Frey Akunuri 2001 PDF
Frey Akunuri 2001 PDF
Frey Akunuri 2001 PDF
Performance, Emissions, and Cost of Texaco GasifierBased Integrated Gasification Combined Cycle
Systems Using ASPEN
Prepared by:
H. Christopher Frey
Naveen Akunuri
Computational Laboratory for Energy, Air, and Risk
Department of Civil Engineering
North Carolina State University
Raleigh, NC
Prepared for:
Center for Energy and Environmental Studies
Carnegie Mellon University
Pittsburgh, PA
January 2001
INTRODUCTION................................................................................................. 1
1.1
1.2
Gasification ..................................................................................... 5
1.1.2
1.3
1.4
Objectives.................................................................................................. 17
1.5
1.6
2.0
1.5.2
1.5.3
1.5.4
1.5.5
Probabilistic Analysis.................................................................... 24
Gasification ............................................................................................... 28
3.0
2.2
2.3
2.4.
2.5
2.6
Combined Cycle........................................................................................ 34
3.2
Major Process Sections in the Radiant and Convective IGCC Model ...... 40
3.2.1
3.2.2
Gasification ................................................................................... 42
3.2.3
3.2.4
3.2.5
3.2.6
Steam Cycle................................................................................... 72
3.2.7
3.3
Convergence Sequence.............................................................................. 86
3.4
Environmental Emissions.......................................................................... 87
3.4.1
NOx Emissions............................................................................... 88
3.4.2
ii
4.0
3.4.3
3.4.4
4.2
Gasification ............................................................................................... 93
4.3
4.4
4.3.1
4.3.2
4.3.3
Selexol........................................................................................... 96
4.3.4
4.3.5
4.3.6
4.3.7
Steam Cycle................................................................................... 97
4.3.8
General Facilities........................................................................... 98
iii
5.0
5.1.2
5.1.3
5.1.4
5.1.5
5.1.6
5.1.7
5.1.8
5.1.9
5.3
5.4
5.5
iv
6.0
7.0
6.1
6.2
7.1.2
7.1.3
7.1.4
7.2
7.3
7.4
7.4.2
7.4.3
8.0
9.0
8.1
8.2
9.1.2
9.1.3
9.1.4
9.1.5
9.2
9.3
9.4
9.5
9.6
10.0
9.5.1
9.5.2
9.5.3
11.0
vii
LIST OF TABLES
Table 1.1
Table 3.1
Table 3.2
Table 3.3
Table 3.4
Table 3.5
Table 3.6
Table 3.7
Table 3.8
Table 3.9
Table 4.1
Table 5.1
Table 5.2
Table 6.1
Table 6.2
Table 6.3
Summary of Cost Model Results for the Example Case Study (1998
Dollars) ...................................................................................................... 126
viii
Table 7.1
Table 7.2
Table 7.3
Table 7.4
Table 7.5
Table 8.1
Summary of the Base Case Parameters Values for the Texaco Coal
Gasification Total Quench System ............................................................ 161
Table 8.2
Table 8.3
Summary of Cost Model Results for the Example Case Study (1998
Dollars) ...................................................................................................... 163
Table 9.1
Table 9.2
Table 9.3
Table 9.4
Table 9.5
Selected Outputs Collected by the Model for Uncertainty Analysis ......... 194
Table 9.6
Selected Outputs Collected by the Model for Uncertainty Analysis ......... 195
Table 9.7
Table 9.8
Table A.1
Table A.2
LIST OF FIGURES
Figure 1.1
Figure 1.2
Figure 1.3
Figure 2.1
Figure 2.2
Figure 2.3
Figure 3.1
IGCC System............................................................................................... 39
Figure 3.2
Figure 3.3
Figure 3.4
Figure 3.5
Figure 3.6
Figure 3.7
Figure 3.8
Figure 3.9
Figure 5.1
Direct Cost for the Coal Handling and Slurry Preparation Process
Area............................................................................................................ 107
Figure 7.1
Figure 7.2
Figure 7.3
Figure 7.4
Figure 7.5
Figure 7.6
Figure 7.7
Power Requirement for the Gasification Section for Total Quench.......... 151
Figure 7.8
Figure 9.1
Figure 9.2
Figure 9.3
Figure 9.4
Figure 9.5
Figure 9.6
Figure 9.7
Figure 9.8
Figure 9.9
Figure 9.10 Comparison of Probabilistic Results for Cases 1 and 4 for the
Levelized Cost of Electricity for Radiant and Convective Model............. 209
Figure 9.11 Comparison of Probabilistic Results for Cases 2 and 5 for the
Levelized Cost of Electricity for Radiant and Convective Model............. 210
Figure 9.12 Comparison of Probabilistic Results for Cases 3 and 6 for the
Levelized Cost of Electricity for Radiant and Convective Model............. 210
xii
Figure 9.13 Comparison of Probabilistic Results for Cases 1 and 4 for the
Levelized Cost of Electricity for Total Quench Coal Model..................... 211
Figure 9.14 Comparison of Probabilistic Results for Cases 2 and 5 for the
Levelized Cost of Electricity for Total Quench Coal Model..................... 212
Figure 9.15 Comparison of Probabilistic Results for Cases 3 and 6 for the
Levelized Cost of Electricity for Total Quench Coal Model..................... 212
xiii
1.0
INTRODUCTION
This study deals with the development and application of new systems models for
estimating the performance, emissions, and cost of selected gasification-based power
generation systems, including characterization of uncertainty in the estimates.
Gasification technologies and their commercial status are briefly reviewed with a focus
on gasification of coal. The study focuses on modeling and assessment of two Texaco
gasifier-based Integrated Gasification Combined Cycle (IGCC) systems using ASPEN.
ASPEN is a steady-state chemical process simulator.
The systems models enable the evaluation of the interactions among various
process areas within the IGCC systems, as well as the performance and cost of alternative
system designs based upon different gas cooling approaches. The technical bases for the
models are briefly presented. For each of the systems modeled detailed information is
given regarding the process performance, auxiliary power, net plant output, plant
efficiency, emissions, capital cost, annual cost, and levelized cost calculations.
pollutant emissions, and capital, annual, and levelized costs. The key uncertainties with
respect to plant efficiency and cost are identified. The Texaco gasifier-based IGCC
models are intended for use as benchmarks in comparisons with other coal/fuel-based
power generation systems, models for many of which have been developed in previous
work (Frey and Rubin, 1990; Frey and Rubin, 1991; Frey and Rubin, 1992a; Frey and
Rubin, 1992b; Frey, 1994; Frey and Williams, 1995; Frey et al, 1994; Agarwal and Frey,
1995; Agrawal and Frey, 1997; Bharvirkar and Frey, 1998). Thus, the models presented
here are several of a set of complimentary models that enable comparisons of competing
systems for strategic planning purposes.
1.1
Gasification systems are a promising approach for clean and efficient power
generation as well as for polygeneration of a variety of products, such as steam, sulfur,
hydrogen, methanol, ammonia, and others (Philcox and Fenner, 1996). As of 1996, there
were 354 gasifiers located at 113 facilities worldwide. The gasifiers use natural gas,
petroleum residuals, petroleum coke, refinery wastes, coal, and other fuels as inputs, and
produce a synthesis gas containing carbon monoxide (CO), hydrogen (H2), and other
components. The syngas can be processed to produce liquid and gaseous fuels, chemicals,
and electric power. In recent years, gasification has received increasing attention as an
option for repowering at oil refineries, where there is currently a lack of markets for lowvalue liquid residues and coke (Simbeck, 1996).
Feedstock
Oxidant
Gasifier
Raw
Syngas
Gas Cooling
Water/Steam
Cooled
Syngas
Gas Scrubbing
Section
Cooled
Syngas
Slag
Electricity
Gas Turbine
Saturated
Syngas
Fuel Gas
Saturation
Clean
Syngas
Acid Gas
Removal
Section
Boiler Feed
Water
Gas Turbine
Exhaust Gas
Electricity
Steam Turbine
Steam
Waste Water
Heat Recovery
Steam Generator
Air
Process Water
Treatment
Reclaimed Water
Exhaust Gas
Acid Gas
Sulfur
Recovery Plant
Tail Gas
Tail gas
Treatment
Plant
Figure 1.1
Elemental
Sulfur
Off
Gas
1.1.1
Gasification
for gasification reactions, which occur primarily in the central zone of the reactor. Steam
is also introduced near the bottom of the gasifier. As the hot gases from combustion and
gasification move upward, they come into contact with the fuel introduced at the top. The
heating of the fuel at the top of the reactor results in devolatilization, in which lighter
hydrocarbon compounds are driven off and exit as part of the syngas. Because the gases
leaving the gasifier contact the relatively cool fuel entering the gasifier, the exit syngas
temperature is relatively low compared to other types of reactors. The counter-current
flow of fuel with the oxidant and steam can result in efficient utilization of the fuel, as
long as the residence time of the fuel is long enough for even the larger particles to be
fully consumed. Ash and unconverted fuel exit the bottom of the gasifier via a rotating
grate.
An overall measure of gasifier performance is the cold gas efficiency. The cold
gas efficiency is the ratio of the heating value of "cold" syngas, at standard temperature,
to the heating value of the amount of fuel consumed required to produce the syngas. The
cold gas efficiency does not take into account recovery of energy in the gasifier such as
through steam generation or associated with sensible heat of the syngas at high
temperatures. Moving bed gasifiers tend to have very high cold gas efficiencies, with
values in the range of 80 to 90 percent.
Typical examples of such reactors are Lurgi dry bottom gasifiers and the British
Gas/Lurgi slagging gasifiers.
o
o
The reactors have a narrow temperature range of 1800 F to 1900 F. The fluidized
bed is maintained at a nearly constant temperature, which is well below the initial ash
fusion temperature to avoid clinker formation and possible defluidization of the bed.
Unconverted coal in the form of char is entrained from the bed and leaves the gasifier
with the hot raw gas. This char is separated from the raw gas in the cyclones and is
recycled to the hot ash agglomerating zone at the bottom of the gasifier. The temperature
in that zone is high enough to gasify the char and reach the softening temperature for
some of the eutectics in the ash. The ash particles stick together, grow in size and become
dense until they are separated from the char particles, and then fall to the base of the
gasifier, where they are removed.
raw gas leaves from the bottom of the reactor at high temperatures of 2300 oF and greater.
The raw gas has low amounts of methane and no other hydrocarbons due to the high
syngas exit temperatures.
The entrained flow gasifiers typically use oxygen as the oxidant and operate at
high temperatures well above ash slagging conditions in order to assure reasonable
carbon conversion and to provide a mechanism for slag removal (Simbeck et al., 1983).
Entrained-flow gasification has the advantage over the other gasification designs in that it
can gasify almost all types of coals regardless of coal rank, caking characteristics, or the
amount of coal fines. This is because of the relatively high temperatures which enable
gasification of even relatively unreactive feedstocks that might be unsuitable for the
lower temperature moving bed or fluidized bed reactors. However, because of the high
temperatures, entrained-flow gasifiers use more oxidant than the other designs. The cold
gas efficiency is approximately 80 percent (Supp, 1990). Typical examples of such
reactors are Texaco Gasifiers and Destec Gasifiers.
The advantage of adopting entrained flow gasification over the above mentioned
reactors is the high yield of synthesis gas containing insignificant amounts of methanol
and other hydrocarbons as a result of the high temperatures in the entrained-flow reactors.
as heat moderator, the gasifier can be operated at higher pressures than other types of
entrained-flow gasifiers. Higher operating pressure leads to increased gas production
capability per gasifier of a given size (Simbeck et al., 1983)
1.1.2
The design of the high temperature syngas cooling process area depends on the
type of gasifier used. The gas cooling requirements for entrained flow gasification
systems are more demanding than for other gasification systems as the former produce
syngas at higher temperatures. Typically, the gas cooling process for systems employing
entrained flow gasification systems either use heat exchangers to recover thermal energy
and generate steam or use water quenching. The former design can be radiant and
convective or radiant only, while the latter is known as total quench high temperature gas
cooling. The former is more efficient as it can produce high temperature and pressure
steam, whereas the latter is much less expensive (Doering and Mahagaokar, 1992).
10
The syngas from the radiant heat exchanger flows into a convection type of heat
exchanger. In the convective heat exchanger, the syngas flows across the boiler tube
banks. These tubes help remove the entrained particles in the syngas that are too fine to
drop out in the bottom of the radiant cooler. High pressure steam is generated in these
tubes. The cooled gas leaves the convective chamber at a temperature of approximately
650 oF.
11
Coal/Water Slurry
and Oxygen
Refractory Lining
Gasifier
High-Pressure
Steam Generation
650 F Gas
To Low Temperature
Gas Cooling
And Scrubbing
Radiant
Heat
Exchanger
Convective
Heat
Exchanger
1500 F
Slag Quench
Chamber
Slag
Figure 1.2
12
slag and the raw gas are quenched in the water pool at the bottom of the radiant cooler.
The cooled slag is removed from the cooler for disposal. The raw gas, saturated with
moisture, flows out of the radiant cooler at a temperature of approximately 400 oF.
13
Coal/Water Slurry
and Oxygen
Refractory Lining
Gasifier
~430 F Gas
To Scrubbing
Water Quench
Chamber
Slag
Figure 1.3
In this study, both the radiant and convective and the total quench high
temperature syngas cooling designs are evaluated. The radiant and convective design has
the advantage over total quench syngas cooling of a higher plant efficiency. However, the
cost of the radiant and convective design is higher than that of the total quench design.
The total quench design results in increased moisturization of syngas, which can prove
effective in terms of preventing NOX formation in the gas turbine combustor and in terms
of augmenting power production from the gas turbine. In a water quench system, large
quantities of water are used and thus contaminated by the slag, requiring complex
primary and secondary treatment facilities. Hence total quench design has additional
14
operating problems such as those caused due to increased water treating facilities,
increased discharge water permitting issues, and added operating and maintenance costs
when compared to radiant and convective design (Doering and Mahagaokar, 1992).
1.2
The IGCC concept has been demonstrated commercially. Table 1.1 lists the IGCC
plants currently in operation or undergoing construction. The Texaco coal gasification
process has been successfully used in a number of chemical plants since the early 1980s
for the production of synthesis gas from coal. A Texaco-based 95 MW IGCC power plant
was operated successfully from 1984 to 1988 in California (Simbeck et al., 1996). API
Energia, a joint venture of Asea Brown Boveri and API, adopted Texaco gasification to
gasify visbreaker residue from an API refinery to produce steam and power. Tampa
Electric Companys Polk Power station also utilizes Texaco gasification, gasifying about
2,000 tons of coal per day to produce 250 MW of power. The El Dorado gasification
project demonstrates that hazardous waste streams can be converted by gasification to
valuable products. (Farina et al., 1998).
15
and the Sarlux plant in Italy using low pressure (38 barg) Texaco gasification to produce
hydrogen and/or steam along with power (Bjorge et al., 1996).
Table 1.1
Plant
Size
Project
Location
Products
Gasifier
Fuel
Cool Water
IGCC
PSI Wabash
River
Tampa
Electric
Pinon Pine
Sierra Pacific
Texaco
El Dorado
Shell Pernis
Barstow,
California
Terre Haute,
Indiana
Polk, Florida
1984
120 MW
Power
Texaco
Coal
1996
262 MW
Power
Destec
Coal
1996
250 MW
Power
Texaco
Coal
Sparks,
Nevada
El Dorado,
Kansas
Netherlands
1996
100 MW
Power
KRW
Coal
1996
40 MW
Texaco
Pet Coke
1997
120 MW
Shell/Lurgi
Oil
Sarlux
Sarroch,
Italy
Falconara
Marittima
1998
550 MW
Texaco
Oil
1999
234 MW
Co-generation
Steam and H2
Co-generation
H2
Co-generation
Steam
Power
Texaco
Oil
1997
335 MW
Power
Prenflo
Coal
API Energia
Puertallano
1.3
Motivating Questions
In order to study the benefit and risks of a new process technology, there is a need
for the development of a systematic approach for technology assessment. The
performance, emissions and costs of individual IGCC systems need to be characterized as
a basis for comparison with conventional and with other advanced alternatives. There is
also a need to develop a baseline case study of an existing commercial IGCC technology
for comparison with other more advanced (less commercial) IGCC systems in future
technology studies. The present study deals with the study of an existing commercial
IGCC technology and has the following motivating questions.
16
1.
What are the thermal efficiencies, emissions, and costs of selected entrained-flow
gasification-based IGCC systems when fueled by coal?
2.
How does the design of the high temperature gas cooling system of a coal-fueled
IGCC system affect the performance, emissions, and costs?
3.
What are the uncertainties in the point estimates assumed for the IGCC systems?
4.
What are the key sources of uncertainty in the performance, emissions, and costs
of the technologies?
1.4
Objectives
To develop new systems models based upon the best available information
regarding process performance, emissions and cost for the following
configurations:
(a)
(b)
2.
3.
17
4.
1.5
performance, emissions and costs of two IGCC systems and the integration of the
performance and cost models. The requirement for a probabilistic analysis of the models
developed is also discussed.
1.5.1
The Federal Energy Technology Center (FETC) of the U.S. Department of Energy
has developed a number of performance simulations of IGCC systems in the ASPEN
modeling environment. A number of these models have been refined by Frey and others
(Frey and Rubin, 1991, Frey et al., 1994, Frey, 1998) in order to calculate mass and
energy balances for IGCC systems, conduct sensitivity analyses of performance
parameters, track environmental species, and evaluate design modifications. Subroutines
that calculate capital, annual, and levelized costs have also been developed and
incorporated with the refined performance models.
18
The Texaco gasifier-based IGCC system models developed in this study are based
primarily on the general configuration and design basis of a study sponsored by the
Electric Power Research Institute (EPRI) (Matchak et al., 1984). K.R. Stone developed a
process simulation model based on the radiant and convective high temperature gas
cooling design in 1985 at FETC. This FETC model has been substantially refined for this
study.
The IGCC simulation models of radiant and convective gasifier design and total
quench high temperature gas cooling design developed in the present study are intended
to predict the output values of process performance measures (e.g., plant thermal
efficiency) for a given set of input assumptions. The key refinements to the earlier FETC
model, which are also incorporated into the new model of the total quench based system,
include complete replacement of the gas turbine flowsheet with a more detailed model,
implementation of a more detailed fuel gas saturation model, incorporation of NOx
emissions as a model output, refinement and more comprehensive inclusion of auxiliary
power demand estimates, and implementation of a capital, annual, and levelized cost
model. The key improvements to the original FETC model of the radiant and convective
based system are described in more detail for the gas turbine and the cost model in
Chapters 3.0 and 5.0 and the auxiliary power consumption models are elaborated upon in
Chapter 4.0.
19
1.5.2
20
A design specification is used for feedback control. The user can set any
flowsheet variable or function of flowsheet variables to a particular design value. A feed
stream variable or block input variable is designated to be manipulated in order to achieve
the design value. FORTRAN statements can be used within the design specification block
to compute design specification function values.
FORTRAN blocks are used for feedforward control. Any FORTRAN operation
can be carried out on flowsheet variables by using in-line FORTRAN statements that
operate on these variables. FORTRAN blocks are one method for incorporating user code
into the model. It is also possible to call any user-provided subroutine from either a
design specification or FORTRAN block.
21
The models developed here are intended to estimate the costs of innovative coal-toelectricity systems for the purpose of evaluating the comparative economics of alternative
process configurations. The models are intended to be used only for preliminary or study
grade estimates using representative (generic) plant designs and parameters.
In the electric utility and chemical process industries, there are generally accepted
guidelines regarding the approach to developing cost estimates. The Electric Power
Research Institute has defined four types of cost estimates: simplified, preliminary,
detailed, and finalized. The cost estimates developed in this work are preliminary
(EPRI, 1986). Preliminary cost estimates are appropriate for the purposes of evaluating
alternative technologies, and for research planning. These cost estimates are sensitive to
the performance and design parameters that are most influential in affecting costs (Frey
and Rubin, 1990).
One of the major constraints on the development of the cost model is the
availability of data from which to develop cost versus performance relationships for
specific process area or for major equipment items. Data from published studies can be
used to develop cost models for specific process areas using regression analysis (Frey and
Rubin, 1990).
The new cost models developed for each of the three technologies evaluated in
this work include capital, annual, and levelized costs. The models estimate the direct
22
capital costs of each major plant section as a function of key performance and design
parameters. The total capital cost is calculated based on direct and indirect capital costs.
The total direct cost is a summation of the plant section direct costs and general facilities
cost. The total indirect cost is the sum of indirect construction costs, engineering and
home office fees, sales tax, and environmental permitting costs. The latest process
contingency factors have been incorporated in the cost model and are included in the total
capital cost.
The annual cost model includes both fixed and variable operating costs. Fixed
operating costs include operating labor, maintenance labor and materials, and overhead
costs associated with administrative and support labor. The latest maintenance cost
factors have been included in the cost model in order to calculate process area annual
maintenance cost. Variable operating costs include fuel, consumables, ash disposal, and
byproduct credits. The operating costs are estimated based on 31 cost parameters such as
unit prices and costs (Frey and Rubin, 1990).
1.5.4
The cost model has been developed as a FORTRAN subroutine, which is linked
to the ASPEN simulation model. The cost model obtains approximately 50 to 60 process
variables from the ASPEN performance model for use in both the capital and annual cost
calculations. Newly developed regression models are used to calculate the auxiliary
power requirements for many of the process areas. The overall plant efficiency is
23
calculated in the cost model subroutine taking into account the gross gas turbine and
steam turbine output and the auxiliary power demands.
1.5.5
Probabilistic Analysis
and cost of new process technologies are often significantly biased toward optimistic
outcomes (Merrow et al., 1981).
gasification and other advanced power generation and environmental control systems
(e.g., Frey and Rubin 1992; Frey et al., 1994).
1.6
The organization of the report is as per the following order. Chapter 2 provides a
technical background for Texaco gasifier-based IGCC systems. Chapter 3 elaborates on
25
the development of the performance model of a coal-fueled IGCC system with Texaco
gasifier with radiant and convective design. Chapter 4 documents the auxiliary power
consumption models of the IGCC plant developed in Chapter 3. The direct capital costs
of the IGCC system with the radiant and convective high temperature gas cooling design
are modeled in Chapter 5. The model developed in Chapters 3 to 5 is applied to a
deterministic case study in Chapter 6. Chapters 7 discusses the development of the
performance, emissions, and costs of a coal-fueled Texaco gasifier-based IGCC system
with total quench high temperature gas cooling. Chapter 8 provides the results of
applying the model developed in Chapter 7 to a deterministic case study. Chapter 9
discusses the uncertainty analysis performed on the three IGCC models developed in the
present study. Chapter 10 presents the conclusions obtained from the current study.
26
2.0
This study describes performance and cost models for two Texaco gasifier-based
IGCC systems: (1) radiant and convective high temperature syngas cooling using coal;
and (2) total quench high temperature syngas cooling using coal. IGCC systems for
radiant and convective model and total quench model are illustrated schematically in
Figure 1.1. The fuel is fed to the gasifier in a slurry in the case of coal being used as
feedstock. Oxygen is used to combust only a portion of the feedstock in order to provide
thermal energy needed by endothermic gasification reactions. The raw syngas leaves the
gasifier at approximately 2400 oF and cooled either by a series of radiant and convective
heat exchangers to a temperature of 650 oF or by contact with water to a temperature of
433 oF. The syngas passes through a wet scrubbing system to remove particulate matter
and water soluble gases such as NH3.
The scrubbed gas is further cooled to 101 oF prior to entering a Selexol acid gas
separation unit. H2S and COS are removed from the syngas in the Selexol unit and sent to
a Claus plant and a Beavon-Stretford tail gas treatment unit for sulfur recovery. The clean
gas is reheated and saturated with moisture prior to firing in a gas turbine. The saturation
helps prevent formation of thermal NOx during combustion. The hot gas turbine exhaust
passes through a Heat Recovery Steam Generator (HRSG) to provide energy input to a
steam turbine bottoming cycle. Both the gas turbine and the steam turbine generate
power.
27
Gasification
Texaco gasification can handle a wide variety of feedstocks including coal, heavy
oils, and petroleum coke (Preston, 1996). The current study focuses on IGCC systems
using coal feed. The feed coal is crushed and slurried in wet rod mills. The coal slurry
containing about 66.5 weight percent solids is fed into the gasifier, which is a open,
refractory-lined chamber, together with a feed stream of oxidant. The slurry is transferred
to the gasifier at high pressure through charge pumps. The water in the coal slurry acts as
a temperature moderator and also as a source of hydrogen in gasification (Simbeck et al.,
1983). Oxygen is assumed as the oxidant for the IGCC systems evaluated in this study.
