Jabal Al Ka'Aba BOQ Modified
Jabal Al Ka'Aba BOQ Modified
Jabal Al Ka'Aba BOQ Modified
Index
Pages
Preambles
P/1 to P/20
General Requirements
B1/1 to B1/12
Site Work
B2/1 to B2/4
Concrete Work
B3/1 to B3/6
Masonry
B4/1 to B4/3
Metal Work
B5/1 to B5/3
B6/1 to B6/5
B7/1 to B7/7
Finishes
B8/1 to B8/11
Specialists
B9/1 to B9/4
B10/1 to B10/14
B11/1 to B11/1
Provisional Sums
B12/1 to B12/6
Grand Summary
GS/1 to GS/1
Dayworks
DW/1 to DW/6
1/81
Index
2/81
Item
Item Description
Quantity
Unit
Rate
GENERAL REQUIREMENTS
TENDER and CONTRACT
This is a fixed priced Lump sum contract as described in
the conditons of Tender & Contract, Rates filled in by the
tenderer againts items in this document deemed to include
for Escalation and all items of works required and so
necessary to complete the project, to the satisfaction of
Engineer and Employer based on the drawings,
specifications and all other guidance / documents provided.
Tenderer shall check and satisfy himself with the
correctness and completeness of the documents provided
and the accuracy of the quantities provided in the BOQ. No
claims for such an error or mistake in quantities will be
accepted except if such an item indicates an alterations and
modifications.
Note
Generally
Item
500,000
Item
250,000
Item
100,000
Item
300,000
Item
250,000
Site Administration
The Contractor shall provide sufficient staff and equipment
to perform the administrative duties in executing the
Contract
Day
1,500
Site Supervision
The whole of the Works shall be under full time supervision
of the Contractor
Day
2,500
B1-General Requirements
B1/3
Security
The Contractor shall protect the Site and works from
unauthorized entry and fire and shall control his labour
force to prevent nuisance or trespass onto adjacent
property
Day
1,500
Day
3,000
Transport of Workpeople
The Contractor shall make all necessary arrangements for
the transport of his own, and his sub-contractor's
employees for the duration of the Works
Day
5,000
CONSTRUCTIONAL PLANT
Generally
The Contractor shall allow for all necessary
Small plant and tools
Item
1,500,000
Scaffolding
Establishment
Item
10,000,000
Maintenance
Day
25,000
Item
250,000
Item
5,000,000
Maintenance
Day
25,000
Item
4,000
Site Transport
Establishment
Item
5,000
Maintenance
Day
3,000
Item
250,000
Item
1,500,000
Maintenance
Day
5,000
Item
250,000
B1-General Requirements
B1/4
Establishment
Item
1,500,000
Maintenance
Day
5,000
Item
250,000
Item
500,000
Item
50,000
Item
150,000
Establishment
Item
250,000
Maintenance
Day
3,000
Item
100,000
Day
1,000
Day
1,500
Secretary
Provide full time office secretary for the use of the Engineer
& his Representative.
Vehicle
Provide 2 Nos. four wheel drive vehicle including
maintenance and the like.
Day
2,500
Attendance of Staff
Provide a full time office attendant including cleaning for
the sole use of the Engineer and his representatives.
Day
1,000
B1-General Requirements
B1/5
Equipment
Provide survey Instruments and protective clothings as
required by the Engineer and his representative.
Item
250,000
Progress Photographs
Supply and hand over set of progress photographs as per
Division 1 - General Requirements.
Item
150,000
Progress Reports
Provide weekly & monthly progress reports as per Division
1 - General Requirements
Item
300,000
Sign Boards
fabricate, erect and maintain sign boars as per specification
and drawings including removal from site.
F
Establishment
Item
50,000
Maintenance
Day
2,000
Item
15,000
Establishment
Item
2,000,000
Maintenance
Day
15,000
Item
150,000
Note
1,000,000
Labor Camp
Labor Camp is not permitted within the Site area or within
the Contractor's site compound. Watchmen and security
staff only may be accommodated subject to the approval of
the Engineer.
