Linan-Faye Construction Co., Inc. v. Housing Authority of The City of Camden, 49 F.3d 915, 3rd Cir. (1995)

Download as pdf
Download as pdf
You are on page 1of 37

49 F.

3d 915

LINAN-FAYE CONSTRUCTION CO., INC., Appellant


v.
HOUSING AUTHORITY OF The CITY OF CAMDEN.
No. 94-5193.

United States Court of Appeals,


Third Circuit.
Argued Sept. 23, 1994.
Decided Feb. 13, 1995.
Sur Petition for Rehearing March 13, 1995.

Cary L. Flitter (argued), Lundy, Flitter & Beldecos, Narberth, PA, for
appellant Linan-Faye Const. Co., Inc.
Mark D. Caswell (argued), Freeman, Zeller & Bryant, Cherry Hill, NJ, for
appellee Housing Authority of the City of Camden.
Before: BECKER, COWEN and GARTH, Circuit Judges.OPINION OF
THE COURT
COWEN, Circuit Judge.

Linan-Faye Construction Company Co., Inc. ("Linan-Faye"), a public housing


contractor, appeals from orders of the district court that granted summary
judgment for the Housing Authority of the City of Camden ("HACC") on
Linan-Faye's claims under public contract law and 42 U.S.C. Sec. 1983.
Because the district court erred in applying federal common law rather than
state law to resolve this dispute, we will reverse and remand to the district court
for further proceedings. Nevertheless, since we conclude that in the absence of
New Jersey law which specifically interprets "termination for convenience"
clauses New Jersey courts would look to federal common law for guidance, we
will limit the triable issues on remand to a determination of: (1) the definition
of "work performed" for purposes of paragraph 17 of Linan-Faye's contract
with HACC; (2) the pre-termination expenses incurred by Linan-Faye that may
be compensable as "work performed" under paragraph 17 of the contract; and
(3) HACC's liability, if any, for damages resulting from HACC's withholding

of Linan-Faye's performance bond after termination. Finally, because the


district court did not err in determining that Linan-Faye failed to demonstrate a
protectible property or liberty interest sufficient to support its Sec. 1983 claim,
we will affirm the district court's grant of summary judgment on this claim.
I. FACTS & PROCEDURAL HISTORY
2

On August 11, 1988, HACC advertised for bids on a housing modernization


project. The project involved the renovation and rehabilitation of 244 housing
units and was to be funded in substantial part by a grant from the United States
Department of Housing and Urban Development pursuant to the Public and
Indian Housing Comprehensive Improvement Assistance Program ("CIAP").
Plaintiff, Linan-Faye, attended all required pre-bid meetings and submitted a
bid of $4,264,000, together with supporting documentation which included a
bid bond, performance bond, qualification statement, and required affidavits.
Linan-Faye was the lowest responsible bidder for the job, underbidding its
nearest competitor by $600,000. Accordingly, HACC informed Linan-Faye that
the contract was to be forthcoming.

Linan-Faye engaged in preparatory activities in connection with the contract,


including meeting with prospective subcontractors, job planning and pricing,
talking with relevant inspectors, and securing insurance. Also, on several
occasions, representatives of Linan-Faye met with HACC and its architect to
discuss specifications and make preparations for the commencement of
physical construction. Linan-Faye, however, never began physical construction
because numerous disputes broke out between the parties over interpretation of
the specifications.

Linan-Faye contends that HACC demanded concessions before permitting


work to begin. HACC maintains that the parties arrived at different
interpretations of the project plans and specifications, and this conflict became
evident at pre-construction meetings. On November 29, 1988, as the result of
these disputes, HACC advised Linan-Faye that it was going to rebid the project.
Linan-Faye filed suit to enjoin this rebidding and allow it to complete the
project as bid.

The district court entered a temporary restraining order to prevent HACC from
accepting further bids. Subsequently, the court approved a Stipulation of
Settlement and Order of Dismissal with Prejudice, under which the parties
agreed to execute the contract and proceed with the project as originally
planned. Nevertheless, disputes soon broke out again.

On November 22, 1989, HACC issued a Notice to Proceed. Linan-Faye


contends that the notice was limited to an order to correct certain plumbing
problems that were a portion of the original contract. Linan-Faye refused to
proceed in a piecemeal fashion, and insisted that it would not begin work until a
certain number of vacant buildings were available at the same time so that it
could achieve economies of scale. HACC responded that it had scattered vacant
units available, but not rows of units.

Subsequently, HACC attempted first to extract the plumbing segment from the
contract and, when that failed, proposed a complete buy-out of Linan-Faye's
contract. The parties entertained the possibility of a buy-out until July of 1990,
at which time HUD informed HACC that it would not approve a buy-out.
HACC reinstated the previous Notice to Proceed by letter dated July 23, 1990.

At a preconstruction meeting on September 6, 1990, Linan-Faye informed


HACC that it would not start work until the contract price was increased to
reflect the costs incurred by the delay in commencing construction. HACC
responded that Linan-Faye had to begin work before it would address the issue
of the price increase.

HACC elected to terminate Linan-Faye's contract by letter dated September 25,


1990. In that letter, Gregory Kern, the Interim Executive Director of HACC,
stated that HACC would instruct the Modernization Office to assist Linan-Faye
in reclaiming its performance bond. While the letter did not mention the terms
"breach" or "default," it did state that Linan-Faye "had continually failed to
demonstrate its intent to perform under the public contract." Letter from Kern to
Norman Faye (September 25, 1990); App.Vol. I at 114-115. HACC confirmed
its decision to terminate by letter dated October 23, 1990.

10

Linan-Faye objected to the termination and filed the instant action on October
26, 1990, setting forth theories of recovery under New Jersey public contracts
law and 42 U.S.C. Sec. 1983. Linan-Faye served HACC with a complaint in
December of 1990 seeking specific performance and damages. HACC did not
surrender Linan-Faye's performance bond until July of 1991, after the district
court determined that specific performance was not available to Linan-Faye.

11

In April of 1992, HACC filed a motion for summary judgment on Linan-Faye's


civil rights claim and for the first time argued, in that same motion, that the
"termination for convenience" clause set forth in paragraph 17 of the General
Conditions of their contract limited Linan-Faye's damages under the contract.1
The district court granted HACC's motion for summary judgment on the Sec.

1983 claim, but deferred decision on the effect of the termination of


convenience clause pending further discovery.
12

Upon a renewed motion for summary judgment, the district court held for
HACC, determining that Linan-Faye's damages would be limited to those
compensable under the contract's termination for convenience clause. The
district court left open, however, the possibility of recovery for damages
accruing from HACC's initial failure to identify specifically the termination as
one of convenience.

13

HACC filed its third motion for summary judgment on October 27, 1993. In
that motion, HACC contended that since Linan-Faye never began work under
the contract, it could not recover any damages under the termination for
convenience clause. Linan-Faye responded that it could recover damages for:
(1) preparatory costs such as soliciting subcontractors, pricing, and preconstruction meetings; (2) improper notice of termination; (3) pre-termination
delay by HACC; and (4) HACC's refusal to relinquish Linan-Faye's
performance bond. Determining that federal common law applied in
interpreting this contract, the district court held that Linan-Faye incurred no
compensable damages under the termination for convenience clause. The court,
therefore, entered an order granting summary judgment for HACC. This appeal
followed.

14

Following oral argument before this Court, HACC and Linan-Faye agreed to
participate in non-binding mediation of the controversy before the Honorable
Max Rosenn, Senior Circuit Judge. By memorandum dated November 9, 1994,
Judge Rosenn informed us that efforts to reach a settlement of the controversy
through mediation were unsuccessful.

II. JURISDICTION & OVERVIEW OF ISSUES RAISED IN THIS APPEAL


15
16

The district court exercised jurisdiction in this matter by virtue of the diversity
of citizenship of the parties with the requisite amount in controversy pursuant to
28 U.S.C. Sec. 1332 (1988). This Court has jurisdiction pursuant to 28 U.S.C.
Sec. 1291 (1988). Linan-Faye essentially raises six issues on appeal:2 (1)
whether the district court erred in applying federal common law and not the law
of New Jersey to interpret this contract; (2) whether New Jersey law precludes
retroactive application of a termination for convenience clause; (3) whether the
district court was correct in its application of the constructive termination for
convenience doctrine; (4) whether the district court erred by engaging in
impermissible fact finding so as to deny Linan-Faye all compensation; (5)
whether Linan-Faye has an actionable claim for violation of its civil rights; and

(6) whether HACC's position that the termination for convenience clause
denies any recovery is barred by principles of equitable and judicial estoppel.
III. CHOICE OF LAW
17

Linan-Faye contends that the district court erred in applying federal common
law and not the law of New Jersey to resolve this dispute. According to LinanFaye, this action involves a contract dispute between a private contractor and an
autonomous public housing authority created pursuant to New Jersey law.
Where such parties enter federal court based upon diversity of citizenship,
Linan-Faye argues, the federal courts presumptively apply state law. See Erie
R. Co. v. Tompkins, 304 U.S. 64, 78, 58 S.Ct. 817, 822, 82 L.Ed. 1188 (1938).
We agree.

18

Our review of a district court's determination as to choice of law is plenary.


Louis W. Epstein Family Partnership v. Kmart Corp., 13 F.3d 762, 766 (3d
Cir.1994) (citing Universal Minerals, Inc. v. C.A. Hughes & Co., 669 F.2d 98,
102 (3d Cir.1981)). This Court's recent decision in Virgin Islands Housing
Authority v. Coastal General Construction Services Corp., 27 F.3d 911 (3d
Cir.1994), strongly indicates the proper result in this case. In Coastal General,
we determined, in the context of deciding a question of federal jurisdiction, that
local law, not federal law, governs a dispute over the termination provisions of
a contract between a public housing authority and a private construction
company. Id. at 917. As we stated in Coastal General, "[t]he fact that a contract
is subject to federal regulation does not, in itself, demonstrate that Congress
meant that all aspects of its performance or nonperformance are to be governed
by federal law rather than state law applicable to similar contracts in businesses
not under federal regulation." Id. at 916 (quoting Lindy v. Lynn, 501 F.2d 1367,
1369 (3d Cir.1974)). In addition, we explained that even if the contractor's
complaint contained assertions respecting the use of federal funds in a
construction project and the adoption of contractual forms authorized by HUD,
there would be no difference in outcome. Id. 27 F.3d at 917.

