Docslide - Us Industrial Training Report I SLT
Docslide - Us Industrial Training Report I SLT
Docslide - Us Industrial Training Report I SLT
TRAINING ORGANIZATION
PERIOD OF TRAINING
FROM: 11.11.2013
FIELD OF SPECIALIZATION
TO: 17.01.2014
ENGINEERING
THUSHAN S.
E/10/361
Acknowledgements
I would like to take this opportunity to express my gratitude to all ladies and gentlemen who have
given their maximum involvement to conclude the Industrial Training Session at Sri Lanka Telecom
(SLT) successfully.
I was trained 02 sections in Sri Lanka Telecom and all the staff members contributed their maximum
to me throughout the training period. Especially sectional heads guided me to extract the maximum out
of each section. The Engineering Section of SLT is highly productive and mine of knowledge for
enhancing the skills and technical knowhow of any apprentice. I would like to express my sincere
gratitude to Mr. K. Kogularanjan, Manager (OPMC-Batticaloa) and his fellow staff for guiding me to
acquire the related engineering and real life applications of the theories which were thought during the
course. In addition I am very much pleased to acknowledge Mr. Y. Kishanthan, Engineer (NetworkEsatern Province), Added to that I would like to give my regards to all other engineers, technical
officers and other staff members for the support they have given to me throughout the session. Further,
it is a must to thank the Training Planning sections of SLT, for arrange my Training and necessary
instructions to carry out our chores during the whole training period.
Finally I would like to express my sincere gratitude to National Apprentice and Industrial Training
Authority (NAITA) for providing us the facilities to undergo a well standard training session, to
Industrial Training and Career Guidance Unit (ITCGU) of Faculty of Engineering as well as the Staff
of Department of Electrical and Electronic Engineering for guiding me throughout the training period.
Thank You,
S. Thushan,
Faculty of Engineering,
University of Peradeniya.
CONTENTS
Acknowledgments
Contents
ii
List of Figures
iv
List of Tables
List of Abbreviations
vi
Chapter 1
INTRODUCTION
1.1
1.2
Introduction of SLT
Chapter 2
Chapter 3
Chapter 4
Chapter 5
2.1
Introduction
2.2
12
3.1
12
3.2
ADSL
15
3.3
16
3.4
PSTN Maintenance
18
3.5
MDF Section
19
CDMA
21
4.1
Introduction
21
4.2
CDMA Technology
21
4.3
CDMA Architecture
21
23
5.1
23
5.2
Introduction
23
5.3
Objective of Rehabilitation
23
Chapter 6
OPERATION SUPPORT
24
Chapter 7
SWITCHING
25
7.1
Introduction
25
7.2
SLT Switches
25
Chapter 8
TRANSMISSION
26
8.1
Introduction
26
8.2
27
8.3
27
ii
Chapter 9
Chapter 10
POWER
29
9.1
Introduction
29
9.2
29
CONCLUSIONS
30
iii
LIST OF FIGURES
Figure.1. 1
SLT Logo
Figure.1. 2
Figure.1.3
Figure.2.1
Figure.2.2
MDF
Figure.2.3
Man Hole
Figure.2.4
Cabinet
Figure.2.5
Figure.2.6
Distribution Point
Figure.2.7
Discharger
Figure.2.8
Rosette
10
Figure.2.9
Splitter
10
Figure.2.10
ADSL Router
10
Figure.2.11
Ethernet Cable
11
Figure.2.12
Telephone
11
Figure.3.1
25-Pair Cable
12
Figure.3.2
14
Figure.3.3
Bicotester
15
Figure.3.4
ADSL Architecture
15
Figure.3.5
16
Figure.3.6
18
Figure.3.7
19
Figure.3.8
20
Figure.3.9
Jumbering at MDF
20
Figure.4.1
CDMA Architecture
21
Figure.4.2
22
Figure.4.3
22
Figure.7.1
25
Figure.8.1
26
Figure.8.2
27
Figure.8.3
28
Figure.9.1
Batteries
29
Figure.9.2
29
iv
LIST OF TABLES
Table 1.1
Training schedule
Table 3.1
Colour Codes
13
LIST OF ABBERVIATIONS
ABBREVIATIONS
DESCRIPTION
ADSL
AE
Assistant Engineer
CCT
CDM
CDMA
CEO
CRO
DGM
DP
Distribution Point
DSLAM
EP
Eastern Province
FTTH
GM
General Manager
HH
Hand Hole
IDD
LTE
MDF
MH
Man Hole
MIMO
MSAN
NOC
ODF
OPMC
PSM
PSTN
RTO
SAE
SEAE
TDMA
VDSL
vi
CHAPTER 01-INTRODUCTION
1.1 INTRODUCTION OF MY TRAINING SESSION
Under the course TR400-Industrial Training I was assigned as an apprentice at Sri Lanka Telecom
PLC, Batticaloa. for a period of 10 weeks, from 11/11/2013 to 17/01/2014 by the Industrial Training
and Career Guidance Unit (ITCGU) of the Faculty of Engineering, University of Peradeniya in
collaboration with National Apprentice and Industrial Training Authority (NAITA). The training
schedule which was given to me is mentioned in Table 1.1.