Establishment
Item
400,000
Maintenance
Day
10,000
Item
350,000
B1-General Requirements
B1/6
H
I
Item
500,000
Item
800,000
Item
250,000
Item
300,000
Traffic Diversion
Provide all temporary diversions of vehicular and
pedestrian traffic if required
Item
100,000
Item
60,000
Item
150,000
Establishment
Item
650,000
Maintenance
Day
5,000
Item
200,000
Item
200,000
Item
50,000
B1-General Requirements
B1/7
Item
1,500,000
Item
250,000
Item
200,000
Item
150,000
Item
600,000
Item
250,000
Item
150,000
Item
100,000
Item
50,000
Item
250,000
Item
250,000
Item
300,000
Item
200,000
B1-General Requirements
B1/8
Item
100,000
Item
250,000
Item
50,000
Security
Performance Security in accordance with Conditions of
Contract, Clause 10.1
Item
100,000
Insurances
For the works in accordance with Conditions of Contract,
Clause 21
Item
500,000
Item
200,000
Item
150,000
Item
200,000
Item
250,000
Conditions of Contract
The Contractor to list and price for all costs associated with
compliance with the Conditions of Contract and not
covered elsewhere (details to be provided).
1
2
3
Specification
The Contractor to list and price for all costs associated with
compliance with the Conditions of Contract and not
covered elsewhere (details to be provided).
1
2
3
B1-General Requirements
B1/9
GENERAL REQUIRMENTS
Collection
Page B1/1
Page B1/2
Page B1/3
Page B1/4
Page B1/5
Page B1/6
Page B1/7
Page B1/8
Page B1/9
Page B1/10
Page B1/11
B1-General Requirements
B1/10
B1-General Requirements
SAR
B1/11
Amount : SAR
500,000
0
0
0
250,000
0
0
100,000
0
0
300,000
0
0
250,000
0
0
0
0
0
0
1,500
0
0
2,500
0
B1-General Requirements
B1/12
0
0
3,000
0
0
5,000
0
0
0
0
1,500,000
0
0
10,000,000
0
25,000
0
250,000
0
0
0
0
5,000,000
0
25,000
0
4,000
0
0
5,000
0
3,000
0
250,000
0
0
1,500,000
0
5,000
0
250,000
0
0
0
0
B1-General Requirements
B1/13
0
1,500,000
0
5,000
0
250,000
0
0
0
0
0
0
500,000
0
50,000
0
150,000
0
0
0
250,000
0
3,000
0
100,000
0
1,000
0
0
1,500
0
0
0
0
0
0
0
2,500
0
0
1,000
B1-General Requirements
B1/14
0
2,000,000
0
15,000
0
150,000
0
0
1,000,000
0
0
0
400,000
0
10,000
0
350,000
B1-General Requirements
B1/15
0
650,000
0
5,000
0
200,000
0
0
0
0
0
0
0
0
0
200,000
0
50,000
0
B1-General Requirements
B1/16
0
250,000
0
200,000
0
150,000
0
600,000
0
250,000
0
0
0
0
0
150,000
0
100,000
0
50,000
0
250,000
0
250,000
0
300,000
0
200,000
B1-General Requirements
B1/17
0
250,000
0
0
0
0
0
0
50,000
0
0
0
0
0
0
100,000
0
0
500,000
0
200,000
0
150,000
0
0
200,000
0
0
0
0
0
250,000
B1-General Requirements
B1/18
37,051,500
Amount : SAR
B1-General Requirements
B1/19
B1-General Requirements
B1/20
Item Description
Quantity
Unit
Rate
Item
100,000
Amount : SAR
SITE WORK
Site clearance
A
Shoring
B
0
0
Item 2,000,000
2,000,000
0
0
0
1 Item 2,000,000
2,000,000
0
00
Dewatering
C
m3
250
2,024,750
0
0
0
8,099
m3
50
404,950
0
0
0
0
0
0
0
Disposal
E
100,000
B2 - Site Work
B2/21
300,000
300,000
0
0
0
50
71,040
0
1,421
m2
Anti-Termite Treatment
C
0
0
Item
100,000
100,000
0
0
0
1,660
m3
100
166,000
0
0
0
0
0
0
Back Filling
D
1 Item
SITE WORK
Amount : SAR
Collection
Page B2/1
Page B2/2
Page B2/3
7,166,740
SAR
Bills of Quantities and Dayworks
7,166,740
B2/22
B2 - Site Work
B2/23
Item Description
Quantity Unit
Rate
Amount : SAR
500
71,000
0
CONCRETE WORK
Sub-structure concrete
Plain Concrete
Plain concrete , in accordance with concrete
specification and mix design complete as shown on
drawings and as specified.
A
142
m3
Reinforced Concrete
Raft
0
0
2,486
m3
500
Columns
116
m3
700
Core walls.
