Scrum Open Practice Test

The document summarizes the results of a Scrum Open assessment completed by the test-taker. They scored 28 out of 30 points (93.3%) and completed the assessment in 00:29:07. The feedback congratulates them on their score and says it demonstrates knowledge of some basic Scrum principles. It provides feedback on individual questions answered incorrectly.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
360 views17 pages

Scrum Open Practice Test

The document summarizes the results of a Scrum Open assessment completed by the test-taker. They scored 28 out of 30 points (93.3%) and completed the assessment in 00:29:07. The feedback congratulates them on their score and says it demonstrates knowledge of some basic Scrum principles. It provides feedback on individual questions answered incorrectly.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17

8/9/2016

Finished.

Title: ScrumOpen
Points: 28outof30
Percentage: 93.3%
Duration: 00:29:07
Datestarted: Tue9thAug201612:22pm
Datefinished: Tue9thAug201612:51pm

Feedback
Congratulations!YourscoreontheOpenassessmentdemonstratesyouknowsomeScrumbasics.
Scrumon,
KenSchwaber

Correctlyanswered

Incorrectlyanswered

Missedcorrectmultiplechoiceoption

Question1of30
ThetimeboxforaDailyScrumis?
Correctanswer:D)
Youchose:D)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) Thesametimeofdayeveryday.

B) Twominutesperperson.

C) 4hours.
D) 15minutes.

E) 15minutesfora4weeksprint.ForshorterSprintsitisusuallyshorter.

https://www.classmarker.com/onlinetest/results/

1/17

8/9/2016

Finished.

Points:1outof1
Feedback
ThelengthofadailyScrumisfixedat15minutes,itdoesnotchangewiththelengthofaSprint.

Question2of30
Whenmultipleteamsworktogetheronthesameproduct,eachteamshould
maintainaseparateProductBacklog.
Correctanswer:B)
Youchose:B)

A) True
B) False

Points:1outof1
Feedback
ProductshaveoneProductBacklog,regardlessofhowmanyteamsareused.Anyothersetupmakesit
difficultfortheDevelopmentTeamtodeterminewhatitshouldworkon.

Question3of30
Whatdoesitmeantosaythataneventhasatimebox?
Correctanswer:D)
Youchose:D)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) Theeventmusthappenatasettime.

B) Theeventmusthappenbyagiventime.

C) Theeventmusttakeatleastaminimumamountoftime.
D) Theeventcantakenomorethanamaximumamountoftime.

Points:1outof1
Feedback
https://www.classmarker.com/onlinetest/results/

2/17

8/9/2016

Finished.

Timeboxedeventsareeventsthathaveamaximumduration.

Question4of30
DuringtheDailyScrum,theScrumMaster'sroleisto:
Correctanswer:D)
Youchose:D)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) LeadthediscussionsoftheDevelopmentTeam.

B) Makesurethatall3questionshavebeenanswered.

C) Managethemeetinginawaythateachteammemberhasachancetospeak.
D) TeachtheDevelopmentTeamtokeeptheDailyScrumwithinthe15minutetimebox.

E) Allanswersapply.

Points:1outof1
Feedback
TheScrumMasterensuresthattheDevelopmentTeamhasthemeeting,buttheDevelopmentTeamis
responsibleforconductingtheDailyScrum.TheScrumMasterteachestheDevelopmentTeamtokeep
theDailyScrumwithinthe15minutetimebox.TheScrumMasterenforcestherulethatonlyDevelopment
TeammembersparticipateintheDailyScrum.

Question5of30
TheDevelopmentTeamshouldnotbeinterruptedduringtheSprint.TheSprint
Goalshouldremainintact.Theseareconditionsthatfostercreativity,qualityand
productivity.Basedonthis,whichofthefollowingisFALSE?
Correctanswer:B)
Youchose:B)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) TheProductOwnercanhelpclarifyoroptimizetheSprintwhenaskedbythe
DevelopmentTeam.
B) TheSprintBacklogisfullyformulatedintheSprintPlanningmeetinganddoesnotchange
duringtheSprint.

C) AsadecompositionoftheselectedProductBacklogItems,theSprintBacklogchanges
andmaygrowastheworkemerges.

https://www.classmarker.com/onlinetest/results/

3/17

8/9/2016

Finished.

