S16.SI.164 Stamp
S16.SI.164 Stamp
S16.SI.164 Stamp
Ref. No.
Date
: S16.SI.164
: June 13, 2016
Project
Owner
Location
Consultant
:
:
:
:
Construction of Villa
Rashid Mohammed Rashid Mallah Almansoori
Plot No. 129, Sector: Al Nahda Al Jadeedah, Al Nahda, Abu Dhabi
M/s Modern Home Engineering Consultants
Sands Laboratories for Soil Testing is pleased to present the attached geotechnical investigation
report for the above project site. This investigation was carried out according to your request dated
on June 5, 2016.
This report includes the recommendations related to the geotechnical aspects of project design and
construction. Conclusions and recommendations presented in this report are based on the results of
field investigation, laboratory testing and engineering analysis.
We would like to thank you for your confidence. We look forward for further cooperation with you
on future projects. For additional information or clarification, please dont hesitate to contact our
office.
Sincerely yours,
Engr.Mohannad Al Khatib
1
S16.SI.164
TABLE OF CONTENTS
Page No.
Letter of Transmittal . 1
1. Introduction .
3. Project Description ..
5. Laboratory Testing ..
7. General Discussion ..
10
10
12
12
2
S16.SI.164
LIST OF FIGURES
APPENDIX A
I. Borehole Logs
II. Figure No. A1: General Site Plan & Location of the Boreholes
III. Figure No. A2: General Sub-surface Profile of the Site AA
LIST OF TABLES
Table No. 1: Sub-surface Description
Table No. 2: Results and Recommended Chemical Class
3
S16.SI.164
1. INTRODUCTION
This report presents the results of two boreholes drilled at 20.0m. The drilling was carried out
according to the request of Rashid Mohammed Rashid Mallah Almansoori.
The geotechnical investigation for the proposed project is to be located at Plot No. 129,
Sector: Al Nahda Al Jadeedah, Al Nahda, Abu Dhabi.
It is therefore necessary to conduct periodically a site inspection during actual site work to
verify the subsurface conditions to ensure a successful construction.
The classifications of the ground water conditions in the site are based on observations made
at the time the site work was carried out. However, it is stressed that the ground water levels are
subject to variations caused by seasonal effects or changes in local drainage and/or pumping
conditions.
The recommendations presented herein should not be extrapolated to other reports. Gathering
of information and its appraisals should continue during any construction works.
4
S16.SI.164
Making site inspection visits to collect information about the site, its surface topography and
geological features.
Drilling of two boreholes to a depth 20.0m each below the existing ground surface level.
Ground water measurement for each borehole and collecting samples for chemical test.
Laboratory testing of the representative samples obtained during the field investigation to
evaluate relevant engineering parameters of the sites sub-surface soil.
Engineering analysis of the laboratory test results on which to base the recommendations for
the design and construction of the project.
The site is located at Plot No. 129, Sector: Al Nahda Al Jadeedah, Al Nahda, Abu Dhabi. A
general site plan is presented in Figure A1.
Geologically, the UAE occupies a corner of the Arabian Platform, a body of continental rock
that has remained relatively stable since the Cambrian Period more than 500 million years ago. From
a geological standpoint, the Arabian Platform encompasses not only present day Arabia but also the
shallow Arabian Gulf and the rocks of the coastal Zagros Mountains of Iran. For most of its history,
the Arabian Platform has been part of the larger Afro-Arabian continent, and the two have behaved
as a unit in response to plate tectonic movements.
Over time, sediments accumulated on the coast and continental shelf that was to become the
UAE. Limited pre-Permian exposures in the UAE reveal fine-grained, shallow water terrigenous
sediments (silts and shale). These were probably relatively thin overall and may have been largely
removed by intermittent emergence and erosion. Later, in the tropical Mesozoic seas, thick
sequences of carbonate rocks, lime stones (CaCO3) and dolomites (CaMg(CO3)2), were deposited.
The late Permian and Mesozoic seas of the UAE were part of an ocean that opened north of Arabia
during that time, separating the Afro-Arabian continent from the Eurasian continent. This palaeoocean is known to geologists as Tethys and at one time it extended westward to the present-day
Mediterranean countries and eastward to the Himalayas.
