Bianchi Trison Corporation v. Elaine L. Chao, Secretary of Labor, 409 F.3d 196, 3rd Cir. (2005)
Bianchi Trison Corporation v. Elaine L. Chao, Secretary of Labor, 409 F.3d 196, 3rd Cir. (2005)
Bianchi Trison Corporation v. Elaine L. Chao, Secretary of Labor, 409 F.3d 196, 3rd Cir. (2005)
3d 196
This matter is before this court on a petition for review in which the petitioner,
Bianchi Trison Corporation (hereinafter "BTC"), challenges the disposition of
administrative proceedings instituted by the Secretary of Labor arising from
safety and health problems that arose in the demolition, implosion, and cleanup of the Three Rivers Stadium in Pittsburgh, Pennsylvania.1 In response to a
complaint alleging unsafe conditions at the site, the Occupational Safety and
Health Administration (hereinafter "OSHA") made several inspections of the
stadium which uncovered conditions that caused the Secretary to bring an
enforcement action against BTC under the Occupational Safety and Health Act
(hereinafter the "OSH Act") setting forth three citations alleging 45 violations
of its standards and proposing substantial penalties. After a hearing, an
We set forth the factual history of the matter as developed at the hearing before
the ALJ. The City of Pittsburgh, through its Sports and Exhibition Authority
(hereinafter the "SEA"), owned the stadium. The SEA, in August 2000, issued
a request for bids for a contract to demolish the stadium. BTC was the
successful bidder, and, accordingly, the SEA awarded it the contract. The
demolition project was broken into three distinct phases: pre-implosion
demolition, implosion, and cleanup. In addition to engaging BTC, the SEA
utilized AMEC Construction Management (hereinafter "AMEC") as project
manager for the demolition and Makin Engineering to oversee contract
compliance. AMEC, in turn, hired Allegheny Asbestos Analysis d/b/a Global
Environmental Management to inspect the stadium for asbestos and hazardous
materials, other than lead. BTC, however, retained the responsibility for lead
abatement. Finally, as material in these proceedings, BTC contracted with
O'Rourke, Inc. to provide full-time, on-site oversight of all safety and health
aspects of the project, including OSHA compliance.
BTC started its work at the stadium on January 2, 2001. The pre-implosion
aspect of the contract required it to remove environmental hazards and prepare
the stadium for implosion. The SEA and AMEC planned a public auction of the
stadium's seats, freezers, and other stadium memorabilia during the preimplosion demolition period. The demand for stadium seats was greater than
expected, and in order to make seats available more quickly than it had thought
would be necessary, BTC directed laborers to torch the bolts off the seats.2 On
January 15, 2001, the memorabilia sale was conducted with the items sold to be
picked up by January 19, 2001.
January 29, 2001, and met with two local union representatives and examined
the safety protections, concluding that they were insufficient. After a meeting
at which McCall received an unsatisfactory response from BTC's project
manager, he and the union representatives filed a complaint with OSHA's
Pittsburgh Area Director, Robert Symanski.
5
The issuance of the safety citations, however, did not stop the project and by
early February, BTC had demolished most of the interior of the stadium. BTC
through a subcontractor imploded the stadium on February 11, 2001, following
which for a two-month period BTC processed and removed the remaining
concrete and steel debris. BTC assigned teams of employees to torch cut the
steel into smaller sizes in order to load them onto the trucks to be hauled away.