19

Similar to Coastal General, in the instant case a public housing authority


contracted with a private construction company. Linan-Faye, the construction
company, did not contract directly with the United States government. While
HUD funded the construction project in part, and HUD forms were used in the
contract, Coastal General teaches that these facts do not dictate application of
federal common law. Rather, the holding of Coastal General indicates that in
construing termination clauses such as the one at issue in this case, courts must
look to local law. Thus, the district court was incorrect in applying federal
common law and not the law of New Jersey to resolve this dispute.

20

The district court erred in deviating from the generally applicable Erie doctrine.
The Supreme Court, in Boyle v. United Technologies Corp., 487 U.S. 500, 108
S.Ct. 2510, 101 L.Ed.2d 442 (1988), set forth a two-pronged inquiry for
determining whether to apply federal common law in the absence of an express
Congressional grant of such authority. According to the Supreme Court, a court
must first determine whether the action involves " 'uniquely federal interests.' "
Id. at 504, 108 S.Ct. at 2514 (citing Texas Industries Inc. v. Radcliff Materials,
Inc., 451 U.S. 630, 640, 101 S.Ct. 2061, 2067, 68 L.Ed.2d 500 (1981)). Once a
court identifies a uniquely federal interest, the court must then determine
whether a "significant conflict" exists between an identifiable "federal policy or
interest and the [operation] of state law." Id. 487 U.S. at 507, 108 S.Ct. at 2516
(quoting Wallis v. Pan American Petroleum Corp., 384 U.S. 63, 68, 86 S.Ct.
1301, 1304, 16 L.Ed.2d 369 (1966)).

21

Relying on American Pipe & Steel Corp. v. Firestone Tire & Rubber Co., 292
F.2d 640 (9th Cir.1961), and United States v. Taylor, 333 F.2d 633 (5th
Cir.1964), the district court concluded that the government's interest in ensuring
a uniform interpretation of the termination for convenience provisions in this
contract provided the "significant federal interest" necessary to pre-empt state
law. Linan-Faye Construction Co. v. Housing Authority of Camden, 847
F.Supp. 1191, 1197 (D.N.J.1994). These cases, however, do not dictate this
result. While both of these cases applied federal law in interpreting a contract,
the government interest was far more significant in those cases than in the case
at hand. In American Pipe & Steel, the Court of Appeals for the Ninth Circuit
stated, "we agree generally with appellee that the construction of subcontracts,
let under prime contracts connected with the national security, should be
regulated by a uniform federal law." American Pipe & Steel, 292 F.2d at 644.
The instant case involves no matter of national security. Further, the court in
American Pipe & Steel expressly acknowledged that the development of the
law in this area was "still uncertain and unclear." Id. Similarly, in Taylor, the
contract at issue involved the construction of an atomic energy plant, a matter
intricately involved with national security during the 1950's and 1960's. Taylor,
333 F.2d at 635. The Taylor court also explicitly referred to the fact that
American Pipe & Steel dictated application of federal common law in such a
case. Id. at 637. Thus, both of these decisions concerned matters of national
security that are simply not present in this case.3

22

Moreover, the district court erred in finding a conflict between federal and state
law that would endanger any federal interest involved. The district court
correctly recognized the proposition that a lawsuit which involves a federal
interest is a "necessary, not a sufficient, condition for the displacement of state
law." Linan-Faye Construction Co., 847 F.Supp. at 1198 (quoting Boyle 487

U.S. at 507, 108 S.Ct. at 2516). The court, however, failed to identify a
significant conflict. In the only paragraph that attempts to identify a conflict,
the court stated:We find it implausible that the federal government would
require all CIAP contracts in excess of $10,000.00 to contain a termination for
convenience clause, and then leave interpretation of that clause to the vagaries
of state law, particularly where, like New Jersey, there are few or no state law
cases interpreting this type of provision. Rather, we believe that the decision to
include a termination for convenience clause in the "Uniform Requirements"
section of the C.F.R. reflects a federal interest in a consistent interpretation of
that clause.
23

Id.

24

The first sentence of this paragraph merely assumes the answer to the question
the court is wrestling with: whether Congress left interpretation of clauses in
these types of contracts to state law. The second sentence of the above quoted
paragraph simply reidentifies the interest involved, it does not point out a
conflict with state law.

25

The problem with the district court's reasoning is highlighted by its own
analysis of what the outcome would be under state law. The court states, "
[e]ven assuming that New Jersey law were to apply, we have no basis for
believing that New Jersey courts would look elsewhere than to federal common
law for guidance." Id. If New Jersey courts, as is likely, would look to federal
common law to decide this question for which there is little state law precedent
on point, then the court is incorrect in its assertion that a conflict exists. The
outcome would be the same under both federal and state common law. Thus,
the court erred in applying federal common law and not the law of New Jersey
to resolve this dispute and we must reverse with the direction that the district
court resolve all remaining issues in accordance with New Jersey law.

IV. NEW JERSEY LAW


26

Having decided that it is the law of New Jersey that governs the interpretation
of this contract, we must now decide whether Linan-Faye is correct when it
argues that the general principles of contract damages under New Jersey law
would permit Linan-Faye to recover full expectation damages under this
contract rather than those damages provided for under the contract's
termination for convenience clause. Citing A-S Development, Inc. v. W.R.
Grace Land Corp., 537 F.Supp. 549, 557 (D.N.J.1982), aff'd 707 F.2d 1388 (3d
Cir.1983), and other cases,4 Linan-Faye states that under New Jersey law one
who breaches an agreement must compensate the injured party in order to put

the non-breaching party in as good a position as he would have been in had


performance been rendered as promised. Further, Linan-Faye argues that New
Jersey courts have declined to import federal procurement concepts into their
contract law jurisprudence. See Edwin J. Dobson, Jr., Inc. v. Rutgers, 157
N.J.Super. 357, 418, 384 A.2d 1121, 1152 n. 10 (1978) ("The policy factors
that have lead [sic] to the development of this concept in federal contracts, such
as a need to expand or abandon a particular arms program with consequent
economic impact on contractors and subcontractors, do not warrant state courts
adopting it wholesale by judicial fiat when traditional remedies for breach of
contract are available."), aff'd sub nom., Broadway Maintenance Corp. v.
Rutgers, 180 N.J.Super. 350, 434 A.2d 1125 (A.D.1981), aff'd, 90 N.J. 253,
447 A.2d 906 (1982). While the cases Linan-Faye cites stand for these general
propositions, such generalities provide insufficient guidance in deciding the
proper construction of a contract that contains a termination for convenience
clause.5
27

It is undisputed that there are no cases in New Jersey construing the effect of
termination for convenience clauses. It is also undisputed that there are
numerous federal cases dealing specifically with termination for convenience
clauses and, in particular, with the doctrine of constructive termination for
convenience. Therefore, as the district court stated, "courts in New Jersey
would recognize that where the parties have incorporated a particular clause
pursuant to federal regulation, they do so against the backdrop of federal case
law addressing the clause." Linan-Faye Construction Co., 847 F.Supp. at 1198.
Accordingly, we align ourselves with the district court in its determination that
if New Jersey law were to apply, New Jersey courts would look to this rich
body of federal common law concerning the termination for convenience
doctrine, unless to do so would violate some enshrined principle of New Jersey
law. Id. Like the district court, we are unable to discern such a principle.6

V. TERMINATION FOR CONVENIENCE


28

Because the New Jersey Supreme Court would likely look to federal common
law as persuasive authority in order to construe this contract's termination for
convenience clause, we must examine the parties' contentions in light of the
relevant federal case law.7 As a preliminary matter, we must determine the
method HACC used to terminate Linan-Faye. HACC argues that it terminated
Linan-Faye by letter of September 25, 1990, and this letter constituted a
termination for convenience. Linan-Faye, on the other hand, argues that this
letter constituted a default termination. Linan-Faye has the better of this
argument.

29

HACC's letter of September 25, 1990 is replete with references to defaults on


the part of Linan-Faye. HACC stated in the letter that Linan-Faye's
correspondence evidences Linan-Faye's "intent to avoid compliance with the
specifications." Letter from HACC to Norman Faye (September 25, 1990);
App.Vol. I at 114. Further, HACC stated in its letter that Linan-Faye had
"continually failed to demonstrate its intent to perform under the public
contract" and that "it is clear" Linan-Faye is "no closer to performing its
contract obligations then it was in September of 1988." Id. at 114, 115.
Nowhere in this letter does HACC state that it is terminating Linan-Faye
simply for convenience. It is apparent from this document that HACC
originally terminated Linan-Faye for default.8

30

Given HACC's original termination of Linan-Faye for default, the question that
we must reach is whether the court should retroactively convert this
termination for default into a termination for convenience. HACC argues, based
on a number of cases from the United States Court of Claims and the Court of
Appeals for the Federal Circuit,9 that the district court did not err in invoking
the constructive termination for convenience doctrine in order to convert this
default termination into a termination for the convenience of the Housing
Authority. Linan-Faye, argues that under federal common law the doctrine of
constructive termination for convenience has no application to this case.
According to Linan-Faye, Federal Acquisition Regulations (FAR's) applicable
to direct procurement contracts provide for a "conversion clause," a clause that
automatically converts a termination for default into a termination for
convenience. 48 C.F.R. Sec. 49.401(b) (1993). Linan-Faye suggests, therefore,
that because no such regulations exist in grant situations10 such as this, there is
an expressed intent that such a conversion not be allowed. We find LinanFaye's argument unpersuasive.

31

The absence of a conversion provision in regulations concerning CIAP grants


does not preclude application of federal common law. While the FAR's have an
explicit conversion clause, it was the federal common law that originally
developed the concept of termination for convenience, and later developed the
concept of constructive termination for convenience. We find it appropriate to
apply federal common law.

32

The idea that the government can, under certain circumstances, terminate a
contract without paying full expectation damages, dates from the winding down
of military procurement following the civil war. Torncello v. United States, 681
F.2d 756, 764, 231 Ct.Cl. 20 (1982). The termination for convenience doctrine
originated "in the reasonable recognition that continuing with wartime contracts

after the war was over clearly was against the public interest." Id. Where the
government terminates a private contractor pursuant to a termination for
convenience clause in a contract, instead of receiving full expectation damages
the contractor's recovery is defined by the termination for convenience clause.
Recovery is limited to " 'costs incurred, profit based on the work done, and the
costs of preparing the termination settlement proposal.' " Maxima Corp. v.
United States, 847 F.2d 1549, 1552 (Fed.Cir.1988) (quoting R. Nash & J.
Cibinic, Federal Procurement Law 1104 (3d ed. 1980)) After World War II,
termination for convenience came to be applied to peacetime non-military
procurement. Id. (citing Torncello, 681 F.2d at 765-66).
33

Constructive termination for convenience, an outgrowth of termination for


convenience, is a judge-made doctrine that allows an actual breach by the
government to be retroactively justified.11 Maxima Corp., 847 F.2d at 1553.
This doctrine has its origins in the Supreme Court's decision in College Point
Boat Corp. v. United States, 267 U.S. 12, 45 S.Ct. 199, 69 L.Ed. 490 (1925). In
that decision, the Supreme Court held:

34party to a contract who is sued for its breach may ordinarily defend on the ground
A
that there existed, at the time, a legal excuse for nonperformance by him, although
he was then ignorant of the fact. He may, likewise, justify an asserted termination,
rescission, or repudiation, of a contract by proving that there was, at the time, an
adequate cause, although it did not become known to him until later.
35

College Point, 267 U.S. at 15-16, 45 S.Ct. at 200-01 (footnotes omitted)


(emphasis added).

