In The Matter of Dutcher Construction CORPORATION, Bankrupt

Download as pdf
Download as pdf
You are on page 1of 9

378 F.

2d 866

In the Matter of DUTCHER CONSTRUCTION


CORPORATION, Bankrupt.
No. 265.
Docket 30809.

United States Court of Appeals Second Circuit.


Argued January 25, 1967.
Decided June 14, 1967.

Raymond T. Miles, Buffalo, N. Y., for appellant, Chester A. Pearlman,


Trustee in Bankruptcy of Dutcher Construction Corporation, Bankrupt.
Mark Turner, Buffalo, N. Y. (Brown, Kelly, Turner, Hassett & Leach,
Buffalo, N. Y., on the brief), for respondent, Reliance Insurance
Company.
Before MOORE and FRIENDLY, Circuit Judges, and BRYAN, * District
Judge.
MOORE, Circuit Judge:

Appellant, Chester A. Pearlman (hereinafter, Trustee), is the Trustee in


Bankruptcy of Dutcher Construction Corporation (Dutcher) which was
adjudicated a bankrupt on August 30, 1956. Appellee, Reliance Insurance
Company (Reliance) is an insurance corporation organized under the laws of
Pennsylvania.

On April 13, 1955, Dutcher contracted with the United States of America,
Corps of Engineers, to perform construction work relating to the Saint
Lawrence Seaway as provided in contract No. DA-30-023-eng-339. In the
contract was a provision for "Changed Conditions." Pursuant to 40 U.S.C.A.
270a Dutcher procured payment and performance bonds, in the respective
amounts of $879,137.20 and $1,098,921.50, with Dutcher as principal and
Reliance as surety.

Because of unforeseen construction difficulties, Dutcher was unable to


complete the work within the required time and the Corps of Engineers
terminated the contract with Dutcher's consent on April 11, 1956. The work
was satisfactorily completed by another firm.

At the same time, Dutcher ran into financial difficulties and could not pay all its
debts. In compliance with its bond obligations, Reliance paid $349,172.81 to
laborers and materialmen satisfying all of Dutcher's debts for labor and
materials supplied to the Saint Lawrence project.

The government had withheld from the monthly progress payments to Dutcher
$87,737.35 as a retainage fund provided for in the prime contract. Prior
litigation between these parties determined that Reliance was entitled to this
fund. Pearlman v. Reliance Insurance Company, 371 U.S. 132, 83 S.Ct. 232, 9
L.Ed. 2d 190 (1962).

The difficulties which prevented Dutcher from performing the contract in the
allotted time also resulted in the actual cost of work done by Dutcher exceeding
the estimated cost by a substantial amount. Under date of May 19, 1958, the
Trustee presented a claim against the United States (Corps of Engineers) "for
additional costs incurred in connection with the performance of the [contract]."
The basis of the claim was stated to be that Dutcher had encountered "changed
conditions" as specified in the contract and that

"the material encountered was far more difficult to excavate than was to be
expected, as well as more difficult to handle. Furthermore, it was not suitable
for haul road construction nor for hauling over when placed in embankment or
wasted in spoil areas. * * *"

The Trustee asserted that this "constituted Changed Conditions within the
meaning of Article 4 of your form of Contract" and that the "Government
represented and agreed that under such a situation an Article 4 Change Order
would be negotiated."

In addition, the Trustee asserted that, irrespective of Changed Conditions, the


Government had represented and warranted to Dutcher that the material was of
a certain type and suitable for certain purposes; that the material was not as
warranted; and that consequently Dutcher was entitled to reimbursement for the
additional costs. The letter also stated that the Trustee had reason to believe the
Corps of Engineers knew that before entering into the contract with Dutcher,
the material was not as represented.

10

Pursuant to the "Changed Conditions" clause of the prime contract and its being
"in the best interest of the Government to modify said contract in certain
particulars," a Change Order dated October 6, 1960, was negotiated wherein
"the total estimated contract price [was] increased by the lump sum amount of
$185,687.46," in order to reflect the "[p]ayment for the increased cost of
performance of the contract resulting from the changed conditions. * * *"

11

The Change Order made specific reference "to Article 4, `Changed Conditions,'
of your Contract No. DA-30-023-eng-339, dated 13 April 1955" and called for
acceptance by Dutcher's Trustee. The Trustee accepted in an endorsement
which read "The foregoing modification of said contract is hereby accepted."
Reliance also agreed that its bond would cover the contract as modified.

12

In addition, the time of performance of the contract was "extended to and


including 11 April 1956." This released liquidated damages in the amount of
$11,000 previously withheld from earned contract moneys and retained by the
Government by reason of Dutcher's failure to complete the performance within
the originally required time. Finally, as the Change Order constituted final
settlement of the claim, the balance of the earned contract money withheld by
the Government, $100 became payable to the Trustee.

