Linan-Faye Construction Co., Inc. v. Housing Authority of The City of Camden, 49 F.3d 915, 3rd Cir. (1995)
Linan-Faye Construction Co., Inc. v. Housing Authority of The City of Camden, 49 F.3d 915, 3rd Cir. (1995)
Linan-Faye Construction Co., Inc. v. Housing Authority of The City of Camden, 49 F.3d 915, 3rd Cir. (1995)
3d 915
Cary L. Flitter (argued), Lundy, Flitter & Beldecos, Narberth, PA, for
appellant Linan-Faye Const. Co., Inc.
Mark D. Caswell (argued), Freeman, Zeller & Bryant, Cherry Hill, NJ, for
appellee Housing Authority of the City of Camden.
Before: BECKER, COWEN and GARTH, Circuit Judges.OPINION OF
THE COURT
COWEN, Circuit Judge.
The district court entered a temporary restraining order to prevent HACC from
accepting further bids. Subsequently, the court approved a Stipulation of
Settlement and Order of Dismissal with Prejudice, under which the parties
agreed to execute the contract and proceed with the project as originally
planned. Nevertheless, disputes soon broke out again.
Subsequently, HACC attempted first to extract the plumbing segment from the
contract and, when that failed, proposed a complete buy-out of Linan-Faye's
contract. The parties entertained the possibility of a buy-out until July of 1990,
at which time HUD informed HACC that it would not approve a buy-out.
HACC reinstated the previous Notice to Proceed by letter dated July 23, 1990.
10
Linan-Faye objected to the termination and filed the instant action on October
26, 1990, setting forth theories of recovery under New Jersey public contracts
law and 42 U.S.C. Sec. 1983. Linan-Faye served HACC with a complaint in
December of 1990 seeking specific performance and damages. HACC did not
surrender Linan-Faye's performance bond until July of 1991, after the district
court determined that specific performance was not available to Linan-Faye.
11
Upon a renewed motion for summary judgment, the district court held for
HACC, determining that Linan-Faye's damages would be limited to those
compensable under the contract's termination for convenience clause. The
district court left open, however, the possibility of recovery for damages
accruing from HACC's initial failure to identify specifically the termination as
one of convenience.
13
HACC filed its third motion for summary judgment on October 27, 1993. In
that motion, HACC contended that since Linan-Faye never began work under
the contract, it could not recover any damages under the termination for
convenience clause. Linan-Faye responded that it could recover damages for:
(1) preparatory costs such as soliciting subcontractors, pricing, and preconstruction meetings; (2) improper notice of termination; (3) pre-termination
delay by HACC; and (4) HACC's refusal to relinquish Linan-Faye's
performance bond. Determining that federal common law applied in
interpreting this contract, the district court held that Linan-Faye incurred no
compensable damages under the termination for convenience clause. The court,
therefore, entered an order granting summary judgment for HACC. This appeal
followed.
14
Following oral argument before this Court, HACC and Linan-Faye agreed to
participate in non-binding mediation of the controversy before the Honorable
Max Rosenn, Senior Circuit Judge. By memorandum dated November 9, 1994,
Judge Rosenn informed us that efforts to reach a settlement of the controversy
through mediation were unsuccessful.
The district court exercised jurisdiction in this matter by virtue of the diversity
of citizenship of the parties with the requisite amount in controversy pursuant to
28 U.S.C. Sec. 1332 (1988). This Court has jurisdiction pursuant to 28 U.S.C.
Sec. 1291 (1988). Linan-Faye essentially raises six issues on appeal:2 (1)
whether the district court erred in applying federal common law and not the law
of New Jersey to interpret this contract; (2) whether New Jersey law precludes
retroactive application of a termination for convenience clause; (3) whether the
district court was correct in its application of the constructive termination for
convenience doctrine; (4) whether the district court erred by engaging in
impermissible fact finding so as to deny Linan-Faye all compensation; (5)
whether Linan-Faye has an actionable claim for violation of its civil rights; and
(6) whether HACC's position that the termination for convenience clause
denies any recovery is barred by principles of equitable and judicial estoppel.
III. CHOICE OF LAW
17
Linan-Faye contends that the district court erred in applying federal common
law and not the law of New Jersey to resolve this dispute. According to LinanFaye, this action involves a contract dispute between a private contractor and an
autonomous public housing authority created pursuant to New Jersey law.
Where such parties enter federal court based upon diversity of citizenship,
Linan-Faye argues, the federal courts presumptively apply state law. See Erie
R. Co. v. Tompkins, 304 U.S. 64, 78, 58 S.Ct. 817, 822, 82 L.Ed. 1188 (1938).
We agree.
18
19
20
The district court erred in deviating from the generally applicable Erie doctrine.
The Supreme Court, in Boyle v. United Technologies Corp., 487 U.S. 500, 108
S.Ct. 2510, 101 L.Ed.2d 442 (1988), set forth a two-pronged inquiry for
determining whether to apply federal common law in the absence of an express
Congressional grant of such authority. According to the Supreme Court, a court
must first determine whether the action involves " 'uniquely federal interests.' "
Id. at 504, 108 S.Ct. at 2514 (citing Texas Industries Inc. v. Radcliff Materials,
Inc., 451 U.S. 630, 640, 101 S.Ct. 2061, 2067, 68 L.Ed.2d 500 (1981)). Once a
court identifies a uniquely federal interest, the court must then determine
whether a "significant conflict" exists between an identifiable "federal policy or
interest and the [operation] of state law." Id. 487 U.S. at 507, 108 S.Ct. at 2516
(quoting Wallis v. Pan American Petroleum Corp., 384 U.S. 63, 68, 86 S.Ct.
1301, 1304, 16 L.Ed.2d 369 (1966)).
21
Relying on American Pipe & Steel Corp. v. Firestone Tire & Rubber Co., 292
F.2d 640 (9th Cir.1961), and United States v. Taylor, 333 F.2d 633 (5th
Cir.1964), the district court concluded that the government's interest in ensuring
a uniform interpretation of the termination for convenience provisions in this
contract provided the "significant federal interest" necessary to pre-empt state
law. Linan-Faye Construction Co. v. Housing Authority of Camden, 847
F.Supp. 1191, 1197 (D.N.J.1994). These cases, however, do not dictate this
result. While both of these cases applied federal law in interpreting a contract,
the government interest was far more significant in those cases than in the case
at hand. In American Pipe & Steel, the Court of Appeals for the Ninth Circuit
stated, "we agree generally with appellee that the construction of subcontracts,
let under prime contracts connected with the national security, should be
regulated by a uniform federal law." American Pipe & Steel, 292 F.2d at 644.
