PIP CVE02350 Roadway Design Guide PDF
PIP CVE02350 Roadway Design Guide PDF
PIP CVE02350
Roadway Design Guide
PRINTING HISTORY
September 2008
Issued
Not printed with State funds
September 2008
PIP CVE02350
Roadway Design Guide
Table of Contents
1. Introduction................................. 3
1.1 Purpose............................................ 3
1.2 Scope ............................................... 3
2. References .................................. 3
2.1 Process Industry Practices .............. 3
2.2 Industry Guides and Standards ....... 3
3. Definitions ................................... 4
4. Roadway Classifications ........... 5
4.1
4.2
4.3
4.4
4.5
General ............................................ 5
Primary Roadways........................... 5
Secondary Roadways ...................... 6
Tertiary Roadways ........................... 6
Construction and Heavy Haul
Roadways ........................................ 6
7. Paving/Roadway Design.......... 15
7.1
7.2
7.3
7.4
8. Drainage Considerations......... 29
8.1
8.2
8.3
8.4
8.5
8.6
8.7
Right-of-Way .................................... 7
Access to Public Roadways............. 7
Materials........................................... 9
Climate ............................................. 9
Traffic Loading ............................... 10
9. Crossings.................................. 39
Page 1 of 40
September 2008
Drawings
CVE02350-01 Typical Roadway Sections at Cut and Fill
CVE02350-02 Guard Rail Assembly
CVE02350-03 Guard Rail Details
CVE02350-04 Guard Posts
CVE02350-05 Headwalls
CVE02350-06 Headwalls with Wing Walls
CVE02350-07 Typical Roadway Clearance Envelope
CVE02350-08 Roadway Contraction Joint
CVE02350-09 Roadway Doweled Expansion Joint
CVE02350-10 Roadway Doweled Construction Joint
CVE02350-11 Roadway Doweled/Keyed Joint
Page 2 of 40
September 2008
1.
PIP CVE02350
Roadway Design Guide
Introduction
1.1
Purpose
This Practice provides guidance and recommended procedures for the layout and design
of roadways inside plant boundaries and for access to a plant facility.
1.2
Scope
This Practice describes roadway classifications and provides guidance for design of rightof-ways, access to public roads, use of local materials, climate effects, traffic loading,
layout and traffic control, design of paving and roadways, providing drainage, and
providing railroad and pipeline crossings for roadways within plant boundaries and for
access to a plant facility.
2.
References
Applicable requirements of the following Practices, and industry codes and standards, and
references should be considered an integral part of this Practice. The edition in effect on the date
of contract award should be used, except as otherwise noted. Short titles are used herein where
appropriate.
2.1
2.2
Page 3 of 40
PIP CVE02350
Roadway Design Guide
September 2008
ASTM D1883 Standard Test Method for CBR (California Bearing Ratio) of
Laboratory-Compacted Soils
ASTM D2844 Standard Test Method for Resistance R-Value and Expansion
Pressure of Compacted Soils
3.
Definitions
asphalt concrete: High-quality, thoroughly-controlled hot mixture of asphalt cement and wellgraded, high-quality aggregate, thoroughly compacted into a uniform dense mass
base course: A layer of well-graded granular material that supports the paving and distributes
wheel loads over a greater area of the subgrade
binder course: For a multi-layered paving system, a layer directly below the wearing course, and
composed of intermediate-sized aggregate with a lesser amount of asphalt than the wearing
course
geogrid: High tensile strength polymer material designed with transverse and longitudinal grids.
Laid directly on the subgrade, the grid geometry provides a mechanism for interlocking aggregate
base or subbase material placed on the geogrid. The interlocking prevents lateral movement of the
aggregate and improves load distribution to the subgrade.
geotextile: Polyester fabric material laid over subgrade materials directly below an aggregate
subbase. It maintains separation of subbase from subgrade. Geotextile is permeable, allowing
pore water to pass vertically through the fabric.
owner: The party who owns the facility wherein the roadway will be constructed
paved surface: Reinforced or asphaltic concrete that distributes the load to base and subbase,
seals against penetration of surface water or liquids, resists abrasion, and provides traction
plant boundaries: The delineation between areas accessible to the general public and areas where
access is controlled by the plant
subbase: A compacted layer of well-graded fill that may be required under the base course.
Typically provided over fine grained subgrade soils to improve drainage, resist frost heave,
provide structural support by distributing loads, and to prevent pumping of finer grained soils into
the base material at paving joints and edges.
subgrade: Foundation soil placed and/or compacted during the rough grading work. Typically
consists of natural soils found on site, unless soil strength is inadequate and imported soils are
required.
wearing course: A layer of fine aggregate or course sand held by an asphalt binder and designed
to resist wear from traffic. The layer which directly supports traffic.
Page 4 of 40
September 2008
4.
PIP CVE02350
Roadway Design Guide
Roadway Classifications
4.1
4.2
General
4.1.1
All major plant areas should be accessible by primary roads from two opposite
sides minimum and preferably all around to provide adequate access for
firefighting and other emergency equipment. As a minimum, a tertiary road
around the plant should be considered.
4.1.2
4.1.3
4.1.4
Type of roadway pavement is defined based on traffic, load, weather, air and
ground pollution controls, cost, etc. It includes paved roads such as asphalt and
concrete and unpaved roads such as gravel. This guide focus is on paved roads.
Primary Roadways
4.2.1
4.2.2
4.2.1.2
Vehicle velocities are normally set by owner and are posted 30 mph or
less.