13

The total amount payable to the Trustee by virtue of the Change Order was,
then, $196,787.46. The orders of the Bankruptcy Court of October 26, 1960,
and January 6, 1961, authorizing the settlement and receipt of payment by the
Trustee contained the proviso that the rights of the surety to the $196,787.46
fund should be prejudiced in no way by such payment, and that for purposes of
determining those rights, the fund should be treated as if it were still in the
hands of the government. These orders also provided that the fund would be
subject to certain expenses involved in reducing it to possession. After
deduction of those uncontested expenses, the fund now amounts to
$132,619.71.

14

Reliance claims that the fund represents money earned by and owed to Dutcher
under the prime contract, and that by virtue of paying Dutcher's remaining
debts under the contract, in the amount of $349,172.81, Reliance became the
equitable owner of the fund, having a right to it prior to that of the Trustee.
Reliance also claims that the fund is not subject to any further administrative
expenses.

15

The Trustee asserts that the fund represents the settlement of a claim against
the United States for fraud in the inducement; that the fund arose solely

through the efforts of the Trustee; and that the fund should pass into the
bankrupt's estate to be distributed according to the bankruptcy laws.
16

We disagree with the Trustee's characterization of the fund in controversy. We


feel that the fund is precisely what it appears to be: an increase in the contract
price negotiated by the government pursuant to a promise in the Changed
Conditions Clause of the original contract in recognition of the fact that the
conditions encountered were substantially different from those anticipated,
thereby rendering the work more costly to perform.

17

It seems highly unlikely that the United States would settle a claim for fraud,
when such a claim would be unenforceable under 28 U.S.C.A. 2680(h).
Moreover, it is apparent that even the Trustee regarded the claim as arising
under the Changed Conditions clause of the contract whether or not the Corps
of Engineers had material information in its possession prior to the bidding
which it did not reveal to Dutcher because in his claim, he stated: "Whichever
way one looks at it, it seems to me that the subsequent information clearly
demonstrates that the Bankrupt did, in fact, encounter `Changed Conditions.'"

18

Thus, we view the fund established by the Change Order as monies earned by
and owed to Dutcher under the prime contract. The Trustee also claims that
even if Reliance is entitled to receive the fund, the fund should be subject first
to general administrative expenses, including the cost to the Trustee of
conducting the present litigation.

19

The Referee in Bankruptcy decided in favor of the Trustee on both claims. By


orders dated August 30, 1965, and July 29, 1966, the District Court reversed
the Referee and sustained the claim of Reliance to the fund, free from
additional administrative expenses. From those orders of the District Court, the
Trustee has appealed.

20

This case is not a dispute over the priorities of distribution in bankruptcy. What
is at issue here is whether the fund is a part of the bankrupt's estate at all. The
property interests of Reliance at the time Dutcher was adjudicated a bankrupt
did not, of course, vest in the Trustee. Pearlman v. Reliance Ins. Co., 371 U.S.
132, 83 S.Ct. 232 (1962). If Reliance

21

"at the time of adjudication was * * either the outright legal or equitable owner
of this fund, or had an equitable lien or prior right to it, this property interest of
[Reliance] never became a part of the bankruptcy estate to be administered,
liquidated, and distributed to general creditors of the bankrupt." 371 U.S. at

136, 83 S.Ct. at 234.


22

Consequently, the disposition of this case depends, initially, upon whether


Reliance had "ownership of, an equitable lien on, or a prior right to this fund
before bankruptcy adjudication." 371 U.S. at 136, 83 S.Ct. at 235.

23

In Pearlman, this court had held, 298 F.2d 655 (2 Cir., 1962), that laborers and
materialmen had an equitable priority in funds earned by the contractor but
withheld by the United States pursuant to a 10% retainage clause in the contract
and that the surety who had paid the laborers and materialmen was subrogated
to the priority and, hence, was entitled to the funds as against the Trustee in
Bankruptcy.

24

The decision was by no means without precedent. See, Martin v. National


Surety Co., 85 F.2d 135 (8th Cir. 1936), aff'd 300 U.S. 588, 57 S.Ct. 531, 81 L.
Ed. 822 (1937); American Surety Co. of New York v. Westinghouse Electric
Mfg. Co., et al., 75 F.2d 377 (5th Cir. 1935); Belknap Hardware & Mfg. Co. et
al. v. Ohio River Contract Co. et al., 271 F. 144 (6th Cir. 1921); Greenville
Savings Bank et al. v. Lawrence et al., 76 F. 545 (4th Cir. 1896). In fact, the
issues in the Pearlman case, supra, centered not on whether such a priority had
ever existed, but on whether that priority had been "affected or altered" either
by the passage of the Miller Act in 1935 (49 Stat. 793 (1935); 40 U.S.C.A.
2702 [or 270a]) or by the decision of the Supreme Court in United States v.
Munsey Trust Co., 332 U.S. 234, 67 S.Ct. 1599, 91 L.Ed. 2022 (1947). The
Court held that it had not.

