GridCode 2014
GridCode 2014
1 of 199
GRID CODE
INDEX
CHAPTER 1: GENERAL CONDITIONS
1.
2.
3.
4.
SECTION: BACKGROUND
1.1.
Title
1.2.
1.3.
1.4.
1.5.
2.1.
Objective
2.2.
Unforeseen circumstances
2.3.
Enforcement
10
2.4.
Definitions
10
2.5.
Interpretation
10
2.6.
Derogations
11
2.7.
Hierarchy
13
2.8.
14
2.9.
Effectiveness
14
15
3.1.
Review Panel
15
3.2.
15
3.3.
15
17
4.1.
General
17
4.2.
Monitoring
17
4.3.
Testing
18
4.4.
Investigations
19
4.5.
19
CHAPTER 2: PLANNING
5.
6.
7.
20
20
5.1.
Objectives
20
5.2.
Purpose
20
5.3.
SCOPE
21
21
6.1.
Objective
21
6.2.
22
22
Planning standards
22
2 of 199
8.
7.2.
22
7.3.
User involvement
24
26
8.1.
Information Required
26
8.2.
27
8.3.
32
8.4.
35
8.5.
36
8.6.
40
8.7.
41
8.8.
Network Data
43
10.
11.
12.
45
45
9.1.
Objective
45
9.2.
Purpose
45
9.3.
Scope
46
47
10.1.
47
10.2.
Voltage Perturbations
48
50
11.1.
50
11.2.
52
11.3.
54
SECTION: TECHNICAL CRITERIA FOR PLANT AND APPARATUS AT THE CONNECTION POINT
12.1.
General
56
12.2.
56
12.3.
Telecommunication Installations
57
12.4.
58
12.5.
58
12.6.
59
CHAPTER 4: OPERATION
13.
14.
56
63
63
13.1.
Objective
63
13.2.
Scope
63
65
14.1.
Objective
65
14.2.
General
65
14.3.
66
14.4.
66
14.5.
66
3 of 199
15.
16.
17.
18.
19.
14.6.
De-energisation of plant
67
14.7.
68
70
15.1.
Objective
70
15.2.
General
70
15.3.
Frequency limits
70
15.4.
Frequency Control
71
15.5.
71
15.6.
72
15.7.
74
15.8.
74
77
16.1.
Objective
77
16.2.
General
77
16.3.
Voltage Control
77
16.4.
77
16.5.
78
16.6.
78
16.7.
79
81
17.1.
Objective
81
17.2.
General
81
17.3.
Ancillary Service
81
17.4.
Requirements
81
83
18.1.
Objective
83
18.2.
General
83
18.3.
Emergency operation
84
18.4.
Restoration of supply
85
18.5.
86
18.6.
86
18.7.
87
89
19.1.
Objective
89
19.2.
General
89
19.3.
90
19.4.
91
19.5.
93
19.6.
Connections
93
19.7.
94
4 of 199
21.
22.
23.
94
95
20.1.
Objective
95
20.2.
General
95
20.3.
Requirement to notify
95
20.4.
95
20.5.
96
20.6.
96
20.7.
96
20.8.
Notification of events
97
20.9.
97
20.10.
97
20.11.
Recording of an event
97
20.12.
97
20.13.
97
20.14.
Contact locations
98
20.15.
Communication facilities
100
20.16.
100
20.17.
Computer equipment
101
20.18.
Telephone/Facsimile
101
20.19.
101
20.20.
Time standards
101
20.21.
102
20.22.
102
20.23.
Data retention
102
104
21.1.
Objective
104
21.2.
General
104
21.3.
104
21.4.
Dispatch Scheduling
105
21.5.
Generation Dispatch
107
113
22.1.
Objective
113
22.2.
General
113
22.3.
Outage scheduling
113
22.4.
115
22.5.
116
117
23.1.
Objective
117
23.2.
General
117
5 of 199
24.
25.
26.
23.3.
117
23.4.
Reliability Indicators
117
23.5.
Reporting
118
119
24.1.
Objective
119
24.2.
General
119
24.3.
119
24.4.
120
24.5.
121
24.6.
121
24.7.
122
24.8.
123
24.9.
Test Reporting
123
24.10.
Disputes
124
125
25.1.
Objective
125
25.2.
GEneral
125
25.3.
Interpretation
125
25.4.
Procedure
126
25.5.
127
25.6.
128
132
1.
APPENDIX 1: DEFINITIONS
134
2.
154
3.
155
4.
167
4.
169
4.
171
4.
172
4.
173
5.
174
6.
188
7.
192
8.
197
9.
198
6 of 199
SECTION: BACKGROUND
1.1.
TITLE
1.1.1. The Grid Code and guidelines shall be called the Grid Code for the Electricity
Industry of Nigeria (the Code)
1.2.
1.2.1. The Electric Power Sector Reform Act, 2005 (henceforth referred to as the Act) gave
legal backing to the unbundling of the Nigeria Power Sector. The Act stipulates the
functional unbundling of the Generation, Transmission and Distribution Sectors.
1.2.2. Pursuant to Sections 8, 65 and 66 of the Act, a Transmission and System Operating
Company (TCN) shall be established and licenced to perform the functions of transmission
and system operations of the High Voltage network of the Nigerian Electricity Supply
Industry.
1.3.
1.3.1. The Grid Code contains the day-to-day operating procedures and principles
governing the development, maintenance and operation of an effective, well-coordinated and
economic Transmission System for the electricity sector in Nigeria.
1.3.2. The code is designed to:
(a) Facilitate an efficient production and supply of electricity for all Users of the
Transmission System and TCN itself, without any act of discrimination between
Users or class of Users.
(b) Facilitate competition in the generation and supply of electricity in the country.
1.3.3. For complete understanding of the operation of the Nigeria Electricity industry post deregulation, this document has to be read in conjunction with the Market Rules, Metering
Code, Distribution Code and other documents relating to other operational aspects of the
industry.
1.4.
1.4.1. The Grid Code shall apply to TCN and Users of the Transmission System. TCN shall
be responsible for implementation of the Grid Code. All Users the System Operator and the
Transmission Service Provider shall comply with the Grid Code and assist TCN in this
regard. Users must provide all the required information and reasonable rights of access,
service and facilities necessary for implementation of the Grid Code.
7 of 199
(a) If any User has any difficulty in complying with any of the provisions of the
Grid Code, the User shall immediately, without delay, inform the same to the
Nigerian Electricity Regulatory Commission and TCN, and shall remedy his
non-compliance promptly.
(b) Consistent failure in compliance with the Grid Code may lead to disconnection
of the Users plant, Equipment or Apparatus.
(c) Consistent failure by the System Operator or the Transmission Service Provider
to comply with the Grid Code shall be dealt with under Section 4.5.
(d) The operation of the Grid Code shall be reviewed regularly by the Grid Code
Review Panel in accordance with the provisions of the relevant Sections of the
Code.
1.5.
1.5.1. TCN shall perform two different groups of functions in relation to network and
system operation activities:
(a) As Transmission Service Provider (TSP):
(i)
admit Users in accordance with the this Grid Code who satisfy the
requirements for connection;
(ii)
(iii)
(iv)
dispatch Generating Units in accordance with this Code at least cost, on the
basis of Nominations by Generators;
(ii)
b.ii.1)
(iii)
(iv)
(v)
(vi)
(vii) test and monitor Users Equipment to ensure their compliance with the Grid
Code;
The Grid Code -Version 02
8 of 199
(viii) report scheduled and planned actions and unexpected occurrences such as
faults to Users and the Regulator; and
(ix)
2.
2.1.
OBJECTIVE
9 of 199
2.2.4. If circumstances not envisaged by the provisions of the Grid Code should arise, the
System Operator shall, to the extent reasonably practicable in the circumstances, consult
promptly and in good faith with the Grid Code Review Panel (the Panel) or all affected Users
in an effort to reach agreement as to what should be done. If agreement between the System
Operator and the Panel or affected Users cannot be reached in the time available, the System
Operator shall determine what shall be done in accordance with Good Utility Practice.
2.2.5. The System Operator shall promptly refer any unforeseen circumstance identified,
together with the determinations and interpretations made, to the Panel for consideration.
2.2.6. Each User shall comply with all instructions given to it by the System Operator,
following a determination of actions regarding an unforeseen circumstance even if there is a
difference in interpretation, provided that such instructions are consistent with the technical
characteristics of the User's System and the principles established in the Grid Code, and do
not endanger the safety of its Equipment or staff.
2.2.7. Users should note that the provisions of the Grid Code may be suspended in whole
or in part during a Security Period or in accordance with a Civil Emergency Direction issued
under a Civil Emergency directive by an appropriate authority.
2.2.8. Users shall provide such reasonable cooperation and assistance as TCN may require
in any such unforeseen circumstances.
2.3. ENFORCEMENT
2.3.1. The Act assigns to NERC the authority to establish the appropriate technical codes
and manuals that may be required for the safe, reliable and efficient operation of the System.
Within such powers, the NERC has the authority to establish the initial Grid Code and to
approve amendments from time to time, as proposed by the TCN and affected Users.
2.3.2. The provisions of this Code shall be enforced by the System Operator in accordance
with the Rule 45 of the Market Rules, guidelines from NERC, and Grid Connection
Agreements.
2.4. DEFINITIONS
2.4.1. Capitalised words and expressions used in this Code, unless the context otherwise
requires, shall have the meaning assigned to them in Appendix1.
2.4.2. Where a term is not defined in this document it takes the meaning assigned in the Act
or the Market Rules with the Act definition taking precedence.
2.5. INTERPRETATION
2.5.1. In this Code, unless the context otherwise requires:
(a) a reference to a particular Section, Subsection, or Appendix is to a Section or
Subsection of, or Appendix to, this Code;
10 of 199
2.6. DEROGATIONS
2.6.1. If a User finds that it is, or will be, unable to comply with any provision of this Code,
then the User shall, without delay, report such non-compliance to the System Operator and
shall make such reasonable efforts as are required to remedy such non-compliance as soon as
is reasonably practicable.
2.6.2. When the non-compliance described in the Subsection 2.6.1 arises upon the issuance
of this Grid Code relating to Equipment already connected to the Transmission System or
Equipment approved to be connected to the Transmission System where the User has
commenced the procurement or works prior to the issuance of this Grid Code and the User
believes either that it would be unreasonable (including on the grounds of cost and technical
considerations) to remedy such non-compliance or that it should be granted an extended
period to remedy such non-compliance, the User shall promptly submit to the System
Operator a request for derogation from such provision in accordance with this Section. The
burden of proof shall rest with the User to show good reason why it cannot comply.
11 of 199
2.6.3. If TCN finds that it is, or will be, unable to comply with any provision of this Grid
Code, then it shall, without delay, report such non-compliance to the NERC and shall make
such reasonable efforts as are required to remedy such non-compliance as soon as is
reasonably practicable.
2.6.4. When the non-compliance described in the previous Subsection arises upon the
issuance of this Grid Code, relating to Equipment already connected to the Transmission
System or Equipment approved to be connected to the Transmission System where TCN has
commenced the procurement or works prior to the issuance of this Grid Code, and TCN
believes either that it would be unreasonable (including on the grounds of cost and technical
considerations) to remedy such non-compliance or that it should be granted an extended
period to remedy such non-compliance, TCN shall promptly submit to the NERC a request
for derogation from such provision in accordance with this Section. The burden of proof
shall rest with TCN, to show good reason why it cannot comply.
2.6.5. A request for derogation from any provision of this Grid Code shall contain:
(a) the detail of the Equipment and if relevant Connection Point in respect of
which derogation is sought and the nature and extent of non-compliance;
(b) the provision of this Grid Code with which the TCN or User that requests the
derogation, is or will be unable to comply;
(c) the reason for the non-compliance; and
(d) the remedial actions and the date by which compliance could be achieved (if
remedy of the non-compliance is possible).
2.6.6. Every six months, the System Operator shall report to the NERC:
(a) the list of derogations requested during the previous six (6) months, including
requests by the TCN, and the status of each request;
(b) the list of approved derogations during the previous six (6) months indicating
type of derogation and party; and
(c) for each approved derogation, the progress of remedial actions in achieving
compliance.
2.6.7. On receipt of any request for derogation, the System Operator or the NERC, as
applicable, shall promptly consider such a request provided that the System Operator or the
NERC considers that the grounds for the derogation are reasonable. In its consideration of a
derogation request, the System Operator or the NERC, as applicable, may contact the User
or System Operator, to obtain clarifications of the request or request additional information
or to discuss changes to the request, and review possible remedial actions to achieve
compliance as soon as reasonably practicable.
2.6.8. The System Operator shall:
(a) keep a register of all derogations which have been granted, identifying the name
of the User in respect of whom the derogation has been granted, the relevant
provision of this Grid Code and the period of the derogation; and
12 of 199
(b) on request from the NERC or any User, provide a copy of such register of
derogations.
2.6.9. The NERC shall:
(a) keep a register of all derogations that have been granted to the TCN, identifying
the relevant provision of this Grid Code and the period of the derogation; and
(b) on request from any User provide a copy of such register of derogations.
2.6.10. The NERC may initiate on its own initiative or at the request of the System Operator,
or in view of a User complaint, a review of any existing derogations, and any derogations
under consideration where a relevant and material change in circumstance has occurred.
2.7. HIERARCHY
2.7.1. In the event of any inconsistency between this Grid Code and the Act or the Market
Rules, or the license of the TSP or the System Operator or a Licensee that is a User, the Act
shall prevail to the extent of such inconsistency.
2.7.2. Nothing in this Grid Code is intended to or shall derogate from any license obligation
of a Licensee.
2.7.3. If any provision of this Grid Code should be found to be unlawful or wholly or
partially invalid for any reason, the validity of all remaining provisions of this Grid Code shall
not be affected.
2.7.4. If part of a provision of this Grid Code is found to be unlawful or invalid but the rest
of such provision would remain valid if part of the wording were deleted, the provision shall
apply with such minimum modification as may be:
(a) necessary to make it valid and effective; and
(b) most closely achieves the result of the original wording but without affecting the
meaning or validity of any other provision of this Grid Code.
2.7.5. In the event of any conflict between the provisions of this Grid Code and any
contract, agreement or arrangement between TCN and a User, the provisions of this Grid
Code shall prevail unless this Grid Code expressly provides otherwise, provided that in the
case of Grid Connection Agreements with Users signed prior to the approval of this Grid
Code, the conditions in such agreement shall prevail unless:
(a) the parties agree on amendments to such an agreement: or
(b) the User registers a non-compliance situation that negatively affects the security
of the Transmission System, in which case the User must accept the necessary
amendments to ensure full compliance with this Grid Code, except for any
derogation.
2.7.6. This Grid Code shall be interpreted so as to avoid, to the extent reasonably possible,
findings of inconsistency between this Grid Code and the Market Rules; but where there is
such an inconsistency and it relates to financial issues the Market Rules shall prevail and
where it relates to engineering issues and/or technical issues this Grid Code shall prevail.
The Grid Code -Version 02
13 of 199
2.9. EFFECTIVENESS
2.9.1. The provisions of this Code shall come into effect upon the satisfaction or fulfilment
of the events and matters set out or referred to in Appendix 2 (the Conditions Precedent),
as declared by the Commission.
14 of 199
3.
3.1.
REVIEW PANEL
3.1.1. A Grid Code Review Panel (GCRP) shall be formed pursuant to Rule 42 of the
Market Rules. This Panel shall be in charge of the Grid Code review and amendment.
(ii)
For a period of 30 days after the appointment of the Expert or such other
period as the parties may agree, each party may make such written
submissions as it wishes to the Expert and shall simultaneously provide a
copy to the other party.
(iii)
At the end of such 30 day period each party shall have a period of 15 days to
make counter-submissions to the Expert (with a copy to the other party) in
reply to the other partys written submissions made during the
aforementioned 15 day period provided that neither party shall during such
15 day period make any written counter-submission which purports to reply
to, raise or refer to, any new matters not raised or referred to in any
submission made during the aforementioned 15 day period.
15 of 199
(iv)
At the end of the 15 day period referred to in Subsection (iii) above, and no
later than 15 days thereafter, either party may, with the consent of the Expert
and at a time and place decided by the Expert, make an oral presentation to
the Expert in the presence of the other party commenting on or explaining
matters previously submitted to the Expert in writing.
(v)
The Expert shall render his determination in writing within 30 days of the
completion of the oral presentations made in accordance with Subsection (iv)
and give reasonable details of the reasons for his determination.
(vi)
The decision of the Expert shall be final and binding on the parties save in
the event of fraud or manifest error or mistake.
Neither party shall have any right to commence or maintain any legal
proceedings pertaining to a Dispute until the Dispute has been resolved in
accordance with Subsections (i), (ii) or (v) above, and then only to enforce or
execute the award under such procedure.
(x)
The parties shall each secure that all Experts and arbitrators shall agree to be
bound by the provisions on confidentiality of this Code as a condition of
appointment.
16 of 199
4.
4.1.
GENERAL
4.1.1. The System Operator or the TSP, as applicable, will need to carry out certain
monitoring, testing and investigations in respect of the performance and characteristics of
Generation and Load plant in order to discharge its responsibilities in respect of the safe,
secure and economic operation of the Transmission System and in respect of Generation
Dispatch.
4.1.2. In order to achieve the primary objectives, procedures need to be established for the
monitoring, testing and investigation for each of the following:
(a) Whether centrally Dispatched Generating Units comply with Dispatch
Instructions;
(b) Whether Generators are in compliance with registered Availability, Ancillary
Services capabilities, operating characteristics and any other data required to be
registered by those Generators;
(c) Whether power quality of Users conforms to the standards and limits agreed
upon between the affected parties, with respect to the minimum and maximum
fault levels, harmonic current injected limits, harmonic voltage contributions,
short-term and long-term voltage Flicker, voltage unbalance, the number and
the duration and severity of voltage depressions; and
(d) Whether Users are in compliance with protection requirements and protection
settings, Grid Connection Agreements, Ancillary Services Agreements and other
relevant support agreements between Users and the System Operator or the
TSP, as applicable.
(e) Whether Service Providers are in compliance with protection requirements and
protection settings, Grid Connection Agreements, Ancillary Services
Agreements and other relevant support agreements between Users and the
System Operator or the TSP, as reasonably applicable.