On February 14, the OSHA assistant area director, Edward Selker, assigned
two industrial hygienists to inspect the project for health hazards. But the next
day when the two hygienists went to the stadium to begin their inspection, BTC
denied them entry. The hygienists were able to gain entry to inspect the
premises only after contacting the SEA, which granted them permission to
inspect the premises. BTC, however, informed the hygienists that all burning
work had been suspended that day and thus they were only able to interview the
union steward, who indicated that employees had performed pre-implosion
torch burning and cutting.4 This revelation led to OSHA serving both an
administrative subpoena on BTC to secure records related to the pre-implosion
activities and an inspection warrant to conduct a full inspection. 5 Between
February 15 and February 21, BTC implemented a lead protection program at
the stadium, its first formal lead program at the site.6
OSHA made its full inspection on February 21, during which its inspectors
took bulk samples, did air monitoring, and conducted interviews. BTC
Though the Safety Case involved two citations and numerous infractions, the
only issues material to the Safety Case in these proceedings relate to fall
hazards and hazards relating to falling debris. In this regard, there were
allegations stemming from falling debris from BTC's demolition and removal of
the stadium's escalators, which BTC removed by burning each escalator's top
loose from its supports. Sometimes, when the workers cut an escalator loose, it
would not fall, and in that circumstance workers would use a machine to lower
it the floor below. After one of the first escalators fell, the work crew, in
conjunction with the union stewards, enclosed the areas below the escalators
with tape, as a warning not to enter.7
11
BTC contends that when an escalator did fall, it fell onto the concrete level
from which it had come and did not cause a risk danger to its employees. Three
BTC employees, however, testified about the risk from the failing debris, and
documented incidents in which different escalators fell two and four levels.
12
The BTC workers faced an additional risk during the pre-implosion period
when they were exposed to floor holes created by uncovered drain-pipes and
expansion joints.8 BTC employees testified that despite injuries and repeated
notifications to their supervisors about these dangers, BTC did not rectify the
violations.
13
14
The Health Case allegations are divided into pre-implosion exposure and postimplosion exposure violations. Ultimately, the ALJ concluded that the
Secretary had established that there were many OSH Act health violations, and
concluded that BTC engaged in "willful violations includ[ing] failure to make
an appropriate initial determination of lead exposure and to provide interim and
other protections from excessive lead exposure." App. at 17. The ALJ,
however, did not uphold all of the charges.9
1. Pre-Implosion Exposure
15
16
There was a second pre-implosion exposure when BTC employees torch cut
"notch-cuts" on lead-based painted structural steel beams. These cuts were
necessary to ensure that there was a complete cave-in at the time of the
implosion. Approximately four employees performed this task in ten-hour
shifts for varying degrees of duration.
17
18
19
20
OSHA Time
Weighted Average
(Time Sampled)
Date
Employee
BTC Time
Weighted Average
(Time Sampled)
2/21/2001
Shawn Cramer
36μg/m3
(321 min.)
36μg/m3
(234 min.)
2/21/2001
Kevin Opfar
259μg/m 3
(323 min.)
209μg/m3
(230 min.)
2/21/2001
Eric Yockey
318.6μg/m3
(317 min.)
975μg/m3
2/22/2001
Shawn Cramer
37μg/m3
(458 min.)
40μg/m3
2/22/2001
Kevin Opfar
954.4μg/m3
(318 min.)
2158μg/m 3
2/22/2001
Eric Yockey
615.1μg/m3
(464 min.)
1453μg/m 3
21
See app. at 69.10 It was thus evident that BTC had been operating with
insufficient safety precautions given the significant lead exposure risk.
22
23
The citations in the Health Case stem from BTC's failure to comply with the
Standard, see 29 C.F.R. 1926.62, which "applies to all construction work
where an employee may be occupationally exposed to lead." Id. Where
employees may be exposed to lead, the employer is required to perform an
"exposure assessment" to determine if any employee is exposed to lead "at or
above the action level." Section 1926.62(d)(1)(i). The action level is defined as
"employee exposure, without regard to the use of respirators, to an airborne
concentration of lead of 30 micrograms per cubic meter of air (30 μg/m3 )
calculated as an 8-hour time-weighted average." Section 1926.62(b).