4.2.1.3
Roadways with high volume truck traffic (e.g., between main shipping
and receiving docks) may require a greater than typical radius and
should also be designed for loadings in accordance with AASHTO
Guide for Design of Pavement Structures, and the local state highway
design manuals for the applicable locale.
4.2.1.4
4.2.1.5
4.2.2.2
Page 5 of 40
PIP CVE02350
Roadway Design Guide
4.3
September 2008
4.2.2.3
4.2.2.4
Secondary Roadways
4.3.1
4.3.2
4.4
4.5
Page 6 of 40
Tertiary Roadways
4.4.1
4.4.2
Tertiary roadways may have one or two lanes and be up to 20 ft wide, with or
without shoulders.
4.4.3
Construction and heavy haul roadways provide greater than typical load capacity
and have specialized service conditions.
4.5.2
September 2008
5.
PIP CVE02350
Roadway Design Guide
4.5.3
4.5.4
Service life, maximum grade, clearances, turning points, load and unloading
points, drainage, and environmental impact on the surrounding areas
(e.g., surface drainage, noise, dust, etc.) should be considered in the initial layout
of these roadways.
Right-of-Way
5.1.1
5.1.2
5.2
General
5.2.1.1 Design of roadways within plant property boundaries is typically
unencumbered by regulation and should be performed and executed with
good engineering practices specific to a plants mobility needs and safety
requirements.
5.2.1.2 Movement of people, products and material across plant property
boundaries requires interaction with adjacent property owners or
authorities and entities vested with the power to regulate or control
waterway usage, rail and pipeline systems, utilities, and roadways.
5.2.1.3 Consideration of access to public roadways is important for the design of
a new plant and can also be important for a major project at an existing
plant.
5.2.2
Page 7 of 40
PIP CVE02350
Roadway Design Guide
September 2008
5.2.2.2 Plant shift changes can place a heavy, short-term demand on a local
roadway system two or more times a day.
5.2.2.3 Outbound and inbound shipping of products, supplies and feed stocks by
truck requires special consideration regarding access to local roadway
systems.
5.2.2.4 Because of additional transportation for craft workers and other project
team members, increased truck traffic for delivery of equipment and
materials, and traffic from permit loads for equipment and construction
material, plant construction projects can affect local traffic conditions.
Controlled and adequate access to local streets and highways during
major construction projects requires early team planning and may require
investment in new road access points.
5.2.3
Regulation of Access
5.2.3.1 Control of access points is a method used by regulators to manage the
quality of a roadways mobility, capacity, potential for collisions, and
access for adjacent land use.
5.2.3.2 Methods used by governmental authorities for controlling access points
to public streets and roadways include the following:
a. Regulations - Ordinances at the local level
b. Eminent Domain - A way for the government to purchase property
for public roads. Property owners are compensated for the property
taken; however, property owners may donate land for right-of-way if
they can benefit from a road project or from having new or
additional access to a road.
5.2.3.3 Long term planning is an essential aspect of access management and the
principles and policies adopted by regulators are defined for an entire
system that includes the roads and local land use that generates travel.
5.2.3.4 Regulators are typically required to provide reasonable access, although
not necessarily direct access, to roads from adjacent property.
5.2.4
Page 8 of 40
September 2008
PIP CVE02350
Roadway Design Guide
5.2.4.5 Expected plant traffic volume and generated loads should be determined
to complete the pavement and drainage design to the plant boundary.
5.2.5
Plant Entry
5.2.5.1 Permanent parking facilities for plant employees and visitors are
typically located outside the plant fence.
5.2.5.2 Permanent security facilities to enter a plant from the parking area are
typically required and may consist of badge controlled turnstiles for
pedestrians and checkpoint shelters occupied by security staff for
vehicular access.
5.2.5.3 Truck weigh stations are often required at plant vehicular entrances.
5.2.5.4 Temporary parking and security facilities for construction projects may
be required to be located on available plot space within the plant fence.
5.2.6
Easements
5.2.6.1 Plant boundaries may be adjacent to or include dedicated easements or
right-of-ways for drainage, utilities, pipelines and railroads. New plant
roadways can be required to cross or run parallel to these easements.
5.2.6.2 Design interfaces with one or more entities that own or regulate
easements may be required in order to protect their facilities from new
traffic loads. If more than one entity is involved, it can be challenging to
resolve multiple requirements.
5.2.6.3 Resolutions of easement concerns can involve the following items that
are typically paid for by the plant owner:
a. Raising or rerouting overhead lines
b. Providing protective sleeves for pipelines
c. Installing culverts or bridges for ditches
d. Improving traffic crossings for railroads
5.3
Materials
5.3.1
5.3.2
5.4
Climate
5.4.1
Rainfall and temperature extremes should be considered for both the design and
construction phases of roadway projects.
5.4.2
Page 9 of 40
PIP CVE02350
Roadway Design Guide
5.5
6.
September 2008
5.4.3
Cold weather affects the installation of concrete and asphalt surfaces. Asphalt
may not be available in colder climates during part of the year.
5.4.4
For hot weather, special provisions for placing concrete can be required.
Traffic Loading
5.5.1
5.5.2
5.5.3
5.5.4
For design of haul roads, type of transport equipment and frequency of travel
should be considered.
6.2
6.3
General
6.1.1
Layout for a roadway within a plant should be in accordance with the plant grid
system and the established plant coordinate system for horizontal and elevation
control (e.g., Horizontal Control Plant Datum and Plant Elevation).