4.2. MONITORING
4.2.1. Time
Monitoring may be carried out at any time by the System Operator or TSP, as applicable,
and may result, without the application of further testing, in the evaluation by the System
Operator or TSP of User non-compliance.
4.2.2. Period
17 of 199
Monitoring may be continuous for a specified or unspecified period and shall be carried
out by monitoring, data recording and analysis. It shall not require advance notice from
the System Operator or TSP to User.
4.2.3. Recording and analysis system
Where a data recording and analysis system is used, the System Operator shall inform the
User that this is so and describe any instrument being used. On request from the User,
shall make available to the User information in respect of the data recording and analysis
system.
4.2.4. Disputes
Disputes shall be handled according to Subsection 3.3 above.
4.2.5. Performance parameters
Performance parameters shall be defined according to Rule 12 of the Market Rules.
4.2.6. Monitoring systems and procedures
The systems and procedures shall be laid out as defined in this Code.
4.3. TESTING
4.3.1. System Operators or TSPs right to testing
System Operator or TSP may, from time to time, carry out tests to verify that a User is
complying with its connection conditions and registered operating characteristics in the
Registered Information. Such testing by the System Operator and/or TSP should be
done in such way as to minimize risk to personnel, Generating Unit and grid integrity.
The System Operator may:
(a) Induce controlled Power System Frequency or voltage conditions or variations
for the purpose of determining that the Generating Units response is in
accordance with its registered Availability, Ancillary Service capabilities and
operating characteristics, and
(b) Having given three (3) Business Days notice, or less where agreed, send a
representative to the Users site to verify by testing in accordance with the test
procedures specified, that the User is in compliance with its registered values.
4.3.2. Dispatch Instruction
Tests shall be carried out to a Dispatch Instruction from the System Operator.
A test may require the User to carry out specific actions in response to a Dispatch
Instruction.
In particular in order to test the Generating Units Availability the System Operator may
instruct it to operate at full load and if it is shut down instruct it to start and then operate
at full load.
4.3.3. Site attendance
The Grid Code -Version 02
18 of 199
A System Operator or TSP representative shall be allowed at User sites in order to carry
out tests in accordance with agreed or generic testing procedures.
4.3.4. Results
The results of a test may be derived from the monitoring of performance during the test.
4.3.5. Subcontracting of testing work
If the System Operator or TSP subcontracts testing work on a Users site, then the User
and the System Operator or TSP shall be in agreement on the selection of a suitable
subcontractor.
4.3.6. Confidentiality
Confidentiality shall be adhered to in accordance with the Market Rules or the Grid
Connection Agreement as applicable.
4.4. INVESTIGATIONS
4.4.1. Refer to Market Rules 45 for details on investigations.
19 of 199
CHAPTER 2: PLANNING
5.
5.1.
OBJECTIVES
(ii)
(e) To promote interaction between TSP and Users in respect of any proposed
development on the network or on a Users system that might impact on the
performance of the Nigeria Transmission Network or interconnection to the
network.
5.2. PURPOSE
5.2.1. The Transmission System expansion planning will cater for the connection of new
Load/Generation to the Transmission System. It will ensure that the impact of these
connections can be handled by the existing Transmission System or, if not, it will identify the
need for required expansion. The planning and development of the Transmission System
shall be in accordance with the Transmission Planning Criteria and relevant standards
applicable in Nigeria.
5.2.2. Reasons for development: The development of the Transmission System, involving
its reinforcement or extension, will occur for a number of reasons including, but not limited
to:
(a) A development on a Users System (e.g. a Distribution Company) already
connected to the Transmission System;
(b) The introduction of a new substation or the modification of an existing
substation between a Users System and the Transmission System;
20 of 199
5.3. SCOPE
5.3.1. This Planning Chapter applies to the System Operator, TSP and to Users of the
Transmission System which in this Part of the Code are:
(a) Generators;
(b) Distributors;
(c) Interconnected parties; and
(d) Directly Connected Customers.
6.
6.1.
OBJECTIVE
6.1.1. The objective of this Section is to specify the Generation and Demand Forecasts that
the System Operator has to generate for short, medium and long term planning expansion
purposes.
21 of 199
7.
7.1.
PLANNING STANDARDS
7.1.1. Transmission Planning Criteria: The System Operator, in consultation with the TSP
shall develop comprehensive Transmission Planning Criteria to guide the expansion planning
of the Transmission System. The Transmission Planning Criteria shall be approved by the
Commission.
7.1.2. The System Operator shall apply the Transmission Planning Criteria and relevant
standards in the planning and development of the Transmission System.
22 of 199
The TSP in consultation with System Operator shall perform refurbishment audits on
the existing Transmission System in order to determine the remaining useful life of the
Transmission System components.
The TSP shall produce a refurbishment plan to replace ageing and damaged Equipment.
Such plan shall take into consideration security of the Transmission System and the
impact of such activities on Users.
7.2.3. Analyse current network
The System Operator shall analyse and document the current Transmission System
adequacy.
7.2.4. Expansion alternatives
The System Operator in collaboration with the TSP shall hold workshops with
stakeholders to determine possible alternatives to address the combination of the
following inputs:
(a) Long term Demand Forecast;
(b) Refurbishment needs; and
(c) Current Transmission System performance.
7.2.5. Analyse alternatives
The System Operator in collaboration with the TSP shall evaluate the alternatives
determined pursuant to Subsection 7.2.4 for at least five, ten, fifteen and twenty years
into the future. At least the following analysis shall be performed:
(a) Load flow analysis;
(b) Fault level calculations;
(c) Stability studies;
(d) Reliability studies; and
(e) Financial analysis.
7.2.6. Based on the analysis performed pursuant to Subsection 7.2.5 the System Operator
shall develop a financially feasible least cost expansion plan, which meets the approved
Transmission Planning Criteria.
7.2.7. Long-term expansion plan report
The System Operator shall document the long-term twenty year expansion plan in a
report every year. This report shall include at least the following sections:
(a) Long-term Demand Forecast;
(b) Long-term Generation Adequacy Forecast (as required under the Market Rules);
(c) Long-term Transmission Network Adequacy Forecast;
(d) Long-term zonal Supply and Demand Margin;
23 of 199
24 of 199
infeasible. This may include, but shall not be limited to, for example, the installation of
Power System Stabilisers. Such objection shall be dealt with under the terms of the
Users Grid Connection Agreement.
7.3.5. Closing down
The User shall give the System Operator at least a 24-calendar-month notice if the User
plans for any Generating Units with registered capacity greater than 10 MW:
(a) to close down, retire or withdraw it from service; or
(b) to cease to maintain and keep it available.
The TSP shall give the System Operator at least a 24-calendar-month notice if the TSP intends
to remove any transmission circuit or transformer.
25 of 199
8.
SECTION: DATA
PLANNING
REQUIREMENTS
8.1.
INFORMATION REQUIRED
FOR
LONG
TERM
8.1.1. In order to develop the Long Term Expansion Plan, the System Operator shall use
the guidelines and data requirements indicated in Appendices 5, 6, 7 to specify the technical,
design criteria and procedures to be applied in the planning and development of the Nigeria
Transmission Network. This information shall be taken into account by Users, when
planning and developing their own Plant and Equipment connected to the network.
8.1.2. For Network Planning, User information required as stipulated in Appendices 5, 6, 7
includes data on:
(a) Standard Planning Data
(b) Detailed Planning Data
(c) Network Planning data (Forecast and Registered)
(d) Connection Planning Data
8.1.3. Standard Planning Data:
This is the data a User, whether already connected or seeking such connection to the
Transmission Network, shall provide the TSP of its Plant or Equipment at the
Connection Site, which may have impact on the performance of the Nigeria Electricity
Network. In addition each Embedded Generating Unit with capacity greater than
1.0MW connected to the Distribution Network shall provide the TSP with fault infeed
data as specified in this Code.
User shall provide the TSP a Single Line Diagram, depicting both its existing and
proposed arrangement(s) of load current carrying Equipment relating to both existing
and proposed Connection Points that can impact on the Network performance.
8.1.4. Detailed Planning Data:
These are additional detailed data, where it may apply, of the Users Plant and Equipment
required by the TSP to conduct further studies if the Users Plant and Equipment might
have serious impact on the Transmission Network or existing Users already connected to
the Network before allowing the User to connect to the Network. This data must be
provided within 30 Business Days after request.
8.1.5. Network Planning Data:
The data required in this category is in Appendix 7.
8.1.6. Connection Planning Data:
The Grid Code requires that at the time the TSP signs a Grid Connection Agreement
with the User, estimated values assumed in the Standard Planning Data for planning
purposes are confirmed or where practicable replaced by validated actual values. This
26 of 199
data is then termed Connection Planning Data. Connection Planning Data is divided
into:
(a) Forecast Data items in the Standard Planning and Detailed Planning Data that
will always be forecast data.
(b) Registered Data items in the Standard Planning and Detailed Planning Data
which upon connection to the network become fixed (subject to any subsequent
changes).
Connection Planning Data and other relevant Data held by the TSP when a new
application is made shall form the background against which such application shall be
considered and against which planning for the entire network will be based. With the
exception of other data, Users Registered Data shall be treated as non-confidential.
27 of 199
For each circuit shown on the Single Line Diagram, each User shall provide the
following details relating to that part of its Users System:
Circuit Parameters:
Rated voltage (kV)
Operating voltage (kV)
Positive phase sequence reactance
Positive phase sequence resistance
Positive phase sequence susceptance
Zero phase sequence reactance (both self and mutual)
Zero phase sequence resistance (both self and mutual)
Zero phase sequence susceptance (both self and mutual)
For each transformer shown in the Single Line Diagram, User shall provide the
following:
Rated MVA
Voltage Ratio
Winding arrangement
Positive sequence reactance (max, min, nominal tap)
Positive sequence resistance (max, min, nominal tap)
Zero sequence reactance
In addition for all interconnecting bulk transformers between the Users Transmission
Voltage System and the Users sub-Transmission System, the User shall supply the
following
Tap changer range
Tap changer step size
Tap changer type: on load or off circuit
Earthing method: direct, resistance or reactance
Impedance (if not directly earthed)
User shall supply the following about the Users Equipment installed at a Transmission
Site:
Switchgear: For all circuit breakers:o Rated voltage (kV)
28 of 199
29 of 199
(a) General
To allow the TSP and System Operator to calculate fault currents, each User is
required to provide data, calculated in accordance with best international practice as
set out in this Code.
The data should be provided from the Users System with all Generating Units
Synchronised to that Users System. The User must ensure that the pre-fault
network conditions reflect a credible System operating arrangement.
The list of data items required, in whole or part under the following provisions is set
out in Section 8.2.4. The fault currents in sub-paragraphs (a) and (b) of the data list
in Section 8.2.4 should be based on a.c. load flow that takes into account any prefault current flow across the point of connection being considered.
Where prospective short-circuit currents on Equipment owned, operated or
managed by the TSP are close to the Equipment rating, and in TSP or System
Operators reasonable opinion more accurate calculations of the prospective short
circuit currents are required, then the TSP may request additional short circuit data.
(b) Data from Directly Connected Customers
Directly Connected Customers at each Node on the Single Line Diagram provided
to the TSP shall provide motor loads and/or Embedded Generating Units and other
installations of direct current converters which do not form a DC converter Station
assuming a fault at that location, as follows:The data items listed under the following parts of 8.2.4
(a)
30 of 199
(i) to (vi)
And the data items shall be provided in accordance with the detailed provisions
of 8.2.4(b)-(f)
Data for the fault infeeds through both Unit and Station Transformers shall be
provided for the normal running arrangement when the maximum number of
Generating Units are Synchronised to the Network. Where there is an alternative
running arrangement which can give higher fault infeed through the Station
Transformers, then a separate data submission representing this condition shall be
made.
No account should be taken of the interconnection between the Station and Unit
Board, unless the normal operating arrangement within the Power Station is to have
the Station and Unit Boards interconnected within the Power Stations.
Auxiliary motor short circuit current contribution through the Station Transformers
must be represented as a combined short circuit contribution through the Station
Transformers.
8.2.4. Data Items
(a) Below is the list of data utilised in this part of the Planning Chapter. It also
contains rules on the data which generally apply:(i)
Root mean square of the symmetrical three-phase short circuit current infeed
at the instant of fault (I1).
(ii)
Root mean square of the symmetrical three-phase short circuit current after
the subtransient fault current contribution has substantially decayed (I1).
(iii)
The zero sequence source resistance and reactance values of the Users
Equipment as seen from Node on the Single Line Diagram provided under
8.2.1 (or Station Transformer high voltage terminals or Generating Unit
terminals as appropriate) consistent with the infeed described in 8.2.1
(iv)
Root mean square of the pre-fault voltage at which the maximum fault
currents were calculated;
(v)
(vi)
31 of 199
sequence resistance and reactance which would be derived from the data
provided above.
(b) In considering this data, unless the User notifies TCN accordingly at the time of
data submission, TCN will assume that the time constant of decay of the
subtransient fault current corresponding to the change from I1 to I1 (T) is
not significantly different from 40ms. The User must inform TCN if the
assumption is not correct in relation to an item of data.
(c) The value for X/R ratio must reflect the rate of decay of the d.c. component
that may be present in the fault current and hence that of the sources of the
initial fault current. All shunt elements and loads must therefore be deleted from
any system model before the X/R ratio is calculated.
(d) In producing the data, the User may use time step analysis or fixed-point-intime analysis with different impedances.
(e) If a fixed-in-time analysis with different impedances method is used, then in
relation to the data submitted under (a) (i) above, the data will be required for
time zero to give I1. The figure of 120ms is consistent with a decay time
constant T of 40ms, and if that figure is different, then the figure of 120ms
must be changed accordingly.
(f) Where a time step analysis is carried out, the X/R ratio may be calculated
directly from the rate of the d.c. component. The X/R ratio is not that given by
the phase angle of the fault current if this is based on a system calculation with
shunt loads, but from the Thevenin equivalent of the System impedance at the
instant of fault with all non-source shunts removed.
32 of 199
Data items 8.3.2(a) to (h) are required with respect to each Power Station and each
Generating Unit of each Power Station.
CCGT Units/Modules
Data item 8.3.2(g) is required with respect to each CCGT unit.
Data item 8.3.2(a) is required with respect to each CCGT Module
Data item 8.3.2(b), (c), (d) and (e) are required with respect to each CCGT Module
unless TCN informs relevant User in advance of the submission that it needs the
data item with respect to each CCGT Unit. Where any definition utilised or referred
to in relation to any of the data items does not reflect CCGT Units, such definition
shall be deemed to relate to CCGT Units for the purpose of these data items.
Hydro Schemes
Data item Appendix 5 is required with respect to each Hydro Scheme.
(a) Data Items: Registered Capacity (MW)
(b) Output Usable (MW) on a monthly basis
(c) Network Constrained Capacity (MW) which may be placed on the capacity of
an Embedded Generating Unit due to Distribution Network Operators System
in which it is embedded. Where the Embedded Generating Unit connected to a
Distribution Network via a busbar arrangement which is or is expected to be
operated in separate sections, details of the busbar arrangements and connected
circuits at the substation to which the Embedded Generating Unit is connected
must be provided to TCN to determine where the power generated by the
Embedded Generating Unit would appear on the Transmission Network.
(d) Minimum Generation (MW)
(e) MW obtainable from Users Generating Units in excess of Registered Capacity.
(f) Generating Unit Capability Chart:
(i)
(ii)
(g) A list of CCGT Units within a CCGT Module, identifying each CCGT Unit and
the CCGT Module of which it forms part, this must be unambiguous in the case
of a Range CCGT Module:
(i)
33 of 199
(ii)
for each case details of the single Grid Connection Point at which power is
provided from the Range CCGT Module shall be submitted,
(iii)
(Nothing shall prevent the busbar at the relevant point being operated in separate
sections)
(h) Expected running regime(s) at each Power Station and type of Generating Unit
(e.g. Steam Unit, Gas Turbine Unit, Combined Cycle Gas Turbine Unit, etc.)
(i) A list of Power Stations and Generating Units within a cascade Hydro Scheme,
identifying each Generating Unit and Power Station and the cascade Hydro
Scheme of which each form part unambiguously. In addition:
(i)
(ii)
where the Active Power output of a User Generating Unit is split between
more than one Transmission Network Supply Point the percentage that
would appear under normal and Outage conditions at each Transmission
Network Supply point.
Without prejudice to paragraph (g) above, identification of CCGT Units within a CCGT
Module can only be amended in accordance with the following provision:
If the CCGT Module is a Normal or Range CCGT Module, the CCGT Units
within that Module can only be amended if TCN gives its prior consent in
writing. At least 6 months notice of desire to amend the CCGT Units within such
CCGT Module must be given before the amendment can take effect.
8.3.3. Rated Parameter Data
The following information is required to facilitate an early assessment of the need for
more detailed studies:
(a) For all Users Generating Units Rated MVA, Rated MW
(b) For each synchronous Generating Unit:
(i)
(ii)
(iii)
Rated MVA
(ii)
34 of 199
35 of 199
(i)
Domestic customers
(ii)
Commercial customers
(iii)
Industrial customers
(iv)
(v)
Traction
(vi)
In addition, the total User losses and Active Energy provided by Distributed
Generating Units shall be supplied.
(ii)
In order that Users can provide the above data, the SO shall by calendar week 20,
inform Users of the Transmission Network in writing of the following, for the
current year and each of the subsequent 5 years, which will apply until replaced by
the following years notification:
(iii)
The date and time of the annual peak of the Transmission Network Demand
36 of 199
(iv)
The date and time of the annual minimum of the Transmission Network
Demand
(ii)
Rated MVA
(iii)
Rated MW
(iv)
Minimum generation MW
(v)
(vi)
(x)
(xi)
Rated MVA
(ii)
Voltage ratio
(iii)
(iv)
(v)
(vi)
37 of 199
(ii)
(iii)
(iv)
(v)
(vi)
Incremental droop values (in %) are required for each Generating Unit at six
MW loading points (MLP1 to MLP6).
