Dolomite Manual
Dolomite Manual
Dolomite Manual
AUGUST 2004
INTRODUCTION
This document serves as a guideline on appropriate development and risk
management of infrastructure located on dolomite in South Africa. These guidelines
are aimed at informing principal agents and other consultants of the minimum requirements
of the Department of Public Works concerning the upgrading, extension and development
of new infrastructure on dolomite, thereby promoting safe, sustainable development.
The objective of applying a risk management strategy to infrastructure is to ensure the
safety of personnel and visitors, protection of property and to avoid fruitless expenditure.
Avoiding sinkholes is not only important from a safety point of view, rehabilitating sinkholes
and repairing buildings/infrastructure is costly.
In a climate of increasing awareness of individual rights, it is apparent that failure to proactively manage dolomite risk may constitute dereliction of duty and may expose the
Department of Public Works, its officials, its principal agents and other consultants involved,
to recourse through a number of avenues, including the Occupational Health and Safety Act
of 1993. It should be clearly understood that principal agents and consultants are not
absolved of their responsibilities and cannot claim ignorance in the event of damage or loss
of life in a sinkhole.
In terms of bona mores, the criterion of reasonableness, it is essential that the Department
of Public Works and its consultants "act" and are seen to act positively in order to prevent
harm. Infrastructure must be appropriately designed, constructed, and serviced to facilitate
management of the dolomite risk. To this end the Department of Public Works has adopted
a Centralised Dolomite Risk Management Strategy for infrastructure located on all dolomitic
land. This strategy aims to ensure appropriate:
-
site selection,
development design
building design
design of services, material selection, maintenance friendly systems etc.
ongoing risk management.
The principal agent and other consultants play a crucial role in ensuring that this strategy is
successfully implemented. Background information and appropriate planning, water
precautionary and remedial measures are outlined below.
2.
BACKGROUND INFORMATION
This section is devoted to providing a rudimentary background perspective on the dolomite
issue.
2.1
2.2
2.2.1
Sinkholes
Sinkholes result from the hollowing out of a space below the earth surface
which eventually breaks through and 'daylights' at the surface. Sinkholes are
usually cylindrical to conical in shape and can be 1 m to 100 m in diameter and
1 m to 150 m deep. Sinkholes are catastrophic and can cause property
damage or loss of life. See figure 2 (page 35) for mechanism of sinkhole
formation and plates 1 to 7 (page 38 to 41) for typical sinkholes.
Sinkholes:
-
2.2.2
Dolines
Dolines are less sharply defined than sinkholes, occur slowly and not
catastrophically (see doline effect on structures in Plates 8 and 9 on page 42).
These features may be large ranging from tens of metres to kilometres in
diameter or length. Typical visual observations at small dolines are shallow
earth depressions and surface cracks in a circular or semi circular pattern.
It should be noted that in South Africa the terms sinkhole and doline are
currently used to refer to geomorphological features and are no longer
distinguished by the mechanism of formation.
2.2.3
filled over time by transported soil material, e.g. wind blown, aeolian
sands. These materials may extend below the original ground water
level. In such instances a fall in the ground water level leads to a
change in the moisture regime of the soils that re-activates the
sinkhole.
The dolomitic environment is often characterised by zones of deep
weathering and preferential leaching. This process of preferential
weathering is particularly well advanced within the shear zones of
faults. Subsurface karst valleys up to 200 m in depth may develop in
these shear zones. Spectacular representations of these features can
be seen on the Far West Rand.
In many of these areas, the water table is located above the bedrock,
in residual soils. These residual materials are essentially composed of
wad and ferroan soil. The artificial lowering of the water table may
produce significant ground movement at the surface. This process
manifests as a doline at ground surface.
2.3
2.4
LOW
MEDIUM
HIGH
Table 1:
2.5
3.
3.1
3.1.2
See also section 3.1.2.2 below and PRM 011 in Appendix 8 on page
162
electricity etc
existing water boreholes.
4.
4.1
4.1.2
b.
c.
d.
e.
Water, sewer and storm water piping should, wherever possible, not
be placed parallel to buildings unless it is at least 5 meters away from
the structure. Single direct connections to buildings are preferred.
This precaution also applies to electricity and communication cables.
f.
g.
b.
4.1.3
c.
d.
e.
Storm water
a.
The site and surrounding area shall be shaped (if required) to permit
the rapid drainage of surface water and to prevent ponding on the site.
Careful attention is to be given to the drainage of areas with gradients
less than 1:100.
b.
c.
d.
e.
f.
g.
h.
pipes should be tested for leakage using standard SABS air or water
tests. All pipes and structures shall be constructed to show zero
percent leakage, when tested as prescribed.
i
j.
Open drains are preferably to be shallow, 1000 mm (min) wide, cast insitu, V-shaped drains with sealed key type construction and expansion
joints. Steel reinforcement (if applicable) is to be continuous over joints
to preclude horizontal displacement.
k.
4.1.4
Sewer
a.
b.
PVC
4.1.5
4.1.6
c.
d.
All sewerage pipes and fittings must be watertight. All laid drainage
and sanitary sewer pipes should be tested for leakage using the
standard SABS water test on installation. Welded HDPE pipe systems
to be pressure tested to relevant pipe pressure class and
manufacturers specification. The welding on of purpose made endcap sections with feed and bleed valves as well as a pressure gauge
can be used for this purpose to test welded pipe sections between
manholes, prior to welding on of manholes.
e.
f.
Avoid using rodding and cleaning eyes and rather use small HDPE
manholes (multi directional collecting pots) that are pre-manufactured
small size (300, 500 and 700 mm diameter) manholes with factory fitted
HDPE benching. Piping from the manhole to surface level shall consist
of HDPE pipes and long radius bends with electro fusion/butt welded
connections. All HDPE material to be Type PE 100 as per SABS ISO
4427/SANS 4427 and all welding to conform to SABS 0268/SANS
10268, SABS 0269/SANS 10269, SABS 1269/SANS 1269, SABS
0270/SANS 10270, SABS 1655/SANS 1655 and SABS 1671/SANS
1671. Manhole shafts to be structured or solid wall HDPE pipes with
8,0 kN/m2 ring stiffness or alternatively manufactured to same
standard.
g.
Swimming pools
a.
b.
c.
d.
The sleeve and draw box systems for electrical and communication
cables shall also be water tight, flexible and constructed to avoid water
entering the system. HDPE piping and small diameter manholes as
described for sewers above are ideally suited for this purpose. Design
and material selection to be similar as for sewer reticulation described
above.
b.
c.
4.1.7
The use of non-cohesive, single size, graded sand or crusher sand for
bedding, surround blankets and backfilling of trenches is not permitted.
Construction details are to be similar to water and sewer pipes.
Water
a.
The piping used in bulk supply, ring mains and secondary reticulation
should be flexible. Joints should be minimal in number and of the
flexible, self anchoring type, i.e. not reliant on thrust blocks or friction
for their anchorage.
b.
4.1.8
4.1.9
c.
d.
e.
f.
Shut-off valves and water meters shall be supplied at main supply with
permanently fixed pressure gauge on the building side of the main
shut-off valve (for regular systems testing).
g.
Roads
a.
b.
c.
Ensure that surfaced roadways and parking areas are in fact placed
below site level so as to facilitate drainage.
Plumbing
a.
b.
4.1.10
4.1.11
c.
All connections between flexible and rigid pipes shall be provided with
flexible, self-anchoring joints. Such connections must be in watertight
structures or above ground level.
d.
e.
The use of surface mounted GMS water pipes on external walls and
from the roof downward is preferred for all building water reticulation.
The chasing of water piping into walls should be kept to a minimum.
The placing, protection and support of exposed pipes are to be
designed to ensure serviceability during fires.
f.
Drainage
a.
The collection of sewer and waste pipes from multiple adjoining toilets
or washbasins should be externally surface mounted. These pipes
should feed into a single down pipe draining into the subsurface
systems.
b.
c.
All sewer pipes and fittings shall be provided with flexible, watertight
joints.
d.
e.
f.
b.
c.
4.1.12
4.1.13
4.1.14
d.
e.
f.
Blasting
a.
b.
b.
Foundations
a.
b.
c.
d.
18
4.2
The precautionary measures as detailed above for Low Risk areas shall
apply as well as amendments thereof and additional requirements listed
below.
a.
b.
c.
d.
e.
f.
Earthworks on pipes: SABS 1200 LB: Bedding and selected fill Clause 3.1 is amended to allow the maximum aggregate size, not to
exceed 6 mm. Material should not be free draining as described in this
particular clause. The compacted bedding and fill material shall be
less permeable than the in-situ soil.
g.
h.
i.
Storm water canals should have a 250 micron HDPE lining and
continuous light steel mesh reinforcement over sealed key construction
and expansion joints that preclude any vertical movement.
j.
4.3
k.
l.
m.
n.
All storm water from down pipes shall discharge into concrete lined
channels which in turn will discharge the water at least 10 metres away
from structures onto areas that permit free surface drainage away from
structures.
o.
p.
All concentrated storm water entering the site shall be diverted away
from any structure or developed area by means of concrete lined
channels.
q.
The use of welded HDPE piping systems for water, sewer and storm
water is required as the material is more tolerant of movement. The
above ground mounting of a GMS water reticulation on steel pedestals
is preferred. Alternative materials only to be used if approved by
departmental Engineer. All material for HDPE pipes, structures and
fittings must be in accordance with SABS ISO 4427/SANS 4427 for
type PE 100 and all welding and manufacturing to be in accordance
with SABS 0268/ SANS 10268, SABS 0269/SANS 10269, SABS
0270/SANS 10270, SABS 1655/SANS 1655 and SABS 1671/SANS
1671 codes. All joints to be welded, unless joint is installed for future
dismantling. Such joints are to be installed in water retaining structures
that can be inspected.
r.
s.
t.
The water precautionary measures listed above for Low and Medium Risk
areas as well as additional measures and amendments outlined below
are applicable in High Risk areas. These measures are also applicable
where development on high risk areas is unavoidable e.g. where the additions
are made to existing infrastructure in a high risk area or where an entire site is
regarded as a high risk area.
a.
Use only HDPE piping for water (Class PN 12,5 and higher), sewer
(Class PN 10 minimum) and storm water (8 kN/m2 ring stiffness) in
20
4.3.2
b.
c.
d.
Use aprons of large (5,0 m min width) impervious paved areas around
structures to enhance drainage. If rapid drainage (slopes 1:15 and
steeper) away from structures is possible apron slabs may be reduced
to 3,0 m width.
e.
f.
b.
c.
5.
d.
e.
f.
6.
6.1
General
OF
To be issued in future
(Red Book)
Water Supply and Drainage for Buildings
(Part 1 and Part 2)
Code of Practice for Community
Protection against Fire
The Application of the National Building
Regulations
Specifications of Materials and Methods
to be used
All documents referenced in Section F,
paragraph F.2 of Civil Engineering
Manual
6.3
Status of Documents
6.2.1
6.2.2
Project Standards
6.3.1
General
New infrastructure shall be located as far as possible on the lowest risk
dolomitic soil.
The Project Requirements below have preference above all the listed
documents.
The prescriptions of the local fire fighting authority shall prevail.
The basic design standards of the Department are as follows (in addition to
the requirements of the documents listed in item 6.1).