The detail of the geologic history of the Arabian Platform in this area comes from drilling
and seismic information.
Most of the surface of the present day UAE is a sand desert, stretching from the Arabian Gulf
coast south to the unbroken and uninhabited sands of the Empty Quarter, and east to the gravel
plains bordering the Hajar Mountains. The desert is a geologically recent feature, the result of
prolonged subaerial erosion and deposition in an arid environment. The sands overlie the thick, oilrich sedimentary strata of the Arabian Platform which constitutes the bedrock of most of the UAE,
but the oil producing rocks are nowhere exposed at the surface.
5
S16.SI.164
Sand dune formation is controlled by a combination of wind strength and direction, and
sediment supply. Sabkha is the Arabic term for low-lying saline flats subject to periodic inundation.
Three types are recognized, based on their environment of formation. All are found in the UAE.
Coastal sabkha, as the name implies, forms at or near the marine shoreline. Fluvio-lacustrine (ie
river-lake) sabkha is formed in association with riverine drainage patterns in arid areas. Inland or
interdune sabkha is found in low-lying basins within the sand desert.
All sabkhas share certain characteristics. Although they are restricted to hot, arid regions, the
sabkha surface is always very close to the local water table, usually within about a metre.
Groundwater is drawn towards the surface by capillary action and evaporates in the upper subsurface
in response to the high temperatures. There it deposits dissolved salts, including calcium carbonate,
gypsum (CaSO4-2H2O), anhydrite (CaSO4) and sodium chloride or halite (NaCl), which precipitate
in that order. These salts create a hard, impermeable crust in a zone about half a metre below the
surface. This crust, along with high salinity, discourages all plant growth. The crust also impedes the
drainage of surface water, so that after rains the sabkhas flood. The surface water then evaporates
over time, often leaving behind a dazzling white crust of salt.
3. PROJECT DESCRIPTION
The proposed project involves the construction of villa. It is consist of ground floor, first
floor & roof.
4. FIELD WORK
4.1 DRILLING
As per clients instructions, two boreholes were drilled to a depth of 20.0m each below the
existing ground level at the site where the proposed project is to be constructed. The drilling was
carried out during the period of June 6 & 7, 2016. Both boreholes were located in the field by the
clients representative. The location of the boreholes is presented in Figure A1.
The drilling was executed in the field by hydraulic drilling rig using rotary drilling method
with bentonite mud circulation.
7
S16.SI.164
Material Description
0.70
made ground
0.70
11.0
11.0
20.0
Detailed descriptions of the sub-surface conditions encountered during our field investigation are
generalized in the sub-surface profile presented in Fig. A2. The location of the profile is shown in
Fig. A1. The profile was constructed by direct interpolation between the materials revealed from the
boreholes, therefore, it should not be considered as actual field condition.
8
S16.SI.164
Chlorides which are normally present in the subsoil and groundwater penetrate porous
concrete and cause corrosion of steel reinforcement. The groundwater and subsoil are likely to be
contaminated with aggressive salts. Such contamination is a major factor in the design of concrete
mixes and it needs special protection.
Sulphate may also be present in the concrete materials, gypsum which is added to the cement
during manufacture to produce the required rate of setting and in the environment to which the
concrete is exposed often in combination with the chlorides. Sulphate attack to concrete is caused by
the presence of the high sulphate content either by the ingress from the sulphate of the surrounding
environment such as foundation soils or by the presence of sulphate in the concrete ingredients such
as sand or aggregates or both. The main effect of both the sulphate and chloride attack on concrete
leads to the internal expansion and disruption of the concrete. However, their effect can be reduced
by the use of sulphate resisting cements and cement containing blast-furnace slag. Where sulphates
and chlorides occur together, sulphates resisting cement provide less protection to steel against
attack in the presence of the chlorides compared with the Ordinary Portland Cement (OPC).
PH value attack to concrete occurs when acid attack on concrete is coming from the soil
samples and ground water and chemical attack to concrete may come from the use of salts in the
construction materials or from chemicals in the ground soil or water below the ground concrete. Just
like sulphate and chloride attack on concrete, their effect results in a considerable internal expansion
which may lead to crack and disintegration of the concrete. It is necessary to check and control the
amount of salts incorporated in all the materials used in making concrete which is a primary defense
against chemical attack.
