Change Order PDF
Change Order PDF
Change Order PDF
EST.02
Reviewing Change Orders 101
Mr. Brian S. Clare, CCC
here is that dreaded word Change Order. As one of my colleagues recently stated, Change Orders suck.
During the building of the great pyramids, the builders surely ran into unforeseen changes to the original
design because of the weather, famine, wars, material shortages, and user changes (the Pharaoh).
A change order is defined as a written agreement between the owner, contractor and architect upon a change in
the work and any appropriate adjustment in the contract sum or the contract time [1].
Unfortunately, no project is without its share of changes or change orders, ranging from the home builder to the
mega billion dollar projects. How change orders are handled, however, can affect the outcome and financial
stability of the project. The sooner change orders are dealt with and resolved, the better chance of project success.
The contractor is also entitled to fair and reasonable compensation for the extra work that was performed.
The purpose of this paper is to present a methodology of how to review a change order, that any professional
layman can follow and use.
DETERMINATION OF MERIT
One of first line of defenses for change order review is the litmus test to see if the change order is definitely a
change in the scope of work. Comparing the change order directly to the contract documents (contract, drawings and
specifications) will help in the determination if the alleged change order has merit.
The following type questions should be asked:
Is it already defined in the drawings or specifications, or is the contractor is trying to pull a fast one?
Is it a gray area that is conflicting with contract documents?
Maybe the onsite inspector or fire marshal is advising changes for building or safety code compliance.
Depending on size of change order, is there a take off included? And,
Are there differing site conditions which may have been encountered?
There are numerous reasons for a change order, but are they legitimate?
The architect, engineer and onsite construction management staff can also offer a second opinion on the merit
issue. Their input can be easily obtained at the weekly meeting, or in a specific meeting set-up solely for the change
orders.
Proper notification by the contractor will also help in the entitlement of the change order. Notice requirements
typically are found not only in the changes clause of the contract but may also be found in other clauses contained in
the contract document. [2] This gives the owner options and allows time in how to react to the alleged change
order. Notification should be immediate, especially if it is affecting the critical path of the project. It may also be
formally required by the owner or government agency that the contractor is working for.
Options:
The owner can then decide if they want to track the proposed work on a time and material basis. That way the
owner can have more input to work around situations which will lesson the impact on operations.
EST.02. 1
The owner can choose to get a lump sum price from the contractor before proceeding.
All these options allow the owner to make good sound business decisions and minimize the impact time of the
change order. In proving and pricing construction claims, it states, The requirement for notification is for the
benefit of the owner and is to allow the owner the opportunity to correct and/or accommodate a change in the most
effective manner. [3]
As an example of a notification time frame, this author has seen a contract where the first written notification
was to be within 10 days from the first time the change was encountered or determined. However, when it involved
a possible change in time or excusable delay to the critical path of the project, because of neglect of the owner or
architect, this author has also seen a contract with a provision for a 24 hour written notice. In return, the owner
should also provide a response back to the contractor in a reasonable timeframe, depending on its urgency.
Notification requirements should become part of the contract and change order procedure. Without them in
place, the contractor could submit a lot of after the fact change orders.
TYPES OF CHANGE ORDERS AND COST PROPOSALS
Once a change is known, the legal instruments commonly used to initiate scope changes are the change order,
letter or field directive. [3] These legal instruments are usually issued from the Architect or Engineer in the form of
a Bulletin or Change Order Directive to the contractor as a result of a Request for Information (RFI) or from direct
contact with the contractor. In return, the contractor will provide the owner with a Cost Proposal, which usually
includes a Rough Order of Magnitude (ROM) Estimate. A lot of times these costs are based on input from its
subcontractor and estimating team. Sometimes a Change Order Proposal is referred to as a PCO (Potential Change
Order) or a COR (Change Order Request), depending on the organization you are dealing with. There maybe formal
Change Order Forms for the contractor to use in filling out and presenting its costs, such as the AIA G701 Forms
(Architectural Institute of America) or specific forms developed or specified by the owner or government agency.
In Proving and Pricing Construction Claims it defines, A directed change is typically a formal change order
issued by the owner or its authorized representative. [2]. This is the formal kind of change that the owner or
architect is aware of that changes the scope of the contract. It also states, A constructive change is defined as any
conduct by an owner or its representative that is not a formal change order but which has the effect of requiring the
contractor to perform work different from that prescribed by the original terms of the contract. [2]
Typical types of change orders and cost proposals include the following:
Lump Sum Change Orders The contractor provides a lump sum price prior to performing the work. The risk
is usually on the contractor, as they may do it for less or more of the actual cost. The detail documentation may
still include a breakdown of labor, material, and equipment cost. Vendor quotes may also be included.