6.3.2
Water Supply
6.3.2.1
6.3.2.2
6.3.2.3
6.3.2.5
6.3.2.6
6.3.2.7
6.3.2.8
6.3.2.9
6.3.2.10
6.3.2.11
6.3.2.12
6.3.2.13
6.3.2.14
6.3.2.15
6.3.2.16
6.3.2.17
6.3.2.18
6.3.2.19
15 m
5m
6.3.3
Average
Outside traffic areas
In traffic areas
0.75 m
0,60 m (min)
1,0 m (min)
6.3.2.20
6.3.2.21
6.3.2.22
Sewerage Design
6.3.3.1
6.3.3.2
6.3.3.3
6.3.3.4
6.3.3.5
6.3.3.6
6.3.3.7
6.3.3.8
6.3.3.9
6.3.3.10
6.3.3.11
6.3.3.12
Cover to pipes
a
b
c
Average
Outside traffic areas
Inside traffic areas
0.75 m
0,60m (min)
1,0 m (min)
6.3.3.13
6.3.3.14
6.3.3.15
6.3.3.16
6.3.3.17
6.3.3.18
6.3.3.19
26
6.3.4
6.3.4.2
6.3.4.3
6.3.4.4
6.3.4.5
6.3.4.6
6.3.4.7
6.3.4.8
6.3.4.9
6.3.4.10
6.3.4.11
6.3.4.12
6.3.4.13
calculations.
6.3.4.14
6.3.4.15
6.3.4.16
6.3.4.17
6.3.4.18
Cover to pipes:
a
b
c
6.3.4.19
0.75 m
0,60m (min)
1,0 m (min)
Friction coefficients:
a
i
ii
b
i
ii
6.3.5
Average
Outside traffic areas
Inside traffic areas
Colebrook White
secondary losses)
Plastic pipes
Concrete pipes
friction
coefficient
(including
k = 0.6 mm
k = 1.5 mm
6.4
Scope
This material specification outlines the requirements for the manufacture of
PE-HD (High Density Polyethylene) Pipes & Fittings to be utilised.
6.4.2
Quality assurance
It is the responsibility of the manufacturer/supplier to establish Quality
Assurance by means of quality control procedures, which shall ensure that
the product will meet the requirements of this specification. The
28
Inspection
The design Engineer must ensure that pre-delivery tests are conducted at
the manufacturers/suppliers works.
Tender documentation must stipulate that the Contractor will arrange with
the supplier access to his works for the purpose of inspecting either during
the course of manufacturing or when completed and shall permit the design
Engineer all reasonable access to conduct such inspections.
Copies of all test schedules and manufacturers quality control records as
called for in the relevant SABS (or similar) specifications and Tender
specifications shall be submitted by the Contractor for examination by the
design Engineer.
6.4.4
6.4.5
Characteristics
Raw material composition for pipes, fittings (e.g. stubs) and other elements
(e.g. sheeting for benching) shall be PE 100 pre-compounded black.
6.4.5.1 Technical considerations for raw material and finished product:
Physical/Chemical
Property
Density
Melt Flow Index
(190C/5Kg)
Vicat Softening Point
Crystalline Melting
Range
Standard
Value
Unit
ISO 1183
ISO 1133
0.949-0.960
0.25-0.35
g/cm3
g/10min.
ISO 306
ISO 3146-85
64-68
130-135
C
C
29
Viscosity Number
ISO 1628-3
Mechanical Property
Shore D, Hardness
Elastic Modulus
Tensile Yield strength
Ultimate Tensile
Ultimate Elongation
Flexural Stress (3.5%
Deflection)
Thermal Stability (OIT
@ 210C)
Carbon Black Content
6.4.5.2
cm3/g
Standard
ISO 868
ISO 527
ISO 527 /
ISO 6259
ISO 527 /
ISO 6259
ISO 527 /
ISO 6259
ISO 178
Value
61
900
24
Unit
MPa
MPa
35
MPa
>600
19
MPa
ISO 10837
>40
minutes
ASTM D 1603 /
ISO 6964
2.25 +/0.25
Pipe characteristics
Characteristics
Outer Diameter
Min Wall Thickness at any
point
Ovality
6.4.6
390
Applicable Standard
ISO 11922-1 (Grade B)
ISO 11922-1 (Grade U)
ISO 4065
ISO 11922-1 (Grade N)
Welding requirements
PE-HD pipes and fittings welders to be certified under the Thermoplastics
Welding Institute of South Africa (TWISA)
The following standards shall apply:
SABS 0268/SANS
Part 1
SABS 0268/SANS
Part 2
SABS 0268/SANS
Part 3
SABS 0268/SANS
Part 4
SABS 0286/SANS
Part 10
SABS 0269/SANS
10268
10268
10268
10268
10268
10269
30
6.4.7
6.4.8
Testing of pipes
Testing as contained in the SABS ISO 4427 /SANS 4427 specification shall
apply. Tests shall also be conducted ad-hoc by a registered and authorised
testing body as determined by the Department of Public Works.
6.4.9
6.4.10
Pipe marking
All PE-HD Pipes shall be indelibly marked at 1 meters intervals with the
following details:
Reference item
Trade name
Specification
Pipe OD
Pipe OD tolerance
Wall thickness
Nominal pressure
Material designation
Batch no.
Mark printed
Manufacturer/Supplier Name
SABS ISO 4427/SANS 4427
e.g. 160
Grade B
e.g. 7.7
e.g. PN 10
PE 100
Manufacturer/Supplier Trace ability
8.
SPECIFICATIONS,
QUANTITIES
8.1
The General Conditions of Contract for Civil Engineering Construction: Latest eddition
shall be applicable. Refer to latest copy of specials/amendments.
Tender document and Schedule of Quantities shall be drawn up in accordance with
SABS 1200/SANS1200 Specification except where amended by the Department.
No dumping is allowed on Site other than at the designated and approved fill areas.
Dumping will only be allowed for filling sinkholes and dolines and may not be detrimental
to the natural storm water drainage of the area. Only soil, rock and clean masonry and
concrete rubble may be dumped in the designated dump areas.
No borrow pits are allowed on Site.
No overhaul is payable on any material whether on site or off site.
All backfill for trenches, manholes etc, shall be composed of material which, after
compaction, will be less permeable than the in-situ soil. This applies to pipe bedding,
blanket and surround material as well.
Rate-only items shall as far as possible not be used. Balance quantities out to allow a
reasonable quantity of each item, which may be required on Site.
All storm water pipe work shall also be HDPE pipes except where otherwise approved by
the Department. Provide therefore also items with quantities for HDPE storm water pipes
up to the maximum available in the RSA, in addition to concrete pipes with rubber rings
for the larger storm water pipes.
The inlets and outlets of each manhole and junction box shall be sealed, the structures
then filled to the brim and water tight covered against evaporation, where after they are
independently tested for zero leakage over a minimum period of 48 hours.
No contingency sums/items are allowed.
Where trench excavated material is utilized for bedding, surround and backfill materials,
the materials shall be compacted to at least 93 % Mod AASHTO or the density of the insitu soil, whichever is higher. Where imported materials are used for trench bedding,
surround or backfill materials, laboratory permeability and density tests shall be
conducted on both the in-situ trench material and the imported materials to ensure that
the bedding, surround and backfill materials are less permeable than the in-situ soil after
placement and compaction to at least 93 % Mod AASHTO. Suitable bill items shall be
provided in the Schedule of Quantities for all the above work.
Bedding material shall conform to SABS 1200/SANS1200 LB subject to the maximum
aggregate not exceeding 6mm and the permeability to be lower than the in-situ soil.
Tender specifications in terms of HDPE pipes, fittings and structures shall include or refer
to all relevant specifications as per this document. Please specify the pipe materials,
supply lengths, joining methods, removing of internal welding bead (de-burring), camera
inspections of finished joints as well as the specific pressure testing requirements and
methods. The Tender must specifically state that the tender acceptance shall be subject
to the submission (one submission only) and approval of the HDPE product
manufacturer/s or supplier/s to be used by the Tenderer. Such submission may be
called for during evaluation of Tenders. The Department reserves the right to reject a
Tender if the proposed manufacturer or supplier of HDPE products does not meet the
requirements as stipulated in the relevant SABS (or similar) specifications.
The latest revision of the Occupational Health and Safety Act shall be applicable to this
contract. Consultants to note the reference to this Act and the execution thereof as per
the standard forms of appointment, related to professional service providers, as issued
by the Department.
Preliminary Bills of Quantities are attached as Appendix 11 of this document. These bills
serve as a guideline and must be verified and checked by consultant for correctness and
appropriateness.
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
8.10
8.11
8.12
8.13
8.14
8.15
CONSTRUCTION
REQUIREMENTS
AND
SCHEDULE
OF
32
FIGURES
33
34
LEAKING PIPE
GAP GRADED SOIL WITH
HIGH PERMEABILITY
DOLOMITE (SEE ALSO
FIG 3)
CHERT
PERCOLATING WATER
ARCH IN SOIL ABOVE
CAVITY
RECEPTICALE
SINKHOLE DAYLIGHTS
LEAKING PIPE
ARCH MIGRATION
SLOT FLUSHING
FIGURE 2:
35
FIGURE 3:
36
PLATES
37
40
41
42
APPENDIX 1
43
APPENDIX 1
PRO FORMA GEOTECHNICAL INFORMATION SHEET FOR TOWNSHIP PROCLAMATION STAGE
CIRCULATION OR PROCUREMENT OF NEW SITES
The following format and relevant clauses are to be incorporated in the documentation to be submitted
by any developer seeking approval for proclamation or wishing to sell property to GOVERNMENT
DEPARTMENTS for the purpose of erecting police/court/community or other state facilities on dolomitic
land.
PROPOSED GENERAL PLAN OF ................................................. (township name) FOR TOWNSHIP
ESTABLISHMENT
PROVIDE TITLE / REFERENCE NO / DATE / AND AUTHOR OF GEOTECHNICAL REPORT FOR
TOWNSHIP PROCLAMATION OR SITE TO BE SOLD:
SERVICES/
POLICE
(stand no:__________/ size ____________)
* Dolomite stability risk zonation as portion (%) of total site: Inherent Risk Class 1:..%,
Inherent Risk Class 2,3 and 4:...%, Inherent Risk Class 5,6,7 and 8:...%
JUSTICE
(stand no:__________/ size ____________)
* Dolomite stability risk zonation as portion (%) of total site: Inherent Risk Class 1:..%,
Inherent Risk Class 2,3 and 4:...%, Inherent Risk Class 5,6,7 and 8:...%
DEFENCE
(stand no:__________/ size ____________)
* Dolomite stability risk zonation as portion (%) of total site: Inherent Risk Class 1:..%,
Inherent Risk Class 2,3 and 4:...%, Inherent Risk Class 5,6,7 and 8:...%
CORRECTIONAL SERVICES
(stand no:__________/ size ____________)
* Dolomite stability risk zonation as portion (%) of total site: Inherent Risk Class 1:..%,
Inherent Risk Class 2,3 and 4:...%, Inherent Risk Class 5,6,7 and 8:...%
PUBLIC WORKS
(stand no:__________/ size ____________)
* Dolomite stability risk zonation as portion (%) of total site: Inherent Risk Class 1:..%,
Inherent Risk Class 2,3 and 4:...%, Inherent Risk Class 5,6,7 and 8:...%
*
DRAWINGS ATTACHED
Township layout and site with dolomite risk zoning indicated as well as position of boreholes and test
pits.
DOCUMENT ATTACHED
Detail geotechnical report compiled in terms of current practice.
44
..........................
DEVELOPER
..............................
DATE
............................
TEL.
..........................
FAX
45
APPENDIX 2
46
APPENDIX 2
MINIMUM REQUIREMENTS FOR A GEOTECHNICAL INVESTIGATION ON A DOLOMITIC SITE
1.
geophysical investigation
borehole work
geological investigation
geohydrological data
Dolomite risk characterisation procedure
surficial soils mantling the site and comment on the immediate environs
Dolomite stability zonation
2.
3.
4.
Previous investigations
Old borrow pits
Rehabilitated areas
Dumpsites
Water boreholes
Permanent or temporary natural water drainage features traversing the site
REPORT FORMAT
The geotechnical report shall be structured as follows:
4.1
Terms of reference
4.2
Existing information
4.3
4.4
Desk studies
Gravity survey
(Note: Only drilling will be required if the footprint of building is fixed).