(ii)
(iii)
38 of 199
(v)
(vi)
o Normal droop
o Minimum droop
+/- Hz
+/- Hz
+/- Hz
39 of 199
+/-MW
+/-MW
+/-MW
(vii) Frequency settings between which Unit load controller droop applies:
o Maximum
Hz
o Normal
Hz
o Minimum
Hz
(x)
(xi)
40 of 199
(a) Busbar layout plan(s), including dimension and geometry showing positioning
of any current and voltage transformer, through bushings, support insulators,
isolators, circuit breakers, surge arrestor etc. Electrical parameters of any
associated current and voltage transformer, stray capacitance, off wall bushings
and support insulators, and giving capacitances of circuit breakers;
(b) Electrical parameters and physical construction details of lines and cables
connected at the busbar. Electrical parameters of all Plant (e.g. transformersincluding neutral earthing impedance or zigzag transformers if any), series
reactors and shunt compensation Equipment connected at that busbar (or to
the tertiary of a transformer) or by lines or cables to the busbar;
(c) Basic insulation levels of all Equipment connected directly by lines or by cables
to the busbar;
(d) Fault levels at the lower voltage terminals of each transformer connected
directly or indirectly to the TSP Network without intermediate transformation;
and
(e) All transformers operating at 132kV and over, three or five limb cores or single
phase units to be specified and operating peak flux density at nominal voltage.
41 of 199
Systems, especially when Equipment like capacitor banks is involved. For proper
evaluation, in respect of the Connection Site, Users are required to submit current and
forecast data if not already submitted under 8.2 for any sub-Transmission System for
overhead and underground cable circuits:
Positive phase sequence resistance
Positive phase sequence reactance
Positive phase sequence susceptance
For transformers connecting the Users Subtransmission System to a lower voltage:
Rated MVA
Voltage Ratio
Positive phase sequence resistance
Positive phase sequence reactance
And at the lower voltage points of those connecting transformers:
Equivalent positive phase sequence susceptance
Connection voltage and MVAr rating of any capacitor bank and component
parameters if designed as a filter
Equivalent positive phase sequence interconnection impedance with other lower
voltage points
The minimum and maximum Demand (both MW and MVAr) that could occur
Harmonic current injection sources in Amps at the Connection voltage points
Details of traction load (e.g. connection phase pairs, continuous variation with time
etc.)
An indication of which items of Equipment may be out of service simultaneously
during planned Outage condition
8.7.3. Voltage Assessment Studies
In the course of operating the Transmission Network, the System Operator will have to
undertake voltage assessment studies on the Network to examine potential voltage
instability, Voltage Control co-ordination or calculate voltage step changes. Users are
required, to submit current and forecast data if not already submitted under section 8.2
for any Subtransmission System for overhead and underground cable circuits:
(a) For Users Subtransmission System:
Positive phase sequence resistance
Positive phase sequence reactance
42 of 199
43 of 199
(d) Pre-fault voltage magnitude at which the maximum fault currents were
calculated
(e) Positive sequence X/R ratio at the instant of fault
(f) Negative sequence resistance and reactance values of the Transmission System
seen from the Point of Connection
(g) Initial positive sequence resistance and reactance values of the two or more
sources and the linking impedances derived from a fault study constituting the
equivalent and evaluated without the User network and load
(h) Corresponding zero sequence impedance values of the equivalent
(i) The TSP or System Operator, as applicable, shall provide additional reasonable
and relevant information as requested by User.
The positive sequence X/R ratio and zero sequence impedance will correspond to
the Transmission Network only.
44 of 199
9.1.
OBJECTIVE
9.1.1. This Connection Conditions Chapter specifies the minimum technical, design and
certain operational criteria which must be complied with by the Users connected to, or
seeking connection to the Transmission Network. They also set out the procedures by which
the Transmission Service Provider (TSP) will process an application for connection to the
Transmission System, seeking to ensure compliance with these criteria as a requirement for
the granting of approval for the connection of a User to the Transmission System.
9.1.2. The provisions of the Connection Conditions shall apply to all connections to the
Transmission Network:
(a) existing at the date when this Grid Code comes into effect;
(b) existing at the date of commencement of the TSPs approval, where these dates
precede the date in (a) above; and
(c) as established or modified thereafter.
9.1.3. The Connection Conditions are designed to ensure that:
(a) No new or modified connection will impose unacceptable effects upon the
Transmission System or on any User network nor will it be subject itself to
unacceptable effects by its connection to the Transmission System.
(b) The basic rules for connection treat all Users within an equivalent category in a
non-discriminatory fashion.
9.2. PURPOSE
9.2.1. The purpose of this Connection Conditions is:
(a) to specify the technical, design, and operational criteria at each Connection
Point;
(b) to ensure that there is no undue discrimination in the application of the Grid
Code between Users or classes of User;
(c) to facilitate the use of the Transmission System by any User connected to or
seeking connection to the Transmission System, in accordance with a Grid
Connection Agreement;
(d) to define the requirements for a User seeking connection and/or for a
modification of the current connection; and
(e) to enable the TCN to develop, maintain and operate the Transmission System
in a coordinated and economic manner in compliance with its licence.
45 of 199
9.3. SCOPE
9.3.1. The Connection Conditions apply to the System Operator, TSP and to Users of the
Transmission System which in this Connection Conditions are:
(a) Generators;
(b) Distributors;
(c) Interconnected parties;
(d) Directly Connected Customers.
46 of 199
10.
SECTION:
TRANSMISSION
CHARACTERISTICS
SYSTEM
PERFORMANCE
Voltage level
Minimum Voltage
Maximum Voltage
kV (pu)
kV (pu)
330 kV
280.5 (0.85)
346.5 (1.05)
132 kV
112.2 (0.85)
145.2 (1.10)
66 kV
62.04 (0.94)
69.96 (1.06)
33 kV
31.02 (0.94)
34.98 (1.06)
11 kV
10.45 (0.95)
11.55 (1.05)
47 of 199
transient disturbances).
10.1.6. Due to the effect of travelling waves on the Transmission Network as a result of
atmospheric disturbances or the switching of long transmission lines, transient over-voltage
can occur at certain Node points of the network. The insulation level of all Apparatus must
be coordinated to take account of transient over-voltages and sensitive User Equipment, such
as computer and other solid state Equipment, which should be suitably isolated from this
effect.
10.1.7. The transient over-voltage during lightning strikes is typically experienced over a
voltage range of 20% of nominal voltage. Connection Points close to a network lightning
strike will experience voltages higher than this.
10.1.8. Unless otherwise agreed by the TSP, the basic insulation value (BIL) for User
Apparatus shall be as follows:
(a) For the 330 kV system, the BIL is 1050 kV.
(b) For the 132 kV system, the BIL is 650 kV.
48 of 199
(b) IEC/TR3 61000-3-6 ed2.0 (2008) Assessment of emission limits for distorting
loads in MV and HV power systems.
10.2.5. In general, the maximum total levels of harmonic distortion on the System under
Normal Operation conditions, planned outages and fault outage conditions (unless during
System Stress) shall not exceed following values:
(a) 330 kV a Total Harmonic Distortion of 1.5% with no individual harmonic
greater than 1%
(b) 132 kV a Total Harmonic Distortion of 2% with no individual harmonic greater
than 1.5%.
10.2.6. Under Normal Operation, the maximum negative phase sequence component of the
phase voltage of the Transmission System should remain below 1%.
10.2.7. Under planned outage conditions, infrequent short duration peaks with a maximum
value of 2% are permitted for phase unbalance.
49 of 199
11.
50 of 199
11.1.5. Planning data: Transmission System planning data, together with other data held by
the TSP relating to the Transmission System shall form the basis from which new
applications by any User shall be considered and from which planning of the Transmission
System shall be undertaken. Transmission System planning data shall not be treated as
confidential to the extent that the TSP is obliged:
(a) To use it in the preparation of the forecast;
(b) To use it when considering and/or advising other Users;
(c) To use it for the SO planning purposes; and
(d) Under the terms of a Grid Connection Agreement to pass it on as part of
system information on the Power System.
11.1.6. Type of data: Transmission System planning data is divided into the following type of
data:
(a) Which will always be forecast, known as forecast data;
(b) Which upon connection becomes fixed, known as Registered Information; and
(c) Which relate to Plant, Equipment or Apparatus for the purposes of the Plant
concerned as at the date of submission, known as Registered Information, but
which for the ten succeeding years shall be an estimate of what is expected,
known as estimated Registered Information.
11.1.7. Actual data: Users shall supply the TSP with all outstanding data as stipulated in
Appendixes 6 and 7 not later than the operational date if not previously requested by the
TSP. This shall include confirming any estimated values assumed for planning purposes or,
where practical, replacing them by validated actual values and by updated estimates for the
future and by updating forecasts for forecast data items.
11.1.8. Additional information: The TSP shall request that a User supply additional
information, as the TSP deems necessary to verify the accuracy of the data received, if in the
opinion of the TSP it is incorrect.
11.1.9. Tests for data verification: The TSP or the System Operator shall request that the
User carry out specific tests, at the Users expense, to verify the data, if it maintains that the
additional information is insufficient to verify the accuracy of the original. Where such a test
or tests are requested, they shall be subject to the provisions of the relevant Section of the
Grid Code.
11.1.10.Costs for tests:
(a) The TSP shall carry all costs incurred as a result of the test or tests in the event
that the initial data as submitted by the User is verified by the test or tests to be
correct.
(b) The User shall carry all costs incurred as a result of the test or tests in the event
that the data as submitted by the User is verified by the test or tests to be
incorrect. If the TSP has to redo or perform additional system studies then the
51 of 199
User shall also bear the costs reasonably incurred as a result of the said
additional work.
The size of the Generating Units and the number of Generating Units
comprised in the potential Users System;
(ii)
(iii)
(iv)
52 of 199
(c) Directly Connected Customers voltage level: The Transmission System voltage
level at which a Directly Connected Customers shall be connected to the
Transmission System shall depend upon, but shall not be limited to the
following:
(i)
(ii)
(iii)
(iv)
(d) Distribution voltage level: The Transmission System voltage level at which a
Distributor shall be connected to the Transmission System shall depend upon
but shall not be limited to the following:
(i)
(ii)
(iii)
(iv)
(v)
(e) Method of connection: The method of connection used may exceed the
relevant standards where the User requires it. In this case the TSP shall accept
this provided:
(i)
(ii)
the User pays all relevant costs associated with this higher standard.
11.2.7. After evaluating the application submitted by the User, the TSP shall inform the User
whether the proposed application is acceptable or not. The TSP may disapprove an
application for connection or a modification of an existing connection to the Transmission
System only if it is determined through System Studies that the proposed connection or
modification does not fulfil the technical requirements or results in the degradation of the
Transmission System.
11.2.8. If the application of the User is not acceptable:
(a) The TSP shall notify the User as to why its application is not acceptable.
(b) The TSP shall include in its notification details of the amendments required to
make the Users application acceptable to the TSP.
(c) The TSP shall immediately report any rejected application to the NERC.
11.2.9. Offer detail: In case the application is accepted, the TSP shall submit to the User an
offer to connect to the Transmission System. This Connection Offer shall include, but shall
not be limited to the following:
53 of 199
(a) Details of how the connection shall be made, including details of the Plant and
Apparatus that shall be required to implement the connection;
(b) A description of any modification that the applicant User shall be required to
pay for;
(c) An indication of the connection date and the operational date; and
(d) An estimate of the charges for connection.
11.2.10.Acceptance of the offer: A connection offer shall provide that the applicant User
accepts it within the period stated in the offer, which shall never be less than forty five (45)
days, after which the offer shall automatically lapse. Acceptance of the offer shall be effected
by execution of the Grid Connection Agreement by both parties, which renders the TSP
works relating to that User development committed and shall bind both parties in accordance
with its terms. The User shall supply the data pertaining to the Users development within
sixty (60) days of acceptance of the connection offer.
11.2.11.Committed planning data: Once a connection offer has been accepted, all data
supplied in the application form and any other data submitted along with the application
form, shall be treated as committed project planning data.
54 of 199
55 of 199
12.
PLANT
AND
12.1. GENERAL
12.1.1. At the Connection Point all Users Plant and Apparatus shall meet acceptable
technical design and operational criteria. Detailed information relating to a particular
connection will be made available by the TSP on request by the User. Such information will
include, but not be limited to, the following:
(a) Load flow studies.
(b) Short circuit studies.
(c) Power System stability analysis.
(d) Annual/monthly load curves.
(e) Line Forced Outage rates, for the network associated with the proposed
Connection Point.
(f) Telecommunications network associated with the proposed Connection Point.
12.1.2. All Plant and Apparatus connected to or proposed for connection to the
Transmission System are required to meet relevant current international and pan-European
technical standards, such as IEC, ISO, and EN.
(a) Furthermore, Plant and Apparatus shall be designed, manufactured and tested
in accordance with IEC or equivalent approved standard, and quality assurance
requirement of ISO 9001 or equivalent.
(b) The User shall ensure that the specification of Plant and Apparatus at the
Connection Point shall be such to permit operation within the applicable safety
procedures agreed between the User and SO as required in Section 25.
56 of 199
12.2.3. Requirements: The technical facilities provided shall adhere to the following
minimum requirements:
(a) Double bit status indications measurement;
(b) Three phase Active Power and Reactive Power measurement;
(c) Single-phase Voltage measurement; and
(d) Support open SCADA protocols to allow interface with other vendors
Equipment.
12.2.4. Recording facilities: Transient recording facilities shall be installed on the
Interconnecting circuits between different parties networks. These facilities shall be
synchronised to the Universal Time Coordinated reference time (UTC time).
12.2.5. Power interchange: Each Control Centre responsible for a Control Area shall provide
the Facilities to schedule the power interchange with other Control Areas effectively on a
frequent and continuous basis.
57 of 199
58 of 199
59 of 199
(ii)
(iii)
60 of 199
control loop shall be such that under isolated operating conditions, the damping coefficient
shall be above 0.25 for the entire operating range.
The Automatic Voltage Regulator (AVR) shall have no negative impact on Generating
Unit oscillation damping. If required, the appropriate Power System Stabiliser (PSS) shall
be provided. Control principle, parameter setting and switch on/off logic shall be
coordinated with the System Operator and specified in the Grid Connection Agreement.
12.6.4. Each Generating Unit shall be required to withstand, without tripping, the negative
phase sequence loading experienced during clearance of a close-up phase-to-phase fault by
System back-up protection on the Transmission Network.
12.6.5. The System Frequency could rise to 51.5 Hz or up to 51.75Hz for no more than 15
seconds or fall to 47.5 Hz and Generating Units must continue to operate within this
Frequency range unless the System Operator has agreed to any Frequency-level relays and/or
rate-of-change-of-Frequency relays which shall trip such Generating Units within this
Frequency range, as stated in the Grid Connection Agreement.
12.6.6. Generators shall be responsible for protecting all their Generating Units against
damage should System Frequency variations exceed 51.75 Hz or over 51.5 Hz for up to 15
seconds or go below 47.5 Hz or such limits agreed with the System Operator. In the event
that such variations occur, the Generator shall disconnect the Generating Unit for reasons of
safety of personnel, Apparatus, and/or Plant.
Protection Arrangements
12.6.7. Each connection between a Generating Unit and the Transmission Network must be
controlled by a circuit breaker capable of interrupting the maximum short circuit current at
the point of connection as determined by the System Operator and/or the TSP.
12.6.8. The System Operator and/or the TSP shall provide each Generator at each
Connection Point where its Power Station is connected with the appropriate voltage signals
to enable the Generator to obtain the necessary information to synchronise its Generating
Units to the Power System.
12.6.9. Electrical protection of the Generating Unit shall take precedence over operational
controls (e.g. Voltage Controllers, excitation Equipment) and the Generating Unit shall
disconnect from the network should unacceptable Operational States arise as a result of
failure of the operational controls. This shall apply in particular when spontaneous faults
occur (e.g. earth faults, short-circuits).
12.6.10.The settings for the electrical protection Equipment must be agreed upon between
the TSP and the Generator, and reflected in the Grid Connection Agreement. The possibility
of protection and switchgear failures must also be taken into account. Consideration must be
given to the following points:
(a) External short-circuits
(b) Load unbalance
(c) Stator and rotor overload
(d) Under-excitation
The Grid Code -Version 02
61 of 199
Back-up protection.
12.6.11.To cater for the possibility that the indicated fault clearance times are not met as a
result of failure in the operation of the main protection systems, the Generator shall provide
the necessary back up protection. The TSP shall also provide back-up protection which shall
be coordinated to provide discrimination and protect Equipment from damage.
12.6.12.Where System requirements dictate, the TSP and/or the System Operator shall
specify in the Grid Connection Agreement a requirement for Generators to fit pole slipping
protection on their Generating Units.
Work on Protection Apparatus at the Connection Point
12.6.13.No busbar protection, circuit breaker fail protection, AC or DC wiring on the
Interconnection Facilities may be worked upon or altered:
a) by the TSP personnel in the absence of a representative from the Generator; and
b) by Generator personnel in the absence of a representative from the TSP.
62 of 199
CHAPTER 4: OPERATION
13.
13.1. OBJECTIVE
13.1.1. The general objective of this part of the Chapter is to specify the required System
Operator and User actions in order to ensure that the Power System in Nigeria is operated in
a way to maintain adequate and safe transportation of Energy, plus System security at all
times.
13.1.2. This adequate and secure operation is achieved through:
(a) Adequate and economic ancillary services:
(i)
(ii)
(iii)
(b) Outline the general restoration strategy adopted by the System Operator in the
event of a Partial or Total Shutdown (Section 18)
(c) Specifying procedures for Operational Planning in the short to medium term
(Section 19)
(d) Provision of information regarding risks or events in the Transmission System
(Section 20)
(e) Determining the actions that the System Operator shall undertake to perform
the economic dispatch, and to provide Generators with running orders for the
Dispatch Day. (Section 21)
(f) Defining the requirements for notification of Generation Outages to the System
Operator (Section 22).
(g) Defining the reliability criteria that the System Operator and the TSP have to
adhere to in operating and developing the Transmission System (Section 23).
(h) Establishing central co-ordination and control of System Tests required by the
System Operator, TSP or Users (Section 24)
(i) Setting safety procedures for works to be carried out at the interface between
User networks and the Transmission Network (Section 25)
13.2. SCOPE
13.2.1. The Operation Chapter applies to the System Operator, TSP and Users of the
Transmission System which are:
(a) Generators;
63 of 199
(b) Distributors;
(c) Interconnected parties;
(d) Directly Connected Customers.
64 of 199
14.
14.1. OBJECTIVE
14.1.1. The objective of this Section is to specify the required System Operator and User
actions in order to ensure that the Power System in Nigeria is operated in such a way as to
maintain adequate and safe transportation of Energy, plus System security at all times.