36

The decision of the Court of Claims in John Reiner & Company v. United
States, 325 F.2d 438, 163 Ct.Cl. 381 (1963), cert. denied, 377 U.S. 931, 84
S.Ct. 1332, 12 L.Ed.2d 295 (1964), demonstrates the operation of this doctrine.
In John Reiner, the plaintiff contracted with the government to supply generator
sets to the Army. Id. 325 F.2d at 439. Following delivery of a written contract,
but before performance commenced, the government notified the plaintiff that
the contract was canceled and that the contract would be rebid because of an
impropriety in the original bidding procedure identified by a competitor. Id.
Nevertheless, no such impropriety was found to exist. Id. at 442. The Court of
Claims, therefore, was forced to consider the proper measure of damages to the
contractor. In answering this question, the court determined that while the
government did not rely on the termination for convenience clause in canceling
the contract with the plaintiff, because it could have so relied, the measure of
damages was limited to the damages provided for in that clause. Id. at 443.
According to the court, even though the excuse originally offered was not a

"valid justification," a "good ground did exist in the far-reaching right to


terminate under the termination article." Id. This case granted the government
great latitude in retroactively terminating contracts for convenience.
37

Perhaps the high-water mark of courts' permissiveness in allowing the


government to terminate for convenience, constructively or otherwise, was
Colonial Metals Co. v. United States, 494 F.2d 1355, 204 Ct.Cl. 320 (1974),
overruled in part by Torncello v. United States, 681 F.2d 756, 231 Ct.Cl. 20
(1982). In that case, a dealer in copper contracted with the government to sell
copper ingot to the Navy. Id., 494 F.2d at 1357. The government terminated
this contract to obtain the copper ingot from other sources at a cheaper price.
Id. The court held that even where the government knew of the better price
elsewhere at the time it awarded the contract and then later decided to terminate
the contract to pursue the better price, in the absence of proof of malice or
conspiracy, termination was not improper. Id. at 1361.

38

Termination for convenience, and its expansion into the constructive


termination for convenience doctrine, however, does not confer upon the
government a discretion that is unbounded. In granting the government the
privilege of constructive termination for convenience, courts brush up against
the problem of allowing the government to create an illusory contract. See
Torncello, 681 F.2d at 769 (when evaluating a termination for convenience,
one cannot ignore hornbook law that "a route of complete escape vitiates any
other consideration furnished and is incompatible with the existence of a
contract."). Accordingly, courts have articulated limits on the use of the
constructive termination for convenience doctrine in various ways. For
instance, in Torncello the Court of Claims stated that the constructive
application of a termination for convenience clause requires "some kind of
change from the circumstances of the bargain or in the expectations of the
parties" Id. at 772. In Kalvar Corp. v. United States, 543 F.2d 1298, 1301, 211
Ct.Cl. 192 (1976), cert. denied, 434 U.S. 830, 98 S.Ct. 112, 54 L.Ed.2d 89
(1977), by contrast, the court's inquiry into whether to prevent the government
from receiving the benefit of the termination for convenience clause focused on
whether the government evidenced any bad faith in terminating the contract.
Pointing out that the court is required to presume good faith on the part of
public officials, the court in that case determined that the contractor could not
avoid the application of the termination for convenience clause. Id. 543 F.2d at
1301-02; see also SMS Data Products Group, Inc. v. United States, 19 Cl.Ct.
612, 617 (1990) ("This court presumes that Government officials act in good
faith.").

39

In this matter, the district court concluded that under the bad faith test it was

proper to allow HACC to invoke the doctrine of constructive termination for


convenience. Additionally, the district court commented that even under the
changed circumstances test of Torncello, the deterioration in the relationship
between HACC and Linan-Faye would constitute sufficiently changed
circumstances to apply this doctrine. We agree with the district court's decision
that it was appropriate to apply the constructive termination for convenience
doctrine in this case for two reasons. First, Linan-Faye has produced
insufficient evidence of bad faith on the part of HACC to overcome the
presumption that public officials act in good faith. Second, this case is very
different from Torncello.
40

In Torncello, the government awarded a private contractor the right to service


all of the Navy's pest control needs. Torncello, 681 F.2d at 758, 762. However,
after awarding the contract to this contractor, the Navy called the Department
of Navy Public Works to perform the task because this organization, from its
initial bid, appeared to be able to do the work cheaper. Id. at 758. The
government invoked the constructive termination for convenience doctrine
arguing that since it had never called the private contractor to perform any
actual work, the private contractor was not entitled to any damages. Id. at 759.
Limiting its decision in Colonial Metals, the court held, in an opinion joined by
only three of six judges, that the requirement of the government's good faith is
not sufficient and that without other checks, free termination for convenience is
not supportable. Id. at 771.12

41

In the matter at hand, Linan-Faye does not claim that HACC terminated its
contract to obtain the work at a cheaper price. Linan-Faye also does not claim
that HACC terminated the contract in order to obtain work from a lower bidder
who was known to HACC at the time it contracted with Linan-Faye. Indeed,
Linan-Faye points out in its brief that it was the low bidder for the project.
Brief of Linan-Faye at 1. Thus, the divisive facts presented in Torncello are not
present here.

42

Moreover, subsequent cases have limited the scope of Torncello. The Court of
Appeals for the Federal Circuit, for example, has stated that Torncello "stands
for the unremarkable proposition that when the government contracts with a
party knowing full well that it will not honor the contract, it cannot avoid a
breach claim by adverting to the convenience termination clause." Salsbury
Industries v. United States, 905 F.2d 1518, 1521 (Fed.Cir.1990), cert. denied,
498 U.S. 1024, 111 S.Ct. 671, 112 L.Ed.2d 664 (1991); see also T.I.
Construction Co. v. Kiewit Eastern Co., No. 91-2638, 1992 WL 382306, at * 9
(E.D.Pa. Dec. 10, 1992) (citing language in Torncello indicating that its holding
was limited to the facts presented); Modern Systems Technology Corp. v.

United States, 24 Cl.Ct. 699, 704 (1992) (applying bad faith test and reading
Torncello to stand only for the above stated proposition), aff'd, 980 F.2d 745
(Fed.Cir.1992). In addition, in a subsequent case, the United States Claims
Court stated that "Torncello did not change the traditional understanding" that
the "Government could invoke the clause so long as it did not act in bad faith or
clearly abuse its discretion." SMS Data Products, 19 Cl.Ct. at 619-20. In light of
these developments, and considering the division among the court in Torncello,
we decline to read that case as significantly limiting the power of the
government in terminating for convenience.13
43

As the district court recognized, the post award deterioration of the relationship
between HACC and Linan-Faye which included conflict over the specifications
would likely constitute sufficiently changed circumstances to justify application
of the doctrine of constructive termination for convenience even under the
reasoning in Torncello. See Embrey v. United States, 17 Cl.Ct. 617, 62425
(1989) (deterioration of business relations considered sufficiently changed
circumstances to allow government to terminate for convenience); see also
SMS Data Products, 19 Cl.Ct. at 621 (genuine concern that contractor could not
meet the contract's mandatory requirements constituted changed
circumstances). Without establishing a litmus test as to what constitutes
changed circumstances, which is unnecessary in view of subsequent limits on
Torncello, we hold that New Jersey courts, looking to federal law as persuasive
authority, would permit HACC to invoke the constructive termination for
convenience doctrine in this instance.14 Accordingly, damages will be limited
by the termination for convenience clause of the contract.15

44 COMPENSATION IN LIGHT OF THE TERMINATION FOR


VI.
CONVENIENCE CLAUSE
45

Having determined that the termination for convenience clause is applicable in


this case, we must next decide whether the district court erred in granting
summary judgment for HACC and denying Linan-Faye all compensation.
Linan-Faye contends that the district court exceeded its role at the summary
judgment stage because there still remain six contested issues concerning its
contract claim. According to Linan-Faye, the district court erred in
determining: (1) the definition of "work performed" under the contract; (2)
there was no evidence of compensable pre-termination expenses under the
contract; (3) the reason why HACC retained Linan-Faye's performance bond;
(4) that Linan-Faye "refused" to begin work; (5) that Linan-Faye
misunderstood the contract specifications; and (6) that there was proper HUD
approval of the contract's termination.

46

Our scope of review is plenary in determining the propriety of summary


judgment. Oritani Savings & Loan Ass'n v. Fidelity & Deposit Co., 989 F.2d
635, 637 (3d Cir.1993). Summary judgment is proper only "if the pleadings,
depositions, answers to interrogatories, and admissions on file, together with
the affidavits, if any, show that there is no genuine issue as to any material fact
and that the moving party is entitled to judgment as a matter of law." Celotex
Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265
(1986). Further, at the summary judgment stage, "the judge's function is not
himself to weigh the evidence and determine the truth of the matter but to
determine whether there is a genuine issue for trial." Anderson v. Liberty
Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 2511, 91 L.Ed.2d 202 (1986).

47

Three of the issues that Linan-Faye raises are genuine issues of material fact in
dispute. The other issues concern facts that are either not material, or are not in
dispute. We will reverse the decision of the district court granting summary
judgment on those issues where there is a genuine issue of material fact in
dispute.

A. Definition of "Work Performed" under the Contract


48
49

Linan-Faye argues that the trial court improperly selected isolated phrases from
correspondence between the parties in its determination that the phrase "work
performed" in paragraph 17 of the contract16 refers only to "physical
construction" and not to preparatory work. The district court conceded that the
contract documents, which include the contract's General Conditions and its
Supplement to the Standard Form Agreement, failed to define the term "work."
Linan-Faye Construction Co., 847 F.Supp. at 1206. Based on an analysis of the
word "work" as used in several paragraphs of the contract, the district court
concluded that "work" could not include "preparatory work" until after LinanFaye began physical construction on the project. Id. at 1207. We conclude that
the district court erred in determining this disputed issue of fact.