Drilling programme
Trail holes
The visual inspection procedures used shall be referenced, i.e. Jennings et al
(1973).
Laboratory Testing. The original lab reports shall be incorporated in the report
4.5
4.6
4.7
4.8
5.0
Risk characterisation
Indicate remedial Work
Indicate specific/special site development criteria
Recommendation concerning appropriate development of site.
Precautionary measures.
Site layout: 1:500 scale drawings showing the exact positions of:
*
*
*
*
*
*
*
*
Test pits
Boreholes (old and new)
Gravimetric survey
Specific site features
Risk zones
Proposed optimum location of buildings
Boreholes for water
Site contours (if available)
48
APPENDIX 3
49
APPENDIX 3
PRELIMINARY SITE INVESTIGATION BY THE PRINCIPAL AGENT: DOLOMITE STABILITY
RELATED MATTERS
Reports presented to the Department for the development of a site (as per PRM 17) should on a
minimum have the following information:
-
Cadastral information
Site contours
Services
*
Existing services that traverse the site
*
Comprehensive reporting on condition and upgrading requires or shifting thereof
Roads
*
Township roads (surfaced/gravel/non existing)
Water
*
Municipal connection
Size
Pressure
Type
Exact location of connection
Storm water
*
Natural drainage features
*
Drainage of the surrounding area
*
Canals (lined, unlined, general condition, possible connection)
*
Stormwater pipes (size, type, possible connection)
Sewer
*
Municipal connection
Location
Size
Material and jointing
Manholes (type, material, joint sealing)
Possible connections
50
APPENDIX 4
51
APPENDIX 4
ENGINEERING SITE INVESTIGATION OF INFRASTRUCTURE ON DOLOMITE: SCOPE OF
WORK
CONTENTS:
1.
2.
3.
4.
WATER
5.
SEWER
6.
STORM WATER
7.
GARDENING
8.
PAVED AREAS
9.
FOUNDATIONS
10.
BUILDINGS
11.
12.
WATER TANKS
13.
14.
SITE MAINTENANCE
15.
16.
GEOLOGICAL
52
1.
2.
Drawing number.....................................................................
Drawing number.....................................................................
Drawing number.....................................................................
Drawing number.....................................................................
Drawing number.....................................................................
Drawing number.....................................................................
Contractor
Tel. no
Water
Sewer
General Building
Storm water
53
).
Description
Now
Future
4.
WATER
Position of water meter
Indicate on site layout (type, condition, shut-off valve, leakages and valve
box, lockable, condition)
Pressure test
Results, pressure and leakages
Approximate route of main water supply.
Inspect routes for:
Depressions
Trees (5m zone)
Unnatural green grass patches
Wet patches
Excavate and report on condition of pipe
External reticulation
Fire hydrants
Garden taps
Sports fields (size, type of irrigation, frequency of irrigation and flow rate, if
metered)
Building reticulation
Indicate position of pipe distribution around building and inspect this route for
any visible leakages, depressions etc.
54
SEWER
Pit latrines
Indicate position, number, can storm water ingress, type of structure, position
of previous pit latrines, duration in use.
Soak-away
Describe condition and size of septic tank and indicate position. Indicate
position of subsurface soak-away, evidence of overflowing)
Conservancy tank
Position, size, general condition, empty cycle, Contractor currently employed
to empty, evidence of overflowing)
Sewage treatment works
Type, condition, age
Discharge
Reed beds, maturation ponds etc.
Water borne sewerage system
Pipe (position, type, condition, depth)
Manholes (position, type, condition, depth, connection details, indicate
regular overflowing, silt deposits etc.)
Route (type of pipe, recent modifications, inspect line for depressions or
unnatural green patches and trees or vegetation on the route).
Drains from buildings
Position, accumulation route, cleaning and rodding eyes, valleys, inspect for
general condition and indicate which portion is above and which below
ground level, leakages, regular overflowing, general condition of surrounding
area, paving, grass, etc.
Pipes above natural ground level for exit from buildings
Pipes through walls (allowance for movement)
All connections between flexible and rigid pipes shall be provided with
flexible, self-anchoring joints.
Pipes under floor slabs (service ducts, inspection possible)
Area of high concentration of sewer outlets out of buildings (condition)
WC pans (provided with a flexible connection).
55
6.
STORM WATER
General drainage onto site
Water courses, location, ponding against boundary, entry at drive ways etc.,
canals, general slopes, position, etc.
Drainage system of surrounding area
The diversion of drainage onto the site
Earth berms, cut off trenches etc.
Diversions of natural watercourses on the site
Natural ponds and watercourses located within 30m of any structure.
Type, lining material, etc.
Drainage of site and surrounding area
Free drainage of surface water
Areas of ponding on the site
Indicate any areas with gradients less than 1:100
Site fence
Type of fence, position of storm water in/outlets, conditions of outlets, ease of
draining, clogging, vegetation etc.
Lowest point of the site.
Storm water canals on the site, further than 10m from buildings.
Gradients, type, size, position, condition, joint sealant, cracking,
displacement, panel lengths, expansion joints, depositing of silt or sand
Storm water pipes
Gradients, type, position, size, location, age, general condition, inlet
structures, jointing, condition of seals.
Storm water drainage around buildings and up to 10 metres away.
Detail of surfacing and open canals, joint sealants, panel dimensions
cracking, displacement joint sealant and condition.
Sloping of surfaces around buildings.
Drainage in passages or between buildings
Slope and direction of flow
Drainage towards a structure.
Storm water pipes and gulleys next to, under or parallel to buildings.
Drainage of grassed areas such as sports fields (minimum of 1:80)
Water tightness of all conduits.
Tests for leakage.
Concrete non-pressure pipes
Type, size, condition, jointing.
56
GARDENING
Indicate all gardening and flower boxes in between or around structures
Inspect for type of gardening activity
Excessive watering, algae, moss growth, type gardening and general
condition
8.
PAVED AREAS
Indicate on drawings all paved areas (e.g. drive ways and parking areas)
Type and current state
Accumulation of debris
Gradients
Purpose to facilitate drainage.
9.
FOUNDATIONS
Foundation type
Exposed foundation or lowering of surrounding ground is causing exposure.
Termite activity
10.
BUILDINGS
Building (original structure) (indicate in black ink)
Date of additions or alterations (indicate in red ink)
Comment on each structure individually and if known on the type foundation,
bricks used etc.)
Inspect each individual structure and indicate on drawings exact positions of
all cracks and magnitudes of deformation.
Mark origin and end of all cracks on date of inspection and give indication of
size.
All cracks in excess of 1 mm and longer than 1 metre must be inspected on a
regular basis and propagation thereof reported immediately.
Indicate all construction and expansion joints in buildings.
57
12.
WATER TANKS
Type, location, condition, depth, height.
13.
14.
SITE MAINTENANCE
General condition of site and building surrounds (general upkeep)
Presence of ash/dump pits and storm water drainage in that area
Sandpits or areas of soil removal
15.
GEOLOGICAL
Risk classification of the site
Indicate the known geological zones on the layout drawings.
Note site conditions (surficial soils, rock outcrop, sudden changes in soil
profile, and soil consistency/type)
Sinkholes, dolines or any other depression
59
APPENDIX 5
60
APPENDIX 5
TYPICAL ENGINEERING DETAILS FOR SERVICES ON DOLOMITIC LAND
Typical, minimum standard, details for engineering designs on dolomitic land are included in this section.
These details and specifications are to be extended/improved to suit the site-specific conditions. All
drawings and specifications are to be checked by the design Engineer.
CONTENTS:
1.
2.
3.
4.
5.
6.
WATER DETAILS
DRAINAGE DETAILS
STORM WATER DETAILS
ROADS DETAILS
PAVING DETAILS
SINKHOLE DETAILS
61
APPENDIX 6
132
APPENDIX 6
PARTICULAR SPECIFICATIONS
The following specifications deal with the particular requirements of work to be executed in dolomitic
areas.
PA:
PB:
PC:
PD:
PARTICULAR SPECIFICATION:
GEOLOGICAL INVESTIGATION
PE:
PF:
EXPLORATORY
DRILLING
FOR
ENGINEERING
133
PA:
Note:
(*)
PA 1
TENDERER S EXPERIENCE
EQUIPMENT
Equipment shall comprise of the following mobile unit/s:
1.
Mobile Crane (* 60 tons) fitted with boom and appropriate cable, clutch and braking
system to handle (*12 tons) free falling square tamper with face not to exceed
(*1,0x1,0 m) as well as a (*12-ton) ball type tamper of (*900 mm) diameter face and a
(*3,0 m) diameter (*12-ton) ironing tamper.
2.
The Boom configuration shall allow drop height of (*18 metres) measured from
normal ground level whilst closest portion of the crane is a minimum of (*13 metres)
away from point of impact. Furthest point of impact to be possible shall be a minimum
of (*20 metres)
3.
Crane to stay stable in the event of weight dropping into a cavity beyond its normal
cable and braking configuration.
4.
Cable shall allow for accidental dropping to a depth of (*20 metres) below ground
level.
PA 4
CONTRACTORS SUPERINTENDENCE
No work shall be executed unless supervised by a Suitable Representative of the Contractor
who shall be made known, in writing, to the Engineer for his approval prior to commencement
of the work.
PA 5
PA 6
PA 7
STANDING TIME
No provision or claims for standing time shall be heard or allowed. In the event of insufficient
information to continue compaction due to lack of information or uncertainty regarding
compaction sequence or the location of marked compaction positions the Contractor shall
inform the Engineer 6 hours (normal business hours) in advance of planned execution of
work.
PA 8
PA9
DYNAMIC COMPACTION
PA10.2 COMPACTION
Compaction to be executed by dropping the weight from an (*18 metre) height in the desired
pre-marked pattern to result in an even distribution of
a.
Primary compaction
b.
Secondary compaction
c.
Ironing/finishing compaction
The compaction imprints shall be filled once it exceeds 700 mm in depth and between each
compaction phase. The Contractor needs to record the settlement of each blow or number of
blows as may be required by the Engineer.
As alternative can the Engineer specify the depth of influence required as well as the required
compaction density at specified depths. In such cases shall the Tenderer submit a proposed
method of work with the Tender.
PA10.3 MEASURED QUANTITY IN BILLS
Tenderer to note that the quantity allowed for in the Schedule of Quantities are provisional
and could change depending on the site conditions encountered.
PA11
FIELD REPORT
The Contractor to provide marked drawings showing location of pre-marked grid and
subsequent compaction imprints as well as the settlement per blow.
PA 12 TESTING
Plate load testing is measured in the Schedule of Quantities as well as a provisional sum for
the ordering of tests as required by the Engineer.
PA13
Sum
PA13.2 DISMANTLING AND RE-ERECTION FOR MOVEMENT ON THE SITE UNDER OWN
POWER AS PER CLAUSE PA 9.2
Unit rate:
No
PA13.3 DISMANTLING AND RE-ERECTION FOR MOVEMENT ON THE SITE PER TRUCK AS PER
CLAUSE PA 9.2
Unit rate:
No
PA13.4 MOVEMENT ON THE SITE UNDER OWN POWER AS PER CLAUSE PA 9.2
Unit rate:
km
136
PA13.5 PROTECTION TO PAVED SURFACES WHILST MOVING ON THE SITE UNDER OWN
POWER AS PER CLAUSE PA 9.2
The rate shall cover all costs to protect and repair (if required) all paved surfaces traversed in
moving between sites.
Unit rate:
No
m2
Values indicated above are to be changed by Engineer to suit the
project specification.
No
137
PB:
PB1:
BLASTING OPERATIONS
General recommendations hereunder to be read with all SABS/SANS and related
specifications regarding blasting. Applicable anywhere in dolomitic areas
a.
b.
c.
d.
e.