D) TheDevelopmentTeammayworkwiththeProductOwnertoremoveoraddworkifit
findsithasmoreorlesscapacitythanitexpected.

Points:1outof1
Feedback
TheSprintBacklogmakesvisiblealloftheworkthattheDevelopmentTeamidentifiesasnecessaryto
meettheSprintGoal.TheDevelopmentTeammodifiestheSprintBacklogthroughouttheSprint,andthe
SprintBacklogemergesduringtheSprint.

Question6of30
DevelopmentTeammembershipshouldchange:
Correctanswer:C)
Youchose:C)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) EverySprinttopromotesharedlearning.

B) Never,becauseitreducesproductivity.
C) Asneeded,whiletakingintoaccountashorttermreductioninproductivity.

D) Asneeded,withnospecialallowanceforchangesinproductivity.

Points:1outof1
Feedback
Teamstypicallygothroughsomestepsbeforeachievingastateofincreasedperformance.Changing
membershiptypicallyreducescohesion,affectingperformanceandproductivityintheshortterm.

Question7of30
WhichstatementbestdescribestheSprintReview?
Correctanswer:B)
Youchose:B)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) ItisamechanismtocontroltheDevelopmentTeam'sactivitiesduringaSprint.

https://www.classmarker.com/onlinetest/results/

4/17

8/9/2016

Finished.

B) ItiswhentheScrumTeamandstakeholdersinspecttheoutcomeofaSprintandfigure
outwhattodonext.

C) ItisademoattheendoftheSprintforeveryoneintheorganizationtocheckonthework
done.

Points:1outof1
Feedback
EveryeventinScrum,besidestheSprintwhichisacontainerfortheotherevents,isanopportunityto
InspectANDAdapt.

Question8of30
WhenmanyDevelopmentTeamsareworkingonasingleproduct,whatbest
describesthedefinitionof"done?"
Correctanswer:C)
Youchose:C)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) EachDevelopmentTeamdefinesandusesitsown.Thedifferencesarediscussedand
reconciledduringahardeningSprint.

B) EachDevelopmentTeamusesitsownbutmustmaketheirdefinitioncleartoallother
Teamssothedifferencesareknown.
C) AllDevelopmentTeamsmusthaveadefinitionof"done"thatmakestheircombinedwork
potentiallyreleasable.

D) Itdepends.

Points:1outof1
Feedback
ScrumrequiresanIncrementtobereleasable.ThisisanIncrementofproduct.Manyteamsworkingona
singleproductareexpectedtodeliversuchanIncrement.

Question9of30
WhatistheroleofManagementinScrum?

https://www.classmarker.com/onlinetest/results/

5/17

8/9/2016

Finished.

Correctanswer:C)
Youchose:C)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) ContinuallymonitorstaffinglevelsoftheDevelopmentTeam.

B) MonitortheDevelopmentTeam'sproductivity.
C) SupporttheProductOwnerwithinsightsandinformationintohighvalueproductand
systemcapabilities.SupporttheScrumMastertocauseorganizationalchangethat
fostersempiricism,selforganization,bottomupintelligence,andintelligentreleaseof
software.

D) Identifyandremovepeoplethataren'tworkinghardenough.

Points:1outof1
Feedback
ManagementhasnoactiveroleintheactualproductdevelopmentthroughScrum.However,management
externaltotheScrumteamisincrediblyimportantinsettingthevisionandstrategytoguidetheoverall
directionoftheorganization.

Question10of30
ThelengthofaSprintshouldbe:
Correctanswer:D)
Youchose:D)

A) ShortenoughtokeepthebusinessriskacceptabletotheProductOwner.

B) Shortenoughtobeabletosynchronizethedevelopmentworkwithotherbusiness
events.

C) Nomorethanonemonth.
D) Alloftheseanswersarecorrect.

Points:1outof1
Feedback
AllofthesechoicesareappropriateconsiderationsindeterminingthelengthofaSprint.

Question11of30
https://www.classmarker.com/onlinetest/results/

6/17

8/9/2016

Finished.