49
m3
750
Shear walls
210
m3
750
Tie beams
m3
750
213
m3
700
Slab on grade
78
m3
500
510
m3
600
1,243,000
0
81,200
0
36,750
0
157,500
0
750
0
149,100
0
38,750
0
306,000
0
0
215,000
kg
5.00
To columns
7,212
kg
5.00
To core walls.
20,309
kg
5.00
To shear walls
39,035
kg
5.00
0
0
1,075,000
0
36,060
0
101,545
0
195,175
0
To tie beams
688
kg
5.00
3,440
42,300
Kg
5.00
To slab on grade.
5,500
Kg
5.00
120,000
kg
5.00
211,500
0
27,500
0
600,000
0
0
To raft
To Collection
B3 - Concrete Work
B3/24
Formwork
A
To Raft
270
m2
200
To columns
108
m2
400
To core walls.
376
m2
400
To shear walls
462
m2
400
To tie beams
m2
400
950
m2
300
To slab on grade
39
m2
200
2,533
m2
400
Item
300,000
Item
200,000
Sundries
I
Super-structure
Reinforced Concrete
Reinforced concrete , in accordance with concrete
specification and mix design complete as shown on
drawings and as specified (reinforcement and
formwork measured separately).
A
Columns.
2,125
m3
1,200
Core walls.
1,014
m3
1,200
Shear walls
441
m3
1,200
10,723
m2
300
12,368
m2
320
976
m2
800
Ramp Slab
133
m3
800
11
m3
800
80
m3
1,000
267
m3
1,000
180
m3
1,200
B3 - Concrete Work
150,400
0
184,800
0
3,300
0
285,000
0
7,700
0
1,013,200
0
0
0
0
0
0
0
54,000
0
43,200
0
300,000
0
200,000
0
0
0
0
0
0
0
0
0
0
2,550,000
0
1,216,800
0
529,560
0
3,216,900
0
3,957,760
0
780,800
0
106,400
0
8,800
0
80,000
0
267,000
0
216,000
0
0
0
B3/25
Columns
22,340
kg
5.00
Core walls
176,109
kg
5.00
Shear walls
142,660
kg
5.00
17,252
kg
5.00
282,980
kg
5.00
0
111,700
0
880,545
0
713,300
0
86,260
0
1,414,899
13,128
kg
5.00
65,640
85,440
kg
5.00
19,200
kg
5.00
427,200
0
96,000
24,067
m2
300
7,220,100
0
7,220,100
0
0
0
0
282,600
0
3,923,500
0
1,623,600
0
9,342,200
0
390,600
0
709,200
0
600,000
24,067
m2
300
Sides of columns
471
m2
600
7,847
m2
500
2,706
m2
600
Sides and soffits of solid and post tension slabs and Ram 26,692
m2
350
651
m2
600
1,182
m2
600
1,000
m2
600
Item
700,000
Item
350,000
Item
300,000
Item
350,000
350,000
0
Item
150,000
150,000
Sundries
J
B3 - Concrete Work
700,000
0
350,000
0
300,000
0
B3/26
Superstructure (Cont'd)
Wheel stopper
A
Item
200,000
Item
500,000
500,000
1 Item
250,000
250,000
200,000
0
0
0
Item
CONCRETE WORK
Amount : SAR
Collection
Page B3/1
Page B3/2
Page B3/3
Page B3/4
Page B3/5
57,413,334
SAR
B3/27
B3 - Concrete Work
B3/28
Item Description
Quantity
Unit
Rate
Amount : SAR
MASONRY
Light weight AAC Block
Supply & fix light weight AAC block bedded and
jointed as manufacture, tied to concrete columns and
beams with galvanized steel anchor as per specification.
A
7,708
m2
70
539,560
0
35
m2
85
2,975
0
13,606
m2
100
1,360,600
0
m2
120
720
0
637
m2
164
104,468
0
7,504
m2
120
900,480
0
0
Solid Block
0
0
0
0
824
m2
150
123,600
0
0
0
Lintels
Allow for precast reinforced concrete lintels including
all bearing blocks isolation paper, metal supports, etc.
0
0
100 x 200mm.
1,678
30
200 x 200mm.
753
60
300 x 200mm.
135
90
B4 - Masonry
50,340
0
45,180
0
12,150
B4/29
MASONRY (Cont'd)
Additional Items
A
Item
MASONRY WORKS
Collection
Amount : SAR
Page B2/1
3,140,073
Page B2/2
B4 - Masonry
SAR
B4/30
Item Description
Quantity Unit
Rate
Amount : SAR
METAL WORK
Aluminum Handrail & Balustrade
Supply & fix poder coated aluminum handrail &
balustrade as per drawings and specifications and to
the engineer's approval.