138
PC
PC1
Surface cracks
Cavities (irrespective of size)
Any ground movement
Any sudden variation in soil profiles
Should any of the above occur or be noticed, stop work immediately and clear the site of all
personnel until the Engineer inspects the site.
PC 2
METHOD OF REPAIR
Generally the Inverted Filter Method of repair as illustrated in drawing DT 01/SH shall be used
for repair. See also drawings DT 02/SH to DT 06/SH
Repair of sinkholes and dolines shall consist primarily of the following operations:
a.
b.
Choking the throat of the sinkhole with boulders of 500 mm and larger (no fines
allowed) or with a mass or reinforced concrete slab or a combination of all these
solutions.
c.
d.
e.
1.
2.
Further filling to be done with finer material compacted in 200 mm layers to 93% Mod
AASHTO density by means of rammers, walk behind vibrating roller of minimum 900
139
mm wheel width up to 10 ton vibrating roller depending on the area to be filled. The
contact zone between fill and natural material is to be compacted by rammer to
ensure full compaction. Selected material shall have typical consistency of roads subgrade (G8) material and maximum particle size to be 125 mm in diameter
PC 3
f.
Filling of the sinkhole to continue, as above, to a depth of 1,0 metre below ground
level. From 1,0 to 0,5 m below ground level the compaction density needs to be 95%
Mod AASHTO density. Compact in layers not exceeding 150 mm in thickness and
the maximum course size material to be 63 mm in diameter. Selected material shall
have typical consistency of roads sub-grade (G8) material.
g.
Final 500 mm to be filled to specified height above ground level with material
generally classified in the range of silty sand to clay (particle size 1,55 and smaller)
and compacted to 95% mod AASHTO density. This layering shall continue to a height
suitable to allow a minimum of 1: 60 sloping in all directions, falling away from the
centre of the filled area in order to form a positive relief feature. The area is to be
finished off in smooth surfaces preventing water ponding.
140
PD:
GENERAL
This section deals with the drilling of exploratory rotary-percussion boreholes for an Engineering
Geological investigation as well as preparation for subsurface grouting. The Contractor shall be
liable for any work not executed as per specification and shall redo faulty work at own expense if
ordered to do so. The Employer is not liable for any losses or damages to any equipment or
personnel.
PD 1
TENDERER S EXPERIENCE
Only offers from Tenderers with proven past experience of drilling for Engineering
Geological assessments in dolomitic areas will be considered. Tenderer to submit on
Annexure I full details regarding past experience of drilling for Engineering Geological
assessments in dolomitic areas.
Tenderer to indicate all past experience with reference to previous work (give project/site
name) for the Department of Public Works, Department of Mineral and Energy Affairs:
Geoscience and individual Consultants.
PD 2
EQUIPMENT
Drilling equipment shall comprise of the following mobile unit/s:
1.
2.
3.
A compressor unit with measured and calibrated constant air delivery rating (800cfm
minimum) at 16 Bar minimum.
Pneumatic rotary-percussion drilling rig with 165 mm nominal diameter button bit
capable of drilling in all soil types up to 100 m and at any inclination up to 30 degrees
to the vertical.
Additional spares: 1 x drill bit, 60 metres of drilling rods, 60 metres of 150 mm steel
casing.
ALTERNATIVE EQUIPMENT
Tenderer needs to submit details, on Annexure J, of alternative equipment of similar nature
available for the project. Further the Tenderer shall state the down time duration of
replacement, in the event of equipment on site becoming unserviceable or experience major
mechanical failure. Maximum of 4 hours down time will be allowed for minor mechanical
repairs/failures per 40 hours of drilling.
PD 4
CONTRACTORS SUPERINTENDENCE
No work shall be executed unless supervised by a Suitable Representative of the Contractor
that shall be made known, in writing, to the Engineer for his approval prior to commencement
141
of the work. Any faulty work executed in the absence of the Contractors representative shall
be for the account of the Contractor.
PD 5
Payment shall include the surveying cost of the surveyor as appointed by the
Engineer.
Unit rate:
PD6
Provisional
PD 7
STANDING TIME
No provision or claims for standing/idle time shall be heard, allowed, or paid for. In the event of
insufficient information to continue drilling operations due to lack of information or uncertainty
regarding the drilling sequence or the location of marked drilling positions, the Contractor shall
inform the Engineer 6 hours (normal business hours) in advance.
PD 8
PD 9
Rate shall cover all cost to provide, maintain in working order and remove
equipment from the site for the drilling phase. The site establishment shall be
paid once only and no claims for standing time shall be heard or paid for.
Unit rate:
no
142
PD10
no
0 to 30 metre
30 to 60 metre
60 to 100 metre
The drilling shall further be categorised, and paid for, in categories of soil types classified as:
1.
2.
3.
Hard
Soft
Cavity -
Payment:
The applicable rate for drilling in the above classified depths and soil types
shall cover all costs for the supply and maintenance of drilling equipment,
expendable materials, drilling, recovery of samples at 1,0 metre intervals,
addition of water as material to enhance sample recovery, completion of
Drillers field report and delivery of samples to the Engineers laboratory in
.................... on three (3) day intervals.
Unit rate:
PD10.3DRILLING AT INCLINATION
The inclination of boreholes, to be noted in degrees, shall be measured as the deviation from
the vertical. The Drillers log shall indicate the direction of propagation and inclination.
Payment:
Unit rate:
Drilling foam shall be paid for as foam used on the basis of metres drilled
using drilling fluid.
Unit rate:
PD11
litre
CASING
The rate for this work shall cover insertion and recovery of casing.
Unit rate:
Payment:
The rate for this work shall cover cost of supply of casing, insertion, concrete
collar and sealing with a metal cap.
Unit rate:
The rate for this work shall cover cost of supply of casing, insertion, grouting
of annulus, concrete collar and cap as described.
Unit rate:
no
The rate for this work shall cover cost of supply of concrete and work
involved.
Unit rate:
PD12
no
PD13
BACKFILLING OF BOREHOLE
Boreholes are to be backfilled with soil, recovered from drilling, suitably wetted to form flowing
slurry. Back filling and plugging shall be executed only after written instruction to do so is
issued by the Engineer.
Payment:
Payment shall include supply of water, mixing of slurry and filling of borehole.
Unit rate:
PD14
Payment shall include supplying of cement, sand, water, mixing of slurry and
filling of borehole.
145
Unit rate:
Payment shall include supplying of cement, steel rod, wood floating and
inscriptions.
Unit rate:
no
146
PE:
GENERAL
This section deals with the grouting of subsurface cavities with a pumpable concrete or soilcrete
mixture. Work comprises of the pumping of grout mix directly from the mixing truck or stationary
mixer into 50 mm HDPE housing connected to 50 mm steel piping down a previously drilled borehole
to depths as indicated by the Engineer. Execution of each pumping operation shall be continuous
and thus shall the Contractor provide for instances where grouting continues after normal working
hours. The Contractor shall be liable for any work not executed as per specification and shall redo
faulty work at own expenses if ordered to do so. The Employer will not be liable for any losses or
damages to any equipment.
PE 1
TENDERER S EXPERIENCE
Only offers from Tenderers with proven past experience of grouting of subsurface
cavities in dolomitic areas will be considered. Tenderer to submit on Annexure K full
details regarding past experience of execution of subsurface grouting in dolomitic areas.
Tenderer to indicate all past experience with particular reference to previous work (give
project/site name) for the Department of Public Works, Department of Mineral and Energy
Affairs: Geological Survey and individual Consultants.
PE 2
EQUIPMENT
Grouting equipment shall comprise of the following:
ALTERNATIVE EQUIPMENT
The Tenderer needs to submit details, on Annexure L, of alternative equipment of similar
nature available to him. Furthermore, he shall state the down time duration of replacement, in
the event of equipment on site becoming unserviceable or experiencing major mechanical
failure. Maximum of 4 hours down time will be allowed for minor mechanical repairs/failures
per 40 hours of grouting.
147
PE 4
CONTRACTORS SUPERINTENDENCE
No work shall be executed unless supervised by a Suitable Representative of the Contractor
that shall be made known, in writing, to the Engineer for his approval prior to commencement
of the work.
PE 5
PE 6
PE 7
STANDING TIME
No provision or claims for standing time during the execution of grouting shall be heard,
allowed, or paid for. In the event of insufficient information to continue grouting operation,
due to lack of information or uncertainty regarding grouting sequence or depth, the Contractor
shall inform the Engineer thereof before commencing grouting.
PE 8
PE 9
The rate shall cover all cost to provide, maintain in working order and remove
equipment from the site for the grouting phase. The site establishment shall
be paid once only and no claims for standing time shall be heard or paid for.
Unit rate:
Sum
Payment: Set-up rates shall include all costs to set-up the equipment, attaching of
reusable couplings to grout pipes and decommissioning it, movement to next
hole and clearing the site of the completed borehole.
Unit rate:
PE10
no
GROUTING
149
Unit rate:
m3
Grout type 2:
Unit rate:
Grout type 3:
Unit rate:
.
Payment:
The rate shall cover supply, insertion, anchoring to the surface, fitting and
removal of the coupling unit.
Unit rate:
PE12
Surface cracks
Cavities (irrespective of size)
Any ground movement
Should any of the above occur or are noticed, stop work immediately and clear the site of all
personnel until the Engineer inspects the site.
150
PF:
TENDERERS EXPERIENCE
Tenderer needs to indicate in Annexure H experience regarding demolishing of buildings of
this magnitude.
PF 2:
INSPECTION OF STRUCTURE
The Tenderer needs to inspect the structure prior to tendering and sign the appropriate
portion of the Bill of Quantities.
PF 3:
PF 4:
LEGISLATION
The Contractor, whilst executing the work, shall be responsibility for compliance with the
following legislation:
PF 5:
Occupational Health and Safety Act, 1993 (Act 85 of 1993) in general and in
particular with reference to Construction Regulation R1010 dated 18 July 2003. The
Tenderer needs to demonstrate a high standard of safety achievement and a history
of safe work practices and compliance with the Act.
Latest issue of SABS 0142: Code of Practice for the Wiring of Premises
USE OF EXPLOSIVES
The use of explosives will be limited due to the meta stable subsurface conditions.
Demolishing methods using explosives shall be subject to the same requirements as
prescribed in Particular Specification PB: Blasting Requirements.
151
Ground vibrations of both the blasting operation and the collapsing structural elements shall
be subject to the conditions of Particular Specification PB. The Tenderers Method Statement
must reflect measures to be introduced to ensure this (include previous site recordings to
proof this).
If explosive demolition is used, the following shall be covered extensively in the Tenders
Method Statement:
Steps to be taken to avoid injuring the public and causing damage to existing property
in the area.
Plans and safety measures to avoid damage to possible subsurface cavities and
meta-stable ground conditions in the area.
The use of explosives to implode or weaken the structure(s) to such an extent that more than
5% of the structure collapses at any time shall not be allowed.
PF 6
PF 6.1
Rate shall include the complete demolishing and removal of the super
structure, foundations and foundation slabs to 300 mm below natural ground
level and disposing of material at commercial dumpsites. Compacted filling
300 mm proud of natural ground level (to enhance drainage) on footprint of
demolished building to be measured elsewhere as earth works.
Unit rate:
PF 6.2
Rate shall include the complete demolishing and removal of the super
structure, foundations and foundation slabs to 300 mm below natural ground
level and dispose of material at commercial dumpsites. Fill of areas after
demolishing to be measured elsewhere. Dismantling and recovery of
material as well as future re-erection, if required, will be indicated in bill of
quantities. Compacted filling 300 mm proud of natural ground level (to
enhance drainage) on footprint of demolished building to be measured
elsewhere as earth works.
Unit rate:
PF 6.3
Aircraft Hangers
All steel elements inclusive of side cladding and windows need to be dismantled for later reerection. Structure elements are to be dismantled to sizes suitable for road transport. Floor
slabs shall not be removed or damaged.