The oxidant stream contains 95 percent pure oxygen. The oxygen is compressed to a
pressure sufficient for introduction into the burner of the Texaco gasifier (Matchak et al.,
1984).
o
Gasification takes place rapidly at temperatures exceeding 2300 F. Coal is
partially oxidized at high temperature and pressure. Figure 2.1 demonstrates the
temperature variation across the gasifier (Simbeck et al., 1983). The combustion zone is
near the top of the reactor, where the temperature in the gasifier changes from
o
approximately 250 to 2500 F. As a result, a raw gas composed mainly of carbon dioxide,
carbon monoxide, hydrogen, and water vapor is produced. The syngas contains soot
particles. The syngas leaves the gasifier at temperatures in the range of 2300 oF to 2700
28
contains smaller amounts of methane than other types of gasifiers and is free of tars and
other hydrocarbons (Simbeck et al., 1983).
Coal/Water Slurry
and Oxygen
Gasifier
Top
Coal
Steam,
Oxygen,
or Air
Gasifier
Gasifier
Bottom
0
500
1000
1500
2000
Temperature, F
Syngas
and
Slag
Figure 2.1
29
2500
2.2
the gasifier is initially cooled in a radiant heat exchanger. High pressure steam is
generated in tubes built into the heat transfer surface at the perimeter of the cylindrical
gas flow zone. Molten slag entrained in the raw gas drops into a water quench pool at the
bottom of the radiant gas cooler, where it is cooled and removed for disposal. The gas
o
leaves the radiant cooler at a temperature of approximately 1500 F, and enters a
convective heat exchanger. In the convective gas cooler, the gas flows across boiler tube
banks, where high pressure steam is generated. The syngas leaves the convective cooler at
a temperature of approximately 650 oF, and flows to the gas scrubbing unit.
In the total quench case, the hot gas is cooled in a water spray chamber and then
directly quenched in a quench pool at the bottom of the gasifier and is cooled to a
temperature of 433oF before it flows to the gas scrubbing unit.
2.3
scrubbing unit, where it is washed with water to remove fine particles. The particle-laden
water is sent to a water treatment plant and used again as quench water. The scrubbed gas
enters various heat exchangers in the low temperature gas cooling section. The heat
removed from the syngas is utilized to generate low-pressure steam to heat feed water or
as a source of heat for fuel gas saturation.
30
2.4.
removal section of the plant. The acid gas removal system employs the Selexol process
for selective removal of hydrogen sulfide (H2S) and carbonyl sulfide (COS). Usually COS
is present in much smaller quantities than H2S. In this unit, most of the entering H2S is
removed by absorption in the Selexol solvent, with a typical removal efficiency of 95 to
98 percent (Simbeck et al., 1983). Typically only about one third of COS in the syngas
will be absorbed. H2S and COS stripped from the Selexol solvent, along with sour gas
from the process water treatment unit is sent to the Claus sulfur plant for recovery of
elemental sulfur.
2.5
turbine combustor fired on syngas. To control the formation of thermal NOx, water vapor
must be introduced along with the cleaned gas into the combustors of gas turbines. The
water vapor lowers the peak flame temperatures. The formation of NO from nitrogen and
oxygen in the inlet air is highly temperature sensitive. Lowering the peak flame
temperature in the combustor by introducing water vapor results in less formation of
thermal NO and hence, lower NO emissions.
31
Another advantage of fuel gas moisturization is to increase the net power output
of the gas turbine. The introduction of moisture into the syngas lowers the syngas heating
value and requires an increase in fuel mass flow in order to deliver the same amount of
total heating value to the gas turbine engine. Because the mass flow of combustor gases is
constrained by choked flow conditions at the turbine inlet nozzle, the inlet air flow has to
be reduced to compensate for the increased fuel flow. This results in less power
consumption of power by the gas turbine compressors, resulting in an increase in the net
gas turbine output.
The saturation of fuel gas takes place in a saturator vessel, which is adiabatic. The
clean gas from the acid gas removal system enters the saturator from the bottom while hot
water, which is at a higher temperature than that of the syngas, is sprayed from the top of
o
the vessel, as shown in Figure 2.2. The typical temperature of the hot water is 380 F,
while that of the syngas is 85 oF before saturation. The saturated gas is heated to a
temperature of approximately 350 oF and exits from the saturator from the top of the
vessel while the hot water gets cooled and exits from the bottom of the vessel. The heat
needed for heating the water is transferred from low temperature gas cooling units and the
heat recovery steam generators to the fuel gas saturation unit as shown in Figure 2.3. A
portion of the cold water leaving the fuel gas saturator is sent to heat exchangers in low
temperature gas cooling section, where it get heated while cooling the hot syngas from
the gas scrubbing section. The remaining portion of cold water is heated by heat
exchange with boiler feedwater from the heat recovery steam generation system. Both the
32
portions of heated water are combined to form the hot water spraying from the top of the
saturator vessel. The clean, medium BTU gas from the fuel gas saturator is combusted in
the gas turbine combustors.
Saturated
Syngas
Water Spray
Hot
Water
Saturator
Syngas
Cold
Water
Figure 2.2
33
Heat Exchanger
Syngas in LTGC
Section
Cooled Syngas
Mixer
Saturated
Syngas
Hot Water
Saturator
Clean Syngas
from
Selexol
Cold Water
Heat Exchanger
Splitter
Figure 2.3
2.6
Combined Cycle
A combined cycle system is composed of a gas turbine and a bottoming steam
cycle. Both the gas turbine and the steam turbine provide shaft energy to a generator for
production of electricity. The gas turbine primarily consists of a compressor, a
combustor, and an expander. The compressor supplies required air to the combustor. The
combustor is divided into a section for stoichiometric adiabatic combustion of the fuel
gas and a subsequent section for quench of the primary combustion products with
secondary air. The gases exiting the quench stage of the combustor are at the turbine inlet
temperature. The hot exhaust gases from the gas turbine combustors are at a temperature
o
of 2350 F. The hot gases are sent to the gas turbine expanders, which in turn drive the
generators.
34
If the gas turbine design is used for syngas as well as for natural gas, then the total
mass flow through the turbine is more or less equal in both the cases. However, the
heating value of natural gas is higher than the heating value of syngas. Therefore, the fuel
flow rate for syngas is significantly larger than that for the natural gas. Typically, the
mass flow at the turbine inlet nozzle is limited by choking. Therefore, an increase in the
fuel mass flow rate must be compensated by a reduction in the compressor air flow rate,
for a given pressure ratio and firing temperature. This causes a net reduction in the power
consumed by the compressors leading to a net increase in the gas turbine output.
The hot gas turbine exhaust gases enter the heat recovery steam generator (HRSG)
process area. The heat recovery steam generator system has gas-gas heat exchangers that
recover the sensible heat from the hot exhaust gases. The HRSG consists of a superheat
system including reheaters, high pressure evaporators, and boilers. High pressure steam is
generated in the superheat steam system using the heat recovered from the hot turbine
exhaust gases. This unit also superheats the high pressure saturated steam generated in the
high temperature gas cooling unit in the radiant and convective cooling process. The
exhaust gases that have been cooled flow out of the heat recovery steam generators at
o
o
temperatures in the range of 250 F to 300 F. Most of the steam generated in the HRSGs
is sent to the steam turbines where it is expanded and more electric power is generated. A
portion of steam is sent to the fuel gas saturation unit.
35
3.0
3.1
Process Description
The model of the Texaco gasifier-based IGCC system with radiant and convective
high temperature gas cooling is based primarily on the findings of a study sponsored by
the Electric Power Research Institute (Matchak et al., 1984). This study provides
extensive information on the mass flows, temperatures, and pressures of streams, power
production and consumption, and costs associated with each process section of the plant.
Thus it provides comprehensive and internally consistent information for use in model
development.
36
The model presented in this study is based upon a previous model developed by
K.R.Stone in 1985 for FETC. The modifications that were made to the previous model
include incorporation of a new and more detailed model of the gas turbine,
implementation of a fuel gas saturation model, modeling of NOX emissions, incorporation
of refined auxiliary power consumption estimates, and implementation of a capital,
annual, and levelized cost model.
The present model consists of slurry preparation units, a gasification unit, high
temperature gas cooling, particulate removal and ash removal, low temperature gas
cooling unit, fuel gas saturator and acid gas removal section, byproduct sulfur production,
and combined-cycle power system as shown in Figure 3.1. In addition to these units, the
model also incorporates auxiliary support facilities such as those that collect and treat
utility waste water.
37
Coal
Slurry
Gasifier
Air or
Oxygen
Hot
Fuel
Gas
High
Temperature
Gas
Gas
Cooled
Cleanup
Cooling
Gas
Acid
Gas
Sulfur
Recovery
Sulfur
Clean Fuel
Gas
Ash
Combustor
Air
Gas
Turbine
Compressor
Generator
39
Hot Exhaust
Electricity
Boiler Feed
Water
Stack
Flue Gas
Heat
Recovery
Steam
Generator
Steam
Steam
Turbine
Generator
Water
Figure 3.1
IGCC System
3.2
The major flowsheet sections in the process are described below. Each major
process section is referred to as a flowsheet. Within each flowsheet, unit operation
models represent specific components of that process area. There are user-specified
inputs regarding key design assumptions for each unit operation model. The numerical
values of the design assumptions are presented in this chapter. However, a user could
substitute other values for these to reflect other design alternatives.
Figure 3.2 illustrates the mass flows in the gasification process area, while Table
3.2 describes the unit operations that are modeled in this process area. The coal slurry
flows through a pump, modeled as a unit operation of the type "PUMP" with a block
identification of "SLURPUMP", to a user-defined unit operation identified as
"COALCONV". The slurry pump serves to raise the pressure of the slurry to 650 psia,
40
which is high enough for introduction into the gasifier, which operates at 615 psia in the
base case scenario. The COALCONV block serves to decompose the coal into its
constituent elements. The portions of the coal that represent soot and slag are modeled as
being removed from the coal by the blocks "MAKESLAG" and "MAKESOOT".
MAKESLAG calculates the heat required to convert a portion of the coal to slag and
MAKESOOT calculates the heat required to convert a portion of the coal to soot. Both of
the heat streams are directed to the gasifier main reactor modeled by the block
"GASIFIER". The equations used in MAKESOOT and MAKESLAG are, respectively,
(3-1)
(3-2)
o
The oxidant feed is modeled to consist of 95 percent pure oxygen at 250 F and
734 psia. The mass flow rate of oxidant is modeled by a design specification, SETOXYG.
SETOXYG varies the flow of oxidant such that the heat loss from the gasifier is less than
one percent of the total heat input to the gasifier. Thus, the ASPEN model calculates the
oxygen flow required to obtain the user specified gasifier outlet temperature and to
overcome this heat loss. The coal slurry and oxidant feed are mixed in the unit operation
block GASIFMIX and sent to the gasification unit modeled by the equilibrium reactor
unit operation block GASIFIER.
41
Table 3.1
Proximate and Ultimate Analysis of the Base Case Illinois No.6 Coal
Proximate Analysis
Moisture
10.00
Fixed Carbon
48.87
Volatile Matter
32.22
Ash
8.91
Ultimate Analysis
Carbon
69.62
Hydrogen
5.33
Nitrogen
1.25
Sulfur
3.87
Oxygen
10.03
Ash
9.90
2,300
12,774
3.2.2 Gasification
The coal slurry and oxidant feed are delivered to the gasifier burners where
gasification takes place. The gasifier is modeled to operate at a design pressure of 615
psia and a design temperature of 2400 oF. The operating temperature is sufficiently higher
than the ash fusion temperature of 2300 oF of the Illinois No. 6 coal to cause the ash to
become molten and separate out easily from the raw gas. The unit operation block
42
GASIFIER simulates the gasification process. A portion of the coal feed burns, providing
heat for the endothermic gasification reactions that result in the formation of CO, CO2,
H2, CH4, and H2S. The chemical reactions modeled in the equilibrium gasifier reactor
model are:
C + 2 H 2 CH 4
(3-3)
C + H 2O CO + H 2
(3-4)
CO + H 2O CO2 + H 2
(3-5)
CH 4 + 1.5 O2 CO + 2 H 2 O
(3-6)
2 CO + O2 2 CO2
(3-7)
S + H2 H 2S
(3-8)
N 2 + 3 H 2 2 NH 3
(3-9)
CO + H 2 S COS + H 2
(3-10)
Ar Ar
(3-11)
Equations (3-3), (3-4), and (3-5) are the primary gasification reactions. Equation
(3-3) is an exothermic reaction and is known as methanation. The formation of methane
increases the heating value of the product gas. Equations (3-4) and (3-5) are endothermic
reactions and are known as watergas and water gas shift reactions respectively, leading to
the formation of hydrogen. Equation (3-6), in series with Equation (3-3), represents the
43
partial combustion of coal and Equation (3-7) in sequence with Equations (3-3) and (3-4),
models the complete oxidation of coal.
44
WSLURRY
SLURPUMP
(PUMP)
SLURRY1
MAKESLAG
(RSTOIC)
QSLAG
RXRIN
GASIFMIX
(MIXER)
OXYGEN
RXROUT
GASIFIER
(RGIBBS)
SLURRY3
SLURRY4
QCONV
MAKESOOT
(RSTOIC)
QSOOT
SLURRY2
QRXR
RADCOOL
(HEATER)
SLAG
SLAGOUT
(SEP2)
QRADCOOL
QRCSPLIT
QRCNET
WARMGAS
COALCONV
(USER)
RAWGAS
SLURRY
TO CONCOOL
IN
SOLIDSEP
FLOWSHEET
Figure 3.2
Gasification Flowsheet
45
TO QMIX
IN
STEAMCYCLE
FLOWSHEET
QRCLOST
Table 3.2
NO
1
BLOCK ID
(ASPEN BLOCK
NAME)
SLURPUMP
(PUMP)
BLOCK
PARAMETERS
TYPE=2
Pressure = 650 psia
Efficiency = 0.65
COALCONV
(USER)
MAKESOOT
(RSTOIC)
Temperature = 59 oF
Pressure drop = 0 psia
MAKESLAG
(RSTOIC)
Temperature = 59 oF
Pressure drop = 0 psia
GASIFMIX
(MIXER)
GASIFIER
(RGIBBS)
RADCOOL
(HEATER)
QRCSPLIT
(FSPLIT)
Temperature = 2400 oF
Pressure = 615 psia
NAT = 6
NPHS = 1
NPX = 2
NR = 9
IDELT = 1
Temperature = 1500 oF
Pressure = 613 psia
FRAC QRCLOST =
0.06
RFRAC QRCNET =
1.0
46
DESCRIPTION
This block simulates CoalWater Slurry Pump, which
delivers slurry to the
gasifier burners.
This block decomposes
coal into its elements
using the subroutine
USRDEC
Simulates the
stoichiometric reaction,
which produces soot based
on the coals ultimate
analysis.
Simulates the
stoichiometric reaction,
which produces slag based
on the coals ultimate
analysis.
Represents a Mixer that
mixes the coal slurry and
the oxidant feed.
This block simulates the
stoichiometric reactions
associated with the
Gasifier Reactor.
Simulates a Radiant
Cooler which lowers the
temperature of the syngas
to 1500 oF from 2400 oF
This block is used to
indicate that some amount
of heat is lost from the
Radiant Cooler.
COMP FRAC
COAL = 1.0
ASH = 1.0
SLAG = 1.0
SOOT = 0.0
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
47
The cooled raw gas from the radiant gas coolers is sent through a separating block,
SLAGOUT, which separates the slag from the rawgas. Carbon conversion indicates the
amount of carbon in the fuel that is in the syngas. The carbon loss refers to the carbon in
the slag, and it is specified as one of the parameters of SLAGOUT. The raw gas, removed
o
of slag, is further cooled to 650 F in the vertical convective syngas coolers, simulated by
block CONCOOL as shown in Table 3.3 and Figure 3.3. The heat stream leaving
CONCOOL is modeled by QCONCOOL. QCONCOOL is a heat stream, obtained by
transferring heat for the cooled syngas, which exits CONCOOL at 650 oF and an output
pressure of 603 psia. QCONCOOL is used for generating additional high pressure (1545
psia) saturated steam to be used in the steam cycle. The cooled raw gas from the
o
convective coolers, modeled by CONGAS, is further cooled to 403 F by a gas-gas heat
exchanger, simulated by the GASCOOL block. QGASCOOL models the heat stream
leaving the GASCOOL block. QGASCOOL is used for simulating the reheating of the
saturated fuel gas, which enters the gas turbine combustor.
Figure 3.3 and Table 3.3 illustrate the particulate scrubbing sections of the model.
The cooled raw gas, which contains particulate matter, enters the particulate scrubbing
unit, modeled by the unit operation block PARTSCRB. The solids in the raw gas are
removed through contact with recycled condensate, modeled by the stream CONDSATE,
from the low-temperature gas cooling section and makeup water. The scrubbed gas,
modeled by the NH3FREE stream, then enters the low-temperature gas cooling section.
48
The solids flow to the ash dewatering unit, simulated by block WWSEP, where the
stream MIXEDWW is filtered to yield an ash cake and water.
49
RAWGAS
FROM SLAGOUT
IN
GASIFIER
FLOWSHEET
CONCOOL
(HEATER)
TO QMIX
IN
STEAMCYCLE
FLOWSHEET
CONGAS
QCONCOOL
FROM
CONDMIX
IN
GASCOOL
FLOWSHEET
GASCOOL
(HEATER)
TO REHEAT
IN
GASCOOL
FLOWSHEET
COOLGAS
ALLCOND
PARTSCRB
(FLASH2)
NH3SEP
(SEP2)
NH3
NH3MIX
(MIXER)
MIXEDWW
SCRUBOUT
PARTFREE
CONDSATE
WWSEP
(SEP2)
NH3FREE
CLCHNG2
(CLCHNG)
QGASCOOL
TO CLCHNG1
IN
GASCOOL
FLOWSHEET
Figure 3.3
50
SOOT
PURGEH2O
Table 3.3
NO
1
2
3
4
BLOCK ID
(ASPEN BLOCK
NAME)
CONCOOL
(HEATER)
GASCOOL
(HEATER)
CLCHNG2
(CLCHNG)
PARTSCRB
(FLASH2)
NH3MIX
(MIXER)
NH3SEP
(SEP2)
WWSEP
(SEP2)
BLOCK
PARAMETERS
DESCRIPTION
Temperature = 650 oF
Pressure = 603 psia
Temperature = 403 oF
Pressure = 598 psia
Simulates a Convective
Syngas Cooler.
Simulates a Fuel Gas
Reheater - Hot Side.
Q=0
Pressure = 572
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
51
cooling water. The condensate from the heat exchangers is collected in the condensate
collection drum, the latter of which is simulated by mixer block CONDMIX. The cooled
gas, stream COLDGAS, is sent to the Selexol acid gas removal unit.
The Selexol unit separates the stream COLDGAS into streams CLEANGAS,
ACIDGAS, and FLASHGAS. ACIDGAS, containing 97.6 percent of H2S by volume is
sent to the mixer, CLAUSMIX, in the Claus plant. The stream FLASHGAS is sent to the
mixer, BSMIX, in the Beavon-Stretford tail gas treatment plant.
The clean gas from the Selexol process, modeled by the stream CLEANGAS,
enters the saturation unit at 85 oF and 429 psia. The details of the modeling of the fuel gas
saturation unit are shown in Figure 3.5 and Table 3.4. The required amount of water to be
added to clean gas to make its moisture content 28.2 % by weight is calculated by a
FORTRAN block SATURH2O. SATURH2O obtains the mass flow of clean gas entering
the saturator block and calculates the required saturated fuel gas mass flow, modeled by
the stream SATGAS. SATGAS is required to be at a temperature of 347 oF which is
achieved by using a design specification SETSATR. SETSATR calculates the required
amount of hot water entering the saturation unit through the block FAKESPLT. This
block splits the hot water stream, HOTH2O into HOTH21 and SATCOM streams.
o
HOTH21 is cooled by a heat exchanger, FAKECOOL, to a temperature of 235 F.
SATCOM and CLEANGAS enter FAKEMIX, which simulates a mixer. The saturated
fuel gas from FAKEMIX, SATGAS1, is heated to the required temperature of 347 oF in
52
the block FAKEHEAT by QHEATS, the heat stream leaving FAKECOOL. As shown in
Figure 2.3, the required amount of circulating water to the saturation unit is maintained
by heating the circulating water in heat exchanger COOL1. A slip stream of high pressure
boiler feed water (BFW) is used to supply the necessary heat to the circulating water
coming out of GASCOOL. The slipstream BFW, the circulating water from GASCOOL
and COOL1 combine to form the hot water, HOTH2O which enters the block
o
FAKESPLT. The fuel gas exits the saturator at 347 F with a moisture content of 28.2
weight percent and is reheated to 570 oF in the block REHEAT with the help of the heat
stream QGASCOOL from the high temperature gas cooling section. The reheated fuel
gas, the stream GTFUEL, flows to the gas turbine combustors.
53
COND1
FROM
CLCHNG2
IN
SOLIDSEP
FLOWSHEET
QCOOL3
QCOOL2
COOL2
(FLASH2)
TOCOOL2
CONDMKUP
COND3
CONDMIX
(MIXER)
ALLCOND
HOTH2O
SATURATION
COOL3
(FLASH2)
SELEXOL
(SEP)
CLEANGAS
QSELEXOL
SATGAS
COLDH2O
TOCOOL3
FLASHGAS
COOL1
(FLASH2)
COLDGAS
QCOOL1
ACIDGAS
CLCHNG1
(CLCHNG)
COND2
TO FGSHTR
IN
HRSG
SECTION
NH3FREE
TOCOOL1
FROM
NH3SEP
IN
SOLIDSEP
FLOWSHEE
T
TO
DEAERATR
IN
STEAMCYCLE
FLOWSHEET
REHEAT
(HEATER)
QGASCOOL
GTFUEL
TO GT-COMP1
IN
GAS TURBINE
FLOWSHEET
GTPOC
FROM GASCOOL
IN
SOLIDSEP
FLOWSHEET
TO QMIX
IN
STEAMCYCLE
FLOWSHEET
TO BOIL100
IN
HRSG
SECTION
Figure 3.4
E2-HRSG
(HEATER)
E2IN
HP-HRSG
(HEATER)
HPIN
TO QMIX
IN
STEAMCYCLE
FLOWSHEET
TO QMIX
IN
STEAMCYCLE
FLOWSHEET
54
SH-HRSG
(HEATER)
QSH-HRSG
LPIN
QHP-HRSG
LP-HRSG
(HEATER)
QE2-HRSG
E1IN
QLP-HRSG
QE1-HRSG
STACKGAS
E1-HRSG
(HEATER)
TO QSPLIT
IN
STEAMCYCLE
FLOWSHEET
QEXCESS
HOTH2O
HOTH21
FROM SELEXOL
IN
GASCOOL
FLOWSHEET
CLEANGAS
FAKEMIX
(MIXER)
Figure 3.5
Table 3.4
FAKECOOL
(HEATER)
COLDH2O
TO FGSMIX
IN
HRSG
SECTION
QHEATS
SATCOM
FAKESPLT
(FSPLIT)
SATGAS1
FAKEHEAT
(HEATER
SATGAS
TO REHEAT
IN
GASCOOL
FLOWSHEET
NO
1
BLOCK ID
(ASPEN BLOCK
NAME)
CLCHNG1
(CLCHNG)
BLOCK
PARAMETERS
COOL1
(FLASH2)
Temperature = 262 oF
Pressure = 567 psia
COOL2
(FLASH2)
Temperature = 130 oF
Pressure = 562 psia
55
DESCRIPTION
This block changes stream
class from MIXCINC to
Conventional.
This block simulates a
heat exchanger, which
reduces the temperature of
o
the syngas to 262 F from
o
323 F across a pressure
drop of 5 psia.
This block simulates a
heat exchanger, which
reduces the temperature of
the syngas to 130 oF from
o
262 F across a pressure
drop of 5 psia.
Temperature = 101 oF
Pressure = 557 psia
CONDMIX
(MIXER)
SELEXOL
(SEP)
FAKESPLT
(FSPLIT)
FAKECOOL
(HEATER)
FAKEMIX
(MIXER)
Temperature = 235 oF
Pressure = 429 psia
10
FAKEHEAT
Temperature = 347 oF
Pressure = 419 psia
11
REHEAT
(HEATER)
SH-HRSG
(HEATER)
12
CLEANGAS
T = 85 oF P = 429 psia
ACID GAS
T = 120 oF P=22 psia
FLASH GAS
o
T = 58 F P = 115 psia
Temperature = 743 oF
Pressure drop = 0 psia
56
Temperature = 641 oF
Pressure drop = 0 psia
13
E2-HRSG
(HEATER)
Temperature = 401 oF
Pressure drop = 0 psia
14
LP-HRSG
(HEATER)
Temperature = 366 oF
Pressure drop = 0 psia
15
E1-HRSG
(HEATER)
Temperature = 271 oF
Pressure drop = 0 psia
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
into the blades and vanes of the hottest turbine stages in order to cool the blades and
vanes. The gas turbine combustor receives the syngas and the compressed air and
combusts them. The hot exhaust gases are expanded in the turbine in several stages,
represented in the model by three expanders.