The instant case involves no matter of national security. Further, the court in
American Pipe & Steel expressly acknowledged that the development of the
law in this area was "still uncertain and unclear." Id. Similarly, in Taylor, the
contract at issue involved the construction of an atomic energy plant, a matter
intricately involved with national security during the 1950's and 1960's. Taylor,
333 F.2d at 635. The Taylor court also explicitly referred to the fact that
American Pipe & Steel dictated application of federal common law in such a
case. Id. at 637. Thus, both of these decisions concerned matters of national
security that are simply not present in this case.3
22
Moreover, the district court erred in finding a conflict between federal and state
law that would endanger any federal interest involved. The district court
correctly recognized the proposition that a lawsuit which involves a federal
interest is a "necessary, not a sufficient, condition for the displacement of state
law." Linan-Faye Construction Co., 847 F.Supp. at 1198 (quoting Boyle 487
U.S. at 507, 108 S.Ct. at 2516). The court, however, failed to identify a
significant conflict. In the only paragraph that attempts to identify a conflict,
the court stated:We find it implausible that the federal government would
require all CIAP contracts in excess of $10,000.00 to contain a termination for
convenience clause, and then leave interpretation of that clause to the vagaries
of state law, particularly where, like New Jersey, there are few or no state law
cases interpreting this type of provision. Rather, we believe that the decision to
include a termination for convenience clause in the "Uniform Requirements"
section of the C.F.R. reflects a federal interest in a consistent interpretation of
that clause.
23
Id.
24
The first sentence of this paragraph merely assumes the answer to the question
the court is wrestling with: whether Congress left interpretation of clauses in
these types of contracts to state law. The second sentence of the above quoted
paragraph simply reidentifies the interest involved, it does not point out a
conflict with state law.
25
The problem with the district court's reasoning is highlighted by its own
analysis of what the outcome would be under state law. The court states, "
[e]ven assuming that New Jersey law were to apply, we have no basis for
believing that New Jersey courts would look elsewhere than to federal common
law for guidance." Id. If New Jersey courts, as is likely, would look to federal
common law to decide this question for which there is little state law precedent
on point, then the court is incorrect in its assertion that a conflict exists. The
outcome would be the same under both federal and state common law. Thus,
the court erred in applying federal common law and not the law of New Jersey
to resolve this dispute and we must reverse with the direction that the district
court resolve all remaining issues in accordance with New Jersey law.
Having decided that it is the law of New Jersey that governs the interpretation
of this contract, we must now decide whether Linan-Faye is correct when it
argues that the general principles of contract damages under New Jersey law
would permit Linan-Faye to recover full expectation damages under this
contract rather than those damages provided for under the contract's
termination for convenience clause. Citing A-S Development, Inc. v. W.R.
Grace Land Corp., 537 F.Supp. 549, 557 (D.N.J.1982), aff'd 707 F.2d 1388 (3d
Cir.1983), and other cases,4 Linan-Faye states that under New Jersey law one
who breaches an agreement must compensate the injured party in order to put
It is undisputed that there are no cases in New Jersey construing the effect of
termination for convenience clauses. It is also undisputed that there are
numerous federal cases dealing specifically with termination for convenience
clauses and, in particular, with the doctrine of constructive termination for
convenience. Therefore, as the district court stated, "courts in New Jersey
would recognize that where the parties have incorporated a particular clause
pursuant to federal regulation, they do so against the backdrop of federal case
law addressing the clause." Linan-Faye Construction Co., 847 F.Supp. at 1198.
Accordingly, we align ourselves with the district court in its determination that
if New Jersey law were to apply, New Jersey courts would look to this rich
body of federal common law concerning the termination for convenience
doctrine, unless to do so would violate some enshrined principle of New Jersey
law. Id. Like the district court, we are unable to discern such a principle.6
Because the New Jersey Supreme Court would likely look to federal common
law as persuasive authority in order to construe this contract's termination for
convenience clause, we must examine the parties' contentions in light of the
relevant federal case law.7 As a preliminary matter, we must determine the
method HACC used to terminate Linan-Faye. HACC argues that it terminated
Linan-Faye by letter of September 25, 1990, and this letter constituted a
termination for convenience. Linan-Faye, on the other hand, argues that this
letter constituted a default termination. Linan-Faye has the better of this
argument.
29
30
Given HACC's original termination of Linan-Faye for default, the question that
we must reach is whether the court should retroactively convert this
termination for default into a termination for convenience. HACC argues, based
on a number of cases from the United States Court of Claims and the Court of
Appeals for the Federal Circuit,9 that the district court did not err in invoking
the constructive termination for convenience doctrine in order to convert this
default termination into a termination for the convenience of the Housing
Authority. Linan-Faye, argues that under federal common law the doctrine of
constructive termination for convenience has no application to this case.
According to Linan-Faye, Federal Acquisition Regulations (FAR's) applicable
to direct procurement contracts provide for a "conversion clause," a clause that
automatically converts a termination for default into a termination for
convenience. 48 C.F.R. Sec. 49.401(b) (1993). Linan-Faye suggests, therefore,
that because no such regulations exist in grant situations10 such as this, there is
an expressed intent that such a conversion not be allowed. We find LinanFaye's argument unpersuasive.
31
32
The idea that the government can, under certain circumstances, terminate a
contract without paying full expectation damages, dates from the winding down
of military procurement following the civil war. Torncello v. United States, 681
F.2d 756, 764, 231 Ct.Cl. 20 (1982). The termination for convenience doctrine
originated "in the reasonable recognition that continuing with wartime contracts
after the war was over clearly was against the public interest." Id. Where the
government terminates a private contractor pursuant to a termination for
convenience clause in a contract, instead of receiving full expectation damages
the contractor's recovery is defined by the termination for convenience clause.
Recovery is limited to " 'costs incurred, profit based on the work done, and the
costs of preparing the termination settlement proposal.' " Maxima Corp. v.
United States, 847 F.2d 1549, 1552 (Fed.Cir.1988) (quoting R. Nash & J.
Cibinic, Federal Procurement Law 1104 (3d ed. 1980)) After World War II,
termination for convenience came to be applied to peacetime non-military
procurement. Id. (citing Torncello, 681 F.2d at 765-66).
