Guide Inspection Plan For CUI
Guide Inspection Plan For CUI
10F (12C) and 350F (175C) for carbon and low alloy steels,
140F (60C) and 400F (205C) for austenitic stainless steels and duplex stainless steels
So in first step, equipments are classified as per material of construction. The equipments falls under above
temperature range are susceptible to CUI with temperature range of 49 0C to 93 0C being the most severe
environment. Also equipments working in cyclic temperature range and equipments which are down for long
time demand special attention.
STEP 2 : DETERMINE THE PURPOSE OF THE INSULATION SYSTEM
Insulation systems are provided for heat conservation, process requirement, personal protection and noise
reduction. Identify the purpose of insulation. With the help of process and operating department, understand the
process environment.
Insulation for personal safety is applicable where exposed surface temperatures exceed 65 0C in normal or short
term operating conditions. As per refinery standards exposed surfaces located within 600mm horizontally or
2100mm vertically of a normal access, walkway work area are to be insulated.
Also contact process department to determine insulation removal is possible in any of the systems. Some time
insulation removal can lead to more corrosion (for eg corrosion due to condensation) or process upsets. But
there are instances where entire insulation is removed due to change in process conditions.
STEP 3: IDENTIFY THE COATING SYSTEM UNDER INSULATION
Till 80s, industry did not understand that the environment under insulation was going to be almost like
immersion conditions so the correct type of coating was not used. As a result almost none of the surface under
insulation older than 15 years is properly protected from CUI. Now it is widely accepted that protective coatings
under insulation are the most effective method for preventing CUI.
Different types of coatings are available for different materials and temperature range (Refer Annexure 2).
Repair or over coating of an installed system requires evaluation of existing coating that remains on the
substrate. Identification of type of coating under insulation will give some idea of CUI happening on metal
surface. So proper documentation of type of coating applied is essential for effective inspection against CUI of
equipment in future.
Some of the points noted are;
Average life of most of the coatings under insulations is observed to be around 8 years.
Inorganic zinc coatings or galvanizing shall not be used under thermal insulation in the 50 to 150C
(120 to 300F) service temperature range for long-term or cyclic service. Zinc provides inadequate
corrosion resistance in closed, sometimes wet environments.
Thermally sprayed aluminum coatings have performed successfully in marine and high temperature
environments
The coating systems recommended for use on carbon steel operating below 150C (300F) under
thermal insulation are typically tank lining systems formulated to prevent corrosion.
Austenitic Stainless Steel coating system shall not contain free, soluble chlorides or other halides after
curing to prevent SCC. Similarly the coating shall not contain zinc, lead, copper, or their compounds due
to the risk of liquid metal cracking.
Aluminum foil wrapping has been used to prevent ESCC of stainless steel under insulation
From the above data it is clear that insulations having inorganic zinc coating need more attention than thermally
sprayed aluminum coatings. Similarly austenitic stainless steel systems without aluminum coating require more
attention.
STEP 4: ASSESS AGE AND APPEARANCE OF INSULATION SYSTEM
It is observed that average life of most of the coatings under insulation is around 8 years where as a properly
maintained insulations lasts for 15 years. So even if insulation appears damage free, corrosion can start on metal
surface due to coating damage if the age of insulating system is more than 8 years. At the same time if the
insulation cladding is damaged chances are more for water ingress which accelerates CUI. So even though age
is the primary concern, appearance of insulation system also needs to be considered during inspection.
Remove all the inspection windows are access the condition of the surface under the window. Special
consideration to be given on the condition of the coating under insulation. If the coating under the
inspection window is good then it is an indication of less CUI in the system.
If there is indication of coating damage or starting of general corrosion under inspection window some
insulation can be removed from the most critical areas. Effect of design, external factors, site condition
and CUI history of the equipment (or similar equipment) shall be considered to identify the critical areas
of CUI. As per various refinery standards and observations, locations in insulated equipments where
CUI can mostly be found are enlisted below.
EFFECT OF DESIGN
1. Equipments with vapor barriers, weatherproofing or protrusions through the insulation or at insulation
termination points such as flanges.
2. Equipment designed with insulation support rings welded directly to the vessel wall; particularly around
ladder and platform clips, and lifting lugs, nozzles and stiffener rings.
3. Locations where moisture/water will naturally collect (gravity drainage) before evaporating (insulation
support rings on vertical equipment) and improperly terminated fireproofing.
4. Dead legs (vents, drains, and other similar items).
5. Pipe hangers and other supports.
6. Valves and fittings (irregular insulation surfaces).
7. Bolted-on pipe shoes.
8. Steam tracer tubing penetrations.
4. Steam discharge
5. Process liquids spillage
6. Spray from fire sprinklers, deluge systems and wash-downs
7. Marine environment/ proximity of sea
8. Proximity of chlorine containing process units
These points should be considered while doing inspection removal. As per OISD standards insulation removal
can be carried out on sample basis in such a way that all the identified locations get inspected at least once in 12
years. Inspection frequencies can also be followed as per annexure 1. Inspector can decide on the extent of
insulation removal to carry out thickness survey and to assess the pipe surface condition as per the frequency
stipulated for the pipeline based on its service.
As a general practice for piping, insulation is opened at the support locations and at elbows, tees and every ten
meters interval if operating temperature is below 150 0C. If operating temperature is above 150 0C insulation
pockets are removed for ultrasonic thickness gauging.
Similarly for Columns / vessels / heat exchangers;
Insulation is opened at the top dish and at insulation support rings in top zone in CUI prone zone.
In all the vertical columns and vessels, insulation is opened at the nozzles/ manways and at sample
Pockets for UT (Ultrasonic thickness) measurements
In the equipment sections operating above 150 0C, the insulation pockets are removed for ultrasonic
thickness gauging.
STEP 6: INSPECTION PLAN FOR AREAS WHERE INSULATION REMOVAL IS NOT PRACTICAL
When insulation removal is not practical, suitable NDT methods can be used. Piping under non accessible
culverts, long stretch of pipe lines where insulation removal is not cost effective etc includes in this list. Some
of the NDT methods that can be used are Long Range Ultrasonic Testing (LRUT), Pulsed Eddy Current
Technique (PEC) and profile radiography.
Long Range Ultrasonic Testing (LRUT) can be used for pipeline inspection where operating temperature is less
than 125 Deg C. A small band of insulation needs to be removed for mounting array of UT transducers band in
LRUT technique. It scans the pipeline longitudinally on both sides of transducer ring using guided ultrasonic
waves. This technique gives the cross-sectional metal loss of pipelines. Technique is suitable for long straight
length pipe.
Pulsed Eddy Current (PEC) may be deployed without removal of insulation on both equipment & pipelines and
average metal wall thickness of the location below the insulation can be measured. PEC technique may also be
used for inspection of fire proofing, skirts/pipelines. Necessary caution to be taken when PEC is used at
projections like nozzle, stiffener ring etc as the projection also generates additional eddy current.
Profile radiography may be used for measuring thickness without removing insulation. Cordoning of the area
for radiography is the main disadvantage.
STEP 7 (FINAL STAGE): Further action can be taken after accessing the condition of metal surface exposed
by the above guidelines. If the metal surface is found to be in good condition there is no need for further
removal of insulation. But if there is indication of CUI, inspector should access the extent of CUI damage and if
necessary, action to be taken for extensive removal of insulation.