Time and Material The contractor proceeds with the work and records his time, material and equipment
costs on a daily report or some kind of a daily tally sheet which is then verified and signed by the owner. The
danger of the time and material change order is when the work is performed, it needs to be verified and signed
off by the owner, or its representative on a daily basis. The biggest disagreements come when this task is not
performed and the owner believes he is being taken advantage of. Another school of thought includes the idea
that the contractor may increase his crew intentionally or not worry about its productivity, since his fee is based
on a percentage mark-up f the actual cost.
Contract Time Extension Requests This is almost a separate subject and paper in its self. However, when a
change order affects contract time, the procedure is to develop a fragment or time line of events or activities for
the scope of the change order, and then to insert it into the current approved monthly CPM (critical path)
schedule to determine if it affects the critical path of the project and pushes the end date out.
Unilateral When no agreement in time or price is derived from the negotiation of a change order, it is called
a unilateral change order. [3] The owner then issues this change order unilaterally, and the contractor can then
accept it or contest it.
There can also be variations of these types of change order proposals, where there is a not-to-exceed amount set
as a limit, and further authorization is needed in order to proceed further.
EST.02. 2
Pick a group of line items and do a spot check using the resources listed below. Maybe after you have gone
through a few change orders in depth and detail, you see the pricing of the work is continually reasonable. In
some cases where the contractor is playing games, you might have to scrutinize everything. And,
It is best to keep your guard up and not to get too comfortable, as even the most honest people can make
mistakes. If you already know what the going prices are for the work, you can put together some quick working
crew and equipment rates and put together a quick ROM (rough order of magnitude) estimate to quickly test if
the contractor is in the ballpark.
When every change order has to be fully reviewed, the man-hours of labor and equipment use and the quantities of
materials can be reviewed by the following comparison methods:
Individual Takeoff Estimates and Comparison an independent take-off and pricing of the scope of work.
This can be done by an owners project staff, its consultants or architect.
Use of Industry Standard References References and trade publications such as Means, Walker, NECA
Manual National Electrical Contractors Association for electrical, MCA Manual Mechanical Contractors
Association, etc. can be used to compare labor production installation rates, and in some cases, material and
equipment rates. Even Caltrans the Department of Transportation, State of California, publishes a book that is
available on-line for equipment rates.
Use of Previous Change Orders or Similar Jobs Use previously approved change orders that you believe
were reasonable or similar project estimates. If they are older, you can escalate to normalize the costs.
Historical Data Bases - If one has been developed, unit rates from actual completed projects maybe available
for similar work.
Verification of Material and Equipment Costs from Vendors Call other contractors who do the work that
you trust for ballpark/rule of thumb numbers, call local material supply houses, manufacturers, distributors,
construction equipment rental companies.
f the change orders remain unresolved, it may become part of a claim package or Request for Equitable
Adjustment. Then even more time and money has to be spent to investigate and resolve them. The project
personnel originally involved with the review of the change orders may have moved on to other projects or even
companies, so the item they were arguing about may no longer apply. Litigation is also possible because of
unresolved change orders, which is costly for both the owner and the contractor.
The bottom line is that it is much easier to resolve these change orders as they occur, than to wait until the end
of the project when details maybe forgotten. Both the contractor and the owner will benefit from having an efficient
change order review process procedure in place.
REFERENCES
1. Callahan, Michael T., Construction Change Orders Claims, Aspen Publishers (2005): 10.
2. Cushman, Robert F., Craig M. Jacobsen, P.J. Trimble, Proving and Pricing Construction Claims, Wiley Law
Publications, 1996, pp.8-3,8-4 and 8-5.
3. Driscoll, Thomas, James J. OBrien, PE, and Robert G. Zilly, PE, The Contract Managers Handbook,
McGraw-Hill Book Company, 1971, p.16-2.
4. Inspector General Report, 2005-01-0043, INDOT CHANGE ORDERS, Indiana Department of Transportation
(October 27, 2005): 7.
5. OBrien, PE, James J. and Robert G. Zilly, PE, The Contract Managers Handbook, McGraw-Hill Book
Company (1971): 1-21.
6. Stevens, Matt, Change Orders Your Right and Your Headache, The Contractors Business Digest (May 17,
2007).
EST.02. 5