50

Paragraph 8(a) of the General Conditions of this contract is the paragraph from
which the district court draws the most support for its conclusion that "work"
under the termination for convenience clause does not include "preparatory
work." The court's reading of this paragraph, however, is too strained to support
a grant of summary judgment. Paragraph 8(a) of the General Conditions states:

51
Progress
payments will be made at approximately thirty (30) day intervals; and in
preparing estimates, acceptable work in place, material delivered to and properly
stored on the site, and preparatory work done will be taken into consideration. If the
contract covers more than one project, a separate estimate shall be furnished for

each.
52

App.Vol. II at 42. From this paragraph, the district court deduced that expenses
for preparatory work were recoverable only if the contractor begins the
physical construction required under the contract. Linan-Faye Construction Co.,
847 F.Supp. at 1207. This conclusion is unjustified.

53

There is nothing in the language of paragraph 8(a) that speaks to situations


where HACC terminates Linan-Faye for convenience after Linan-Faye has
performed preparatory work, but before it has begun physical construction. If
anything, the language of this paragraph demonstrates that both parties
considered preparatory work to be a compensable cost because the paragraph
states that preparatory work will be taken into consideration in preparing
estimates for compensation. Thus, the district court erred in concluding that this
paragraph is dispositive.

54

The district court's survey of numerous other paragraphs containing the word
"work" also produces inconclusive results. According to the court, paragraph 2
which requires the contractor to "furnish all necessary labor, materials, tools,
equipment, water, light, heat, power, transportation, and supervision necessary
for performance of the work," and paragraph 22 which allows the contractor to
request from the architect drawings "which will [be required] in the planning
and production of the work " somehow indicate that "work performed" under
paragraph 17 does not include preparatory work. Id. at 1206 (emphasis added).
These provisions, on their face, do not appear to support any such conclusion.
In addition, the district court determined that paragraphs 26, 29 and 35, which
refer to the contractor's obligation to protect "work completed to date" and to
the warranty as to "work done," support the conclusion that work performed
under the termination for convenience clause does not include preparatory
work. Once again, if anything, these provisions merely beg the question of how
to define "work" under paragraph 17 of the contract. Finally, the court refers to
paragraphs 7 and 31 that speak to obligations of the contractor before and
shortly after "commencing work" under the contract. Unfortunately, these
paragraphs also do not illuminate whether the parties considered preparatory
work to constitute compensable work for purposes of the termination for
convenience clause.17

55

Linan-Faye asks for the opportunity to present testimony and cross-examine


witnesses concerning the intent of the parties in using the phrase "work
performed" in paragraph 17 of the contract. Based on the evidence mustered by
the district court, we cannot conclude that there is no dispute as to this issue.
Further, this issue is material to the question of what constitutes proper

compensation under paragraph 17. Therefore, Linan-Faye should be allowed to


present the evidence that it feels is appropriate to determine the intent of the
parties. Accordingly, we hold that the district court erred in granting summary
judgment for HACC on this disputed issue.
B. Evidence of Pre-Termination Expenses
56

Related to the disputed issue of the definition of "work performed" under the
contract is the issue of whether Linan-Faye produced any evidence of pretermination expenses compensable as "work performed." The district court
determined that Linan-Faye "had presented no evidence of expenses that would
merit an equitable adjustment to the contract." Id. at 1208 n. 22. Linan-Faye
argues that the certification which it submitted in opposition to HACC's third
motion for summary judgment provides the requisite evidence. Linan-Faye is
correct.

57

The district court, at this early stage of the litigation, improperly concluded that
there was "no evidence" of expenses compensable under the termination for
convenience clause. Linan-Faye described 15 types of expenses that LinanFaye incurred preparing for work on the HACC contract. Certification of
Norman Faye (October 21, 1993); App. at 231-33. While many of these
"expenses" may not be compensable, some of the stated expenses, such as time
spent "with municipal building, plumbing and electrical inspectors regarding
job phasing, contract details, code requirements, and problem solving," may be
compensable if the parties so intended under the termination for convenience
clause of the contract. Cf. ITI Defense Communications Division, Nos. 11858,
13439, 1970 WL 1124, 1970 ASBCA Lexis 29, at * 56 (July 29, 1970) (cost of
work done by appellant in preparing and submitting configurations that were
never used still properly compensable under the termination for convenience
clause); Navgas, Inc., No. 9240, 1964 WL 475, 1964 ASBCA Lexis 1139, at *
29 (November 18, 1964) (costs of investigating work to be done, and
determining the best way to perform the contract, if awarded, are properly
compensable under termination for convenience clause). Although, on the
whole, the evidence produced by Linan-Faye in this certification appears
meager, by granting summary judgment for HACC the district court
improvidently prevented the plaintiff from developing the record more fully.
There was not a complete lack of evidence. Accordingly, we must reverse the
grant of summary judgment on this issue and remand for trial.

58

In remanding for trial on this issue, however, it is important to explain precisely


the scope of our holding. We do not hold that Linan-Faye is entitled to pretermination expenses that accrued as the result of any alleged pre-termination

breaches of contract by HACC. As the district court correctly held, cases that
have addressed the issue of pre-termination breaches have concluded that
claims for such damages are subsumed in the termination for convenience
clause. Linan-Faye Construction Co., 847 F.Supp. at 1203, 1204 (citing Nolan
Brothers, Inc. v. United States, 405 F.2d 1250, 186 Ct.Cl. 602 (1969)); Descon
System Ltd. v. United States, 6 Cl.Ct. 410 (1984)). Pre-termination expenses
that accrued as the result of any alleged pre-termination breaches by HACC are
not compensable. On remand, the triable issue is limited to a determination of
the pre-termination expenses which Linan-Faye incurred that the parties
intended to be compensable as "work performed" under the termination for
convenience clause of the contract.
C. Why HACC Retained Linan-Faye's Performance Bond
59
60

Linan-Faye next contends that the trial court improperly resolved a factual
dispute as to why HACC retained Linan-Faye's performance bonds after
terminating Linan-Faye. According to Linan-Faye, it is entitled to damages
arising from HACC's failure to return this performance bond. Linan-Faye
alleges that by retaining its bond, HACC prevented it from accepting other
construction contracts and used the bond as an inducement to force Linan-Faye
to accept an unreasonable resolution of this dispute. HACC argues that it
retained Linan-Faye's performance bond because Linan-Faye instituted a suit
seeking specific performance and if Linan-Faye were successful, HACC would
need Linan-Faye's bond.

61

This issue is not resolved solely by reference to the termination for convenience
clause because the events that give rise to this claim occurred after
termination.18 Recognizing this, the district court decided the issue by
concluding that keeping the bonds during the pendency of the litigation was the
"logical response" to the plaintiff's lawsuit. Linan-Faye Construction Co., 847
F.Supp. at 1205.

62

Unfortunately, there is no testimony or record evidence to support the


conclusion that HACC engaged in the "logical response" posited by the district
court. No one from HACC ever indicated that it was Linan-Faye's suit for
specific performance that prevented HACC from returning the bond. Counsel
for HACC simply raised this argument when the case took on a litigation
posture. This naked assertion by counsel, without record support, is not
sufficient to warrant a grant of summary judgment.

63

The district court attempts to justify its decision to accept HACC's argument by
referring to the September 25, 1990 termination letter sent by Gregory Kern,

the Interim Executive Director of HACC. Nevertheless, its reasoning is


unpersuasive. According to the court, Mr. Kern's letter which indicated that
HACC would return the bonds was sent before Linan-Faye instituted suit.
Linan-Faye, 847 F.Supp. at 1205 n. 16. Therefore, the court reasoned, "[t]he
decision of the HACC to depart from Mr. Kern's original plan only supports
[the] finding that HACC felt compelled to hold onto the bonds until the Court
had disposed of plaintiff's claims for specific performance." Id. (emphasis
added). The court in this passage, however, merely assumes its conclusion.
What eludes the district court is any evidence indicating that it was the suit for
specific performance that caused retention of the bond. In effect, what the
district court stated is that the decision of HACC to depart from Kern's original
plan supports HACC's decision to depart from Kern's original plan--a statement
without significance.
64

Moreover, even taking HACC's view of the timing of the relevant events, there
was an unjustified gap of over one month between the time HACC terminated
Linan-Faye and the time Linan-Faye served its complaint seeking specific
performance. According to HACC, after it issued its September 25, 1990 letter
of termination, Linan-Faye sought reversal of HACC's decision to terminate.
HACC states that it sent a letter to Linan-Faye on October 23, 1990 confirming
its decision to terminate. Linan-Faye did not serve its complaint for specific
performance until early in December of 1990, however, and the bond had not
yet been returned. This unexcused delay strengthens Linan-Faye's argument
that HACC did not decide to hold onto the performance bond as the result of
the specific performance suit. In light of these facts, we will reverse the district
court's grant of summary judgment for HACC and remand for trial on this
disputed issue.19

D. Whether Linan-Faye "Refused" to Begin Work


65
66

Linan-Faye asserts that the district court improperly found it "refused" to begin
work. According to Linan-Faye, it did not refuse to begin work, but merely
wanted to agree on any changes that HACC desired before it began
construction. Linan-Faye contends that there is no basis in the record for the
district court's finding that it flatly refused to begin work.

67

We find that the question of whether Linan-Faye flatly refused to begin work is
immaterial to this case. Whether Linan-Faye actually "refused" to begin work
would be relevant if it was necessary to decide if Linan-Faye defaulted on its
obligations. The district court, however, based its holding on the doctrine of
constructive termination for convenience. Linan-Faye Construction Co., 847
F.Supp. at 1203. The constructive termination for convenience doctrine makes

the original reason for termination relevant only to the extent that it evidences
the government's bad faith or a change in circumstances from the time of
contracting.20 The issue of whether there was an actual default by Linan-Faye
in refusing to begin work is immaterial. In this case the default termination is
converted into a termination for convenience of the government by operation of
law. Since we agree with the district court that it was appropriate to apply the
constructive termination for convenience doctrine, we hold that this issue is
immaterial.
E. Whether Linan-Faye Misunderstood the Specifications
68
69

Linan-Faye argues that the district court improperly concluded that it


misunderstood the contract specifications because the court indicated in a
footnote that "[a]t the very least, plaintiff misinterpreted the architect's
specifications" for the project. Linan-Faye Construction Co., 847 F.Supp. at
1203 n. 13. According to Linan-Faye, it was HACC who "misinterpreted" the
contract specifications. The dispute over proper interpretation of the contract
specifications, argues Linan-Faye, prevented the court from resolving this issue
at the summary judgment stage.