6.1.2
6.1.3
Traffic Flow
6.2.1
Traffic flow within plant boundaries is typically limited to low volume, low
speed vehicles, trucks, and construction and maintenance equipment.
6.2.2
Emergency vehicle access and flow to the most critical sites of a plant should be
considered.
6.2.3
Page 10 of 40
September 2008
PIP CVE02350
Roadway Design Guide
6.3.2
Page 11 of 40
PIP CVE02350
Roadway Design Guide
September 2008
PATH OF
OVERHANG
PATH OF LEFT
FRONT WHEEL
"
"C
MI
RA N.TU
DI RN
US
I
("A NG
")
"
"B
PATH OF RIGHT
REAR WHEEL
VEHICLE DIMENSIONS
11'
5'
14.4'
1.5'
3'
7'
24.0'
4'
8'
6'
28.3'
1.5'
40.0'
19.3'
0.8'
45.0'
17.0'
0.7'
8'
2'
42.0'
31.4'
4.2'
10.4'
3'
8.5'
2'
Page 12 of 40
Lane Width
Shoulder Width
Primary Roads
Secondary Roads
Tertiary Roads
10 - 12 ft
10 ft
8 ft
3 ft
3 ft
2.5 ft
September 2008
6.4
PIP CVE02350
Roadway Design Guide
Vertical Alignment
6.4.1
Gradients
6.4.1.1 Maximum and minimum vertical gradients along a roadway alignment or
across a paved area are shown in Table 2.
6.4.1.2 If possible, vertical gradients should be kept near the minimum value
shown in Table 2.
6.4.1.3 For areas subject to ice and snow conditions, the vertical gradient should
be 5% maximum.
Table 2 Vertical Gradients
Type
Maximum
Minimum
Primary Roads
5.0%
Secondary Roads
7.5%
Tertiary Roads
10.0%
10.0%
3.0%
1.0%
Paved Areas
6.0%
1.0%
Unpaved Areas
1.5%
1.0%
6.4.2
Curves
6.4.2.1 Vertical curves provide a gradual transition between two intersecting
tangent grade lines.
6.4.2.2 The types of vertical curves are sag and crest. Each curve type has three
subsets depending on the signs and relative magnitudes of the tangent
gradient lines. The typical sign convention is positive for grades
ascending forward and negative for grades descending forward.
6.4.2.3 Algebraic change in gradient and stopping sight distance are the
important parameters for vertical curve design at typical plant vehicle
speeds. For example, at 20 mph, the AASHTO recommended stopping
sight distance is 115 ft. The minimum recommended curve length for a
5% change in gradient is 35 ft for a crest curve and 85 ft for a sag curve.
These lengths include factors for height of eye and the object sighted that
would permit 115 ft stopping sight distance.
6.4.2.4 Vertical curves should be provided for hard surfaced roads having a
change in vertical alignment greater than 3% at typical low plant speeds.
6.4.2.5 Vertical curves are designed parabolic with length measured as the
horizontal projection of the curve, and are typically designed
symmetrical with tangents of equal length.
6.4.2.6 See AASHTO, A Policy on Geometric Design of Highways and Streets,
or route design textbook for additional geometric design information.
Page 13 of 40
PIP CVE02350
Roadway Design Guide
6.5
September 2008
6.5.2
Owner should be consulted for special requirements that can dictate specific
clearances.
6.5.3
6.5.4
6.6
6.7
Page 14 of 40
Minimum
Clearance
18-0
10-0
22-0
6.6.2
6.6.3
Special hazards that have the minimum clearances can still require protection
with guardrails or guard posts.
6.6.4
See drawings CVE02350-02 to -04 for typical details for guardrail and guard
posts.
Pavement Marking/Signage
6.7.1
Pavement marking and signage within plant boundaries are typically limited to
road names, speed limits, stop signs, clearance signs, railroad crossings, and
evacuation routes.
6.7.2
For designating traffic control devices, pavement markings and signage within
and outside plant boundaries, see FHWA Manual on Uniform Traffic Control
Devices (MUTCD).
September 2008
7.
PIP CVE02350
Roadway Design Guide
Paving/Roadway Design
7.1
Types
7.1.1.1 Typically, two types of paving systems are used for roadways: flexible
and rigid. See example configurations in Figure 2.
7.1.1.2 Flexible paving is composed of material such as asphaltic concrete, and
relies on a relatively thin paving (e.g., 2 to 4 inches thick) in combination
with layers of base and subbase material to distribute vehicle loads.
7.1.1.3 Rigid paving is composed of material such as portland cement concrete
which has low flexibility and is capable of distributing wheel loading
over a wide area of subgrade.
7.1.1.4 The relative costs of asphaltic concrete and portland cement concrete
paving vary considerably between geographic locations. Typically, the
initial cost of portland cement concrete is higher (30 to 50% in some
cases) than asphaltic concrete paving. However, studies of state and
federal highway records by the Portland Cement Association have shown
that portland cement concrete paving has a lower total cost of ownership
than asphaltic concrete paving.