25

The Trustee asserts that this case differs from the first Pearlman case in that:

26

(1) the fund in controversy here is not a retainage fund, but the settlement of a
claim against the government (and resisted by it) of fraud in the inducement;
and

27

(2) the fund was not in existence at the time Dutcher was adjudicated a
Bankrupt.

28

In Martin v. National Surety Co., supra, the Court specifically rejected a claim
that the equitable rights of laborers and materialmen were limited to retained
percentages. In that case, suppliers of labor and materials (and, consequently,
the surety standing in their shoes) were held to have an equitable right to
progress payments superior to that of one "who at best was a general creditor."
While the Supreme Court chose to affirm that decision on narrower grounds, it

specifically cautioned that its opinion was not intended to deny "the possibility
of arriving at the same conclusion through other avenues of approach * * *."
300 U.S. at 598, 57 S.Ct. at 535. In National Surety Corporation v. United
States, 133 F.Supp. 381, 132 Ct.Cl. 724 (1955), the court indicated that sureties
who pay under bonds are always superior to assignees, and also that the
government's equitable obligation to pay laborers and materialmen gives it a
right to use all money due the contractor for this purpose:
29

"There would seem to be no doubt of the right of the United States to use the
contractor's money in its hands to discharge the contractor's obligations to
laborers and materialmen. One of the obligations assumed by the contractor
under his contract with the United States was to pay laborers and materialmen.
If he fails to do so, the United States has the right to use money due him to do
what he agreed to do." 133 F.Supp. at 384. * * *

30

"Since the United States is under an equitable obligation to see that laborers
and materialmen are paid, as held in the Henningsen case [Henningsen v.
United States Fidelity & Guaranty Co., 208 U.S. 404, 28 S.Ct. 389, 52 L.Ed.
547], the laborers and materialmen have the equitable right to assert a claim to
moneys in the hands of the [government] which are due the contractor." Ibid.

31

Also cited in Pearlman footnote 23 (371 U.S. at 141, 83 S.Ct. 232, 9 L.Ed.2d
190) was Continental Cas. Co. v. United States, 169 F.Supp. 945, 145 Ct.Cl. 99
(1959). There the surety who paid laborers and materialmen on a payment bond
was allowed to recover sums owing to the contractor, prior to the trustee in
bankruptcy. The court said that the surety, by satisfying the contractor's
contractual obligation to pay laborers and materialmen, was subrogated to the
United States' superior right to use the money due the contractor for this
purpose: "The United States, in requiring the contractor to agree to pay its
laborers and materialmen, and in requiring it to furnish a bond to insure that
they would be paid, acquired a right against the contractor that they should be
paid. We suppose that, if in such a situation the bondsman should * * * become
insolvent so that it could not, if need be, pay the laborers and materialmen, the
United States could withhold money otherwise due the contractor and pay
them." 169 F.Supp. at 947.

32

In London & Lancashire Indem. Co. v. Endres, 290 F. 98 (8 Cir. 1923), the
construction contract was fully performed but some laborers and materialmen
were left unpaid. The surety paid them. The government then appropriated an
additional $30,000 to compensate the contractor for the additional
unanticipated costs of performance. The surety was held to have priority to this
money over the trustee in bankruptcy.

33

California Bank v. United States F. & G. Co., 129 F.2d 751, 754-755 (9 Cir.
1942), also indicates that the Government, because of its equitable obligation to
see that laborers and materialmen are paid, has "the right to retain, as security
for their payment, the then unpaid part ($37,170.04) of the contract price
[including retainages and an amount not "retainage" but simply due on the
contract and as yet unpaid]; and appellee, when it paid the claims, became
subrogated to that right." 129 F.2d at 754.

34

United Pacific Ins. Co. v. United States, 319 F.2d 893, 162 Ct.Cl. 361 (1963),
decided after Pearlman, held that the surety who paid laborers and materialmen
on payment bonds and completed performance under a performance bond was
subrogated to laborers' rights under the former and the government's rights
under the latter, and was thus entitled to a priority as to all money earned but as
yet unpaid on the contract, whether a "retainage" or not.

35

Various courts, especially the Court of Claims, have frequently said that the
right of the laborers and materialmen to be paid is prior to the corresponding
right of general creditors. Thus, laborers and materialmen have an equitable
lien on all the proceeds of the contract, and the government has an equitable
obligation to see that they are paid, which obligation gives it the right to apply
any and all proceeds due the contractor to this end. The reason for this
equitable obligation rests on the principle that it would be unfair for the
government to permit money to go to general creditors, whose services did not
contribute to performance of the contract, when laborers and materialmen
responsible for performing the contract remained unpaid. The result is to put
the contractor, laborers and materialmen and general creditors in the same
positions vis-a-vis the money due on the contract as they would have been had
they contracted with a private party whose property was subject to mechanics'
liens. See generally 71 Yale L.J. 1274 (1962); National Surety Corp. v. United
States, 133 F.Supp. 381, 383-384, 132 Ct.Cl. 724 (1955).