3.2.5.1 Compression
Ambient conditions of the atmospheric air entering the gas turbine compressor are
assumed to be 59 oF, 14.7 psia, and 60 percent relative humidity. These values are taken
as defaults and can be changed by the user. The default compressor ratio is assumed to be
15.5, which is typical of heavy duty gas turbines (Farmer, 1997), resulting in a
compressor outlet pressure of 227.85 psia. Figure 3.6 and Table 3.5 present the gas
turbine model in detail.
58
TO SH-HRSG
IN GASCOOL
FLOWSHEET
WGT-C1
GTPOC
GT-COMP1
(COMPR)
AIR2
GTAIR
GTCOOL1
GT-MIX4
(MIXER)
GT-COMP2
(COMPR)
GT-TURB3
(COMPR)
GT-MIX3
(MIXER)
GTCOOL2
GT-COMP3
(COMPR)
GTCOOL4
GT-SPLT3
(FSPLIT)
POC6
GT-TURB2
(COMPR)
POC4
QGTLOST
GT-QLOSS
(FSPLIT)
GT-TURB1
(COMPR)
DBURNFD
GT-BURN
(RSTOIC)
GT-MIX1
(FLASH2)
GT-DUPL
(DUPL)
BURNFD
Figure 3.6
WGT-T3
POC3
DPOC2
GT-DBURN
(RSTOIC)
GT-MIXER
(MIXER)
XBURNFD
GTFUEL
GT-MIX2
(MIXER)
GTCOOL3
AIR7
TO
GT-TMIX1
WGT-T2
POC5
AIR6
WGT-C3
QGTRECOV
AIR5
GT-SPLT2
(FSPLIT)
WGT-T1
POC7
AIR4
WGT-C2
POC8
AIR3
GT-SPLT1
(FSPLIT)
POC2
59
GTCOOL4
Table 3.5
NO
BLOCK ID
(ASPEN
BLOCK
NAME)
GT-COMP1
(COMPR)
GT-SPLT1
(FSPLIT)
GT-COMP2
(COMPR)
GT-SPLT2
(FSPLIT)
GT-COMP3
(COMPR)
GT-SPLT3
(FSPLIT)
GT-MIXER
(MIXER)
BLOCK
PARAMETERS
TYPE = 3
Pressure = 34.77 psia
Isentropic Efficiency = 0.88
TYPE = 3
Pressure = 83.07 psia
Isotropic Efficiency = 0.88
TYPE = 3
Pressure = 227.85 psia
Isentropic Efficiency = 0.88
DESCRIPTION
Similar to GT-SPLT1.
This corresponds to 1st
stage Rotor and 2nd stage
Vane Cooling.
Similar to GT-COMP1
Similar to GT-SPLT1.
This corresponds to 1st
stage Vane Cooling.
This block simulates the
mixing of the compressed
air and expanded fuel gas.
NPK = 1
60
GT-BURN
(RSTOIC)
Temperature = 2350 oF
Pressure = 218.74 psia
10
GT-DBURN
(RSTOIC)
Temperature = 2350 oF
Pressure = 218.74 psia
11
GT-QLOSS
(FSPLIT)
12
GT-MIX1
(FLASH2)
13
GT-TURB1
(COMPR)
Temperature = 2350 oF
Pressure = 218.74 psia
ENT = 1.0
TYPE = 3
Pressure = 83.07 psia
Isoentropic Efficiency = 0.89
14
GT-MIX2
(MIXER)
15
GT-TURB2
(COMPR)
TYPE = 3
Pressure = 34.77 psia
Isoentropic Efficiency = 0.89
16
GT-MIX3
(MIXER)
17
GT-TURB3
(COMPR)
TYPE = 3
Pressure = 15.2 psia
Isoentropic Efficiency = 0.89
61
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
The outlet pressure at the last compressor stage is estimated in the FORTRAN
block STCTAIL based on the inlet pressure of the first stage compressor and the user
specified pressure ratio, which is 15.5 in this case. The individual compressor stage
outlets for the first, second, and third stages are estimated by the following relationships,
respectively:
0.33
(3-12)
(3-13)
Pc,3,o = Pambient PR
(3-14)
Pc,1,o = Pambient PR
where,
PR
The compressors were modeled by three unit operation blocks, GT-COMP1, GTCOMP2, and GT-COMP3 with outlet pressures specified as 36.41 psia, 91.08 psia, and
227.85 psia allowing for some pressure loss. The isentropic efficiencies of each of the
compressors is 0.81 as discussed in Section 3.2.5.7 Based upon these default
assumptions, the discharge temperature of outlet air entering the gas turbine combustor is
62
found to be 838 oF based upon simulation results from the ASPEN model. After each
stage of compression, the compressed air is split into two or more streams. One stream
undergoes further compression and the other streams represented by GT-COOL1, GTCOOL2, GT-COOL3, and GT-COOL4 are used for cooling the turbine blades after each
expansion stage of the gas turbine.
The reheated fuel gas, GTFUEL and the compressed air, AIR7 enter the
combustor modeled by the stoichiometric reactor block GT-BURN. The following
chemical reactions are used in the block GT-BURN to simulate the combustion.
2 CO + O2 2 CO2
(3-15)
2 H 2 + O2 2 H 2 O
(3-16)
CH 4 + 1.5 O2 CO + 2 H 2 O
(3-17)
2 H 2 S + 3 O2 2 H 2 O + 2 SO2
(3-18)
(3-19)
(3-20)
(3-21)
These reactions represent the oxidation of the syngas components CO, H2, CH4,
H2S, COS, and NH3. In addition, Equation (3-21) is used to model the formation of
thermal NO and NO2, while Equation (3-20) is used to model the formation of fuel-bound
NO and NO2 from NH3 in the syngas.
63
This constraint is met using a design specification, SETHRST, which is described Section
3.2.5.6.
The expansion of the hot products of combustion, stream POC2, leaving the
combustor is modeled in three stages. Each of the three stages consist of a turbine, which
are modeled by GT-TURB1, GT-TURB2, and GT-TURB3 and a mixer, which are
modeled by GT-MIX1, GT-MIX2, GT-MIX3. In each of these stages, the hot gases are
mixed with the cooler air coming from one of the blocks GT-SPLT1, GT-SPLT2, or GTSPLT3 and then expanded in the turbine. The first, second, and third turbines have an
outlet pressures of 91.08 psia, 36.41 psia, and 15.42 psia, respectively, and each has an
isentropic efficiency of 0.919. The exhaust gases, GTPOC, enter the heat recovery steam
generation (HRSG) unit.
64
The flow at the inlet of the gas turbine expander is choked; that is, the Mach
number of the gas stream is unity. The choked flow condition is assumed to hold
regardless of the type of fuel used due to the large pressure ratio across the first stage
turbine nozzle (Eustis and Johnson, 1990). The design specification TCHOKE sets the
flow of hot air at the turbine inlet nozzle corresponding to choked flow conditions by
varying the compressor inlet flow.
+1
MW
M flow = P A
T
2 1
R + 1
where,
Mflow
= total pressure
MW
(3-22)
= total temperature
The mass flow rate of the ambient air entering the gas turbine combustor is
initialized in the ASPEN input file. The mass flow rate of the ambient air is adjusted by
TCHOKE to achieve a specified turbine nozzle gas mass flow rate. The choked mass flow
is calculated based on a reference mass flow, adjusted for differences in pressure,
temperature, and molecular weight, and assuming that the critical area and ratio of
specific heats of exhaust gas for reference and actual case are constant. The reference
mass flow is estimated based on a GE MS7001F firing syngas, with an exhaust mass flow
of 3,775,000 lb/hr and assuming that 12 percent of the compressor air is diverted for gas
turbine blade and vane cooling similar to previous studies (Frey and Rubin, 1991).
66
the third stage turbine. The cooling air percentages were estimated by calibrating the
model to the overall efficiency and output specifications for a typical heavy duty gas
turbine and they are specified in the FORTRAN block AIRCOOL.
At high exhaust gas temperatures, the gas turbine blades lifetime can be reduced.
To prevent possible damage to the gas turbine blades, the temperature of the gas turbine
exhaust gas is controlled such that it is kept below 1120 oF. The control temperature of
1120 oF is obtained from published data (Holt, 1998). This is achieved by varying the gas
turbine firing temperature in the SETHRST design specification until the desired
expander exhaust gas temperature is obtained.
67
GT-HEAT sets the combustor heat loss to four percent of the heat input to the gas
turbine combustor by varying the fuel flow. In this design specification, the mass flow of
coal is varied until the desired combustor heat duty is achieved. The unit operation block
GT-MIX1, mixes the hot exhaust gases from the gas turbine combustor with cool air from
the compression stages of the gas turbine before sending the hot gases to the first stage of
gas turbine expanders. BURNTEMP sets the firing temperature of the gas by ensuring
that there is no heat loss from the mixer, GT-TMIX1, after it mixes the hot exhaust gas
from the combustor with the cool air from the first stage of compression.
68
efficiency is selected from Figure 3.7 (a) based upon the desired exhaust temperature; in
this case, an isentropic efficiency of 87.2 percent was selected. A compressor isentropic
efficiency of 91.8 percent is selected based on Figure 3.7 (b) in order to obtain the correct
simple cycle efficiency. The reference mass flow at the turbine inlet is adjusted to
3,470,000 lb/hr obtain the desired power output. The estimated power output of 170.0
MW, obtained from the ASPEN gas turbine model with the selected values of isentropic
efficiencies, is within 0.11 percent of the published data. A similar procedure was used to
calibrate the gas turbine to data for a coal gasification application. The isentropic
efficiencies obtained in the case of syngas are 0.81 and 0.919 for gas turbine compressors
and gas turbine expanders respectively.
69
70
Ex h a u st G a s T e m p . (o F )
1135
ET
1130
1125
0.86
1120
0.87
1115
0.88
1110
1105
0.88
0.89
0.9
0.91
0.92
0.93
37.5
ET
37
36.5
0.86
36
0.87
35.5
0.88
35
34.5
0.88
0.89
0.9
0.91
0.92
0.93
174
O u tp u t (M W )
172
ET
170
168
0.86
166
0.87
164
0.88
162
160
158
0.88
0.89
0.9
0.91
0.92
0.93
Figure 3.7
1.
2.
3.
Economizer,
4.
5.
Economizer.
pressure boiler. The inlet steam to the high pressure economizer and the makeup water for
steam generation is initialized in the ASPEN input file through FORTRAN block
SETSTEAM. The low pressure boiler is used to produce steam for the deaerator for the
flue gas leaving the economizer at 366 oF. The heat losses in the HRSG process are
accounted for through block QSPLIT shown in Table 3.6 and Figure 3.8
72
The hot exhaust gases from the gas turbine section, represented by GTPOC, are
cooled by a series of heat exchangers, modeled by blocks SH-HRSG, HP-HRSG, E2HRSG, LP-HRSG, and E1-HRSG in that order and are illustrated in Figure 3.4. The heat
streams obtained from three of the blocks, namely E1-HRSG, E2-HRSG, and HP-HRSG
are mixed in a mixer, simulated by QMIX. The heat stream from SH-HRSG, QSH-HRSG
is split into three heat streams by the block QSPLIT. One heat stream is discarded as heat
lost, one of the heat streams, QREHEAT is diverted to block TURBHEAT in steam
turbine section shown in Figure 3.11, and the remaining heat stream, QSUPER, is sent to
the block QMIX.
The total heat from the QMIX block, QTOTHRSG, is sent to the block
ECONOMZR which simulates a heat exchanger. ECONOMZR heats a stream of water to
o
a temperature of 553 F. The mass flow of the stream of water, TOECON is calculated by
the FORTRAN block SETSTEAM. The remaining amount of heat available is sent to
block HPBOILER which simulates a high pressure steam boiler in HRSG. The steam
generated by HPBOILER enters the superheater, SUPERHTR and generates superheated
o
steam at a temperature of 997 F. which is sent to a high pressure (350 psia) steam
The low pressure (1 psia) steam generated by the block TURB1, representing a
steam turbine, is cooled by a heater simulated by block CONDENSR, as shown in Figure
73
3.8. The condensate from CONDENSR is pumped to 25 psia and delivered as WATER25
to a deaerator, simulated by the block DEAERATOR. DEAERATOR mixes the various
condensates from the auxiliaries section, stream WATER25 and makeup water, which is
required to makeup for the water sent to the fuel saturation unit from the steam cycle
section. The mixed condensate, represented by DEAERH2O is sent to a block H2OSPLIT
which simulates the splitting of the total condensate to streams TOECON, TOB100,
TO565PSI, and TO65PSI. The ratios of the split are calculated by the FORTRAN block
SETSTEAM.
Streams TOECON and TOB100 are sent to the blocks ECONMZR and BOIL100,
respectively, in the HRSG section. BOIL100 simulates the generation of 100 psia steam.
The steam from BOIL100 is split by the block SPLIT100 into streams SLXSTM and
STM100, both of which are sent to the auxiliaries section shown in Figure 3.10. The unit
operation blocks of the auxiliaries section are listed in Table 3.8.
The water streams TO565PSI and TO65PSI from the block H2OSPLIT are also
sent to the auxiliaries section. The block CLAUS565 in the auxiliaries section heats the
stream TO565PSI and generates steam of 565 psia pressure which is sent to the block
TURBREHT and is further heated by the heat stream QREHEAT to a temperature of 996
o
F.
74
TO TURBREHT
IN
STEAM TURBINE
FLOWSHEET
QRXR
QTOTHRSG
QCONCOOL
QMIX
(MIXER)
QSUPER
QRCNET
QSPLIT
(FSPLIT)
QSH-HRSG
QHP-HRSG
QE2-HRSG
QREHEAT
FROM
GASCOOL
FLOWSHEET
QE1-HRSG
FROM
GASCOOL
FLOWSHEE
T
FROM CONCOOL
IN
SOLIDS SEPARATION
FLOWSHEET
FROM
GASIFIER
FLOWSHEET
FROM TURB1
IN
STEAM TURBINE
FLOWSHEET
CONDENSR
(HEATER)
QCOND
WATER1
STEAM1
TO
ECONOMZR
IN
HRSG
SECTION
WP25
WATER25
PUMP25
(PUMP)
FROM
STEAMCYLCE
FLOWSHEET
TOECON
QDEAER
FROM COOL2
IN
GASCOOL
FLOWSHEET
Figure 3.8
TO565
H2OSPLIT
(FSPLIT)
TO65
TOB100
DEAERVAP
DEAERH2O
QO2PLANT
DEAERATR
(FLASH2)
QCOOL2
QDESUPER
STM55
SLXCOND
WWCON
D
MISCCOND
MAKEUP
TO
HRSG
SECTION
75
TO
AUXILIARIES
SECTION
Table 3.6
NO
1
BLOCK ID
(ASPEN BLOCK
NAME)
QSPLIT
(FSPLIT)
BLOCK
PARAMETERS
FRAC
QRADROSS 0.03
QREHEAT 0.0388
RFRAC
QSUPER 1.0
QMIX
(MIXER)
CONDENSR
(HEATER)
Pressure = 1 psia
Vfrac = 0
PUMP25
(COMPR)
TYPE = 1
Pressure = 25 psia
DEAERATOR
(FLASH2)
Pressure = 25 psia
Vfrac = 0
H2OSPLIT
(FSPLIT)
MOLE_FLOW
TOECON 1.0
TOB100 1.0
TO565PSI 1.0
TO65PSI 1.0
DESCRIPTION
Simulates the radiation
losses in the HRSG and
diverts QREHEAT to
REHEAT in HRSG
section.
Simulates the mixing of
the various heat stream in
the HRSG used in the
calculation of
superheated steam mass
flow.
Simulates the block
which heats the steam
which comes out of the
Steam Turbine section.
Simulates a pump which
delivers the condensate to
the deaerator.
Simulates the mixing of
the condensates and
steam.
Simulates the splitting of
the total condensate into
the required ratios in
which the condensate will
be sent to various blocks.
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
76
TOECON
PUMP1785
(PUMP)
QTOTHRSG
ECONOMZR
(HEATER)
WP1785
ECONIN
FROM H2OSPLIT
IN
STEAM CYCLE
FLOWSHEET
QFGS
QECONXS
FGSHTR
(HEATER)
QCOOL1
FROM COOL1
IN
GASCOOL
FLOWSHEET
TOFGSHTR
ECONH2O
FROM QMIX
IN
STEAMCYCLE
FLOWSHEET
FGSMAKUP
FGSMIX
(MIXER)
COLDH2O
FROM SATURATOR
IN
GASCOOL
FLOWSHEET
HPBFW
FGSSPLIT
(FSPLIT)
QHPXS
SUPERHTR
(FLASH2)
TOB100
PUMP180
(PUMP)
TO TURB350
IN
STEAM TURBINE
FLOWSHEET
SHSTEAM
WP180
B100BFW
FROM H2OSPLIT
IN
STEAM CYCLE
FLOWSHEET
HPBLOWDN
HPSTEAM
HPBOILER
(FLASH2)
QLP-HRSG
QCLRXR
FROM CLAUSRXR
IN
CLAUS
FLOWSHEET
BOIL100
(FLASH2)
STEAM100
SPLIT100
(FSPLIT)
SLXSTM
STM100
B100BLDN
FROM
GASCOOL
FLOWSHEET
Figure 3.9
77
TO
AUXILIARIES
SECTION
Table 3.7
NO
1
2
3
BLOCK ID
(ASPEN BLOCK
NAME)
PUMP1785
(COMPR)
ECONOMZR
(HEATER)
QECOSPLT
(FSPLIT)
FGSSPLIT
(FSPLIT)
FGSMIX
(MIXER)
FGSHTR
(HEATER)
HPBOILER
(FLASH2)
SUPERHTR
(HEATER)
PUMP180
(COMPR)
8
9
BLOCK
PARAMETERS
TYPE = 1
Pressure = 1785 psia
Temperature = 553 oF
Pressure = 1625 psia
FRAC
QECONXS 0.81
QECOREH 0.19
MOLE-FLOW
FGSMAKUP 1.0
RFRAC
HPBFW
1.0
Properties
SYSOP3
Properties
SYSOP3
o
Temperature = 366 F
Pressure drop = 0 psia
Pressure = 1545 psia
Vfrac = 0.97
Pressure = 1465
TYPE = 1
Pressure = 180 psia
10
BOIL100
(FLASH2)
11
SPLIT100
(FSPLIT)
MOLE-FLOW
SLXSTM 0.1
RFRAC
STM100 1.0
DESCRIPTION
Simulates a pump which
delivers condensate to the
HRSG economizer.
Simulates economizers 1
and 2 of HRSG.
Simulates the splitting of
the heat stream coming
out the economizer block.
This block provides hot
water for fuel gas
saturator.
Simulates a mixer which
mixes makeup water and
cold water from the
SATURATR.
Simulates a heater which
heats the makeup water to
the SATURATR.
Simulates a high pressure
steam boiler in HRSG.
Simulates the steam
superheater in HRSG.
Simulates a pump which
delivers water to the 100
psia steam boiler.
This block simulates a low
pressure (100 psia) steam
boiler.
This block splits the steam
from BOIL100. The splits
are set by FORTRAN
block SETSTEAM.
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
78
TO565
PUMP565
(PUMP)
QFURNACE
CLAUS565
(FLASH2)
WP565
WATER565
FROM H2OSPLIT
IN
STEAMCYCLE
FLOWSHEET
CLBLOWDN
STEAM565
FROM
FURNACE
IN
CLAUS
FLOWSHEET
TO TURBREHT
IN
STEAM TURBINE
FLOWSHEET
TO65
PUMP65
(PUMP)
WP65
WATER65
FROM H2OSPLIT
IN
STEAMCYCLE
FLOWSHEET
FROM SPLIT100
IN
HRSG
SECTION
DESUPER
(FLASH2)
QDESUPER
LIQ55
MISCSTM
TO DEAERATOR
IN
STEAMCYCLE
FLOWSHEET
STM55
TO DEAERATOR
IN
STEAMCYCLE
FLOWSHEET
MISC-USE
(HEATER)
MISCCOND
WWTREAT
(HEATER)
WWCOND
TO DEAERATOR
IN
STEAMCYCLE
FLOWSHEET
SPLIT55
(FSPLIT)
WWSTEAM
Figure 3.10
Auxiliaries Flowsheet
79
SLXSTEAM
(HEATER)
SLXCOND
STM100
STEAM55
FROM SPLIT100
IN
HRSG
SECTION
SLXSTM
STRFDSTM
STRETSTM
(HEATER)
QSLXSTM
Table 3.8
NO
1
BLOCK ID
(ASPEN BLOCK
NAME)
PUMP565
(PUMP)
BLOCK
PARAMETERS
TYPE = 1
Pressure = 565 psia
CLAUS565
(FLASH2)
PUMP65
(PUMP)
TYPE = 65
Pressure = 65 psia
STRETSTM
(HEATER)
SLXSTEAM
(HEATER)
Pressure = 65 psia
DESUPER
(FLASH2)
SPLIT55
(FSPLIT)
WWTREAT
(HEATER)
Pressure = 55 psia
Vfrac = 1
MOLE-FLOW
WWSTEAM 1.0
MISCSTM 1.0
RFRAC
STM55
1.0
Pressure = 55 psia
Vfrac = 0
MISC-USE
(HEATER)
Pressure = 55 psia
Vfrac = 0
DESCRIPTION
This block simulates a
pump which delivers
water to the Claus plant
steam generator.
This block simulates the
Claus plant steam
generator.
This block simulates a
pump which delivers
water to the BS plant
steam generator.
This block simulates the
BS plant steam generator.
This block simulates the
115 psia steam
condensation in the
Selexol process.
Simulates 55 psia steam
desuperheater.
This block splits the steam
from DESUPER. The
splits are set by
FORTRAN block
SETSTEAM.
Simulates the
condensation of 55 psia
steam condensation in
Texaco Waste Water
Treatment.
This block simulates the
miscellaneous user of 55
psia steam.
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
80
The superheated steam, stream SHSTEAM, from the HRSG section enters the
block TURB350 which simulates a 350 psia exhaust steam turbine. The output stream
from this block, STEAM350, is steam at 350 psia. The stream STEAM350 is mixed with
STEAM565 from the auxiliaries section in the block TURBHEAT simulating a mixer
o
and is heated by QREHEAT to a temperature of 996 F. The resulting stream, modeled by
HOTSTEAM at a pressure of 350 psia, enters the block TURB115, which generates
steam at 115 psia. This steam at 115 psia is split by the block SPLIT115 into streams
TURB70IN and TURB1IN. The ratio of the split is decided by the design specification
DEAERHT. The outlet stream modeled by TURB70IN enters the low pressure (70 psia)
exhaust turbine, simulated by TURB70. The resulting stream from TURB70 is steam at
70 psia, which enters the DEAERATOR block. The output stream from TURB1,
STEAM1, at a pressure of 1 psia enters the block CONDENSR.
81
FORTRAN block SETMAKEUP sets the steam cycle makeup water and the
FORTRAN block SETSTEAM calculates the various mass flows of water streams such
as those represented by TOECON, TOB100, TO565PSI, and TO65PSI. The required
water circulation rate to the heat economizers in HRSG is calculated by FORTRAN block
SETSTEAM, based on the temperature of the superheated steam, 997 oF and the
o
temperature at which the water enters the HRSG from the deaerator, 244 F. The flow
rates of water and steam to other parts of the model is also calculated by the same block.
82
SHSTEAM
TURB350
(COMPR)
STEAM565
TURBREHT
(MIXER)
WT350
STEAM350
FROM SUPERHTR
IN
HRSG
SECTION
FROM QSPLIT
IN
STEAMCYCLE
FLOWSHEET
HOTSTEAM
QREHEAT
TURB115
(COMPR)
STEAM115
WT115
SPLIT115
(FSPLIT)
TURB1IN
WT1
TURB70
(COMPR)
STEAM70
TURB70IN
TO
DEAERATR
IN
STEAMCYCLE
FLOWSHEET
TURB1
(COMPR)
STEAM1
FROM
CLAUS565
IN
AUXILIARY
FLOWSHEET
TO
CONDENSR
IN
STEAMCYCLE
FLOWSHEET
Figure 3.11
WT70
Table 3.9
NO
1
BLOCK ID
(ASPEN BLOCK
NAME)
TURB350
(COMPR)
TURBREHT
(MIXER)
TURB115
(COMPR)
SPLIT115
(FSPLIT)
TURB70
(COMPR)
TURB1
(COMPR)
BLOCK
PARAMETERS
TYPE = 3
Pressure = 350 psia
Isoentropic = 0.847
TYPE = 3
Pressure = 115 psia
Isoentropic = 0.901
FRAC
TURB70IN 0.015
RFRAC
TURB1IN 1.0
TYPE = 3
Pressure = 70 psia
Isoentropic = 0.85
TYPE = 3
Pressure = 1 psia
Isoentropic = 0.849
DESCRIPTION
Simulates a high pressure
steam turbine.