A
80
1,000
Staircase 2
101
1,000
Staircase 3
101
1,000
80,000
0
101,000
0
101,000
0
0
0
17
1,500
25,5000
0
0
Item
250,000
250,0000
00
Item 1,000,000
Access platform
F
For roof.
Item
15,000
Item
30,000
1,000,000
0
0
0
0
0
0
0
0
0
15,000
0
30,000
0
0
00
Ladder
00
B5 - Metal Work
B5/31
Item
25,494
Item
20,000
20,0000
00
Item
25,000
25,0000
0
0
Item
100,000
100,000
0
00
Item
Supply & fix access cover and ladder for the water
tanks, all complete as per drawings for Engineer
approval.
Canopy
Supply & fix stainless steel mirror finished grade 316
canopy including accessories, bolts, fixing elements all
complete as drawings, for Engineer's approval.
Additional Items
E
0
25,4940
METAL WORK
Amount : SAR
Collection
Page B5/1
1,772,994
Page B5/2
Total of Bill No. 5 - METAL WORK
To The Grand Summary
B5 - Metal Work
SAR
B5/32
Item Description
Quantity
Unit
Rate
20
Amount : SAR
1,686
m2
5,663
m2
33,712
0
20
113,260
0
0
0
To Horizontal surface.
3,354
m2
80
268,320
0
To Vertical surface.
2,310
m2
100
231,000
0
2,310
m2
3,354
item
60
138,600
0
40
2
134,160
0
0
0
Water Stopper
G
40,000
40,000
0
Water tank
H
0
0
2,900
m2
100
290,000
00
0
Planters
I
00
43
m2
70
2,975
0
0
0
0
0
0
0
70
763
53,410
0
B6/33
60
763
m2
763
m2
763
763
m2
763
m2
312
312
312
763
Item
C
D
45,780
0
60
45,780
0
60
2
45,780
0
40
30,520
0
20
15,260
0
25
7,800
0
40
12,480
0
100
31,200
0
100
2
76,300
0
10,000
10,000
0
0
0
0
0
0
0
0
253
m2
253
253
m2
253
m2
60
15,180
0
109
25
2,725
0
109
109
70
17,710
0
60
2
15,180
0
60
15,180
0
40
4,360
0
100
10,900
0
B6/34
0
0
Jabal
Al-Ka'aba
for kitchen/ restaurant/ baths/ toilets/
linens/
laundry/Hotel
ablution/ veg. wash /shaft/ pump/ garbageetc.
H
0
0
75
4,207
m2
315,525
0
0
0
0
0
0
0
0
15,552
m2
100
1,555,200
0
0
Fire stopping
B
0
0
500,000
Item
500,000
0
0
0
Item
Amount : SAR
Page B6/1
4,078,297
Page B6/2
Page B6/3
Page B6/4
Total of Bill No. 6 - THERMAL & MOISTURE PROTECTION
To The Grand Summary
SAR
B6/35
Item Description
Quantity
Unit
Rate
Amount : SAR
Type -CW1.
No
520,000
520,0000
445,0000
Type -CW2.
No
445,000
Type -CW3.
No
80,000
Type -CW4.
No
70,000
80,0000
70,0000
Type -CW5.
No
Type -CW6.
No
35,000
31,000
31,000
35,0000
31,0000
Type -CW7.
No
50,000
Type -CW8.
No
45,000
50,0000
45,0000
Type -CW9.
11
No
40,000
Type -CW10.
23
No
25,000
Type -CW11.
13
No
20,000
440,0000
575,0000
260,0000
0
0
0
00
00
B7 - Doors Windows
No
No
10,000
60,0000
25,2000
6,300
B7/36
205
No
7,500
No
3,000
1,537,5000
654,0000
19
No
4,000
76,0000
1
1
No
No
No
20,000
75,000
75,0000
18,0000
18,000
G
H
16
No
6,000
No
2,000
No
8,500
20,0000
96,0000
12,0000
17,0000
0
0
Supply & fix 10mm thick clear heat tempered glass window
with aluminum frame including hardware, accessories.. Etc.
all complete as per drawings and specifications and to the
Engineer's approval. (super durable powder coated).