152
All columns and elements cast into floor slabs shall be demolished to 100 mm below the
surrounding floor slab level. Finish such areas flush with surrounding floor slab by means of
20 MPa concrete.
Payment:
PF 6.4
Sum
Mobile structures
Mobile structures are to be removed from current location to another area.
Payment:
PF 6.5
Sum
Rate includes the complete removal of entire building complex and related
site services and paving. Compacted filling 300 mm proud of natural ground
level (to enhance drainage) on footprint of demolished building to be
measured elsewhere as earth works.
Unit rate:
PF 7:
sum
SAFETY
The Contractor needs to provide proper barricade or security and safety signs around the
building to prevent any person from entering whilst demolishing activities are in progress.
The same shall apply for after hours and over weekends.
Payment:
Sum
153
PF 8
PF 9
DISPOSAL OF DEBRIS
The Contractor shall make his own arrangements for disposal of the rubble or surplus
material in collaboration with the Engineer. All costs related to such disposal shall be deemed
to be included in the rates tendered for the demolition or cleaning up of the buildings.
The Contractor shall submit written consent from the proper authorities for the dumping of
material on sites provided by him. Under no circumstances shall a Contractor be allowed to
dump material on these provided sites without written consent.
Should the Contractor be required or wish to spoil any of the excavated or other material
resulting from the contract on a site to be arranged by the Contractor, he shall provide the
following fully signed documents to the Engineer before spoiling commences:
An indemnity signed by the Contractor and the owner on whose property the material is
to be spoiled. This indemnity must completely indemnify the Department and the
Engineer against all claims whatsoever arising from the spoil of material on this
particular property.
PF 10 METHOD STATEMENT
The Tender must submit a Method Statement for the demolishing of the various structures.
The proposed submission shall include full details (in the absence of which the tender will not
be considered) of the following:
Full detail of the methods that the Tenderer propose to use to carry out the work as
specified, together with the time for completion tendered.
State start and completion dates and a detailed daily program to be implemented.
These methods shall specifically include detail reference to the geological conditions
and Dolomite Hazard and the Tenderers experience in similar geotechnical
conditions.
Preliminary calculations and all relevant data shall be submitted with the tender.
A full description of the assumptions and codes of practice used shall accompany the
calculations.
Specify fence / hoarding to secure site and protect the public as well as other safety
measures to be introduced
Method of notifying adjoining owners / residents.
Evacuation procedures of surrounding buildings and areas during demolition.
Safeguarding of the existing and adjoining properties.
Subsurface geotechnical conditions and the impact that the proposed method may
have as well as ground vibration measuring methods.
Meeting of requirements of legislation pertaining to the work to be executed (submit
relevant documentation).
The Engineer reserves the right to call on the Tenderer to submit additional method
statements, calculations or information regarding the proposed demolishing to be
implemented. Such further details are to be submitted in seven days of request to do so.
154
DATE
VALUE
CLIENT
ENGINEER
TEL. NUMBER
PROJECTS BY SUBCONTRACTOR:
(name) .
PROJECT
DATE
VALUE
CLIENT
ENGINEER
TEL. NUMBER
Signature of Tenderer
155
NO
AGE
SPECIFICATION/RATING
DESCRIPTION
NB:
NO
AGE
SPECIFICATION/RATING
Signature of Tenderer
156
DATE
VALUE
CLIENT
ENGINEER
TEL.
NUMBER
PROJECTS BY SUBCONTRACTOR:
(name) .
PROJECT
DATE
VALUE
CLIENT
ENGINEER
TEL.
NUMBER
Signature of Tenderer
157
NO
AGE
SPECIFICATION/RATING
DESCRIPTION
NO
AGE
SPECIFICATION/RATING
158
DATE
VALUE
CLIENT
ENGINEER
TEL.
NUMBER
CLIENT
ENGINEER
TEL.
NUMBER
PROJECTS BY SUBCONTRACTOR:
(name) .
PROJECT
DATE
VALUE
Signature of Tenderer
159
NO
AGE
SPECIFICATION/RATING
DESCRIPTION
NO
AGE
SPECIFICATION/RATING
160
APPENDIX 7
161
APPENDIX 7
SPECIAL CONDITIONS OF CONTRACT
The latest revision of the Special Conditions of Contract forming the Annexure to the General Conditions
of Contract for use in connection with Works of Civil Engineering Construction Sixth Edition 1990 (as
issued by the Department of Public Works) and in particular clauses referring to work in the dolomitic
environment should be discussed with the departmental Engineer prior to compilation of documentation.
162
APPENDIX 8
163
APPENDIX 8
DEPARTMENTAL PROJECT MANAGEMENT FORMS (PRM)
CONTENTS:
1.
2.
3.
4.
5.
6.
PRM 006
PRM 007
PRM 011
PRM 012
PRM 017
PRM 018
The above PRM forms should be obtained from the Project Manager or downloaded from the official
departmental website at http://www.publicworks.gov.za.
164
APPENDIX 9
165
APPENDIX 9
LIST OF PROVINCES, MAGISTERIAL DISTRICTS, MUNICIPALITIES AND TOWNS LOCATED ON
DOLOMITE
TABLE 9.1.
TABLE 9.2.
TABLE 9.3.
TABLE 9.4.
166
TABLE 9.1
PROVINCE
LIMPOPO
MPUMALANGA
NORTH WEST
NORTHERN CAPE
GAUTENG
FREE STATE
167
TABLE 9.2
ALBERTON
BARBERTON
BARKLY WEST
BENONI
BOKSBURG
BRAKPAN
BRITS
BRITSTOWN
BRONKHORSTSPRUIT
CAROLINA
DELAREYVILLE
DELMAS
GA RANKUWA
GERMISTON
GROBLERSDAL
HAY
HEIDELBERG
HERBERT
HOPETOWN
HUHUDI
JOHANNESBURG
KEMPTON PARK
KIMBERLEY
KLERKSDORP
KROONSTAD
KRUGERSDORP
KUDUMANE
KURUMAN
LETABA 2
LICHTENBURG
LYDENBURG
MADIKWE
MANKWE
MMABATHO
MOKERONG 2
MAGISTERIAL DISTRICTS
MOKERONG 3
MOUTSE 3
NAPHUNO 1
NAPHUNO 2
NELSPRUIT
NIGEL
OBERHOLZER
PARYS
PELGRIM'S REST
PHALABORWA
PHOKWANI
PIETERSBURG
POSTMASBURG
POTCHEFSTROOM
POTGIETERSRUS
PRETORIA
PRIESKA
RANDFONTEIN
RUSTENBURG
SASOLBURG
SEKHUKHUNELAND
SPRINGS
THABAMOOPO
THABAZIMBI
VANDERBIJLPARK
VENTERSDORP
VEREENIGING
VILJOENSKROON
VREDEFORT
VRYBURG
WARMBAD
WATERBERG
WATERVAL-BOVEN
WESTONARIA
WITRIVIER
168
TABLE 9.3
MUNICIPALITIES
COMMON NAME
NEW NAME
BARBERTON
UMJINDI
BARKLEY WEST
THUSANANG MUNICIPALITY
BELFAST
HIGHLANDS
BENEDE
BENEDE
BO KAROO
BO KAROO
BRITS
NW372 LOCAL COUNCIL
BRONKHORSTSPRUIT
KUNGWINI LOCAL MUNICIPALITY
BURGERSFORT/OHRIGSTAD/EASTERN GREATER TUBATSE MUNICIPALITY
TUBATSE
BUSHBUCKRIDGE
BUSHBUCKRIDGE MUNICIPALITY
CARLETONVILLE
MERAFONG CITY LOCAL MUNICIPALITY
DANIELSKUIL
DAN-LIME MUNICIPALITY
DELMAS
DELMAS
DIAMONDFIELDS
DIAMONDFIELDS
DMA LOWVELD
DMA LOWVELD
EAST RAND
GREATER EAST RAND METRO
ELLISRAS
LEPHALALE
ELUKWATINI/CAROLINA
ALBERT LUTHULI
GANYESA
KAGISANO LOCAL MUNICIPALITY
GRIEKWASTAD
SIYANCUMA MUNICIPALITY
GROBLERSDAL
GREATER GROBLERSDAL MUNICIPALITY
HEIDELBERG
LESEDI LOCAL MUNICIPALITY
HOEDSPRUIT
DRAKENSBERG MUNICIPALITY
HOPETOWN
ORANJE-KAROO MUNICIPALITY
JOHANNESBURG
CITY OF JOHANNESBURG
KALAHARI CBDC
KALAHARI CBDC
KATHU
GAMMAGARA MUNICIPALITY
KGALAGADI
SEGONYANA MUNICIPALITY
KLERKSDORP
KLERKSDORP LOCAL MUNICIPALITY
KOSTER
NW374 LOCAL MUNICIPALITY
KROONSTAD
MOQHAKA LOCAL MUNICIPALITY
KRUGERSDORP
MOGALE CITY LOCAL MUNICIPALITY
KURUMAN
KURUMAN-MOTHIBISTAD MUNICIPALITY
LEBOWAKGOMO
LEPELLE-NKUMPI
LICHTENBURG
LICHTENBURG LOCAL MUNICIPALITY
MAFIKENG
MAFIKENG LOCAL MUNICIPALITY
MARBLE HALL
GREATER MARBLE HALL MUNICIPALITY
MEYERTON
MIDVAAL LOCAL MUNICIPALITY
MOGWASE
MANKWE-MADIKWE LOCAL MUNICIPALITY
NELSPRUIT
MBOMBELA
NYLSTROOM
MODIMOLLE
PARYS
NGWATHE LOCAL MUNICIPALITY
PIETERSBURG
POLOKWANE
POMFRET
MOLOPO LOCAL MUNICIPALITY
POSTMASBURG
RE A IPELA MUNICIPALITY
POTCHEFSTROOM
POTCHEFSTROOM LOCAL MUNICIPALITY
POTGIETERSRUS
MOGALAKWENA
PRETORIA
TSHWANE METROPOLITAN MUNICIPALITY
PRIESKA