24
25
BTC, however, did not monitor the potential exposure to lead at the stadium to
BTC utilized a lead assessment from its earlier National Starch and Chemical
Company demolition project (hereinafter called the "National Starch report")12
as the "historical data" for the stadium project, reasoning that the National
Starch project "closely resembled" the stadium project. The National Starch
project required BTC to demolish an old power house and drying facility inside
a corn starch factory complex in Indianapolis, Indiana. The National Starch
report showed exposures below the action level for workers torch cutting in that
project. BTC concluded that it was not required to perform initial monitoring
(or to take interim steps in lieu of monitoring) at the stadium because that
project "closely resembled" that at National Starch. Accordingly, BTC deemed
it necessary only to provide hand-washing facilities as protection against lead
exposure. BTC does not claim that it provided any protection against lead
exposure for employees who were torch cutting lead based paint between
January 4 and, at least, February 14. See petitioner's br. at 23; respondent's br.
at 31.
27
BTC's management first expressed concern over lead exposure on February 13,
and on February 14, 2001, BTC provided half-mask respirators but not airsupplied respirators to affected employees. It was not until February 16, a day
after BTC attempted to deny entry to the OSHA hygienists, that the first site
specific lead compliance program was drafted. The "plan" stated that BTC used
the National Starch report to determine that employees would not be exposed to
lead, and that there would be air monitoring.13
28
As we already have noted, the results from monitoring by both OSHA and BTC
revealed that there were lead exposure levels substantially greater than the
action level allowed. On February 20, 2001, O'Rourke, in response to the
sampling results, modified the compliance program to require additional
measures. The ALJ noted that, "[e]ven the final revised plan did not provide
sufficient detail concerning the engineering controls to be used, technology to
be used, air monitoring, or a schedule for compliance." App. at 96.
II. JURISDICTION
29
As we have indicated, the parties tried the case before an ALJ who upheld
most of the citations. BTC then filed a petition for discretionary review with the
Occupation Safety and Health Review Commission, which, on February 27,
2004, denied review and entered a final order. BTC then filed a petition for
review with this court on April 20, 2004.
30
III. DISCUSSION
A. Standard of Review
31
32
33
The first issue we address is "whether it was appropriate for BTC to use
`historical data' to make an `initial determination' that potential employee
exposure to lead was below the `action level' when torch burning operations
occurred during the pre-implosion and post-implosion phases of the demolition
of the stadium." Petitioner's br. at 10. The ALJ determined that BTC's use of
the National Starch report's "historical data" was not appropriate for making an
35
(i) Except as provided under paragraphs (d)(3)(iii) and (d)(3)(iv) of this section
the employer shall monitor employee exposures and shall base initial
determinations on the employee exposure monitoring results....
36
....
37
(iii) Where the employer has previously monitored for lead exposures, and the
data were obtained within the past 12 months during work operations
conducted under workplace conditions closely resembling the processes, type
of material, control methods, work practices, and environmental conditions
used and prevailing in the employer's current operations, the employer may rely
on such earlier monitoring results to satisfy the requirements of paragraphs (d)
(3)(i) and (d)(6) of this section if the sampling and analytical methods meet the
accuracy and confidence levels of paragraph (d)(10) of this section.
38
39
The ALJ first addressed the issue of whether the "historical data" method
represents an exception to monitoring, which is treated as the preferred means
of making an initial assessment, or, as BTC contends, whether the "historical
data" method is another valid, and equally accepted, method that an employer
can use to make the initial determination with respect to lead exposure. The
ALJ rejected BTC's contention and concluded that the "historical data" method
of making an initial assessment was an exception to the monitoring method.
Because she deemed the use of "historical data" to be an "exception" to the
preferred means to make an initial assessment, the ALJ placed the burden on
BTC to prove that its use of the "historical data" was appropriate. In reaching
her conclusion, the ALJ noted that, "[i]n general, exceptions in remedial
legislation, such as the OSH Act, must be narrowly construed." App. at 71.
40
The ALJ continued by noting that the phrase "closely resembling," contained
within the "historical data" exception, was not defined in the Standard. BTC
offered a broad interpretation of the phrase which relied on comparing "the
processes,"14 "the type of material,"15 "the control methods,"16 "the work
practices,"17 and "the environmental conditions"18 involved in the two projects.