The quality of water to be added to the cement and aggregates during mixing shall be just
sufficient and free from contamination to produce a workable mix to enable it to be well compacted
and worked into corners from and around reinforcement.
Determination of the concentrations of sulphate expressed as (SO3), chlorides as (CL) and (PH)
value for the soil samples tested from boreholes are presented in table 1 in Appendix B.
Based on the results of sulphate content determination test for the soil samples, the sites are
divided into five categories of increasing severity. The site of the proposed project falls within Class
2 by both requirement of BS 5328 and BRE digest 363.
9
S16.SI.164
7. GENERAL DISCUSSION
The recommendation for the allowable bearing capacity (qa) to be used for design is based on
the minimum of either:
Limiting the settlement to a tolerable amount
The ultimate bearing capacity, which considers soil strength against shear failure.
The allowable bearing capacity based on shear control (qa) is obtained by dividing the
ultimate bearing capacity (qult) based on soil strength by a Safety Factor (SF) that is deemed
adequate to avoid a base sheer failure. To obtain:
The safety factor is based on the type of soil (cohesive or cohesionless), reliability of the soil
parameters and structural information.
In geotechnical engineering, bearing capacity is the capacity of soil to support the loads
applied to the ground. The bearing capacity of soil is the maximum average contact pressure
between the foundation and the soil which should not produce shear failure in the soil. Ultimate
bearing capacity is the theoretical maximum pressure which can be supported without failure while
allowable bearing capacity is the ultimate bearing capacity divided by a factor of safety. Sometimes,
on soft soil sites, large settlements may occur under loaded foundations without actual shear failure
occurring. In such cases, the allowable bearing capacity is based on the maximum allowable
settlement.
7.1 BEARING CAPACITY FROM STANDARD PENETRATION TEST
The SPT is widely used to obtain the bearing capacity of soils. Meyerhof published equations
for computing the allowable bearing capacity for a 25mm settlement. These could be used to
produce curves similar to those of Terzaghi and Peck and thus were also very conservative.
Considering the accumulation of field observations and the stated opinions of the authors and others,
Myerhofs equations were adjusted to an approximate 50 percent increase in the allowable bearing
capacity to obtain the following:
=
= 20
1.2 .(E1)
>
= 12.5
1.2 .(E2)
10
S16.SI.164
= 1 + 0.33 1.33
F factors:
F1
F2
F3
F4
=
=
=
=
.. (E3)
0.05
0.08
0.3
1.2
In these equations N is the statistical average value for the footing influence zone of about
0.5B above footing base to at least 2B below. Footing width is a significant parameter. Obviously if
the depth of influence is on the order of 2B, a larger footing width will affect the soil to a greater
depth and strains integrated over a greater depth will produce a larger settlement. This is taken into
account somewhat for mats which were considered by Meyerhof and adjusted for 50 percent
increase to obtain:
=
.........................................................................................................(E4)
= 12.5
...........
(E5)
In these equations the allowable soil pressure is for an assumed 25mm settlement. In general
the allowable pressure for any settlement Hj is
=
.......(E6)
Where Ho = 25 mm.
Hj is the actual settlement that can be tolerated, in millimeters.
However these recommendations are considered to produce too severe a reduction in
allowable pressure and a correction should be made only if the water table is within a depth B
(below the foundation). Peck, Hanson and Thornburn proposed that linear interpolation should be
used between a reduction of 50 % of the water table which is at ground level and zero reduction if
the water table is at depth B (below the foundation). Thus, the provisional value of allowable bearing
pressure should be multiplied by a factor Cw given by:
= 0.5 + 0.5
Where:
.(E7)
Cw
Dw
D
B
=
=
=
=
Correction of water
Water depth
Depth of footing
Width of footing
In using the correlations, the average N value is determined for each borehole on the site in
question and the lowest average is then used in design. For a series of footings, the bearing pressure
is obtained for the largest footing.
11
S16.SI.164
shall be selected, well-graded sand and gravel containing a small percentage of fines
shall be free from organic matter or other deleterious substances
shall be free from lumps over 15 cm in greatest dimension
shall not be more than 15 percent larger than 7 cm
shall be spread in lifts not exceeding 25cm in non-compacted thickness
The moisture conditioned to its optimum moisture content and compacted to a dry density
shall not be less than 95 percent of the maximum dry density as obtained by modified proctor
test (ASTM D-1557)
The plasticity index for the backfill material shall not exceed 10 percent.