33
34party to a contract who is sued for its breach may ordinarily defend on the ground
A
that there existed, at the time, a legal excuse for nonperformance by him, although
he was then ignorant of the fact. He may, likewise, justify an asserted termination,
rescission, or repudiation, of a contract by proving that there was, at the time, an
adequate cause, although it did not become known to him until later.
35
36
The decision of the Court of Claims in John Reiner & Company v. United
States, 325 F.2d 438, 163 Ct.Cl. 381 (1963), cert. denied, 377 U.S. 931, 84
S.Ct. 1332, 12 L.Ed.2d 295 (1964), demonstrates the operation of this doctrine.
In John Reiner, the plaintiff contracted with the government to supply generator
sets to the Army. Id. 325 F.2d at 439. Following delivery of a written contract,
but before performance commenced, the government notified the plaintiff that
the contract was canceled and that the contract would be rebid because of an
impropriety in the original bidding procedure identified by a competitor. Id.
Nevertheless, no such impropriety was found to exist. Id. at 442. The Court of
Claims, therefore, was forced to consider the proper measure of damages to the
contractor. In answering this question, the court determined that while the
government did not rely on the termination for convenience clause in canceling
the contract with the plaintiff, because it could have so relied, the measure of
damages was limited to the damages provided for in that clause. Id. at 443.
According to the court, even though the excuse originally offered was not a
38
39
In this matter, the district court concluded that under the bad faith test it was
41
In the matter at hand, Linan-Faye does not claim that HACC terminated its
contract to obtain the work at a cheaper price. Linan-Faye also does not claim
that HACC terminated the contract in order to obtain work from a lower bidder
who was known to HACC at the time it contracted with Linan-Faye. Indeed,
Linan-Faye points out in its brief that it was the low bidder for the project.
Brief of Linan-Faye at 1. Thus, the divisive facts presented in Torncello are not
present here.
42
Moreover, subsequent cases have limited the scope of Torncello. The Court of
Appeals for the Federal Circuit, for example, has stated that Torncello "stands
for the unremarkable proposition that when the government contracts with a
party knowing full well that it will not honor the contract, it cannot avoid a
breach claim by adverting to the convenience termination clause." Salsbury
Industries v. United States, 905 F.2d 1518, 1521 (Fed.Cir.1990), cert. denied,
498 U.S. 1024, 111 S.Ct. 671, 112 L.Ed.2d 664 (1991); see also T.I.
Construction Co. v. Kiewit Eastern Co., No. 91-2638, 1992 WL 382306, at * 9
(E.D.Pa. Dec. 10, 1992) (citing language in Torncello indicating that its holding
was limited to the facts presented); Modern Systems Technology Corp. v.
United States, 24 Cl.Ct. 699, 704 (1992) (applying bad faith test and reading
Torncello to stand only for the above stated proposition), aff'd, 980 F.2d 745
(Fed.Cir.1992). In addition, in a subsequent case, the United States Claims
Court stated that "Torncello did not change the traditional understanding" that
the "Government could invoke the clause so long as it did not act in bad faith or
clearly abuse its discretion." SMS Data Products, 19 Cl.Ct. at 619-20. In light of
these developments, and considering the division among the court in Torncello,
we decline to read that case as significantly limiting the power of the
government in terminating for convenience.13
43
As the district court recognized, the post award deterioration of the relationship
between HACC and Linan-Faye which included conflict over the specifications
would likely constitute sufficiently changed circumstances to justify application
of the doctrine of constructive termination for convenience even under the
reasoning in Torncello. See Embrey v. United States, 17 Cl.Ct. 617, 62425
(1989) (deterioration of business relations considered sufficiently changed
circumstances to allow government to terminate for convenience); see also
SMS Data Products, 19 Cl.Ct. at 621 (genuine concern that contractor could not
meet the contract's mandatory requirements constituted changed
circumstances). Without establishing a litmus test as to what constitutes
changed circumstances, which is unnecessary in view of subsequent limits on
Torncello, we hold that New Jersey courts, looking to federal law as persuasive
authority, would permit HACC to invoke the constructive termination for
convenience doctrine in this instance.14 Accordingly, damages will be limited
by the termination for convenience clause of the contract.15
46
47
Three of the issues that Linan-Faye raises are genuine issues of material fact in
dispute. The other issues concern facts that are either not material, or are not in
dispute. We will reverse the decision of the district court granting summary
judgment on those issues where there is a genuine issue of material fact in
dispute.
Linan-Faye argues that the trial court improperly selected isolated phrases from
correspondence between the parties in its determination that the phrase "work
performed" in paragraph 17 of the contract16 refers only to "physical
construction" and not to preparatory work. The district court conceded that the
contract documents, which include the contract's General Conditions and its
Supplement to the Standard Form Agreement, failed to define the term "work."
Linan-Faye Construction Co., 847 F.Supp. at 1206. Based on an analysis of the
word "work" as used in several paragraphs of the contract, the district court
concluded that "work" could not include "preparatory work" until after LinanFaye began physical construction on the project. Id. at 1207. We conclude that
the district court erred in determining this disputed issue of fact.
50
Paragraph 8(a) of the General Conditions of this contract is the paragraph from
which the district court draws the most support for its conclusion that "work"
under the termination for convenience clause does not include "preparatory
work." The court's reading of this paragraph, however, is too strained to support
a grant of summary judgment. Paragraph 8(a) of the General Conditions states:
51
Progress
payments will be made at approximately thirty (30) day intervals; and in
preparing estimates, acceptable work in place, material delivered to and properly
stored on the site, and preparatory work done will be taken into consideration. If the
contract covers more than one project, a separate estimate shall be furnished for
each.
52
App.Vol. II at 42. From this paragraph, the district court deduced that expenses
for preparatory work were recoverable only if the contractor begins the
physical construction required under the contract. Linan-Faye Construction Co.,
847 F.Supp. at 1207. This conclusion is unjustified.
53
54
The district court's survey of numerous other paragraphs containing the word
"work" also produces inconclusive results. According to the court, paragraph 2
which requires the contractor to "furnish all necessary labor, materials, tools,
equipment, water, light, heat, power, transportation, and supervision necessary
for performance of the work," and paragraph 22 which allows the contractor to
request from the architect drawings "which will [be required] in the planning
and production of the work " somehow indicate that "work performed" under
paragraph 17 does not include preparatory work. Id. at 1206 (emphasis added).