This block simulates the
mixing of steams at 350
psia and 565 psia.
Simulates an intermediate
pressure steam turbine.
This block splits the steam
from TURB115. The splits
are set by design-spec
DEAERHT.
Simulates a low pressure
(70 psia) steam turbine.
Simulates a low pressure
(1 psia) steam turbine.
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
84
Assuming a generator loss of 0.5 percent, the net gas turbine power output is
calculated to be the sum of the work done by the gas turbine expanders and work required
by the gas turbine compressors.
The total gross output of the steam turbine is the sum of the total work done by
the four steam turbines.
85
3.3
Convergence Sequence
The convergence sequence for the model simulation is based on nine design
specifications and seven FORTRAN blocks. Most of the design specifications and
FORTRAN blocks have been described in earlier sections of this chapter and the rest are
elaborated upon in this Section.
The FORTRAN block SETFEED maintains the water-to-coal ratio in the model
by setting the mass flow of water to the gasifier based upon calculation that the coal
slurry has 66.5 percent of solids by weight.
The convergence sequence starts with the initialization of key input variables in
the FORTRAN block STCTAIL. Then the gasification, high temperature gas cooling, and
86
solid separation process area sequences are called by the master sequence. This is
followed by the low temperature gas cooling sequence. The Selexol process and the fuel
gas saturation process area sequences are specified next. Then the gas turbine flowsheet
sequence is specified followed by the Claus plant and the Beavon-Stretford plant
sequences. Then the gas side of the HRSG, and the entire steam cycle sequences are
specified. Finally, the FORTAN block which presents user defined results, SUMMARY
is attached to the sequence followed by the cost model FORTRAN subroutine,
TEXCOST.
3.4
Environmental Emissions
SO2 emissions from IGCC systems are controlled by removing sulfur species from
the syngas prior to combustion in the gas turbine. NOx emissions tend to be low for this
particular IGCC system for two reasons. The first is that there is very little fuel-bound
nitrogen in the fuel gas. The second reason is that thermal NO formation is low because
of the low syngas heating value and correspondingly relatively low adiabatic flame
temperature. A primary purpose of the gas cleanup system is to protect the gas turbine
from contaminants in the fuel. Hence, no post-combustion control is assumed. However,
it is possible to further control NOx emissions, for example, through use of Selective
Catalytic Reduction (SCR) downstream of the gas turbine. The emission rates of these
pollutants are lower than for conventional power plants and for many advanced coalbased power generation alternatives. CO2 emissions are lower than for conventional coal-
87
fired power plants because of the higher thermal efficiency of the IGCC system (e.g.,
nearly 40 percent in this case versus typical values of 35 percent for conventional
pulverized coal-fired power plants).
3.4.1 NOx Emissions
The generation of NO and NO2 from the gas turbine has been modeled in the
present study. Both the fuel NOx as well as thermal NOx have been taken into
consideration for the estimation of NO and NO2. The default assumptions made for these
estimations are that fuel NO is 95 percent by volume of the fuel NOx, and that the fraction
of ammonia that is converted to fuel NOx is 0.90. The conversion rate of nitrogen to NOX
during the gas turbine combustion is assumed to be 0.00045. Atmospheric emission rates
are calculated on a lb/MMBTU basis as part of the model output.
88
89
4.0
4.1
Coal Handling
The Texaco IGCC system uses a coal slurry with typically 66.5 weight percent of
solids as feed to the gasifier. Coal handling involves coal unloading, stacking,
reclamation, and conveying equipment followed by three operating and one spare train of
wet grinding equipment. To estimate the auxiliary power requirements of the coal
handling unit, a predictive model was developed by Rocha and Frey (1997) using 13 data
points obtained from the sources listed in Table 4.1. The coal feed rate was chosen as the
independent variable for development of an auxiliary power model. Two models were
selected for consideration: power consumed per slurry train vs. coal feed rate per slurry
90
train; and total power consumed by the slurry preparation process area vs. total coal flow
to slurry preparation. The power consumed per slurry train vs. coal feed rate per slurry
train produced a standard error of 1,183 kW per train and a R2 of 0.716, whereas the
standard error for the other model is 2,949 kW for the entire plant and the R2 value is
2
0.807. Because of the higher R value, the latter model was selected.
(4-1)
where,
We, CH = Auxiliary power consumption of the coal handling process, kW.
mcf, CH, i = Coal feed rate, tons/day.
3,300 mcf, CH, i 20,000 tons per day as-received.
The model and data are shown in Figure 4.1. The model fit is greatly influenced
by the data point that is at 20,000 tons/day gasifier coal feed rate (McNamee and White,
1986). A much better fit could occur if this value was removed from the power
consumption model consideration. The data point was not removed because no reason
could be found to exclude the value from the development of the power consumption
model.
91
Table 4.1
Report No.
AP-3109
AP-3486
AP-4509
AP-5950
GS-6904
TR-100319
MRL
Texaco
Pietruszkiewicz
Hager and
Heaven
Smith and
Heaven
Robin et
al.
1988
EPRI
Texaco
1990
EPRI
Dow
1991
EPRI
Destec
1991
DOE
Texaco
92
and Slurry
Coal
Illinois No.
6
Illinois No.
6
Illinois No.
6
Texas
Lignite
Illinois No.
6
Eastern
Bituminous
Illinois No.
6
Pittsburg
No. 8
Power Consumption, kW
10000.0
AP-4509
GS-6904
AP-3486
AP-5950
MRL Texaco
Model
8000.0
6000.0
4000.0
2000.0
0.0
0.0
Figure 4.1
4.2
Gasification
A single data point is used to estimate the auxiliary power consumption for the
gasification process area based upon radiant and convective high temperature gas cooling
from a study by Matchak et al. (1984). Coal feed rate is used as the independent variable
as it is most commonly available for data analysis.
93
(4-2)
4.3
The auxiliary power consumptions of other process areas such as oxidant feed,
low temperature gas cooling, Selexol, process condensate treatment, general facilities,
pump and compressor power consumption in the Claus, Beavon-Stretford, and steam
cycle systems are calculated using regression models developed by Frey and Rubin, 1990.
For the convenience of the reader, the models are briefly presented here. For additional
details, please refer to Frey and Rubin (1990).
94
-6
2
We, OF = (0.9466 + 3.73 - 4 TA + 9.019 x 10 TA ) (0.00526 MO,G,i)
(4-3)
where,
MO,G,i = Oxygen gas flow to the gasifier, lb/hr.
TA = Ambient temperature = 59 oF.
-5
We, LT = 4.3887 x 10 Msyn, LT, o
where,
Msyn, LT, o = Molar flowrate of syngas to LTGC section, lbmole/hr.
95
(4-4)
4.3.3 Selexol
The auxiliary power consumption model for Selexol process in MW was
developed by Frey and Rubin (1990) using 18 data points with and R2 of 0.881 and is
given by
(4-5)
where,
4,000 Msyn,S,o 74,500 lb/hr
-5
We, C = 2.1 x 10 Ms,C,o
where,
1,000 Ms,C,o 30,800 lb/hr
Ms,C,o = Mass flow of sulfur from Claus plant, lb/hr.
96
(4-6)
(4-7)
where,
9,000 Ms,BS,o 18,000 lb/hr
Ms,BS,o = Mass flow of sulfur from BS plant, lb/hr.
(4-8)
where,
Ms,BD = Scrubber blowdown flowrate, lb/hr.
97
the sum of all the work done by the pumps dealing with this section. These pumps are
modeled in the ASPEN flowsheet.
(4-9)
where,
WBFW = Auxiliary power consumption by boiler feedwater section, MW
P1785 = Work done on the centrifugal pump which delivers BFW at 1785 psia, MW
P565 = Work done on the centrifugal pump which delivers BFW at 565 psia, MW
P180 = Work done on the centrifugal pump which delivers BFW at 180 psia, MW
P65 = Work done on the centrifugal pump which delivers BFW at 65 psia, MW
P25 = Work done on the centrifugal pump which delivers BFW at 25 psia, MW
We, GF = 0.1 (We, CH + We, CH + We, OF + We, LT + We, S + We, C + We, BS + We, PC + WBFW) (4-10)
98
The sum of all the above auxiliary power loads gives the total auxiliary power
consumption of the power plant, We, AUX in MW.
4.4
(4-11)
The net plant power output is the total power generated from the gas turbines and
steam turbines less the total auxiliary power consumption. The gas and steam turbines
have been modeled as a series of compressors and turbines in ASPEN using the unit
operation block COMPR. This unit operation block requires outlet pressure and
isoentropic efficiencies as parameters. The power consumed by the compressors and the
power generated by the turbines are calculated by the ASPEN performance model. The
net power output is calculated as part of the cost model which is a part of the FORTRAN
subroutine TEXCOST called by the ASPEN input file. The net power output in MW is
given by
99
(4-12)
= 3.414 x 106
MWnet
M cf ,CH ,i x HHV
where,
= net plant efficiency.
Mcf, CH, i = Coal feed rate, lb/hr.
HHV = Higher heating value of fuel, BTU/lb.
100
(4-13)
5.0
This chapter documents the cost model developed for the coal-fueled Texaco
gasifier-based IGCC plant with radiant and convective high temperature gas cooling. The
direct capital costs for all the important process areas of oxidant feed section, coal
handling and slurry preparation, gasification section, low temperature gas cooling section,
Selexol section, Claus sulfur recovery section, Beavon-Stretford tail gas removal section,
boiler feedwater system, process condensate system, gas turbine section, heat recovery
steam generator section, steam turbine section, and general facilities are described in that
order. The annual, and levelized costs of the model are elaborated upon later in the
chapter.
New direct cost models for the major process areas in the IGCC system are
presented. For the purpose of estimating the direct capital costs of the plant, the IGCC
plant is divided into thirteen process areas as listed in Table 5.1. The direct cost of a
process section can be adjusted for other years than that year for which they were
developed using the appropriate Chemical Engineering Plant Cost Index (PCI) (Chemical
Engineering Magazine, 1984-1999) as shown in Table 5.2. For example, if a direct capital
101
cost model, DC1989 was developed based on January 1989 dollars, then the direct capital
cost in January 1998 dollars, DC1998, is given by:
DC1998 = DC1989
Table 5.1
388.0
351.5
Cost Section
10
Oxidant Feed
20
Coal Handling
30
Gasification
40
50
Selexol
60
Claus Plant
70
Beavon-Stretford Plant
80
85
91
Gas Turbine
92
93
Steam Turbine
100
General Facilities
102
(5-1)
103
Table 5.2
1983
315.5
1984
320.3
1985
324.7
1986
323.5
1987
318.3
1988
336.3
1989
351.5
1990
354.7
1991
360.0
1992
359.5
1993
357.2
1994
361.4
1995
376.1
1996
380.9
1997
383.3
1998
388.0
104
NT ,OF Ta0.067 M O ,G ,i
DGOF =14.35
( 1 Ox )0.073 N O ,OF
0.852
( R 2 =0.936 ; n = 31 )
where,
20 Ta 95; oF
M
105
(5-2)
Slurry preparation trains typically have one to five operating trains with one spare
train. The typical train consists of vibrating feeders, conveyors, belt scale, rod mills,
storage tanks, and positive displacement pumps to feed the gasifiers. All of the equipment
for both the coal handling and the slurry feed are commercially available. This typical
train design is assumed in two reports (McNamee and White, 1986; Matchak et al.,
1984).
A regression model was developed for the direct capital cost of coal handling and
slurry preparation using the data collected for possible independent variables affecting
direct capital cost. The data sources are shown in Table 4.1 and Figure 5.1 shows the data
points. Coal feed rate to gasifier on as-received basis is the most common and easily
106
available independent variable. The direct cost model for the coal handling is based upon
the overall flow to the plant rather than on per train basis. This is because a better value
of R2 was obtained in the former case. The regression model derived is:
(5-3)
where,
R2 = 0.882, n = 16
DCCH = Direct capital cost of gasification section in $ 1000
3,300 Mcf,G,I 25,000 tons/day
160000.0
140000.0
120000.0
100000.0
80000.0
60000.0
40000.0
20000.0
0.0
0.0
10000.0
20000.0
30000.0
Figure 5.1
TR-100319
GS-6904
AP-3486
AP-5950
MRL Texaco
AP-3109
AP-4509
Model
Direct Cost for the Coal Handling and Slurry Preparation Process
Area.
107
The model for the direct capital cost of the gasification section was developed
using data collected from various studies sponsored by the Electric Power Research
Institute (EPRI) and the U.S. Department of Energy. Of the data collected, the coal flow
rate on an as-received basis was the most readily available predictive variable. This was
used as the primary predictive variable, since the size and cost of the gasifier is
proportional to the coal flow rate. Moisture and ash free coal flow rate, oxidant flow rate,
temperature of the gasifier, and the pressure of the gasifier were other possible predictive
variables considered. However, as-received coal flowrate was found to be the most useful
variable. The direct capital cost model for the gasification section is:
Mcf ,G ,i
DCG = 216 NT ,G
NO,G
0.677
(R 2 = 0.438; n= 5)
where,
1,200 M cf ,G ,I 1,600 tons/day per train (as-received).
Standard error = 1.3 million January 89 dollars
108
(5-4)
Although theR2 value for this model is relatively low, the gasifiers are typically of
a relatively narrow size range. Hence the low R2 is influenced by the fact that there is a
relatively narrow domain of values for the predictive variables in this data set.
M syn ,LT ,o
DC LT = 2.379
N
O ,LT
where,
109
0.79
NT ,LT
(5-5)
M syn ,LT ,o
37 ,200lbmole / hr .
16 ,000
N
O
,
LT
0.420 NT ,S M syn ,S ,i
DCS =
( 1 )0.059 NO ,S
0.980
( R 2 =0.909 ; n = 28 )
where,
M
110
(5-6)
This model is valid for H2S removal efficiencies between 83.5 and 99.7 percent.
DCC =6.28 NT ,C s ,C ,o
N O ,C
0.668
( R 2 =0.994 ; n = 21 )
where,
M
111
(5-7)
0.645
( R 2 =0.998 ; n =7 )
(5-8)
where,
75 M s ,BS ,o 1,200 lb/hr.
Standard error = 260,000 January 89 dollars
from the miscellaneous process users such as waste water treatment. The number of trains
used for this commercially available process area is one, with no spare. The direct capital
cost model for this process area is:
0.307 0.435
DC BFW =0.145 M rw
M pw ( R 2 =0.991;n =14 )
(5-9)
where,
24 ,000 M rw 614 ,000 lb/hr; and
234 ,000 M pw 3 ,880 ,000 lb/hr
M SBD
DCPC = 9700
300000
113
0.6
(5-10)
(5-11)
114
HRSG. A simple regression model based only on the high pressure steam flow rate to the
steam turbine was developed by Frey and Rubin (1990) and is given by:
DC LT = 5364 +7.21 10
M hps ,HR ,o
N O ,HR
0.242
1.526
NT ,HR Phps
,HR ,o
( R 2 =0.966 ; n =10 )
(5-12)
where,
650 Phps, HR, o 1545 psia; and
Mhps,HR ,o
640,000 lbmole / hr.
66,000
NO, HR
Standard error = 6.0 million January 89 dollars
115
(5-13)
12
GF = fGF DCi
(5-14)
i =1
where,
fGF = 0.17.
5.2
costs, indirect construction costs, engineering and home office fees, sales tax, allowances
for funds used during construction (AFDC), project contingency, and total process
contingencies.
The equations for the plant cost model are the same as those given in Frey and
Rubin (1990) and are not repeated here. However, the model is briefly described.
116
5.3
The total capital requirement (TCR) includes the total plant investment, prepaid
royalties, spare parts inventory, preproduction (or startup) costs, inventory capital, initial
chemicals and ctatlyst charges, and land costs. The methodology for calculating TCR is
given in detail in Frey and Rubin (1990).
117
5.4
Annual Costs
The annual costs of an IGCC plant consists of fixed and variable operating costs.
The fixed operating costs are annual costs including operating labor, maintenance labor,
maintenance materials, and overhead costs associated with administrative and support
labor. The variable operating costs include consumables, fuels, slag and ash disposal, and
byproduct credits. For more details on the annual cost models, please refer to Frey and
Rubin (1990).
5.5
Levelized Costs
The total capital requirement, fixed operating cost, and operating variable cost are
used to calculate the cost of producing electricity that is available for sale from the power
plant, based on the net electrical output from the power plant. The calculated cost of
electricity is also known as total annualized cost and is the levelized annual revenue
requirement to cover all of the capital and operating costs for the economic life of the
plant.
Celec
1,000 mills
[ 1,000 f cr TCR + f vclf ( FOC + VOC )]
dollar
=
MWnet 8 ,760 c f
118
(5-15)
where,
Celec = The cost of electricity in mills per kWh
TCR = Total capital requirement in $1000
FOC = Fixed operating costs in dollars
VOC = Variable operating costs in dollars
MWnet = Net power output in MW
fcr = Fixed charge factor = 0.1034
fvclf = Variable levelization cost factor = 1.0
Cf = Capacity Factor = 0.65
119
6.0
An example case study is presented here to illustrate the use of the new IGCC
system model. The key steps in running the ASPEN simulation model of the Texaco
gasifier-based IGCC system are: (1) specify input assumptions; (2) execute the model;
(3) collect results; and (4) interpret the results.
6.1
Input Assumptions
Model input assumptions were developed for the performance and cost model
based upon a review of design and performance parameters obtained from literature (Frey
and Rubin, 1990; Frey and Rubin, 1991; Matchak et al., 1984; Farmer, 1997; Holt, 1998).
The assumed composition of the 3.9 weight percent (dry basis) sulfur Illinois No. 6 coal
is given in Table 3.1. The model is configured to represent three parallel trains of heavy
duty Frame 7F gas turbines.
Table 6.1 summarizes a number of the input assumptions for the example case study,
with a focus on the key inputs for the gasifier and gas turbine process areas of the model.
Many of these assumptions have been previously described in the technical description of
the technology. Two of the assumptions listed in the table are initial values that may be
120
modified during the simulation. These are the Oxygen/Coal ratio in the gasifier and the
Turbine Inlet Temperature in the gas turbine. The Oxygen/Coal ratio is varied by a design
specification in order to achieve the specified syngas exit temperature and overcome a
two percent heat loss from the gasifier. The Turbine Inlet Temperature may be lowered
o
from the initial value of 2,350 F in order to maintain the exhaust gas temperature below
1,120 oF. There are literally hundreds of other input assumptions to the model. Only the
most significant ones affecting plant design and operation are shown here. The cost
model assumptions used in this case study are similar to those reported by Frey and
Rubin (1991).
Selected performance and cost results from the model output are summarized in
Tables 6.2 and 6.3. The overall energy balance is indicated in Table 6.2. The plant is
121
estimated to produce a net of 863 MW with an overall plant efficiency of 39.4 percent on
a higher heating value basis. The breakdown of plant power production and internal plant
power consumption for auxiliaries is given in the Table 6.2. Buchanan et al. (1998)
mentions a first-of-a-kind (FOAK) IGCC plant which has a gasifier that closely
resembles the radiant and convective design adopted in the present study. The efficiency
of the FOAK plant is given to be 40.1 percent which is comparable to the efficiency
obtained by the current model. The FOAK plant produces 543 MW on a higher heating
value basis.
Estimated emission rates for SO2, NOx, particulate matter (PM), and CO2, are
provided in Table 6.2. SO2 emissions from IGCC systems are controlled by removing
sulfur species from the syngas prior to combustion in the gas turbine. NOx emissions tend
to be low for this particular IGCC system because there is very little fuel-bound nitrogen
in the fuel gas and thermal NO formation is low due to the low syngas heating value and
correspondingly relatively low adiabatic flame temperature. PM emissions are controlled
in the syngas cleanup system prior to the gas turbine. A primary purpose of the gas
cleanup system is to protect the gas turbine from contaminants in the fuel. Hence, no
post-combustion control is assumed. However, it is possible to further control NOx
emissions, for example, through use of Selective Catalytic Reduction (SCR) downstream
of the gas turbine. The emission rates of these pollutants are lower than for conventional
power plants and for many advanced coal-based power generation alternatives. CO2
emissions are lower than for conventional coal-fired power plants because of the higher
122
thermal efficiency of the IGCC system (e.g., nearly 40 percent in this case versus typical
values of 35 percent for conventional pulverized coal-fired power plants).
The estimated costs for the IGCC system given in Table 6.3 include capital,
annual, and levelized costs. These costs are inclusive of the entire power plant, including
the environmental control system. The breakdown of total capital cost of $1,732/kW
includes a 47.1 percent contribution from direct costs, a 5.4 percent contribution from
process contingencies, a 12.2 percent contribution from project contingencies, and a 13.1
percent contribution from allowances for funds used during construction. The remaining
contributions are from other indirect costs and startup costs. The largest annual cost is for
fuel consumption. The byproduct credit for sale of elemental sulfur offsets the
incremental variable costs for all consumables other than fuel. The levelized cost of
electricity, based upon a 65 percent capacity factor, is 50.9 mills/kWh (5.09 cents/kWh).
This cost of electricity is comparable to that of many other coal-based power generation
systems evaluated using similar financial assumptions.
123
Table 6.1
Summary of Selected Base Case Input Values for the Texaco GasifierBased IGCC System with Radiant and Convective High Temperature
Gas Cooling
Description
Value
615
2,400
0.915
0.504
1,500
650
6
570
28.2
Pressure Ratio
15.5
o
Turbine Inlet Temperature, F (Initial Value)
2,350
81.0
91.9
Generator Efficiency, %
98.5
124
Table 6.2 Summary of Selected Performance Model of the Coal-Fuel System with
Radiant and Convective High Temperature Gas Cooling Point Estimate
Results from the Example Case Study
Description, Units
Value
579.5
400.8
7.3
Oxidant Feed, MW
83.5
Gasification, MW
1.2
Low T. Cool., MW
2.4
Selexol, MW
4.8
Claus, MW
0.4
Beavon-Stretford, MW
1.3
Steam Cycle, MW
5.3
Process Condensate, MW
0.6
General Facilities, MW
10.7
117.4
862.9
8,664
39.4
6
SO2 Emissions, lb/10 BTU
0.22
0.13
< 0.03
1.70
125
Table 6.3
Summary of Cost Model Results for the Example Case Study (1998
Dollars)
Description, Units
Value
815
299
Process Contingencies
94
Project Contingency
211
1,419
227
1,647
43
a
1,732
50.4
1.2
-1.5
10.9
10.6
50.9
126
7.0
7.1
Major Process Sections in the Total Quench IGCC Process Simulation Model
Most of the major flowsheet sections in the process simulation model of the total
quench-based system, such as coal slurry preparation, gasification, particulate scrubbing,
acid gas removal, Claus sulfur recovery, Beavon-Stretford tail gas treatment, and gas
turbine, are similar in design to those in the radiant and convective-based model. The
127
flowsheet sections in the total quench model that are significantly different from their
counterparts in the radiant and convective design which are the high temperature gas
cooling section, low temperature gas cooling section, fuel gas saturation, and steam cycle,
are described below. The other process are modeled in the same manner as descibed in
Chapter 3.
7.1.1
Figure 7.1, and Table 7.1 illustrate the structure and input assumptions of the
gasification and high temperature gas cooling models. The gasification process is similar
to that in the radiant and convective design. The crude gas leaving the gasificaton unit is
o
o
at a temperature of 2400 F to 2600 F. As shown in Figure 7.1, the hot gas is introduced
directly into a water quench chamber located below the gasifier vessel. In the model, the
hot gas is simulated by the stream RXROUT. RXROUT enters the unit operation block
QUENMIX, which simulates a mixer. Quench water and the hot gas from the block
GASIFIER are mixed in QUENMIX. The resulting output stream, modeled by
QUENGAS, flows to the unit operation block QUENHEAT which simulates a heater.
o
QUENHEAT cools the QUENGAS stream to a temperature of 433 F.
128
The other components of this process area, such as the blocks SLURPUMP,
COALCONV, MAKESOOT, MAKESLAG, and SLAGOUT, are the same as described
in Chapter 3.0.