PRIEMANDAY MUNICIPALITY
169
COMMON NAME
RANDFONTEIN
REIVILO
RUSTENBURG
SABIE
SASOLBURG
SCHUINSDRAAI NATURE RESERVE
STERKFONTEIN
THABAZIMBI
TZANEEN
VENTERSDORP
VEREENIGING
VRYBURG
WARMBATH
WESTONARIA
ZEERUST
MUNICIPALITIES
NEW NAME
RANDFONTEIN LOCAL MUNICIPALITY
GREATER TAUNG LOCAL MUNICIPALITY
RUSTENBURG LOCAL MUNICIPALITY
THABA CHWEU
METSIMAHOLO LOCAL MUNICIPALITY
SCHUINSDRAAI NATURE RESERVE
STERKFONTEIN
THABAZIMBI
GREATER TZANEEN MUNICIPALITY
VENTERSDORP LOCAL MUNICIPALITY
EMFULENI LOCAL MUNICIPALITY
NALEDI LOCAL MUNICIPALITY
BELA BELA
WESTONARIA LOCAL MUNICIPALITY
ZEERUST LOCAL MUNICIPALITY
170
TABLE 9.4
PROVINCE
DISTRICT NAME
MUNICIPAL COMMON
NAME
TOWN NAME
FREE STATE
VREDEFORT
KROONSTAD
MOQHAKA LOCAL
MUNICIPALITY
SPES BONA
GAUTENG
ALBERTON
EAST RAND
GREATER EAST
RAND METRO
KATLEHONG
GAUTENG
ALBERTON
EAST RAND
GREATER EAST
RAND METRO
TOKOZA
GAUTENG
BOKSBURG
EAST RAND
GREATER EAST
RAND METRO
VOSLOORUS
GAUTENG
BRONKHORSTSPRUI
T
EAST RAND
GREATER EAST
RAND METRO
BAPSFONTEIN
GAUTENG
JOHANNESBURG
JOHANNESBURG
CITY OF
JOHANNESBURG
ELDORADO
PARK
GAUTENG
JOHANNESBURG
JOHANNESBURG
CITY OF
JOHANNESBURG
LENASIA
GAUTENG
KEMPTON PARK
EAST RAND
GREATER EAST
RAND METRO
TEMBISA
GAUTENG
OBERHOLZER
CARLETONVILLE
CARLETONVILLE
GAUTENG
OBERHOLZER
CARLETONVILLE
GAUTENG
PRETORIA
PRETORIA
MERAFONG CITY
LOCAL
MUNICIPALITY
MERAFONG CITY
LOCAL
MUNICIPALITY
TSHWANE
METROPOLITAN
MUNICIPALITY
GAUTENG
PRETORIA
PRETORIA
TSHWANE
METROPOLITAN
MUNICIPALITY
CENTURION
GAUTENG
RANDFONTEIN
RANDFONTEIN
BANK
GAUTENG
RANDFONTEIN
RANDFONTEIN
GAUTENG
VEREENIGING
MEYERTON
RANDFONTEIN
LOCAL
MUNICIPALITY
RANDFONTEIN
LOCAL
MUNICIPALITY
MIDVAAL LOCAL
MUNICIPALITY
GAUTENG
VEREENIGING
MEYERTON
MIDVAAL LOCAL
MUNICIPALITY
MEYERTON
GAUTENG
VEREENIGING
MEYERTON
MIDVAAL LOCAL
MUNICIPALITY
RANDVAAL
GAUTENG
WESTONARIA
WESTONARIA
WESTONARIA
LIMPOPO
LIMPOPO
LETABA 2
THABAMOOPO
LEBOWAKGOMO
LEBOWAKGOMO
WESTONARIA
LOCAL
MUNICIPALITY
LEPELLE-NKUMPI
LEPELLE-NKUMPI
LIMPOPO
LIMPOPO
LIMPOPO
LIMPOPO
LIMPOPO
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
THABAZIMBI
GANSKUIL
KOEDOESKOP
MIDDELWIT
SENTRUM
THABAZIMBI
WELVERDIEND
ATTERIDGEVILL
E
MOHLAKENG
DALESIDE
THE DOWNS
CHUNIESPOORT
171
PROVINCE
DISTRICT NAME
TOWN NAME
MPUMALANGA
MPUMALANGA
DELMAS
GROBLERSDAL
DELMAS
GROBLERSDAL
DELMAS
GROBLERSDAL
MPUMALANGA
GROBLERSDAL
MARBLE HALL
MPUMALANGA
LYDENBURG
BURGERSFORT/O
HRIGSTAD/EASTE
RN TUBATSE
DELMAS
GREATER
GROBLERSDAL
MUNICIPALITY
GREATER
MARBLE HALL
MUNICIPALITY
GREATER
TUBATSE
MUNICIPALITY
MPUMALANGA
MPUMALANGA
NELSPRUIT
PELGRIM'S REST
NELSPRUIT
SABIE
MBOMBELA
THABA CHWEU
KAAPSEHOOP
GRASKOP
MPUMALANGA
PELGRIM'S REST
SABIE
THABA CHWEU
HENDRIKSDAL
MPUMALANGA
PELGRIM'S REST
SABIE
THABA CHWEU
MAUCHSBERG
MPUMALANGA
PELGRIM'S REST
DMA LOWVELD
DMA LOWVELD
PILGRIMS REST
MPUMALANGA
PELGRIM'S REST
SABIE
THABA CHWEU
SABIE
MPUMALANGA
PELGRIM'S REST
SABIE
THABA CHWEU
VAALHOEK
NORTH WEST
BRITS
BRITS
LOCAL COUNCIL
ASSEN
NORTH WEST
BRITS
BRITS
LOCAL COUNCIL
ATLANTA
NORTH WEST
HUHUDI
POMFRET
MOLOPO LOCAL
MUNICIPALITY
POMFRET
NORTH WEST
KLERKSDORP
KLERKSDORP
KLERKSDORP
LOCAL
MUNICIPALITY
STILFONTEIN
NORTH WEST
KUDUMANE
KURUMAN
KURUMANMOTHIBISTAD
MUNICIPALITY
MOTHIBISTAT
NORTH WEST
KUDUMANE
KGALAGADI
SEGONYANA
MUNICIPALITY
TSINENG
NORTH WEST
LICHTENBURG
LICHTENBURG
LICHTENBURG
LOCAL
MUNICIPALITY
BAKERVILLE
NORTH WEST
LICHTENBURG
LICHTENBURG
LICHTENBURG
LOCAL
MUNICIPALITY
CARLSONIA
NORTH WEST
LICHTENBURG
LICHTENBURG
LICHTENBURG
LOCAL
MUNICIPALITY
ELANDSPUTTE
NORTH WEST
LICHTENBURG
LICHTENBURG
LICHTENBURG
LOCAL
MUNICIPALITY
ITSOSENG
MARBLE HALL
BRANDDRAAI
172
PROVINCE
DISTRICT NAME
TOWN NAME
NORTH WEST
MADIKWE
LICHTENBURG
LICHTENBURG
LOCAL
MUNICIPALITY
LEAD MINE
NORTH WEST
MADIKWE
MAFIKENG
MAFIKENG LOCAL
MUNICIPALITY
OTTOSHOOP
NORTH WEST
MADIKWE
LICHTENBURG
LICHTENBURG
LOCAL
MUNICIPALITY
WONDERMERE
NORTH WEST
PHOKWANI
REIVILO
MADIPELESA
NORTH WEST
PHOKWANI
REIVILO
NORTH WEST
PHOKWANI
REIVILO
NORTH WEST
RUSTENBURG
LICHTENBURG
GREATER TAUNG
LOCAL
MUNICIPALITY
GREATER TAUNG
LOCAL
MUNICIPALITY
GREATER TAUNG
LOCAL
MUNICIPALITY
LICHTENBURG
LOCAL
MUNICIPALITY
NORTH WEST
RUSTENBURG
KOSTER
LOCAL
MUNICIPALITY
MERINDOL
NORTH WEST
VENTERSDORP
VENTERSDORP
VENTERSDORP
LOCAL
MUNICIPALITY
KLERKSKRAAL
NORTH WEST
VENTERSDORP
VENTERSDORP
SWARTPLAAS
NORTH WEST
VRYBURG
VRYBURG
VENTERSDORP
LOCAL
MUNICIPALITY
(NW401)
NALEDI LOCAL
MUNICIPALITY
NORTH WEST
VRYBURG
GANYESA
KAGISANO LOCAL
MUNICIPALITY
GELUK
NORTH WEST
VRYBURG
REIVILO
LYKSO
NORTH WEST
VRYBURG
VRYBURG
GREATER TAUNG
LOCAL
MUNICIPALITY
NALEDI LOCAL
MUNICIPALITY
NORTH WEST
VRYBURG
VRYBURG
NALEDI LOCAL
MUNICIPALITY
TIERKLOOF
NORTHERN
CAPE
BARKLY WEST
DANIELSKUIL
DAN-LIME
MUNICIPALITY
BLESMANSPOS
NORTHERN
CAPE
BARKLY WEST
DANIELSKUIL
DAN-LIME
MUNICIPALITY
BLIKFONTEIN
NORTHERN
CAPE
HAY
GRIEKWASTAD
SIYANCUMA
MUNICIPALITY
GRIQUATOWN
NORTHERN
CAPE
HERBERT
GRIEKWASTAD
SIYANCUMA
MUNICIPALITY
CAMPBELL
NORTHERN
CAPE
KURUMAN
KURUMAN
KURUMANMOTHIBISTAD
MUNICIPALITY
BEKKER
NORTHERN
CAPE
KURUMAN
KURUMAN
KURUMANMOTHIBISTAD
MUNICIPALITY
KURUMAN
REIVILO
STEEKDORINGS
GROOTPAN
DE BEERS
SALPETERPAN
173
PROVINCE
DISTRICT NAME
TOWN NAME
NORTHERN
CAPE
KURUMAN
POSTMASBURG
RE A IPELA
MUNICIPALITY
LOHATLHA
NORTHERN
CAPE
POSTMASBURG
DANIELSKUIL
DAN-LIME
MUNICIPALITY
ARIESFONTEIN
NORTHERN
CAPE
POSTMASBURG
POSTMASBURG
RE A IPELA
MUNICIPALITY
BEESHOEK
NORTHERN
CAPE
POSTMASBURG
POSTMASBURG
RE A IPELA
MUNICIPALITY
BOKKOPPIE
NORTHERN
CAPE
POSTMASBURG
DANIELSKUIL
DAN-LIME
MUNICIPALITY
DANIELSKUIL
NORTHERN
CAPE
POSTMASBURG
POSTMASBURG
RE A IPELA
MUNICIPALITY
GLOSAM
NORTHERN
CAPE
POSTMASBURG
DANIELSKUIL
DAN-LIME
MUNICIPALITY
LIME ACRES
NORTHERN
CAPE
POSTMASBURG
POSTMASBURG
RE A IPELA
MUNICIPALITY
LOHATLHA
NORTHERN
CAPE
POSTMASBURG
POSTMASBURG
RE A IPELA
MUNICIPALITY
MOOKANENG
NORTHERN
CAPE
POSTMASBURG
POSTMASBURG
RE A IPELA
MUNICIPALITY
PALINGPAN
NORTHERN
CAPE
POSTMASBURG
DANIELSKUIL
DAN-LIME
MUNICIPALITY
PAPKUIL
NORTHERN
CAPE
POSTMASBURG
KATHU
GAMMAGARA
MUNICIPALITY
SISHEN
NORTHERN
CAPE
POSTMASBURG
DANIELSKUIL
DAN-LIME
MUNICIPALITY
SWARTPUTS
NORTH WEST
MADIKWE
ZEERUST
ZEERUST LOCAL
MUNICIPALITY
RAMOTSWA
174
APPENDIX 10
175
APPENDIX 10
SUBMISSION OF DRAWINGS IN ELECTRONIC FORMAT FORMAT FOR INTEGRATION INTO
DEPARTMENTAL GEOGRAPHICAL INFORMATION SYSTEM (GIS).
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
REFERENCE DOCUMENTS
GENERAL
PRIMARY DRAWING LAYER SYSTEM
LAYERS CREATED BY CONSULTANT
ELECTRONIC COMPATIBILITY OF DRAWINGS
GIS - GEOGRAPHIC COORDINATE SYSTEM
GIS - PROJECTED COORDINATE SYSTEM
GRID AND GENERAL RULES FOR DRAWINGS TO BE IMPORTED INTO GIS
FIELD DATA COLLECTED BY GLOBAL POSITIONING SYSTEM (GPS) OR SURVEYS
DRAWING FILE NAMES
DIGITAL SUBMISSION
DRAWING AND TEXT FILE LIST
176
1.
REFERENCE DOCUMENTS
All engineering and related drawings must comply with the standards as set out in PW347,
Civil Engineering Manual of May 2004 or later revisions.
2.
GENERAL
The Department intent to incorporate all as built drawings in a single Geographical
Information System (GIS) and as such requires that drawings shall be submitted in a format
that is compatible with the currently adopted system in ArcGIS suite of programmes.
The ArcGIS suit format of drawings are filename.shp (shape) files and the programme is
compatible to incorporate filename.dxf formats. As such it will thus be a requirement that
all electronic drawings be submitted as follow:
3.
format normally used by consultant (i.e. Caddie, AutoCad, MicroStation, etc. See
PW347 Annexure A2 paragraph 6.5);
dxf.format
pdf (portable document format) format at 300 dpi (dots per inch) minimum (complete
drawing as used for construction).
4.
5.
All circles or polygons must be closed elements. Circles must consist of one single line.