ASPHALT BINDER COURSE
PRIMECOAT
CONCRETE
BASE COURSE
SUBBASE
SUBBASE
SUBGRADE
SUBGRADE
FLEXIBLE PAVING
RIGID PAVING
7.1.2
Advantages/Disadvantages
7.1.2.1 Flexible Paving
Page 15 of 40
PIP CVE02350
Roadway Design Guide
September 2008
Flexible Pavement
7.2.1
Asphalt Terminology
Following are definitions of terms used for various aspects of asphalt paving
components and construction:
a. Asphalt pavement structure: Combination of asphalt courses and asphaltaggregate or untreated aggregate courses, placed above the subgrade
b. Full-depth asphalt pavement: Pavement in which asphalt mixtures are used
for all courses above the subgrade
c. Asphalt prime coat: Spray application of low-viscosity asphalt emulsion to
an untreated base to bind the granular material to the asphalt layer
d. Asphalt tack coat: Spray application of asphaltic material to existing
pavement (e.g., portland cement or old asphalt) to insure bond between
superimposed material and existing surface
e. Asphalt seal coat: Thin asphalt surface treatment used to waterproof and
improve the durability of an existing surface
f.
Emulsified asphalt: Fine droplets of asphalt suspended in water used for road
construction, sealing and surface treatments, and patching mixes. Droplets
are held in suspension for a long time because of emulsifying agents. The
material can be handled with little or no heat. The following types are
available: rapid setting, medium setting, and slow setting.
g. Liquid asphalt or cutback asphalt: Uses solvents to thin the asphalt to enable
handling at lower temperatures. Naphtha-type, kerosene-type, and light oil
Page 16 of 40
September 2008
PIP CVE02350
Roadway Design Guide
solvents are used to produce rapid, medium, and slow curing asphalt
materials, respectively. Because of environmental concerns, federal and state
regulations either severely restrict or prohibit the use of liquid asphalt. Liquid
asphalts have typically been replaced by emulsified asphalts.
h. Asphalt cold mix: Mixture of unheated mineral aggregate and emulsified
asphalt. May be produced in stationary plants with close control of the
production process or mixed in place. Spreading and compaction is
performed with conventional equipment.
7.2.2
1. General
a. Thickness requirements for asphalt pavements depend mainly on
the strength requirements of the finished subgrade.
b. For a project with significant paving requirements, with heavy
vehicle loading, and no directly relatable paving experience for
the site, subgrade evaluation should be included as part of other
Page 17 of 40
PIP CVE02350
Roadway Design Guide
September 2008
Page 18 of 40
September 2008
PIP CVE02350
Roadway Design Guide
Page 19 of 40
PIP CVE02350
Roadway Design Guide
September 2008
Typical Evaluation
Values
Relative Quality
GOOD
Coarse-grained
soils
(well-graded)
Gravel, sand
w/limited clay
binder
FAIR
Coarse-grained
soils
(poorly-graded)
Sands, and
sand/clay
mixtures
POOR
Fine-grained soils
Traffic Volume
Resist.
Mod. (Mr)
Trucks
>500
CBR
Cars
Unlimited
<500
Unlimited
<50
<2000
<20
<300
<5
<50
40-60
12,000 psi
Pavement
(Note 1)
Base &
Subbase
(Note 2)
Pavement
(Note 1)
Base &
Subbase
(Note 2)
Pavement
(Note 1)
Base &
Subbase
(Note 2)
12
11
10
20-40
5,500 psi
4-20
3,000 psi
Plastic, high
shrinkage
and expansion,
low-permeability
Notes:
(1) Paving thicknesses are based on asphaltic concrete (hot-mix). Alternative paving materials (cold-mix) may require additional
thickness or additional base/subbase.
(2) A minimum of 6-inches of higher quality base materials should be placed over lower quality subbase materials.
Examples
Good
Fair
Poor
12,000
5,500
3,000
Dry, no freeze
S California, S Texas
Wet, no freeze
9,500
5,000
2,800
Wet, freeze/thaw
cycling
7,300
4,500
2,700
5,700
4,000
2,700
Dry, freeze/thaw
cycling
E Washington, N Texas
8,200
5,000
3,000
Wyoming, Montana
5,700
4,100
2,800
Page 20 of 40
September 2008
PIP CVE02350
Roadway Design Guide
7.2.4
7.2.5
Sand/shell mixtures
Page 21 of 40
PIP CVE02350
Roadway Design Guide
September 2008
1. For areas subject to frost damage, base and subbase materials should
contain not greater than 8% by weight of particles finer than 200
mesh. This helps to maintain good drainage through the materials
and reduce frost heave potential.
2. If low-quality subgrade soils are present, consideration should be
given to the use of geotextiles (see Section 7.4). The cost of using
geotextile fabric over the weak subgrade may be offset by reduction
in base and subbase costs.
7.2.6
Page 22 of 40
September 2008
PIP CVE02350
Roadway Design Guide
1. Road mix paving is emulsified asphalt sprayed onto and mixed into
aggregate at moderate-to-warm ambient temperatures. Mixed-inplace construction may be used for surface, base, or subbase courses.
2. If used as a surface or wearing course, road mix is typically
satisfactory for light and medium traffic. However, mixed-in-place
layers covered by a high-quality plant mix surface course can
provide a pavement suitable for heavy traffic.
3. Advantages of road mix include the following:
a. Can use aggregate already on the roadbed or available from
nearby sources, and without extensive processing
b. Eliminates the need for a central mixing plant
c. Placement can be performed with a variety of machinery often
readily available (e.g., motor graders, rotary mixer with
revolving tines, and traveling mixing plants).
4. Limitations of road mix include the following:
a. Should not be installed if ambient temperatures is less than 50F
because proper mixing of asphalt and aggregate is difficult
b. If surface moisture on the aggregate is not properly controlled,
excessive moisture causes problems in mixing, curing and
compacting. Typically surface moisture should not be greater
than 3%.
c. Quality of mixed-in-place paving is more difficult to control than
plant mixes.