129
WSLURRY
SLURRY1
SLURPUMP
(PUMP)
QCONV
GASIFIER
(RGIBBS)
SLURRY3
QUENHEAT
(HEATER)
QUENGAS
RXRIN
QUENMIX
(MIXER)
SLAGOUT
(SEP2)
RAWGAS
SLAG
TO QMIX
IN
STEAMCYCLE
FLOWSHEET
TO CONCOOL
IN
SOLIDSEP
FLOWSHEET
Figure 7.1
Gasification Flowsheet
130
MAKESLAG
(RSTOIC)
QSLAG
RXROUT
QRXR
MAKESOOT
(RSTOIC)
SLURRY4
SLURRY2
QSOOT
COALCONV
(USER)
COOLGAS
SLURRY
GASIFMIX
(MIXER)
OXYGEN
Table 7.1
NO
1
BLOCK ID
(ASPEN BLOCK
NAME)
SLURPUMP
(PUMP)
COALCONV
(USER)
MAKESOOT
(RSTOIC)
MAKESLAG
(RSTOIC)
GASIFMIX
(MIXER)
GASIFIER
(RGIBBS)
QUENMIX
(MIXER)
QUENHEAT
(HEATER)
BLOCK
PARAMETERS
TYPE=2
Pressure = 650 psia
Efficiency = 0.65
DESCRIPTION
131
COMP FRAC
COAL = 1.0
ASH = 1.0
SLAG = 1.0
SOOT = 0.0
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
7.1.2
Figure 7.2 and Table 7.2 illustrate the structure of the low temperature gas cooling
section of the total quench model. The scrubbed gas from the solids separation section,
represented by TOBSAT100, is cooled by heat exchange with the circulating saturator
water. The scrubbed gas is first cooled by heat exchanger BSAT100. The heat recovered
here is used to generate 100 psia steam in the HRSG section. Blocks COOLA, COOL1,
and BSAT55 are other heat exchangers which cool the raw gas to 332 oF. The gas is
further cooled to 130 oF by heating vacuum condensate and makeup water from block
DAERATOR in the steam cycle. The raw gas at 130 oF is cooled to 101 oF in the trim
cooler. The condensate from all the above mentioned heat exchangers is collected in the
condensate collection drum, CONDMIX. The cooled gas is sent to the Selexol acid gas
removal unit.
132
CLCHNG1
(CLCHNG)
BSAT100
(FLASH2)
COND100
COOLA
(FLASH2)
CONDA
COOL1
(FLASH2)
T=361
P=554
CONDMIX
(MIXER)
COND55
BSAT55
(FLASH2)
CLEANGAS
T=85
P=429
Figure 7.2
COLDGAS
QCOOL55
TO
DEAERATOR
QCOOL2
IN
STEAMCYCLE
FLOWSHEET
COOL3
(FLASH2)
QCOOL3
T=101
P=537
133
TO GCWHB55
IN
AUXILIARIES
FLOWSHEET
TOCOOL3
QSELEXOL
FLASHGAS
ACIDGAS
COND3
SELEXOL
(SEP)
COOL2
(FLASH2)
T=130
P=542
TO HEAT2
IN
GASPROC3
FLOWSHEET
QCOOL1
TOCOOL2
T=332
P=547
COND2
TO HEAT1
IN
GASPROC3
FLOWSHEET
QCOOLA
TOBSAT55
ALLCOND
COND1
TO BOIL100
IN HRSG
FLOWSHEET
TOCOOL1
QCOOL100
TOCOOLA
T=412
P=564
TO
CLCHNG2
IN
SOLIDSEP
FLOWSHEET
TOBSAT10
T=424
P=572
FROM
NH3SEP
NH3FREE
IN
SOLIDSEP
FLOWSHEET
TO
DEAERATOR
IN
STEAMCYCLE
FLOWSHEET
Table 7.2
Description
NO
1
2
BLOCK ID
(ASPEN BLOCK
NAME)
CLCHNG1
(CLCHNG)
BSAT100
(FLASH2)
BLOCK
PARAMETERS
Temperature = 412 oF
Pressure drop = 8 psia
COOLA
(FLASH2)
Temperature = 396.1
o
F Pressure drop = 5
psia
COOL1
(FLASH2)
Temperature = 361 oF
Pressure drop = 5 psia
BSAT55
(FLASH2)
Temperature = 332 oF
Pressure drop = 7 psia
COOL2
(FLASH2)
Temperature = 130 oF
Pressure drop = 5 psia
COOL3
(FLASH2)
Temperature = 101 oF
Pressure drop = 5 psia
CONDMIX
(MIXER)
(continued on next page)
134
DESCRIPTION
This block changes stream class
from MIXCINC to Conventional.
This block simulates a heat
exchanger which reduces the
temperature of the syngas to 412
o
F from 424 oF across a pressure
drop of 8 psia.
This block simulates a heat
exchanger which reduces the
temperature of the syngas to
396.1 oF from 412 oF across a
pressure drop of 5 psia.
This block simulates a heat
exchanger which reduces the
temperature of the syngas to 361
o
F from 391.1 oF across a pressure
drop of 5 psia.
This block simulates a heat
exchanger which reduces the
temperature of the syngas to 361
o
F from 323 oF across a pressure
drop of 7 psia.
This block simulates a heat
exchanger which reduces the
temperature of the syngas to 130
o
F from 332 oF across a pressure
drop of 5 psia.
This block simulates a heat
exchanger which reduces the
temperature of the syngas to 101
o
F from 130 oF across a pressure
drop of 5 psia.
This block simulates the mixing
of all condensates in this section.
RMHEAT
(HEATER)
HEAT1
(HEATER)
10
HEAT2
(HEATER)
WARMCOOL
(HEATER)
HOTSPLIT
(FSPLIT)
9
10
11
12
13
14
15
16
PUMP1K1
(PUMP)
WMIX
(MIXER)
COOLSPLT
(FSPLIT)
COLDCOOL
(HEATER)
COLDSPLT
(FSPLIT)
PUMP1K2
(PUMP)
17
HMIX
(MIXER)
(continued on next page)
CLEANGAS
T = 85 oF, P = 429 psia
ACID GAS
o
T = 120 F, P=22 psia
FLASH GAS
T = 58 oF, P = 115 psia
Temperature = 421 oF
Pressure = 500 psia
MOLE-FLOW
TOHEAT12
1.0
RFRAC
COOLH2O 1.0
Temperature = 252 oF
Pressure = 429 psia
MOLE-FLOW
COLDH2O 1.0
RFRAC
SATCOM2 1.0
TYPE = 1
Pressure = 500 psia
135
19
SATHEAT
(HEATER)
20
REHEAT
(HEATER)
SH-HRSG
(HEATER)
22
HP-HRSG
(HEATER)
Temperature = 639 oF
Pressure drop = 0 psi
23
E3-HRSG
(HEATER)
Temperature = 541 oF
Pressure drop = 0 psi
24
IP-HRSG
(HEATER)
Temperature = 469 oF
Pressure drop = 0 psi
25
E2-HRSG
(HEATER)
Temperature = 420 oF
Pressure drop = 0 psi
26
LP-HRSG
(HEATER)
Temperature = 365 oF
Pressure drop = 0 psi
21
Temperature = 856 oF
Pressure drop = 0 psi
136
Temperature = 307 oF
Pressure drop = 0 psi
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
Figure 7.3 shows the details of the fuel gas saturation unit. The syngas leaving the
Selexol acid gas recovery unit, CLEANGAS is saturated with moisture before the gas
enters the gas turbine combustor. This is done with the intent of raising the net plant
power output and to control NOx emissions from the gas turbine, as previously described
in Section 2.5. The steam saturation increases the mass throughput and the heat capacity
of the inlet pressurized fuel gas stream to the gas turbine resulting in an increase in the
gas turbine power output.
The clean gas, modeled as stream CLEANGAS, from the Selexol process, enters
the saturation unit at 85 oF and 429 psia. The saturation unit is provided with two stages
in order to achieve a high moisture content of 40 weight percent in the fuel gas. Large
quantities of heat are required to achieve the high moisture content in the fuel gas because
large amount of cold water from the saturator and boiler feed water from the HRSG have
to be heated. This required heat is supplied from the raw gas during low temperature gas
o
cooling. The saturated gas is also reheated in this unit to 520 F using high pressure boiler
137
The model of saturator for the total quench system is different from that described
in Section 2.5. Instead of direct contact of syngas with water, the heat transfer between
the clean syngas and the saturator water are modeled. The amount of water required to
saturate the clean syngas to 40 weight percent moisture is calcuated, and the heat required
to vaporize this amount of water is obtained from blocks HEAT1 and HEAT2. Finally,
the water vapor is mixed with the clean syngas and reheated in REHEATR before the
syngas is sent to the gas turbine. HEAT1 and HEAT2 simulate blocks which heat the
circulating water using heat recovered from unit operartion blocks COOLA and COOL1
respectively. WARMCOOL cools the hot water entering the saturator unit to an
intermediate temperature. The cooled hot water, HOTH21, is split into two streams,
WARMH2O and SATCOM1, by HOTSPLIT. PUMP1K1 is a pump, which increases the
pressure of WARMH2O to 500 psia. A mixer WMIX mixes the 500 psia WARMH2O
and the heated water from HEAT2. The mixed stream, TOSPLT, is split by COOLSPLT
into two streams, COOLH2O and TOHEAT12. The stream COOLH2O is cooled to a
o
temperature of 252 F in block COLDCOOL, and split into COLDH2O and SATCOM2.
PUMP1K2 increases the pressure of COLDH2O to 500 psia before it is sent to HEAT2
block. TOHEAT12 is sent to the block HEAT1, where it is heated to become HOTW2.
CLEANGAS, SATCOM1, and SATCOM2 are mixed and heated to a temperature of 370
o
F in the block SATHEAT. The high pressure boiler feedwater from the HRSG,
o
FGSMAK, is cooled to 421 F by RMHEAT. The heat recovered from FGSMAK is used
to heat the saturated clean gas to 520 oF. The reheated fuel gas, GTFUEL flows to the gas
turbine combustors.
138
M water =
M Clean Gas
100
(7-1)
where,
Mwater = Mass flow of water to be added to the clean syngas, lb/hr
= SATCOM1 + SATCOM2
The FORTRAN block SETINIT also calculates the split ratios for the blocks
HOTSPLIT and COLDSPLT using similar methods as in
SETSTEAM, elaborated upon in Section 3.2.6.3. SETINIT also sets the mass flow
makeup water to the steam cycle equal to the mass flow of water added to the clean
syngas.
139
GTFUEL
T=520
P=414
REHEATR
(HEATER)
QTOREH
RMHEAT
(HEATER)
HOTW1
T=421
P=1000
HMIX
(MIXER)
SATCOM1
T=350
P=425
HOTSPLIT
(FSPLIT)
WARMH2O
T=351.7
P=1000
COLDSPLIT
(FSPLIT)
WMIX
(MIXER)
COOLH2O
T=349.9
P=1000
HEAT2
(HEATER)
T=253.2
P=429
COOLSPLIT
(FSPLIT)
COLDH2O
Figure 7.3
TOHEAT2
COLDCOOL
(HEATER)
FR-HEAT2
T=346.5
P=1000
TOSPLT
T=350.2
P=1000
COOLH21
T=252
P=429
TOHEAT12
T=350
P=425
SATCOM2
COLDH2O
T=252
P=429
TOHEAT1
WARMCOOL
(HEATER)
QHEAT1
HOTH21
SATMIX
(MIXER)
T=252
P=429
T=350.2
P=1000
QCOOLA
HOTH20
SATHEAT
(HEATER)
SATGAS1
CLEANGAS
T=85
P=429
HEAT1
(HEATER)
T=381.5
P=1000
T=378
P=419
QHEAT2
HOTW2
T=379.1
P=1000
HOTH22
SATGAS
T=382.5
P=1000
FGSMAK
T=549
P=1600
QCOOL1
7.1.3
Steam Cycle
The steam cycle designed for the total quench model is similar to the one
designed for radiant and convective IGCC system except for a few differences. The
HRSG section in the total quench model has two extra economizers and an intermediate
pressure evaporator. The auxiliaries section has an additional 55 psia centrifugal pump
and a 55 psia steam boiler. The steam turbine section has only one low pressure (1 psia)
steam turbine unlike in the case of radiant and convective model in which there is also a
70 psia low pressure steam turbine. The rest of the steam cycle is the same as that
described in Section 3.2.6.
1.
2.
3.
Economizer,
4.
5.
Economizer,
6.
141
7.
Economizer.
Most of the HRSG section design is similar to the HRSG design in the radiant
and convective model. The key additions are ECONOMZ3, which models two
economizers, and the intermediate pressure boiler, IPBOILER, which generates saturated
steam of 350 psia. This steam is combined in the high pressure power turbine,
TURBREHT, with the high pressure steam (565 psia), STEAM565, from the Claus plant.
142
PUMP1785
(PUMP)
QTOTHRSG
ECONOMZR
(HEATER)
WP1785
FROM
GASCOOL
FLOWSHEET
QIP-HRSG
TOECON
ECONIN
ECONOUT
IPSTEAM
IPBLOWDN
IPBOILER
(HEATER)
TOIPB
TO TURBREHT
IN
STEAM TURBINE
FLOWSHEET
QECONXS
ECONOMZ3
(HEATER)
QHPXS
HPSTEAM
HPBOILER
(FLASH2)
HPBLOWDN
TOB100
SUPERHTR
(FLASH2)
SHSTEAM
PUMP180
(PUMP)
WP180
TO TURB350
IN
STEAM TURBINE
FLOWSHEET
B100BFW
FROM H2OSPLIT
IN
STEAM CYCLE
FLOWSHEET
ECOSPLIT
(FSPLIT)
TOECON3
FGSSPLIT
(FSPLIT)
FGSMAKUP
HPBFW
TO RMHEAT
IN
GASCOOL
FLOWSHEET
ECONH2O
ECONH2O
QECONTOT
FROM QMIX
IN
STEAMCYCLE
FLOWSHEET
QIPXS
FROM H2OSPLIT
IN
STEAM CYCLE
FLOWSHEET
QLP-HRSG
QCOOL100
BOIL100
(FLASH2)
STEAM100
SPLIT100
(FSPLIT)
QCLRXR
FROM CLAUSRXR
IN
CLAUS
FLOWSHEET
B100BLDN
FROM
GASCOOL
FLOWSHEET
Figure 7.4
SLXSTM
STM100
TO
AUXILIARIES
SECTION
Table 7.3
NO
1
2
3
4
5
6
7
8
9
BLOCK ID
(ASPEN BLOCK
NAME)
PUMP1785
(COMPR)
ECONOMZR
(HEATER)
ECOSPLT
(FSPLIT)
ECONOMZ3
(HEATER)
FGSSPLIT
(FSPLIT)
HPBOILER
(FLASH2)
SUPERHTR
(HEATER)
IPBOILER
(HEATER)
PUMP180
(COMPR)
BLOCK
PARAMETERS
TYPE = 1
Pressure = 1785 psia
Temperature = 553 oF
Pressure = 1625 psia
MOLE-FLOW
TOIPB 1.0
RFRAC
TOECON3 1.0
Temperature = 549 oF
Pressure = 1600 psia
MOLE-FLOW
FGSMAKUP 1.0
RFRAC
HPBFW
1.0
Pressure = 1545 psia
Vfrac = 0.97
Pressure = 1465
Pressure = 350 psia
Vfrac = 0.97
TYPE = 1
Pressure = 180 psia
10
BOIL100
(FLASH2)
11
SPLIT100
(FSPLIT)
MOLE-FLOW
SLXSTM 0.1
RFRAC
STM100 1.0
DESCRIPTION
Simulates a pump which
delivers condensate to the
HRSG economizer.
Simulates economizers 1
and 2 of HRSG.
Simulates the splitting of
the heat stream coming
out the economizer block.
Simulates economizer 3 of
HRSG.
This block provides hot
water for fuel gas
saturator.
Simulates a high pressure
steam boiler in HRSG.
Simulates the steam
superheater in HRSG.
Simulates a 350 psia
steam boiler.
Simulates a pump which
delivers water to the 100
psia steam boiler.
This block simulates a low
pressure (100 psia) steam
boiler.
This block splits the steam
from BOIL100. The splits
are set by FORTRAN
block SETSTEAM.
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
144
TO565
PUMP565
(PUMP)
QFURNACE
CLAUS565
(FLASH2)
WP565
WATER565
FROM H2OSPLIT
IN
STEAMCYCLE
FLOWSHEET
FROM SPLIT100
IN
HRSG
SECTION
CLBLOWDN
STEAM565
FROM
FURNACE
IN
CLAUS
FLOWSHEET
TO TURBREHT
IN
STEAM TURBINE
FLOWSHEET
TO65
WP65
FROM SPLIT100
IN
HRSG
SECTION
TO55
STRETSTM
(HEATER)
SLXSTM
QGCWHB55
GCWHB55
(FLASH2)
TO DEAERATOR
IN
STEAMCYCLE
FLOWSHEET
STM55
SLXSTEAM
(HEATER)
GCBLOWDN
STEAM55
FROM
GASCOOL QCOOL55
FLOWSHEET
MISCSTM
SLXCOND
WATER55
STRFDSTM
PUMP55
(PUMP)
WP55
PUMP65
(PUMP)
WATER65
FROM H2OSPLIT
IN
STEAMCYCLE
FLOWSHEET
MISC-USE
(HEATER)
MISCCOND
WWTREAT
(HEATER)
WWCOND
TO DEAERATOR
IN
STEAMCYCLE
FLOWSHEET
SPLIT55
(FSPLIT)
WWSTEAM
Figure 7.5
Auxiliaries Flowsheet
145
QSLXSTM
Table 7.4
NO
1
BLOCK ID
(ASPEN BLOCK
NAME)
PUMP565
(PUMP)
BLOCK
PARAMETERS
TYPE = 1
Pressure = 565 psia
CLAUS565
(FLASH2)
PUMP65
(PUMP)
TYPE = 65
Pressure = 65 psia
STRETSTM
(HEATER)
SLXSTEAM
(HEATER)
Pressure = 65 psia
PUMP55
(PUMP)
TYPE = 1
Pressure = 55 psia
GCWHB55
(FLASH2)
SPLIT55
(FSPLIT)
WWTREAT
(HEATER)
Pressure = 55 psia
Vfrac = 1
MOLE-FLOW
WWSTEAM 1.0
MISCSTM 1.0
RFRAC
STM55
1.0
Pressure = 55 psia
Vfrac = 0
MISC-USE
(HEATER)
Pressure = 55 psia
Vfrac = 0
DESCRIPTION
This block simulates a
pump which delivers
water to the Claus plant
steam generator.
This block simulates the
Claus plant steam
generator.
This block simulates a
pump which delivers
water to the BS plant
steam generator.
This block simulates the
BS plant steam generator.
This block simulates the
115 psia steam
condensation in the
Selexol process.
Simulates a pump that
delivers water to
GCWHB55.
Simulates 55 psia steam
heater.
This block splits the steam
from DESUPER. The
splits are set by
FORTRAN block
SETSTEAM.
Simulates the
condensation of 55 psia
steam condensation in
Texaco Waste Water
Treatment.
This block simulates the
miscellaneous user of 55
psia steam.
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
146
The superheated steam from the HRSG section, SHSTEAM enters the block
TURB350, which simulates a 350 psia steam turbine. The output stream of TURB350,
STEAM350 is mixed in the block TURBREHT with the stream STEAM565 from the
auxiliaries section and stream IPSTEAM from the HRSG section. The output stream of
TURBREHT, HOTSTEAM is sent to intermediate pressure (90 psia) steam turbine,
TURB90. The stream STEAM90 from TURB90 flows to the low pressure steam turbine,
TURB1 generating 1 psia steam which flows to the block CONDENSR in the steam
cycle flowsheet The work streams, WT350, WT90, and WT1 are summed to estimate the
shaft power input to the generator.
147
SHSTEAM
TURB350
(COMPR)
WT350
STEAM350
FROM SUPERHTR
IN
HRSG
SECTION
QREHEAT
TURBREHT
(MIXER)
QIPXS
IPSTEAM
HOTSTEAM
STEAM565
WT90
STEAM90
TURB90
(COMPR)
WT1
TURB1
(COMPR)
STEAM1
FROM
CLAUS565
IN
AUXILIARY
FLOWSHEET
FROM QSPLIT
IN
STEAMCYCLE FLOWSHEET
TO
CONDENSR
IN
STEAMCYCLE
FLOWSHEET
Figure 7.6
148
FROM IPBOILER
IN
HRSG FLOWSHEET
Table 7.5
NO
1
BLOCK ID
(ASPEN BLOCK
NAME)
TURB350
(COMPR)
TURBREHT
(MIXER)
TURB90
(COMPR)
TURB1
(COMPR)
BLOCK
PARAMETERS
TYPE = 3
Pressure = 350 psia
Isoentropic eff. = 0.847
TYPE = 3
Pressure = 90 psia
Isoentropic eff. = 0.901
TYPE = 3
Pressure = 1 psia
Isoentropic eff. = 0.849
DESCRIPTION
Simulates a high pressure
steam turbine.
This block simulates the
mixing of steams at 350
psia and 565 psia.
Simulates an intermediate
pressure steam turbine.
Simulates a low pressure
(1 psia) steam turbine.
The user assigned unit operation block identification and the ASPEN unit operation block name are given.
For a glossary of ASPEN block names, please see Table A.1 in Appendix A.
For a glossary of ASPEN block parameters, please see Table A.2 in Appendix A.
7.1.4
The plant energy balance is comprised of four energy balance calculations. They
are: (1) the gas turbine section power output estimation; (2) the estimation of the total
gross power output of the steam turbine; (3) the estimation of power consumption of
auxiliary pumps modeled in the ASPEN flowsheet; and (4) the estimate of all other
process area auxiliary loads. The latter are calculated in the cost model subroutine. The
approach to calculating the plant energy balance is the same as described in the Section
3.2.7.
149
The auxiliary power consumption models for oxidant feed, coal slurry
preparation, Beavon-Stretford plant, general facilities section are similar to those used in
the radiant and convective design as elaborated upon in Chapter 4.0. The sections which
use different auxililary power models than those in the radiant and convective design are
described below.
7.1.4.1 Gasification
Only two data points were available for the determination of the auxiliary power
consumption model for the gasification section based upon water quench high
temperature syngas cooling. The two data points were obtained from studies by Matchak
et al. (1984) and Robin et al. (1993). A linear model with zero intercept was developed
based upon the coal flow rate (as-received basis) per gasifier train and is shown in Figure
7.7. The auxiliary model developed has a standard error of 16 kW for the entire plant and
R2 of 0.970.
The R2 variable is very high because only two data points were available.
150
(7-2)
Power Consumption, kW
300
250
200
AP-3486
MRL Texaco
Model
150
100
50
0
0
500
1000
1500
2000
2500
Figure 7.7
151
(7-3)
7.1.4.3 Selexol
The auxiliary power consumption model for the Selexol section was developed as
part of the current study using a single data point from the study by Matchak et al. (1984)
The auxiliary power consumption model for Selexol process in MW is given by
(7-4)
where,
MSYN,S,I = Molar flow rate of syngas entering Selexol process, lbmole/hr.
(7-5)
where,
MS,C,O = Mass flow of sulfur from Claus plant, lb/hr.
152
(7-6)
where,
MS,BD = Scrubber blowdown flowrate, lb/hr.
7.2
Convergence Sequence
The convergence sequence for the total quench model simulation is similar to the
convergence sequence specified in the radiant and convective design as described in
Section 3.3. The additional blocks used for designing the total quench section of the
model replace the high temperature gas cooling section of the model containing the
radiant and convective design and the additional economizers in the total quench model
are added the convergence sequence developed for the radiant and convective model.
7.3
Environmental Emissions
NOX, particulate, SO2, and CO2 emissions are modeled in the same method as
153
7.4
This section documents the cost model developed for the Texaco gasifier-based
IGCC plant with total quench high temperature gas cooling. New direct capital cost
models for major process sections are presented here. For the purpose of estimating the
direct capital costs of the plant, the IGCC plant is divided into thirteen process areas as
listed in Table 5.1. The direct cost of a process section can be adjusted for other years
using the appropriate Chemical Engineering Plant Cost Index (PCI) as shown in Table
5.2 and described in Section 5.1.
The direct capital cost models for coal handling section, oxidant feed section,
Claus recovery section, Beavon-Stretford plant, gas turbine, boiler feedwater system,
process condensate system, heat recovery steam generation system, steam turbine section,
and general facilities are the same as those in radiant and convective design for coal. The
process area direct capital costs for gasification, low temperature gas cooling, and Selexol
are different from those in the radiant and convective system and are described here.
154
Only two data points were available for the development of this cost model. The
data points are not conducive to cost model development using regression analysis, since
a straight line connecting them would have a negative slope. Therefore, a representative
value based upon the average of the two points is used to represent the direct cost of a
single gasifier train. A plot of the data is given Figure 7.8. From the two data points an
approximation was determined to be 10 million January dollars per train. Since the data
are based upon a coal feed rate of 1,300 to 2,300 tons/day (as-received basis), the average
cost is assumed to apply for individual trains in this size range. The direct capital cost in
January 1989 dollars for the gasification section is:
DCG = 10,000,000 NT ,G
where,
NT,G = Number of trains
155
(7-7)
15000
10000
AP-3486
MRL Texaco
5000
0
0
500
1000
1500
2000
2500
Figure 7.8
O , LT
0.79
where,
Msyn,LT,o = Molar flow of syngas from the LTGC section, lbmol/hr
NO,LT = Number of operating trains
NT,LT = Total number of trains
156
(7-8)
0.2746 NT , S M syn, S , i
DCS =
(1 )0.059 N O , S
where,
Msyn, G,i
67,300lbmole / hr; and
2,000
NO, S
0.835 HS 0.997.
157
0.980
(7-9)
8.0
An example case study is presented here to illustrate the use of the new IGCC
system model for the coal-fueled system with total quench high temperature gas cooling.