8.4 DEWATERING
Dewatering is the removal of the ground water or surface water when it is necessary to lower
the ground water table from a construction site to allow construction to be done in the dry until all
underground work is completed. Water is usually removed by pre-drainage of the site or using well
points and power driven pumps. Specialized contractors must be consulted.
13
S16.SI.164
Table No.2
Results and Recommended Chemical Class
BS 1377: Part 3: 1990,
Method 5.5
Maximum
Sulphate (SO3)
content in soil
(%)
Maximum Sulphate
((SO3) content in
groundwater
(g/L)
Maximum Chloride
(CL) content in soil
(%)
Maximum Chloride
(CL) content in
groundwater (g/L)
PH value in
soil
(%)
PH value in
groundwater
(g/L)
0.89
0.10
8.2
CHEMICAL CLASS 2
Type of Cement
Maximum Free
Water/Cement Ratio
(Note 1)
Maximum Free
Water/Cement Ratio
(Note 1)
A-G
530
0.50
H
280
0.55
I-L
300
0.55
Note 1. Cement content includes pfa and slag.
Note 2. Cement contents relate to 20mm nominal maximum size aggregate. In order to maintain the
cement content of the mortar fraction at similar values, the minimum cement contents given
should be increased by 40 kg/m3 for 10mm nominal maximum size aggregate and may be
decreased by 30 kg/m3 for 4 mm nominal maximum size aggregate as described in Table 8 of
BS 5328: Part 1.
Trial mix shall be prepared for concrete in accordance with BS 5328 showing that the
proposed mix proportions and manufacture will produce a concrete of strength and quality required
having adequate workability for compaction by the method to be used in placing.
14
S16.SI.164
BOREHOLE LOG
Ref. S16.SI.164
Client
Project
Location
Drilling Date
Drilling Method
D
SPT
(m) No.
Borehole No. 1
ST Leg
end
Description
(Blows)
TCR
SCR
(%)
(%)
RQD) U.C.S.
(%)
1
8,10,15
R
L
(m)
x SM : (Silty SAND).
Medium dense to dense, light brown,
fine grained silty SAND.
*made ground on the top 0.70m
S1
MPa
-1
25
-2
S2 10,10,16 26
-3
S3
4,6,7
13
S4
4,5,7
12
-4
5
S5
4,6,8
14
S6
5,7,9
16
S7
6,7,10
17
-5
11.0
-6
-7
x
8
-8
S8
8,11,14
25
-9
S9 12,18,24 42
10
-10
ST:
Sample Type
N:
RL:
Reduced Level
penetration
LT:
Layer Thickness
Sample No.
S:
REMARKS:
D:
Depth
BOREHOLE LOG
Ref. S16.SI.164
Client
Project:
Location
Drilling date
Drilling Method
D
SPT
(m) No.
Borehole No. 1
ST Leg
end
Description
(Blows)
TCR
SCR
(%)
(%)
RQD) U.C.S.
(%)
MPa
R
L
(m)
x SM : (Silty SAND).
x
11
S10 50/17cm
50
11.0
-11
.....
12
-12
0
.....
.....
13
S11 50/14cm
-13
50
.....
.....
14
-14
60
.....
.....
15
S12 50/12cm
-15
50
.....
9.0
.....
16
-16
.....
.....
17
-17
.....
S13 50/10cm
50
.....
18
-18
.....
.....
19
70
30
10
-19
.....
.....
20
-20
ST:
Sample Type
N:
RL:
Reduced Level
penetration
LT:
Layer Thickness
Sample No.
S:
REMARKS:
D:
Depth
BOREHOLE LOG
Ref. S16.SI.164
Client
Project:
Location
Drilling date
Drilling Method
D
SPT
(m) No.
Borehole No. 2
ST Leg
end
Description
(Blows)
TCR
SCR
(%)
(%)
RQD) U.C.S.
(%)
S1 20,13,11 24
2
4,5,6
R
L
(m)
x SM : (Silty SAND).
Medium dense to dense, light brown, fine
grained silty SAND.