Id. at 74. In addition, BTC denied that a comparison of materials between the
two projects required a gathering and testing of bulk paint samples.
41
The Secretary disagreed with BTC's broad interpretation of the phrase "closely
resembling." She noted that the "similarities suggested by BTC [were] too
superficial to meet an exception to a standard intended to protect employees
generating airborne lead." Id. The Secretary also asserted that BTC simply did
not have enough information to compare the two projects. In particular, she
observed that BTC had not taken bulk samples of the paint, nor made any other
attempts to secure data to make comparisons between the two sites.
42
The ALJ concluded that the term "closely resembling" was ambiguous. Thus,
she looked to the Standard's preamble to glean the Secretary's intent for
including the "historical data" exception. The ALJ found that the stated purpose
of the exception was for those situations where:
43
44
45
The ALJ held that, while the exception may not require an "absolute identity"
between projects, a case-by-case factual analysis was necessary. The ALJ
concluded that, "informed by the synonyms for `closely resembling' in the
preamble and the stated purpose of the exception, it is determined that BTC's
reliance on the historical data was incorrect." Id. The ALJ relied heavily on the
fact that BTC had not attempted to determine the lead content of the stadium,
and thus never bothered to discover "one component of what is necessarily a
two-part comparison." Id. She therefore concluded that, "BTC could not know
whether the lead-containing material at the two projects was `substantially
similar' or `essentially the same.'"19 Id. While bulk sampling would not always
be necessary, the ALJ determined that it was in this case.20 The ALJ concluded
that BTC's reliance on the historical data exception, therefore, was not
reasonable.
46
BTC urges that the ALJ erroneously concluded that the use of historical data to
make an initial lead assessment constitutes an exception to monitoring, and
thereby incorrectly elevated monitoring to the preferred method of performing
an initial determination. BTC contends that the use of historical data is not an
"exception," but is another acceptable, and equally viable method by which the
employer may make the initial determination. BTC continues by contending
that this "erroneous legal determination had significant negative consequences
for BTC because it permitted the ALJ to erroneously shift the burden of proof
on that issue from the Secretary to BTC." Petitioner's br. at 24. BTC also
asserts that because the ALJ deemed the use of "historical data" an exception to
the monitoring requirement, she erroneously narrowed the scope of what could
be deemed a permissible comparison site.
47
We reject BTC's contentions. The Commission and this court must accept the
Secretary's interpretation of the Standard if it is reasonable. See Martin, 499
U.S. at 150-52, 111 S.Ct. at 1175-76 (1991). The Secretary's interpretation of
the Standard, deeming the historical data exception as just that, i.e. an
exception to the monitoring mandate, clearly is reasonable. First, the plain
language of the Standard identifies the "historical data method" as an
exception: "Except as provided under paragraphs (d)(3)(iii) ...." 29 C.F.R.
1926.62(d)(3) (emphasis added); see also 29 C.F.R. 1926.62, Appendix B, II
(explaining that the "initial determination requires [the] employer to monitor
workers' exposure unless he or she has objective data which can demonstrate
conclusively that no employee will be exposed to lead in excess of the action
level") (emphasis added). Second, Congress intended in the OSH Act to protect
employees from the disastrous effects of lead exposure. The statute and
regulations repeatedly demonstrate a preference for the protection of
employees. See, e.g., 29 C.F.R. 1926.62(d)(2) (establishing presumption that
certain tasks, including torch cutting materials with lead based paint or coating,
results in exposures above the action level). It was clearly reasonable for the
Secretary to apply the statute and regulations in a manner so that the acquisition
of actual data on the potential exposure to lead through monitoring on the
current project, rather than reliance on data from an entirely separate project,
constitutes the preferred method of performing an initial assessment.
48
dissimilar that they could not be deemed to "closely resemble" one another
under any meaningful construction of that phrase. The ALJ, at length,
documented the differences between the two sites with respect to environmental
conditions and work practices.