14.2. GENERAL
14.2.1. The System Operator shall carry out Power System Planning, Switching and Control
Actions, which may from time to time affect User operations or the security of supply to
Users.
(a) Power System Planning is required for technical and design criteria and
procedures to be applied by the System Operator for adequate and secure
development of the Transmission Network by the TSP for the benefit of all
Users.
(b) Network switching is required to implement the Transmission Outage
scheduling programme, routine operation of the Transmission Network and in
response to emergency and fault situations on the Transmission Network.
(c) Additionally, network switching may occur automatically and without advance
warning due to operation of protection Equipment in isolating or clearing faults
on the Transmission System or on Users Apparatus that is connected to the
Transmission System.
14.2.2. All network Control Actions carried out on the Transmission System have the
potential to affect Users. To attempt to inform Users of every Control Action is not
practicable and in most cases the information will not be of value to the User, as the User will
not take or cause any specific action as a result of receipt of the information.
(a) It may not always be possible for the System Operator to inform Users in
advance of the switching or other Control Actions. This would be the case
when the System Operator needs to carry out urgent switching or other network
Control Actions resulting from a Power System condition or fault. The System
Operator shall endeavour to inform Users where time permits, but this shall not
delay timely implementation of Control Actions as required.
(b) In the event of a Power System fault or protection operation or other automatic
operation, it will not be possible for the System Operator to invoke standing
procedures prior to the occurrence of the Control Action.
65 of 199
66 of 199
rectified to normal, the System Operator shall inform Users of the occurrence of the
actions.
Generators shall promptly inform System Operator of the tripping of a Generating Unit,
with reasons, in accordance with the guidelines in Section 21 of the Grid Code and other
operational event/incident reporting procedures operating at the time. The System
Operator shall keep a written log of all such tripping, including the reasons for the
purpose of demonstrating the effect on system performance and identifying the need for
remedial measures. The Generators shall submit a detailed report of their Generating
Unit tripping to the System Operator every month.
14.5.2. Duration of condition
The System Operator shall also inform Users as to the likely duration of the condition
and shall update this prognosis as appropriate. Additionally, the System Operator shall
inform Users when the condition has ended.
67 of 199
The Generator shall submit a written report to the System Operator within
48 hours of the cause of any unit trip that could in future cause is reasonably
anticipated to result in heightened risk of tripping of that unit or others,
identifying the root causes of the incident and the corrective actions taken.
(ii)
In addition, provide a full report as per this Grid Code (in particular item
(e)(ii) below).
(c) Off-takers, shall report the loss of major loads (>10MW) to the System
Operator within 15 minutes of the event occurring. Notification of intent to
reconnect such loads shall be given at least 30 minutes in advance.
(d) Incidents on the Power System involving sabotage or suspected sabotage, as
well as threats of sabotage, shall be reported to the System Operator.
The Grid Code -Version 02
68 of 199
(e) The System Operator shall investigate any incident that materially affected the
quality of service to a User. These include interruptions of supply,
disconnections, under or over voltage or Frequency incidents, quality of supply
contraventions, etc.
(i)
a preliminary incident report shall be available after three working days and a
final report within three months.
(ii)
(iii)
the System Operator shall make the report available to any requesting User
within the confidentiality constraints, and submit it to the NERC.
(f) Any User shall have a right to request an independent audit of the report, at its
own cost. If these audit findings disagree with the report, the User may follow
the dispute resolution mechanism. If the audit agrees with the report, the report
recommendations shall stand.
(g) User shall implement NERC-approved recommendations to reduce the
likelihood of a recurrence of the incident within the time frames specified.
69 of 199
15.
SECTION:
RESERVE
FREQUENCY
CONTROL
AND
OPERATING
15.1. OBJECTIVE
15.1.1. The objectives of this Section are:
(a) To specify the System Operator requirements to ensure that adequate
Frequency Control capability is provided on the Transmission System to enable
operational Frequency Control by the System Operator, so as to achieve the
applicable limits, and
(b) To specify the Operating Reserve and Reliability Must-run requirements the
System Operator has to adhere to in order to achieve the mentioned Frequency
Control and adequate system reliability.
15.2. GENERAL
15.2.1. In order to maintain the security and integrity of the Transmission System it is
necessary that the System Operator operate the Transmission System and Dispatch it in such
a manner in order to provide adequate Frequency Control so as to achieve operation within
applicable Frequency limits at all times. Frequency Control can be obtained by using primary
or secondary Reserve.
15.2.2. Depending on network condition, Generating Units will be required to move to or
from Frequency Sensitive mode in combinations agreed in the relevant Ancillary Services
Agreement or as instructed by the System Operator.
15.2.3. In order to achieve this Control, the System Operator shall operate the System with
adequate Operating Reserve. Operating Reserve is additional Active Power output provided
from Generating Units, or a reduction in consumer Demand, which must be realisable in
real-time operation to contain and correct any potential Power System Frequency deviation to
an acceptable level.
Operating Reserve is required to secure capacity that will be available for reliable and
secure balancing of supply and demand.
70 of 199
71 of 199
(ii)
(b)
15.5.3. Slow Reserve: Slow Reserve is the component of the Operating Reserve not
connected to the Transmission System but capable of serving demand within a specified time.
Slow Reserve is used to restore Quick Reserve when required. Slow Reserve shall consist of
Hot Standby and Cold Standby.
(a) Hot Standby: Hot Standby is a condition of readiness in relation to any
Generating Unit that is declared available, where it is ready to be synchronised
and attain an instructed load within 30 minutes, and subsequently maintain such
load continuously.
(b) Cold Standby: Cold Standby is a condition of readiness in relation to any
Generating Unit that is declared available, to start, synchronise and attain target
loading within a pre-defined period of time, typically up to 14 hours.
72 of 199
(d) The predicted Frequency drop on loss of the Largest Credible Trip as
determined through simulation using a dynamic model of the Power System;
(e) Constraints imposed by agreements in place with externally interconnected
parties;
(f) Historical Availability and Reliability performance of individual Generating
Units;
(g) Notified risk to the Reliability of individual Generating Units; and
(h) Demand Forecasting uncertainties.
15.6.3. Unless proved to be technically impossible, or the economic burden imposed on the
dispatch cost excessive, the Operating Reserve Policy shall be developed under following
premises:
(a) Primary Reserve: It shall be ensured that enough primary reserve is available to
maintain system Frequency within acceptable limits, following a contingency
such as a unit trip or a sudden surge in load, without any Under-Frequency
Load Shedding.
The Frequency shall stabilize above 49.00Hz following the Largest Credible Trip.
(b) Secondary Reserve: Sufficient Secondary Reserve shall be carried to ensure
that any decay in Primary Reserve is replaced.
(c) The minimum Operating Reserve shall be sufficient to cover 150% of capacity
of the Largest Credible Trip.
(d) Operating Reserve mix: The mix of Operating Reserve shall be as follows:
(i)
(ii)
(iii)
At least 50% of these Operating Reserves shall be spinning and the other
50% shall be Quick Reserve;
(e) Operating Reserve shall be dispersed throughout the system and shall consider
the effective use of capacity in an emergency, time required to be effective,
transmission limitations, and local area requirements.
15.6.4. The System Operator shall, in consultation with the other Users, review probable
contingencies frequently to determine the adequacy of Operating Reserve Policy, maintain it
permanently under review. On an annual basis, it shall submit to the NERC an amended
version for approval, taking into consideration the previous years Frequency recovery
performance.
The Grid Code -Version 02
73 of 199
15.6.5. Record keeping: The System Operator shall keep records of significant alterations to
the Operating Reserve policy.
74 of 199
75 of 199
(i)
The AGC shall act as a secondary Frequency Control device and shall raise
or lower the Generating Unit output according to an economic analysis of
the participating Generating Units. This economic analysis takes the
registered operating characteristics of Generating Units, Generator
Nominations, Transmission System losses and Availability of Plant into
account to determine optimal Generating Unit output.
(ii)
The System Operator shall ensure the balance between Generation and the
Load. The System Operator shall achieve this by the deployment of
secondary Frequency Control (AGC);
(iii)
(iv)
On the basis of an annual Dispatch Schedule, the System Operator and the
corresponding Generators shall enter into Bilateral Agreements for operation
under secondary Frequency Control (providing of Secondary Reserve);
(v)
Based upon these conditions and the Dispatch Schedule, the System
Operator shall decide which Generators to involve in secondary Frequency
Control (providing Secondary Reserve) and at what time intervals, in
accordance with the principle of minimum costs and Availability;
(vi)
The AGC shall be managed via the SCADA system at the National Control
Centre.
76 of 199
16.
16.1. OBJECTIVE
16.1.1. The objective for Voltage Control is to achieve a healthy voltage profile for the
Power System.
16.2. GENERAL
16.2.1. The System Operator shall endeavour to maintain sufficient Availability of dynamic
and static Reactive Power in order to maintain the Power System voltages at Connection
Points within the levels specified, at all times.
16.2.2. The System Operator should use the effects of Power System capacitance in
controlling the Power System voltage.
16.2.3. The System Operator can operate the Power System voltage towards the upper
portion of the allowable control range at times of high Reactive Power Demand (normally
times of high Active Power Demand).
16.2.4. The System Operator can operate the Transmission System voltage towards the lower
portion of the allowable control range at times of low Reactive Power Demand (normally
times of low Active Power Demand).
77 of 199
16.4.2. Procedures: The System Operator shall determine and modify, as appropriate,
general procedures for controlling voltages on the Power System. The procedures shall be
formulated considering the relevant economics of Power System operation and Power
System Reliability. In determining these procedures, the System Operator shall consider daily,
weekly and seasonal factors. The System Operator shall determine:
(a) suitable target voltages in order to limit/control the effect of Transmission
Capacitance;
(b) best utilisation of dedicated Voltage Control facilities; and
(c) Reactive Power dynamic reserve requirements.
78 of 199
(c) Load shedding may be used to prevent Voltages from contravening Low
Voltage limits at Connection Points.
where the action is essential for the safety of personnel and/or Plant;
(ii)
(iii)
where the restriction has been agreed upon between System Operator and
the Generator in advance.
79 of 199
(i)
The minimum amount of reactive power each Generating Unit shall be able
to produce, if required by the System Operator, is defined by the following
limits:
a.i.1)
a.i.2)
The Generating Unit shall be able to deliver this reactive power within the whole
range of generated active power (from technical minimum to rated capacity)
(ii)
(iii)
AVR restriction: While the reactive power produced by the Generating Unit
is within the limits indicated in Section 12 of the Connection Conditions the
Generator may only disable or restrict AVR action-
a.iii.1)
where the action is essential for the safety of personnel and/or Plant;
a.iii.2)
a.iii.3)
where the restriction has been agreed upon between System Operator
and the Generator in advance.
(iv)
The Off-takers shall maintain a Power Factor not less than 0.95 at the
Connection Point.
80 of 199
17.
17.1. OBJECTIVE
17.1.1. The objective of this Section is to stipulate the Black Start requirements the System
Operator has to cater for.
17.2. GENERAL
17.2.1. Generating Units have to be identified that can start on own resources from a total
De-energised state which may be due to emergency condition declared by System Operator as
in Section 18 or Appendix 8 of this Code. Such Generating Units may be necessary to start
other Generating Units and revive the Power System following a Total Shutdown. The
necessary contracts must be executed between the System Operator and Generators to
provide Black Start Capability and appropriate tests must be done on a regular basis to ensure
that the Power System can be reactivated following such an extreme emergency situation.
17.4. REQUIREMENTS
17.4.1. The System Operator shall set out the requirements for Black Start Stations to enable
recovery of the Power System from a Partial Shutdown or Total Shutdown.
17.4.2. Requirements for Black Start Stations:
(a) Black Start Stations shall have the ability for at least one of its Generating Units
to start-up from shutdown and to energise a part of the total system, or be
Synchronised to the System.
(b) The Black Start Stations shall perform Black Start upon instruction from the
System Operator, without an external electrical power supply.
(c) The Black Start Power Station shall inform the System Operator if during the
Demand restoration process any Black Start unit cannot, because of the
Demand being experienced, keep within its safe operating parameters.
(d) The System Operator shall where possible, either instruct Demand to be altered
or will re-configure the Transmission System or will instruct a User to reThe Grid Code -Version 02
81 of 199
configure its system in order to alleviate the problem being experienced by the
Generator.
(e) However, the System Operator may decide to keep a Generating Unit in a
Power Station operating outside its safe operating parameters, for a limited
period of time. The System Operator shall accept that the Generator operator
may change Generation on that unit if it believes it is necessary for safety
reasons. The Generator shall inform the System Operator as soon as reasonably
practical if such a change is made without prior notice.
82 of 199
18.
18.1. OBJECTIVE
18.1.1. The objective of this Section is to outline the general restoration strategy, which shall
be adopted by the System Operator in the event of a Partial or Total Shutdown of the
Transmission System, emergency condition or that indicated in Appendix 8. This includes the
need for a restoration plan and an Under-Frequency Load Shedding scheme.
18.2. GENERAL
18.2.1. The Operating States of a Power System are classified into five Operating States,
namely normal, alert, emergency, extreme and restorative.
18.2.2. The different Operating States can be defined as follows:
(a) Normal Operating State
The Power System variables, voltage and lines, are within the normal range and no
Equipment is being overloaded. The Power System operates in a secure manner and
can withstand any single contingency without violating any of the limits.
The Power System should be in this mode of operation for most of the time. The
System Operator shall endeavour to operate the Power System such that it is in the
normal Operating State.
(b) Alert Operating State
The Power System will move into this state of operation once the security level falls
below a certain limit. This could also be due to the possibility of a disturbance due
to bad weather conditions, such as a severe storm.
The Power System variables, voltage and lines, are within acceptable operating range
and limits. However, the Power System is weakened and the next contingency could
cause an overload or voltage violation.
(c) Emergency Operating State
The Power System will move into this state of operation if a severe disturbance
occurs or under a civil emergency situation as in Appendix 8, when the system is in
the alert operating state. Some of the busbar voltages will be low and/or Equipment
will exceed its short-term emergency ratings. The system will still be intact and can
return to the alert Operating State once the emergency actions have been initiated,
such as fault clearing, excitation control, generating tripping and Load curtailment.
(d) Extreme Operating State
The Power System will move into this state of operation once the emergency actions
have failed to be effective. This will result in a possible cascade tripping of the
transmission lines and Generating Units and a possible Shutdown of a part of the
Power System. The Power System can then be saved by the initiation of Under
The Grid Code -Version 02
83 of 199
84 of 199
18.3.6. The System Operator shall set the requirements for automatic and manual load
shedding. Users shall make available loads and schemes to comply with these requirements.
18.3.7. The System Operator, in consultation with the TSP shall be responsible for
determining all operational limits on the Transmission Network, updating these periodically
and making these available to the Users.
18.3.8. The System Operator shall conduct load flow studies regularly (at least monthly) to
determine the effect that various component failures would have on the reliability of the
Transmission Network. At the request of the System Operator, Distribution Network
Operators shall perform related load flow studies on their part of the network and make the
results available to the System Operator.
18.3.9. Procedures and facilities
System Operator shall ensure that the necessary procedures and facilities are in place to
support quick and secure re-establishment of the Shutdown parts and restore supply to Users.
18.3.10.Safety
The System Operator shall De-energise certain Plant in order to provide for safe and secure
operation of the Transmission System within prescribed standards, including:
(a) During a System Emergency Condition;
(b) During Power System restoration; and
(c) Following the issue of a declaration of being in an Extreme Operating State.
85 of 199
The System Operator shall, in consultation with all stakeholders, issue an Extreme Operating
State declaration at least once each year. This will be a test and not a real situation. The
purpose of this would be to ensure proper training of all personnel involved. The
stakeholders shall be notified in advance of the content of the tests and a date and time for
execution of the tests shall be agreed. The stakeholders must, acting in accordance with Good
Utility Practice, co-operate with any such testing.
86 of 199
18.6.4. The System Operator shall ensure that the emergency co-ordination facility is
equipped with up to date Single Line Diagrams, operating diagrams and operating procedures
at least once a year.
87 of 199
capacitor tripping, and other automatic actions which occur during abnormal Frequency or
voltage conditions.
18.7.4. Testing
Under Frequency Load shedding relays shall be tested at six-monthly intervals to ensure that
they are still connected and in good working order.
18.7.5. Manual Load shedding
Should the Under-Frequency Load Shedding not be sufficient, the System Operator shall
shed Load manually if the System can still be saved from a Total Shutdown.
18.7.6. Re-Synchronisation
The System Operator shall shed additional Load manually before re-Synchronising the
different islands after the Power System separates into various islands and there is insufficient
generating capacity in the islands to restore the Power System Frequency following UnderFrequency Load Shedding.
88 of 199
19.
19.1. OBJECTIVE
19.1.1. The objective of Operational Planning is to specify technical, design, information
exchange and procedures to be applied by the System Operator to ensure proper operation of
the Transmission System in the short to medium term. This also includes the studying and
documentation of short and medium-term events. It shall ensure that the System Operator is
prepared for short to medium term situations and emergencies. This Section describes the
different technical activities necessary to ensure that Users and System Operator are well
informed of the status of the System during maintenance, planned Outage and following a
Forced Outage condition.
19.2. GENERAL
19.2.1. The following activities shall be performed by the System Operator to enable it
operationally plan for a stable Power System at all times:
(a) Create a data base for:
(i)
Steady state;
(ii)
(iii)
Dynamic data.
(ii)
(c) Perform load flow studies for all cases involved, checking the power flow and
the voltage profile for the existing network;
(d) Calculate maximum and minimum fault levels at all substations on at least an
annual basis;
(e) Use the daily Demand Forecast to conduct n-1 / n-2 contingency studies to
prepare for the next operational day, or any other situation in the near future.