70

Linan-Faye's argument misinterprets the district court's reasoning. The relevant


statement the court made in this footnote is merely that there was discord
between the parties over interpreting their agreement. The district court
mentioned the discord to support its conclusion concerning the constructive
termination for convenience doctrine. Whether Linan-Faye actually
misunderstood the specifications, or whether it was HACC's misunderstanding,
is irrelevant where there is a termination for convenience. As the district court
held, the constructive termination for convenience doctrine operates to allow
the government to extricate itself from contractual relationships without
arguing as to which party was in default. Id. at 1203. Accordingly, the issue of
who misunderstood the contract specifications is not material, and played no
part in the order granting summary judgment.

F. Whether HUD Approval was Necessary for Termination


71
72

Linan-Faye suggests that whether HUD approved a termination for


convenience is a disputed issue that precludes summary judgment. It concedes
that HACC obtained HUD's general approval to terminate the contract, but
argues that HUD never approved a termination for convenience. Linan-Faye
contends that HUD approval of a termination for convenience was a condition
precedent to invoking that clause, and failure to obtain such approval precludes
summary judgment. Linan-Faye does not succeed in raising a disputed material

issue on this point.


73

For the purposes of deciding this case, the district court did not assume that
HACC originally terminated for convenience. While there is a dispute as to
whether the original letter of termination constituted a default termination or a
termination for convenience, HACC prevails under the district court's reasoning
without having to prove that it obtained HUD approval of a termination for
convenience. The court proceeded on a constructive termination for
convenience theory. Linan-Faye does not dispute that HUD had approved
HACC's right to terminate generally. Thus, concerning the original termination,
HACC fulfilled its obligations by informing HUD, and obtaining from HUD a
general approval for the termination of the contract. Because HACC received
general HUD approval to terminate, there is no bar to this court's using the
constructive termination for convenience doctrine to convert this into a
termination for convenience by operation of law. Further, and most
importantly, there is simply no dispute as to the material facts of what approval
HACC obtained. Indeed, both parties concede that HACC obtained HUD
approval to terminate generally, but did not obtain specific HUD approval of a
termination for convenience. Therefore, this cannot be a disputed factual issue
as Linan-Faye erroneously contends.

74

Accordingly, we will reverse the district court's grant of summary judgment


and remand for trial on the issues of: (1) the definition of "work performed"
under paragraph 17 of the contract; (2) the pre-termination expenses incurred
by Linan-Faye that are compensable as "work performed" under the termination
for convenience clause; and (3) HACC's possible liability for damages resulting
from its retaining Linan-Faye's bond after termination.

VII. SECTION 1983


75

Linan-Faye next asserts that the district court erred in granting summary
judgment against it on its claim under 42 U.S.C. Sec. 1983. Linan-Faye argues
it has a protectible property interest in its contract with HACC that is entitled to
Fourteenth and Fifth Amendment protection. Further, Linan-Faye contends that
HACC's retention of its performance bond implicates a liberty interest entitled
to constitutional protection. In granting summary judgment, the district court
held that whatever property interest Linan-Faye may have had, it does not rise
to a sufficient level of certainty or dependency to merit constitutional
protection. Linan-Faye Construction Co. v. Housing Authority of Camden, 797
F.Supp. 376, 380 (D.N.J.1992).

76

We agree with the district court's resolution of this matter. This Court recently

surveyed the law concerning Fourteenth Amendment claims based on contracts


with state entities. Unger v. National Residents Matching Program, 928 F.2d
1392 (3d Cir.1991). We stated in Unger that it is beyond dispute today that a
contract with a state entity can give rise to a property right protected under the
Fourteenth Amendment. Id. at 1397 (citing Perry v. Sindermann, 408 U.S. 593,
599-601, 92 S.Ct. 2694, 2698-2700, 33 L.Ed.2d 570 (1972)). Nevertheless, we
stated that the Supreme Court has never held that every state contract gives rise
to such a protectible property interest. Id.
77

As we explained in Unger, relevant Supreme Court cases and cases from other
courts of appeals instruct that two general types of contract rights are
recognized as property protected under the Fourteenth Amendment: (1) where
"the contract confers a protected status, such as those 'characterized by a quality
of either extreme dependence in the case of welfare benefits, or permanence in
the case of tenure, or sometimes both, as frequently occurs in the case of social
security benefits' "; or (2) where "the contract itself includes a provision that the
state entity can terminate the contract only for cause." Id. 928 F.2d at 1399
(citing S & D Maintenance Co. v. Goldin, 844 F.2d 962, 966-67 (2d Cir.1988)).
In Unger, a physician licensed to practice medicine in Pennsylvania was
admitted into Temple University Hospital's dermatology residency program
through the National Resident Matching Program. Id., 928 F.2d at 1393.
Shortly before Unger was to begin the program, she received a letter stating
that the University had decided to discontinue the program. Id. Unger filed suit
under 42 U.S.C. Sec. 1983. Id.

78

Declaring that the contract in Unger did not fall into either of the two protected
categories, we dismissed Unger's Sec. 1983 claim. Id. at 1402. We relied in part
on the reasoning of our previous decision in Reich v. Beharry, 883 F.2d 239 (3d
Cir.1989), where we stated:

79
Many
... courts have observed that if every breach of contract by someone acting
under color of state law constituted a deprivation of property for procedural due
process purposes, the federal courts would be called upon to pass judgment on the
procedural fairness of the processing of a myriad of contract claims against public
entities. We agree that such a wholesale federalization of state public contract law
seems far afield from the great purposes of the due process clause.
80

Reich, 883 F.2d at 242 (citations omitted).

81

Linan-Faye's contract with HACC does not fall into either of the two categories
we delineated in Unger. The contract does not confer a protected status on the
plaintiff and the state entity could terminate the contract for reasons other than

for cause. Indeed, it could be terminated for convenience. To grant Linan-Faye


a remedy under Sec. 1983 would create the wholesale federalization of state
public contract law that concerned us in Unger and Reich. Accordingly, the
district court did not err in granting summary judgment for HACC on LinanFaye's claim.
82

Turning to Linan-Faye's assertion that it has been deprived of a constitutionally


protected liberty interest, we also find that the district court did not err in
granting summary judgment for HACC. The Court of Appeals for the Second
Circuit addressed a case factually similar to the one at hand in S & D
Maintenance Co. v. Goldin, 844 F.2d 962 (2d Cir.1988). In that case, a
contractor brought a Sec. 1983 claim against the City of New York, claiming
that the City's withholding of payments under a contract to maintain parking
meters resulted in the contractor being left with insufficient capital to pursue
other work. Id. at 963, 970. The court held that although the consequential
damages of an alleged breach may be severe, this fact alone cannot convert a
contract claim into a deprivation of liberty. Id. at 970. We agree with the
reasoning of the Court of Appeals for the Second Circuit, and conclude that
Linan-Faye fails to establish a claim of constitutional magnitude. We will
affirm the district court's grant of summary judgment to HACC on Linan-Faye's
Sec. 1983 claim.

VIII. ESTOPPEL CLAIMS


83

Linan-Faye's final contention is that HACC is precluded from refusing to pay


compensation by reason of principles of equitable and judicial estoppel. LinanFaye argues that HACC could have terminated for convenience in 1988 but that
it did not, and it breached a duty of fairness by waiting two years before
deciding to terminate. Linan-Faye relies on a single case, M. & O. Disposal Co.
v. Township of Middletown, 100 N.J.Super. 558, 242 A.2d 841 (A.D.1967),
aff'd, 52 N.J. 6, 242 A.2d 841 (1968), to support its equitable estoppel
argument. Additionally, Linan-Faye argues that because HACC asserted in
prior judicial proceedings that there would be a "defined measure of damages"
under the termination for convenience clause, HACC is now judicially
estopped from arguing that it owes Linan-Faye nothing.

84

We find Linan-Faye's equitable estoppel claim unpersuasive. HACC could have


terminated for convenience in 1988, but it also could have pursued completion
of the contract according to its terms. HACC's decision to terminate after an
inability to agree to such terms does not breach a duty of fairness. Indeed, this
termination was within HACC's rights under the contract and, as explained
above, the constructive termination for convenience doctrine allows HACC to

convert its original termination into a termination for convenience.


85

Moreover, Linan-Faye's reliance on M. & O. Disposal is misplaced. That case


involved the question of whether a municipality impliedly ratified a contract for
extra work which was outside the scope of contract to dispose of garbage. Id.,
100 N.J.Super. at 560, 567, 242 A.2d at 841, 846. In that case, the New Jersey
court merely stated the general precept that equitable principles of estoppel will
be applied against municipalities where the interests of justice, morality, or
common fairness clearly dictate this course. Id. at 567, 242 A.2d at 846.
Beyond the obvious fact that the timing problem presented here has almost
nothing to do with the ratification issue presented in M. & O. Disposal, LinanFaye has failed to demonstrate how HACC's exercise of its rights under this
contract violates principles of justice, morality, or common fairness. Thus, we
find Linan-Faye's equitable estoppel argument unconvincing.

86

Linan-Faye's argument for judicial estoppel is also unpersuasive. Judicial


estoppel precludes a party from assuming a position in a legal proceeding
inconsistent with one previously asserted to the prejudice of an adverse party.
Brown v. Allied Plumbing & Heating Co., 129 N.J.L. 442, 446, 30 A.2d 290,
292 (Sup.Ct.), aff'd 130 N.J.L. 487, 33 A.2d 813 (E. & A.1943); Chattin v.
Cape May Greene, Inc., 243 N.J.Super. 590, 620, 581 A.2d 91, 107 (A.D.1990)
(citations omitted), aff'd, 124 N.J. 520, 591 A.2d 943 (1991). There is no
inconsistency in taking the position that HACC took in prior proceedings.
HACC merely argued that the termination for convenience clause provided the
defined measure of damages. After the district court decided the difficult
question of whether the termination for convenience clause defines the measure
of damages, it was not only appropriate, but necessary, for HACC to address
the question of what the measure of damages is under that clause. At this later
stage, HACC may contend that this clause provides no compensation for
Linan-Faye in this instance. The attempt by Linan-Faye to describe a
contradiction in HACC's legal position has no force under the facts presented in
this case.