L
No
0
0
0
72,0000
0
0
8,000
0
0
0
No
7,000
No
7,000
No
6,500
7,0000
7,0000
13,000
0
0
0
0
0
0
0
No
12,000
No
12,500
No
12,000
No
17,000
No
24,500
No
10,000
No
25,500
B7 - Doors Windows
0
0
36,000
0
12,500
0
12,000
0
136,000
0
73,500
0
10,000
0
25,500
0
B7/37
No
8,000
No
11,500
No
4,000
No
7,500
No
80,000
16,000
0
11,500
0
4,000
0
7,500
0
320,000
0
0
0
0
0
0
No
3,200
10
No
21,500
No
3,200
No
5,200
No
3,200
No
5,200
No
4,800
No
6,000
No
4,000
21
No
4,000
No
4,000
No
200,000
Steel Door
Supply & fix steel door including hardware, accessories ...etc
all complete as per drawings and specifications and to the
Engineer's approval (PC rate for supply SAR 150,000.00)
L
DS1
Third Party Assurance Test for all Aluminum Works
Item 250,000
Item 150,000
0
0
19,200
0
215,000
0
3,200
0
26,000
0
12,800
0
10,400
0
4,800
0
36,000
0
20,000
0
84,000
0
4,000
0
0
0
0
0
0
0
0
0
200,000
0
0
0
250,000
0
150,000
0
0
0
0
0
0
0
B7/38
0
0
0
0
484,5000
285
No
1,700
84
No
1,900
No
No
1,900
D
E
4
84
6
No
1,550
408
No
1,450
9,3000
591,6000
Type DT7, 1500 x 2100mm hig, service lift lobby & corr.
H
I
34
60
No
No
2,600
1,300
88,4000
78,0000
No
3,000
No
No
2,400
K
L
3
4
15,0000
7,2000
12,4000
29
No
1,450
No
No
1,700
N
O
11
10
5
No
1,900
Ite
m
500,000
1,700
159,6000
7,6000
142,8000
3,100
42,0500
18,7000
17,0000
1,700
9,5000
0
0
0
0
Sundries
P
Additional Items
A
Item
500,000
0
0
0
0
0
0
0
Amount : SAR
Page B7/1
9,124,250
B7 - Doors Windows
B7/39
Page B7/2
Page B7/4
Page B7/5
Page B7/6
Total of Bill No. 7 - DOORS & WINDOWS
To The Grand Summary
B7 - Doors Windows
SAR
B7/40
Quantity Unit
Item Description
Rate
Amount : SAR
FINISHES
Internal Flooring
Terrazzo tiles (to receive Carpet)
A
11,606
m2
55
638,330
0
0
0
379
m2
600
227,400
0
0
0
778
m2
500
389,000
0
0
0
271
m2
110
29,810
0
1,670
m2
110
183,700
0
292
m2
110
32,120
0
0
0
0
Granite tiles
B
FINISHES (Cont'd)
Internal Flooring (Cont'd)
0
0
0
B8 - Finishes
B8/41
m2
110
91,300
0
2,252
m2
110
247,720
0
253
m2
11,044
m2
250
2,761,000
0
562
m2
200
112,400
0
0
0
0
0
0
0
0
110
27,830
0
0
0
FINISHES (Cont'd)
Internal Flooring (Cont'd)
Granite Tile for Staircase 1
0
0
62
400
62
400
m2
600
24,800
0
24,800
0
3,000
0
0
0
0
0
3,335
80
266,800
0
for riser
3,335
60
200,100
0
B8 - Finishes
B8/42
for Landings.
404
m2
2,493
m2
100
40,400
0
0
0
FINISHES (Cont'd)
299,160
0
0
0
0
0
0
123
m2
120
14,760
0
13
m2
2,000
26,000
0
0
0
123
250
30,750
0
7,104
100
710,400
0
4,112
40
1,316
30
164,480
0
39,480
0
0
0
Skirting
C
D
E
F
100mm width
366
250
200mm width
528
250
300mm width
98
250
FINISHES (Cont'd)
Ablution Sitting
B8 - Finishes
0
0
91,500
0
132,000
0
24,500
0
0
0
0
0
B8/43
no.