All the maintenance plans shall be studied to see the feasibility of that Outage in
the next day or near future. This shall prepare the National Control Centre for
any unexpected conditions that could occur. This is important considering any
maintenance on major transmission lines that could be planned for the next day;
(f) Conduct contingency studies for 2 years in advance and prepare a strategy of
how to achieve the Reliability indices pursuant to Subsection 23.4
(g) The results of the contingency studies shall be documented in a contingency
plan. This plan shall be needed when the remaining lines overload or have
severe voltage depression. The contingency plan shall be studied to arrive at a
89 of 199
viable operational solution. The primary aim shall be to maintain supply to the
Users;
(h) In order to prepare the contingency plan, the thermal rating of all the links
should be determined for the relevant areas of the network. It should also
include the transformer rating and breaker breaking capacity. It is important to
have information of both the 75C and 90C thermal limits of all the power
Equipment involved;
(i) The results shall be in the form of a load flow diagram, and the contingency
plan shall consist of the load flow diagram and detailed switching instructions
and precautions that should be taken prior to any operational activity;
(j) The dynamic data shall be used to perform studies related to voltage collapse
that could occur during certain contingencies. It shall also be used to see the
dynamic behaviour of the system during certain major contingencies. It can
also be used to check the optimum ARC dead time for the circuits. Some of
these times can be optimised and subsequently lead to the improvement of the
Quality of Supply to Users;
(k) Voltage collapse studies should also be performed using steady-state data. This
shall be necessary to determine the maximum transfer across a part of network.
These studies shall indicate at what stage more expansion would be needed
given the rate of consumer Load growth in a particular area;
(l) The System Operators Operational Planning staff shall ensure that the
contingency plan documentation is in the control room and that these
documents are always updated to the latest expansion of the Power System; and
(m) System Operators Operational Planning staff shall study the implementation of
the Under-Frequency Load Shedding scheme. These studies shall be updated on
at least an annual basis and the new settings and requirements shall be given to
the TSP to implement as soon as possible.
90 of 199
The System Operator shall utilise the appropriate staff to implement operational
plans and to assure that the System is operated reliably and securely.
(d) Information and training
The System Operator shall also ensure that the National Control Centre and the
relevant Control Centre staff are well informed and trained to use this information.
(e) Reviews
The Operational Planning staff of the System Operator shall be responsible for
reviewing the Under-Frequency Load Shedding scheme, as defined in Subsection
18.7.2 on at least an annual basis.
19.3.2. The Operational Planning staff shall be experienced in the operation and planning of
a Power System. The required areas of expertise are the following:
(a) Technical Operational Studies
(i)
Load flows;
(ii)
Contingency studies;
(iii)
Under-Frequency studies
(iv)
(v)
Voltage collapse;
(vi)
(ii)
(iii)
91 of 199
Users shall supply the following information in writing to the System Operator annually in
advance:
(a) Typical monthly maximum and minimum Demand values of the anticipated
Demand per Connection Point over a year;
19.4.3. Generating Units
Users shall supply typical Active and Reactive Power profiles for their operation, and
Availability as appropriate, for Generating Units under their control and for Embedded
Generating Units where the total registered capacity of Generating Units on a single site
exceeds 5MW. The method for submitting these data schedules for such Generating Units
shall be the same as provided for in the Market Rules or other agreements with the SO.
19.4.4. On the last Business Day of every calendar week, Users shall provide the System
Operator with the data requested below (except Demand solely related to Power Station
Auxiliary Plant when fed in accordance with pre-agreed feeding arrangements), for the
following 14 days after the submission.
19.4.5. Day-ahead Demand and Availability Forecast
(a) Demand Forecast factors
The System Operator shall take the following factors into account when conducting
Day-ahead Demand Forecasting:
(i)
(ii)
(iii)
The incidence of major national and local events or activities that are known
to the System Operator in advance;
(iv)
(v)
(vi)
92 of 199
Users shall supply the following information in writing to the System Operator 14
days in advance:
(i)
(d) Demand Off-takers shall supply Active and Reactive Power demand profiles by
8:00 hours on the Pre-Dispatch Day of the amount and duration of anticipated
Demand Control per Connection Point that may result in a Demand change of
1 MW or more during each Dispatch Period of the Dispatch Day.
(e) Generating Units
Users shall supply typical Active and Reactive Power profiles for their operation,
and Availability as appropriate, of Generating Units under their control and those
Embedded Generating Units where the total registered capacity of Generating Units
on a single site exceeds 5MW. The method for submitting these data schedules for
such Generating Units shall be the same as provided for in the Market Rules (or by
such electronic data transmission facilities as have been agreed upon with the
System Operator) or other agreements with the SO.
19.6. CONNECTIONS
19.6.1. New connections
Users shall provide to the System Operator written information pertaining to new
connections or additional Generation or Demand greater than 1 MW immediately when
this information becomes available. This information shall include:
(a) Anticipated connection date;
(b) Location of connection;
(c) Size of consumers category of connection (e.g. residential, industrial etc.); and
(d) The typical profiles of the anticipated Generation or Demand on half hourly
basis for defined categories of day type as determined by the System Operator;
The Grid Code -Version 02
93 of 199
19.6.2. Disconnection
Users shall provide to the System Operator written information pertaining to
disconnection of existing Generation or Demand immediately and not more than 12
Calendar weeks when this information becomes available. This information shall include:
(a) Anticipated disconnection date;
(b) Location of connection;
(c) Size of connection; and
(d) The revised typical profiles of the anticipated Generation or Demand on a half
hourly basis at the Connection Point for defined categories of day type as
determined by the System Operator;
94 of 199
20.
20.1. OBJECTIVE
20.1.1. The objective of this Section is to provide for the exchange of information so that the
implications of an Operational error and/or Power System Event can be considered. The
possible risks must be assessed and appropriate action taken by the relevant party in order to
assist in maintaining a secure Power System. The correct information needs to be identified
and communicated to the correct structures in the Nigeria ESI.
20.2. GENERAL
20.2.1. This Section sets out the requirements for the exchange of information particularly in
relation to Operations and/or events on the Power System, which have had or shall have an
operational effect, and thereby have become Power System incidents (being an Abnormal
Operation or an Event:
(a) On the Transmission System in the case of an Abnormal Operation and/or
Event occurring on a Users system; and
(b) On a Users system in the case of an Abnormal Operation and/or Event
occurring on the Transmission System.
20.2.2. The System Operator shall report any Event or Abnormal Operation on the
Transmission System to all Users. This notification is expected to report what shall happen or
what has happened on the Power System.
20.2.3. The System Operator shall have information available for system incident analyses by
means of:
(a) The System Operators SCADA system(s) and other data collection systems;
and
(b) Information provided to the System Operator by Users under other Subsections
of this Code.
95 of 199
20.4.2. The System Operator shall notify all Users of any Abnormal Operations on the
Transmission System, which shall have, in the reasonable opinion of the System Operator, an
operational effect on any User.
20.4.3. The System Operator may proceed with urgent operations without notifying all Users
and without the required procedures. This can only be done if it is of a temporary nature and
less than 15 minutes. The System Operator shall notify all Users of any operations on the
Transmission System without any delay as soon as the System has been restored to normal.
The System Operator shall also inform the Users as to the likely duration of the condition
and shall update this prognosis as appropriate. The System Operator shall additionally inform
the Users as soon as reasonably possible when the condition has ended.
20.4.4. The User shall notify the System Operator of Abnormal Operations on the Users
system, which shall have an operational effect on the Transmission System. The System
Operator shall notify any Users on whose system(s) the Abnormal Operation shall have an
operational effect.
96 of 199
97 of 199
98 of 199
(b) To receive and acknowledge receipt of requests, for amongst other matters,
operation outside the registered values of Availability, Ancillary Service
capability, or operating characteristics of the Generating Units during System
Emergency Conditions as stipulated in Appendix 8.
At any point in time, a single person shall be designated as the Responsible Manager by
the Generator and notified to the System Operator. The Responsible Manager shall be
responsible for dealing with the System Operator on matters relating to the Grid Code.
In the event that the Responsible Manager is not a person on duty at the control Facility,
then the Responsible Manager must be capable of being contacted from the control
Facility at all times. In the event that the System Operator issues a request to the control
Facility requiring the Responsible Manager to contact the NCC, the Responsible
Manager shall comply with the request without undue delay and in any case within 15
minutes of the request.
The Responsible Manager shall be authorised by the Generator to perform the following
functions on behalf of the Generator:
(a) To make estimates in accordance with Good Utility Practice as to the
Availability, Ancillary Service capability and operating characteristics of each
Generating Unit;
(b) To make declarations for each Generating Unit; and
(c) To communicate with respect to issues regarding Outages of each Generating
Unit.
The Generator may, from time to time, notify a replacement contact location and
personnel, which meets the foregoing requirements.
20.14.3.Directly Connected Customers
The Directly Connected Customer shall notify the System Operator of its contact locations
and the detail of its personnel prior to connection and thereafter it shall be updated as
appropriate.
The Directly Connected Customer is required to provide the System Operator with the
contact information of a responsible operator(s) who shall respond to communications from
the System Operator without undue delay. The operators shall be of suitable experience and
training and shall be authorised to perform functions on behalf of the Directly Connected
Customer.
The responsible operator shall have the ability to attend to the site of the Directly Connected
Customer within 60 minutes of an instruction being issued by the System Operator.
At any point in time, the Directly Connected Customer shall notify the System Operator of a
single person designated by the Directly Connected Customer as the Responsible Manager.
The Responsible Manager shall be responsible for dealing with the System Operator on
matters relating to the Grid Code. In the event that the Responsible Manager is not a person
on duty at the site of the Customer Connected to the Transmission System, then the
Responsible Manager must be capable of being contacted from the site of the Directly
99 of 199
Connected Customer at all times. In the event that the System Operator issues a request to
the site of Directly Connected Customer requiring the Responsible Manager to contact the
NCC, the Responsible Manager shall comply with the request without undue delay and in any
case within 60 minutes of the request.
20.14.4.Distribution Network Operators
The Distribution Network Operator shall notify the System Operator of its contact locations
and the detail of its personnel prior to connection and thereafter it shall be updated as
appropriate.
The Distribution Network Operator shall be required to provide a control Facility.
The Distribution Network Operator shall ensure by acting in accordance with Good Utility
Practice that the control Facility is staffed at appropriate staffing levels at all times.
The Distribution Network Operator shall operate its control Facility according to the
provisions agreed upon with the System Operator as set out in the Distribution Network
Operators and the System Operator agreement.
100 of 199
20.18. TELEPHONE/FACSIMILE
20.18.1.Each User shall be responsible for the provision and maintenance of telephone and
facsimile Equipment.
20.18.2.The System Operator shall provide one or more telephone extension to be connected
to the System Operator private operational telephone system. This Facility shall be reserved
for operational purposes only, and shall be attended continuously by an authorised
operational person and answered without undue delay. Users shall be responsible for
optimising the Reliability and security of this telephone service including the provision at no
charge of an uninterruptible power supply.
20.18.3.Users shall provide a public switched telephone network circuit to the
communications and control room.
20.18.4.Users shall provide no less than two separate public switched telephone network
circuits to the control Facility.
20.18.5.Users shall provide no less than one facsimile unit, connected to a dedicated public
switched telephone network circuit at the control Facility.
20.20.TIME STANDARDS
20.20.1.Time shall be set by a standard determined by the System Operator. The time
standard shall be broadcast to relevant telecommunications devices in order to maintain time
coherence.
101 of 199
20.23.DATA RETENTION
20.23.1.This provision has to be read in conjunction with the Market Rules to form the
complete requirement with regard to data retention.
20.23.2.Operational data is all data to be supplied by Users under this Code and any other
data expressly provided to be operational data under this Code. Operational data to be
supplied by the Users shall be submitted to the department or address as the System
Operator may from time to time advise.
102 of 199
103 of 199
21.
21.1. OBJECTIVE
21.1.1. The objective of this Section is to provide Generators with provisional running orders
for the Dispatch Day ahead, such that Generating Units will be made available in the correct
timescale to enable the System Operator to Dispatch them whilst maintaining the required
Operating Reserve. In order to achieve the primary objective, this Section details the
timescale for the System Operator to make specific information available to Generators and
other Users.
21.1.2. A further objective of this Section is to establish a framework to enable the System
Operator to issue Dispatch Instructions to:
(a) Generators with respect to their Generating Units; and
(b) Users in relation to Ancillary Services.
Dispatch Instructions are primarily issued such that available Generation is matched to
Demand with appropriate margin of Operating Reserve whilst maintaining the integrity and
security of the Transmission System with acceptable Quality of Supply.
21.2. GENERAL
21.2.1. The System Operator shall dispatch Generating Units according to Market Rules,
subject to constraints of safety of personnel, Equipment, System Security, System Stability,
Reliability and the environmental requirements.
21.2.2. The Dispatch of Generating Units is necessary to ensure that the most economical
combination of Generating Units possible is used for each Dispatch Period. This optimal
combination of Generating Units must meet the Demand such that the necessary Frequency
Control can be achieved.
21.2.3. In order to achieve this, the System Operator will have to calculate the optimal
combination of Generating Units on a continuous basis using specialised software suitable for
this. These calculations by the System Operator are based on Day-ahead Nominations from
Generators for each Generating Unit and the anticipated Demand.
104 of 199
21.3.4. System Operator shall adjust Generating Unit Active Power Output by using a merit
order based (this may be manual or by using specialist software) on the Day-ahead
Nominations provided by Generators for each Generating Unit as variations occur due to
such factors as Demand or Availability variations.
Energy
Trade
105 of 199
The System Operator shall produce a Pre-dispatch Day constrained Schedule for each
Dispatch Day by 16:00 hours on the Pre-dispatch Day.
The System Operator shall issue provisional running orders based upon the Dispatch
Schedule for the Dispatch Day to the Generator for each Generating Unit by 16:00 hours on
the Pre-dispatch Day.
The provisional running orders issued to each Generating Unit by the System Operator, shall
indicate the planned Generating Unit Active Power Output pattern specifying:
(a) Forecast start-up and shut-down times, if relevant;
(b) Forecast Active Power Dispatch levels for each Dispatch Period; and,
(c) Forecast levels of Operating Reserve provision for each Dispatch Period, if the
Generating Unit is contracted for Operating Reserve requirements.
Provisional running orders are indicative only, provided as a guide to the expected output
requirements from Generating Units and are not Dispatch Instructions.
21.4.3. Pre-dispatch Day unconstrained Schedule
The System Operator shall produce a Pre-dispatch Day unconstrained Schedule for each
Dispatch Day by 16:00 hours on the Pre-dispatch Day. The same principles specified in
Condition 21.4.1 shall be applied with the following change:
(a) The known Transmission System constraints must be excluded.
This Schedule shall be used to forecast the Day-ahead Price consistent with the
appropriate Market Rules.
21.4.4. Dispatch Day schedule
If the System Operator forecasts a significant difference between the provisional running
orders and anticipated Dispatch Instructions, in the interval between the issue of
provisional running orders and the issue of relevant Dispatch Instructions, the System
Operator shall endeavour to notify this difference to impacted Generators.
21.4.5. System congestion
System Operator shall install and commission such real time Equipment and software as
to calculate Transmission Constraints and Reliability margins per Dispatch Period.
System Operator shall change the Dispatch Schedule of the Generating Units in order to
eliminate Transmission System congestion and to ensure the security and Reliability of
system operation.
System Operator shall reduce the Load in the importing region contributing to the
congestion if it was not possible to eliminate congestion by changing the Dispatch of the
Generating Units.
System Operator shall further instruct all Users to take specific action in order to avoid
more major disturbances in emergency situations.
21.4.6. Ex-post Unconstrained Dispatch Schedule
106 of 199
The System Operator shall produce an Ex-post Unconstrained Dispatch Schedule for
each Dispatch Day by no later than 12:00 hours on the Calculation Day. This leaves the
System Operator sufficient time to calculate the System Marginal Price for each Dispatch
Period pursuant Rule 33.2 of the Market Rules. The same principles specified in
Subsection 21.4.1 shall be applied with the following two changes:
(a) The actual Load readings must be used; and
(b) The Transmission System constraints must be excluded.
107 of 199
108 of 199
flow. System stability depends on the voltage profile across the System. In view of
these considerations it is necessary from time to time to employ certain Power
Stations to supply or consume Reactive Power, whether or not they are producing
Active Power, for the purpose of Voltage Control.
The Reactive Power output of any Generating Unit in respect of which a Dispatch
Instruction is given shall then, without delay be adjusted in accordance with its Registered
Information, to the new target Reactive Power so instructed, within, a tolerance of +/- 2%
of the target or +/- 2MVAr whichever is greater. The Reactive Power output of a
Generating Unit shall not be adjusted (other than under AVR action) other than in
response to a Dispatch Instruction from the System Operator.
Generators having achieved the new target Reactive Power output should not attempt to
sustain this level of Reactive Power output as the System Voltage varies but should, rather,
allow the Reactive Power output to vary under AVR control in accordance with registered
Ancillary Service capabilities in the Registered Information.
While a Reactive Power Dispatch Instruction shall normally specify a new Reactive Power
target for a Generating Unit, the System Operator may also from time to time instruct
Generators to perform one or more tap changes on the Generating Unit Transformer of a
Generating Unit if it has on-load tap-change capability. The instruction for tap changes
may be a simultaneous tap change instruction whereby the tap change shall be effected by
the Generator in response to an instruction from the System Operator issued
simultaneously to relevant Power Stations. The instruction, which is normally preceded by
advance warning, shall be effected within 1 minute of receipt from the System Operator of
the instruction.
Where a Generating Unit has off-load tap-change capability the SO shall before it
synchronises instruct it to the appropriate tap position.
a. Where the SO does not give such instruction the Generator shall request the SO to
give this instruction.
Dispatch Instructions in relation to Reactive Power shall include target Voltage levels to
be achieved by the Generating Unit on the Transmission System at the Connection Point
(or on the Off-taker System at the Off-taker System Entry Point in the case of an
Embedded Generating Unit) namely on the higher voltage side of the Generating Unit
step-up transformer). Where a Generating Unit is instructed to a specified target voltage,
the Generator shall achieve that target within a tolerance of 1 kV by tap changing on the
Generating Unit step-up transformer unless otherwise agreed with the System Operator.
Under normal operating conditions, once this target Voltage level has been achieved, the
Generator shall not tap change again without prior consultation with and agreement of
the System Operator.
Under certain conditions such as low System Voltage, an instruction to maximum Reactive
Power output at instructed Active Power Output shall be given and the Generator shall
take appropriate action to maximise Reactive Power output unless constrained by Plant
operational limits or safety grounds relating to personnel or Plant.
