Basic & Detail Engineering Services
Basic & Detail Engineering Services
Basic & Detail Engineering Services
than 80 years.
In each phase Hatch plans carefully for quality outcomes and zero harm to employees and
contractors.
The diagram to the right shows the four major phases of project development through Hatchs
Project LifeCycle Process. This staged approach to project development has proven to reduce
risk and deliver predictable outcomes on projects.
In FEL 1, in conjunction with the client, Hatch reviews concepts, processes, equipment
needs, recent technology developments, site suitability, and the likely costs of each viable
concept.
In FEL 2, the strongest option is selected and more fully developed through the pre-feasibility
study. Basic design and equipment costs and availability are carefully assessed.
In FEL 3, with the formal approval of the client team and board of directors, careful planning,
detail design, and contract commitments for the procurement of technologies and equipment
are undertaken.
In FEL 4, process systems are designed and the facilities are constructed and commissioned.
Engineering excellence centre for EPC contractors Ingenero serves as a seamless part of
engineering divisions of EPC companies, either through remote engineering services or a
dedicated, on-site engineering service team. Our remote satellite office setup specifically for
catering to clients needs provides best cost country advantage to several engineering
conglomerates and manufacturing companies world wide. The typical work flow for the
Engineering excellence center:
Engineering for Green and Brown fields projects Ingenero provides end-to-end
engineering solutions that combine leading edge technology with a best practices approach
where highly qualified engineers routinely optimize designs. We provide assemblage of
customized engineering services to meet diversified needs of our Process Industry clients.
Ingeneros process engineering offerings encompass:
Conceptual Design
Conceptual Design The conceptual design is a study phase in which ideas and possibilities
are evaluated. This phase results in a basic process concept, a preliminary schedule and a
rough cost estimate. At Ingenero, we evaluate the process to assess its technical feasibility
and economic viability for developing project scope as well as providing a well defined
starting point for a more detailed process design.
Ingeneros Concept designing covers:
Literature Survey
Concept development
Concept refinement
Conceptual Layout
Basic Engineering The basic engineering services offered by Ingenero consist of core
documentation of projects, including process flow diagrams, heat & mass balances, piping
and instrumentation diagrams (P&IDs), control & operational philosophy, basic equipment
sizing, equipment specifications, conceptual equipment layout, etc.
Ingeneros basic engineering covers:
Front End Engineering Design (FEED): Ingeneros extensive experience facilitates the
client to have a FEED that reflects all technical specific requirements and avoid any
significant changes during execution of the same.
Ingeneros FFED packages cover:
Basis of Design.
Feasibility Study.
Mechanical data sheets of the main equipment, starting from the process
specifications issued during the BED and incorporating the specific requirements of
codes and standards to be applied to the project.
Development of process and utility Piping and Instrument Diagrams released for
detail engineering.
Elaboration of the main piping, instrument, electrical and civil works layouts.
Carrying out all the studies to be performed before ordering the main equipment.
Detail Engineering Detail engineering includes the extraction of all the essential information
from all the basic engineering drawings and calculations to provide the exact drawings in
detail for all production, fabrication & erection items and in turn the details of entire project
along with the precise bill of quantities and specifications for each of the equipment.
Ingeneros detail engineering covers:
Equipment List.
Line List.
Valve List.
Nitrogen Purging
Pickling / Passivation
Feed Cut in
Specification of effluents.
And, generally speaking, all the basic studies required to support a Basic Engineering
Design Package (BEDP) containing all data needed by a competent contractor to
perform the Detail Engineering.
These basic engineering studies may consist of consolidating a Process Package initiated by
an external process licensor.
2. Front End Engineering Design (FEED) covering:
Mechanical data sheets of the main equipment, starting from the process
specifications issued during the BED and incorporating the specific requirements of
codes and standards to be applied to the project in question.
Development of process and utility Piping and Instrument Diagrams released for
detail engineering.
Elaboration of the main piping, instrument, electrical and civil works layouts.
And, generally speaking, all the studies to be performed before ordering the main
equipment.
Start-up procedures.
And, generally speaking, all the studies to be performed before construction of the plant.
Before starting a project, the pipeline owner/investor (the body funding the project) must
prove the economic viability and need for the project i.e. will the project produce the required
revenues and profit? This phase captures the reasoning behind initiating the project and can
take considerable time to prepare.
FEL 1 includes:
Business case
Strategic objectives
Economic analysis
Project expectations
Market analysis
Competitors review
Environmental constraints
Routing
Preliminary schedules
Led by the owner, developer or an appointed and experienced engineering contractor, these
issues are performed by a joint team and should include a range of technical, engineering,
environmental, social and legal specialists. The level of cost estimate at this point is typically
+/-30%.
Project planning or the FEED phase looks to develop the approved selected solution by
narrowing the cost estimate to +/-15% and achieving a higher level of development schedule.
At this point any project showstoppers would have been identified as part of the
environmental and social impact assessment process and suitable mitigation measures agreed
with the relevant stakeholders (as part of the project consent). It is only when consent has
been granted that project sanction takes place and particularly since it is then possible to
place material orders for long lead items (LLIs) at this stage so as to meet the development
schedule. Project planning could take from 6-12 months depending on the complexity of
project and the environment through which it is routed. If the pipeline has not managed to
avoid sensitive environments, timescales for the FEL process can be extended by many
months whilst detailed ecological or cultural studies are performed
In comparison with plant projects, the cost of FEL developments for a pipeline project are
typically lower, except for possibly international cross-border pipelines or complex systems
such as high temperature pipelines (design temperature > 70C), high pressure pipelines
(design pressure > 200 bars), or fast track projects.
However, whilst the cost of the development activity is lower, it is still significant and often
underestimated. Pipeline project facility planning (FEL 2) for example can range from one
third to three quarters of the activity associated with plant developments. However, the time
taken can in certain circumstances be longer.