2,500
137,500
0
Plaster Works
0
0
44,311
m2
40
47
m2
50
Internal ceiling
C
1,988
m2
70
221
m2
150
m2
200
External Wall
E
0
0
0
0
1,772,440
0
0
0
2,350
0
0
0
0
139,160
0
0
0
33,150
0
0
0
1,600
0
0
0
0
0
0
0
0
Granite tiles
A
0
0
383
m2
650
248,950
0
0
0
6,382
m2
450
2,871,900
0
0
0
Marble tiles
B
B8 - Finishes
B8/44
m2
130
1,142,440
0
0
0
353
m2
130
45,890
0
1,165
m2
130
151,450
0
0
0
0
FINISHES (Cont'd)
Painted walls
A
B
C
D
0
0
19,737
m2
50
986,850
0
2,581
m2
35
90,335
0
10,062
m2
35
352,170
0
11,931
m2
100
1,193,100
0
0
0
0
m2
m2
150
7,277
6,679
200
1,091,550
0
1,335,800
0
1,112
m2
100
111,2000
303
m2
120
36,360
0
22
m2
150
3,300
0
F
G
B8 - Finishes
B8/45
Hotel
159
m2
150
23,850
0
0
FINISHES (Cont'd)
0
0
0
0
0
0
Bulk heads
A
Item 300,000
300,000
0
0
0
Item
250,000
0
250,000
Painted Ceiling
C
D
0
0
2,816
m2
80
225,280
0
2,533
m2
100
253,300
0
0
0
0
0
0
0
0
45
m2
700
600
31,332
0
4,920
0
FINISHES (Cont'd)
External Finishes
Floors
A
Supply & fix 30mm thick cut to size granite tiles with
patterns at the main entrance to the Engineer approval.
(PC supply rate SAR 500/ m2)
Ditto, but for entrance steps.
0
0
0
0
Interlocking
C
102
m2
80
8,160
0
0
0
130
80
10,400
0
Curbstone
D
B8 - Finishes
B8/46
0
0
Granite Cill
E
30
600
18,000
0
0
0
221
m2
120
26,520
0
43
m2
700
44
m2
700
30,100
0
30,450
0
0
0
0
0
0
0
0
0
0
Wall
F
G
FINISHES (Cont'd)
External Finishes (Cont'd)
Precast Panels (including concrete pyramid shape)
A
Design ,manufacture, supply, fixing and erection of prefinished, sand blasted, thermally insulated architectural
precast panels on elevations, including supply and
erection of all the required accessories, fittings, grooves,
sealant, plants, equipment, etc... required for the precast
panels stability, tidiness and acoustic insulation
including preparation of shop drawings.
1
Item 1,000,000
1,000,000
0
0
0
100
4,700
0
0
0
0
Ceiling
B
47
m2
Additional Items
C
Item
FINISHES
Collection
Amount : SAR
Page B8/1
B8 - Finishes
B8/47
Page B8/2
20,798,047
Page B8/4
Page B8/5
Page B8/6
Page B8/7
Page B8/8
Page B8/9
Page B8/10
SAR
B8 - Finishes
B8/48
Item Description
Quantity Unit
Rate
Amount : SAR
SPECIALISTS
Traffic Barriers
A
No
60,000
120,000
0
0
0
Ite
m
20,000
20,000
0
0
0
0
Item 100,000
100,000
0
0
0
0
Item 500,000
500,000
0
0
0
Item 100,000
100,000
0
0
0
0
Column guards
D
B9 - Specialists
B9/49
Pipe guards
A
0
0
0
Item 500,000
500,000
0
0
0
Item 200,000
200,000
0
0
0
0
0
Speed hump
B
Garbage Chute
Allow for supply, install , testing and commission of
Garbage Chute System as per drawings and
specifications and to the Engineer's approval.
No
SPECIALISTS (Cont'd)
Additional Items
A
Item
500,000
500,000
0
0
0
0
0
0
0
0
SPECIALISTS
Collection
Amount : SAR
Page B9/1
2,040,000
Page B9/2
Page B9/3
Total of Bill No. 10- SPECIALISTS
To The Grand Summary
B9 - Specialists
B9/50
Item Description
Quantity
Unit
Rate
Amount : SAR
PROVISIONAL SUMS
Provisional sums for works to be executed by
nominated Sub-contractors/ Suppliers, to be expended
in whole or in part, or not at all at the direction of the
Engineer.
Window cleaning system
Allow for supply, installation, testing & commissioning
of window cleaning system / by nominated
subcontractor .
B Add: Main Contractor's Profit
Sum
350,000
20
70,000
Sum
50,000
50,000
Sum
Sum
250,000
30
75,000
Sum
50,000
50,000
Sum
3,700,000
20
740,000
Sum
100,000
100,000
Sum
6,000,000
B12/51
20
1,200,000
Sum
200,000
200,000
Sum
Faade Lighting
E Allow for Faade Lighting works to be carried out by
Specialist Nominated Contractor.
Sum
350,000
20
70,000
Sum
100,000
100,000
Sum
Ironmongery Works
I Allow for supply only Ironmongery Works for wooden
doors to be carried out by nominated supplier.
