Delaware River Basin Commission and Commonwealth of Pennsylvania v. Federal Energy Regulatory Commission, 680 F.2d 16, 3rd Cir. (1982)

Download as pdf
Download as pdf
You are on page 1of 6

680 F.

2d 16
48 P.U.R.4th 66

DELAWARE RIVER BASIN COMMISSION and


Commonwealth of
Pennsylvania, Petitioners,
v.
FEDERAL ENERGY REGULATORY COMMISSION,
Respondent.
No. 81-2506.

United States Court of Appeals,


Third Circuit.
Argued May 11, 1982.
Decided June 2, 1982.
Rehearing and Rehearing In Banc Denied July 12, 1982.

David J. Goldberg, Warren Goldberg & Berman, Princeton, N. J., John E.


Childe, Jr. (argued), Asst. Counsel, Com. of Pennsylvania, Dept. of
Environmental Resources, Harrisburg, Pa., for petitioners.
Charles A. Moore, Gen. Counsel, Jerome M. Feit, Sol., Joshua Z. Rokach
(argued), Atty., F. E. R. C., Washington, D. C., for respondent.
Before GIBBONS and HUNTER, Circuit Judges, and THOMPSON,
District Judge.*
OPINION OF THE COURT
GIBBONS, Circuit Judge:

The Delaware River Basin Commission (DRBC) and the Department of


Environmental Resources of the Commonwealth of Pennsylvania (DER)
petition for review of a Federal Energy Regulatory Commission (Commission)
order granting the Borough of Weatherly (Weatherly) a preliminary permit to
study the feasibility of developing hydropower on the Francis E. Walter Dam.1
This court has jurisdiction to review the Commission's actions pursuant to

Section 313(b) of the Federal Power Act, as amended, 16 U.S.C. 825l (b) (the
Act).2 We conclude that the Commission's order is supported by substantial
evidence and we affirm.
2

The Francis E. Walter Dam, located on the Lehigh River in Pennsylvania, is a


flood control project maintained by the Army Corps of Engineers. Starting in
May, 1979 and in chronological order, four applicants filed for a preliminary
permit from the Commission's Office of Electric Power Regulation to explore
the development of hydroelectric power at the dam: Pennsylvania
Hydroelectric Development Corp. (May 8, 1979); Borough of Weatherly
(September 12, 1979); Borough of Lehighton (November 5, 1979); DRBC and
DER jointly (November 23, 1979). A notice of competing applications was
published and comments were submitted thereon. The Office of Electric Power
Regulation decided that it could not differentiate among the various proposals
because none of the applicants had presented a sufficiently developed plan
based on detailed studies. Following the preference hierarchy established by
Section 800 of the Act and by Sections 4.33g(2) & (3) of the Commission's
regulations, 18 C.F.R. 4.33g(2) & (3), Weatherly was granted a preliminary
permit because it was the first public applicant to file. All other applications
were denied.

DRBC and DER appealed the denial of their application. The Commission
affirmed the earlier order, Pennsylvania Hydroelectric Development Corp., 15
FERC P 61,152 (1981), and also denied the subsequent petition for a rehearing.
Pennsylvania Hydroelectric Development Corp., 16 FERC P 61,025 (1981).
Having exhausted their avenues of administrative relief, DRBC and DER now
seek judicial review of the Commission's actions. See 16 U.S.C. 825l (b).

The Commission regulates the development of hydroelectric power from


waters under federal jurisdiction. 16 U.S.C. 796 et seq. This task is
discharged by issuing licenses for the construction and maintenance of
necessary facilities. 16 U.S.C. 797(e). To obtain a license, a prospective
applicant must provide the Commission with a plethora of information,
including feasibility studies, planned compliance with state laws and other
relevant data. 16 U.S.C. 802; 18 C.F.R. 4.1 et seq. Compliance with
statutory and regulatory conditions takes time and money, and an applicant
may not be willing to undertake these up-front expenses without some level of
protection. To deal with that situation, the Act authorizes the Commission to
issue preliminary permits "for the purpose of enabling applicants for a license
... to secure the data and to perform the acts required by section 802 of this
title." 16 U.S.C. 797(f). The preliminary permit gives the holder a measure of
priority when a license is ultimately granted. There is also an order of

preference for the granting of preliminary permits. Section 7(a) of the Act
mandates that as between two equivalent applications, the Commission shall
favor a State or municipality, and as between these the "Commission may give
preference to the applicant the plans of which it finds and determines are best
adapted to develop, conserve, and utilize in the public interest the water
resources of the region, if it be satisfied as to the ability of the applicant to carry
out such plans."3 16 U.S.C. 800(a). The Commission regulations adopt the
statutory hierarchy and provide, moreover, that "(i)f two or more applications
for preliminary permits ... are filed for project work which would develop,
conserve, and utilize, in whole or in part, the same water resources, ... and the
plans of the applicants are equally well adapted to develop, conserve, and
utilize in the public interest the water resources of the region, taking into
consideration the ability of each applicant to carry out its plans, the
Commission will favor the applicant whose application was first accepted for
filing."4 18 C.F.R. 4.33(g)(2). This is a "first in time" rule.
5