49
While these differences are important factors that show dissimilarities, the
major focus must rest on a comparison of potential lead exposure. As the
results of the sampling revealed, there were wide inconsistencies between the
conditions at the National Starch project and those at the stadium predicated on
the differences between the actual level of lead exposure at the sites. To
highlight one glaring example, two bulk samples taken from the painted steel
beams at the National Starch site revealed 0.095 and 0.484 percent lead
content. At the stadium, the bulk samples of the seats ranged from 3.0 to 8.0
percent lead content, and the steel beams ranged from 2.2 to 43 percent lead
content. It is clear that conditions involving such divergent amounts of lead
cannot be deemed to "closely resemble" one another under any coherent
definition of that phrase.
50
The ALJ therefore correctly held that BTC's use of the National Starch report
as "historical data" to make the "initial determination" that potential employee
exposure to lead at the stadium was below the "action level" was inappropriate.
51
52
The next issue raised is whether there was substantial evidence in the record
supporting the ALJ's determination that BTC willfully violated the Standard.
The ALJ concluded that BTC's violations were "willful" because "[t]he record
establishe[d] that BTC had a heightened awareness of the cited requirements of
the lead standard yet chose to disregard them." App. at 108. She found that
BTC had heightened awareness of the presence of lead based on its experience
with comparable projects in which it dealt with lead and its having held itself
out to the public as an expert on lead and applicable OSHA standards.
Moreover, the ALJ indicated that "it is well known that torch burning and
cutting steel can generate high levels of airborne lead." Id. at 109-10.
53
In addition, the ALJ found that the Secretary independently also could have
established a willful violation by demonstrating "plain indifference" to
employee safety. The ALJ documented at length the instances in which BTC
ignored or deflected questions by its employees related to inquiries about lead,
and noted several occasions in which BTC denied its employees' requests for
safety equipment. App. at 111 (citing Fluor Daniel, Nos. 96-1729 and 96-1730,
19 O.S.H. Cas. (BNA) 1529 (2001), 2001 WL 1117965 (O.S.H.R.C.), aff'd sub
nom., Fluor Daniel v. Occupational Safety & Health Comm'n, 295 F.3d 1232
(11th Cir.2002) (employer who consciously chose to deprive employees of
emergency respirators committed willful violation)).
54
55
"Although the [OSH] Act does not define the term `willful,' courts have
unanimously held that a willful violation of the [OSH] Act constitutes `an act
done voluntarily with either an intentional disregard of, or plain indifference to,
the [OSH] Act's requirements.'" Ensign-Bickford Co. v. Occupational Safety &
Health Review Comm'n, 717 F.2d 1419, 1422 (D.C.Cir.1983) (quoting Cedar
Constr. Co. v. Occupational Safety & Health Review Comm'n, 587 F.2d 1303,
1305 (D.C.Cir.1978)); see also Ensign-Bickford, 717 F.2d at 1422 (citing nine
cases from courts of appeals embracing the "intentional disregard or plain
indifference" standard); Universal Auto Radiator Mfg. Co. v. Marshall, 631
F.2d 20, 23 (3d Cir.1980). Multiple violations of the lead standard can be
deemed willful where the employer manifested both intentional disregard for
the Standard and plain indifference to employee safety. See Interstate Lead Co.,
Nos. 89-2088P and 89-3296, 15 O.S.H. Cas. (BNA) 1989 (1992), 1992 WL
277025, at *29-32 (O.S.H.R.C.A.L.J.). We will uphold the Commission's
factual findings if they are supported by substantial evidence in the record as a
whole; whether a violation was willful is a question of fact. See Universal Auto,
631 F.2d at 23.
56
BTC asserts that there is not substantial evidence in the record to support the
findings that its violations were "willful." BTC raises three arguments to lend
credence to its purported lack of willfulness: (1) it did not engage in willful
conduct because it reasonably relied on O'Rourke's expert advice pertaining to
lead hazard; (2) the ALJ did not amply factor into her analysis the confusion
rendered by the Standard's ambiguity and incompleteness, resulting in a
violation that was more a misunderstanding than a willful violation; and (3)
after it discovered that it erroneously had relied on the National Starch report it
took steps to remedy the problem.
