Soil Analysis For Draft Final Geotechnical Report Zone A (Fill Area) PG 9

The document summarizes soil analyses from draft final geotechnical reports for zones A, B, C, and D. For each area, it lists the zone, recommendations from the report to remove 2-3 meters of soft material and mix with good soil to minimize consolidation settlement, and the current status of work in the area. Work status updates include that removal of soft material is in progress, completed, or that no activities have started yet in some areas. It also notes future planned uses for some areas.

Uploaded by

KesavanMohanadas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views6 pages

Soil Analysis For Draft Final Geotechnical Report Zone A (Fill Area) PG 9

The document summarizes soil analyses from draft final geotechnical reports for zones A, B, C, and D. For each area, it lists the zone, recommendations from the report to remove 2-3 meters of soft material and mix with good soil to minimize consolidation settlement, and the current status of work in the area. Work status updates include that removal of soft material is in progress, completed, or that no activities have started yet in some areas. It also notes future planned uses for some areas.

Uploaded by

KesavanMohanadas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Soil Analysis for Draft Final Geotechnical Report

Zone A (Fill Area) pg 9


ABH No
2
2A

Zone Draft Final Geotecnical Report Analysis


A6 To remove 2-3 m @ mix with good soil to minimize
consolidation settlement

Status of the Area


In progress of removing soft material, 3 meter as
per discussion with SIC

A6
Contain silty sand / loose sand which easily consolidated In progress of filling platform

A7

A5

Contain silty sand / loose sand which easily consolidated In progress of filling platform
To remove 2-3 m @ mix with good soil to minimize
Done and handed over to UEM on March 2011
consolidation settlement

A1

Done and handed over to UEM on March 2011


Contain silty sand / loose sand which easily consolidated

A1

Done and handed over to UEM on March 2011


Contain silty sand / loose sand which easily consolidated

Zone B (Fill Area) pg 11


ABH No

Zone

Draft Final Geotecnical Report Analysis

Status of the Area

BH12

B2-5 To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

Currently filling 3rd Layer as per 20.5.2011

B1-8 To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

Completed and officially handover.

12

B 2-1 To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

Completed, Removal of Soft Material done on


November.

13

B2-2

In progress of filling 26th layer as per 21.5.2011

29
32

Contain silty sand / loose sand which easily consolidated


To remove 2-3 m @ mix with good soil to minimize
Filling up to +10 layers at previously ponding area
consolidation settlement
B1-2 To remove 2-3 m @ mix with good soil to minimize
consolidation settlement

Completed and officially handover.

13

B 2-2 To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

In progress of filling 26th layer as per 21.5.2011

Zone C (Fill Area) pg 13


ABH No
BH 5
16

Zone

Draft Final Geotecnical Report Analysis


To remove 2-3 m @ mix with good soil to minimize
consolidation settlement

Status of the Area


Completed workers camp area.

C1

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

Completed and handing over to UEMB

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

Completed (toe of slope for batching plant area)

17
19

C5

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

Site clearing done at the area

22

C7

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

No activities yet for the area

23

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

No activities yet for the area

24

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

No activities yet for the area

38

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

Completed and removed 3 meters at the area

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

In progress

39

C4

Zone C (Fill Area) pg 13


ABH No
BH7

Zone
D11

Draft Final Geotecnical Report Analysis


To remove 2-3 m @ mix with good soil to minimize
consolidation settlement

Status of the Area


In progress, removing 3 meters at the area

27

D7

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

90% completed

33

D5

To remove 2-3 m @ mix with good soil to minimize


consolidation settlement

Site clearing done for the area

Remarks

Future Area Transport Terminal

Remarks

Removed 2 meters by UEMB

Access Road

Remarks
Future Area - Police Station
Minor filling 2 meter
Future Area - Town Center
Flushing method until edge of
access, removed the soft material

Reserve site for future STP


Retention Pond
Access Road B1-7
Flushing method until edge of
access, removed the soft material

Remarks

Flushing method until edge of


access, removed the soft material