109 of 199
Under certain conditions such as high System Voltage, a Dispatch Instruction to maximum
Reactive Power absorption at instructed Active Power Output shall be given and the
Generator shall take appropriate action to maximise Reactive Power absorption unless
constrained by Plant operational limits or safety grounds relating to personnel or Plant.
The issue of Dispatch Instructions for Active Power shall be made with due regard to any
resulting change in Reactive Power capability and shall include reduction in Active Power
Generation in order to increase Reactive Power capability (i.e. take account of the
Generating Unit Capability Chart).
The excitation system, unless otherwise agreed with the System Operator, shall be operated
only in its constant terminal voltage mode of operation with Reactive Power limiters in
service, with any constant Reactive Power output control mode or constant power factor
output control mode always disabled, unless agreed otherwise with the System Operator.
In the event of any change in System Voltage, a Generator shall not take any action to
override automatic Reactive Power response which is produced as a result of constant
terminal voltage mode of operation of the automatic excitation control system unless
instructed otherwise by the System Operator or unless immediate action is necessary to
comply with stability limits or unless constrained by Plant operational limits or safety
grounds (relating to personnel or Plant).
A Dispatch Instruction relating to Reactive Power shall be implemented without delay and
will be achieved not later than 2 minutes after the instruction time, or such longer period as
the System Operator may instruct.
Where Dispatch Instructions relating to Active Power and Reactive Power are given
together, and to achieve the Reactive Power output would cause the Generating Unit to
operate outside its Capability Chart as a result of the Active Power instruction being met at
the same time, then the timescale of implementation of the Reactive Power instruction
shall be extended to be no longer than the timescale for implementing the Active Power
instruction but in any case to achieve the Reactive Power Dispatch Instruction as soon as
possible.
For Power Stations with on-load tap change capability:
a) In circumstances where the System Operator issues new instructions in relation
to more than one Generating Unit at the same Power Station at the same time
tapping shall be carried out by the Generator one tap at a time either alternately
between (or in sequential order, if more than two), or at the same time on, each
Generating Unit, as the case may be.
b) Where the instructions require more than two taps per Generating Unit meaning
that the instructions cannot be achieved within 2 minutes of the instruction time,
(or such longer period at the System Operator may have instructed), the
instructions shall each be achieved with the minimum of delay after the expiry of
that period.
c) On receiving a new Active Power Dispatch Instruction, no tap changing shall be
carried out to change the Reactive Power output unless there is a new Reactive
Power Dispatch Instruction.
110 of 199
111 of 199
The Generator shall inform the System Operator by telephone without delay if at any
time a Generating Unit is unable to comply with any Dispatch Instruction correctly
issued by the System Operator in respect of any Generating Unit.
21.5.8. Constrained Generation
Constrained generation is the service supplied by a Generator at one of its Power
Stations to the System Operator by constraining its power output below (alternatively
above) the unconstrained schedule level. The service is required to ensure that the
Transmission Network remains between appropriate operational limits (e.g. thermal,
voltage or stability limits).
If in providing the service, the Generator experiences a financial loss, for which it shall
be compensated by the Transmission Service Provider according to the Market Rules.
Constrained generation is required to meet network Reliability as there are no current
rules for market splitting across transmission constraints or the handling of units in
strategic positions.
The identification of the specific Transmission Network constraints applicable at any
point in time shall be the responsibility of the System Operator.
112 of 199
22.
22.1. OBJECTIVE
22.1.1. The objective of this Section is to define the obligations for formal notification of
Outages by Users and TSP to the System Operator.
22.2. GENERAL
22.2.1. Secure operation of an electricity system requires that the maintenance of the
Generating Units should be coordinated with the Outages of critical Transmission lines. This
is essential in order to enable the System Operator to fulfil its obligations relating to the
operation of the Transmission System, and to enable Users and TSP to plan their Outages in
an orderly way. The mechanisms by which this is achieved will be formalised in this Section.
113 of 199
The Generator shall ensure under its fuel supply and fuel transport
agreements or under any fuel supply or transport code that it is informed of
any outage planned in its fuel supply.
(ii)
(b) TSP shall specify with regard to each of their items of Equipment the start date,
time and duration of each Outage for the year after the current year. This must
reach the System Operator by the 1st of August of the current year pursuant to
Section 22.3.1.
(c) TSP and each Generator shall act in accordance with Good Utility Practice in
planning their Outages, so as to avoid a situation arising in which TSP or a
Generator is obliged to schedule an Outage at short notice.
(d) Generators (and TSP where relevant) shall specify the following, unless they
reasonably substantiate that an Outage is inflexible:
(i)
(ii)
The minimum Outage duration which would be acceptable, if less than the
scheduled Outage duration;
(iii)
(iv)
(v)
Any Outages where it is particularly desirable that they should take place
within the year scheduled.
(e) Any Outage where its timing is dependent on Generating Unit operating hours,
equivalent operating hours or starts.
22.3.6. Distribution Network Operator and Directly Connected Customer Obligations
Each Distribution Network Operator shall act in accordance with Good Utility Practice
in planning their circuit Outages. Each Distribution Company (and Directly Connected
Customers where relevant) shall furnish by 1st of August of each year the following
information:
(a) Load in MW not to be available from any Connection Point.
114 of 199
(b) Identification of Equipment and /or Apparatus at the Connection Point where
there will be an Outage.
(c) Period during which a circuit at or near a Connection Point will be unavailable
with Start-date and Start-time and End-date and End-time.
22.3.7. Outage scheduling programme
The System Operator shall present the coordinated Outage plans as well as the results of the
Reliability studies in report format to the Commission for approval.
115 of 199
116 of 199
23.
23.1. OBJECTIVE
23.1.1. The objective of this Section is to define the Reliability criteria and measures the
System Operator and the TSP have to adhere to in operating, maintaining and developing the
Transmission System.
23.2. GENERAL
23.2.1. In order to maintain reliable operation of the Transmission System, it is necessary that
all SO, TSP and Users observe and subscribe to certain minimum planning criteria.
23.2.2. The criteria and principles provided in this document serve as a guideline to develop
criteria and methodologies applicable to the TSP, System Operator, Users and related
Interconnections.
23.2.3. Reliability measures
Traditionally the measurement of transmission Reliability is achieved through the
deterministic N-1 Criteria. This criterion should be regarded as a minimum standard.
Additional to this the System Operator should develop probabilistic criteria. The
fundamental attributes for Reliability measures to be considered to evaluate risk of probable
extreme events include:
(a) The frequency of events (e.g. frequency of circuit overload 0.72 events/year);
(b) Duration of events (e.g. duration of circuit overload 2.5 hours/year); and
(c) Severity of events (how does event impact on load curtailment)
From these attributes other indices to quantify network performance can be calculated. To
enable the definition of applicable indices, which may apply to the TSP and System Operator,
a number of concepts and definitions related to network, configuration and aspects
influencing network performance are discussed in Appendix 3.
117 of 199
and Users needs. All of these indicators must be measurable and calculable for a defined
recording period. The length of the period should be measured in years to facilitate
comparison.
23.5. REPORTING
23.5.1. The System Operator shall prepare and publish an annual assessment report of the
Reliability of the Transmission System for review by the Commission.
23.5.2. To carry out these tasks, sufficient data and input must be made available to evaluate
and analyse the Applicable Reliability Criteria.
118 of 199
24.
24.1. OBJECTIVE
24.1.1. The objective of this Section is to establish the approach to central co-ordination and
control of a System Test required by the System Operator, the TSP or a User, where such test
shall or may:
(a) Affect the secure operation of the Transmission System;
(b) Have a significant effect on the operation of the Transmission System or a
User's System;
(c) Affect the economic operation of the Transmission System or a User's System;
or
(d) Affect the quality or continuity of electricity supply to Users.
24.2. GENERAL
24.2.1. This Section deals with the responsibilities and procedures for arranging and carrying
out System Tests that may have an effect on the systems of the TSP and/or Users.
24.2.2. By their nature, System Tests may have an impact on either or both of:
(a) The System Operator's responsibilities in respect of the Transmission System,
including Dispatch of Generation; and
(b) The operations of Users and the quality and continuity of supply of electricity to
Users.
24.2.3. To minimise disruption to the operation of the Transmission System and to the
Systems of other Users, it is necessary that tests that affect the operation of the Transmission
System or Users Systems be subject to central co-ordination and control.
24.2.4. These tests are not intended to deal with tests that may be called for routinely by TSP
or SO in order to assess compliance of Users with their defined design, operating and
connection characteristics.
119 of 199
System Tests required by the System Operator or the TSP from time to time shall include,
but shall not be limited to the following:
(a) Tests involving the controlled application of Frequency and/or Voltage variations
aimed at gathering information on Power System behaviour;
(b) Power System restoration tests (i.e. Black Start test at a Power Station);
(c) Testing of standing procedures for System Emergency Conditions; and
(d) Testing or monitoring of power quality under various Power System conditions and
Dispatch configurations.
24.3.3. Notice to Users
Where the System Operator or TSP intends to carry out a System Test, and such test will or
may have an operational effect on a Users system, the System Operator shall provide notice
to the relevant User of the scheduled time and effect of the System Test as is reasonable in all
the circumstances and shall keep the relevant User informed as to any changes to the
scheduled time and nature of the System Test.
24.3.4. Request for additional time
A User, having been informed about a System Test may contact the System Operator to
request additional time to consider the impact of the test on the User. The System Operator
shall co-operate with the User to assess the risks. The test shall not proceed until all Users are
satisfied unless, in the System Operators view, a User is acting unreasonably.
120 of 199
(d) Whether there may be an adverse material impact on the User if the System Test is
cancelled at short notice or delayed; and
(e) Where the User is a Generator, the Dispatch required by the Generator for
completion of the test.
Additionally, the factors that influence the completion of the stages should be outlined to the
System Operator, e.g., if the procedure to be followed for a certain stage depends on the
outcome of a previous stage.
24.4.3. Generator Specific request
A request by a Generator for a System Test requiring a Generating Unit to be Dispatched to
a particular Active Power output or operating condition shall not be considered a redeclaration of Availability, Ancillary Service capability or operating characteristics.
121 of 199
122 of 199
123 of 199
The Report shall include a description of the Plant and/or Apparatus tested and a
description of the system test carried out together with the results, conclusions and
recommendations as they relate to the System Operator and operationally affected Users.
24.9.3. Report confidentiality
The Report shall not be submitted to any person who is not a representative of the
System Operator or the test requestor unless the System Operator and the test requestor,
having reasonably considered the confidentiality issues arising shall have unanimously
approved such submission.
24.10. DISPUTES
Disputes shall be handled according to relevant industry rules and regulations as
approved by NERC.
124 of 199
25.
25.1. OBJECTIVE
25.1.1. The objective of this Section is to achieve Safety on the network when either:
(a) work on TSP Equipment necessitates the provision of Safety Precautions on
User Equipment; or
(b) work on User Equipment necessitates the provision of Safety Precautions on
TSP Equipment.
25.1.2. A flow chart in Appendix 4C illustrates the process utilised in this Section to achieve
Safety on the network. In the case of a conflict between the flow chart and the provisions of
this Section, this Section will prevail.
25.2. GENERAL
25.2.1. This Section specifies the standard operating procedures to be used by System
Operator, TSP and Users of the network for the co-ordination, establishment and
maintenance of necessary Safety Precautions when work is to be carried out on the
Transmission Network or on a Users Apparatus and when there is a need for Safety
Precautions on the high voltage Equipment on the others system for work to be carried out
safely. The term work includes testing, other than Network Tests. This Section applies
between System Operator, TSP and Users and does not impose a particular set of Safety
Rules on SO, TSP and Users; the Safety Rules to be adopted and used by SO, TSP and Users
shall be those chosen by them. This Safety procedure applies to:
(a) TSP
(b) System Operator
(c) Generators
(d) Distribution Network Operators
(e) Directly Connected Customers
25.3. INTERPRETATION
25.3.1. In this Section 25, the following terms shall have the meaning:
(a) High Voltage Equipment means high voltage electrical circuits forming part
of a System, on which Safety from the System may be required or on which
Safety Precautions may be applied to allow work to be carried out on a circuit.
(b) Isolation means the disconnection of Equipment from the remainder of the
network in which the Equipment is situated by either of the following:
(i)
125 of 199
b.i.1)
b.i.2)
(ii)
(ii)
25.4. PROCEDURE
25.4.1. Approval of Local Safety Instructions
(a) In accordance with the timing requirements of its Grid Connection Agreement
with the TSP, each User will supply to the SO a copy of its Local Safety
Instructions relating to its side of the Connection Point at each Connection Site.
(b) In accordance with the timing requirements of each User Agreement, the SO
will supply to each User a copy of its Local Safety Instructions relating to the
TSP side of the Connection Point at each Connection Site.
(c) Prior to connection each party must have approved the others relevant Local
Safety Instructions in relation to Isolation and Earthing.
(d) Either party may require that the Isolation and/or Earthing provisions in the
other partys Local Safety Instructions affecting the Connection Site should be
made more stringent in order that approval of the other partys Local Safety
Instructions can be given. Provided that these requirements are not
unreasonable, the other party will make such changes as soon as reasonably
practicable.
If approved, a party that wishes to change the provisions in its Local Safety Instructions
relating to Isolation and/or Earthing after approval, must inform the other party. If the
change is to make the provisions more stringent, then the other party merely has to note the
The Grid Code -Version 02
126 of 199
changes. If the change is to relax the provisions, then the other party need to assess and
approve the new provisions and procedures referred to in 25.4.1(c).
25.4.2. Safety Coordinators
For each Connection Point, the SO and each User must at all times have person(s) Safety
Coordinator(s) to be responsible for the coordination of Safety Precautions when work is to
be carried out on the network or parts of it which necessitates the provision of Safety
Precautions on High Voltage Equipment pursuant to this Section of the Grid Code. A Safety
Coordinator may be responsible for the coordination of safety at more than one Connection
Point on the network.
Each Safety Coordinator shall be authorised by the SO or a User, as the case may be, as
competent to carry out the functions set out to achieve Safety from the Network at all times.
Only Authorised Persons of the SO and the User(s) will carry out Safety activities at all times.
Contact between Safety Coordinators at SO and User(s) will be made via normal operational
channels, and accordingly separate telephone numbers for Safety Coordinators need to be
registered and available at SO and Users at all times.
If work is to be carried out on the network which necessitates the provision of Safety
Precautions, in accordance with the provisions of this Section, the Requesting Safety
Coordinator who requires Safety Precautions to be provided shall contact the relevant
Implementing Safety Coordinator to coordinate the establishment of Safety Precautions
throughout the work.
127 of 199
25.5.6. If the SO disapproves, it shall explain in its response why it has disapproved and will
suggest an alternative prefix. In this situation, the User shall either notify the SO in writing of
its acceptance of the suggested alternative prefix or it shall apply in writing to the SO with its
revised prefix proposal and the above procedure shall apply.
128 of 199
(c) Where an adequate physical separation has been used that will be in accordance
with, and maintained by the method set out in the Local Safety Instructions of
SO or that of the User, as the case may be, and, if it is part of that method, that
a Caution Notice be placed at the point of separation.
(d) The confirmation of Isolation shall be recorded in the respective Safety Logs.
25.6.4. Implementation of Earthing
The Requesting Safety Coordinator will confirm to the Implementing Safety Coordinator
that the relevant Isolation of its Equipment in the Safety Precautions agreed in 25.6.2 has
been performed, in order that the Implementing Safety Coordinator may proceed to the
Earthing phase.
The Implementing Safety Coordinator shall confirm to the Requesting Safety
Coordinator that the agreed Earthing has been established, and identify the Requesting
Safety Coordinators High Voltage Equipment for which Earthing has been provided.
The confirmation shall specify:
(a) For each location, the identity (by means of the High Voltage Equipment name,
nomenclature and numbering or position, as is applicable) of each point of
Earthing; and
(b) In respect of the Earthing Device used, whether it is:
(i)
(ii)
129 of 199
recorded by the RNSP being issued. The RNSP is applicable to High Voltage Equipment
up to the Connection Point identified in the RNSP-R and RNSP-I forms.
Where Safety Precautions are being provided to enable work to be carried out on both
sides of the Connection Point an RNSP will need to be issued for each side of the
Connection Point with the SO and the respective User each enacting the role of
Requesting Safety Coordinator. This will result in an RNSP-R and RNSP-I form being
completed by each of the SO and the User, with each Safety Coordinator issuing on
RNSP number.
Once the Safety Precautions have been established, the Implementing Safety
Coordinator shall complete form RNSP-I recording the details specified in 25.6.2, 25.6.3
and 25.6.4.
The Requesting Safety Coordinator shall complete form RNSP-R, making a precise copy
of the details received. On completion, the Requesting Safety Coordinator shall read the
entries made back to the sender and check that an accurate copy has been made.
The Requesting Safety Coordinator shall then issue the number of the RNSP taken from
the RNSP-R, to the Implementing Safety Coordinator who will ensure that the number,
including the prefix and suffix, is accurately recorded in the designated space on the
RNSP-I form.
The Requesting Safety Coordinator and the Implementing Safety Coordinator shall
complete and sign appropriate parts of the RNSP-R and RNSP-I forms respectively and
then enter the time and date. When signed no alteration to the RNSP is permitted; the
RNSP may only be cancelled.
The Requesting Safety Coordinator is then free to authorise work (including a test that
does not affect the Implementing Safety Coordinators Equipment. Where testing is to
be carried out which affects the Implementing Safety Coordinators Equipment, the
procedure set out in 25.6.7 shall be implemented.
25.6.6. RNSP Cancellation Procedure
When the Requesting Safety Coordinator decides that Safety Precautions are no longer
required, he will contact the relevant Implementing Safety Coordinator to effect
cancellation of the associated RNSP.
The Requesting Safety Coordinator will inform the relevant Implementing Safety
Coordinator of the RNSP identifying number (including the prefix and suffix), and agree
it is the RNSP to be cancelled.
The Requesting Safety Coordinator and the relevant Implementing Safety Coordinator
shall then respectively complete RNSP-R and RNSP-I forms with their names and
contact address and shall then exchange details. On exchange of details the respective
RNSP is cancelled.
Neither Safety Coordinator shall instruct the removal of any Isolation forming part of
the Safety Precautions as part of the returning of the High Voltage Equipment to service
until it is committed to each by each other that every earth on each side of the
130 of 199
Connection Point, within the points of isolation identified on the RNSP has been
removed or disconnected by the provision of additional Points of Isolation.