These provisions, on their face, do not appear to support any such conclusion.
In addition, the district court determined that paragraphs 26, 29 and 35, which
refer to the contractor's obligation to protect "work completed to date" and to
the warranty as to "work done," support the conclusion that work performed
under the termination for convenience clause does not include preparatory
work. Once again, if anything, these provisions merely beg the question of how
to define "work" under paragraph 17 of the contract. Finally, the court refers to
paragraphs 7 and 31 that speak to obligations of the contractor before and
shortly after "commencing work" under the contract. Unfortunately, these
paragraphs also do not illuminate whether the parties considered preparatory
work to constitute compensable work for purposes of the termination for
convenience clause.17
55
Related to the disputed issue of the definition of "work performed" under the
contract is the issue of whether Linan-Faye produced any evidence of pretermination expenses compensable as "work performed." The district court
determined that Linan-Faye "had presented no evidence of expenses that would
merit an equitable adjustment to the contract." Id. at 1208 n. 22. Linan-Faye
argues that the certification which it submitted in opposition to HACC's third
motion for summary judgment provides the requisite evidence. Linan-Faye is
correct.
57
The district court, at this early stage of the litigation, improperly concluded that
there was "no evidence" of expenses compensable under the termination for
convenience clause. Linan-Faye described 15 types of expenses that LinanFaye incurred preparing for work on the HACC contract. Certification of
Norman Faye (October 21, 1993); App. at 231-33. While many of these
"expenses" may not be compensable, some of the stated expenses, such as time
spent "with municipal building, plumbing and electrical inspectors regarding
job phasing, contract details, code requirements, and problem solving," may be
compensable if the parties so intended under the termination for convenience
clause of the contract. Cf. ITI Defense Communications Division, Nos. 11858,
13439, 1970 WL 1124, 1970 ASBCA Lexis 29, at * 56 (July 29, 1970) (cost of
work done by appellant in preparing and submitting configurations that were
never used still properly compensable under the termination for convenience
clause); Navgas, Inc., No. 9240, 1964 WL 475, 1964 ASBCA Lexis 1139, at *
29 (November 18, 1964) (costs of investigating work to be done, and
determining the best way to perform the contract, if awarded, are properly
compensable under termination for convenience clause). Although, on the
whole, the evidence produced by Linan-Faye in this certification appears
meager, by granting summary judgment for HACC the district court
improvidently prevented the plaintiff from developing the record more fully.
There was not a complete lack of evidence. Accordingly, we must reverse the
grant of summary judgment on this issue and remand for trial.
58
breaches of contract by HACC. As the district court correctly held, cases that
have addressed the issue of pre-termination breaches have concluded that
claims for such damages are subsumed in the termination for convenience
clause. Linan-Faye Construction Co., 847 F.Supp. at 1203, 1204 (citing Nolan
Brothers, Inc. v. United States, 405 F.2d 1250, 186 Ct.Cl. 602 (1969)); Descon
System Ltd. v. United States, 6 Cl.Ct. 410 (1984)). Pre-termination expenses
that accrued as the result of any alleged pre-termination breaches by HACC are
not compensable. On remand, the triable issue is limited to a determination of
the pre-termination expenses which Linan-Faye incurred that the parties
intended to be compensable as "work performed" under the termination for
convenience clause of the contract.
C. Why HACC Retained Linan-Faye's Performance Bond
59
60
Linan-Faye next contends that the trial court improperly resolved a factual
dispute as to why HACC retained Linan-Faye's performance bonds after
terminating Linan-Faye. According to Linan-Faye, it is entitled to damages
arising from HACC's failure to return this performance bond. Linan-Faye
alleges that by retaining its bond, HACC prevented it from accepting other
construction contracts and used the bond as an inducement to force Linan-Faye
to accept an unreasonable resolution of this dispute. HACC argues that it
retained Linan-Faye's performance bond because Linan-Faye instituted a suit
seeking specific performance and if Linan-Faye were successful, HACC would
need Linan-Faye's bond.
61
This issue is not resolved solely by reference to the termination for convenience
clause because the events that give rise to this claim occurred after
termination.18 Recognizing this, the district court decided the issue by
concluding that keeping the bonds during the pendency of the litigation was the
"logical response" to the plaintiff's lawsuit. Linan-Faye Construction Co., 847
F.Supp. at 1205.
62
63
The district court attempts to justify its decision to accept HACC's argument by
referring to the September 25, 1990 termination letter sent by Gregory Kern,
Moreover, even taking HACC's view of the timing of the relevant events, there
was an unjustified gap of over one month between the time HACC terminated
Linan-Faye and the time Linan-Faye served its complaint seeking specific
performance. According to HACC, after it issued its September 25, 1990 letter
of termination, Linan-Faye sought reversal of HACC's decision to terminate.
HACC states that it sent a letter to Linan-Faye on October 23, 1990 confirming
its decision to terminate. Linan-Faye did not serve its complaint for specific
performance until early in December of 1990, however, and the bond had not
yet been returned. This unexcused delay strengthens Linan-Faye's argument
that HACC did not decide to hold onto the performance bond as the result of
the specific performance suit. In light of these facts, we will reverse the district
court's grant of summary judgment for HACC and remand for trial on this
disputed issue.19
Linan-Faye asserts that the district court improperly found it "refused" to begin
work. According to Linan-Faye, it did not refuse to begin work, but merely
wanted to agree on any changes that HACC desired before it began
construction. Linan-Faye contends that there is no basis in the record for the
district court's finding that it flatly refused to begin work.
67
We find that the question of whether Linan-Faye flatly refused to begin work is
immaterial to this case. Whether Linan-Faye actually "refused" to begin work
would be relevant if it was necessary to decide if Linan-Faye defaulted on its
obligations. The district court, however, based its holding on the doctrine of
constructive termination for convenience. Linan-Faye Construction Co., 847
F.Supp. at 1203. The constructive termination for convenience doctrine makes
the original reason for termination relevant only to the extent that it evidences
the government's bad faith or a change in circumstances from the time of
contracting.20 The issue of whether there was an actual default by Linan-Faye
in refusing to begin work is immaterial. In this case the default termination is
converted into a termination for convenience of the government by operation of
law. Since we agree with the district court that it was appropriate to apply the
constructive termination for convenience doctrine, we hold that this issue is
immaterial.