57
BTC's attempt to claim that its violations were not willful are unconvincing.
First, the ALJ correctly denied BTC's attempt to shift responsibility for the
violations to O'Rourke. The Commission previously had held that a company
cannot evade its safety and health responsibilities to its workers simply by
contracting away the responsibilities mandated under the OSH Act. See Well
Solutions, Inc., No. 91-340, 17 O.S.H. Cas. (BNA) 1211, 1214 (1995), 1995
WL 242595, at *3 (O.S.H.R.C.) ("[T]he [OSH] Act places ultimate
responsibility for compliance with its requirements on the employer, who
cannot contract away those duties to another party.")21 As the ALJ noted, BTC
has experience in the undertaking of demolition projects involving lead hazards.
In the circumstances, its claims of naivete as to the dangers of its course of
conduct, based on the suggestions of a small consulting firm, are dubious at
best. App. at 110. Considering that OSHA employees ascertained BTC's safety
failures by watching the local nightly news, its claims of ignorance are
unconvincing.
58
59
BTC next argues that its failings were not "willful," but rather stemmed from
the ambiguity and incompleteness in the regulations. In an attempt to
demonstrate this point, BTC cites 29 C.F.R. 1926.62(d)(3)(iii) (emphasis
added):
60
(iii) Where the employer has previously monitored for lead exposures, and the
data were obtained within the past 12 months during work operations
conducted under workplace conditions closely resembling the processes, type
of material, control methods, work practices, and environmental conditions
used and prevailing in the employer's current operations, the employer may rely
on such earlier monitoring results to satisfy the requirements of paragraphs (d)
(3)(i) and (d)(6) of this section if the sampling and analytical methods meet the
62
63
BTC argues that the ALJ's finding of willfulness was erroneous because,
"nowhere in her decision does she take into account the potential for mistake
the ambiguity and incompleteness of the standard would create for a
layperson." Petitioner's br. at 33. BTC continues by arguing that "willfulness
should not be found where the standard is complex and not perfectly clear and a
violation resulted in negligence and misunderstanding rather than intentional
disregard or plain indifference." Id. at 34.
64
65
66
Finally, BTC claims that its violations were not willful, as witnessed by the
steps it undertook to alleviate exposure after the level of lead was discovered.
The ALJ correctly rejected this claim as well. BTC, in fact, did not take steps to
alleviate the valid concerns of its employees during the pre-implosion phase of
the demolition. Moreover, the steps it took in response to the OSHA inspection
were inadequate, and continued to violate unambiguous standards of the
applicable OSH Act provisions and regulations. For example, rather than
suspend burning or prospectively comply with the OSH Act's mandates, BTC
gave its employees half-mask respirators, not the required mandated airsupplied respirators. Additionally, BTC did not (1) advise its employees in
writing of its "negative determination"; (2) failed to advise employees of their
blood test results; (3) failed to use known engineering controls to reduce
exposures; and (4) failed even to post a warning sign. There clearly was
substantial evidence in the record supporting the ALJ's determination that BTC
willfully violated OSHA's lead standards.
C. The Safety Case
1. The "Cutting" of Escalators
67
BTC next asserts that the ALJ erred in holding that "dropping" the escalators
without proper safety measures violated 29 C.F.R. 1926.850(h). The violation
at issue arose when BTC "cut" escalators, i.e., "when the top of the escalator
was released, on some occasions it would fall to the floor unexpectedly."
Petitioner's br. at 47. The regulations at issue provide:
68
(h) When debris is dropped through holes in the floor without the use of chutes,
the area onto which the material is dropped shall be completely enclosed with
barricades not less than 42 inches high and not less than 6 feet back from the
projected edge of the opening above. Signs, warning of the hazard of falling
materials, shall be posted at each level. Removal shall not be permitted in this
lower area until debris handling ceases above.