Sum
700,000
20
140,000
Sum
150,000
150,000
Sum
1,000,000
20
200,000
Sum
150,000
150,000
Sum
3,800,000
21
798,000
Sum
500,000
500,000
Sum
1,700,000
B12/52
25
425,000
Sum
200,000
200,000
Sum
Mirrors
H
500,000
25
125,000
Sum
50,000
50,000
Sum
1,000,000
35
350,000
Sum
200,000
200,000
Sum
Sum
By Owner
20
Sum
300,000
300,000
Sum
Electrical Appliances
By Owner
All furniture.
By Owner
Item
B12 - Provisional Sums
Item Description
Quantity
Bills of Quantities and Dayworks
Unit
Rate
Amount : SAR
B12/53
Supply, installation, testing, commissioning of substation equipment including transformers, ring main
units, power cables in between transformers & main
distribution boards/ air circuit breakers, from ring
main unit to EWA supply network, KWH meters,
electricity connection charges, power supply connection
charges.
Prime cost sum for the drainage, water supply
connection charges.
Item 3,000,000
3,000,000
Item
1,500,000
PROVISIONAL SUMS
Collection
Amount : SAR
Page B12/1
30,093,000
Page B12/2
Page B12/3
Page B12/4
Page B12/5
Total of Bill No. 12 - PROVISIONAL SUMS
To The Grand Summary
SAR
B12/54
Item Description
Amount : SAR
Grand Summary
B1 General Requirements
Grand Summary
B2 Site Work
7,166,740
B3 Concrete Work
57,413,334
B4 Masonry
3,140,073
B5 Metal Work
1,772,994
4,078,297
9,124,250
B8 Finishes
20,798,047
B9
2,040,000
Specialists
37,510,705
56,862,560
30,093,000
GS/1
Grand Summary
GS/1
Profit
Grand Summary
230,000,000
SAR
total
230,000,000
GS/1
t : SAR
Grand Summary
GS/1
Grand Summary
GS/1
Grand Summary
GS/1
Item
Item Description
A General Notes
Day works will be administered strictly in accordance with Clause 52.4 of the Conditions of Contract.
The Contractor will be paid for Day Works carried out during the course of the works, while other
operations are in progress, at the rates set out in this schedule. Profits and Overheads are not to be
included in the actual rates but stated as a percentag
The basic unit rates to be inserted in the Day Works Schedule shall be the rates, which the Contractor
has used in determining his unit rates inserted elsewhere in these Tender Documents.
Actual time engaged in the works only will be allowed. In the event of Labor or Plant having to be
brought to the site specifically for an item of Day work, then a reasonable allowance for traveling
time shall be considered. Any such allowance shall be ag
B General Notes on Rates for Labor
The Day Work rates quoted for labor are to be the net amount payable, including wages, bonuses and
all other allowances paid to the operatives directly engaged on Day Works. The Day Work rates shall
include for the use of hand tools and consumables, ordin
No special rates for working overtime will be admissible unless specifically authorized by the
Engineer in writing.
The cost of all supervisory and administrative staff, including Engineers, Foremen, Clerks, Store
men, Secretaries, Assistants etc. is to be included in the percentage addition for overheads and profits.
C General Notes on Rates for Material
Materials used in Day Works shall be as specified elsewhere for the works. The rates are to be the net
invoice price including the cost of delivery to the site. In the event of any material not included in the
Schedule is to be used in an item of Day Work
General Notes on Rates for Plant
Plant hire rates hall include for the cost of maintaining in proper working order, insurance, fuel and
all consumables, cleaning material, replacement and/or sharpening of tools and the like.
Idle time, maintenance or
traveling time to the site will not
The
actual cost of hiring plant not listed in the Schedule will be paid based on the Contractor's
be considered.
invoices. Competitive quotations must be obtained for all plant hired. In the event of Contractor's
own plant and equipment being used, a reasonable rate bas
E General Notes on Percentage Addition
The percentage inserted at the item provided at the end of each section shall, in addition to any item
referred to previously, include for the following: overheads and profits, supervisory and
administrative staff, establishment costs, all costs related t
Dayworks
61/81
Item
Item Description
Quantity
Unit
Rate
A Laborers / helpers.
500
Hr
15.00
B Scaffolders.
150
Hr
25.00
C Steel fixers.
250
Hr
35.00
D Drainage layers.
100
Hr
25.00
250
Hr
35.00
F Plasterers.
250
Hr
30.00
250
Hr
30.00
H Plumbers.