To
11/11/2013
29/12/2013
11/11/2013
17/11/2013
18/11/2013
24/11/2013
25/11/2013
01/12/2013
02/12/2013
08/12/2013
PSTN Maintenance
09/12/2013
15/12/2013
16/12/2013
22/12/2013
MDF
23/12/2013
29/12/2013
30/12/2013
17/11/2014
Switching
30/12/2013
05/01/2014
Transmission
06/01/2014
12/01/2014
Power
13/01/2014
19/01/2014
NETWORKING- Batticaloa
SLT- VISSION
All Sri Lankans seamlessly connected with world class information, communication and
entertainment services.
SLT- MISSION
Your trusted and proven partner for innovative and exciting communication experiences delivered
with passion, quality and commitment.
SLT- VALUES
Customer Caring - Put customers at the center of everything SLT do
Trustworthy
Innovative
Responsive
Teamwork
Excellence
Results Driven
Group of CEO
CRO
GM/Region 3
DGM/EP
PSM
EP
Manager
OPMC/Batticaloa
SEAE
CDM & New
Connection
SAE/CDM
AE/ADSL
Manager
RTO/Batticaloa
SEAE
Maintenance
SAE/ New
Connection & Data
AE/CDMA
Accountant
EP
SEAE
Rehabilitation &
Development
Engineer
Network/EP
SEAE
Switching,
Transmission & Power
SAE/Power
& AC
SAE/PSTN
AE/MDF
AE
AE
Switching
AE
Transmission
SLT-SUBSIDIARIES
SLT-CUSTOMER PACKAGES
SLT provides various kinds of Packages to their customers. They introduce new technologies for the
satisfaction of their customers. More than this they provide 24 hours customer service for reduces the
inconvenience of telecommunication.
1. Megaline
Single play, Double play and triple play offering for telephone, Broadband and PEO TV.
Enabling the customer to choose the combination that is appropriate for envisaged usage.
2. Broadband
Ten broadband packages available in the market to enable user to choose one that suits their
specific needs.
3. Peo TV
Platform for best of local and international news and entertainment from around the world
This offers new features such as digital quality pictures, time shifted TV, Rewind TV and
etc.
4. IDD
All SLT residential phones are now IDD enabled and 232 numbers of countries connected
with direct links to provide better quality international service.
Fig.2.2 MDF
2.2.2 Man Hole and Hand Hole
Man Hole and Hand Hole are the gates to the underground cables Maintenance and repairing. The
main difference between Hand Hole and Man Hole is a person can do repairs in a man hole. But hand
hole can operate only by using hands.
Fig.2.4 Cabinet
2.2.4 MSAN
Multiple Service Access Node (MSAN) is a new technology replaced for Cabinet. But here no need to
connect with MDF or Exchange. Because all the MSANs connected with Nation Ring in SriLanka.
The advantage of this new technology is however one side of the ring is disconnected MSAN works
with other side of the ring
Fig.2.7 Discharger
2.2.7 Rosette
Rosette is used to connect Discharger and Telephone. Purpose of this instrument is easy to access and
change the connection pin.
Fig.2.8 Rosette
2.2.8 Splitter
Splitter is used when there is an ADSL line. Normally Data contains with high frequency range and
voice contains low frequencies. To filter them and connected to Telephone and router use Splitter. It
has a low pass filter. With is splitter we can access telephone and internet connection without
interruption.
Fig.2.9 Splitter
2.2.9 ADSL Router
ADSL Router is Provides internet service to customers through Ethernet interface.
Receiving circuit: -
Dialing circuit: -
Ringing circuit: -
Fig.2.12 Telephone
11
Installing and maintenance of the primary side of the telephone lines (MDF to Cabinet)
3.1.2 INTRODUCTION
Cable Development and Maintenance section is responsible for the cable connect ion from the
primary side (MDF to Cabinet/ODFOptical Distribution Frame to MSAN- Multi Service Access
Node)
From
the
Line
Side
of
1 0 / 2 0 / 3 0 / 5 0 / 200/300/600/../2400 pairs
the
MDF,
cables
as underground
are
drawn
in
sets
of
lines
available/direct buried cables if the ducts are not available/aerial cables ( for small number of pairs
only) to the Cabinets through HH (Hand Ho les) and Man Holes (MH).MH and HH are found in
different sizes to suit different capacities and they are used as a access interface to the
underground cables for installation/maintenance purposes. Since the copper pairs starting from
SLT end consist of large number of pairs, therefore color codes are used to indent iffy pair
numbers. More than this there are two other types of cables used for connection through direct sand
and water. They are Varry Cables and Submarine Cables.