*made ground on the top 0.70m
S2
MPa
-1
-2
11
-3
x
S3
5,5,7
12
-4
S4
6,7,8
15
-5
11.5
S5
4,9,9
18
-6
x
S6
7,10,11
21
-7
S7
8,12,15
27
-8
S8 10,15,18 33
9
-9
x
10
-10
ST:
Sample Type
N:
RL:
Reduced Level
penetration
LT:
Layer Thickness
Sample No.
S:
REMARKS:
D:
Depth
BOREHOLE LOG
Ref. S16.SI.164
Client
Project:
Location
Drilling date
Drilling Method
D
SPT
(m) No.
Borehole No. 2
ST Leg
end
Description
(Blows)
TCR
SCR
(%)
(%)
RQD) U.C.S.
(%)
MPa
R
L
(m)
x SM : (Silty SAND).
S9 15,19,24 43
11
11.5
-11
11.5 m
Very dense, light brown and light gray,
. . . . . cemented SAND (very weak poorly
cemented sandstone).
12
-12
50
.....
.....
13
S10 50/18cm
-13
50
.....
.....
14
-14
0
.....
.....
15
S11 50/14cm
-15
50
.....
8.5
.....
16
.....
-16
70
20
.....
17
-17
.....
S12 50/10cm
50
.....
18
-18
.....
.....
19
80
40
10
-19
.....
.....
20
-20
ST:
Sample Type
N:
RL:
Reduced Level
penetration
LT:
Layer Thickness
Sample No.
S:
REMARKS:
D:
Depth
A
BH1
A'
BH2
Medium dense to dense, light brown, fine
grained silty SAND.
*made ground on the top 0.70m
2
3
4
5
6
7
D E P T H (m)
8
9
10
11
.....
14 . . . . .
.....
15 . . . . .
.....
16 . . . . .
.....
17 . . . . .
.....
18 . . . . .
.....
19 . . . . .
.....
20 . . . . .
.....
.....
By Acid
Extraction
%
< 0.24
By 2:1
Water/Oil
Extract g/l
< 1.2
Minimum
Cement
/
(Notes 1 & 2)
Maximum
Free
Water/Cement
Ratio (Note1)
In Ground
Water
g/l
Cement Type
(See Table 1c)
< 0.4
AL
Note 3
0.65
330
280
300
0.55
0.55
0.55
1.2 2.3
0.4 1.4
AG
H
IL
2.3 3.7
1.4 3.0
H
IL
320
340
0.50
0.50
3.7 6.7
3.0 6.0
H
IL
360
380
0.45
0.45
3.7 6.7
3.0 6.0
360
0.45
> 6.7
> 6.0
> 6.7
> 6.0
If > 0.24
classify on
basis of 2:1
extract
Note 3. The minimum value required in BS 8110: 1985 and BS 5328: Part 1: 1990 is 275 / for
un-reinforced structural concrete in contact with non-aggressive soil. A minimum cement
content of 300/ for (BS 8110) and maximum free water/cement ratio of 0.60 is required
for reinforced concrete. A minimum cement content of 220 / and maximum free
water/cement ratio of 0.80 is permissible for C20 grade concrete when using un-reinforced strip
foundations and trench fill for low-rise buildings in Class 1.
General Recommendations
For Classes2,3 and 4the requirements for type of cement content and
water/cement ratio given in the Table 1 may be reduced by on class if other
durability and structural considerations permit.
Blocks complying with BS 6073 and with BS 5328:Part 3 relating to use below
ground will be satisfactory for Class 1 conditions in Table 1. For Classes 2 and
3 of Table 1, as an alternative to compliance with the minimum cement content
and water/cement ratio, autoclaved blocks (including aerated blocks Aircrete
with a minimum density of 600 kg/m3) or pressed blocks with more than 50%
of their least cross-sectional area carbonated* may be used.
Concrete bricks
Concrete pipes
Classification with respect to type of cement may be reduced by one class for
pipes complying with Parts 100 and 120 of BS 5911. Cement contents and
water/cement ratios in Table 1 are not relevant.
Compliance with BS 1194. Porous concrete pipes are not suitable for use in
Class3, 4 or 5 soils.