Page 23 of 40
PIP CVE02350
Roadway Design Guide
7.2.7
September 2008
Asphalt Coatings
7.2.7.1 Prime Coat
1. Typically for untreated granular bases, when the base course has
been properly compacted and loose material removed, an asphalt
prime coat should be applied.
2. A pressure distributor should be used to spray approximately 0.2 to
0.5 gal/sq yd of low-viscosity asphalt on the prepared surface of the
base.
3. The asphalt prime coat should be fully absorbed by the base and
permitted to set and cure before placing the surfacing.
7.2.7.2 Tack Coat
Rigid Paving
7.3.1
Subgrade
7.3.1.1 General
Page 24 of 40
September 2008
PIP CVE02350
Roadway Design Guide
k Value (pci)
Very Good
>550
Crushed Rock
Good
400-550
Well-graded gravel
Fair
250-350
Poor
150-250
Very Poor
<150
7.3.2
Subbase
7.3.2.1 General
1. Dense-graded material
2. Maximum aggregate size, 1/3 subbase thickness
3. Particles finer than 200 mesh, 15% maximum
4. Plasticity Index, 6% maximum
Page 25 of 40
PIP CVE02350
Roadway Design Guide
7.3.3
September 2008
Paving Thickness
7.3.3.1 For light traffic areas, walkways, and areas designed for automobiles or
pick-up trucks, paving should be 4 inches thick.
7.3.3.2 For areas designed for heavier vehicles (e.g., equivalent H-20 loading
maximum), paving should be 6 inches minimum.
7.3.3.3 For areas designed for heavier loads (e.g., large mobile cranes), a more
detailed paving analysis should be considered.
7.3.3.4 See Table 7 for recommended thicknesses for various subgrade strengths
and expected loadings.
7.3.3.5 See drawings CVE02350-08 to -11 for typical details of rigid roadway
joints.
7.3.3.6 See ACI 504R for joint sealants information.
Table 7 Concrete Paving Thicknesses
Design
Vehicle
Loading
Pickup
H-15
H-20
7.4
Paving (inch)
Subbase (inch)
Paving (inch)
Subbase (inch)
Paving (inch)
Subbase (inch)
General
7.4.1.1 Paving with asphalt or portland cement concrete is typically limited to
areas where, because of traffic loads or other considerations, the cost of
paving is justified.
7.4.1.2 Other surface treatments that have application for limited vehicle traffic
include the following:
a. Crushed rock
b. Gravel
c. Stabilized soil
7.4.1.3 Walking on these alternate surfaces can be difficult unless suitable
material gradations are used and compacted to 90 to 95% of their
maximum density.
7.4.2
Page 26 of 40
September 2008
PIP CVE02350
Roadway Design Guide
7.4.2.2 Crushed rock surfacing is typically used for the following conditions:
a. An all-weather, well-drained surface is specified.
b. Neat appearance is important.
c. Heavy vehicle traffic is not expected.
7.4.2.3 For the best wearing, well-compacted surface, a well-graded crushed
rock material with the gradation (e.g., grain-size distribution) shown in
Table 8 should be provided.
Table 8 Crushed Rock Gradation
Sieve Size
1 inch
100
3/4 inch
90-100
1/2 inch
25-60
3/8 inch
10-15
No. 4
0-3
7.4.2.4 To limit the growth of vegetation through the rock surface, a weed killer
approved by owner should be applied to the area before spreading the
crushed rock.
7.4.3
Gravel
7.4.3.1 Gravel is defined to be the wide variety of soil mixtures that have a
significant portion of gravel (e.g., grain size .08 inch to about 3 inches)
and/or coarse sand.
7.4.3.2 Gravel can be found naturally at the site, or imported from a borrow pit.
7.4.3.3 Gravel can be well-graded (e.g., relatively uniform distribution of grainsize particles) to poorly graded (e.g., excessive percentages of certain
grain sizes and absence of others). Some gravels have some plasticity,
whereas others are non-plastic.
7.4.3.4 Well-graded gravels provide better and longer-lasting surfaces, and tend
to perform better if they have a small percentage of clay which acts as a
binder.
7.4.3.5 Poorly-graded gravels can become soft during wet weather and loose and
dusty in dry weather.
7.4.3.6 The wearing properties of gravel surfaces can be improved by applying
emulsified asphalt to cement the gravel.
7.4.3.7 For well-graded gravel, the gradation shown in Table 9 should be
provided.
Table 9 Gravel Gradation
Designated Sieve
No. 10
20-100
No. 40
10-70
No. 200
3-25
Page 27 of 40
PIP CVE02350
Roadway Design Guide
7.4.4
September 2008
Stabilized Soil
7.4.4.1 In addition to typical compaction techniques for strengthening soils,
chemical additives including the following can enhance soil properties:
a. Portland cement
b. Asphalt
c. Lime
d. Calcium chloride
7.4.4.2 Chemical additive treatments can accomplish the following:
a. Upgrade the strength of very poor subgrade materials under
roadways
b. Decrease the permeability of soils
c. Act as a palliative to control dust problems
d. Provide a surface for areas not subject to heavy vehicle loads
7.4.4.3 The quantity of additive required and the expected stabilization gain
depends on the properties of the natural soil and the depth of soil to be
stabilized. Laboratory testing may be performed to assess the value of
using chemical additives.