36

Other federal decisions indicate that the equitable rights of laborers and
materialmen extend to all monies earned by the contractor under the contract
but remaining in the hands of the government.

37

In Belknap Hardware & Mfg. Co. et al. v. Ohio River Contract Co. et al.,
supra, in a dispute between the suppliers of labor and materials for the
government contract and the general creditors of the contractor, the laborers
and materialmen were held to have an equitable right to the "balance due from
the government." The balance due was $98,674.64 and, as the retainage fund
provided for in the contract had a maximum of $75,000, part of this balance
must have consisted of monies other than the retainage fund. This fact passed

without comment by the court.


38

In American Surety Co. of N. Y. v. Westinghouse Electric Mfg. Co. et al.,


supra, the dispute between suppliers of labor and materials and the surety who
had already paid the penal amount of his bond was over a final payment of
$2,775 by the government to the Trustee in Bankruptcy of the contractor. While
the court referred to this payment as "the amount of 10 per cent. of estimates,
retained pursuant to a provision of the contract" (75 F.2d 378), the court, Judge
Sibley, dissenting, pointed out that the 10% retainage fund could amount to
only $1,524, the inevitable inference being that the remaining $1,251
represented monies due under the contract but not retained pursuant to the
retainage clause of the contract. The distinction between the two types of funds
evidently did not impress the majority as significant, for they referred to a
judicial recognition of "an enforceable equitable right of unpaid furnishers of
labor or materials for [government contracts] in or to a part of the contract
price thereof remaining in the possession of the government after the
completion of that work by the contractor" (emphasis added). The laborers and
materialmen prevailed. See also London and Lancashire Indemnity Co. of
America v. Endres, supra; National Surety Corp. v. United States, 133 F. Supp.
381, 132 Ct.Cl. 724 (1955).

39

United States v. Munsey Trust Co., supra, does not preclude recovery by the
surety here. In Munsey, the United States admitted that it owed the contractor
$12,445.03 in retained percentages on one contract, but asserted, and this
assertion was not contested, that the contractor was indebted to it in the amount
of $6,731.50 on other transactions. The United States paid all but $6,731.50 of
the retained percentages to the contractor's receiver, retaining the latter sum.
The surety sought to recover from the United States part of the retained
$6,731.50 without contesting the contractor's indebtedness in that amount.

40

In Pearlman, the Supreme Court clearly defined the limitations of its decision
in the Munsey Trust case by stating that there they had held that the United
States could "exercise the well-established common-law right of debtors to
offset claims of their own against their creditors. This was all we held." 371
U.S. at 140, 83 S.Ct. at 237, 9 L.Ed.2d 190. Thus, the Munsey decision seems
to us to be nothing more than an application of the rule that at any given
moment in time, the rights of laborers and materialmen to monies in the hands
of the government are no greater than the rights of the contractor himself to
those same funds.

41

In summary, the facts are clear that the $196,787.46 payment by the
Government was made under, pursuant to, and in modification of the original

contract. Just as the surety was held to be entitled to the retainage fund in the
first Pearlman case, so here the avails of the contract should be recoverable by
the surety which has paid out some $349,172.81 on Dutcher's debts under the
contract to laborers and materialmen. This does not inflict any injustice on the
general creditors since until the contractor had satisfied its obligations to
laborers and materialmen, it would have had no avails from the contract for
general purposes.
42

As to administrative expenses, it is provided in 11 U.S.C. 102 that they "shall


be paid or allowed out of the estates in which they were incurred." The effect of
our holding that Reliance had a prior right to the fund in question is that the
fund never became part of the bankrupt's estate. See, Pearlman v. Reliance Ins.
Co., supra, 371 U.S. at 136, 83 S.Ct. 232. Thus, the administrative expenses
should not be assessed against this fund. This is not to say that the Trustee
should not be allowed to recover the necessary expenses of litigation or a
commission for handling this fund under 11 U.S.C. 76, sub. c.(1), but simply
that these allowances must be paid out of the general estate, and not out of the
fund belonging to Reliance. There is no claim that the general estate is not
sufficient to pay the Trustee. Under these circumstances, In re Toole, 294 F.
975 (D.C. S.D.N.Y.1920), at pp. 977-978 supports our decision not to deduct
administrative expenses from the fund belonging to Reliance.

43

Affirmed.

Notes:
*

Of the Southern District of New York, sitting by designation

You might also like