IX. CONCLUSION
87

In sum, we find that the district court erred in its decision to apply federal
common law and not the law of New Jersey to resolve this dispute. Applying
New Jersey law, we will reverse the district court's grant of summary judgment
and remand for trial on the issues of material fact that are in dispute. The three
issues that remain in dispute in this case are the definition of "work performed"
under paragraph 17 of the contract, whether and to what extent Linan-Faye
incurred preparatory expenses prior to termination that are compensable as

"work performed" under paragraph 17, and HACC's possible liability for
damages resulting from its withholding of Linan-Faye's performance bond after
termination. Finally, we will affirm the district court's grant of summary
judgment in favor of HACC on Linan-Faye's Sec. 1983 claim.
88

BECKER, Circuit Judge, Concurring and Dissenting.

89

I join in Parts I, II, and III of the majority opinion. However, I dissent from Part
IV because I do not agree that New Jersey would apply to this garden variety
construction dispute between a builder and a local governmental agency
precepts drawn from a potpourri of federal cases which amount at best to a
hodgepodge, and at worst to a regime so inhospitable and unfair to small
contractors who deal with government agencies as to be inconsistent with New
Jersey jurisprudence. Rather, I believe that New Jersey would apply its own
law, which would not recognize the doctrine of "constructive termination for
convenience" but rather would apply the normal rule of contract breach which,
on this record, would unquestionably render HACC liable. Moreover, even if
the New Jersey Supreme Court were to assimilate federal law, I do not think
that it would read that law in the matter predicted by the majority. The precepts
that the majority applies are gleaned from cases that have been excoriated in
critical commentary because they are in considerable measure poorly reasoned.

90

I also find myself unable to join in Part VII, dealing with Linan-Faye's 42
U.S.C. Sec. 1983 claims. I cannot agree with the majority that HACC's
arguably improper retention of Linan-Faye's performance bond, which the
company requires in order to engage in any business, did not impair LinanFaye's liberty interest. I do, however, join the majority with respect to its
rejection of Linan-Faye's property interest claim.1

I. WHAT LAW WOULD NEW JERSEY APPLY?


91
92

The majority, notwithstanding the considerable authority of the Dobson case,


supra Maj.Op. at 921, reasons that because there are no cases in New Jersey
construing the effect of termination for convenience clauses, "courts in New
Jersey would recognize that where the parties have incorporated a particular
clause pursuant to federal regulation, they do so against the backdrop of federal
case law addressing the clause," and hence would adopt federal law, whatever
that may be. That is the sum and substance of the majority's argument. It is, I
suggest, pretty "thin soup," neither documented nor reasoned.

93

The majority's prediction also ignores the facts that should govern the analysis

required in such circumstances. A review of the facts Linan-Faye has advanced


and supported in connection with the summary judgment motion--which are
glossed over by the majority--will illuminate the correct prediction of New
Jersey law. At this stage, these facts must obviously be viewed in the light most
favorable to Linan-Faye, the non-moving party. See Goodman v. Mead Johnson
& Co., 534 F.2d 566, 573 (3d Cir.1976).
A. The Facts Viewed in the Light Most Favorable to
94
Linan-Faye
95

It is undisputed that the parties had a binding $4,264,000 contract for the
rehabilitation of 244 housing units. Linan-Faye, with declarations cognizable in
summary judgment proceedings: (1) represents itself to be an experienced,
highly regarded contractor that was ready, willing, and able to perform the job
in a timely fashion; (2) states that through incompetence, poor planning, or
other contractors' delay, the HACC failed or refused to give Linan-Faye even a
Notice to Proceed for a full year; and (3) submits that after finally giving that
Notice, HACC then proceeded, without justification, to delay Linan-Faye for
almost another year. Linan-Faye also represents that HACC never supplied
Linan-Faye with a list of which vacant units to work on; that turmoil reigned at
HACC as the Executive Director was replaced by a new Acting Executive
Director, Gregory Kern, in July 1990; and that Kern decided to "clean house"
by, inter alia, summarily terminating Linan-Faye's contract.

96

It is also undisputed that in the course of the termination dialogue, HACC


never suggested that the termination was "for convenience." All the discussion
and written notices instead alleged contractor default, which Linan-Faye
staunchly denied. Moreover, whether or not it was legally required, HACC
never got HUD approval to terminate for convenience. Indeed, HACC did not
invoke the termination for convenience clause until two years after termination,
when the litigation began. Most importantly, during the period from September
1988 through August 1991, HACC held Linan-Faye's performance bonds,
effectively precluding LinanFaye from bidding any other significant work.
Linan-Faye has proffered evidence that it suffered damages of $1,492,000 as a
result of HACC's breach of the contract and a further loss of $1,249,999 from
its inability to use its bonding line.

B. General New Jersey Contract Law Principles


97
98

Under general common law contract principles, applicable in New Jersey and
elsewhere, one who breaches a contract must compensate the injured non-

breaching party so as to put it in the position it would have occupied had


performance been rendered as promised. Donovan v. Bachstadt, 91 N.J. 434,
453 A.2d 160, 165 (1982); 5 ARTHUR L. CORBIN, CORBIN ON
CONTRACTS Sec. 992 (1951). A court in a breach of contract case aims to
fashion a remedy in order to compensate the non-breaching party fully.
Donovan, 453 A.2d at 165; 5 ARTHUR L. CORBIN, CORBIN ON
CONTRACTS Sec. 992 (1951).
99

The New Jersey courts have long maintained a liberal rule that non-breaching
parties are entitled to damages. Cf. In re Merritt Logan, Inc., 901 F.2d 349, 357
(3d Cir.1990) (interpreting New Jersey contract damages law); Sandler v.
Lawn-A-Mat Chem. & Equip. Corp., 141 N.J.Super. 437, 358 A.2d 805, 814
(App.Div.), cert. denied, 71 N.J. 503, 366 A.2d 658 (1976) (non-breaching
party "presumptively" entitled to damages, with doubts resolved against the
breaching party). New Jersey courts have also narrowly construed clauses that
tend to restrict a party's right to recover its full common law damages. See
American Sanitary Sales Co. v. State, 178 N.J.Super. 429, 429 A.2d 403, 407
(App.Div.), cert. denied, 87 N.J. 420, 434 A.2d 1094 (1981) (narrowly
interpreting a "no damage for delay" clause in a New Jersey state contract).

100 The reluctance of the New Jersey Courts to give expansive effect to exculpatory
clauses extends to cases involving its own government agencies. See, e.g.,
Buckley & Co., Inc. v. State, 140 N.J.Super. 289, 356 A.2d 56, 62 (Law
Div.1975); Ace Stone, Inc. v. Township of Wayne, 47 N.J. 431, 221 A.2d 515,
518-19 (1966); American Sanitary Sales Co., 178 N.J.Super. 429, 429 A.2d at
407; see also Department of Transp. v. Arapaho Constr., Inc., 257 Ga. 269, 357
S.E.2d 593, 594-95 (1987) (relying in part on Ace Stone). Moreover, under
New Jersey law there is a presumption against finding a contractual intent to
alter common law rights and remedies. See, e.g., Gibraltar Factors Corp. v.
Slapo, 41 N.J.Super. 381, 125 A.2d 309, 310 (Law Div.1956) (parties presumed
to contract with reference to existing law), aff'd, 23 N.J. 459, 129 A.2d 567
(1957), appeal dismissed, 355 U.S. 13, 78 S.Ct. 44, 2 L.Ed.2d 20 (1957); see
also Rescigno v. Picinich, 151 N.J.Super. 587, 377 A.2d 733, 739 (Law
Div.1977) (applying a presumption against a statutory intent to alter common
law rights); Blackman v. Iles, 4 N.J. 82, 71 A.2d 633, 636 (1950) (same).
Indeed, New Jersey courts commonly award contractors common law contract
damages against the State, including damages for delay. See, e.g., American
Sanitary Sales Co., 178 N.J.Super. 429, 429 A.2d at 407; Buckley & Co., 140
N.J.Super. 289, 356 A.2d at 65 (see also cases cited therein).
C. New Jersey and the Federal Law Alternative
101

102 This is not the first case in which a court applying New Jersey law has had to
adjudicate a contract dispute with some federal connection. In Edward J.
Dobson, Jr., Inc. v. Rutgers, 157 N.J.Super. 357, 384 A.2d 1121 (Law
Div.1978), aff'd sub nom. Broadway Maintenance Corp. v. Rutgers, 180
N.J.Super. 350, 434 A.2d 1125 (App.Div.1981), aff'd, 90 N.J. 253, 447 A.2d
906 (1982), plaintiff-contractors sought to avoid the impact of a "no-damage
for delay" clause by asserting their claim for delay as an "equitable
adjustment." The court traced the history of the "equitable adjustment"
provisions in federal construction contracts and federal regulations. But the
court refused to import this wholly federal concept into the New Jersey law of
public construction contracts. Finding that the term "equitable adjustment" had
become a term of art in federal contracts, the court held:
103 policy factors that have lead [sic] to the development of this concept in federal
The
contracts, such as a need to expand or abandon a particular arms program with
consequent economic impact on contractors and subcontractors, do not warrant state
courts adopting it wholesale by judicial fiat when traditional remedies for breach of
contract are available. Id., 157 N.J.Super. 357, 384 A.2d at 1153 n. 10.
104 This holding was affirmed by both the intermediate appellate court and
Supreme Court of New Jersey and strongly suggests that New Jersey courts
would not import the federal concept of constructive termination for
convenience into its public construction contracts jurisprudence.
105 As the majority correctly points out, because there is no reported New Jersey
precedent interpreting a "termination for convenience" clause, it is the function
of this court to predict how the New Jersey Supreme Court would rule if
confronted with this issue. In my view, there is no reason to believe that that
court, if called upon to resolve the question, would jettison a century of settled
contract law supporting liberal contract remedies and narrowly construing
similar exculpatory provisions in order to adopt a harsh--and harshly criticized,
see infra--federal interpretation of the clause at issue here. In this case, the
retroactive application of this dramatic change in the law imposed by the
majority to the factual scenario described above not only exacerbates the
harshness of the result but also increases my confidence that the New Jersey
Supreme Court would never have adopted this interpretation.
D. The Termination of Convenience Provision and Its Harsh
106
Construction by the Majority
107 The termination for convenience clause has, as the majority explains, a long

