applied and given
a rating “B”.
If the Change is completed, but resulted in Major incidents and require additional
RFC’s to patch-up, the RFC is given a Rating “C”.
If the Change does not get desired result and needs to be backed out due in any
condition, the RFC is given a rating “D”
If the Change is not completed within the approved time, or an unauthorized
change is implemented, the Change Manager will give a rating “E”.
3 RFC’s with Rating “C, D and E” are forwarded to SVP of respective teams for informational
reasons.