Quantity Estimation Report

This document summarizes the reinforcement and concrete requirements for various structural elements of a building, including: - Columns require 25mm, 20mm, and 16mm reinforcement bars totaling over 7000kg - Beams require 25mm, 20mm, and 16mm bars totaling over 13,500kg - Slabs require over 27,000kg of reinforcement and have a total concrete volume of 116m3 - The raft foundation requires over 15,000kg of 16mm bars and uses over 400m3 of concrete - Shear walls use over 5000kg of rebar and require 36m5 of concrete - The basement includes column and tie beam reinforcement and uses over 25m3 of concrete
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
435 views9 pages

Quantity Estimation Report

This document summarizes the reinforcement and concrete requirements for various structural elements of a building, including: - Columns require 25mm, 20mm, and 16mm reinforcement bars totaling over 7000kg - Beams require 25mm, 20mm, and 16mm bars totaling over 13,500kg - Slabs require over 27,000kg of reinforcement and have a total concrete volume of 116m3 - The raft foundation requires over 15,000kg of 16mm bars and uses over 400m3 of concrete - Shear walls use over 5000kg of rebar and require 36m5 of concrete - The basement includes column and tie beam reinforcement and uses over 25m3 of concrete
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

Quantity Analysis Report:

Beam Engineering

Consultancy

Column Reinforcement summary:


Ground Floor :
25 mm bar = 520 Kg
20 mm bar = 1055 Kg
First Floor:
20 mm bar = 1125 Kg
16 mm bar = 170 Kg
Second Floor:
20 mm bar = 790 Kg
16 mm bar = 385 Kg
Third Gloor:
20 mm bar = 230 Kg
16 mm bar = 745 Kg
Fourth Floor:
16 mm bar = 890 Kg
Fifth Floor:
16 mm bar = 255 Kg
All Floor:

25 mm bar-520 kg
20 mm bar -3200 kg
16 mm bar -2445 kg

Lateral Ties : 8 mm bar -1320 kg

Calculation of volume of concrete

column

Number of column =74 column


Size of column= 400 mm*400 mm
Volume of each column = .4*.4*2.85 ( considering 2.85m length of column)

Number of column in each floor =14


Vol of column in each floor = 0.4*0.4*2.85*14 =6.38 m3
M20 (1:1.5:3)
cement: 1.16 m3 =(45-50) bags
Sand: 1.74 m3
Aggregate: 3.48 m3

Total Volume of column =33.74 m3 (74 column)

M20 (1:1.5:3)
cement: 7.10 m3 =250 bags
Sand: 8.87 m3
Aggregate: 17.75 m3

Beam Reinforcement Summary:

All floor:
25 mm bar 746 kg
20 mm bar -5070 kg
25 mm bar 7657 kg

Lateral Ties 8 mm bar =13900 kg


Calculation of volume of concrete

BEAM

Ground Floor:
10 m3 ( Tie Beam )
First Floor :
Main Beam =13.6 m3
Sec Beam = 1.92 m3
Second Floor Fifth Floor :
Main Beam = 55.68 m3
Sec Beam = 8.32 m3
Top Floor :
Main Beam =7.6 m3

Total volume of Beam = 97.12 m3 ( suppose 100 m3)


M20 (1:1.5:3)
CEMENT =700 Bags
SAND = 27.27 m3 (ie. 30 m3)
AGGREGATE=54.54 (ie .55 m3)
Reinforcement in slab:
Thickness of slab=5 inch=0.127 m
Area of slab=14.021*12+11.51 =180 m2

Vol. of each slab= 22.86 m3


Cement bags required for each slab= 160 bags (M20)
Cement: 4.15 m3
Sand : 6.23 m3
Aggregate: 12.46 m3

Total vol. of slabs=116 m3


Total Reinforcement for slab:
116*0.03*7850 =27318 kg (considering 3 % reinforcement)

Cement bags required for slabs= 812 bags (M20)


Cement: 25.2 m3
Sand : 38 m3
Aggregate: 75 m3

Raft Foundation Details

Area covered by raft foundation=


=

(15.821*11.87+10.33+37.55)

575.67 m2

Raft Reinforcement Detail:


16 mm rod used on bothways:
16 mm @ 100 c/c spacing
16 mm steel = 15000 kg
Stirrups: (10 mm @ 300 c/c spacing)
= 1700 kg

Concrete Requirement
Depth of raft foundation

0.7 m

Volume of raft foundation =

405 m3

Cement: 2592 ~ 2600 cement bags


Sand : 110.45 m3 ~ 117 m3
Aggregate: 220 m3
Including P.C.C ( 1:2:4 )
75 mm P.C.C

Area of P.C.C = 575.67 m2

Volume of P.C.C = 43.17 ~45 m3


Cement: 300 cement bags
Sand : 13 m3
Aggregate : 25 m3

Summary of Raft Reinforcement


16 mm rod used on bothways:
Bothways (16 mm) = 15000 kg
Stirrups: (10 mm ) = 1700 kg

Summary of Concrete requirement for P.C.C and Raft Foundation

Cement : 2600 + 300


bags

2900

Sand : 117+13

130 m3

Aggregate: 220+25

245 m3

Shear Wall Details:


Length of Shear wall = 55 m

Reinforcement Details:
12 mm rod ( Horizontal ) = 3000 kg

10 mm rod ( Vertical) = 1700 kg


10 mm rod ( Stirrups clips) =700 kg

Concrete Requirement for Shear wall :


Considering Typical height of Building = 2.85 m
Volume of concrete : 36.05 m3
Cement: 6.55 m3

230 cement bags

Sand : 9.83 m3

10 m3

Aggregate:19.66 m3

20 m3

Basement Reinforcement Requirement:


Column Reinforcement :
25 mm bar = 520 Kg
20 mm bar = 1055 Kg

Vol of column in each floor = 0.4*0.4*2.85*14 =6.38 m3

M20 (1:1.5:3)
cement: 1.16 m3 =(45-50) bags
Sand: 1.74 m3
Aggregate: 3.48 m3

Tie Beam Reinforcement:


Reinforcement:
16 mm = 900 kg
Volume of Concrete:

10 + 13.6 + 1.92

25.52 m3
Concrete Requirement for tie beam and Basement:
Cement =165 cement bags
Sand = 7 m3
Aggregate = 14 m3
BEAM reinforcement :
16 mm=640 kg
20mm =655 kg
25 mm =130 kg

Cement bags required for each slab= 160 bags (M20)


Cement: 4.15 m3
Sand : 6.23 m3
Aggregate: 12.46 m3