lineage, dating from the Civil War era. During that era federal government
contracting was attended by much impropriety and scandal. See generally
CARL SANDBURG, ABRAHAM LINCOLN, THE WAR YEARS (1948).
The modern (post-1970) incarnation of the clause is ensconced in the Code of
Federal Regulations:
108
If
the contractor can establish, or if it is otherwise determined that the contractor
was not in default or that the failure to perform is excusable; i.e., arose out of causes
beyond the control and without the fault or negligence of the contractor, the
[prescribed default clauses] provide that a termination for default will be considered
to have been a termination for the convenience of the Government....
109 Federal Acquisition Regulations ("FAR's"), 48 C.F.R. Sec. 49.401(b) (1993).
The FAR's apply to direct United States government procurement (including
HUD procurement). They do not apply to grants of federal funds to local public
housing authorities. The district court acknowledged this undisputed point.
(Dist.Ct.Op. at 18 n. 7)
110 Moreover, regulations that govern grants to local housing agencies contain their
own specific scheme and procedures for federally funded contracts made by
state and local housing authorities that are separate and distinct from the FAR's.
These "CIAP" requirements mandate a variety of terms and provisions that
must be set forth in such contracts, including a termination for convenience
clause. See 24 C.F.R. Sec. 85.36(i)(2). In contrast to the FAR's, however, the
Administrative Requirements for CIAP Grants do not include any counterpart
to the automatic conversion language of 48 C.F.R. Sec. 49.401(b), or the other
specific termination provisions found in HUD's own FAR's. This is consistent
with the mandate of the CIAP enabling statute, which is designed to allow the
housing authority grantees maximum discretion and individualized judgment.
42 U.S.C.S. Sec. 1437l(e)(1)(E), (e)(4)(D) (1994).
111 The absence of an express conversion clause in the Administrative
Requirements for Grants is significant because, under the venerable maxim of
statutory construction, expressio unius est exclusio alterius, the inclusion of one
is the exclusion of another. As I see it, the exclusion of an automatic conversion
provision in the Requirements for Public Housing Authority Contracts (when
specifically included in HUD's own FAR's) expresses an intent to exclude such
a provision, unless local PHA administrators choose to include it. Cf. Marshall
v. Western Union Tel. Co., 621 F.2d 1246, 1251 (3d Cir.1980) (refusing to
apply a Department of Labor standard in one subsection of a regulation where it
had been excluded when it was included elsewhere); SUTHERLAND
STATUTORY CONSTRUCTION Sec. 31.06 (4th ed.). Moreover, without the

conversion clause, HACC's initial failure to allege that it was terminating the
contract with Linan-Faye for convenience prevents HACC from subsequently
embracing that argument.
112 Before contracts with the federal government included automatic conversion
clauses, courts did not permit government agencies to use the termination for
convenience clauses to escape from a breach. In Klein v. United States, 285
F.2d 778, 152 Ct.Cl. 8 (1961), for example, the Court of Claims rejected the
government's argument that, because it had a contractual right to terminate for
convenience, its illegal breach of contract should be disregarded. Id. at 784.
Accord Goldwasser v. United States, 325 F.2d 722, 725, 163 Ct.Cl. 450 (1963);
Dynalectron Corp. v. United States, 518 F.2d 594, 604, 207 Ct.Cl. 349 (1975);
Torncello v. United States, 681 F.2d 756, 771-72, 231 Ct.Cl. 20 (1982);
Rogerson Aircraft Corp. v. Fairchild Indus. Inc., 632 F.Supp. 1494, 1499
(C.D.Cal.1986) (changed circumstances required).
113 The problems confronted by government contracting officers operating under
the Klein rule resulted in the adoption of the automatic conversion clause by
regulation, 48 C.F.R. Sec. 49.401(b). The clause now appears in most direct
federal government procurement contracts. However, as the Rogerson court
noted in footnote 5 of its opinion, where the "automatic conversion clause" is
not made part of the contract, either expressly or by regulation, the Klein rule
remains fully applicable and bars the implication of such clause. Rogerson, 632
F.Supp. at 1500 n. 5. Although the contract in Rogerson appears more specific
than the instant contract in its requirement that the agency elect its basis for
termination (i.e., default or convenience), the Rogerson decision remains
important and persuasive. Without a conversion clause, HACC cannot invoke
the termination for convenience provision to cure its improper default
termination. And a wrongful termination for default constitutes a breach of the
contract entitling the wrongly terminated subcontractor to state law damages for
the breach, including lost profits. Id. at 1500-01; Clay Bernard Sys. Int'l, Ltd. v.
United States, 22 Cl.Ct. 804, 810-11 (1991) (holding that absent a "conversion
clause" a wrongful termination for default is a breach, entitling contractor to
recovery under federal procurement law).
114 But even if HACC had initially invoked its termination for convenience clause,
thus avoiding the issue of the absence of a conversion clause, HACC could not
avoid liability in this case. The majority acknowledges that the case law
construing the termination for convenience clause has retrenched from its high
water mark. While the majority's discussion does not clearly depict the current
state of the law, the leading cases appear to hold that government agencies can
only invoke the clause where there has been some change in the circumstances

of the parties. See Torncello, 681 F.2d at 772. The majority holds that a
deterioration in business relations, demonstrated in not insignificant part by a
dispute over specifications, constitutes such a change in circumstances. In my
view, such a rule would largely eviscerate the limitation. As lawyers who have
dealt with construction disputes know, these contracts almost always generate
some dispute over specifications, and any construction dispute rancorous
enough to spawn litigation will almost certainly have led to the requisite
deterioration in business relations. The facts of this case illustrate how circular
a deterioration-of-business-relations test can be, for HACC did not even attempt
to invoke the clause until litigation began.
115 The majority constructs a regime under which a dispute arising out of a garden
variety contract between a builder and a local housing authority, which is not a
federal government contract but only a local agency contract to which certain
federal regulations apply, has been severed from its common law roots. The
majority's application of selected federal cases renders these local agency
contracts virtually illusory by giving an arguably defaulting local agency the
right to avoid its own breach, and sharply limit its liability simply by incanting
the termination for convenience clause two years after the fact. In my view, it is
inconceivable that the New Jersey Supreme Court, which has so consistently
supported liberal awards of contract damages, would countenance that result,
especially in the fact scenario at bar.
116 This conclusion is strongly buttressed by the scathing criticism that has been
levied at Torncello and the cognate jurisprudence. See, e.g., Stephen N. Young,
Note, Limiting the Government's Ability To Terminate for Convenience
Following Tornecello, 52 GEO.WASH.L.REV. 892 (1984) (suggesting that the
Torncello decision provides a reason to eliminate the government's ability to
terminate for convenience entirely).
117 Because I do not believe that the New Jersey Supreme Court would adopt the
federal interpretation but would instead continue to give exculpatory clauses
such as the termination for convenience clause only narrow--if any--effect, I
dissent.2
II. THE Sec. 1983 CLAIM
118 I also dissent from the majority's affirmance of the summary judgment granted
on Linan-Faye's Sec. 1983 claim. While I agree that Linan-Faye's interest in the
contract did not rise to a property interest protected by the Constitution, I cannot
agree that HACC's unjustified retention of Linan-Faye's performance bond did
not deprive Linan-Faye of a protected liberty interest.

119 The majority dismisses Linan-Faye's claim rather summarily, overlooking


precedent which would, in my view, require reversal. The right to follow a
chosen profession free from unreasonable interference comes within both the
liberty and property concepts of the Fifth and Fourteenth Amendments. See
Greene v. McElroy, 360 U.S. 474, 492, 79 S.Ct. 1400, 1411-12, 3 L.Ed.2d 1377
(1959); Piecknick v. Commonwealth of Pennsylvania, 36 F.3d 1250, 1259 (3d
Cir.1994); Bernard v. United Township High Sch. Dist. No. 30, 5 F.3d 1090,
1092 (7th Cir.1993). It is true that the Constitution protects only the right "to
pursue a calling or occupation, and not the right to a specific job." Bernard, 5
F.3d at 1092 (quoting Wroblewski v. City of Washburn, 965 F.2d 452, 455 (7th
Cir.1992)). Nevertheless, the majority and the sole case on which it relies, S &
D Maintenance Co. v. Goldin, 844 F.2d 962 (2d Cir.1988), fail to consider how
disputes over specific jobs can, under certain circumstances, affect a party's
pursuit of its occupation.
120 In S & D, although the Court of Appeals for the Second Circuit framed the Sec.
1983 claim as one challenging the plaintiff's dismissal from government
employment, which clearly did not rise to a constitutional violation, the true
basis of the plaintiff's liberty claim was that New York City's refusal to pay
amounts already due had essentially forced the company out of business and
left it "tottering near bankruptcy, unable to get work, as a direct result of the
city's alleged breach of the contracts and withholding of payments." S & D, 844
F.2d at 970. While I believe that S & D may be in error to the extent it denies
that the plaintiff's claim implicated a protected liberty interest, the instant case
provides an even stronger claim. Whereas the city defendant in S & D could
argue that the plaintiff was not entitled to the amounts that it alleged it had
already earned, HACC cannot make any such argument about its (arguably
unjustified) failure to return Linan-Faye's own performance bond. Also, when
HACC interfered with Linan-Faye's (pre-existing) capacity to obtain large
construction contracts, the core of its business, it brought this case into close
resemblance to those cases where the state actors are held liable under Sec.
1983 for revoking or interfering substantially with a person's license to pursue a
chosen occupation. Cf. Herz v. Degnan, 648 F.2d 201 (3d Cir.1981) (finding
violation of a property interest in the revocation of a professional license).
121 Without the use of its bonding line, Linan-Faye was paralyzed: It could not bid
on any significant contracts and thus could not replace the business lost through
the government's breach. Hence, because HACC's arguably unjustified
retention of the bond did impinge on protected liberty interests, the district
court erred by awarding the defendant summary judgment on this claim. I
therefore also dissent from the portion of the majority opinion that affirms this
ruling.

122 Before: SLOVITER, Chief Judge, BECKER, STAPLETON, MANSMANN,


GREENBERG, HUTCHINSON, SCIRICA, COWEN, NYGAARD, ALITO,
ROTH, LEWIS, MCKEE, SAROKIN and GARTH * , Circuit Judges.
SUR PETITION FOR REHEARING
March 13, 1995
The petition for rehearing filed by appellant having been submitted to the
123 judges who participated in the decision of this court and to all the other
available circuit judges of the circuit in regular active service, and no judge
who concurred in the decision having asked for rehearing, and a majority of the
circuit judges of the circuit in regular active service not having voted for
rehearing by the court in banc, the petition for rehearing is denied.

Paragraph 17 of this contract's General Conditions of the Contract for


Construction states in relevant part:
a. Subject to the approval of HUD, the performance of work under this contract
may be terminated by the PHA in accordance with this paragraph in whole, or
from time to time in part, whenever the Contracting Officer shall determine that
such termination is in the best interest of the PHA. Any such termination shall
be effected by delivery to the Contractor of a Notice of Termination specifying
the extent to which the performance of the work under the contract is
terminated, and the date upon which such termination becomes effective.
b. If the performance of the work is terminated, either in whole or in part, the
PHA shall be liable to the Contractor for reasonable and proper costs resulting
from such termination, which costs shall be paid to the Contractor within 90
days of receipt by the PHA of a properly presented claim setting out in detail:
(1) the total cost of the work performed to date of termination less the total
amount of contract payments made to the contractor ...; and (5) an amount
constituting a reasonable profit on the value of work performed by the
Contractor.
App.Vol. II at 45.