E. Whether Linan-Faye Misunderstood the Specifications
68
69
70
For the purposes of deciding this case, the district court did not assume that
HACC originally terminated for convenience. While there is a dispute as to
whether the original letter of termination constituted a default termination or a
termination for convenience, HACC prevails under the district court's reasoning
without having to prove that it obtained HUD approval of a termination for
convenience. The court proceeded on a constructive termination for
convenience theory. Linan-Faye does not dispute that HUD had approved
HACC's right to terminate generally. Thus, concerning the original termination,
HACC fulfilled its obligations by informing HUD, and obtaining from HUD a
general approval for the termination of the contract. Because HACC received
general HUD approval to terminate, there is no bar to this court's using the
constructive termination for convenience doctrine to convert this into a
termination for convenience by operation of law. Further, and most
importantly, there is simply no dispute as to the material facts of what approval
HACC obtained. Indeed, both parties concede that HACC obtained HUD
approval to terminate generally, but did not obtain specific HUD approval of a
termination for convenience. Therefore, this cannot be a disputed factual issue
as Linan-Faye erroneously contends.
74
Linan-Faye next asserts that the district court erred in granting summary
judgment against it on its claim under 42 U.S.C. Sec. 1983. Linan-Faye argues
it has a protectible property interest in its contract with HACC that is entitled to
Fourteenth and Fifth Amendment protection. Further, Linan-Faye contends that
HACC's retention of its performance bond implicates a liberty interest entitled
to constitutional protection. In granting summary judgment, the district court
held that whatever property interest Linan-Faye may have had, it does not rise
to a sufficient level of certainty or dependency to merit constitutional
protection. Linan-Faye Construction Co. v. Housing Authority of Camden, 797
F.Supp. 376, 380 (D.N.J.1992).
76
We agree with the district court's resolution of this matter. This Court recently
As we explained in Unger, relevant Supreme Court cases and cases from other
courts of appeals instruct that two general types of contract rights are
recognized as property protected under the Fourteenth Amendment: (1) where
"the contract confers a protected status, such as those 'characterized by a quality
of either extreme dependence in the case of welfare benefits, or permanence in
the case of tenure, or sometimes both, as frequently occurs in the case of social
security benefits' "; or (2) where "the contract itself includes a provision that the
state entity can terminate the contract only for cause." Id. 928 F.2d at 1399
(citing S & D Maintenance Co. v. Goldin, 844 F.2d 962, 966-67 (2d Cir.1988)).
In Unger, a physician licensed to practice medicine in Pennsylvania was
admitted into Temple University Hospital's dermatology residency program
through the National Resident Matching Program. Id., 928 F.2d at 1393.
Shortly before Unger was to begin the program, she received a letter stating
that the University had decided to discontinue the program. Id. Unger filed suit
under 42 U.S.C. Sec. 1983. Id.
78
Declaring that the contract in Unger did not fall into either of the two protected
categories, we dismissed Unger's Sec. 1983 claim. Id. at 1402. We relied in part
on the reasoning of our previous decision in Reich v. Beharry, 883 F.2d 239 (3d
Cir.1989), where we stated:
79
Many
... courts have observed that if every breach of contract by someone acting
under color of state law constituted a deprivation of property for procedural due
process purposes, the federal courts would be called upon to pass judgment on the
procedural fairness of the processing of a myriad of contract claims against public
entities. We agree that such a wholesale federalization of state public contract law
seems far afield from the great purposes of the due process clause.
80
81
Linan-Faye's contract with HACC does not fall into either of the two categories
we delineated in Unger. The contract does not confer a protected status on the
plaintiff and the state entity could terminate the contract for reasons other than
84
86
IX. CONCLUSION
87
In sum, we find that the district court erred in its decision to apply federal
common law and not the law of New Jersey to resolve this dispute. Applying
New Jersey law, we will reverse the district court's grant of summary judgment
and remand for trial on the issues of material fact that are in dispute. The three
issues that remain in dispute in this case are the definition of "work performed"
under paragraph 17 of the contract, whether and to what extent Linan-Faye
incurred preparatory expenses prior to termination that are compensable as
"work performed" under paragraph 17, and HACC's possible liability for
damages resulting from its withholding of Linan-Faye's performance bond after
termination. Finally, we will affirm the district court's grant of summary
judgment in favor of HACC on Linan-Faye's Sec. 1983 claim.
88
89
I join in Parts I, II, and III of the majority opinion. However, I dissent from Part
IV because I do not agree that New Jersey would apply to this garden variety
construction dispute between a builder and a local governmental agency
precepts drawn from a potpourri of federal cases which amount at best to a
hodgepodge, and at worst to a regime so inhospitable and unfair to small
contractors who deal with government agencies as to be inconsistent with New
Jersey jurisprudence. Rather, I believe that New Jersey would apply its own
law, which would not recognize the doctrine of "constructive termination for
convenience" but rather would apply the normal rule of contract breach which,
on this record, would unquestionably render HACC liable. Moreover, even if
the New Jersey Supreme Court were to assimilate federal law, I do not think
that it would read that law in the matter predicted by the majority. The precepts
that the majority applies are gleaned from cases that have been excoriated in
critical commentary because they are in considerable measure poorly reasoned.
90
I also find myself unable to join in Part VII, dealing with Linan-Faye's 42
U.S.C. Sec. 1983 claims. I cannot agree with the majority that HACC's
arguably improper retention of Linan-Faye's performance bond, which the
company requires in order to engage in any business, did not impair LinanFaye's liberty interest. I do, however, join the majority with respect to its
rejection of Linan-Faye's property interest claim.1
93
The majority's prediction also ignores the facts that should govern the analysis
It is undisputed that the parties had a binding $4,264,000 contract for the
rehabilitation of 244 housing units. Linan-Faye, with declarations cognizable in
summary judgment proceedings: (1) represents itself to be an experienced,
highly regarded contractor that was ready, willing, and able to perform the job
in a timely fashion; (2) states that through incompetence, poor planning, or
other contractors' delay, the HACC failed or refused to give Linan-Faye even a
Notice to Proceed for a full year; and (3) submits that after finally giving that
Notice, HACC then proceeded, without justification, to delay Linan-Faye for
almost another year. Linan-Faye also represents that HACC never supplied
Linan-Faye with a list of which vacant units to work on; that turmoil reigned at
HACC as the Executive Director was replaced by a new Acting Executive
Director, Gregory Kern, in July 1990; and that Kern decided to "clean house"
by, inter alia, summarily terminating Linan-Faye's contract.