There is no allegation that the Commission's regulations are improper under the
enabling statute and, therefore, our task on review is the limited one of
determining whether the agency's order is supported by substantial evidence. 16
U.S.C. 825l (b). See Consolo v. Federal Maritime Commission, 383 U.S. 607,
86 S.Ct. 1018, 16 L.Ed.2d 131 (1966); see also Universal Camera Corporation
v. NLRB, 340 U.S. 474, 488, 71 S.Ct. 456, 464, 95 L.Ed. 456 (1951). The
Commission, in the orders denying petitioners' permit application, denying
appeal and denying rehearing, set forth meticulously its reasons for rejecting
petitioners' application. The Commission determined that there were no
significant differences among the various applicants' plans for the Francis E.
Walter Dam, and that no plan was sufficiently developed to enable a conclusion
to be reached.5 The Commission, therefore, granted a permit to the first filer,
Weatherly. The record indicates that the Weatherly and the DRBC (and DER)
applications had almost equal estimates of capacity and energy output, they
were both devoid of data and both pointed to prospective tests and studies to
develop the information necessary to determine feasibility and the hard
numbers needed to analyze the suggested development project. The petitioners'
application does in fact have a section entitled "Manner the Proposed Project
Would Develop, Conserve and Utilize, in the Public Interest, Water Resources
of the Region," with no counterpart in Weatherly's application. This section,
however, adds little to the substance of petitioners' plans for it only sets forth
the various water resources projects in which DRBC and DER are involved.
The Commission also assessed the relative ability of applicants to carry out the
permit obligations. It decided that DRBC's and DER's intimate involvement
with and expertise in water management, as well as the regional scope of their
concerns, did not put them in a position superior to Weatherly's. The

Commission believed that regional considerations together with the various


state agencies' concerns and expertise could be adequately channeled through
Weatherly, the permit holder, because the permit required Weatherly "to
consult with the appropriate agencies in conducting its preliminary permit
studies, in the interest of protecting and developing the natural resources and
the other environmental values of the project area." Pennsylvania Hydroelectric
Development Corp., 15 FERC P 61,152 (1981). Moreover, the petitioners did
not allege to the Commission any specific facts to support their position that
Weatherly was not a suitable candidate. All this more than satisfies us on
review. "Whether we would have reached the same conclusions on this
evidence were we to consider the matter ab initio is not determinative." N.
Jonas & Co. v. EPA, 666 F.2d 829, 834 (3d Cir. 1981). It suffices that the
Commission's decision is supported by substantial evidence.
6

The petition for review will be denied.

Hon. Anne E. Thompson, United States District Judge for the District of New
Jersey, sitting by designation

Pennsylvania Hydroelectric Development Corp., 14 FERC P 62,285 (1981)

Any party to a proceeding under this chapter aggrieved by an order issued by


the Commission in such proceeding may obtain a review of such order in the
United States Court of Appeals for any circuit wherein the licensee or public
utility to which the order relates is located or has its principal place of business,
or in the United States Court of Appeals for the District of Columbia, by filing
in such court, within sixty days after the order of the Commission upon the
application for rehearing, a written petition praying that the order of the
Commission be modified or set aside in whole or in part
16 U.S.C. 825l (b).

Section 7 of the Act reads:


800. Preference in issuance of preliminary permits or licenses; development
of water resources by Government; taking over of projects by Government
when licenses expire
(a) In issuing preliminary permits hereunder or licenses where no preliminary
permit has been issued and in issuing licenses to new licensees under section
808 of this title the Commission shall give preference to applications therefor
by States and municipalities, provided the plans for the same are deemed by

the Commission equally well adapted, or shall within a reasonable time to be


fixed by the Commission be made equally well adapted, to conserve and utilize
in the public interest the water resources of the region; and as between other
applicants, the Commission may give preference to the applicant the plans of
which it finds and determines are best adapted to develop, conserve, and utilize
in the public interest the water resources of the region, if it be satisfied as to the
ability of the applicant to carry out such plans.
16 U.S.C. 800(a).
4

Sections 4.33g(2) & (3) of the FERC regulations read:


(g) If two or more applications for preliminary permits, or two or more
applications for licenses (not including applications for a new license under
section 15 of the Federal Power Act) by applicants none of whom was a
preliminary permittee whose application for license was accepted for filing
within the permit period, are filed for project works which would develop,
conserve, and utilize, in whole or in part, the same water resources, the
Commission will select between or among the applicants on the following
bases:
(2) If both of two applicants are either a municipality or a state, or neither of
them is a municipality or a state, and the plans of the applicants are equally
well adapted to develop, conserve, and utilize in the public interest the water
resources of the region, taking into consideration the ability of each applicant to
carry out its plans, the Commission will favor the applicant whose application
was first accepted for filing (see 4.31(e) );
(3) If one of two applicants is a municipality or a state, and the other is not, and
the plans of the municipality or state are at least as well adapted to develop,
conserve, and utilize in the public interest the water resources of the region,
taking into consideration the ability of each applicant to carry out its plans, the
commission will favor the municipality or state.

18

C.F.R. 4.33g(2) & (3)

Petitioners argue that the Commission impermissibly avoided comparing


competing applicants' ability to "conserve, and utilize in the public interest the
water resources of the region" until after the preliminary permit had been
issued. We find the point meritless. The Commission effected whatever
comparison it could based on the limited information provided by all the
applicants. The Commission's inability to differentiate among the applicants is
not an indication that it was remiss in its duties but rather that, at such an early
stage of project development, detailed information is just not available. The

Commission Order Issuing Preliminary Permit did indicate that a proper


assessment of "adaptability" would be undertaken later; that, however, was not
a postponement of its task, but merely a prediction that as more data became
available, the Commission would better decide on the applicant best suited for
a license. At the preliminary permit stage, the Commission could not have
acted differently

You might also like