69
(i) All floor openings, not used as material drops, shall be covered over with
material substantial enough to support the weight of any load which may be
imposed. Such material shall be properly secured to prevent its accidental
movement.
70
71
BTC asserts that the ALJ erred in determining that subparagraph (h) was
applicable to the escalator drops, because the escalators were not "debris ...
dropped through holes in the floor without the use of chutes." See petitioner's
br. at 47. BTC's argument is simply that there were no "holes," because despite
the potential crashing of escalators to the surfaces below, it was the removal of
the escalators that "created" the holes.22
72
BTC's contention that the ALJ inappropriately applied the regulation to the
falling escalators is simply erroneous. The ALJ was correct in her assessment
that "whether or not BTC specifically created the escalator and elevator holes
for removal of debris is irrelevant. BTC specifically used the holes for removal
of debris." App. at 56 (emphasis in original).23 It clearly is reasonable to
interpret the regulation so as to recognize that an escalator falling only one
floor, even through the hole in which it originally stood, creates the precise
hazard against which the standard required BTC to protect. The fact that the
hole was not "preexisting" is immaterial. The Commission's and Secretary's
interpretation of section 1926.850(h) "sensibly conforms to the words and
purpose of the standard" and therefore we must uphold it. See Martin, 499 U.S.
at 151, 111 S.Ct. at 1176.
73
74
BTC also contends that there is not substantial evidence in the record as a
whole to support the ALJ's determination that certain violations relating to fall
hazards and hazards relating to falling debris were willful. The ALJ concluded
that in light of BTC's experience with and knowledge of OSHA requirements,
as well as evidence demonstrating BTC's knowledge of these hazards
(demonstrated by its own employees' complaints), BTC acted willfully with
respect to both the fall hazards, as well as the hazards from falling debris. BTC
argues that the ALJ's determination that these violations were willful was
unfounded.
75
76
The final issue BTC raises is that "[t]he ALJ allowed the Secretary to proffer
expert testimony in derogation of Rule 26 of the Rules of Civil Procedure."
Petitioner's br. at 25. The OSH Act provides that the Federal Rules of Civil
Procedure apply to actions before the Commission unless the Commission has
adopted an applicable procedural rule. 29 U.S.C. 661(g); 29 C.F.R.
2200.2(b). While the Commission has adopted procedural rules governing
discovery, these rules do not address expert testimony specifically. See 29
C.F.R. 2200.51-2200.57.
77
On January 28, 2002, the ALJ issued an order setting the date of the hearing
for March 20, 2002. Discovery was set to end ten days prior to the start of that
hearing. During a February 5, 2002 teleconference, the ALJ rescheduled the
hearing for June 3, 2002. At that time the ALJ directed the parties to comply
with Fed.R.Civ.P. 26.
78
79
It is without dispute that the Secretary did not comply with the 90-day
requirement.24 See petitioner's br. at 26; respondent's br. at 47. On these
grounds, BTC challenges the ALJ's decision to allow the testimony of John
Cignatta, Raymond Feldman, Dr. Cortinovis, Compliance Officer Jan
Oleszeweski, and Assistant Area Director Edward Selker.
80
BTC's claims, however, are without merit as it does not demonstrate that the
ALJ's decision to allow the testimony in question prejudiced it. Cignatta and
Cortinovis, the witnesses with whom that BTC takes the most umbrage,
testified on a number of points, none of which was in contention. BTC never
disputed the fact that overexposure to lead poses a "serious" hazard, nor was
their testimony essential to establish the violations at issue. Indeed, BTC's own
testing revealed unacceptably high lead exposure at the stadium and,
accordingly, its erroneous reliance on the National Starch report as historical
data.
81
The Secretary offered the testimony of the other witnesses BTC challenged to
After a complete examination of this matter we are satisfied that the points
BTC has raised lack sufficient merit and thus we will deny its petition for
review of the February 27, 2004 order.