96
Under general common law contract principles, applicable in New Jersey and
elsewhere, one who breaches a contract must compensate the injured non-
The New Jersey courts have long maintained a liberal rule that non-breaching
parties are entitled to damages. Cf. In re Merritt Logan, Inc., 901 F.2d 349, 357
(3d Cir.1990) (interpreting New Jersey contract damages law); Sandler v.
Lawn-A-Mat Chem. & Equip. Corp., 141 N.J.Super. 437, 358 A.2d 805, 814
(App.Div.), cert. denied, 71 N.J. 503, 366 A.2d 658 (1976) (non-breaching
party "presumptively" entitled to damages, with doubts resolved against the
breaching party). New Jersey courts have also narrowly construed clauses that
tend to restrict a party's right to recover its full common law damages. See
American Sanitary Sales Co. v. State, 178 N.J.Super. 429, 429 A.2d 403, 407
(App.Div.), cert. denied, 87 N.J. 420, 434 A.2d 1094 (1981) (narrowly
interpreting a "no damage for delay" clause in a New Jersey state contract).
100 The reluctance of the New Jersey Courts to give expansive effect to exculpatory
clauses extends to cases involving its own government agencies. See, e.g.,
Buckley & Co., Inc. v. State, 140 N.J.Super. 289, 356 A.2d 56, 62 (Law
Div.1975); Ace Stone, Inc. v. Township of Wayne, 47 N.J. 431, 221 A.2d 515,
518-19 (1966); American Sanitary Sales Co., 178 N.J.Super. 429, 429 A.2d at
407; see also Department of Transp. v. Arapaho Constr., Inc., 257 Ga. 269, 357
S.E.2d 593, 594-95 (1987) (relying in part on Ace Stone). Moreover, under
New Jersey law there is a presumption against finding a contractual intent to
alter common law rights and remedies. See, e.g., Gibraltar Factors Corp. v.
Slapo, 41 N.J.Super. 381, 125 A.2d 309, 310 (Law Div.1956) (parties presumed
to contract with reference to existing law), aff'd, 23 N.J. 459, 129 A.2d 567
(1957), appeal dismissed, 355 U.S. 13, 78 S.Ct. 44, 2 L.Ed.2d 20 (1957); see
also Rescigno v. Picinich, 151 N.J.Super. 587, 377 A.2d 733, 739 (Law
Div.1977) (applying a presumption against a statutory intent to alter common
law rights); Blackman v. Iles, 4 N.J. 82, 71 A.2d 633, 636 (1950) (same).
Indeed, New Jersey courts commonly award contractors common law contract
damages against the State, including damages for delay. See, e.g., American
Sanitary Sales Co., 178 N.J.Super. 429, 429 A.2d at 407; Buckley & Co., 140
N.J.Super. 289, 356 A.2d at 65 (see also cases cited therein).
C. New Jersey and the Federal Law Alternative
101
102 This is not the first case in which a court applying New Jersey law has had to
adjudicate a contract dispute with some federal connection. In Edward J.
Dobson, Jr., Inc. v. Rutgers, 157 N.J.Super. 357, 384 A.2d 1121 (Law
Div.1978), aff'd sub nom. Broadway Maintenance Corp. v. Rutgers, 180
N.J.Super. 350, 434 A.2d 1125 (App.Div.1981), aff'd, 90 N.J. 253, 447 A.2d
906 (1982), plaintiff-contractors sought to avoid the impact of a "no-damage
for delay" clause by asserting their claim for delay as an "equitable
adjustment." The court traced the history of the "equitable adjustment"
provisions in federal construction contracts and federal regulations. But the
court refused to import this wholly federal concept into the New Jersey law of
public construction contracts. Finding that the term "equitable adjustment" had
become a term of art in federal contracts, the court held:
103 policy factors that have lead [sic] to the development of this concept in federal
The
contracts, such as a need to expand or abandon a particular arms program with
consequent economic impact on contractors and subcontractors, do not warrant state
courts adopting it wholesale by judicial fiat when traditional remedies for breach of
contract are available. Id., 157 N.J.Super. 357, 384 A.2d at 1153 n. 10.
104 This holding was affirmed by both the intermediate appellate court and
Supreme Court of New Jersey and strongly suggests that New Jersey courts
would not import the federal concept of constructive termination for
convenience into its public construction contracts jurisprudence.
105 As the majority correctly points out, because there is no reported New Jersey
precedent interpreting a "termination for convenience" clause, it is the function
of this court to predict how the New Jersey Supreme Court would rule if
confronted with this issue. In my view, there is no reason to believe that that
court, if called upon to resolve the question, would jettison a century of settled
contract law supporting liberal contract remedies and narrowly construing
similar exculpatory provisions in order to adopt a harsh--and harshly criticized,
see infra--federal interpretation of the clause at issue here. In this case, the
retroactive application of this dramatic change in the law imposed by the
majority to the factual scenario described above not only exacerbates the
harshness of the result but also increases my confidence that the New Jersey
Supreme Court would never have adopted this interpretation.
D. The Termination of Convenience Provision and Its Harsh
106
Construction by the Majority
107 The termination for convenience clause has, as the majority explains, a long
lineage, dating from the Civil War era. During that era federal government
contracting was attended by much impropriety and scandal. See generally
CARL SANDBURG, ABRAHAM LINCOLN, THE WAR YEARS (1948).
The modern (post-1970) incarnation of the clause is ensconced in the Code of
Federal Regulations:
108
If
the contractor can establish, or if it is otherwise determined that the contractor
was not in default or that the failure to perform is excusable; i.e., arose out of causes
beyond the control and without the fault or negligence of the contractor, the
[prescribed default clauses] provide that a termination for default will be considered
to have been a termination for the convenience of the Government....
109 Federal Acquisition Regulations ("FAR's"), 48 C.F.R. Sec. 49.401(b) (1993).
The FAR's apply to direct United States government procurement (including
HUD procurement). They do not apply to grants of federal funds to local public
housing authorities. The district court acknowledged this undisputed point.
(Dist.Ct.Op. at 18 n. 7)
110 Moreover, regulations that govern grants to local housing agencies contain their
own specific scheme and procedures for federally funded contracts made by
state and local housing authorities that are separate and distinct from the FAR's.