The key steps in running the ASPEN simulation model of the Texaco gasifier-based
IGCC system are: (1) specify input assumptions; (2) execute the model; (3) collect
results; and (4) interpret the results.
8.1
Input Assumptions
Model input assumptions were developed for the performance and cost model
similar to those developed for radiant and convective model. The model is configured to
represent three parallel trains of heavy duty Frame 7F gas turbines. Table 8.1
summarizes a number of the input assumptions for the example case study, with a focus
on the key inputs for the gasifier and gas turbine process areas of the model. Many of
these assumptions have been previously described in the technical description of the
technology. Two of the assumptions listed in the table are initial values that may be
modified during the simulation. These are the Oxygen/Coal ratio in the gasifier and the
Turbine Inlet Temperature in the gas turbine. The Oxygen/Coal ratio is varied by a design
specification in order to achieve the specified syngas exit temperature and overcome a
two percent heat loss from the gasifier. The Turbine Inlet Temperature may be lowered
158
from the initial value of 2,350 oF in order to maintain the exhaust gas temperature below
1,120 oF. There are literally hundreds of other input assumptions to the model. Only the
most significant ones affecting plant design and operation are shown here. The cost
model assumptions used in this case study are similar to those reported by Frey and
Rubin (1991).
8.2
Model Results
The version of ASPEN used in the present study is the one developed by US
Department of Energy. To execute the ASPEN model, an input file is prepared using
standard ASPEN keywords and is submitted to a multi-step process leading to model
execution. In the first step, the input file is translated into a FORTRAN program, which is
then compiled and linked to the extensive library of ASPEN unit operation and other
subroutines. The model is then executed and produces numerous output files. This
particular case study was executed on a VAX 4000 located at Carnegie Mellon
University, and the clock time for the run was about 5 minutes.
Selected performance and cost results from the model output are summarized in
Tables 8.2 and 8.3. The overall energy balance is indicated in Table 8.2. The plant is
estimated to produce a net of 793 MW with an overall plant efficiency of 35.0 percent on
a higher heating value basis. The breakdown of plant power production and internal plant
power consumption for auxiliaries is given in the Table 8.3.
159
Estimated emission rates for SO2, NOx, particulate matter (PM), and CO2 are
provided in Table 8.2. The estimated costs for the IGCC system given in Table 8.3
include capital, annual, and levelized costs. These costs are inclusive of the entire power
plant, including the environmental control system. The breakdown of total capital cost of
$1,540/kW includes a 47.2 percent contribution from direct costs, a 4.7 percent
contribution from process contingencies, a 12.1 percent contribution from project
contingencies, and a 13.1 percent contribution from allowances for funds used during
construction. The remaining contributions are from other indirect costs and startup costs.
The largest annual cost is for fuel consumption. The byproduct credit for sale of
elemental sulfur offsets the incremental variable costs for all consumables other than fuel.
The levelized cost of electricity, based upon a 65 percent capacity factor, is 47.7
mills/kWh (4.77 cents/kWh). This cost of electricity is comparable to that of many other
coal-based power generation systems evaluated using similar financial assumptions.
160
Table 8.1
Summary of the Base Case Parameters Values for the Texaco Coal
Gasification Total Quench System
Description, Units
Value
615
2,400
0.915
0.504
433
526
40.0
Pressure Ratio
15.5
o
Turbine Inlet Temperature, F (Initial Value)
2,350
81.0
91.9
Generator Efficiency, %
98.5
161
Table 8.2 Summary of Selected Performance Model Results from the Example Case
Study
Description, Units
Value
615.0
293.7
7.6
Oxidant Feed, MW
86.3
Gasification, MW
0.8
Low T. Cool., MW
1.8
Selexol, MW
1.2
Claus, MW
0.3
Beavon-Stretford, MW
1.3
Steam Cycle, MW
4.6
Process Condensate, MW
1.3
General Facilities, MW
10.5
115.6
793.0
9,478
Efficiency, %
35.0
6
SO2 Emissions, lb/10 BTU
0.22
0.12
6
< 0.03
1.91
162
Table 8.3 Summary of Cost Model Results for the Example Case Study (1998
Dollars)
Description, Units
Value
728
267
Process Contingencies
73
Project Contingency
187
1,256
201
1,457
68
a
1,540
42.6
1.6
1.7
12.3
12.2
47.7
163
164
9.0
UNCERTAINTY ANALYSIS
Process technologies that are still in the research phase are subject to uncertainty
with respect to prediction of performance, emissions, and costs. Insights into risks of such
new technologies are obtained by analyzing the uncertainties associated with them.
Uncertainty and sensitivity analysis of technology assessment models are done to find out
which assumptions and uncertainties may affect the conclusions significantly.
In any type of modeling effort, the limitations of data and of knowledge about the
system should be reflected in the model results. Uncertainties are prevalent in the early
stages of any technology development effort and hence must be incorporated in the
analysis and design of the technology. Uncertainty analysis has been described as the
computation of the total uncertainty induced in the output by quantified uncertainty in
inputs and models, and the attributes of the relative importance of the input uncertainties
in terms of their contribution (Morgan and Henrion, 1990). Incorporating uncertainties
in the development of new technology model helps in: (1) identifying robust solutions to
process design questions and to eliminate inferior design options; (2) identifying key
problems areas in a technology failure; (3) comparing competing technologies on a
consistent basis to determine the risks associated with adopting a new technology; and (4)
evaluating the effects that additional research might have on comparisons with
conventional technology (Frey and Rubin, 1991).
165
9.1
9.1.1
Characterizing Uncertainties
There are three general areas of uncertainty that should be explicitly reflected in
engineering models. There are uncertainties in: (1) process performance parameters (e.g.,
heat losses and removal efficiencies); (2) process area capital cost; and (3) process
operating cost (Frey and Rubin, 1992b). The approaches to developing probability
distributions for model input parameters are similar in many ways to the approach one
might take to pick a single best guess number for deterministic (point-estimate)
analysis or to select a range of values to use in sensitivity analysis. However, the
166
The steps involved in estimating uncertainties for model input parameters are
(Frey and Rubin, 1992,a):
1.
2.
3.
4.
167
various statistical tests. When the data available are limited, engineering insight can be
used to supplement the data in coming up with an appropriate probability distribution for
the uncertain variable.
When sufficient data are not available, judgements from technical experts can be
elicited to obtain an appropriate probability distribution for the uncertain variable. In
designing elicitation protocol, it is important to take into account heuristics by which
judgements about uncertainty may be. Some heuristics can lead to biases in the
judgements. However, protocols can be designed to counteract these sources of bias.
9.1.2
9.1.2.1 Variability
Variability is caused due to variations in the process itself. For example, a
variation in the coal composition will cause a variation in the net efficiency of the plant.
Variability can be represented as a probability distribution.
168
9.1.2.2 Uncertainty
Uncertainty represents the lack of knowledge regarding the true value of a
quantity. There are a number of types of uncertainty which can be considered while
developing a probability distribution for a variable. Variability is conceptually distinct
from uncertainty (Frey and Rubin, 1992b). For example, for a given coal composition, the
carbon conversion may be uncertain.
1.
2.
Systematic Error The mean value of a quantity may not converge to the true
mean value because of biases in measurement and procedures. Such biases may
arise from imprecise calibration, faulty reading of meters, and inaccuracies in the
assumptions used to infer the actual quantity of interest from the observed
readings of other quantities.
Uncertainty may also arise due to lack of experience with a process. This type of
uncertainty often cannot be treated statistically because it requires predictions about
something that has yet to be built or tested. This type of uncertainty can be represented
using technical estimates about the range and likelihood of possible outcomes.
169
9.1.3
1.
2.
3.
Normal is a symmetric distribution with mean, mode, and median at the same
point. It is often assumed in statistical analysis as the basis for unbiased
measurement errors.
4.
Lognormal is a positively skewed distribution and has a long tail to the right.
170
0.5
0.6
0.7
0.8
0.9
1.0
1.1
Value of Variable
0.5
0.6
0.7
0.8
0.9
1.0
1.1
Value of Variable
-5
-4
-3
-2
-1
Value of Variable
10
20
Value of Variable
Figure 9.1
171
9.1.4
Monte Carlo methods allow the modeler to use any type of probability
distribution for which values can be generated on a computer, rather than to be restricted
to forms which are analytically tractable. The set of samples obtained for model outputs
can be represented as cumulative distribution functions and summarized using typical
statistics such as mean and variance.
172
LHS methods guarantee that values from the entire range of distribution will be
sampled proportional to the probability density of the distribution. Thus the input samples
typically cover a full span of each parameter's probability density function compared to
173
when the random Monte Carlo method is used (McKay et al., 1979). The number of
samples required to adequately represent the CDF for a distribution is less for LHS than
for random Monte Carlo sampling. The LHS method was employed in the present study.
9.1.5
174
relative importance of each input variate is indicated by the regression coefficient of that
variate, which is the standardized regression coefficient (SRC). SRCs are the partial
derivatives of the output variable with respect to each input variable. SRCs measure the
shared contribution of the input to the output as all of the simulation input uncertainties
are included in the regression analysis simultaneously.
The partial correlation coefficient analysis is used to identify the degree to which
correlations between output and input random variables may be linear, and it is estimated
in conjunction with multi-variate linear regression analysis using a step-wise procedure.
The input variable most higly correlated with the output variable of interest is assumed as
the starting point for construction of a stepwise linear regression model. In the regression
model, the output variable is treated as a dependent variable and the most highly
correlated input variable is treated as a predictive variable. The PCC technique then
searches for another input variable which is most highly correlated with the residuals of
the regression model already in containing the first input variable. The residual is the
difference between the actual sample value of the dependent variable and the estimated
sample values, using the linear regression model already containing the first input
variable. The process is repeated to add more variables in the analysis. The PCC is a
measure of the unique relationship between input and dependent variables that cannot be
explained by variables already included in the regression analysis (Frey and Rubin,
1992).
175
PCC and SRC analysis is limited to cases where the relationship between input
and output variables is linear. However, these techniques can be extended to monotonic
non-linear cases by performing regressions on the ranks, rather than the sample values of
the inputs and outputs. They are known as partial rank correlation coefficients (PRCC)
and standardized rank regression coefficients (SRCC).
The regression techniques are useful for identifying the contribution of each input
variable to variations in the output variable. However, they cannot be used to identify
which input variables may be responsible for a shift in the central tendency of the model
outputs associated with skewness in the input distributions. In such cases, sensitivity
analysis is performed by gradually making one or more input variables uncertain while
setting point estimates to the remaining input variables and observing the output
distribution. The sensitivity analysis is continued till the current model output distribution
closely resembles the original model output distribution in which all the input variables
are uncertain.
9.2
176
Tables 9.1 and 9.2 list the performance, environmental, and cost variables selected
for stochastic analysis, along with the deterministic value and distributions for each of
these variables. Since the gas turbine and steam cycle/steam turbine technology is well
established, the performance variables of these process areas were not considered for
uncertainty analysis.
A total of 40 parameters are treated as uncertain in the two cases. These include
assumptions regarding the performance of the gasifier and gas turbine process areas,
capital cost parameters, direct capital costs, maintenance costs, labor rate, and unit costs.
The deterministic values are based upon the assumptions used in published design
studies.
The deterministic values for the process contingency factors had been adopted
from assumptions in published design studies (e.g., Frey and Rubin, 1991; Dawkins et
al., 1985). For the purposes of preliminary characterization of uncertainty in capital cost,
it was assumed that the process contingency factors were intended to represent the midpoint of symmetric uncertainty distributions for process area direct cost. The relative
177
magnitudes of the contingency factors were assumed to suggest the relative magnitude of
the variances to be used. Uniform distributions between the best and worst values were
assumed for some of the process areas, while triangular distribution was assumed for the
other process areas. The triangular distribution was selected in cases where the author felt
that the published contingency factors were carefully developed. The effect of a triangular
distribution, compared to a uniform distribution, is to place more "weight" on the
outcomes near the published contingency factor than on the extreme high or low
outcomes. An exception to the above described approach is the estimate of uncertainty in
the gas turbine process area and is elaborated upon in Frey and Rubin (1991).
178
Table 9.1
________________________________________________________________________________________________________________________________________________
Description
Units
Deterministic
Value
Distribution
Parametersa
________________________________________________________________________________________________________________________________________________
615
Normal
567.5
to
662.51
Triangular
2400
to
2600
Gasifier Temperature
oF
2400
Oxygen/Oil Ratio
0.915
Water/Oil Ratio
Normal
0.465
to
0.543
Carbon Conversion
fraction
0.99
Triangular
0.96
to
1.00
Approach Temperature 1
-300
Triangular
-350
to
-250
Approach Temperature 2
-500
Triangular
-550
to
-450
Approach Temperature 3
-500
Triangular
-550
to
-450
Approach Temperature 4
-500
Triangular
-550
to
-450
Approach Temperature 5
-500
Triangular
-550
to
-450
Approach Temperature 6
-500
Triangular
-550
to
-450
Approach Temperature 7
-500
Triangular
-550
to
-450
Approach Temperature 8
-500
Triangular
-550
to
-450
Approach Temperature 9
-500
Triangular
-550
to
-450
Uniform
2.5x10-5
to
7.5x10-5
wt-% of CO
in fuel gas
Uniform
0.9998
to
0.9999
F
F
F
F
F
F
F
F
F
28.2
15.5
oF
2,350
Exhaust Flow
lb/sec
1,089
Thermal NOx
fraction of air
Unconverted CO
570
0.99985
179
0.10
Triangular
0.07
to
0.13 (0.10)
Indirect Construction
Cost Factor
fraction
0.20
Triangular
0.15
to
0.25 (0.20)
Project Uncertainty
fraction
0.175
Uniform
0.10
to
0.25
General Facilities
fraction
0.20
DIRECT COSTSb
Coal Handling
% of DC
Oxidant Feed
% of DC
Uniform
to
10
Gasification
% of DC
15
Triangular
to
40
(15)
Selexol
% of DC
10
Triangular
to
20
(10)
Low Temperature
Gas Cooling
% of DC
Triangular
-5
to
(0)
Claus Plant
% of DC
Triangular
to
10
(5)
Beavon-Stretford
% of DC
10
Triangular
to
20
(10)
% of DC
Process Condensate
Treatment
% of DC
30
Triangular
to
30
(10)
Gas Turbine
% of DC
12.5
Triangular
to
25 (12.5)
HRSG
% of DC
2.5
Triangular
to
(2.5)
Steam Turbine
% of DC
2.5
Triangular
to
(2.5)
General Facilities
% of DC
Triangular
to
10
(5)
MAINTENANCE COSTSc
Coal Handling
% of TC
Oxidant Feed
% of TC
Gasification
% of TC
4.5
Triangular
to
(4.5)
Selexol
% of TC
Triangular
1.5
to
(2)
Low Temperature
Gas Cooling
% of TC
Triangular
to
(3)
Claus Plant
% of TC
Triangular
1.5
to
2.5
(2)
Beavon-Stretford
% of TC
% of TC
1.5
Process Condensate
Treatment
% of TC
Triangular
1.5
to
(2)
Gas Turbine
% of TC
1.5
Triangular
1.5
to
2.5
(1.5)
HRSG
% of TC
1.5
180
Steam Turbine
% of TC
1.5
General Facilities
% of TC
1.5
Normal
Triangular
10
to
25
(10)
Sulfur Byproduct
$/ton
125
Triangular
60
to
125
(125)
Byproduct Marketing
fraction
0.10
Triangular
0.05
to
0.15 (0.10)
Fuel Cost
$/MMBTU
1.28
Trinagular
1.15
to
1.41 (1.28)
181
17.70
to 21.70
Table 9.2
________________________________________________________________________________________________________________________________________________
Description
Units
Deterministic
Value
Distribution
Parametersa
________________________________________________________________________________________________________________________________________________
615
Normal
567.5
to
662.51
Triangular
2400
to
2600
Gasifier Temperature
oF
2400
Oxygen/Oil Ratio
0.915
Water/Oil Ratio
Normal
0.465
to
0.543
Carbon Conversion
fraction
0.99
Triangular
0.96
to
1.00
Approach Temperature 1
-300
Triangular
-350
to
-250
Approach Temperature 2
-500
Triangular
-550
to
-450
Approach Temperature 3
-500
Triangular
-550
to
-450
Approach Temperature 4
-500
Triangular
-550
to
-450
Approach Temperature 5
-500
Triangular
-550
to
-450
Approach Temperature 6
-500
Triangular
-550
to
-450
Approach Temperature 7
-500
Triangular
-550
to
-450
Approach Temperature 8
-500
Triangular
-550
to
-450
Approach Temperature 9
-500
Triangular
-550
to
-450
Uniform
2.5x10-5
to
7.5x10-5
wt-% of CO
in fuel gas
Uniform
0.9998
to
0.9999
F
F
F
F
F
F
F
F
F
40.0
15.5
oF
2,350
Exhaust Flow
lb/sec
1,089
Thermal NOx
fraction of air
Unconverted CO
526
0.99985
182
0.10
Triangular
0.07
to
0.13 (0.10)
Indirect Construction
Cost Factor
fraction
0.20
Triangular
0.15
to
0.25 (0.20)
Project Uncertainty
fraction
0.175
Uniform
0.10
to
0.25
General Facilities
fraction
0.20
DIRECT COSTSb
Coal Handling
% of DC
Oxidant Feed
% of DC
Uniform
to
10
Gasification
% of DC
15
Triangular
to
40
(15)
Selexol
% of DC
10
Triangular
to
20
(10)
Low Temperature
Gas Cooling
% of DC
Triangular
-5
to
(0)
Claus Plant
% of DC
Triangular
to
10
(5)
Beavon-Stretford
% of DC
10
Triangular
to
20
(10)
% of DC
Process Condensate
Treatment
% of DC
30
Triangular
to
30
(10)
Gas Turbine
% of DC
12.5
Triangular
to
25 (12.5)
HRSG
% of DC
2.5
Triangular
to
(2.5)
Steam Turbine
% of DC
2.5
Triangular
to
(2.5)
General Facilities
% of DC
Triangular
to
10
(5)
MAINTENANCE COSTSc
Coal Handling
% of TC
Oxidant Feed
% of TC
Gasification
% of TC
4.5
Triangular
to
(4.5)
Selexol
% of TC
Triangular
1.5
to
(2)
Low Temperature
Gas Cooling
% of TC
Triangular
to
(3)
Claus Plant
% of TC
Triangular
1.5
to
2.5
(2)
Beavon-Stretford
% of TC
% of TC
1.5
Process Condensate
Treatment
% of TC
Triangular
1.5
to
(2)
Gas Turbine
% of TC
1.5
Triangular
1.5
to
2.5
(1.5)
HRSG
% of TC
1.5
183
Steam Turbine
% of TC
1.5
General Facilities
% of TC
1.5
Normal
Triangular
10
to
25
(10)
Sulfur Byproduct
$/ton
125
Triangular
60
to
125
(125)
Byproduct Marketing
fraction
0.10
Triangular
0.05
to
0.15 (0.10)
Fuel Cost
$/MMBTU
1.28
Trinagular
1.15
to
1.41 (1.28)
184
17.70
to 21.70
9.3
cost model is executed a number of times using LHS, with a different set of values
(samples) assigned to uncertain input parameters each time. The number of times the
deterministic model is executed is equal to the number of observations or sample size
selected. The sample size should be large enough to give sufficient precision to the
numerical simulation as dictated by the use of the model results and at the same time
ensure that the computational time and disk space usage are not excessive (Morgan and
Henrion, 1990). To characterize the mean and the variance of the results and to identify
key uncertainties, a sample size of 100 or greater is typically sufficient (Frey and Rubin,
1991). For the present study, a sample size of 120 was chosen. Results for all the
uncertain output variables are collected at the end of each deterministic run, which can
then be analyzed statistically to gain insight into the key uncertainties of the system. Such
an analysis enables the identification of the key model uncertainties of the most important
determinants of uncertainty in model outputs.
The results of the simulation can be summarized using statistics, such as mean
and standard deviation, or using graphs of the cumulative distribution function and is
discussed in Section 9.5.
185
regression techniques was used to identify input random variables which are most highly
correlated with uncertainties in output variables. Probabilistic sensitivity analysis was
used for identifying key uncertain inputs. In this approach, the interaction between the
cost and performance uncertain input variables as they affect uncertainty in output
variables can be studied by isolating the uncertainties. For example, one can assign
distributions to one or more input variables while all other model inputs are assigned
point estimates. The third approach, uncertainty screening, which is similar to
probabilistic sensitivity analysis, can be used to confirm the results of a regression or
probabilistic sensitivity analysis by deleting uncertainties from the model inputs which
are not believed to be important and assigning them point estimates. The results of the
screening study can be compared to the results obtained from the original probabilistic
analysis and used to confirm that the deleted uncertainties do not affect the model output
distributions.
A total of six case studies were performed for each technology to characterize the
uncertainty in model outputs and to identify the model inputs that contributed most
significantly to the distribution of values in the model outputs. The general procedure is
illustrated here for the case of radiant and convective-based model. A similar procedure
will be used for the two technologies evaluated. The discussions of the results for all the
three technologies are presented in later sections. The purpose here is to to give a general
description of the approach. The input assumptions for these case studies for the radiant
and convective model are summarized in Table 9.3. Each case study is briefly described:
186
187
Tables 9.4 summarizes the above mentioned case studies for total quench coal
model.
188
Table 9.3
Case Study No
Gasifier Pressure
Gasifier Temperature
Water/Oil Ratio
Carbon Conversion
Approach Temperature 1
Approach Temperature 2
Approach Temperature 3
Approach Temperature 4
Approach Temperature 5
Approach Temperature 6
Approach Temperature 7
Approach Temperature 8
Approach Temperature 9
Thermal Nox
Unconverted CO
Engineering and Home Office Fees
Indirect Construction Cost Factor
Project Uncertainty
Process Contingency
Oxidant Feed
Gasification
Low Temperature Gas
Cooling
Selexol
Claus
Beavon-Stretford
Process Condensate
Gas Turbine
HRSG
Steam Turbine
General Facilities
Maintenance Cost Factors
Gasification
Low Temperature Gas
Cooling
Selexol
Claus
Process Condensate
Gas Turbine
Labor Rate
Fuel Cost
Ash Disposal
Sulfur Byproduct
Byproduct Marketing
Performance
and Cost
1
Original Models
Performance Cost Only
Only
2
3
Performance
and Cost
4
Key Uncertainties
Performance Cost Only
Only
5
6
189
Table 9.4
Case Study No
Gasifier Pressure
Gasifier Temperature
Water/Oil Ratio
Carbon Conversion
Approach Temperature 1
Approach Temperature 2
Approach Temperature 3
Approach Temperature 4
Approach Temperature 5
Approach Temperature 6
Approach Temperature 7
Approach Temperature 8
Approach Temperature 9
Thermal Nox
Unconverted CO
Engineering and Home Office Fees
Indirect Construction Cost Factor
Project Uncertainty
Process Contingency
Oxidant Feed
Gasification
Low Temperature Gas
Cooling
Selexol
Claus
Beavon-Stretford
Process Condensate
Gas Turbine
HRSG
Steam Turbine
General Facilities
Maintenance Cost Factors
Gasification
Low Temperature Gas
Cooling
Selexol
Claus
Process Condensate
Gas Turbine
Labor Rate
Fuel Cost
Ash Disposal
Sulfur Byproduct
Byproduct Marketing
Performance
and Cost
1
Original Models
Performance Cost Only
Only
2
3
Performance
and Cost
4
Key Uncertainties
Performance Cost Only
Only
5
6
190
9.4
systems are Texaco gasifer-based and include: (1) a case of coal-fueled system with
radiant and convective high temperature cooling; and (2) a case of coal-fueled system
with total quench high temperature cooling.
The IGCC system performance models are implemented in the ASPEN chemical
process simulation modeling environment on a DEC VAX Station 3200 mini-computer
using the public version of ASPEN with the stochastic modeling capability. The
simulation process involves several steps. The performance model in ASPEN's keywordbased input language is read by the ASPEN package and converted to a FORTRAN
program. This first step is called "input translation" and takes approximately 1 to 2
minutes. The ASPEN-generated FORTRAN program is compiled and linked, which also
takes 1 to 2 minutes. The linked ASPEN flowsheet is executed. The final step in the
simulation involves the writing of a report file containing the results of the simulation.
The report writing step may take several minutes depending upon the amount of
information requested by the user regarding the simulation. A single deterministic run
takes a total time of about 5 to 6 minutes. In a stochastic run, the input translation,
compilation and linking takes about 5 minutes and is done only once. The execution of
the compiled program for 120 iterations and report writing takes about 100 minutes.