(Test: must be able to delete entire circle as one function.) The hatch function for the
majority of cad programmes can be used to ensure polygons are closed entities. Do not
submit drawings with hatching. Closing of line ends or T-junctions in lines are best extended
by CAD programme snap to functions.
If only the layer with the particular item is switch on in the CAD drawing it must only show that
element and attributes as a line, closed circle, point or closed polygon.
Any element with a common boundary with another element must be drawn as a closed
polygon separate form such other element.
The converting of filename.dxf files to filename.shp files is the separate transfer of each
layer in the CAD environment to a layer in the GIS environment.
Polygons (similar in nature) with a common boundary on the same drawing layer (e.g. stands
in township development, geotechnical zoning, land use demarcations etc.) can be drawn
with a common boundary provided that each polygon is closed and defined by text attributes
with origin of such text inside the polygon.
Polygons that demarcate areas such as geotechnical zones, land use demarcation, pressure
zones etc. must be closed at the extent of the area covered by such zoning. A zone with one
open side is not defined as a zone.
In preparing drawings, only the dimensions wise correct outline (plan view) of a particular
entity must be on the drawing, for example:
shall be defined as a single line. All lines that define a network such as a water or
sewer system shall be on different layers to define various diameters or types but
must be drawn with the snap to end point function to show a continuous line if all
drawing layers are displayed. If a straight pipe of similar diameter enters and exit
from a manhole, valve or valve chamber or similar structure shall the line be ended
and again be continued at the origin (centre point) of such structure. Similarly shall
lines that joins other lines at an angle be joined by means of snap to middle of line
or snap to end point functions. It also applies to lines that converge in a manhole or
chamber. No breaks may exist in lines that defines a network.
Cables The same as for pipes.
Rectangular or square service ducts Must be drawn as a polygon with exact
dimensions as the plan view of the duct. Various shapes and sizes to be drawn in
different layers.
Storm water canal Draw as polygon with dimensions same as plan view of canal.
Various types, shapes and lining material to be drawn as separate layers.
Text to describe line elements shall be with text origin on line and be as follows:
o
o
o
o
o
o
o
o
o
o
o
o
o
o
6.
+X COORD
-X
-Y COORD
-Y
-
7.
Site
The site is located west of 29 longitude and south of the equator, therefore the x and
y coordinates will be negative in the Transeverse Mercator projection.
If the site was located east of 29 longitude the x -coordinates would be positive.
180
8.
9.
10.
Make sure the GPS is set to WGS84 datum before collection of data.
Collected data to be supplied in dbf file format, tab or comma delimited txt file.
Latitude and longitude must be converted to decimal degrees.
Formula for conversion is as follows:
degrees + [((minutes*60) + seconds)/3600]
table columns should contain at least the following fields:
id = unique identifier
x-coord = longitude in decimal degrees
y-coord = latitude in decimal degrees
Data to be supplied in a geographic coordinate system (latitude, longitude) in WGS84
datum or in a Transverse Mercator (gauss) projection in WGS84 datum
If a projection is used all projection parameters must be supplied e.g.:
Projection : Transverse Mercator
Central meridian = 29
Scale factor = 1
False easting = 0
False northing = 0
Datum = Hartebeeshoek 1994 (wgs84)
11.
DIGITAL SUBMISSION
Drawings must be submitted on CD (compact disk) with the following requirements:
Cover label of disk (not case) shall contain the following information:
WCS no.
Project name
Date
Consultants name
Regional office
Town
183
12.
PROJECT
TITLE
DICIPLINE
DRAWING
NUMBER
DRAWING
TITLE
CAD FILE
NAME
REGIONAL
OFFICE
WCS
NO
PROJECT
TITLE
DICIPLINE
DRAWING
NUMBER
DRAWING
TITLE
TEXT FILE
NAME
DESCRIPTION
OF CONTENT
TOWN
DATE ON
DRAWING
COMPILER
NAME
(Please note the table must not include any merged cells. All cells must be filled irrespective
if a column or row has repeatedly the same entry. All txt files that give information regarding
particular drawing must also be included in the drawing list and shall have the same name as
the drawing file.
184
DATE
TABLE A10 .1
TABLE A10 .1: PRIMARY DRAWING LAYER GROUPS
DRAWING ELEMENT REFERENCE TYPE GROUPS
TITLE BLOCKS
SITE IDENTIFICATION
DRAWING ORIENTATION
SURVEY
CADASTRAL
TOPO CADASTRAL
TOWNSHIP PLANNING
TOWN PLANNING FLOOD LINES
CONSTRUCTION NOTES
WATER RETICULATION
WATER SOURCE
WATER TREATMENT
WATER MANAGEMENT
SEWER DISPOSAL
SEWER RETICULATION
SEWER TREATMENT
STORMWATER RETICULATION
ROAD DESIGN
ROAD MANAGEMENT
ROAD MARKING
ROAD PAVING
ROAD SIGNS
RUNWAY
WASTE DISPOSAL
ELECTRICAL RETICULATION
ELECTRICAL SUPPLY
COMMUNICATION
FENCING
EARTH WORKS
MECHANICAL
PNEUMATIC
STEAM
RAIL
BUILDING DEMOLISHED
BUILDING ELEMENTS
BUILDING MOBILE
BUILDING REFERENCE
BUILDINGS
BUILDINGS RECREATIONAL
BUILDINGS TEMPORARY
BUILDINGS UTILITY
SPORT FACILITY
GEOTECHNICAL INVESTIGATIONS
ENVIRONMENTAL IMPACT ASSESSMENT
185
TABLE A10 .2
TABLE A10 .2: CAD DRAWING LAYERS ALREADY DEFINED ON NDPD CAD FILE DATABASE
DRAWING ELEMENT REFERENCE TYPE
LAYER NAME
BUILDING DEMOLISHED
BUILDING DEMOLISHED
CONCRETE BASES
CONCRETE SLAB REMOVED
BUILDING
DEMOLISHED STRUCTURES
OLD FOUNDATIONS
FISH POND
FLAG POLES
LOW WALLS
PLANT BOX
RAMPS
RETAINING WALL
CONTAINERS
MOBILE ABLUTIONS
MOBILE UNIT
MOBILE UNITS
BUILDING NAME
BUILDING NUMBERS
FRN NUMBER
STAND NUMBER
BRIDGE
BUILDING HANGER LEAN TO
BUILDINGS
DAMAGED STRUCTURES
INVESTIGATION
FURNACE
HANGERS
KENNEL
MONUMENTS
WATCH TOWERS
CARPORTS WITH ENCLOSING WALLS
LAPA
LAPA
PAVILION
SWIMMING POOLS
CANOPY
CARPORT
TEMPORARY STRUCTURES
FUEL PUMPS
FUEL TANKS
PYLON
SUBSTATION
SUBSTATION
TELEPHONE BOOTH
TRANSFORMER
WATCHTOWER
ELECTRICAL SERVITUDE
ERFS
BUILDING DEMOLISHED
BUILDING DEMOLISHED
BUILDING ELEMENTS
BUILDING ELEMENTS
BUILDING ELEMENTS
BUILDING ELEMENTS
BUILDING ELEMENTS
BUILDING ELEMENTS
BUILDING MOBILE
BUILDING MOBILE
BUILDING MOBILE
BUILDING MOBILE
BUILDING REFERENCE
BUILDING REFERENCE
BUILDING REFERENCE
BUILDING REFERENCE
BUILDINGS
BUILDINGS
BUILDINGS
BUILDINGS
BUILDINGS
BUILDINGS
BUILDINGS
BUILDINGS
BUILDINGS
BUILDINGS
BUILDINGS RECREATIONAL
BUILDINGS RECREATIONAL
BUILDINGS RECREATIONAL
BUILDINGS RECREATIONAL
BUILDINGS TEMPORARY
BUILDINGS TEMPORARY
BUILDINGS TEMPORARY
BUILDINGS UTILITY
BUILDINGS UTILITY
BUILDINGS UTILITY
BUILDINGS UTILITY
BUILDINGS UTILITY
BUILDINGS UTILITY
BUILDINGS UTILITY
BUILDINGS UTILITY
CADASTRAL
CADASTRAL
LAYER
NO ON
DPW
CAD
FILES
920
911
961
912
933
916
925
960
921
930
957
935
953
934
908
910
909
940
913
905
900
936
904
901
914
926
902
942
932
958
944
903
955
956
931
915
922
907
946
965
917
951
959
721
701
186
LAYER NAME
CADASTRAL
CADASTRAL
CADASTRAL
CADASTRAL
CADASTRAL
CADASTRAL
CADASTRAL
CADASTRAL
CADASTRAL
COMMUNICATION
FARMS
MAGISTERIAL BOUNDARY
PROVINCIAL BOUNDARY
RIGHT OF WAY SERVITUDE
ROADS SERVITUDE
SEWER SERVITUDE
SMALL HOLDINGS
TOWNS
WATER SERVITUDE
100MM PITCH FIBRE COM CABLE
SLEEVE
110MM PVC SLEEVE PIPE
150MM PVC SLEEVE PIPE
50MM COM CABLES
75MM COM SLEEVE
AERIAL LEVELS
AERIAL MAST
AERIAL SUPPORT POLES
AERIALS
CLEARED AREAS AROUND MASTS
COM CABLE MANHOLES
COMMUNICATION LEVELS
COMMUNICATION OVERHEAD
COMMUNICATION UNDERGROUND
FIBRE H BS POINT
FOUNDATIONS MAST
IDF OR DF POINT
SERVICE MARKER COMMUNICATION
SERVICE MARKER DATA CABLES
SERVICE MARKER TELCOM
TELKOM MANHOLE
TELKOM OVERHEAD
TELKOM POLES
TELKOM UNDERGROUND
GENERAL CONSTRUCTION NOTES
SPECIFIC CONSTRUCTION NOTES
BOUNDARY OF LOCALITY MAP
BOUNDARY OF PLANNED WORKS
COORDINATE SYSTEM DEFINITION
GRIDS X AND Y AS WELL AS GRID
TEXT
KEY PLANS
NORTH INDICATOR
PRIMARY SITE BOUNDARY
INDICATION
SCALE REFERENCE AND TEXT
TRIG BEACON REFERENCING
BULK EARTH WORKS
AREAS FOR NORMAL DEVELOPMENT
BIOSPHERE ZONES
BOUNDARY OF INVESTIGATION
AREAS
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
COMMUNICATION
CONSTRUCTION NOTES
CONSTRUCTION NOTES
DRAWING ORIENTATION
DRAWING ORIENTATION
DRAWING ORIENTATION
DRAWING ORIENTATION