These "CIAP" requirements mandate a variety of terms and provisions that
must be set forth in such contracts, including a termination for convenience
clause. See 24 C.F.R. Sec. 85.36(i)(2). In contrast to the FAR's, however, the
Administrative Requirements for CIAP Grants do not include any counterpart
to the automatic conversion language of 48 C.F.R. Sec. 49.401(b), or the other
specific termination provisions found in HUD's own FAR's. This is consistent
with the mandate of the CIAP enabling statute, which is designed to allow the
housing authority grantees maximum discretion and individualized judgment.
42 U.S.C.S. Sec. 1437l(e)(1)(E), (e)(4)(D) (1994).
111 The absence of an express conversion clause in the Administrative
Requirements for Grants is significant because, under the venerable maxim of
statutory construction, expressio unius est exclusio alterius, the inclusion of one
is the exclusion of another. As I see it, the exclusion of an automatic conversion
provision in the Requirements for Public Housing Authority Contracts (when
specifically included in HUD's own FAR's) expresses an intent to exclude such
a provision, unless local PHA administrators choose to include it. Cf. Marshall
v. Western Union Tel. Co., 621 F.2d 1246, 1251 (3d Cir.1980) (refusing to
apply a Department of Labor standard in one subsection of a regulation where it
had been excluded when it was included elsewhere); SUTHERLAND
STATUTORY CONSTRUCTION Sec. 31.06 (4th ed.). Moreover, without the
conversion clause, HACC's initial failure to allege that it was terminating the
contract with Linan-Faye for convenience prevents HACC from subsequently
embracing that argument.
112 Before contracts with the federal government included automatic conversion
clauses, courts did not permit government agencies to use the termination for
convenience clauses to escape from a breach. In Klein v. United States, 285
F.2d 778, 152 Ct.Cl. 8 (1961), for example, the Court of Claims rejected the
government's argument that, because it had a contractual right to terminate for
convenience, its illegal breach of contract should be disregarded. Id. at 784.
Accord Goldwasser v. United States, 325 F.2d 722, 725, 163 Ct.Cl. 450 (1963);
Dynalectron Corp. v. United States, 518 F.2d 594, 604, 207 Ct.Cl. 349 (1975);
Torncello v. United States, 681 F.2d 756, 771-72, 231 Ct.Cl. 20 (1982);
Rogerson Aircraft Corp. v. Fairchild Indus. Inc., 632 F.Supp. 1494, 1499
(C.D.Cal.1986) (changed circumstances required).
113 The problems confronted by government contracting officers operating under
the Klein rule resulted in the adoption of the automatic conversion clause by
regulation, 48 C.F.R. Sec. 49.401(b). The clause now appears in most direct
federal government procurement contracts. However, as the Rogerson court
noted in footnote 5 of its opinion, where the "automatic conversion clause" is
not made part of the contract, either expressly or by regulation, the Klein rule
remains fully applicable and bars the implication of such clause. Rogerson, 632
F.Supp. at 1500 n. 5. Although the contract in Rogerson appears more specific
than the instant contract in its requirement that the agency elect its basis for
termination (i.e., default or convenience), the Rogerson decision remains
important and persuasive. Without a conversion clause, HACC cannot invoke
the termination for convenience provision to cure its improper default
termination. And a wrongful termination for default constitutes a breach of the
contract entitling the wrongly terminated subcontractor to state law damages for
the breach, including lost profits. Id. at 1500-01; Clay Bernard Sys. Int'l, Ltd. v.
United States, 22 Cl.Ct. 804, 810-11 (1991) (holding that absent a "conversion
clause" a wrongful termination for default is a breach, entitling contractor to
recovery under federal procurement law).
114 But even if HACC had initially invoked its termination for convenience clause,
thus avoiding the issue of the absence of a conversion clause, HACC could not
avoid liability in this case. The majority acknowledges that the case law
construing the termination for convenience clause has retrenched from its high
water mark. While the majority's discussion does not clearly depict the current
state of the law, the leading cases appear to hold that government agencies can
only invoke the clause where there has been some change in the circumstances
of the parties. See Torncello, 681 F.2d at 772. The majority holds that a
deterioration in business relations, demonstrated in not insignificant part by a
dispute over specifications, constitutes such a change in circumstances. In my
view, such a rule would largely eviscerate the limitation. As lawyers who have
dealt with construction disputes know, these contracts almost always generate
some dispute over specifications, and any construction dispute rancorous
enough to spawn litigation will almost certainly have led to the requisite
deterioration in business relations. The facts of this case illustrate how circular
a deterioration-of-business-relations test can be, for HACC did not even attempt
to invoke the clause until litigation began.
115 The majority constructs a regime under which a dispute arising out of a garden
variety contract between a builder and a local housing authority, which is not a
federal government contract but only a local agency contract to which certain
federal regulations apply, has been severed from its common law roots. The
majority's application of selected federal cases renders these local agency
contracts virtually illusory by giving an arguably defaulting local agency the
right to avoid its own breach, and sharply limit its liability simply by incanting
the termination for convenience clause two years after the fact. In my view, it is
inconceivable that the New Jersey Supreme Court, which has so consistently
supported liberal awards of contract damages, would countenance that result,
especially in the fact scenario at bar.
116 This conclusion is strongly buttressed by the scathing criticism that has been
levied at Torncello and the cognate jurisprudence. See, e.g., Stephen N. Young,
Note, Limiting the Government's Ability To Terminate for Convenience
Following Tornecello, 52 GEO.WASH.L.REV. 892 (1984) (suggesting that the
Torncello decision provides a reason to eliminate the government's ability to
terminate for convenience entirely).
117 Because I do not believe that the New Jersey Supreme Court would adopt the
federal interpretation but would instead continue to give exculpatory clauses
such as the termination for convenience clause only narrow--if any--effect, I
dissent.2
II. THE Sec. 1983 CLAIM
118 I also dissent from the majority's affirmance of the summary judgment granted
on Linan-Faye's Sec. 1983 claim. While I agree that Linan-Faye's interest in the
contract did not rise to a property interest protected by the Constitution, I cannot
agree that HACC's unjustified retention of Linan-Faye's performance bond did
not deprive Linan-Faye of a protected liberty interest.
Still another distinction exists between the instant case and the cases the district
court relied upon in applying federal common law to interpret this contract.
American Pipe & Steel and Taylor involved direct United States government
procurement contracts, or a subcontract with a United States government prime
contractor. American Pipe & Steel, 292 F.2d at 641; Taylor, 333 F.2d at 635.