DuringaSprint,aDevelopmentTeamdeterminesthatitwillnotbeabletofinish
thecompleteforecast.WhoshouldbepresenttoreviewandadjusttheSprint
workselected?
Correctanswer:B)
Youchose:B)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) TheScrumMaster,theprojectmanagerandtheDevelopmentTeam.
B) TheProductOwnerandtheDevelopmentTeam.

C) TheProductOwnerandallstakeholders.

D) TheDevelopmentTeam.

Points:1outof1
Feedback
DuringtheSprint,scopemaybeclarifiedandrenegotiatedbetweentheProductOwnerandDevelopment
Teamasmoreislearned.

Question12of30
WhyistheDailyScrumheldatthesametimeandsameplace?
Correctanswer:B)
Youchose:B)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) Theplacecanbenamed.
B) Theconsistencyreducescomplexity.

C) TheProductOwnerdemandsit.

D) Roomsarehardtobookandthisletsitbebookedinadvance.

Points:1outof1
Feedback
TheDailyScrumisheldatthesametimeandplaceeachdaytoreducecomplexity.

Question13of30
https://www.classmarker.com/onlinetest/results/

7/17

8/9/2016

Finished.

ThemaximumlengthoftheSprintReview(itstimebox)is:
Correctanswer:B)
Youchose:B)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) 2hours.
B) 4hoursforamonthlySprint.ForshorterSprintsitisusuallyshorter.

C) Aslongasneeded.

D) 1day.

E) 4hoursandlongerasneeded.

Points:1outof1
Feedback
SprintReviewisafourhourtimeboxedmeetingforonemonthSprints.ForshorterSprints,theeventis
usuallyshorter.

Question14of30
ThetimeboxfortheSprintPlanningmeetingis?
Correctanswer:B)
Youchose:B)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) 4hours.
B) 8hoursforamonthlySprint.ForshorterSprintsitisusuallyshorter.

C) Wheneveritisdone.

D) Monthly.

Points:1outof1
Feedback
SprintPlanningistimeboxedtoamaximumofeighthoursforaonemonthSprint.ForshorterSprints,the
eventisusuallyshorter.

Question15of30
https://www.classmarker.com/onlinetest/results/

8/17

8/9/2016

Finished.

TheDevelopmentTeamshouldhavealltheskillsneededto:
Correctanswer:C)
Youchose:C)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) CompletetheprojectasestimatedwhenthedateandcostarecommittedtotheProduct
Owner.

B) Doallofthedevelopmentwork,exceptforspecializedtestingthatrequiresadditional
toolsandenvironments.
C) TurntheProductBacklogitemsitselectsintoanincrementofpotentiallyreleasable
productfunctionality.

Points:1outof1
Feedback
TheDevelopmentTeamconsistsofprofessionalswhodotheworkofdeliveringapotentiallyreleasable
Incrementof"Done"productattheendofeachSprint.DevelopmentTeamsarecrossfunctional,withallof
theskillsasateamnecessarytocreateaproductIncrement.

Question16of30
TheCEOaskstheDevelopmentTeamtoadda"veryimportant"itemtoaSprint
thatisinprogress.WhatshouldtheDevelopmentTeamdo?
Correctanswer:D)
Youchose:D)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) AddtheitemtothecurrentSprintwithoutanyadjustments.

B) AddtheitemtothecurrentSprintanddropanitemofequalsize.

C) AddtheitemtothenextSprint.
D) InformtheProductOwnersohe/shecanworkwiththeCEO.

Points:1outof1
Feedback
TheitemsselectedforaSprinthavebeenselectedasmostvaluablewiththeProductOwner.Theitems
servetheSprint'sgoal.NochangesshouldbemadethatendangertheSprintGoal.Nooneexternaltothe
ScrumTeamcanforcechangesontheDevelopmentTeam(SprintBacklog)andtheProductOwner
(ProductBacklog).
https://www.classmarker.com/onlinetest/results/

9/17

8/9/2016

Finished.

Question17of30
WhichstatementbestdescribesScrum?
Correctanswer:C)
Youchose:C)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) Acompletemethodologythatdefineshowtodevelopsoftware.