Subject to provisions in this Subsection the Implementing Safety Coordinator is then
free to arrange the removal of the Safety Precautions, the procedure to achieve that being
entirely an internal matter for the party the Implementing Safety Coordinator is
representing. Nothing in this Code prevents the SO and Users agreeing to a
simultaneous cancellation and issue a new RNSP, if both agree.
25.6.7. Testing Affecting Another Safety Coordinators Equipment
The carrying out of a test may affect Safety Precautions on RNSPs or work being carried
out which does not require an RNSP. Testing can, for example include the application of
an independent test voltage. Accordingly, where the Requesting Safety Coordinator
wishes to authorise the carrying out of such a test to which the procedures in this Section
of the Grid Code apply he may not do so and the test will not take place unless the steps
in (a) to (c) below have been followed and confirmation of completion has been
recorded in the respective Safety Logs:
(a) Confirmation must be obtained from the Implementing Safety Coordinator
that:
(i)
(ii)
no person will be so authorised until the proposed test has been completed
(or cancelled) and the Requesting Safety Coordinator has notified the
Implementing Safety Coordinator of its completion (or cancellation);
(b) Any other current RNSP which relates to the parts of the Equipment in which
the testing is to take place must have been cancelled in accordance with
procedures set out in 25.6.6
(c) The Implementing Safety Coordinator must agree with the Requesting Safety
Coordinator to permit the testing on that part of the Equipment between the
points of Isolation identified in the RNSP associated with the test and the
points of Isolation on the Requesting Safety Coordinator's Equipment.
(d) The Requesting Safety Coordinator will inform the Implementing Safety
Coordinator as soon as the test has been completed or cancelled and the
confirmation shall be recorded in the respective Safety Logs.
(e) When the test gives rise to the removal of Earthing which it is not intended to
re-apply, the relevant RNSP associated with the test shall be cancelled at the
completion or cancellation of the test in accordance with the procedure set out
in either 25.6.5 or 25.6.6. Where the Earthing is re-applied following the
completion or cancellation of the test, there is no requirement to cancel the
relevant RNSP associated with the test pursuant to this Subsection.
The Grid Code -Version 02
131 of 199
26.
132 of 199
26.1.2. Whenever an accident occurs resulting in or likely to have resulted in loss of life or
injury to human beings the above report should be followed by a detailed report within 48
hours. The System Operator shall take all other statutorily required actions, such as reporting
to the police etc.
26.1.3. The System Operator shall send a preliminary report to the Nigerian Electricity
Regulatory Commission of all Significant Incidents in the Power System which results in
interruption to service, substantial damage to Equipment, loss of life, injury to human beings
within 36 hours of its occurrence followed by a detailed report within two weeks.
26.1.4. For every Significant Incident relating to 26.1.2, NERC shall order an enquiry of the
event. It should be completed with the least possible delay, in any case, not exceeding twenty
days to guard against the possibility of destruction or disappearance of material evidence
being presented, to escape responsibility. It should be a searching probe that may or not
involve members of the security forces to uncover the root causes of the accident, which
sometimes are quite difficult to ascertain. The enquiry should not only fix responsibility for
the accident, but it is more important, to spell out steps to be taken to prevent such accidents
in future.
26.1.5. The System Operator and the affected person or their agent shall establish a format
and procedure for exchange of information for any Significant Incident event.
26.1.6. Users or their agent shall furnish information to the System Operator regarding any
major incident occurring on their Systems promptly.
133 of 199
1.
APPENDIX 1: DEFINITIONS
Table A 1
Abnormal Operation
AC
ACC
Act
Active Power
Agreements
Ancillary Service
Apparatus
Applicable
Criteria
ARC
Reliability
134 of 199
Area
Control
(ACE)
Error
Authorised Person
Automatic
Generation
Control (AGC)
Automatic
Voltage
Regulator (AVR)
Auxiliary
Availability
Black Start
135 of 199
Bulk Power
Energy
Curtailment Index
Business Day
Calculation Day
Capability Chart
Caution Notice
CCGT
Code
Commission
or
Regulator or NERC
Conditions Precedent
Connection Point
Connection Site
Control Action
Control Area
136 of 199
CT
Customer
Damage
Function (CDF)
Day-ahead
Forecast
Demand
Day-ahead Nomination
Day-ahead Price
DC
De-energisation or Deenergise(d)
Demand
Demand Control
Demand Forecast
De-synchronise
Directly
Connected
137 of 199
Customer
transmission system;
Disconnection
Dispatch
Dispatch Day
Dispatch Instruction
Dispatch Period
Dispatch Schedule
Distribution
Distribution Network or
Distribution System
Distribution
Operator
Distribution
Operator
Network
or
System
138 of 199
Distributor
Eligible Customer
Earthing
Earthing Device
Embedded
Unit
Generating
Emergency Generation
Energy
Equipment
ESI
Event
Expected
Energy
Unserved
Expert
Facility
Fault Level
Flicker
Force Majeure
139 of 199
Forced Outage
Frequency
Frequency Control
Generate
Generation
and
Generating Unit
Generator
Governor
System
Control
140 of 199
Governor Droop
Grid Code
Grid
Agreement
Connection
Harmonics
High Voltage
High
Equipment
Voltage
Hot Line
HP
HV
Hz
IEC
Imbalance Energy
Interconnected
Network
141 of 199
Interconnection
Facilities
Interconnector Capacity
Entitlement
Interconnector Energy
Trade Nomination
Interrupted
Energy
Assessment Rate (IEAR)
Interruptible Load
IP
Isolating Device
Isolation
Key Safe
kV
means kilovolt;
kVA
means kilovolt-ampere;
Load
Load Factor
142 of 199
Local
Instructions
Safety
Locked
Locking
Device
Isolating
Low Voltage
LP
LV
Medium Voltage
Meter
Meter Data
Metering Installation
143 of 199
MVA
means megavolt-ampere;
MVAr
MVArh
MW
MWh
Network
Capacity
Constrained
Nigerian
Electricity
Supply Industry
Node
Nomination
Normal
Margin
Regulating
N-1 Criteria
Off-taker
Operating Agreement
Operating Reserve
144 of 199
Reserve
Operating Security
Operating State
Operational Planning
Outage
Partial Shutdown
Planned Outage
Plant
PLC
Power Station
145 of 199
Rules;
Power System
Pre-dispatch Day
Primary Reserve
Procedure
Protection Scheme
Quality of Supply
Quantity Nomination
Quick Reserve
Reactive Power
146 of 199
1000VAr = 1kVAr
1000kVAr = 1MVAr;
147 of 199
Record
Safety
(RNSP)
Of
Network
Precautions
Registered Capacity
Registered Information
Relevant
Point
Connection
Reliability
Reliability
Agreement
Must-run
Reliability
Unit
Must-run
Responsible Manager
Rotational
Shedding
Load
148 of 199
Safety
Safety Coordinators
Safety Key
Safety Log
Safety Precautions
Secondary Reserve
Section
Slow Reserve
Spinning Reserve
Station Capacity
149 of 199
Station Transformer or
Station
Service
Transformer
Subsection
Subtransmission
Subtransmission System
Synchronise
System
System Disturbance
System
Condition
Emergency
150 of 199
System Minutes
System
SO
Operator
or
System Stability
System Tests
TCN
Total Shutdown
Transitional Stage
Transmission
Transmission Constraint
Transmission
Criteria
Planning
Service
Transmission System or
Transmission Network
Transmission
Provider (TSP)
151 of 199
Unplanned Outage
Emergency Outage
or
Unreliability
Usage Charge
Users
Voltage
Voltage Control
Voltage Dip
Voltage Fluctuations
Voltage Reduction
Voltage Support
152 of 199
Voltage Unbalance
VT
has the meaning defined in the relevant intergovernmental agreement between the participating
countries in West Africa.
(WAPP)
153 of 199
2.
154 of 199
3.
3.1
Introduction
The Nigerian Power System consists of those Generation and Transmission facilities, which are
controlled by the TCN System Operator and which function as part of an integrated and
coordinated power supply network.
In order to maintain reliable operation of the Transmission System, it is necessary that all
systems observe and subscribe to certain minimum planning criteria. The criteria and principles
provided in this Appendix serve as a guideline to develop criteria and methodologies applicable
to the TCN and related interconnections and customers.
This Appendix 3 consists of this introduction and a conclusion together with three sections as
follows:
Section 2 provides guidelines to transmission contingency criteria based on NERC standards,
Section 3 provides guidelines to the measuring of Reliability indices in order to produce annual
performance figures, and
Section 4 provides guidelines with regard to the measurement of the value of network
infrastructure.
This Appendix thus provides guidelines that can be used to direct the TCN planning and
operational criteria in future. It does not provide the procedures and measures required to
ensure that the criteria are followed. Neither does the Appendix direct responsibility to any of
the TCN divisions. These issues will need to be developed and resolved before criteria of this
nature can effectively be implemented.
3.2
155 of 199
Annual preparation of adequacy indices of the TCN power system will be required. This
should be read in conjunction with the long-term planning reports for infrastructure
additions with possible quantification of the worth of these network additions as outlined in
Section 4. These working papers to report the results of system tests future planning reports
will provide the basis for statements concerning the adequacy of the planned TCN System.
156 of 199
Category
Contingencies
Components
Thermal
Voltage
System
Out of Service
Limits
Limits
Stable
Loss of
Demand or
Curtailed Firm
Transfers
Cascading c
Outages
A No Contingencies
All Facilities in Service
None
Single
Single
Single
Single
Normal
A/R
A/R
A/R
A/R
A/R
Normal
157 of 199
Yes
No
No
Yes
No b
No
Yes
No b
No
Yes
No b
No
Yes
No b
No
C Event(s) resulting in
the loss of two or more
(multiple) components.
Multiple
A/R
A/R
Yes
Plannedd
No
Multiple
A/R
A/R
Yes
Plannedd
No
Multiple
A/R
A/R
Yes
Plannedd
No
Multiple
A/R
A/R
Yes
Plannedd
No
Multiple
A/R
A/R
Yes
Plannedd
No
Multiple
A/R
A/R
Yes
Plannedd
No
7.Transformer
D e Extreme event
158 of 199
1.Generating Unit
3.Transformer
areas.
2.Transmission Circuit
4.Bus Section
3 Fault, with Normal Clearing:
5.Breaker (failure or internal fault)
Other: 6.Loss of line with three or more circuits
7.All transmission lines on a common right-of way
8.Loss of a substation (one voltage level plus
transformers)
point.
May involve substantial loss of customer demand and generation in a widespread area or
Portions or all of the interconnected systems may or may not achieve a new, stable operating
Evaluation of these events may require joint studies with neighbouring systems.
Document measures or procedures to mitigate the extent and effects of such events.
Mitigation or elimination of the risks and consequences of these events shall be at the
discretion of the entities responsible for the reliability of the interconnected Transmission Systems.
159 of 199
b)
Planned or controlled interruption of Generating Units or electric supply to radial customers or some local network Customers,
connected to or supplied by the faulted component or by the affected area, may occur in certain areas without impacting the overall security of
the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including curtailments of
contracted firm (non-recallable reserved) electric power transfers.
c)
Cascading is the uncontrolled successive loss of system elements triggered by an incident at any location. Cascading results in widespread
service interruption which cannot be restrained from sequentially spreading beyond an area predetermined by appropriate studies.
d)
Depending on system design and expected system impacts, the controlled interruption of electric supply to customers (Load Shedding),
the planned removal from service of certain Generating Units, or the curtailment of contracted firm (non-recallable reserved) electric power
transfers may be necessary to maintain the overall security of the Interconnected Transmission Systems.
e)
A number of extreme contingencies that are listed under Category D and judged to be critical by the transmission planning entity (ies) will
be selected for evaluation. It is not expected that all possible Facility Outages under each listed contingency of Category D will be evaluated.
160 of 199
3.3
Reliability Measures
3.3.1
Reliability indices
From these attributes other indices to quantify network performance can be calculated. To
enable the definition of applicable indices, which may apply to the TCN, a number of
concepts and definitions related to network, configuration and aspects influencing network
performance are discussed below. These concepts and definitions are taken from Reference
[1]1.
3.3.2
Re-dispatch generation,
C.C. Fong, R. Billinton, R.O. Gunderson, P.M. ONeill, J. Raksany, A.W. Schneider, Jr, B. Silverstein, Bulk System Reliability Measurement
and Indices, IEEE Trans. On Power Systems, Vol.4, No32, August 1989, pp. 829-835
161 of 199
3.3.2.2
3.3.2.3
Monitoring Points
With the above in mind, two types of monitoring points are defined. They are illustrated
conceptually in Figure 1: and are defined as follows:
Radial Delivery Point: A radial delivery point is:
A low voltage bus of a Transformer. The bus radially supplies a Distribution System, or
A point in the bulk system, which is an interface between Transmission System and Directly
Connected Customer-owned facilities. The point radially supplies the Directly Connected
Customer.
Meshed Delivery Points: a set of points on the boundary between the Transmission System
and a discrete part of the Distribution System.
Significant point: This is a bus or a point within the bulk system, where SO deems it
important to monitor the reliability of service. This type of monitoring point recognizes that
there may be special purpose monitoring points that are different from radial or meshed
delivery points.
This distinction between radial and meshed delivery points is that interruption of radial
delivery points result in load loss, whereas interruption of meshed delivery points does not
always result in load loss but could result in inadequate service conditions.
162 of 199
Bulk System
C
A
B
B
Load
Radial
Distribution
System
Load
Load
Meshed Distribution
System
A: Radial Delivery Point
B: Meshed Delivery Point
C: Significant Point
Figure
2:
further
illustrates
330 kV
the
two
types
of
delivery
330 kV
330 kV
330 kV
330 kV
132 kV
132 kV
132 kV
132 kV
A
Load
Load
132 kV
33 kV
33 kV
G
C
11 kV
Load
D
Load
Load
Load
Load
Load
11 kV
Load
Load
Radial
Distribution
System
Radial delivery point
3.3.3
Basic Indices
points.
163 of 199
Several fundamental indices are proposed. These can be expanded based on the TCN needs.
All of these indices can be calculated for a defined recording period. The length of the
period should be measured over multiple years to facilitate comparison.
Delivery Point Interruption Indices
(a) Individual Delivery Point Indices: For each delivery point (radial or meshed):
Interruption Frequency
No. of Interruptions
Period Years
Sum of MW Interrupted
Period Years
(b) System-Wide Delivery Point Indices: For the bulk system and for each type of delivery
point (radial or meshed):
System Average Interruption Frequency
No. of Interruptions
Delivery Po int years
Sum of MW Interrupted
Delivery Po int Years
No. of Interruptions
Period Years
164 of 199
The monitoring of significant points is very specific to the needs of individual operations.
System-wide average indices are not suggested here but may be considered, for groups of
significant points.
Automatic and Rotational Load Shedding Indices
For each type of load shedding:
Frequency
No. of Events
Periods Years
These indices may also be calculated for a specific automatic scheme, to indicate its impact
on bulk system reliability. The Load Shedding Severity Index is expressed in System Minutes.
System Disturbance Indices
For an individual System Disturbance:
System Disturbance Severity
This index is expressed in System Minutes. It is again fundamentally the same as the Bulk
Power Energy Curtailment Index, but is applied to an individual System Disturbance in this
case.
3.4
Type of customer;
Duration;
165 of 199
Frequency;
3.4.1
The broadest application of a Customer Damage Function is its use to relate the composite
customer losses to the socio-economic worth of electric service Reliability for an entire Utility
Service Area2. The cost estimates can be obtained by multiplying the Expected Unserved
Energy to customers due to interruptions by a suitable factor, designated as the Interrupted
Energy Assessment Rate (IEAR) expressed in $/kWh.
3.4.2
Some countries with extremely high reliability have attempted to introduce obligations on
Distributors to make some form of payment to customers based on lost load. However this is
not the common application of the Customer Damage Function.
The standard application of the Customer Damage Function is as feedback into the planning
process. This is in order to support the planning security of supply analysis.
3.5
Conclusion
This Appendix serves as a guideline for the TCN to develop applicable Reliability measures
and methodologies to maintain reliable operation of the Transmission System.
The Appendix provided fundamental concepts relating to:
The measuring of Reliability indices in order to produce annual performance figures, and
Li Wenyuan, R. Billinton, A Minimum Cost Assessment Method for Composite Generation and Transmission System Expansion Planning,
IEEE Trans. On Power Systems, Vol.8, No.2, May 1993, pp. 628-635
166 of 199
4.
APPENDIX 4A
PRECAUTIONS (RNSP)
[TCN]
RECORD
OF
NETWORK
SAFETY
167 of 199
_____________________________________________________________________
________________
_____________________________________________________________________
________________
(b) EARTHING
[State the Location(s) at which Earthing has been established (whether on the
implementing Safety Coordinator's Equipment or on the System of another User
connected to the implementing Safety Coordinator's System). For each Location,
identify each point of Earthing. For each point of Earthing, state the means by which
Earthing has been achieved, and whether, immobilised and Locked, other safety
procedures applied, as appropriate].
_____________________________________________________________________
________________
_____________________________________________________________________
________________
_____________________________________________________________________
________________
1.3 ISSUE
I have received confirmation from _________________________________________
(name
of
Implementing
Safety
Coordinator)
at
_________________________________________ (location) that the Safety
Precautions identified in paragraph 1.2 have been established and that instructions will
not be issued at his location for their removal until this RNSP is cancelled.
Signed ................................................................(Requesting Safety Coordinator)
at .......................................(time) on .................................................. (Date)
PART 2
2.1 CANCELLATION
l have confirmed to _________________________________________ (name of the
implementing
Safety
Coordinator)
at
________________________________________ (location) that the Safety
Precautions set out in paragraph 1.2 are no longer required and accordingly the RNSP is
cancelled.
Signed ................................................................(Requesting Safety Coordinator)
at ........................................(time) on ................................................. (Date)
168 of 199
4.
APPENDIX
PRECAUTIONS
4B
[TCN]
RECORD
OF
NETWORK
SAFETY
ISOLATION
[State the Location(s) at which Isolation has been established (whether on the
implementing Safety Coordinator's Equipment or on the System of another User
connected to the implementing Safety Coordinator's Equipment). For each Location,
identify each point of Isolation. For each point of Isolation, state the means by which
the Isolation has been achieved, and whether, immobilised and Locked, Caution
Notice affixed, other safety procedures applied, as appropriate.]