150
Hr
35.00
Painters.
150
Hr
30.00
Electricians./Ac mechanics
150
Hr
30.00
100
Hr
30.00
100
Hr
40.00
M Welders.
100
Hr
25.00
N Pipe Fitter.
100
Hr
25.00
O Metal Worker.
100
Hr
30.00
P Attendant.
100
Hr
35.00
Q Charge hand.
100
Hr
30.00
100
Hr
40.00
Amount : SAR
Labor
7,500
0
3,750
0
8,750
0
2,500
0
8,750
0
7,500
0
7,500
0
5,250
0
4,500
0
4,500
0
3,000
0
4,000
0
2,500
0
2,500
0
3,000
0
3,500
0
3,000
0
4,000
0
0
0
0
0
Percentage Addition
S Allow for all other cost and charges.
Dayworks
62/81
Material
A Building Sand
50
Jabal Al-Ka'aba Hotel
00
2,5000
m3
50.00
10
Ton
400.00
10
Ton
500.00
D Coarse aggregate.
25
80.00
E Fine aggregate.
25
100.00
Ton
5,000.00
Ton
4,500.00
10
250.00
10
400.00
10
450.00
10
500.00
L GGBS (30%)
M GGBS (60%)
N Microsilica (5%)
250.00
250
0
O Form work.
20
m2
150.00
500
No.
3.00
3,0000
1,5000
500
No.
4.00
500
No.
5.00
2,0000
2,5000
500
No.
500
No.
3.00
4.00
4.00
1,5000
2,0000
500
No.
5.00
2,5000
100
m2
00
100
m2
00
100
m2
00
100
00
100
m2
00
AA 12mm Plywood
30
m2
300.00
9,0000
AB 18mm plywood
30
m2
400.00
AC Epoxy Paint
200
liter
50.00
12,0000
10,0000
AD Emulsion Paint
200
liter
40.00
AE Enamel Paint
200
liter
40.00
4,0000
5,0000
2,0000
2,5000
25,0000
9,0000
2,5000
4,0000
4,5000
5,0000
00
00
8,0000
8,000
0
Percentage Addition
AF Allow for all other costs and charges.
00
0
0
0
0
0
30,000
0
10,000
0
Plant
A Concrete mixer.
20
Hr
1,500.00
50
Hr
200.00
Dayworks
63/81
50
50
Jabal Al-Ka'aba Hotel
Hr
150.00
Hr
60.00
E Dumper 1 m3 capacity.
50
Hr
80.00
F Drill machines.
20
Hr
25.00
G Tower Crane.
50
Hr
20,000.00
50
Hr
5,000.00
50
Hr
10,000.00
50
Hr
15,000.00
20
Hr
500.00
L Material hoist.
50
Hr
250.00
M Vibrator.
20
Hr
20.00
N Power float.
30
Hr
150.00
O Electric saw.
20
Hr
150.00
30
Hr
100.00
50
Hr
250.00
50
Hr
200.00
20
Hr
600.00
T Pneumatic compressor.
30
Hr
150.00
20
Hr
250.00
V Bob cat.
20
Hr
100.00
W Welding plant.
X Electric Generator 50 KVA.
Y Electric Generator 10 KVA.
20
Hr
1,500.00
30
Hr
2,000.00
30
Hr
1,700.00
Z Concrete pump.
20
Hr
350.00
20
Hr
250.00
AA Truck mixer.
AB Water Pump 25 KW
7,500
0
3,000
0
4,000
0
500
0
1,000,000
0
250,000
0
500,000
0
750,000
0
10,000
0
12,500
0
400
0
4,500
0
3,000
0
3,000
0
12,500
0
10,000
0
12,000
0
4,500
0
5,000
0
2,000
0
30,000
0
60,000
0
51,000
0
7,000
0
5,000
0
0
0
0
Plant(Cont'd)
A Water tanker 4000 gal. capacity.
25
hr
150.00
20
hr
500.00
C Oxygen cutter.
20
hr
200.00
D Electric cutter.
20
hr
200.00
E Compactor.
30
hr
300.00
F Roller.
20
hr
150.00
Dayworks
0
0
3,750
0
10,000
0
4,000
0
4,000
0
9,000
0
3,000
64/81
Percentage Addition
0
0
0
0
Total of page 1
Total of page 2
3,035,400
Total of page 3
Total of page 4
Total of page 5
Total for Dayworks
Dayworks
65/81
Preambles
B8- Finishes
B9- Specialists
Grand Summary
Dayworks