Notes:
1
BTC is a New York State Corporation with its headquarters in Syracuse, New
York
The violations now at issue stemming from the Safety Case arose from BTC's
failure to protect employees from hazards related to floor openings and falling
debris
OSHA and BTC concurrently took bulk paint samples at various locations in
the stadium on February 15
On February 16, 2001, after OSHA obtained the inspection warrant, the two
hygienists returned to the site. But due to rain, BTC's safety consultant advised
OSHA that BTC had shut down the burning work until further notice. OSHA
and BTC then reached an agreement providing for BTC to notify OSHA when
O'Rourke conceded that BTC did not have a written lead compliance plan
before February 16, 2001
Certain of the charges not upheld were duplicative or involved conduct that was
not willful
10
Shawn Cramer was a working foreman who served as fire watch for the
employees engaged in burning tasks. Though he was not overexposed on either
day of the monitoring, he did not engage in burning work; however, his
sampling results did indicate that he was exposed at more than the action level
and half of the permissible exposure limit
11
(A).
12
The report also was labeled the "Act report" because BTC hired ACT
Environmental Services, Inc. to perform the exposure assessment of the
National Starch demolition project. We call it the "National Starch report" for
clarity purposes
13
14
15
16
Neither project required any control methods, other than "normal [personal
protective equipment], including [a] 3 foot Torch." App. at 74
17
Both projects required notch cuts to be made on the steel during 10 hour shifts
18
Both projects required performing the work in the open air during cold weather
19
The ALJ noted that the characteristics of lead paint could not be assumed to be
the same
20
The ALJ also noted that the methods, work practices, and environmental
factors differed to varying degrees as well
21
BTC relies heavily onSasser Electric & Manufacturing Co., No. 82-178, 11
O.S.H. Cas. (BNA) 2113 (1984), 1984 WL 34886 (O.S.H.R.C.). In Sasser, a
crane operator accidentally swung the boom of the crane into nearby power
lines. The Commission held that the general contractor reasonably had relied on
the safety efforts of the crane company with which it subcontracted, because:
(1) the cited hazard dealt with the operation of a crane and fell within the
expertise of the subcontractor; (2) the subcontractor had exclusive control over
the hazard; (3) the general contractor had warned the subcontractor of the
closeness of the power lines; and (4) considering that the subcontractor had
performed the same work previously without incident, there was no reason for
the general contractor to have foreseen that the crane operator would have
swung the boom into the power lines. Sasser, 1984 WL 34886, at *3.
This case is plainly distinguishable from Sasser. BTC is claiming that it
contracted away its responsibility with respect to OSHA requirements by hiring
an environmental and safety consulting firm. But, unlike the situation in Sasser,
BTC's employees still were performing the labor, and BTC as a company
operated the equipment significant in the context of this case. This situation
also is different from that in Sasser because in that case the general contractor,
by reason of its lack of expertise, contracted out a particular task to an
independent contractor who was expected to perform that discrete function
fully.
22
BTC contends that "[t]here was no `shaft' where heavy machinery fell into. To
the contrary, the escalator top, once unhinged,merely dropped to the level
where the foot of the escalator rested." Petitioner's br. at 49 (emphasis added).
23
We do not discuss separately the elevator situation, but we conclude that the
ALJ did not err in her findings with respect to it
24
The Secretary contends that she was not required to abide by the 90-day
disclosure requirement because the January 28, 2002 scheduling order set the
"discovery deadline" for ten days before trialSee respondent's br. at 46-47. The
Secretary argues that the ten-day deadline represents "other directions from the
court" and therefore the 90-day period was inapplicable. BTC contends that "no
such argument was advanced at trial and, as such, was not preserved for
appeal." Petitioner's reply br. at 10. We need not address this point as BTC does
not demonstrate how the procedure permitting the introduction of the testimony
at issue prejudiced it.