191
Cases 1,2, and 3 are run in ASPEN and the distributions for the all outputs are
obtained. The PRCC obtained in each case are analyzed and formed the basis for cases
4,5, and 6 respectively. The outputs which had a PRCC greater than 0.5 or less than 0.5
are identified as key uncertain variables. The PRCCs for the outputs are listed in
Appendix C. The Cases 4, 5, and 6 are run in ASPEN using only the key uncertain
variables identified. It is desired that the cdfs of the output variables obtained after the
running Cases 4, 5, and 6 are identical to the cdfs obtained from the results of Cases 1, 2,
and 3 respectively. However, the distributions of the uncertainties in the costs of
electricity and total capital requirement in Cases 1 and 4 were not similar due to the
skewness of some assumptions regarding the unit costs of consumables, some process
contingency factors ,and some maintenance cost factors. This skewness results in a shift
in the central value of the uncertainty in the cost of electricity when uncertainties in
performance and costs are considered. To avoid this shift in the central value of the
uncertainty in the cost of electricity, probabilistic sensitivity analysis was performed by
192
introducing each of the unit cost assumptions, process contingency factors, and
maintenance cost factors one by one as a key uncertainty factor. After introducing one
variable as an uncertain parameter, the model was run again and the distributions were
examined. This procedure was continued till the distributions of the cost of electricity of
Cases 1 and 4 are similar.
Tables 9.5, and 9.6 list the distributions of selected outputs obtained from
executing Case 1 for radiant and convective model and total quench coal model
respectively.
193
Table 9.5
Parameter
Plant Performance
Plant Thermal Efficiency
Net Plant Output
Gross Power Output
Total Auxiliary Power
Consumption
Fuel Consumption
Sulfur Byproduct
Production
Best
Guess"
f.50
f.05
f.95
Fraction
MW
MW
MW
39.41
862.9
980.3
117.4
38.91
867.5
988.4
121.0
38.88
867.4
988.6
121.2
0.46
4.04
6.09
2.41
38.03
860.8
978.3
117.6
39.52
873.5
998.7
125.9
lb/kWh
lb/MWh
0.68
24.88
0.69
24.95
0.69
24.94
0.01
0.10
0.68
24.77
0.70
25.10
Units
Plant Emissions
SO2 Emissions
NOX Emissions
CO2 Emissions
lb/10 BTU
6
lb/10 BTU
lb/kWh
0.221
0.129
1.70
0.224
0.140
1.71
0.224
0.141
1.71
0.013
0.041
0.01
0.205
0.078
1.70
0.245
0.205
1.71
Plant Costs
Total Capital Cost
Total Direct Cost
Total Plant Cost
Total Plant Investment
Fixed Operating Cost
Variable Operating Cost
Fuel Cost
Byproduct Credit
All Others
Cost of Electricity
$/kW
$/kW
$/kW
$/kW
$/kW-year
mills/kWh
mills/kWh
mills/kWh
mills/kWh
mills/kWh
1732
815
1419
1647
50.35
10.59
10.91
1.52
1.20
50.88
1748
822
1433
1663
51.94
11.27
11.09
1.29
1.38
52.00
1756
822
1439
1670
52.27
11.20
11.07
1.26
1.39
52.27
80.7
5.1
67.4
78.2
3.31
0.54
0.49
0.19
0.13
3.88
1619
815
1324
1536
47.19
10.28
10.19
0.89
1.22
49.38
1892
832
1553
1802
58.15
12.16
11.89
1.50
1.65
55.58
194
Table 9.6
Parameter
Plant Performance
Plant Thermal Efficiency
Net Plant Output
Gross Power Output
Total Auxiliary Power
Consumption
Fuel Consumption
Sulfur Byproduct
Production
Best
Guess"
f.50
f.05
f.95
Fraction
MW
MW
MW
35.03
793.0
908.6
115.6
34.46
793.9
913.5
119.3
34.40
793.8
913.3
119.5
0.50
2.14
3.86
2.54
33.51
789.9
906.7
115.5
35.14
797.1
920.1
124.1
lb/kWh
lb/MWh
0.76
27.49
0.78
27.71
0.78
27.70
0.01
0.16
0.76
27.43
0.80
27.96
Units
Plant Emissions
SO2 Emissions
NOX Emissions
CO2 Emissions
lb/10 BTU
6
lb/10 BTU
lb/kWh
0.219
0.120
1.91
0.222
0.130
1.93
0.222
0.130
1.93
0.012
0.038
0.01
0.203
0.072
1.91
0.243
0.190
1.95
Plant Costs
Total Capital Cost
Total Direct Cost
Total Plant Cost
Total Plant Investment
Fixed Operating Cost
Variable Operating Cost
Fuel Cost
Byproduct Credit
All Others
Cost of Electricity
$/kW
$/kW
$/kW
$/kW
$/kW-year
mills/kWh
mills/kWh
Mills/kWh
Mills/kWh
Mills/kWh
1540
729
1256
1457
42.55
12.23
12.28
1.68
1.63
47.67
1549
736
1263
1465
44.06
13.04
12.54
1.43
1.85
48.71
1557
736
1269
1473
44.20
12.98
12.51
1.40
1.87
49.01
67.8
5.4
56.6
65.6
1.91
0.62
0.56
0.21
0.15
1.64
1447
729
1178
1367
41.35
11.97
11.49
1.00
1.67
46.49
1677
746
1370
1589
47.89
14.10
13.45
1.67
2.16
51.85
195
The distributions for three important model outputs - total capital cost, levelized
cost of electricity, and plant thermal efficiency are discussed in Section 9.5.
The regression analysis of results of Cases 1, 2 and 3 for the two models indicated
that three performance parameters were significantly correlated with uncertainty in plant
efficiency including carbon conversion, water to feedstock ratio, and gasifier temperature.
For both the total capital cost and levelized cost of electricity, uncertainty in project cost
contingency, engineering and home office fees, indirect construction costs, process
contingency for gas turbine, and fuel cost were found to be influential from the analysis
of Cases 1,2 and 3 for all the three models.
196
capital requirement, and the cost of electricity are the key outputs analyzed in the
following sections for the two models.
9.5.1
The distributions of the plant thermal efficiencies are collected for two models
and results are discussed below. For each model, the plant thermal efficiency of the
deterministic simulation and the frequency distributions of the plant thermal efficiency
for Cases 2 and 5 are plotted on a graph and analyzed.
9.5.1.1 Coal-Fueled Texaco-based IGCC system with Radiant and Convective
Design
The uncertainty in the plant thermal efficiency for the radiant and convective
model is shown in Figure 9.2. The deterministic result of 39.41 percent is shown as a
vertical dotted line in the graph. The probabilistic simulation (Case 2) indicates that the
mean is 38.88 percent and the median (50th percentile) is 38.91 percent, both of which
are less than the deterministic value. The key uncertain variables are the gasifier
temperature, water-to-coal ratio, carbon conversion, and the 4rth and 5th approach
temperatures. The number of uncertain variables reduced from 15 to 5. Case 5 results in
similar outputs for thermal efficiency. This indicates that there is little difference between
the two cases. Thus, the uncertainties screened out of case studies need not be the subject
of any further study and these screened model inputs were assigned point estimates. Table
9.7 indicates that the range of the efficiencies enclosed by the 90 percent confidence
interval of the distribution is from 38.05 to 39.51 percent for Case 5. The probability
distribution is negatively skewed. There is a 5 percent probability that the efficiency
197
could be less than 38.00 percent and it may go as low as 37.5 percent. There is a 15
percent probability that the efficiency would be higher than the deterministic estimate of
39.41 percent and it could go as high as 39.75 percent. Therefore, if only a point estimate
was used to predict the plant thermal efficiency, then the efficiency will be overestimated
85 percent of the time.
Cumulative Probability
1
0.8
Performance
Only - Case 2
0.6
Screened
Performance
0.4
0.2
0
37%
38%
39%
40%
Efficiency, %
Figure 9.2
198
Table 9.7
Parameter
Units
f.50
f.05
f.95
38.91
38.91
38.91
38.88
38.88
38.88
00.46
00.46
00.45
38.03
38.03
38.05
39.52
39.52
39.51
1748
1734
1737
1756
1741
1741
81
80
79
1619
1605
1605
1892
1872
1871
52.00
51.47
50.37
52.27
51.78
51.78
1.97
1.93
1.86
49.38
48.81
48.73
55.58
54.71
54.58
Deterministic
199
Cumulative Probability
1
0.8
Performance
Only - Case 2
0.6
Screened
Performance
0.4
0.2
0
33%
33%
34%
34%
35%
35%
36%
Efficiency, fraction
Figure 9.3
200
Table 9.8
Parameter
Units
Deterministic
9.5.2
f.50
f.05
f.95
34.46
34.46
34.45
34.40
34.40
34.39
00.49
00.49
00.48
33.51
33.51
33.46
35.14
35.14
35.05
1549
1533
1534
1557
1540
1540
68
66
66
1447
1432
1427
1677
1654
1649
48.71
48.06
48.00
49.00
48.41
48.41
1.64
1.58
1.57
46.88
46.07
46.19
51.85
50.95
50.89
IGCC models are discussed in the following sections. The key uncertain variables for the
total capital costs in each model are identified. The results are plotted on a graph in for
each model.
9.5.2.1 Coal-Fueled Texaco-based IGCC system with Radiant and Convective
Design
The uncertainty in the total capital cost is shown in Figures 9.4, 9.5, and 9.6.
Figure 9.4 shows the CDF' s of total capital requirements of Case 1 and Case 4, Figure
9.5 for Case 2 and Case 5, and Figure 9.6 for Cases 3 and 6. The deterministic result of
1732 $/kW is shown as a vertical dotted line in the all the above figures. The above
figures and Table 9.7 indicate that uncertainties in cost parameters have the strongest
influence on the total capital cost distribution.
201
In Case 2 and Case 5 with uncertainties only in performance input variables, the
total capital cost requirement distribution has a narrow 90% confidence interval from
1731 $/kW to 1767 $/kW as indicated in Figure 9.5. Therefore, the performance
uncertainties have less influence on the costs of the model.
In Cases 3 and 6, with uncertainties only in cost input variables, the 90 percent
confidence interval of total capital cost distribution is from 1605 $/kW to 1871 $/kW.
The probabilistic simulation with all cost uncertain variables (Case 3) indicates that the
mean is 1741 $/kW and the median (50th percentile) 1734 $/kW. The probabilistic
simulation with key cost uncertain variables (Case 6) gives a mean of 1741 $/kW and
median of 1737 $/kW. This indicates that there is little difference between the two cases.
Thus, the uncertainties screened out of case studies need not be the subject of any further
study and the screened model inputs were assigned point estimates. The total number of
uncertainties in costs reduced from a total of 25 to 11. The key uncertain variables
identified are engineering and home office fees, Indirect construction cost factor, project
contingency, process contingency factors for oxidant feed, gasification, and gas turbine,
maintenance cost factors Selexol, process condensate, and gas turbine, and units costs for
fuel cost and ash disposal.
From the Figure 9.6 showing case 3 and 6, the probability that the total capital
cost is greater than the deterministic value of 1732 $/kW is 50 percent. Therefore, if only
202
deterministic results are considered, then the total capital cost is overestimated 50 percent
of the time.
Cumulative Probability
1
0.8
0.6
Performance and
Cost - Case 1
Deterministic
0.4
0.2
0
1550
Performance and
1600
1650
1700
1750
1800
1850
1900
1950
2000
Figure 9.4
203
Cumulative Probability
1
0.8
0.6
0.4
Performance Only - Case 2
0.2
Deterministic
Performance Key - Case 5
0
1550
1600
1650
1700
1750
1800
1850
1900
1950
2000
Cumulative Probability
1
0.8
0.6
0.4
Cost Only - Case 3
0.2
Deterministic
Cost Only Key - Case 6
0
1550
1600
1650
1700
1750
1800
1850
1900
1950
Figure 9.6
204
2000
The total capital cost requirement distribution has a narrow 90% confidence
interval from 1557 $/kW to 1576 $/kW, in Cases 2 and 5, indicating that the performance
only uncertainties have small influence on the total capital cost distributions.
In Cases 3 and 6, with uncertainties only in cost input variables, the 90 percent
confidence interval of total capital cost distribution is from 1427 $/kW to 1649 $/kW.
The probabilistic simulation with all cost uncertain variables indicates that the mean is
1540 $/kW and the median (50th percentile) is 1533 $/kW, which are similar to those in
the Case 6. The key uncertain cost inputs identified for this model are engineering and
home office fees, Indirect construction cost factor, project contingency, process
contingency factors for oxidant feed, gasification, and gas turbine and units costs for fuel
cost. The total number of uncertain cost inputs reduced from 25 to 7. From the Figure 9.9
showing case 3 and 6, the probability of the total capital cost is greater than the
deterministic value of 1540 $/kW is about 50 percent. Therefore, in the case of selecting
205
only a point estimate model for predicting costs, then the total capital cost is
overestimated 50 percent of the time.
Cumulative Probability
1
0.8
0.6
Performance and
Cost - Case 1
Deterministic
0.4
0.2
0
1400
Performance and
1450
1500
1550
1600
1650
1700
1750
Figure 9.7
206
Cumulative Probability
1
0.8
0.6
0.4
0.2
0
1400
1450
1500
1550
1600
1650
1700
1750
Cumulative Probability
1
0.8
0.6
0.4
Cost Only - Case 3
0.2
Deterministic
Cost Only Key - Case 6
0
1400
1450
1500
1550
1600
1650
1700
Figure 9.9
207
1750
9.5.3
Cost of Electricity
The following sections discuss the results of probabilistic simulations for the two
IGCC models for the cost of electricity. The deterministic results are analyzed with
respect to the probabilistic results for each model. In the two models, the uncertainties in
cost parameters have the dominating influence on the cost of electricity. Therefore, Cases
3 and 6, which contain uncertainties in only cost inputs, are discussed in detail. The key
uncertainties in cost parameters influencing the cost of electricity are the same as those
described for the total capital cost in each IGCC model.
In Cases 3 and 6, with uncertainties only in cost input variables, the 90 percent
confidence interval of cost of electricity distribution is from 48.73 mills/kWh to 54.58
mills/kWh. The probabilistic simulation with all cost uncertain variables (Case 3)
indicates that the mean is 51.78 mills/kWh and the median (50th percentile) 51.47
mills/kWh both of which are higher than that of the deterministic simulation of 51.88
mills/kWh. From the Figure 9.12 showing Case 3 and 6, the total capital cost is
208
underestimated 65 percent of the time if only the point estimate simulation is used for
predicting the cost of electricity.
Cumulative Probability
1
0.8
0.6
0.4
Performance and Cost - Case 1
0.2
Deterministic
Performance and Cost Key - Case 4
0
45
47
49
51
53
55
57
59
Figure 9.10
Cumulative Probability
1
0.8
0.6
0.4
Performance Only - Case 2
0.2
Deterministic
Performance Only Key - Case 5
0
45
47
49
51
53
55
209
57
59
Figure 9.11
Cumulative Probability
1
0.8
0.6
0.4
Cost Only - Case 3
0.2
Deterministic
Cost Only Key - Case 6
0
45
47
49
51
53
55
57
59
Figure 9.12
Cases 3 and 6 are cases with uncertainties only in cost input variables. In these
cases the 90 percent confidence interval of cost of electricity distribution is from 46.19
mills/kWh to 50.89 mills/kWh. The probabilistic simulation with key cost uncertain
210
variables (Case 6) gives a mean of 48.41 mills/kWh and median of 48.00 mills/kWh
which is similar to those obtained from Case 3. Both the mean and the median are greater
than the deterministic result of 47.67 mills/kWh. From the Figure 9.15 showing case 3
and 6, the probability that the total capital cost is greater than the deterministic value of
47.67 mills/kWh is 60 percent. Therefore, if only point estimates are used, then the cost
of electricity is underestimated 60 percent of the time.
Cumulative Probability
1
0.8
0.6
0.4
Performance and Cost - Case 1
0.2
Deterministic
Performance and Cost Key - Case 4
0
44
45
46
47
48
49
50
51
52
53
Figure 9.13
211
Cumulative Probability
1
0.8
0.6
0.4
Performance Only - Case 2
0.2
Deterministic
Performance Only Key - Case 5
0
44
45
46
47
48
49
50
51
52
53
Figure 9.14
Cumulative Probability
1
0.8
0.6
0.4
Cost Only - Case 3
0.2
Deterministic
Cost Only Key - Case 6
0
44
45
46
47
48
49
50
51
212
52
53
9.6
Discussion
The probabilistic analysis indicated that the deterministic case study overestimates
the plant thermal efficiency 85 percent of the time in both the IGCC systems. The
deterministic case study underestimates the cost of electricity 60 to 65 percent of the
time.
The probabilistic analysis indicated that the range of the plant thermal efficiency
of the radiant and convective coal-fueled model (38.0 - 39.5 percent) is higher than that of
the total quench coal-fueled model (33.5 - 35.1 percent). However, the range of cost of
electricity of radiant and convective coal-fueled model (45.4 - 55.6 mills/kWh) and that
of total quench coal-fueled model (46.5 - 51.9 mills/kWh) are similar.
213
10.0
CONCLUSIONS
In the first case, a new performance, emissions, and cost model was developed
based upon refinements and modifications to a performance model previously developed
by DOE/FETC. The new model incorporates more performance details regarding key
process areas, such as the gas turbine and gasifier. New comprehensive capital, annual,
and levelized cost models have been developed in this study. In addition, the new model
includes additional features regarding flowsheet calculation sequencing and convergence
schemes, as illustrated by the addition of a number of key design specifications to
enhance the scope of important design assumptions and constraints. The new gas turbine
performance model was calibrated to published data for operation on natural gas and also
to data for operation on syngas. The other IGCC systems developed also contain the
features included for the first model such as the new gas turbine model. The models are
based upon properly sized gas turbines and deal with interactions among all process areas
in order to properly capture differences due to fuel type and gas cooling design thereby
facilitating the comparison of the different models..
214
The models of the Texaco-gasifier based IGCC systems are primarily based on the
findings of a study sponsored by the Electric Power Research Institute (EPRI) (Matchak
et al., 1984). The EPRI study provided extensive process designs which were modified as
deemed appropriate for the development of the current models. The performance model
for radiant and convective high temperature gas cooling design was adopted and modified
from a previous model developed by K.R. Stone in 1985 for Federal Energy Technology
Center (FETC). The performance model for the total quench high temperature gas
cooling model is newly developed in the present study.
Cost models for each of the IGCC system models were developed using
guidelines as suggested by the EPRI Technical Assessment Guide (EPRI, 1986), to
estimate the capital, annual, and levelized costs of the IGCC systems. The cost models
were developed as FORTRAN subroutines which are called by the performance models
of the respective IGCC systems. The inputs to the cost models are provided by the
ASPEN performance models in the form of values for key system variables, such as
flowrates.
An example case study in each of these cases illustrates the type of results that
may be obtained from the model regarding plant performance, emissions, and cost. The
results indicate that of the two IGCC system models using coal as fuel to the gasifier, the
IGCC system using the radiant and convective high temperature gas cooling has a higher
plant efficiency of 39.4 percent, and higher cost of electricity of 50.88 mills/kWh than the
215
IGCC system using the total quench high temperature gas cooling design, which has a
plant efficiency of 35.0 percent and cost of electricity of 47.67 mills/kWh.
The radiant and convective model has higher plant efficiency than that of the total
quench coal-fueled model due to the additional steam generation in the gasifier process
which in turn results in more power generation from the steam turbines. However, the
radiant and convective coolers are expensive units to maintain resulting in higher costs in
the case of the radiant and convective model than those of the total quench coal-fueled
model.
IGCC is in the early stages of development. It has been demonstrated for only
first-of-a-kind applications and there is not much history regarding the performance of
these systems. Therefore, there are inherent uncertainties in the performance and cost
parameter estimates. Therefore incorporation of uncertainties is critical for the design and
evaluation of the IGCC systems.
The efficiency, total capital cost, and cost of electricity of an IGCC system
depends on the values of key design and performance variables and cost parameter
assumptions. The new IGCC systems developed in the present study were applied
extensively in probabilistic case studies to evaluate the response of the models to changes
in these parameters and to identify key uncertainties. The uncertainties in the IGCC
systems were characterized by a systematic approach. In each of the three IGCC systems,
216
The total uncertain input variables initially assumed were 40. The total number of
key uncertainty variables were atmost 16 in any of the three cases. This reduction in the
number of uncertainties reduces the costs of conducting research in the less uncertain
process areas. The key uncertain performance input variables include the gasifier
temperature, the carbon conversion and the water-to-fuel ratio. The uncertainties in these
parameters largely influence the plant thermal efficiency and net plant output. This
indicates that significant research has to be done in the gasifier process area to reduce
risks or poor plant efficiencies. Uncertainties in the engineering and home office fees, the
project contingency, the indirect construction factor, and the fuel cost largely influence
the capital, annual, and levelized cost of all the three IGCC systems.
The probabilistic analysis indicated that the deterministic case study overestimates
the plant thermal efficiency 85 percent of the time in both the IGCC systems. The
deterministic case study underestimates the cost of electricity 60 to 65 percent of the
time.
217
The probabilistic analysis indicated that the range of the plant thermal efficiency
of the radiant and convective coal-fueled model (38.0 - 39.5 percent) is higher than that of
the total quench coal-fueled model (33.5 - 35.1 percent). However, the range of cost of
electricity of radiant and convective coal-fueled model (45.4 - 55.6 mills/kWh) and that
of total quench coal-fueled model (46.5 - 51.9 mills/kWh) are similar.
The radiant and convective model has high costs compared to conventional power
plants. However, it might be competitive in terms of high plant efficiencies and low
emissions. The coal-fueled total quench model has higher costs and lower plant
efficiencies than the conventional power plants. Therefore, it may not have any
competitive edge in the United States except under stringent NOX and SO2 regulations.
The probabilistic analysis can be used to identify key process areas which have
potential for further research, to possibly optimally configure the IGCC systems, and also
to compare more comprehensively the trade-offs between the three technologies. The
uncertainties in the costs can be reduced by a detailed cost estimate study. The models
218
will be used in future work as a benchmark for comparison with more advanced and
technologically-risky power generation system concepts.
219
11.0
REFERENCES
Agarwal, P, and H.C. Frey (1995), Development and Application of Performance and
Cost Models for the Externally-Fired Combined Cycle, Task 1 Topical Report, Volume
2, DOE/MC/29094--5246-Vol.2, Prepared by North Carolina State University for
Carnegie Mellon University and U.S. Department of Energy, Morgantown, West
Virginia, July.
Agarwal, P. and H.C. Frey (1996), Modeling and Assessment of the Externally-Fired
Combined Cycle System, Prepared by North Carolina State University for U.S.
Department of Energy, Morgantown, WV.
Anand, A.K., F.C. Jahnke, and R.R. Olson, Jr (1992), High Efficiency Quench
Gasification Combined Cycles with Integrated Air Separation, Proceedings of Eleventh
EPRI Conference on Gasification Power Plants, Electric Power Research Institute, Inc.,
Palo Alto, CA, October.
Bharvirkar, R. and H.C. Frey (1998), Development of Simplified Performance and Cost
Models of Integrated Gasification Combined Cycle Systems, Prepared by North
Carolina State University for Carnegie Mellon University, Pittsburgh, Pennsylvania, July.
220
Bjorge, R and M. Jandrisevits (1996), IGCC Technology for the 21st Century, 1996
Gasification Technologies Conference, Electric Power Research Institute, Inc., Palo Alto,
CA, October.
Buchanan, T. L., M.R. DeLallo, and J.S. White (1998), Economic Evaluation of
Advanced Coal Gasification Technologies for Power Generation, 1998 Gasification
Technologies Conference, Electric Power Research Institute, Inc., Palo Alto, CA,
October.
DeMoss, T.B. (1995), Gas, Coal Duke it out Over Repowering, Power Engineering,
21-24, June.
Doering, E.L., and U. Mahagaokar (1992), Benefits of Heat Recovery vs Water Quench
in Coal or Petroleum Coke Gasification for Power Generation, Proceedings of Eleventh
EPRI Conference on Gasification Power Plants, Electric Power Research Institute, Inc.,
Palo Alto, CA, October.
TM
1986, P-4463-SR, Electric Power Research Institute, Inc., Palo Alto, CA, December.
221
Eustis, F. H. and M.S. Johnson (1990), Gas Turbine Effects on Integrated-GasificationCombined-Cycle Power Plant Operations, GS/ER-6770, Prepared by Stanford
University for Electric Power Research Institute, Inc, Palo Alto, CA, March.
Farina, G.L., L. Bressan, and D. Todd (1998), IGCC Capital Cost and Performance,
1998 Gasification Technologies Conference, Electric Power Research Institute, Inc., San
Francisco, CA, October.
Farmer, R (1997); Gas Turbine World; Pequot Publishing Inc., Fairfield, CT; Vol 18., p
44.