Estimated by breaking block and applying phenolphthalein see BRE Information Paper 6/81
Portland cement BS 12
K
L
In Code I and J, slag with alumina (AI2O3) content over 14% should be used only with Portland cement having low to moderate C3A
content (typically less than 10%)
Total
SO3
SO3 in
2:1
water:soi
l extract
%
Less
than 0.2
g/L
Less
than 1.0
g/L
Leass than
0.3
0.2 to
0.5
1.0 to 1.9
0.3 to 1.2
0.5 to
1.0
1.9 to 3.1
1.2 to 2.5
Free
water/cement
ratio not
more than
Table 1
Kg/m3
330
0.50
310
0.55
BS 4027 (SRPC)
BS 4248 (SSC)
280
0.55
380
0.45
BS 4027 (SRPC)
BS 4248 (SSC)
330
0.50
1.0 to
2.0
3.1 to 5.6
2.5 to 5.0
BS 4027 (SRPC)
BS 4248 (SSC)
370
0.45
Over 2
Over 5.6
Over 5.0
BS 4027 and
BS 4248 (SSC) both with adequate protective
coating (see BS 8110)
370
0.45
1)
Adjustments to minimum cement content should be made for aggregates of nominal maximum size other than 20mm in accordance
with table 8.
2)
If much of the sulphate is present as low solubility calcium sulphate, analysis on the basis of a 2:1 water extract may permit a lower
site classification than that obatained from the extraction of total SO3. Reference should be made to BRE Current Paper 2/79 for
methods of analysis and to BRE Digests 250 (see foreword) and 276 for interpretation in relation to natural soils and fills, respectively.
Note 1. Within the limits specified in this table, the sulphate resistance of combinations of ggbs and pfa with SRPC will be at least
equivalent to combinations with cement complying with BS 12.
Note 2. It is recommended that the alumina content of ggbs does not exceed 15%.
Table 2. Requirements for concrete exposed to attack from acids of pH > 2.5
Use
Foundation
s including
poured
cast-in-situ
piles. For
piles made
by special
techniques
using low
water/ceme
nt ration,
slightly less
stringent
requiremen
ts may be
applicable
pH
Natural Ground
>5.5
3.5
to
5.5
<3.5
External Surface
Pipes to BS
5911: Parts
100 and
120
Internal Surface
Ground
containing
wastes or
made-up
ground
Natural Water
Effluent.
Domestic
Sewage
Industrial
Effluent
Porous
pipes to BS
1194
Land Drainage
Agricultura
l and
Industrial
S or M
No change
No change
>3.5
No change
<3.5
>4.5
No change
<4.5
4.5
to
5.5
>5.0
<5.0
No change
No change
No change
>5.0
<5.0
>3.5
H or L
No change
<3.5
H or L
No change
>5.5
<5.5
Advance to Class 5
<5.5
H = High
L = Low
Industrial Effluent
M = Mobile
S = Static
>5.5
Culverts :
cast-in-situ
or precast
<4.5
Natural
Ground
Aggressiv
e CO2
(Table 3)
>5.5
Ground containing wastes or made
up ground
Mobility of
Water
(Table 1a)
See Dairy Floors: Ministry of Ag Fish and Food 1967 and Concrete in milking parlours
Cement and Concrete Association Farm Note 8:1980
Acid spillage in
industrial processes
Aggressiveness
Description used
in Table 2
High
Aggressive CO2
mg/l
3.5 to .5
above 35
15 and above
High
below 15
Low
40 and above
High
below 40
Low
NATURAL
SOIL
NATURAL
GROUNDWATER
INDUSTRIAL
EFFLUENT
2:1 WATER
EXTRACT
Analytical
determinations
WASTECONTAINING SOIL
2:1 WATER
EXTRACT
SO3 and pH
SO3 and pH
15 pH
LESS
THAN 7
15 pH
LESS
THAN 7
YES
NO
YES
NO
Cl and NO3
CALCULATE
EQUIVALENT SO3
and add to
DETERMINED
SO3
CLASSIFY SITE
ON BASIS OF SO3
CHOOSE:
Type of cement
Water/cement ratio
Cement content
from Table 1
CLASSIFY SITE
ON BASIS OF SO3
CHOOSE:
Type of cement
Water/cement ratio
Cement content
from Table 1