Linan-Faye styles its appeal as containing seven issues. Brief of Appellant at


ix-x. The first of these issues, according to Linan-Faye, is that the district court
engaged in impermissible fact finding on contested matters. Given our
conclusion concerning the application of the termination for convenience
clause, however, this issue is best resolved in conjunction with a discussion of

the proper application of that clause. See discussion infra part VI


3

Still another distinction exists between the instant case and the cases the district
court relied upon in applying federal common law to interpret this contract.
American Pipe & Steel and Taylor involved direct United States government
procurement contracts, or a subcontract with a United States government prime
contractor. American Pipe & Steel, 292 F.2d at 641; Taylor, 333 F.2d at 635.
Neither of these situations involved, as is the case here, the outright grant of
funds to a public agency. The closer nexus to the United States government in
American Pipe & Steel and Taylor heightens the federal government's interest.
The weaker link in this case diminishes the significance of the government
interest. Thus, the district court was incorrect in finding a government interest
significant enough to warrant deviating from Erie and applying federal common
law

Linan-Faye also cites Donovan v. Bachstadt, 91 N.J. 434, 453 A.2d 160 (1982),
for the proposition stated above. Further, Linan-Faye cites In Re Merritt Logan,
Inc., 901 F.2d 349, 357-58 (3d Cir.1990) and Sandler v. Lawn-A-Mat Chemical
& Equipment Corp., 141 N.J.Super. 437, 454, 358 A.2d 805 (A.D.),
certification denied, 71 N.J. 503, 366 A.2d 658 (1976), for the proposition that
the courts of New Jersey have long maintained a liberal rule of damages to a
non-breaching party

Additionally, the quoted language in Dobson represents only the opinion of a


single judge on this matter. The relevant issue was not addressed in the New
Jersey Supreme Court opinion affirming this case

Linan-Faye argues that decisions of the New Jersey Supreme Court such as
W.V. Pangborne & Co. v. New Jersey Dept. of Transportation, 116 N.J. 543,
562 A.2d 222 (1989), where the court has found against governmental entities,
are inconsistent with the broad discretion federal courts have conferred on the
government in cases concerning termination for convenience clauses.
Pangborne, however, involved a failure of a governmental entity to deal in good
faith. Id. at 562, 562 A.2d at 231 ("DOT's failure ... to deal expressly and
clearly with this material term constitutes a breach of an implied duty of good
faith and fair dealing and the supervening obligation of the government to deal
scrupulously with the public."). Federal common law also looks disfavorably
on the government in cases of governmental bad faith. See infra Part V.
Therefore, Linan-Faye's argument is unpersuasive

We recognize that the district court also applied federal common law to resolve
this dispute. Linan-Faye Construction Co. 847 F.Supp. at 1198. Nevertheless,
there is a difference between looking to federal common law as persuasive

authority and being bound by federal law. The district court opted for the latter
approach and determined that construction of the termination for convenience
clause was purely a matter of federal common law. In light of our previous
holding in Coastal General, 27 F.3d at 917, we opt for the former approach
8

HACC argues that the last paragraph of this letter which states that HACC has
"instructed the Modernization Office to assist [Linan-Faye] as needed in
obtaining release of [Linan-Faye's Bond]," App. at 115, is inconsistent with a
default termination because if HACC had terminated for a default it was
entitled to hold onto the bond. Just because HACC had the right to hold onto
the bond under the contract, however, does not mean that it intended to exercise
this right at the time of the letter. HACC may not have felt that the defaults it
cited, such as a failure to begin work, were compensable via the bond, or it may
have decided that it did not wish to encourage litigation over the bond issue. In
any event, this paragraph provides insufficient support for HACC's argument
that this letter constituted a termination for convenience

See discussion infra this part

10

HACC received a grant pursuant to the Public and Indian Housing


Comprehensive Improvement Assistance Program ("CIAP"). CIAP grants,
which are administered by HUD, require recipients to set forth various terms
and conditions in their agreements with contractors. 24 C.F.R. Sec. 968.110(j)
(1994). The regulations concerning CIAP grants, collected at 24 C.F.R. Sec.
85.1 et seq., differ from the FAR's applicable to direct government procurement
contracts. The CIAP grant regulations do not provide for a mandatory
conversion clause

11

The "government" involved in these cases is typically the United States


government. In the instant case, the entity seeking to terminate for convenience
is the Housing Authority of Camden. While the doctrine of constructive
termination for convenience originally developed to allow the United States
government maximum flexibility to deal with military contractors during times
of war, the expansion of this doctrine into areas other than those involving
military contracts suggests that its precepts should be applied to all government
entities that provide services to the public. Of course, the final word on this
issue rests with the New Jersey Supreme Court

12

Notably, the disagreement among the judges in that case was on the precise
issue of whether it was appropriate to create a stricter test for convenience
terminations by the government. Id. at 773-74 (Friedman, C.J., Davis, J., and
Nichols, J. concurring) While all the judges agreed on the result in that case,
the court could not muster a majority to embrace the new "changed

circumstances" test
13

Linan-Faye also cites a law review note written shortly after the Torncello
decision in support of its claims. Stephen N. Young, Note, Limiting the
Government's Ability to Terminate For Its Convenience Following Tornecello
[sic], 52 Geo.Wash.L.Rev. 892 (1984). In that note, the author suggests that
Torncello provides a reason to eliminate the government's right to
constructively terminate for convenience. Id. at 911. As this author was writing
without the benefit of recent decisions, all that can be said of his
recommendation is that future courts declined to take the hint

14

The dissent states that the majority "holds that a deterioration in business
relations, demonstrated in not insignificant part by a dispute over specifications,
constitutes such a change in circumstances." See infra at 937 (emphasis added).
The dissent is incorrect insofar as it reads this to be the holding of our decision.
As we have already explained, Torncello, and its changed circumstances
approach, has been sharply limited by more recent cases. See discussion supra
this Part. We have therefore declined to endorse wholeheartedly the changed
circumstances approach. Accordingly, an accurate statement of our position is
that (1) Linan-Faye has not demonstrated actual bad faith on the part of HACC
and (2) this case does not present the divisive facts presented in Torncello that
warranted finding against the government

15

At oral argument, Linan-Faye suggested that the application of paragraph 16(d)


of the General Conditions of this Contract "trumps" the constructive application
of the paragraph 17 termination for convenience clause. Paragraph 16(d) states,
in pertinent part:
The Contractor's right to proceed shall not be terminated or the Contractor
charged with damages under this clause if:
(1) The delay in completing the work arises from unforeseeable causes beyond
the control and without the fault or negligence of the Contractor. Examples of
such causes include (1) acts of God, or of the public enemy, (ii) acts of the
PHA or other governmental entity in either its sovereign or contractual capacity
(iii) acts of another contractor in the performance of a contract with the PHA
(iv) fires
....
App. Vol II at 45.
This subsection of paragraph 16 carves out an exception to when HACC can
terminate for default.

While Linan-Faye's argument goes to whether HACC breached the agreement


in terminating for default, it cannot prevent application of the constructive
termination for convenience doctrine. The very premise of the College Boat
decision is that a party may defend a suit for breach on the grounds that a legal
excuse existed at the time of the alleged breach. College Boat, 267 U.S. at 1516, 45 S.Ct. at 200-01. Thus, whether HACC breached its agreement by
terminating the contract for default is largely beside the point.
16

See supra note 1 for the text of paragraph 17

17

The district court also refers, in a footnote, to letters exchanged between the
parties that purportedly explain the understanding of the parties concerning the
definition of "work performed." The fact that the court goes beyond the contract
and looks to these letters to reinforce its conclusion demonstrates the
impropriety of granting summary judgment and the need to make such
decisions on a more fully developed record

18

Linan-Faye argues that it is entitled to damages because of HACC's improper


withholding of its performance bond both before and after termination.
Concerning Linan-Faye's claim for damages for pre-termination withholding of
the bond, we agree with the district court that such damages are not recoverable
because the termination for convenience clause controls and does not provide
for such recovery. Claims arising from events following termination, however,
would not be governed by the termination for convenience clause

19

We recognize that Linan-Faye's complaint in this matter does not set forth a
theory of recovery for damages due to improper retention of the performance
bond following termination. Indeed, the complaint could not set forth such a
theory because the events giving rise to this aspect of Linan-Faye's claim (i.e.,
HACC's continued refusal to relinquish the bond during the pendency of the
specific performance action) did not occur until after the complaint was filed.
Nevertheless, the district court made findings on this issue. Linan-Faye, 847
F.Supp. at 1205. Further, both parties briefed and argued the issue before this
Court and HACC did not argue that the issue was not properly before the
district court. Accordingly, we find it appropriate to set forth the applicable
theory of recovery on remand. On remand, the theory upon which damages
would be predicated is the common law action of detinue (or its modern
counterpart). According to the New Jersey Supreme Court, "[t]he gist of the
common law action of detinue was that [the] defendant originally had and
acquired possession of the chattels lawfully, as by finding or bailment, but
holds them subject to the plaintiff's superior right to immediate possession
which has been asserted by a demand." Baron v. Peoples National Bank of
Secaucus, 9 N.J. 249, 256, 87 A.2d 898, 901 (1952). At common law, the

appropriate remedy in a detinue action where property has been unlawfully


detained is a judgment for the value of the property and damages in detention.
Id
Here, HACC lawfully received Linan-Faye's performance bond pursuant to a
contract between the parties. Following termination, however, HACC's legal
right to retain the bond is the subject of the dispute that must be resolved on
remand. If the jury were to find HACC liable for improper retention of the
bond, the appropriate measure of damages would be compensation for jobs lost
by Linan-Faye (after termination) that resulted from HACC's improper action.
20

See infra Part V for analysis of the constructive termination for convenience
doctrine

I take no position on Parts VI.B through F and VIII of the majority opinion, as
they are outside the ambit of this effort, except to note that the discussion of
HACC's delay in invoking the termination for convenience clause, see Part
VIII, supports my views insofar as it highlights the dubiousness of HACC's ex
post reliance thereon

As my discussion explains, I believe that this result would follow even if New
Jersey were to look to federal law, for I do not think New Jersey would read
federal law so expansively as does the majority

As to panel rehearing

You might also like