7.4.4.4 Following is a typical procedure for stabilizing soils:
a. Scarify the existing surface
b. Spread chemical additives
c. Mix with motor grader using windrow mixing or alternative
procedure
d. Spread the mixture
e. Compact the surface as required
7.5
General
Historically, if low-strength soils were encountered, the undesirable soils were
either excavated and replaced with better material, or over-laid with thicker
subbase materials to reduce unit loading to the subgrade. However, with the
development of a line of geogrid and geotextile products, other alternatives are
available for working with problem soils.
7.5.2
Geogrids
7.5.2.1 Geogrids are manufactured from high tensile strength polymer, and
designed with transverse and longitudinal ribs.
7.5.2.2 Laid directly on subgrade, the geogrid geometry provides a mechanism
for interlocking aggregate base or subbase material placed on the
geogrid. The interlocking prevents lateral movement of the aggregate and
improves load distribution to the subgrade.
Page 28 of 40
September 2008
PIP CVE02350
Roadway Design Guide
7.5.2.3 Geogrid materials are inert to typical chemical and biological conditions
in soils and are not expected to degrade.
7.5.3
Geotextile
7.5.3.1 Geotextile is manufactured from polyester in rolls up to 16 ft wide and
300 to 1000 ft long.
7.5.3.2 Laid over subgrade materials directly below an aggregate subbase,
geotextile is designed to perform any or all of the following functions:
a. Maintains separation between subbase and subgrade. Coarse
aggregate cannot move downward, and fine soil particles in the
subgrade cannot rise into the subbase.
b. Is permeable and permits pore water to pass vertically through the
fabric
c. Tensile strength of the geotextile material provides tensile
reinforcement for subbase
d. Permits lateral water flow within the plane of the geotextile material
and dissipates excess pore water pressure
7.5.3.3 Geotextiles are resistant to freeze-thaw and soil chemicals.
8.
Drainage Considerations
8.1
8.2
Roadway Drainage
8.1.1
8.1.2
Subsurface water should also be drained away from the roadbed for a sufficient
depth below the road surface to prevent frost troubles, and maintain a layer of
stable material thick enough to distribute the pavement pressure successfully to
less stable layers beneath.
Culverts
8.2.1
General
8.2.1.1 Culverts are used to channel water under roadways and driveways or to
remove drainage from ditches.
8.2.1.2 A wide variety of standard shapes and sizes are available for most culvert
materials. Because equivalent openings can be provided by a number of
standard shapes, the selection of shape may not be critical in terms of
hydraulic performance.
8.2.1.3 Factors governing culvert shape selection may include some of the
following:
a. Depth of cover
b. Limited headwater elevation where a low profile shape may be
required
Page 29 of 40
PIP CVE02350
Roadway Design Guide
September 2008
Culvert Materials
8.2.2.1 General
Page 30 of 40
September 2008
PIP CVE02350
Roadway Design Guide
8.2.3
Culvert Coatings
8.2.3.1 General
Ditches
8.3.1
General
8.3.1.1 Roadside ditches should prevent water from pooling on the roadway
surface, and prevent overland runoff from reaching the roadway.
8.3.1.2 Design considerations for roadside drainage ditches include ditch shape,
slope, lining considerations, and capacity requirements.
Page 31 of 40
PIP CVE02350
Roadway Design Guide
8.3.2
September 2008
Shape
8.3.2.1 Typically, ditch shape is either V-shaped or trapezoidal.
8.3.2.2 For mild side slopes, the ditch shape tends to approach a parabolic shape,
which is the most hydraulically efficient shape.
8.3.2.3 Because V-shaped ditches are more susceptible to erosion, trapezoidal
ditches may be preferred for certain soil conditions.
8.3.2.4 The size and depth of ditch should be set by volume of water that needs
to be channeled.
8.3.2.5 The roadbed may need to be elevated to permit depth of ditch to be
sufficient for good drainage.
8.3.2.6 Special design features (e.g., drop structures, check dams, etc.) should be
considered to minimize shear stresses exerted on the ditch boundary or
lining, and avoid occurrence of supercritical flow.
8.3.3
Slope
8.3.3.1 The side slopes of a ditch should not exceed the angle of repose of the
soil comprising the ditch line, and should typically be 3:1
(e.g., horizontal:vertical) or less.
8.3.3.2 For typical surface drainage over pavement to a ditch, the road side slope
of the ditch should be 4:1 to minimize erosion. The other side of ditch
can be 4:1 or 3:1 depending on elevation change.
8.3.3.3 If a rigid lining is specified, the use of steeper ditch slopes greater than
2:1 may be more economical.
8.3.4
Lining
8.3.4.1 Linings can be either rigid or flexible. Lined ditches generally allow for
steeper slopes and can provide protection against erosion caused by high
velocities at ditch outlets.
8.3.4.2 Rigid linings include concrete, paved, or other low permeability linings.
Rigid linings may be specified where ditches are designed to carry runoff
from process areas adjacent to roadway.
8.3.4.3 Flexible linings include asphalt, vegetation, riprap, or geotechnical
material.
8.4
Page 32 of 40
Sidewalks and curbs may be specified along a roadway. The change in elevation
from curbs along a roadway edge channels surface water runoff, forming gutters.
8.4.2
8.4.3
Inlets and/or catch basins should be placed along curb and gutters to remove the
surface runoff.
September 2008
PIP CVE02350
Roadway Design Guide
8.4.4
8.5
8.4.5
8.4.6
8.4.7
Headwalls
Headwalls control and direct the transitional flows in and out from a pipeline to an open
ditch or creek. Headwalls may be cast in place or pre-cast units. See drawings
CVE02350-05 to -06 for typical details for headwalls.