Neither of these situations involved, as is the case here, the outright grant of
funds to a public agency. The closer nexus to the United States government in
American Pipe & Steel and Taylor heightens the federal government's interest.
The weaker link in this case diminishes the significance of the government
interest. Thus, the district court was incorrect in finding a government interest
significant enough to warrant deviating from Erie and applying federal common
law
Linan-Faye also cites Donovan v. Bachstadt, 91 N.J. 434, 453 A.2d 160 (1982),
for the proposition stated above. Further, Linan-Faye cites In Re Merritt Logan,
Inc., 901 F.2d 349, 357-58 (3d Cir.1990) and Sandler v. Lawn-A-Mat Chemical
& Equipment Corp., 141 N.J.Super. 437, 454, 358 A.2d 805 (A.D.),
certification denied, 71 N.J. 503, 366 A.2d 658 (1976), for the proposition that
the courts of New Jersey have long maintained a liberal rule of damages to a
non-breaching party
Linan-Faye argues that decisions of the New Jersey Supreme Court such as
W.V. Pangborne & Co. v. New Jersey Dept. of Transportation, 116 N.J. 543,
562 A.2d 222 (1989), where the court has found against governmental entities,
are inconsistent with the broad discretion federal courts have conferred on the
government in cases concerning termination for convenience clauses.
Pangborne, however, involved a failure of a governmental entity to deal in good
faith. Id. at 562, 562 A.2d at 231 ("DOT's failure ... to deal expressly and
clearly with this material term constitutes a breach of an implied duty of good
faith and fair dealing and the supervening obligation of the government to deal
scrupulously with the public."). Federal common law also looks disfavorably
on the government in cases of governmental bad faith. See infra Part V.
Therefore, Linan-Faye's argument is unpersuasive
We recognize that the district court also applied federal common law to resolve
this dispute. Linan-Faye Construction Co. 847 F.Supp. at 1198. Nevertheless,
there is a difference between looking to federal common law as persuasive
authority and being bound by federal law. The district court opted for the latter
approach and determined that construction of the termination for convenience
clause was purely a matter of federal common law. In light of our previous
holding in Coastal General, 27 F.3d at 917, we opt for the former approach
8
HACC argues that the last paragraph of this letter which states that HACC has
"instructed the Modernization Office to assist [Linan-Faye] as needed in
obtaining release of [Linan-Faye's Bond]," App. at 115, is inconsistent with a
default termination because if HACC had terminated for a default it was
entitled to hold onto the bond. Just because HACC had the right to hold onto
the bond under the contract, however, does not mean that it intended to exercise
this right at the time of the letter. HACC may not have felt that the defaults it
cited, such as a failure to begin work, were compensable via the bond, or it may
have decided that it did not wish to encourage litigation over the bond issue. In
any event, this paragraph provides insufficient support for HACC's argument
that this letter constituted a termination for convenience
10
11
12
Notably, the disagreement among the judges in that case was on the precise
issue of whether it was appropriate to create a stricter test for convenience
terminations by the government. Id. at 773-74 (Friedman, C.J., Davis, J., and
Nichols, J. concurring) While all the judges agreed on the result in that case,
the court could not muster a majority to embrace the new "changed
circumstances" test
13
Linan-Faye also cites a law review note written shortly after the Torncello
decision in support of its claims. Stephen N. Young, Note, Limiting the
Government's Ability to Terminate For Its Convenience Following Tornecello
[sic], 52 Geo.Wash.L.Rev. 892 (1984). In that note, the author suggests that
Torncello provides a reason to eliminate the government's right to
constructively terminate for convenience. Id. at 911. As this author was writing
without the benefit of recent decisions, all that can be said of his
recommendation is that future courts declined to take the hint
14
The dissent states that the majority "holds that a deterioration in business
relations, demonstrated in not insignificant part by a dispute over specifications,
constitutes such a change in circumstances." See infra at 937 (emphasis added).
The dissent is incorrect insofar as it reads this to be the holding of our decision.
As we have already explained, Torncello, and its changed circumstances
approach, has been sharply limited by more recent cases. See discussion supra
this Part. We have therefore declined to endorse wholeheartedly the changed
circumstances approach. Accordingly, an accurate statement of our position is
that (1) Linan-Faye has not demonstrated actual bad faith on the part of HACC
and (2) this case does not present the divisive facts presented in Torncello that
warranted finding against the government
15
17
The district court also refers, in a footnote, to letters exchanged between the
parties that purportedly explain the understanding of the parties concerning the
definition of "work performed." The fact that the court goes beyond the contract
and looks to these letters to reinforce its conclusion demonstrates the
impropriety of granting summary judgment and the need to make such
decisions on a more fully developed record
18
19
We recognize that Linan-Faye's complaint in this matter does not set forth a
theory of recovery for damages due to improper retention of the performance
bond following termination. Indeed, the complaint could not set forth such a
theory because the events giving rise to this aspect of Linan-Faye's claim (i.e.,
HACC's continued refusal to relinquish the bond during the pendency of the
specific performance action) did not occur until after the complaint was filed.
Nevertheless, the district court made findings on this issue. Linan-Faye, 847
F.Supp. at 1205. Further, both parties briefed and argued the issue before this
Court and HACC did not argue that the issue was not properly before the
district court. Accordingly, we find it appropriate to set forth the applicable
theory of recovery on remand. On remand, the theory upon which damages
would be predicated is the common law action of detinue (or its modern
counterpart). According to the New Jersey Supreme Court, "[t]he gist of the
common law action of detinue was that [the] defendant originally had and
acquired possession of the chattels lawfully, as by finding or bailment, but
holds them subject to the plaintiff's superior right to immediate possession
which has been asserted by a demand." Baron v. Peoples National Bank of
Secaucus, 9 N.J. 249, 256, 87 A.2d 898, 901 (1952). At common law, the
See infra Part V for analysis of the constructive termination for convenience
doctrine
I take no position on Parts VI.B through F and VIII of the majority opinion, as
they are outside the ambit of this effort, except to note that the discussion of
HACC's delay in invoking the termination for convenience clause, see Part
VIII, supports my views insofar as it highlights the dubiousness of HACC's ex
post reliance thereon
As my discussion explains, I believe that this result would follow even if New
Jersey were to look to federal law, for I do not think New Jersey would read
federal law so expansively as does the majority
As to panel rehearing