Frey, H.C. and E.S. Rubin (1990), Stochastic Modeling of Coal Gasification Combined
Cycle Systems: Cost Models for Selected IGCC Systems, Report No. DOE/MC/242482901 (NTIS No. DE90015345). June. Prepared by Carnegie Mellon University for U.S.
Department of Energy, Morgantown, WV.
Frey, H.C. and E.S. Rubin (1991), Development and Application of a Probabilistic
Evaluation Method for Advanced Process Technologies, DOE/MC 24248-3105
(DE91002095), Prepared by Carnegie Mellon University for U.S. Department of Energy,
Morgantown, WV, April.
222
Frey, H.C., and E.S. Rubin (1992a), "Evaluate Uncertainties in Advanced Process
Technologies," Chemical Engineering Process, p 63-70, May.
Frey, H.C., and E.S. Rubin (1992b), "Evaluation of Advanced Coal Gasification
Combined-Cycle Systems under Uncertainty," Ind. Eng. Chem. Res., 31: 1299-1307.
Frey, H.C., and E.S. Rubin (1992c), "Integration of Coal Utilization and Environmental
Control in Integrated Gasification Combined Cycle Systems," Environ. Sci. and Tech.,
26(10):1982-1990.
Frey, H.C. (1994), "Development and Application of Performance and Cost Models for
Gas Turbine-Based Selective Catalytic Reduction NOx Control," Task 1 Topical Report,
Volume 1, Prepared by North Carolina State University for Carnegie Mellon University
and U.S. Department of Energy, Morgantown, West Virginia, October.
Energy, 19(4):449-463.
223
Frey, H.C., and R.B. Williams (1995), "Performance and Cost Models for the Direct
Sulfur Recovery Process," Task 1 Topical Report, Volume 3, DOE/MC/29094--5246Vol.3, Prepared by North Carolina State University for Carnegie Mellon University and
U.S. Department of Energy, Morgantown, West Virginia, September.
Frey, H.C. (1998), "Quantitative Analysis of Variability and Uncertainty in Energy and
Environmental Systems," Chapter 23 in Uncertainty Modeling and Analysis in Civil
Engineering, B. M. Ayyub, ed., CRC Press: Boca Raton, FL.
Hager, R. L., and D. L. Heaven (1990), Evaluation of a Dow-Based GasificationCombined-Cycle Plant Using Bituminous Coal, GS-6904. Prepared by Flour Daniel, Inc
for EPRI, Irvine, CA
Holt, N. (1998), " IGCC Power Plants - EPRI Design & Cost Studies," Proceedings of
EPRI/GTC Gasification Technologies Conference, Electric Power Research Institute,
Inc., San Francisco, CA, October.
224
Iman, R.L., and M.J. Shortencarier (1984), A FORTRAN 7 Program and User's Guide for
the Generation of Latin Hypercube and Random Samples for Use with Computer Models,
Report No. SAND83-2365, Sandia National Laboratories, Albuquerque, NM. March.
Iman, R.L., and M.J. Shortencarier and J. D. Johnson (1985), A FORTRAN 7 Program
and User's Guide for the Calculation of Partial Correlation and Standardized Regression
Coefficients, Report No. SAND85-0044, Sandia National Laboratories, Albuquerque,
NM. June.
Kerkhof, F.P.J.M. and P.van Steerderen (1993), Integration of Gas Turbine and Air
Separation Unit for IGCC Power Plants, Netherlands Agency for Energy and the
Environment, Amsterdam, Netherlands. August.
Matchak, T.A., A.D. Rao, V. Ramanathan et al. (1984), Cost and Performance for
Commercial Applications of Texaco-Based Gasification-Combined-Cycle Plants, AP3486. Prepared by Flour Engineers, Inc for EPRI, Palo Alto, CA.
Merrow, E. W., Phillips, K. E., Myers, C. W. (1981), "Understanding Cost Growth and
Performance Shortfalls in Pioneer Process Plants," Report No. R-2569-DOE, Rand
Corporation, Santa Monica, CA, September.
225
McNamee, G.P., and G.A. White (1986), Use of Lignite in Texaco Gasification-BasedCombined-Cycle Power Plants, AP-4509. Prepared by Energy Conversion Systems, Inc
for EPRI, Los Angeles, CA.
Mendez-Vigo, I., J. Pisa, J. Cortes et al. (1998), The Puertollano IGCC plant: Status
Update, 1998 Gasification Technologies Conference, Electric Power Research Institute,
Inc., Palo Alto, CA, October.
Nowacki, P. (1981), Coal Gasification Processes, Noyes Data Corporation, Park Ridge,
NJ, p 256.
Preston, W.E. (1996), "Texaco Gasification: Powering the 90's," 1996 Gasification
Technologies Conference, Electric Power Research Institute, Inc., Palo Alto, CA,
October.
226
Rocha, M. F., and H.C. Frey (1997), Cost Modeling of a Texaco Coal Gasification
Combined Cycle System, Prepared by North Carolina State University for Carnegie
Mellon University and U.S. Department of Energy, Morgantown, WV, August.
Sendin, U., W.Schellberg, W.Empsperger, et al. (1996), The Pertollano IGCC Project,
A 335 MW Demonstration Power Plant for the Electricity Companies in Europe, 1996
Gasification Technologies Conference, Electric Power Research Institute, Inc., Palo Alto,
CA, October.
Simbeck D. R., R.L. Dickenson, and E.D. Oliver (1983), Coal Gasification Systems: A
Guide to Status, Applications, and Economics, AP-3109 Prepared by Synthetic Fuel
Associates, Inc for Electric Power Research Institute, Palo Alto, California.
Simbeck, D. R. and R.L. Dickenson (1996), The EPRI Coal Gasification Guidebook - A
Review of the Recent Update, 1996 Gasification Technologies Conference, Electric
Power Research Institute, Inc., Palo Alto, CA, October.
Smith, J., and D. Heaven (1992), Evaluation of a 510-Mwe Destec GCC Power Plant
Fueled With Illinois No. 6 Coal, TR-100319. Prepared by Flour Daniel, Inc for EPRI,
Irvine, CA
Supp., E. (1990), How to Produce Methanol from Coal, Springer-Verlag, New York.
227
APPENDIX A:
BLOCK PARAMETERS
This appendix provides a summary of the ASPEN unit operation blocks and the
associated block parameters. Table 1 lists the ASPEN unit operation block and a brief
description of each block, and Table 2 lists the associated block parameters and a brief
description of each of the parameters.
Table A.1
ASPEN MODEL
DESCRIPTION
NAME
CLCHNG
COMPR
DUPL
228
FSPLIT
The flow splitter block splits an inlet stream into one or more
streams. All outlet streams have the same composition and
intensive properties as the inlet stream. However, the extensive
properties are a fraction of those of the inlet streams.
HEATER
MIXER
PUMP
229
specified
value
and
calculates
the
power
requirement.
SEP2
SEP
RGIBBS
chemical equilibrium
230
231
Table A.2
ASPEN Block
Parameter
DESCRIPTION
ENT
FRAC
IDELT
Isoentropic
Efficiency
MOLE-FLOW
NAT
NPHS
NPX
NR
NPK
RFRAC
SYSOP3
232
233
COAL-FUELED TEXACO ENTRAINED FLOW IGCC POWER PLANT WITH RADIANT AND
CONVECTIVE HIGH TEMPERATURE GAS COOLING: SYSTEM SUMMARY
***
GASIFIER CONDITIONS
***
0.584876E+06 LB/HR
0.539297E+06 LB/HR
0.294777E+06 LB/HR
615.0 PSIA
2400.0 F
***
0.148088E+07 LB/HR
0.104475E+08 LB/HR
3525.5 BTU/LB, 182.5 BTU/SCF
3769.3 BTU/LB, 195.1 BTU/SCF
2350.0 F
2432.4 F
1113.4 F
0.3790
0.9850
***
0.225048E+07 LB/HR
995.2 F
995.9 F
0.9539
0.9850
GAS TURBINE:
STEAM TURBINE:
COMPRESSORS:
PUMPS:
OXYGEN PLANT:
PLANT TOTAL:
***
0.579898E+09
0.401080E+09
-0.856458E+06
-0.559458E+07
-0.100250E+09
0.874277E+09
***
WATTS
WATTS
WATTS
WATTS
WATTS
WATTS
*********************************************
* PLANT THERMAL EFFICIENCY (HHV) = 0.3993 *
*********************************************
PERFORMANCE SUMMARY
Oxygen Blown Texaco-Based IGCC System with Cold Gas Cleanup
234
235
750172.717
640000.000
2264547.546
2200000.000
7816.940
7700.000
COST SUMMARY
Oxygen Blown Texaco-Based IGCC System with Cold Gas Cleanup
A.
C.
Coal Handling
Oxidant Feed
Gasification
Low Temperature Gas Cooling
Selexol
Claus Plant
Beavon-Stretford
Boiler Feedwater Treatment
Process Condensate Treatment
Gas Turbine
Heat Recovery Steam Generator
Steam Turbine
General Facilities
D.
1
2
5
2
2
3
2
1
1
3
3
1
N/A
236
1
2
5
2
2
4
2
1
1
3
3
1
N/A
41963.
108868.
161082.
16716.
26849.
10055.
8720.
5203.
8495.
105969.
36995.
70214.
102192.
2867.
7439.
33018.
0.
3669.
687.
1192.
0.
3483.
18101.
1264.
2399.
6982.
--------------------------------
Description
----------Total Direct Cost
Indirect Construction Cost
Sales Tax
Engineering and Home Office Fees
Environmental Permitting
Total Indirect Costs
Total Process Contingencies
Project Contingency
Total Plant Cost
AFDC
Total Plant Investment
Preproduction (Startup) Costs
Inventory Capital
Initial Catalysts and Chemicals
Land
TOTAL CAPITAL REQUIREMENT ($1,000) -------->
Annual Cost
----------703322.
140664.
28836.
87282.
1000.
257783.
81100.
182386.
1224590.
196241.
1420831.
34522.
14564.
7366.
2745.
1494237.
E.
F.
------------------------------------------
Material
Annual
Description
Unit Cost
Requirement
Operating Cost
-----------------------------------------Sulfuric Acid: 119.52 $/ton
1539.8 ton/yr
184039.
NaOH: 239.04 $/ton
317.7 ton/yr
75933.
Na2 HPO4:
0.76 $/lb
1230.7 lb/yr
936.
Hydrazine:
3.48 $/lb
5915.3 lb/yr
20567.
Morpholine:
1.41 $/lb
5492.2 lb/yr
7758.
Lime:
86.92 $/ton
709.7 ton/yr
61689.
Soda Ash: 173.85 $/ton
782.5 ton/yr
136032.
Corrosion Inh.:
2.06 $/lb
141601.1 lb/yr
292327.
Surfactant:
1.36 $/lb
141601.1 lb/yr
192321.
Chlorine: 271.64 $/ton
21.7 ton/yr
5886.
Biocide:
3.91 $/lb
24053.8 lb/yr
94088.
Selexol Solv.:
1.96 $/lb
55557.5 lb/yr
108659.
Claus Catalyst: 478.08 $/ton
12.7 ton/yr
6078.
Sul.. Acid Cat:
2.06 $/liter
0.0 liter/yr
0.
SCOT Catalyst: 249.91 $/ft3
0.0 ft3/yr
0.
SCOT Chemicals:
0.39 $/ft3
0.0 ft3/yr
0.
B/S Catalyst: 184.71 $/ft3
62.3 ft3/yr
11510.
B/S Chemicals:
N/A
N/A
134457.
Fuel Oil:
45.64 $/bbl
48949.5 bbl/yr
2233815.
Plant Air Ads.:
3.04 $/lb
3671.2 lb/yr
11169.
Raw Water:
0.79 $/Kgal
336233.6 Kgal/yr
266694.
Waste Water: 912.70 $/gpm ww 174714.7 lb/hr
207079.
LPG - Flare:
12.71 $/bbl
4283.1 bbl/yr
54449.
TOTAL CONSUMABLES ($/year) ----------------------->
4105485.
2.
237
53619480.
Ash Disposal:
Byprod. Credit:
7472670.)
10.87 $/ton
135.82 $/ton
694.8 ton/day
10.7 ton/hr
1791195.
(
($/year) ------------>
52043491.
G.
8664. BTU/kWh.
$/kW
$/(kW-yr)
mills/kWh
mills/kWh
H.
238
1420830.97
34522.25
14564.45
7366.21
2744.53
1494236.72
862.89
7488364.00
30097578.11
5858218.57
43444160.69
4105485.16
579.51
400.81
117.43
7472669.60
1791195.13
52043491.09
53619480.39
1731.66
50.35
10.59
10.91
1.52
1.2001
50.8802
8664.3324
0.3941
1.7007
0.0001
0.2209
0.0000
5
5
43
0.0671
0.6778
0.5709
0.0869
0.0249
0.1034
1.0000
584885.69
25.8016
0.0000
0.0990
3.8700
22635.0761
0.9635
239
COAL-FUELED TEXACO ENTRAINED FLOW IGCC POWER PLANT WITH TOTAL QUENCH
HIGH TEMPERATURE GAS COOLING: SYSTEM SUMMARY
***
GASIFIER CONDITIONS
***
0.604729E+06 LB/HR
0.557609E+06 LB/HR
0.304783E+06 LB/HR
615.0 PSIA
2400.0 F
***
0.183004E+07 LB/HR
0.999286E+07 LB/HR
2948.7 BTU/LB, 150.4 BTU/SCF
3152.6 BTU/LB, 160.8 BTU/SCF
2335.0 F
2410.4 F
1123.7 F
0.3891
0.9850
***
0.128138E+07 LB/HR
992.9 F
993.1 F
0.9347
0.9850
GAS TURBINE:
STEAM TURBINE:
COMPRESSORS:
PUMPS:
OXYGEN PLANT:
PLANT TOTAL:
***
0.615370E+09
0.293852E+09
-0.874967E+06
-0.620837E+07
-0.103654E+09
0.798484E+09
***
WATTS
WATTS
WATTS
WATTS
WATTS
WATTS
*********************************************
* PLANT THERMAL EFFICIENCY (HHV) = 0.3527 *
*********************************************
PERFORMANCE SUMMARY
Oxygen Blown Texaco-Based IGCC System with Cold Gas Cleanup
COST MODEL INPUT PERFORMANCE PARAMETERS
Description
----------Mass flow of coal to gasifier
Ambient temperature
Oxidant feedrate to gasifier
Oxygen flow to gasifier
Percent moisture in coal
240
------------------------------Value
----604739. lb/hr
59. F
17275.98 lbmole/hr
16412.18 lbmole/hr
0.00 percent
241
Interest:
Years of construction:
Byproduct marketing:
Average Labor Rate:
Book Life (years):
0.10
4
0.10
19.70
30
B.
C.
Coal Handling
Oxidant Feed
Gasification
Low Temperature Gas Cooling
Selexol
Claus Plant
Beavon-Stretford
Boiler Feedwater Treatment
Process Condensate Treatment
Gas Turbine
Heat Recovery Steam Generator
Steam Turbine
General Facilities
D.
1
2
5
2
2
3
2
1
1
3
3
1
N/A
1
2
5
2
2
4
2
1
1
3
3
1
N/A
50626.
112009.
55192.
32793.
18120.
10163.
8820.
5849.
11219.
105969.
31527.
51442.
83934.
3460.
7655.
11316.
0.
2477.
695.
1206.
0.
4600.
18105.
1077.
1758.
5736.
242
6952.
2860.
1221009.
E.
F.
------------------------------------------
Material
Annual
Description
Unit Cost
Requirement
Operating Cost
-----------------------------------------Sulfuric Acid: 119.52 $/ton
1888.5 ton/yr
225708.
NaOH: 239.04 $/ton
390.4 ton/yr
93318.
Na2 HPO4:
0.76 $/lb
1950.7 lb/yr
1484.
Hydrazine:
3.48 $/lb
9385.8 lb/yr
32634.
Morpholine:
1.41 $/lb
8743.3 lb/yr
12350.
Lime:
86.92 $/ton
648.7 ton/yr
56391.
Soda Ash: 173.85 $/ton
716.8 ton/yr
124623.
Corrosion Inh.:
2.06 $/lb
129328.0 lb/yr
266990.
Surfactant:
1.36 $/lb
129328.0 lb/yr
175651.
Chlorine: 271.64 $/ton
20.1 ton/yr
5453.
Biocide:
3.91 $/lb
22298.0 lb/yr
87220.
Selexol Solv.:
1.96 $/lb
57393.5 lb/yr
112250.
Claus Catalyst: 478.08 $/ton
12.9 ton/yr
6176.
Sul.. Acid Cat:
2.06 $/liter
0.0 liter/yr
0.
SCOT Catalyst: 249.91 $/ft3
0.0 ft3/yr
0.
SCOT Chemicals:
0.39 $/ft3
0.0 ft3/yr
0.
B/S Catalyst: 184.71 $/ft3
63.4 ft3/yr
11716.
B/S Chemicals:
N/A
N/A
136871.
Fuel Oil:
45.64 $/bbl
44983.0 bbl/yr
2052802.
Plant Air Ads.:
3.04 $/lb
3373.7 lb/yr
10264.
Raw Water:
0.79 $/Kgal
545675.3 Kgal/yr
432819.
Waste Water: 912.70 $/gpm ww 1379566.8 lb/hr
1635123.
LPG - Flare:
12.71 $/bbl
3936.0 bbl/yr
50037.
TOTAL CONSUMABLES ($/year) ----------------------->
5529880.
2.
($/year) ------------>
G.
55439532.
1851995.
(
55227476.
243
Capital Cost:
1539.79
Fixed Operating Cost:
42.55
Incremental Variable Costs:
1.63 mills/kWh
Byproduct Credit:
1.68 mills/kWh
Fuel Cost:
12.28 mills/kWh
Variable Operating Cost:
12.23
COST OF ELECTRICITY ---------------------------------> 47.67
Heat Rate is:
9748. BTU/kWh.
$/kW
$/(kW-yr)
mills/kWh
mills/kWh
H.
244
Fuel Cost
Capital Cost $/Kw
FOC, $/kW-yr
VOC, mills/kWh
Fuel Cost mills/kWh
Byproduct Credit, mills/kWh
Incremental VOC, mills/kWh
Cost of Electricity, mills/kWh
Heat Rate
Efficiency
CO2 Emissions
CO Emissions
SO2 Emissions
COS Emissions
CH4 Emissions
H2S Emissions
NOx Emissions
No of Op. Gasifiers
No of Total Gasifiers
No of Plant operators
Ash output
Coal Inputs
Water inputs
Water outputs (blowdown)
Sulfur outputs
Fixed Charge Factor
Variable Levelization Cost Factor
55439532.14
1539.79
42.55
12.23
12.28
1.68
1.63
47.67
9748.37
0.3503
1.9110
0.0001
0.2188
0.0000
0.0000
0.0000
0.1197
5
5
43
0.0755
0.7626
1.0082
0.0850
0.0275
0.1034
1.0000
604738.96
26.4282
0.0000
0.0990
245
HEAVY RESIDUAL OIL-FUELED TEXACO ENTRAINED FLOW IGCC POWER PLANT WITH
TOTAL QUENCH HIGH TEMPERATURE GAS COOLING: SYSTEM SUMMARY
***
GASIFIER CONDITIONS
***
***
0.134825E+07 LB/HR
0.104519E+08 LB/HR
3970.9 BTU/LB, 182.4 BTU/SCF
4283.7 BTU/LB, 196.7 BTU/SCF
2361.7 F
2444.4 F
1122.8 F
0.3770
0.9850
***
0.131168E+07 LB/HR
993.4 F
993.6 F
0.9344
0.9850
GAS TURBINE:
STEAM TURBINE:
COMPRESSORS:
PUMPS:
OXYGEN PLANT:
PLANT TOTAL:
***
0.591583E+09
0.295136E+09
-0.310176E+06
-0.555983E+07
-0.702001E+08
0.810649E+09
***
WATTS
WATTS
WATTS
WATTS
WATTS
WATTS
*********************************************
* PLANT THERMAL EFFICIENCY (HHV) = 0.3927 *
*********************************************
PERFORMANCE SUMMARY
Oxygen Blown Texaco-Based IGCC System with Cold Gas Cleanup
COST MODEL INPUT PERFORMANCE PARAMETERS
Description
----------Mass flow of oil to gasifier
Ambient temperature
Oxidant feedrate to gasifier
Oxygen flow to gasifier
Percent moisture in oil
246
------------------------------Value
----368078. lb/hr
59. F
11700.22 lbmole/hr
11115.21 lbmole/hr
0.00 percent
1642.913
1200.000
0.003
0.004
COST SUMMARY
Oxygen Blown Texaco-Based IGCC System with Cold Gas Cleanup
247
A.
C.
Oil Handling
Oxidant Feed
Gasification
Low Temperature Gas Cooling
Selexol
Claus Plant
Beavon-Stretford
Boiler Feedwater Treatment
Process Condensate Treatment
Gas Turbine
Heat Recovery Steam Generator
Steam Turbine
General Facilities
D.
2
3
2
2
1
1
1
1
3
3
1
N/A
2
3
2
2
2
1
1
1
3
3
1
N/A
0.
80363.
33115.
29064.
15601.
3043.
8730.
5228.
8768.
105969.
31740.
51667.
63459.
0.
5494.
6792.
0.
2133.
208.
1194.
0.
3597.
18113.
1085.
1766.
4339.
248
Project Contingency
Total Plant Cost
AFDC
Total Plant Investment
Preproduction (Startup) Costs
Inventory Capital
Initial Catalysts and Chemicals
Land
TOTAL CAPITAL REQUIREMENT ($1,000) -------->
112336.
754259.
120870.
875129.
20394.
1237.
7143.
2550.
915204.
E.
F.
------------------------------------------
Material
Annual
Description
Unit Cost
Requirement
Operating Cost
-----------------------------------------Sulfuric Acid: 119.52 $/ton
1632.5 ton/yr
195112.
NaOH: 239.04 $/ton
328.3 ton/yr
78470.
Na2 HPO4:
0.76 $/lb
1488.3 lb/yr
1132.
Hydrazine:
3.48 $/lb
7156.9 lb/yr
24884.
Morpholine:
1.41 $/lb
6655.4 lb/yr
9401.
Lime:
86.92 $/ton
664.2 ton/yr
57738.
Soda Ash: 173.85 $/ton
733.5 ton/yr
127523.
Corrosion Inh.:
2.06 $/lb
132447.7 lb/yr
273431.
Surfactant:
1.36 $/lb
132447.7 lb/yr
179889.
Chlorine: 271.64 $/ton
20.5 ton/yr
5563.
Biocide:
3.91 $/lb
22744.3 lb/yr
88966.
Selexol Solv.:
1.96 $/lb
49230.0 lb/yr
96283.
Claus Catalyst: 478.08 $/ton
2.0 ton/yr
955.
Sul.. Acid Cat:
2.06 $/liter
0.0 liter/yr
0.
SCOT Catalyst: 249.91 $/ft3
0.0 ft3/yr
0.
SCOT Chemicals:
0.39 $/ft3
0.0 ft3/yr
0.
B/S Catalyst: 184.71 $/ft3
91.4 ft3/yr
16885.
B/S Chemicals:
N/A
N/A
197254.
Fuel Oil:
45.64 $/bbl
45991.3 bbl/yr
2098815.
Plant Air Ads.:
3.04 $/lb
3449.3 lb/yr
10494.
Raw Water:
0.79 $/Kgal
411164.7 Kgal/yr
326128.
Waste Water: 912.70 $/gpm ww 895040.5 lb/hr
1060841.
LPG - Flare:
12.71 $/bbl
4024.2 bbl/yr
51159.
TOTAL CONSUMABLES ($/year) ----------------------->
4900923.
2.
($/year) ------------>
G.
0.
1127229.
(
4342960.
249
Oil Handling
Oxidant Feed
Gasification
Low T Cool.
Selexol
0.00 Claus
58.47 B/S
0.49 Proc. Cond
1.55 Steam Cycle
1.00 General Fac
Capital Cost:
1128.85
Fixed Operating Cost:
31.40
Incremental Variable Costs:
1.31 mills/kWh
Byproduct Credit:
0.37 mills/kWh
Fuel Cost:
0.00 mills/kWh
Variable Operating Cost:
0.94
COST OF ELECTRICITY ---------------------------------> 26.96
Heat Rate is:
8693. BTU/kWh.
0.04
1.88
0.87
4.23
6.85
$/kW
$/(kW-yr)
mills/kWh
mills/kWh
H.
250
3819458.04
25460617.03
4900922.93
1685191.73
1127228.88
4342960.08
0.00
1128.85
31.40
0.94
0.00
0.37
1.31
26.96
8693.19
0.3928
1.4413
0.0001
0.0467
0.0000
0.0000
0.0000
0.1371
3
3
39
0.0449
0.4540
0.7430
0.0778
0.0060
0.1034
1.0000
368078.29
5.1382
0.0000
0.0990
1.4000
5153.0961
0.9681
251
252