White
Red
Black
Yellow
Violet
Blue
Orange
Green
Brown
Slate
Blue
Orange
Green
Brown
Slate
Blue
Orange
Green
Brown
Slate
Blue
Orange
Green
Brown
Slate
Blue
Orange
Green
Brown
Slate
Disconnection
This fault occurs due to a partial or permanent disconnection in the line. Because of this fault
there is no voltage (or current) to the phone. Therefore we couldnt hear any sound in the
telephone.
Earth
This fault occurs when A leg or B leg or both legs are connected to the earth.
Short circuits
This fault occurs when A leg and B leg are short circuited. Because of this fault the physical
length of the circuit is short circuited.
Current on line
This is an electrical contact between wires of one pair with a wire of another pair.
13
Keep Propan-2-ol
With the cable
Fig.3.3 Bicotester
3.2 ADSL
3.2.1 JOB PROFILE OF THE SECTION
3.2.2 INTRODUCTION
ADSL means asymmetric digital subscriber line. This is a high speed transmission technique used to
transmit both voice and data at the same time. More than one connection can be supplied using this
technique.
configuration errors(Router)
15
Fault in line (fault in line may occur due to inadequate speed required for ADSL/Peo Tv)
Insufficient knowledge of the customer (Dont know how to connect with splitter)
MDF to DP maximum allowable resistance for PSTN 1500 Ohms and for ADSL 600 Ohms
Modem
Ethernet Cable
Fuse
Cable damage
Phone damaged
Carbon problem with Splitter and Rosette box (In Rainy seasons)
When customers reported about their problems to SLT, then workers of the PSTN maintenance section
visit customer premises and fix them. If they couldnt get the solution for the problem with in their
network then handover the work orders to the CDM section. Most of the above problems occurred due
to the expired. Therefore replacing is a good solution for those problems.
Damaged
Fuses
Assign any telephone number to any loop. Because if there is any fault in the subscriber line,
MDF is the place used to assign new loop for same number. And customer can continue the
communication without any changes.
Exchange cannot replace very easily. Because of that Protecting exchange side is one of the
main functions of the MDF. For those Arresters, Proper earth connection and other protection
used in MDF.
19
Updating clarity. Because all the new connection and faults are informed to MDF, MDF must
update SLT data base.
Isolation from Subscriber lines from exchange. To test conditions of the subscriber lines it is
must to isolate from exchange side.
Also the test equipment is fixed at the MDF as it is a flexible point for testing. So the loop is
disconnected and connected to their testing equipment to check the condition of lines, such as
short circuit, cross connection, disconnection. That equipment is consisting of simple circuit
diagrams.
CHAPTER 04-CDMA
4.1 INTRODUCTION
SLT provides many CDMA services such as voice, data, fax and payphones. SLT-CDMA (city link)
has an island wide coverage and it is a very popular and main telecommunication option especially
in the rural areas where there is no wired network or cellular mobile coverage. Some schools in
remote areas are connected to the School-Net using CDMA modems. And police offices in remote
areas using CDMA fax facility for their communication. Around 30,000 customers using CDMA
phones under the Batticaloa OPMC.
21
MS (Mobile Station) -
connection and disconnection, Mobility Management, Power control, Radio resource management,
Provide stable and reliable radio link.
MSC (Mobile Switching Center) -
VLR (Visitor Location Register) - Database contains temporary information about subscribers
that is needed by the mobile services switching center (MSC) in order to service visiting
subscribers
HLR (Home Location Register) - Stores permanent data about subscribers.
SMC (Short Message Center) -
5.2 INTRODUCTION
Planning and Developing is the main of OPMC in SLT. Major projects of SLT depend on the report of
this division, for example when SLT install a new project, it should give profit to SLT. Therefore
achieving profit to the company and customer satisfaction this section comes into a main role of SLT.
5.3 OBJECTIVE OF REHABILITATION
MDF Repairing of faulty or damage tag blocks, Properly earthling, Removing unwanted
wires, Updating records, Checking arrestors /fuses & replacement, Drawing of jumper wires
properly, Labeling of cables, Marking of special circuits for easy identification (Data, ADSL
etc.)
Overhead Routes - Recovery of unwanted items, Tensioning wires and cables, Installation of
stays and struts, Replacement of faulty lines, Normalization of O / H routes.
Cabinets -Cleaning inside & outside, Removing unwanted jumpers, Updating records,
Labeling & earthling, Properly sealing.