DRAWING ORIENTATION
DRAWING ORIENTATION
DRAWING ORIENTATION
DRAWING ORIENTATION
DRAWING ORIENTATION
EARTH WORKS
ENVIRONMENTAL IMPACT ASSESSMENT
ENVIRONMENTAL IMPACT ASSESSMENT
ENVIRONMENTAL IMPACT ASSESSMENT
LAYER
NO ON
DPW
CAD
FILES
702
705
706
725
724
723
703
704
722
612
613
614
617
611
604
600
601
605
603
620
616
610
615
618
602
619
621
622
623
609
606
608
607
7
8
4
5
69
67
6
65
3
66
68
80
743
747
741
187
LAYER NAME
LAYER
NO ON
DPW
CAD
FILES
745
740
744
748
746
742
655
656
651
652
650
653
654
661
659
657
658
660
803
802
820
821
805
800
801
804
521
523
501
524
503
509
513
508
522
502
505
506
520
519
510
512
504
514
188
LAYER NAME
GEOTECHNICAL INVESTIGATIONS
GEOTECHNICAL INVESTIGATIONS
GEOTECHNICAL INVESTIGATIONS
GEOTECHNICAL INVESTIGATIONS
MECHANICAL
PNEUMATIC
PNEUMATIC
PNEUMATIC
RAIL
ROAD DESIGN
SINKHOLES
TEST PITS
UNDER MINING
WATER COMPARTMENTS
CRANES
AIR TANKS
COMPRESSOR
PNEUMATIC PIPES
PROPOSED RAILWAY LINE
ROAD CENTER LINE, CHAINAGE AND
LEVEL
ROAD GRADIENTS
ROAD SIGHT DISTANCE
ROAD VERTICAL CURVES
TRAFFIC CONFLICT NODES
TRAFFIC FLOW DIRECTION
INDICATORS
TRAFFIC FLOW VOLUMES
BOLLARDS
ROAD MARKING BLUE (100 MM WIDE)
ROAD MARKING RED (100 MM WIDE)
ROAD MARKING WHITE (100 MM
WIDE)
ROAD MARKING YELLOW (100 MM
WIDE)
COVERED WALKWAY
ENTRANCE ROADS
FOOT PATHS
GRAVEL ROADS
KERBS
MAIN ROAD
PARKING BITUMINOUS
PARKING CONCRETE
PARKING EARTH
PARKING GRASS
PARKING GRAVEL
PARKING INTERLOCKING PAVING
PAVING
PEDESTRIAN CROSSING
PEDESTRIAN WALKWAY BITUMINOUS
PEDESTRIAN WALKWAY CONCRETE
PEDESTRIAN WALKWAY EARTH
PEDESTRIAN WALKWAY GRAVEL
PEDESTRIAN WALKWAY PAVING CLAY
BRICK
PEDESTRIAN WALKWAY PAVING
CONCRETE BRICK
PROPOSED NEW ROADS
RELATED DRAWINGS
ROAD PAVING KERB LEVELS
TRAIN TRACKS
BOARDS
ROAD DESIGN
ROAD DESIGN
ROAD DESIGN
ROAD MANAGEMENT
ROAD MANAGEMENT
ROAD MANAGEMENT
ROAD MARKING
ROAD MARKING
ROAD MARKING
ROAD MARKING
ROAD MARKING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD PAVING
ROAD SIGNS
LAYER
NO ON
DPW
CAD
FILES
500
516
517
518
860
882
881
880
412
419
420
422
421
441
439
440
445
437
436
435
438
416
401
407
402
403
400
424
425
428
426
427
423
404
418
430
429
432
431
433
434
413
417
405
406
443
189
LAYER NAME
ROAD SIGNS
ROAD SIGNS
ROAD SIGNS
ROAD SIGNS
ROAD SIGNS
ROAD SIGNS
ROAD SIGNS
ROAD SIGNS
RUNWAY
RUNWAY
RUNWAY
RUNWAY
RUNWAY
RUNWAY
RUNWAY
RUNWAYS
SEWER DISPOSAL
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
FILE REFERENCE
NOTES
ROAD NAMES
ROAD REFERENCE MARKER
ROAD SIGN BOARDS
ROBOTS
SIGNS
STREET POLES
ARRESTOR NET
HARD STANDS
RUNWAY LIGHTS
TAXI WAY
TURN CIRCLES
WIND SOCK
RUNWAYS
HELIPAD
MUNICIPAL SEWER MAIN
110MM CLAY PIPE
110MM HDPE PIPE
110MM UNKNOWN PIPE TYPE
110MM UPVC PIPE
150MM AC PIPE
160MM CLAY PIPE
160MM HDPE PIPE
160MM UNKNOWN PIPE TYPE
160MM UPVC PIPE
200MM AC PIPE
200MM CLAY PIPE
200MM HDPE SEWER
200MM UNKNOWN PIPE TYPE
250MM CLAY PIPE
250MM UNKNOWN PIPE TYPE
300MM AC PIPE
300MM CLAY PIPE
300MM HDPE PIPE
300MM UNKNOWN PIPE TYPE
300MM UPVC PIPE
375MM CLAY PIPE
75MM AC PIPE
75MM PVC PIPE
90MM UNKNOWN PIPE TYPE
CE AND IE
CONCRETE SEWER MANHOLES
CONSERVANCY TANK
CONTROL CHAMBER
END CAP
EXTERNAL SEWER LAYOUT
GENERAL TEXT
GREASE TRAP
GULLEY
HDPE MANHOLES
LAYER
NO ON
DPW
CAD
FILES
409
410
408
444
414
411
442
415
456
453
454
451
452
455
450
457
200
229
217
248
218
214
230
213
245
212
210
231
250
247
244
239
235
234
232
246
233
243
220
241
249
227
203
208
222
228
201
225
252
204
238
190
LAYER NAME
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER RETICULATION
SEWER TREATMENT
SEWER TREATMENT
SEWER TREATMENT
SEWER TREATMENT
SEWER TREATMENT
SEWER TREATMENT
SEWER TREATMENT
SEWER TREATMENT
SEWER TREATMENT
SEWER TREATMENT
SITE IDENTIFICATION
SITE IDENTIFICATION
SITE IDENTIFICATION
SITE IDENTIFICATION
SPORT FACILITY
SPORT FACILITY
SPORT FACILITY
SPORT FACILITY
STEAM
STEAM
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
LAYER
NO ON
DPW
CAD
FILES
202
207
236
237
226
257
242
221
251
206
254
224
205
223
260
259
264
263
261
266
262
258
265
267
9
10
7
8
941
924
906
963
840
841
365
379
331
385
377
325
361
357
312
326
336
370
366
327
348
386
191
LAYER NAME
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
150MM AC PIPE
160MM AC SW PIPE
160MM DIA UNKNOWN TYPE
160MM UPVC PIPE
1700MM WIDE CON CHANNEL
1800MM CON PIPE
2000MM DIA UNKNOWN TYPE
2000MM ROUND CHANNEL
2000MM WIDE CON CHANNEL
200MM AC PIPE
200MM DIA AC PIPE
200MM DIA CLAY PIPE
200MM DIA UNKNOWN TYPE
200MM UPVC PIPE
250MM AC PIPE
250MM DIA UNKNOWN TYPE
3000MM WIDE CON CHANNEL
300MM AC PIPE
300MM CONCRETE PIPE
300MM DIA UNKNOWN TYPE
300MM HDPE PIPE
300MM WIDE CON CHANNEL
350MM AC PIPE
350MM DIA UNKNOWN TYPE
375MM CONCRETE PIPE
400MM AC PIPE
400MM DIA UNKNOWN TYPE
450MM AC SW PIPE
450MM CONCRETE PIPE
450MM HDPE PIPE
4900MM WIDE CON CHANNEL
500MM AC PIPE
500MM DIA UNKNOWN TYPE
500MM WIDE CON CHANNEL
525MM CONCRETE PIPE
550MM HDPE PIPE
600MM AC PIPE
600MM CONCRETE PIPE
600MM DIA PVC PIPE
600MM DIA UNKNOWN TYPE
675MM CONCRETE PIPE
750MM CONCRETE PIPE
750MM WIDE CON CHANNEL
75MM DIA AC PIPE
800MM AC PIPE
800MM DIA UNKNOWN TYPE
825MM CONCRETE PIPE
900MM CONCRETE PIPE
CAMERA INSPECTION
CATCH PITS
DAMAGED SECTIONS
LAYER
NO ON
DPW
CAD
FILES
313
367
380
355
335
349
369
347
334
314
383
387
374
356
315
378
333
351
316
372
328
338
350
381
317
358
371
364
318
329
332
352
375
384
319
330
353
320
382
376
321
322
337
389
354
373
323
324
341
302
346
192
LAYER NAME
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
EARTH CHANNELS
EARTH DRAIN
GENERAL TEXT
GRID INLET
HEAD WALLS
KERB INLETS
OPEN CHANNELS
OUTLETS WALLS , FENCES
PIPES
PIT
PONDING WATER
RELATED DRAWINGS STORMWATER
REMOVED SYSTEMS
ROCK FILL
SERVICE DUCTS, SHAFTS AND
SLEEVES
SERVICE MARKER STORMWATER
STILLING BASINS
STORMWATER LAYOUT
STORMWATER LEVELS
STORMWATER MANHOLE
STORMWATER SUMPS
SURFACE BREAKING UP
UNCONFIRMED SW LAYOUT
UNCONFIRMED SW MANHOLE
CONTOURS
NEWLY PLACED SURVEY STATIONS
FOR PROJECT
SPOT LEVELS
SURVEY STATIONS NOT ON SITE
EXISTING
SURVEY STATIONS ON SITE EXISTING
NOTES
TITLE BLOCK
DRAINAGE PATHS MAJOR
DRAINAGE PATHS MINOR
RIVERS
STREAMS
1:10 YEAR FLOOD LINE
1:100 YEAR FLOOD LINE
1:2 YEAR FLOOD LINE
1:20 YEAR FLOOD LINE
1:5 YEAR FLOOD LINE
1:50 YEAR FLOOD LINE
FLOOD LINES
ANTICIPATED FUTURE LAND USE
AREAS NOT TO BE DEVELOPED
FUTURE DEVELOPMENT AREAS
LAND USE PLANNING
OFFICE ZONES
RECREATIONAL ZONES
RESIDENTIAL ZONES
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
STORMWATER RETICULATION
SURVEY
SURVEY
SURVEY
SURVEY
SURVEY
TITLE BLOCKS
TITLE BLOCKS
TOPO CADASTRAL
TOPO CADASTRAL
TOPO CADASTRAL
TOPO CADASTRAL
TOWN PLANNING FLOOD LINES
TOWN PLANNING FLOOD LINES
TOWN PLANNING FLOOD LINES
TOWN PLANNING FLOOD LINES
TOWN PLANNING FLOOD LINES
TOWN PLANNING FLOOD LINES
TOWN PLANNING FLOOD LINES
TOWNSHIP PLANNING
TOWNSHIP PLANNING
TOWNSHIP PLANNING
TOWNSHIP PLANNING
TOWNSHIP PLANNING
TOWNSHIP PLANNING
TOWNSHIP PLANNING
LAYER
NO ON
DPW
CAD
FILES
306
307
345
309
303
339
304
342
311
308
344
388
359
368
340
391
360
300
305
301
310
343
362
363
71
74
70
73
72
2
1
789
790
787
788
783
786
781
784
782
785
780
767
765
766
760
763
762
761
193
LAYER NAME
TOWNSHIP PLANNING
WASTE DISPOSAL
WASTE DISPOSAL
WASTE DISPOSAL
WATER MANAGEMENT
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
LAYER
NO ON
DPW
CAD
FILES
764
281
282
280
187
114
161
124
151
131
115
145
125
117
152
132
116
153
147
126
176
118
168
166
133
127
134
156
177
119
154
155
167
135
157
180
120
142
169
178
164
121
143
149
165
159
122
113
144
146
194
LAYER NAME
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER RETICULATION
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
LAYER
NO ON
DPW
CAD
FILES
162
160
123
179
129
148
136
103
90
91
141
183
181
110
139
102
111
101
158
138
130
140
182
137
107
109
106
150
163
128
105
112
108
104
185
186
184
199
196
195
197
198
170
172
100
171
189
188
193
192
195
LAYER NAME
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER SOURCE
WATER TREATMENT
WATER TREATMENT
WATER TREATMENT
RESERVOIR
WATER BOARD DAMS
WATER BOARD PIPES
WATER POINTS AT RIVERS
CLARIFIERS
DOSING UNITS
PUMP STATIONS OTHER THAN
BUILDING
SAND FILTERS
SETTLEMENT UNITS
WATER PURIFICATION PLANT
BOUNDARY
WATER TREATMENT
WATER TREATMENT
WATER TREATMENT
LAYER
NO ON
DPW
CAD
FILES
175
191
190
194
92
93
94
95
174
173
196
APPENDIX 11
197
APPENDIX 11
PRELIMINARY BILLS OF QUANTITY
(Note all SABS referencing shall also refer to the latest SANS specification)
198