B) Acookbookthatdefinesbestpracticesforsoftwaredevelopment.
C) Aframeworkwithinwhichcomplexproductsincomplexenvironmentsaredeveloped.

D) AdefinedandpredictiveprocessthatconformstotheprinciplesofScientific
Management.

Points:1outof1
Feedback
Scrumisnotaprocessoratechniqueforbuildingproductsrather,itisaframeworkwithinwhichyoucan
employvariousprocessesandtechniques.

Question18of30
ThepurposeofaSprintistoproduceadoneincrementofworkingproduct.
Correctanswer:A)
Youchose:A)

A) True

B) False

Points:1outof1
Feedback
TheheartofScrumisaSprint,atimeboxofonemonthorlessduringwhicha"Done",usable,and
potentiallyreleasableproductIncrementiscreated.

https://www.classmarker.com/onlinetest/results/

10/17

8/9/2016

Finished.

Question19of30
WhendoDevelopmentTeammembersbecometheexclusiveownerofaSprint
Backlogitem?
Correctanswer:B)
Youchose:B)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) AttheSprintplanningmeeting.
B) Never.AllSprintBacklogItemsare"owned"bytheentireDevelopmentTeam,even
thougheachonemaybedonebyanindividualdevelopmentteammember.

C) Wheneverateammembercanaccommodatemorework.

D) DuringtheDailyScrum.

Points:1outof1
Feedback
SprintBacklogandallofitsitemsarecollectivelyownedbytheDevelopmentTeam.Noindividualteam
membercanclaimownershipoveranitemasthiswouldblockcommunicationandcollaboration.

Question20of30
Whichtwo(2)thingsdoestheDevelopmentTeamdoduringthefirstSprint?
Correctanswer:A)C)
Youchose:B)D)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) Deliveranincrementofreleasablesoftware.
B) Determinethecompletearchitectureandinfrastructurefortheproduct.
C) Developanddeliveratleastonepieceoffunctionality.
D) Developaplanfortherestoftherelease.

E) CreatethecompleteProductBacklogtobedevelopedinsubsequentSprints.

Youdidnotselectallavailablecorrectoptions.

Points:0outof1
Feedback

https://www.classmarker.com/onlinetest/results/

11/17

8/9/2016

Finished.

TheheartofScrumisaSprint,atimeboxofonemonthorlessduringwhicha"Done",useable,and
potentiallyreleasableproductIncrementiscreated.ThisappliestoeverySprint

Question21of30
WhoisresponsibleformanagingtheprogressofworkduringaSprint?
Correctanswer:A)
Youchose:C)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) TheDevelopmentTeam

B) TheScrumMaster
C) TheProductOwner

D) ThemostjuniormemberoftheTeam

Points:0outof1
Feedback
TheDevelopmentTeamusestheDailyScrumtoinspectprogresstowardtheSprintGoalandtoinspect
howprogressistrendingtowardcompletingtheworkintheSprintBacklog.

Question22of30
TheProductBacklogisorderedby:
Correctanswer:E)
Youchose:E)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) Size,wheresmallitemsareatthetopandlargeitemsareatthebottom.

B) Risk,wheresaferitemsareatthetop,andriskieritemsareatthebottom

C) Leastvaluableitemsatthetoptomostvaluableatthebottom.

D) Itemsarerandomlyarranged.
E) WhateverisdeemedmostappropriatebytheProductOwner.

Points:1outof1

https://www.classmarker.com/onlinetest/results/

12/17

8/9/2016

Finished.

Feedback
TheProductOwnerdecideswhatmakesthemostsensetooptimizethevalueoftheworkbeingdoneby
theDevelopmentTeam.

Question23of30
AnorganizationhasdecidedtoadoptScrum,butmanagementwantstochange
theterminologytofitwithterminologyalreadyused.Whatwilllikelyhappenifthis
isdone?
Correctanswer:D)
Youchose:D)

A) Withoutanewvocabularyasareminderofthechange,verylittlechangemayactually
happen.

B) TheorganizationmaynotunderstandwhathaschangedwithScrumandthebenefitsof
Scrummaybelost.

C) Managementmayfeellessanxious.
D) Allanswersapply.