DP - Fixing properly to poles, Earthling, Replacing faulty DP, DP dressing & numbering,
Connecting through bridal rings, Fixing DP bands, Closing DP covers
Route Clearance -
Internal Wiring - Fixing without joints, Fixing earth where necessary, Replacement of faulty
wires, Replacing earth wire joints, Checking earth resistance, Replacement of faulty
dischargers, Replacing of telephones which are more than 10 Years old.
Removal of Drop Wire / PVC Bunches- Extending cables, Splitting DPP, Opening of
stumps.
23
update the
duties are finished/work progress so that other sections may work on that from that point. Work
Orders is another concept which is a part of the clarity which defines the duties assigned to each
section on some task/service order. For a one task/service order to be completed, several sub tasks
may be needed to be done by relevant sections. Therefore work orders are issued with all the
requirements and due dates etc. for a single task and they are either displayed on Clarity or posted to
relevant sections. Another supporting mechanism is the concept of call centers. It
makes much
flexible and efficient connection with the customers in order to feed the system with their feedback
or requirements. In order to elaborate, how these mechanisms take place, lets consider several
examples. When a customer needs to complain regarding a service, by just dialing 1212 it connects
the customer to any of the call centers and by considering the complain/request the call center officer
enter the data to the relevant section of the clarity which then will be directed to the relevant
section of the relevant branch through clarity as a work order so that they can attend to that.
When the relevant task is done, it could be entered to the system so that system will remove the
work order after saving necessary data on the task. I think this is a very efficient way which let the
customers more clear to the operation system, but in a very responsible manner. If we consider a
situation where the network planning sect ion needs to configure new links between two switches,
then several sections (transmission, switch) in both branches as well as branches in headquarters
must incorporate to finish the task. Then all the sections are issued with a work orders containing
detailed task descript ion for each section. If we consider another situation when a new PSTN
connect ion is made, the new connect ion section enters all the relevant
details including
DP(Distribution Point) number, slot number, cabinet number etc. and the MDF staff feed the
system with the relevant block and tag block numbers and the switch enters the sub card numbers.
Slot numbers etc. for a given connection. In this way, all the sect ions involved are very well
connected and well informed about the tasks done by other sections which are relevant to them too
24
25
CHAPTER 8 -TRANSMISSION
8.1 INTRODUCTION
SLT provides many services to the customers all around the island and we can say that for each
service, there should be one island wide network since all the services are about communication. For
almost all the services the service providing equipment are placed in SLT premises and customers
are connected to the network through access network. The network which connects each service
providing equipment to others and to the service network can be considered as the core network
and the above connectivity is provided by transmission section. The transmission links for
connecting local service nodes and the core network is managed by transmission section. Mainly
there are two core network types in SLT and different transmission networks as well
IP/MPLS
NETWORK
USING
O/F
LINKS
26
Optical Source
Power Meter
SDH/PDH Analyzer
Core
Positioned at the center of the cable
As thin as human hair
Made of glass
Light travels inside the core
27
Cladding
Positioned around the core
Made of glass with low reflection
Reflect light back in to the core
Jacket
Also called buffer coating
Made of plastic
Outer most covering
Protect the fiber from damage and moisture
Splicing
Protection -Sleeve
28
CHAPTER 9 POWER
9.1 INTRODUCTION
Power is the main part of the telecommunication network. All the instruments used in SLT need
particular amount of power. When we consider about the usage of power are operation of Switches,
MSANs, CDMA instruments, cooling system etc. Therefore CEB provide a special and separate
connection to all Regional telecom offices. Therefore SLT have to maintenance of the power system
that CEB provide. And SLT have to maintenance their generator which are replacement of main
power and mobile generators as well for MSANs.
Fig.9.1 Batteries
Although I was assigned to OPMC-Batticaloa for 10 weeks, I got a chance to have my training in a
well-planned way in OPMC sect ions as well as in switching and transmission sect ions at that
period for which I am very thankful to Mr. K. Kogularanjan -the Manager at OPMC and
Mr.Y.Kishanthan- Engineer Network in Eastern Province. And I think it was better that I had the
lecture series at training center after I being exposed to the field in some level because there I
first tried to understand the technologies and the system by own with the help of the staff and some
introductory lectures from the staff and then at the training centers I could confirm what I
learned. It was actually motivated me to learn things. I really appreciate all the staff members and
the lectures at SLT who helped me to gain all these experiences and the training Planning sect ion of
SLT for coordinating my training.
I think it would be great if Trainees could have more experience on the network planning,
international switching, transmission and other engineering divisions so that they could be
more exposed to technologies and the challenges to be faced as engineers in the future.
Finally I would like to state that the training experience I had at SLT organized by the Industrial
Training Unit of University of Peradeniya in collaboration with NAITA was up to my
expectations and it was a great experience for me which would definitely help me in my future
carrier.
30