8.6
General
8.6.1.1 For designing underground culverts, pipe crushing strength should be
known so the supporting capability of the pipe is not exceeded by the
earth and live loads.
8.6.1.2 Crushing strengths are typically obtained from pipe manufacturers
catalogs, and can also be calculated from formulas derived using specific
tests.
8.6.1.3 ASTM testing standards typically require pipe crushing strengths to
resist expected live and dead loads. However, unusual conditions
(e.g., extraordinary loads or very deep or shallow depths of bury) require
special consideration.
8.6.1.4 Pipe used for culverts is typically classified either rigid or flexible.
8.6.1.5 Rigid pipe (e.g., cast iron, concrete, or clay) either cracks or ruptures if
the combined load (e.g., internal pressure and external load) imposed
becomes greater than the inherent circumferential strength of the pipe.
Page 33 of 40
PIP CVE02350
Roadway Design Guide
September 2008
8.6.1.6 Crushing strengths for various categories and sizes of rigid pipe,
calculated in accordance with ASTM testing methods, are shown in
Table 10.
Table 10 Crushing Strength of Pipe
3-Edge Bearing Test, Pounds per Linear Foot
Pipe Size
(Inches)
Vitrified Clay
Extra Strength
ASTM C-700
Nonreinforced
Concrete
Class 2
ASTM C-14
2,000
C.I. Soil
Pipe
Extra
Heavy
ASTM A-74
6,500
Class III
Class IV
Class V
2,000
2,000
2,000
4,400
2,200
2,000
4,275
10
2,400
2,000
4,275
12
2,600
2,250
4,425
1,000
1,350
2,000
3,000
15
2,900
2,600
5,310
1,250
1,688
2,500
3,750
18
3,300
3,000
1,500
2,025
3,000
4,500
21
3,850
3,300
1,750
2,363
3,500
5,250
24
4,400
3,600
2,000
2,700
4,000
6,000
27
4,700
2,250
3,038
4,500
6,750
30
5,000
2,500
3,375
5,000
7,500
33
5,500
2,750
3,713
5,500
8,250
36
6,000
3,000
4,050
6,000
9,000
8.6.2
Concrete Pipe
8.6.2.1 For reinforced concrete pipe only, laboratory load strength may be
expressed as either of the following:
a. Load per foot of pipe that causes the pipe to develop a 0.01 inch
crack
b. Ultimate load the pipe can withstand
8.6.2.2 The load strength of the pipe, either the 0.01 inch crack or ultimate,
divided by the nominal internal diameter of the pipe in feet, is called the
D load strength.
8.6.2.3 For example, if a 48-inch diameter reinforced concrete pipe has a 3-edge
bearing test load at 0.01-inch crack of 8,000 lb/ft, and an ultimate
strength of 12,000 lb/ft, the 0.01-inch crack strength is 2,000D and the
ultimate strength is 3,000D.
Page 34 of 40
September 2008
PIP CVE02350
Roadway Design Guide
8.6.3
Flexible Pipe
8.6.3.1 Flexible pipe (e.g., steel and plastic) resists deflection using the pipe load
strength combined with the lateral support of the compacted soil at the
side fills.
8.6.3.2 The maximum external load that can be applied to a flexible pipe is the
load that gives a deflection greater than the following:
a. For flexible coating, 5% of nominal pipe diameter
b. For rigid coating, 2% of nominal pipe diameter
8.6.3.3 Internal pressure assists flexible pipe in resisting external loads but
cannot be used in load calculations because the pipe may be empty.
8.7
Pipe Loading
8.7.1
General
8.7.1.1 Formulas and charts for determining loads on an underground pipe have
Types of Bury
8.7.2.1 Types of bury are classified as that in cut (e.g., trench condition) or that
in fill (e.g., embankment condition).
8.7.2.2 Combinations of both trench and embankment conditions can exist.
To simplify and provide conservatism, this guideline is limited to trench
conditions and embankment conditions. Combination conditions are
considered embankment conditions.
8.7.3
Page 35 of 40
PIP CVE02350
Roadway Design Guide
September 2008
10
12
15
18
21
24
27
30
33
36
180
240
290
340
390
450
500
560
610
700
750
820
875
270
370
460
550
630
750
860
950
1,040
1,120
1,200
1,300
1,400
370
520
650
780
920
1,080
1,230
1,400
1,520
1,630
1,750
1,850
2,000
470
660
830
1,000
1,160
1,420
1,610
1,810
2,010
2,200
2,340
2,500
2,630
570
800
1,000
1,200
1,430
1,710
2,000
2,230
2,500
2,700
2,950
3,180
3,350
670
950
1,130
1,420
1,700
2,050
2,400
2,700
3,050
3,300
3,570
3,900
4,100
780
1,080
1,370
1,620
1,960
2,400
2,780
3,200
3,550
3,900
4,200
4,500
4,800
Page 36 of 40
September 2008
PIP CVE02350
Roadway Design Guide
8.7.4
Live Loads
8.7.4.1 Typically live loads do not need to be considered unless the loads are
very large or occur on culverts with very little cover. A few calculations
under various conditions should establish the relative importance of live
loads.
8.7.4.2 Based on depth of cover and size of pipe, trucks or construction
equipment moving over the ground surface above underground piping
can transmit a percentage of the total load to the pipe. If the area above
the piping is paved with flexible pavement, more load can be transmitted
to the pipe; whereas, with rigid pavement (e.g., concrete) the load can
bridge the pipe transmitting more load to the surrounding soil.
