Butler Armco Independent Union v. Armco Inc., A/K/A Armco Steel Corp., 701 F.2d 253, 3rd Cir. (1983)
Butler Armco Independent Union v. Armco Inc., A/K/A Armco Steel Corp., 701 F.2d 253, 3rd Cir. (1983)
Butler Armco Independent Union v. Armco Inc., A/K/A Armco Steel Corp., 701 F.2d 253, 3rd Cir. (1983)
2d 253
112 L.R.R.M. (BNA) 3022, 96 Lab.Cas. P 14,119
This appeal presents the question whether a district court may enjoin an
employer from consolidating two seniority units when a union alleges that the
issue in a current dispute is identical with one resolved in an earlier proceeding.
The district court declined to issue the injunction. We affirm.
A.
2
Plaintiff, the Butler Armco Independent Union, represents the hourly workers
in the Armco Steel Company plant in Butler, Pennsylvania. The workers are
assigned to seniority units, or departments. The portion of the collective
bargaining agreement that covers seniority unit issues generally is Article VIII,
Section C, paragraphs 1-3 ("C(1-3)"). Armco has, on occasion, attempted
Two of Armco's seniority units were known as the "Stores Department" and the
"Engineering Stores Department." The company wanted to merge these two
units, and apparently engaged in some preliminary negotiations on the subject
with the union. These talks did not produce an agreement. On or about April
22, 1982, Armco unilaterally merged the two departments. The merger, which
resulted in the transfer of three employees from the Stores Department to the
Engineering Stores Department, was, according to the company, part of a
reorganization which was to involve the relocation of three pieces of
equipment. At the present time, it may be that only one of the pieces has in fact
been moved; the record is unclear whether the other two pieces either have
been moved or will be moved later.
The union protested Armco's action by filing suit in district court to enjoin the
merger of the departments. Armco argued that the proper course for the union
to take in contesting the action was the grievance and arbitration procedure
outlined in the collective bargaining agreement. The union responded that the
merger question had already been resolved in arbitration, and that the failure of
the district court to enjoin the company would, in effect, defeat the previous
decisions in the union's favor, and reduce arbitration to a "hollow formality."
The district court concluded that Armco was not raising the same arguments in
a situation that was "materially the same" as prior arbitrations, and therefore,
Armco was not attempting to defeat its responsibilities under the previous
decisions. Consequently, the district judge refused to enjoin the department
merger, and instructed the union that if it wished to dispute the merger it would
have to take the matter to arbitration. A timely appeal was filed by the union.
B.
5
In labor law, arbitration is clearly the preferred method for resolving disputes
between the union and the employer. See Steelworkers v. American Mfg. Co.,
363 U.S. 564, 80 S.Ct. 1343, 4 L.Ed.2d 1403 (1960); Steelworkers v. Warrior
& Gulf Co., 363 U.S. 574, 80 S.Ct. 1347, 4 L.Ed.2d 1409 (1960); Steelworkers
v. Enterprise Wheel Corp., 363 U.S. 593, 80 S.Ct. 1358, 4 L.Ed.2d 1424 (1960)
(known collectively as the "Steelworkers' Trilogy"); Local 103 I.U.E. v. RCA
Corp., 516 F.2d 1336 (3d Cir.1975). Courts must therefore "tread gingerly
before intruding upon the arbitral process." Lewis v. AFSCME, 407 F.2d 1185,
1191 (3d Cir.) cert. denied, 396 U.S. 866, 90 S.Ct. 145, 24 L.Ed.2d 120 (1969).
While the rule of deferring to arbitration is generally well-understood,
problems arise in its application to a situation in which the action by one party
in a particular matter is similar to an action that an arbitrator had previously
ruled was prohibited by the collective bargaining agreement. If the court orders
the parties to arbitrate the new matter, it runs the risk of reading the prior
decision so narrowly that it becomes almost meaningless. On the other hand, by
ruling that the prior decision controls the case then before it, the court may be
arrogating to itself the role of contract interpreter which, under the
Steelworkers' Trilogy, should be left, at least in the first instance, to the
arbitrator.
6
Although not entirely free from doubt, it appears that the union relies on two
theories. First, it maintains that the current dispute is not arbitrable simply
because the same issue has been resolved in a prior arbitration. This argument
would appear to be foreclosed, however, by our holding in Metropolitan Edison
v. NLRB, 663 F.2d 478 (3d Cir.1981), cert. granted, --- U.S. ----, 102 S.Ct.
2926, 73 L.Ed.2d 1327 (1982), that, absent contractual language to the
contrary, one arbitrator's interpretation of a collective bargaining agreement is
not binding on a subsequent arbitrator. Second, the union urges that the
rearbitration clause in the contract renders the current dispute not arbitrable.
8
[N]o
provision in the contract removes a dispute over the interpretation or
application of the re-arbitration provision from the arbitration process. Therefore,
we cannot say "with positive assurance that the arbitration clause is not susceptible
of an interpretation that covers the asserted dispute." United Steelworkers v. Warrior
& Gulf Navigation Co., supra, 363 U.S. at 582-83, 80 S.Ct. at 1353. Consequently,
we conclude that it is for the arbitrator to evaluate the relevance and effect of the
[prior] arbitration award and opinion; it is for him to decide whether it qualifies "in
industrial common law", through "experience developed by reason and reason tried
and tested by experience," as the "same question or issue" presented by the
immediate grievance which therefore may not "be the subject of arbitration more
than once."
516 F.2d at 1340-41 (footnote omitted). 1
9
C.
10
We do not believe that the union has asserted that it is seeking to enforce the
terms of a prior arbitration award or settlement agreement. In such a situation,
the standard the district court would apply in determining whether to enforce
the initial award is whether it can be said "with positive assurance" that the
award or settlement agreement is intended to cover the current dispute. United
Mine Workers of America District No. 5 v. Consolidation Coal Company, 666
F.2d 806, 811 (3d Cir.1981)