Points:1outof1

Question24of30
Whoshouldknowthemostabouttheprogresstowardabusinessobjectiveora
release,andbeabletoexplainthealternativesmostclearly?
Correctanswer:A)
Youchose:A)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) TheProductOwner

B) TheDevelopmentTeam

C) TheScrumMaster

D) TheProjectManager

Points:1outof1
Feedback

https://www.classmarker.com/onlinetest/results/

13/17

8/9/2016

Finished.

TheProductOwneristhesolepersonresponsibleformanagingtheProductBacklog,whichincludesthat
theProductBacklogisvisible,transparent,andcleartoall,andshowswhattheScrumTeamwillworkon
next.

Question25of30
WhatisthemainreasonfortheScrumMastertobeattheDailyScrum?
Correctanswer:B)
Youchose:B)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) Tomakesureeveryteammemberanswersthethreequestions.
B) HeorshedoesnothavetobethereheorsheonlyhastoensuretheDevelopment
TeamhasaDailyScrum.

C) TowritedownanychangestotheSprintBacklog,includingaddingnewitems,and
trackingprogressontheburndown.

D) Togatherstatusandprogressinformationtoreporttomanagement.

Points:1outof1
Feedback
TheScrumMasterenforcestherulethatonlyDevelopmentTeammembersparticipateintheDailyScrum.

Question26of30
WhatarethetwoprimarywaysaScrumMasterkeepsaDevelopmentTeam
workingatitshighestlevelofproductivity?
Correctanswer:A)B)
Youchose:A)B)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) ByfacilitatingDevelopmentTeamdecisions
B) ByremovingimpedimentsthathindertheDevelopmentTeam

C) Bystartingandendingthemeetingsatthepropertime

D) BykeepinghighvaluefeatureshighintheProductBacklog

Points:1outof1
https://www.classmarker.com/onlinetest/results/

14/17

8/9/2016

Finished.

Feedback
AScrumMasterisaservantleaderfortheDevelopmentTeam.Facilitationandremovingimpediments
servesateaminachievingthebestproductivitypossible.

Question27of30
Thethreepillarsofempiricalprocesscontrolare:
Correctanswer:C)
Youchose:C)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) RespectForPeople,Kaizen,EliminatingWaste

B) Planning,Demonstration,Retrospective
C) Inspection,Transparency,Adaptation

D) Planning,Inspection,Adaptation

E) Transparency,EliminatingWaste,Kaizen

Points:1outof1
Feedback
Scrumisfoundedonempiricalprocesscontroltheory,orempiricism.Empiricismassertsthatknowledge
comesfromexperienceandmakingdecisionsbasedonwhatisknown.
Threepillarsupholdeveryimplementationofempiricalprocesscontrol:transparency,inspection,and
adaptation.

Question28of30
WhohasthefinalsayontheorderoftheProductBacklog?
Correctanswer:D)
Youchose:D)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) TheStakeholders

B) TheDevelopmentTeam

C) TheScrumMaster
D) TheProductOwner

https://www.classmarker.com/onlinetest/results/

15/17

8/9/2016

Finished.

E) TheCEO

Points:1outof1
Feedback
TheProductOwneristhesolepersonresponsibleformanagingtheProductBacklog.

Question29of30
WhoisontheScrumTeam?
Correctanswer:A)B)C)
Youchose:A)B)C)

A) TheScrumMaster
B) TheProductOwner
C) TheDevelopmentTeam

D) ProjectManager

E) Noneoftheabove

Points:1outof1
Feedback
TheScrumTeamconsistsoftheScrumMaster(managestheprocess),theProductOwner(decideswhat
todo)andtheDevelopmentTeam(doesthework).

Question30of30
WhichofthebelowarerolesonaScrumTeam?
Correctanswer:A)D)E)
Youchose:A)D)E)
Note:ThisquestiondisplayedansweroptionsinrandomorderwhentakingthisTest.

A) DevelopmentTeam

B) Users

C) Customers
D) ProductOwner

https://www.classmarker.com/onlinetest/results/

16/17

8/9/2016

Finished.

E) ScrumMaster
Points:1outof1
Feedback
TheScrumTeamconsistsofaProductOwner,theDevelopmentTeam,andaScrumMaster.