8.7.4.3 Table 12 shows the percent of live load that can be transmitted to the
pipe for various depths of cover. For determining transmitted loads,
Table 12 should be used with the following guidelines:
a. For piping under a roadway, depth of cover should be based on
rough grade elevations for the roadway because underground piping
can be subject to truck traffic before any paving is applied.
b. The minimum wheel load for design purposes is 16,000 pounds
which is normal H-20 loading. If greater loads are expected, the
calculations should be based on actual loads. The heaviest wheel
load that would be expected from a large unladen truck crane is
32,000 pounds (1/2 axle load of 64,000 pounds). The wheel load
may be on dual tires but is still considered one wheel. Heavier loads
could be possible during equipment handling or lifting activities and
this point should be reviewed with construction management.
Generally, the pipe is protected with timber mats or omitted entirely
during these operations.
10
12
15
18
21
24
27
30
33
36
9.3
12.8
15
17.3
20
22.6
24.8
26.4
27.2
28
28.6
29
29.4
4.3
5.7
8.3
9.6
11.5
13.2
15
15.6
16.8
17.8
18.7
19.5
2.9
3.6
4.3
5.2
6.4
7.5
8.6
9.3
10.2
11.1
11.8
12.5
1.2
1.7
2.1
2.5
3.1
3.9
4.6
5.3
5.8
6.5
7.2
7.9
8.5
0.7
1.2
1.4
1.7
2.1
2.6
3.1
3.6
3.9
4.4
4.9
5.3
5.8
0.5
0.8
1.1
1.4
1.8
2.1
2.5
2.8
3.1
3.5
3.8
4.2
0.2
0.5
0.7
0.8
1.3
1.6
1.3
2.1
2.3
2.6
2.9
3.2
0.1
0.4
0.5
0.6
0.8
1.2
1.4
1.6
1.8
2.2
2.3
8.7.4.4 For flexible pavement, the live load transferred to below grade varies in
function of the depth as shown in Figure 3. Cranes are designed so that
the live load applied to the soil is 2,000 psf maximum. Live load from
locomotives is transferred in accordance with the Coopers E-80 curve
Page 37 of 40
PIP CVE02350
Roadway Design Guide
September 2008
AASHTO H-20
Cooper's E-80
12,000
10,000
8,000
6,000
4,000
2,000
0
0.0
2.0
4.0
6.0
8.0
10.0
Depth, ft
8.7.4.5 For rigid pavement, the live load transferred to below grade is negligible
at any depth.
8.7.5
Pipe Bedding
8.7.5.1 Pipe bedding is the contact area between a pipe and the foundation on
which the pipe rests. The soil on the sides of and above a pipe is the
backfill.
8.7.5.2 The 3-edge bearing strength for a pipe is multiplied by the load factor or
number determined from the pipe bedding to calculate the field
supporting strength.
8.7.5.3 The field supporting strength of a rigid pipe and, therefore, the load
factor for a particular culvert, depend on the following installation
characteristics:
a. Width of pipe bedding and quality of the contact between the pipe
and bedding as the contact affects the distribution of the vertical
forces
b. Magnitude of lateral pressure acting against the sides of a pipe and
the area of the pipe over which the lateral pressure acts
Page 38 of 40
12.0
September 2008
PIP CVE02350
Roadway Design Guide
8.7.5.4 Cohesion between backfill material and the sides of a trench for pipe
bedding in trenches should be assumed to be negligible because of the
following:
a. Considerable time is required for effective cohesion.
b. Assuming that cohesion is negligible provides the maximum
probable load on the pipe.
8.7.6
Factor of Safety
8.7.6.1 A factor of safety should be applied to the pipe loading designs to
account for unforeseen stresses which can be imposed on an underground
pipe. A factor of safety cannot be computed by laws and equations, but
depends entirely upon engineering judgment and experience.
8.7.6.2 Typically, the factor of safety should range from 1.0 to 1.5 depending on
a variety of conditions or situations.
8.7.6.3 The following factors should be considered when choosing a factor of
safety for underground pipe designs:
a. Culvert (e.g., non-pressure pipe) typically fails gradually. Pipe under
pressure typically fails quickly once a crack develops.
b. Pipe bedding and backfill variable factors
c. Typically, rigid pipes should be designed with a higher factor of
safety than flexible pipes because flexible pipes can deflect more
before failure.
9.
Crossings
9.1
9.2
Railroad Crossings
9.1.1
Railroad facilities within a process plant are typically owned by the plant but
subject to one or more local railroad operating company specifications.
9.1.2
To cross railroad tracks with a new plant road, an acceptable crossing detail
should be developed in coordination with the railroad operating company.
Typical details can range from asphalt infill between rails to proprietary concrete
panels.
9.1.3
Typically, a process plant has a preferred railroad contractor that performs the
plants rail construction and maintenance. Specialty vendors may be consulted
for rail crossing materials and traffic control signage and devices.
Pipeline Crossings
9.2.1
9.2.2
Page 39 of 40
PIP CVE02350
Roadway Design Guide
10.
September 2008
9.2.3
Pipelines crossing ditches should be placed 24 inches minimum below the ditch
flow line.
9.2.4
Pipe, conduit, sewer, or other similar facility should not be placed inside a
drainage pipe.
9.2.5
Typical Details
See drawings CVE02350-01 to -10 for typical details for road sections, guard rails and posts,
culverts, headwalls, roadway clearances, and concrete pavement joints.
Page 40 of 40