MBTA PMM Section 10 Project Close-Out 2014-01-27
MBTA PMM Section 10 Project Close-Out 2014-01-27
MBTA PMM Section 10 Project Close-Out 2014-01-27
Substantial Completion
This term substantial completion, if used on the project, should be defined
in the contract specifications. Generally, it represents the recognition by
the Authority that the project is substantially completed except for certain
minor punch list items which do not hamper the use of the facility by the
MBTA.
Substantial Completion is defined as the scope of work that is required by
the Contract that has been completed except for work having a Contract
price of less than 1 percent of the adjusted total contract price, or
substantially all of the work has been completed and opened to public use
except for minor incomplete or unsatisfactory work items that do not
materially impair the usefulness of the work required by the Contract.
When the Contractor reaches substantial completion, the Contractor will
request a semi-final inspection of the work. The PM will inspect the work
and inform the Contractor:
Section 10
Page 1 of 12
* Attach Certificate of Occupancy and obtain approval of the fire alarm system, if
applicable
Section 10
Page 2 of 12
10.2
Lessons Learned
As-Built Drawings
Section 10
Page 3 of 12
The PM should provide the PDF copy of the as-built drawings to the
MBTA Document Control Manager for archiving.
10.5
The PM should obtain from the Contractor the following data (with the number of
copies of each), in accordance with the Contract Terms:
The PM is responsible for ensuring that these documents are properly distributed
within the MBTA to all end user groups.
10.6
Final Acceptance
Final acceptance of the work generally allows the Owner to issue a Certificate of
Final Acceptance" to the Contractor for the work. This states that the contract is
competed with no outstanding items remaining. This is also the milestone by
which the Contractor will notify its bonding and insurance companies that no
further obligations remain on the contract. This is performed after all Punch List
items have been completed or corrected to meet Contract requirements.
The Certificate of Final Acceptance formally establishes the date of final
completion for the contract and begins the warranty period. A Certificate of
Final Acceptance is also a required attachment to process the Contractors
request for final payment.
10.7
Final Payment
Section 10
Page 4 of 12
Upon completion of the contract work and receipt of the Certificate of Completion
from the Contractor, the PM shall request the Contractor submit a request for
final payment. The Project Manager must assure that all safety critical elements
are completed and verified by the Safety Department.
The following forms must be completed and signed before contract close
out and submitted with final payment.
Procedures (Construction)
The following forms are generated in the Capital Management System (CMS).
PMs may navigate to these forms through the CMS tool bar by clicking:
Payments > Voucher Backup Documents > CMS-PY-014 through 018.
throughout the contract to ensure the contractor is or will meet the DBE goal. If
upon contract completion the contractor has not met the goal then the PM
must provide a justification documenting the reasons why the goal was not
met. A contractor should provide a good faith effort in the justification.
Final Contractor Performance Evaluation Rating Sheet - The Project
Manager must complete a Final Contractor Performance Evaluation Rating
Sheet , which reviews the performance of the Contractor after all contractual
obligations are completed, and submit the evaluation to Contract
Administration.
10.7.2
Upon completion of the contract work and receipt of the Certificate of Completion
from the Contractor, the PM shall request the Consultant submit a request for
final payment. No final payment may be processed until all required
affidavits and permanent certificates of occupancy have been submitted with
the Form 7 or with approval by the Director of Quality Control.
Procedures (Professional Services)
All final payment invoices must be accompanied by a Closeout Report which is
prepared by the Project Manager and approved by the Director of Design &
Construction.
A printout of all Amendments must be attached to the closeout recommendation.
A letter from the consultant must be included stating there are no outstanding
claims.
The Close-out Report includes the following items:
The terms of the contract scope of services and costs were compiled
with and the objectives accomplished.
The contract was carried out in compliance with MBTA and FTA
Section 10
Page 7 of 12
The contract records are complete and organized for easy future
access by the Design and Construction Department and internal and
external auditors.
Section 10
Page 9 of 12
Section 10
Page 10 of 12
Property Address:
Project: Check (x) one or both as applicable: New construction Existing Construction
Project description:
I MA Registration Number: Expiration date: , am a registered design professional,
and hereby certify that I have prepared or directly supervised the preparation of all design plans,
computations and specifications concerning1:
Entire Project
Architectural
Structural
Mechanical
Fire Protection
Electrical
Other:
for the above named project. I certify that I, or my designee, have performed the necessary professional
services and was present at the construction site on a regular and periodic basis to determine that the work
proceeded in accordance with the requirements of 780 CMR and the design documents prepared by me
and approved as part of the building permit and that I or my designee:
1. Have reviewed, for conformance to this code and the design concept, shop drawings, samples and other
submittals by the contractor in accordance with the requirements of the construction documents.
2. Have performed the duties for registered design professionals in 780 CMR Chapter 17, as applicable.
3. Have been present at intervals appropriate to the stage of construction to become generally familiar
with the progress and quality of the work and to determine if the work was performed in a manner
consistent with the construction documents and this code.
Enter in the space to the right a wet or
electronic signature and seal:
Phone number:
Email:
Building Official Use Only
Section 10
Page 11 of 12
Section 10
Page 12 of 12