_____________________________________________________________________
________________
_____________________________________________________________________
________________
169 of 199
_____________________________________________________________________
________________
(b)
EARTHING
[State the Location(s) at which Earthing has been established (whether on the
implementing Safety Coordinator's Equipment or on the System of another User
connected to the Implementing Safety Coordinator's System). For each Location,
identify each point of Earthing. For each point of Earthing, state the means by which
Earthing has been achieved, and whether, immobilised and Locked, other safety
procedures applied, as appropriate].
_____________________________________________________________________
________________
_____________________________________________________________________
________________
_____________________________________________________________________
________________
1.3
ISSUE
CANCELLATION
170 of 199
4.
Log
ISC
establishes
isolation on his
equipment
is
ISC
completes
RNSP-I.
Details exchanged
RSC
completes
RNSP-R
RNSP cancellation
process
See
4E
171 of 199
Appendix
4.
Safety
Person
requiring
Safety
Precaution from another User
ISC Implementing
Coordinator
Safety
Person
who
co-ordinates
provision of Safety Precautions
RNSP is now
cancelled
Removal being an
internal matter for
the party the ISC
represents
Section
completed
2.1
172 of 199
4.
Continue from
Appendix 4C
No person will be
so authorised until
proposed test is
completed
(or
cancelled) by the
RSC
If testing
required the
removal of
earthing the
RNSP process is
as set out in
section 25
Earthing
reapplied
not
RNSP cancellation
process
See Appendix 4D
173 of 199
5.
5.1
5.1.1
Reinforcements and extensions to the Transmission Network arise due to many reasons
of which a few are mentioned below:
1. A development on a User's Equipment or Apparatus already connected to the
Transmission Network as a User development.
2. Introduction of a new Connection Point between a User's Equipment or
Apparatus and the Transmission Network.
3. The need to increase Transmission Network capacity, removal of operational
constraints, maintenance of Security Standards and meeting general increases in
Demand.
4. Steady state and transient stability considerations.
5. Cumulative effects of any combination of the above four.
5.1.2
The work of such reinforcement and extension to the Transmission Network may also
involve work at a connecting point (entry or exit) of a Power Station/Distributor to the
Transmission Network.
5.1.3
Configurations of sites will vary hence the data requirements below are broadly phrased.
The interpretation of the requests for data is to be based on what the User owns or has necessary
access to.
Ancillary Services (Power Quality Services)
174 of 199
The provision of Ancillary Services by Generators is critical to the secure operation of the Power
System. The requirement to provide them is compulsory on Generators under the Market Rules,
Grid Code and the Generator Licence.
On all timescales the Generator must provide the SO with its AS capability covering:
1) Reserve and Frequency Control
a) Reserve capability at all operating levels
i) Based on Frequency drop
ii) Response time
iii) Sustainability
b) automatic deloading capability at high frequencies
2) Voltage Control
a) Maximum and minimum MVAr levels
b) MVAr response to Voltage change
3) Black Start
a) This is a compulsory service.
PART-1 - GENERATION
To be furnished by Generators to TCN
5A
THERMAL
I. GENERAL: -
1.
Site:
iii.
Furnish information on means of Coal transport from
mines or means of coal carriage if coal is to be brought from
distance.
iv.
In case of other fuels, furnish details of sources of fuel
and their transport.
v. Water Sources (furnish information on availability of water
for operation of the Power Station).
vi. Environmental (State whether forest, lands mining clearance
areas are affected).
2. Site Map:
(To scale)
175 of 199
II. Connection:
1. Point of connection
MW
Services
Generating Unit:
a) Type
b) Rating (MVA)
c) Terminal Voltage (kV)
d) Rated Power Factor
e) Frequency Response Table
f) Reactive Power capability (MVAr) in the range 0.95 leading
and 0.85 lagging.
g) Short Circuit Ratio
h) Direct axis transient reactance (% on MVA rating)
i) Direct axis sub-transient reactance (% on MVA rating)
176 of 199
5B
Hydro Electric:
1. General:
1. Site
3. Submerged Area
1. Point of connection
177 of 199
Maximum
Minimum
Average
2. Turbine
3. Generating Unit
a) Type
b) Rating (MVA)
c) Terminal Voltage (kV)
d) Rated Power Factor
e) Reactive Power capability (MVAr) in the range of
0.95 leading and 0.85 of lagging.
f) Short Circuit Ratio
g) Direct axis transient reactance (% on rated MVA)
h) Direct axis Sub-transient reactance (% on rated
MVA)
i) Auxiliary Power Requirement
4. Generating
Transformer
Unit
a) Type
b) Rated Capacity (MVA)
c) Voltage Ratio HV/LV
d) Tap change Range (+ % to - %)
e) On-load or off-load tap change
f) Percentage Impedance (Positive sequence at Full
load rating)
General:
178 of 199
a)
b)
c)
d)
e)
f)
g)
h)
Full description including settings for all relays and protection systems installed on the
generating Unit, Generating Unit Transformer, Auxiliary Transformer and electrical motor
of major Equipment listed.
2.
Full description including settings for all relays installed on all outgoing circuits from Power
Station substation switchyard, tie circuit breakers, incoming circuit breakers.
3.
Full description of inter-tripping of Breakers at the point or points of Connection with the
Transmission System.
4.
Most probable fault clearance time for electrical faults on the User's system.
5.
5C.3 Switchyard:
1. In relation to interconnecting transformers between High Voltage Transmission System and
the Generating Unit:
a)
b)
c)
d)
e)
f)
g)
h)
Rated MVA
Voltage Ratio
Vector Group
Positive sequence reactance (maximum, minimum, normal Tap(% on MVA)
Positive sequence resistance (maximum, minimum, normal Tap (% on MVA)
Zero sequence reactance (% on MVA)
Tap changer Range (+ % to - %) and steps
Type of Tap changer (off-load/on-load)
2. In relation to switchgear including circuit breakers, isolators on all circuits connected to the
points of connection:
a) Rated Voltage (KV)
179 of 199
b)
c)
d)
e)
f)
g)
Busbar.
Switchgear.
Transformer Bushings.
Transformer windings.
180 of 199
20. Open Circuit saturation characteristic for various terminal voltages giving the exciting current
to achieve the same.
21. Generating Unit Capability Chart
22. SCADA details
23. Communication details
5D.2 Parameters of Excitation control system:
1. Type of Excitation
2. Maximum Field voltage
3. Minimum Field voltage
4. Rated Field voltage
5. Gain Factor
6. Feedback Strength
7. Time constant for control amplifier
8. Time constant for Exciter
9. Time constant for Feedback
10. Output voltage of control amplifier
11. Maximum Output voltage of control amplifier
12. Minimum Output voltage of control amplifier
13. Details of excitation loop in Block Diagrams showing transfer functions of individual
elements using IEEE symbols along with set values.
14. Dynamic characteristics of over - excitation Limiter
15. Dynamic characteristics of under -excitation Limiter
Note: Using IEEE Committee Report symbols the following parameters shall be furnished: D,
A, BSx, Ka, Ke, Kf, Ta, Yf, Vr(max), Vr(min), Sa, Sb.
5E. Parameters of Governor:
1. Governor average gain (MW/Hz)
2. Speeder motor setting range
3. Time constant of steam or fuel Governor valve
4. Governor valve opening limits.
5. Governor valve rate limits.
6. Time constant of Turbine
181 of 199
7. Governor Block Diagram showing transfer functions of individual elements using IEEE
symbols along with set values.
5F. Plant Performance:
5G
Operational Parameters:
182 of 199
11. Any staffing constraints (e.g. only day and evening shifts are employed so no overnight
operation)
5H Hydroelectric Stations:
I.
General:
Turbine (HP):
Generating Units (MVA):
Generating Unit Transformers (MVA):
Auxiliary Transformers (MVA):
Reservoir Data:
Salient features:
Protection:
183 of 199
1. Full description including settings for all relays and protection systems installed on the
Generating units, Generating Unit transformer, Auxiliary transformer and electrical motor of
major Equipment {included}, but not limited to those listed under General.
2. Full description including settings for all relays installed on all outgoing feeders from Power
Station switchyard, tie breakers, and incoming breakers.
3. Full description of inter-tripping of breakers at the point or points of Connection with the
Transmission System.
4. Most probable fault clearance time for electrical faults on the User's system.
IV.
Switchyard:
1. Interconnecting Transformers:
a)
b)
c)
d)
e)
f)
g)
h)
Rated MVA
Voltage Ratio
Vector Group
Positive sequence reactance for maximum, minimum, normal Tap (% on MVA)
Positive sequence resistance of maximum, minimum, normal Tap (% on MVA).
Zero sequence reactance (% on MVA)
Tap changer Range (+ % to - %) and steps
Type of Tap changer (off-load/on-load)
2. Switchgear (including circuit breakers, Isolators on all circuits connected to the points of
connection):
a)
b)
c)
d)
e)
f)
g)
h)
Bus bar
Switchgear
Transformer Bushings
Transformer Windings
6. Generating Units:
i.
184 of 199
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
m)
n)
o)
p)
q)
Type of Turbine:
a)
b)
c)
d)
iii.
Type:
Operating Head (Mtr.)
Discharge with Full Gate Opening (Cumecs)
Speed Rise on total Load throw off (%)
Parameters of Excitation Control system
(AS APPLICABLE TO THERMAL POWER STATIONS)
iv.
Parameters of Governor
(AS APPLICABLE TO THERMAL POWER STATIONS)
7. Operational parameters:
a)
b)
c)
d)
e)
f)
185 of 199
5I.1
5I.1.1 General:
1. Detailed Project report.
2. Status Report:
a)
b)
c)
d)
e)
Land
Fuel type
Cooling Method
Environmental clearance
Rehabilitation of displaced persons.
Topographical survey
Geological Survey
Land
Environmental clearance
Rehabilitation of displaced persons
186 of 199
187 of 199
6.
To enable the TCN to discharge its responsibilities under its Transmission Licence Conditions by
conducting System Studies and preparation of perspective plans for Demand, Generation and
Transmission Network expansion as detailed under the Grid Code, all Users of the Transmission
Network shall furnish all the data to the TCN from time to time detailed below under Data
Registration Requirement of Sections 8 and 12.
Configurations of sites will vary hence the data requirements below are broadly phrased.
The interpretation of the requests for data is to be based on what the Distributor owns or has
necessary access to.
I.
General:
1. Area map
2. Consumer Data
II.
Connection:
1. Points of connection:
III.
188 of 199
1. Line Data:
2. Sub-station Data:
IV.
Loads:
V.
1. Type of load:
2. Rated voltage:
3. Electrical loading of Equipment:
VI.
1. Peak load and energy forecast for each category of loads for each of the succeeding 5 years.
2. Details of methodology and assumptions on which forecasts are based.
189 of 199
3. If supply is received from more than one sub-station, the sub-station breaks up of peak load
and energy projection for each category of loads for each of the succeeding 5 years along with
estimated daily load curve.
4. Details of load 1MW and above.
a)
b)
c)
d)
e)
General:
1. Distribution map (To scale). Showing all lines up to 11 kV and sub-stations belonging to the
Licensee.
2. Single Line Diagram of distribution system (showing distribution lines from points of
connection with transmission system 132/33 kV Sub-station, 33/11 kV sub-station,
consumer bus if fed directly from Transmission System)
3. Numbering and nomenclature of lines and sub-stations (Identified with feeding Grid substations of the Transmission System and concerned 33/11 kV sub-station of supplier).
4. Monitoring Distribution Losses (Methods adopted for reduction of losses to be stated).
6B.2
Connection:
Loads:
190 of 199
General:
Connection:
Loads:
191 of 199
7.
REQUIREMENTS:
To enable the TCN to discharge its responsibilities under its Transmission Licence by conducting
System Studies and preparation of plans for Demand, Generation and Transmission Network
expansion as detailed under the Grid Code, all Users of the Transmission Network shall furnish
all the data to the TCN from time to time detailed below under Data Registration Requirement
of Sections 8 and 12.
[In pursuance of Sections 8 and 12 of the Grid Code, items in this Appendix must be
included in the yearly 5 year planning study report of TCN and provided to Users (e.g.
Generating Companies, Discos) on an annual basis.]
7A.
192 of 199
3. No. of Circuits:
4. Route length (Circuit KM):
5. Conductor sizes:
6. Line parameters (PU on 100 MVA base (a) Resistance/KM
or ohmic values):
(b) Series Inductive Reactance /KM
(c) Shunt Susceptance/KM
7. Approximate power flow MW & MVAr:
8. Terrain of route:
General:
(a) Single Line Diagram of the Users system from 132 KV bus and above at grid sub-station:
(b) Name of sub-station
(c) Power Station connected
(d) Number and length of Circuits
(e) Interconnecting transformers
(f) Sub-station bus layouts
(g) Power Transformers
(h) Reactive compensation Equipment
1. The details of capacitors installed
2. Additional capacitors to be commissioned along with additional loads.
(i) Lightning Arresters
(j) Bus and/or Line Reactors
193 of 199
Transformers
ii.
Circuits
iii.
Circuit Breakers
iv.
Isolating switches
ii.
iii.
iv.
v.
vi.
vii.
194 of 199
(e) Positive sequence resistance on rated MVA base (max., min. & Normal)
(f) Zero sequence reactance on rated MVA base
(g) Tap change range (+% to -%) and steps
(h) Details of tap changer (off-load/on-load)
(i) Neutral Grounding Transformer/Resistor Values
7B.3.3 Equipment Details: (For all Sub-stations):
(a) Circuit Breakers
(b) Isolating switches
(c) Current Transformers
(d) Potential Transformers
(e) Lightning Arresters
7B.3.4 Relaying and metering:
(a) Relay protection installed for all transformers and Feeders along with their settings and level
of co-ordination with other Users.
(b) Metering Details:
(c) SCADA details
(d) Communication details
7B.4.1 Demand Data: (For all sub-stations)
(a) Demand Profile (Peak and lean load)
i.
Current
ii.
195 of 199
Voltage
Length of circuit
Circuit parameters
PLC facilities
Relaying with inter tripping arrangements to inter trip system breaker at point of
connection to isolate on fault
f) Metering at point of connection.
196 of 199
8.
APPENDIX 8:
CIVIL EMERGENCIES
Upon the declaration of civil emergency affecting the production, transportation and/or
consumption of electrical power by competent authority in Nigeria, it is the obligation on
the TCN to prepare and maintain plans for mitigating the effects of any civil emergency
and fuel security situation, which may occur in accordance with the Electricity Supply
Emergency directive issued by the Industry Regulator. That directive shall describe the
steps which authority might take to deal with an electricity production and supply
emergency situation and sets down the actions which Companies in the Electricity Supply
Industry should plan to take and which may be needed or required in order to deal with
such an emergency.
In an electricity emergency it may become necessary to restrict Users Demand for and
consumption of electricity and may be achieved by one or more of the following
methods:
a)
b)
The issue of order(s) under competent Nigeria Authority requiring restrictions
on consumption by industry, commerce and other Users deem appropriate.
c)
The issue of order(s) under competent Nigeria Authority requiring rotating
disconnections and associated restrictions.
In the event that the Industry Regulator issues directions to TCN to implement rotating
disconnections, the TCN will establish an Emergency Coordinating Centre and as soon as
possible establish communications with such relevant Users as is necessary to ensure
operational liaison. The plans to be implemented will be similar or separate from the
schemes outlined in Section 18 of the Grid Code.
The plans shall make provision for the need to maintain supply, so far as practicable, to
consumers in protected categories. For the purpose of the Grid Code Security
installations, Communication Facilities and Hospitals and other designated Facilities
deemed appropriate by competent Nigeria Authority shall be deemed to be protected
Facility in accordance with the provisions of the Civil Emergency Order.
197 of 199
9.
APPENDIX 9:
9.1
The Nigerian Electricity Regulatory Commission (NERC) shall establish the Grid Code
Review Panel. The Panel shall be responsible for developing and improving the Code through
regular review, consultation, research and the consideration of amendment submissions by Users,
TSP, SO or other interested parties and other methodologies deemed appropriate from time to
time. The funding and maintenance of the Panel shall be the responsibility of the SO, including
the location of the Panels secretariat.
The Panel shall be a standing body to carry out the functions referred to in paragraph 9.2.
9.2
i.
ii.
review all amendments to the Grid Code which NERC or any User or TCN may wish to
submit for consideration by the Panel from time to time;
iii.
publish recommendations as to amendments to the Grid Code that TCN or the Panel
feels are necessary or desirable and the reasons for the recommendations;
iv.
issue guidance in relation to the Grid Code and its implementation, performance and
interpretation when asked to do so by any User;
v.
consider what changes are necessary to the Grid Code arising out of any unforeseen
circumstances referred to it by TCN; and
vi.
consider and identify changes to the Grid Code to remove unnecessary Section(s) or
clause(s) that are of irrelevant to the effective operation of the Nigeria Power System.
9.3
i.
ii.
4 members appointed by TCN from Network , System , Market and Safety Operations of
TCN;
iii.
iv.
3 persons representing Generating Companies one of which must represent hydro Power
Stations;
v.
vi.
vii.
viii.
198 of 199
9.4
The Panel shall establish and comply at all times with its own rules and procedures
relating to the conduct of its business, which shall be approved by NERC. Meetings of the Panel
shall be held at regular intervals and at least every month at such time and place as the Panel shall
decide.
9.5
The Panel shall consult in writing all Industry Stakeholders and Operators which are liable
to be affected in relation to all submitted amendments to the Grid Code and shall review and
discuss all submitted amendments and comments to the Grid Code prior to coming up with
recommendations to amending the Grid Code. The Panel however has the right to treat an
amendment as frivolous in accordance with the Market Rules.
9.6
The Panel through TCN shall establish (and, where appropriate, revise from time to time)
joint working arrangements with industry stakeholders or operators to facilitate the identification,
coordination and implementation of change to their operations consequent on an amendment to
the Grid Code in a full and timely manner. These working arrangements shall be such as to
enable development and evaluation of proposed amendments to the Grid Code, how operators
will proceed in a full and timely manner to changes to their operations consequent to an
amendment to the Grid Code to be made and given effect wherever possible (subject to any
necessary consent of the Nigerian Electricity Regulatory Commission) at the same time as such
approved amendment is made and given effect.
199 of 199