Instructions to A/E: The WiFi Specification 27 17 53 shall be included and coordinated with in
the master specification unless directed otherwise by the University Project Manager.
Under certain design and contracting situations such as, design performed by CPO Design
Services, construction by UW Facilities, construction by the Job Order Contractor, bid off the
Small Works Roster, or by the small amount of expected WiFi impact, the University Project
Manager may, after conferring with UWIT, elect to have the WiFi design provided by UWIT for
incorporation into the contract documents.
The design if provided by UWIT would be for location of the WiFi access points (WAP(S)),
predictive performance report, activation and testing a comprehensive post testing survey (heat
mapping). All pathway and cabling for the WAPS would need to be the responsibility of the
Contractor as shown on the contract documents.
If the design is provided as part of the A/E contract the A/E must verify the current design criteria
with UWIT.
All submittals and approvals that need to be provided to/by UWIT shall be done through the CPO
Owners Representative.
_________________________________________________________________
GENERAL
1.1
SCOPE
The design must be such that the installed AP equipment provides coverage that will
support
necessary capacity for 802.11a, g, n and ac Wi-Fi technologies with a
maximum
Standard Noise Ratio of 25dB and a minimum receive signal
strength (Power
Threshold) of -65 dBm throughout the
designated coverage area(s).
a). All areas shall provide sufficient cell overlap such that users can roam through the
area(s) of coverage without loss of connectivity.
b) Each Client should see a minimum of 2 APs at the same time while receiving a signal
of at least -70 dBm.
c). Capacity coverage:
1) The estimated occupancy for each coverage area shall be appropriate for the
expected usage of the area.
2) Within coverage areas, APs shall be installed to accommodate a maximum of
20
users per AP.
3) If the user density exceeds 16 sq. ft. per user, a special layout may be
required beyond the 20 users per AP criteria. In addition to the
pg. 1
types
1.2
WORK INCLUDED
The Designer must be available by phone or other electronic medium to meet with
Owner, UW Information Technology(UW-IT) and others as required by UW-IT;
2.
The Designer shall be available to attend pre-design with the purpose of addressing
specific project requirements prior to commencement of design. (See Section 1.5)
3.
The Designer shall be available to attend other meetings such as site coordination
meetings as required by the Owners representative, UW-IT and others as required.
4.
At the Owners discretion these meetings may be conducted via phone or other
electronic medium. The Designer shall be capability and be available for these
meetings.
5.
The Owner may waive the requirement for any of these specific meetings on perproject bases.
6.
7.
The Designer shall provide revised design if required by UW-IT after validation and
acceptance review.
pg. 2
1.3
QUALITY ASSURANCE
A. Engineer Qualifications
1. The organization providing design work for this section shall employ an Aruba Certified
Mobility Professional (ACMP) and an Aruba Certified Mobility Associate (ACMA), both in
current good standing with Aruba Networks. The ACMP and ACMA shall be direct, full
time employees of the organization providing design (i.e., an ACMP/ACMA designer who is
not a
direct employee is not acceptable) and be available to visit the site throughout
the project when work is ongoing. A current copy of the ACMP and ACMA certificates will be
requested by UW-IT.
2. The Designer shall be a Wireless Design Professional with qualifications per paragraphs
1.3.A.2. though 1.3.A.8 of this document, and have been in the wireless network design
business for a minimum of three (3) years.
3. The Designer shall have successfully completed five (5) designs equal in magnitude (in
terms
of size and construction cost) within the previous three (3) years. For projects
consisting of
less than 35 access points, these completed projects shall have been
successfully integrated
into a network consisting of no fewer than 400 access points
within the previous three (3) years. These projects shall have used similar equipment to
those specified herein.
4. The Designer shall have demonstrated experience in the system design of all
components specified herein;
5. Only full-time permanent employees/staff of the design firm are approved to provide
designs
and documentation as set forth herein;
6. The Design Firm shall provide all needed software and shall provide a Designer and staff
proficient in the use of Ekahau Site Survey and layered AutoCAD Design for
incorporation
into AutoCAD and have the capability to import a design file.
7. The Designer must be proficient in assigning RF attenuation and the signal reflection
characteristics associated with them in both Auto Cad Layers and Auto Cad Objects. This
is
to qualification is to assure designs that are predictively accurate.
8. The WiFi Designer must be proficient in the use of Ekahau Site Survey for predictive RF
CAD
designs that consider buildings and RF signal propagation in 3 dimensions and
necessary capacity, as opposed to a flat, two dimensional assessment of RF coverage and
capacity.
9. The WiFi designer shall be available for the site pre-design meeting with Owner and the
site
pre-installation walk-through and/or other methods as required for understanding
and
communicating project requirements.
10. The WiFi designer shall make and engineer any revisions to the construction documents
that
are a result from the pre-installation walk-through. These revisions shall, once
approved by
the UW-IT WiFi Engineer, be communicated to the A/E team and the
General Contractor to
provide any required revisions in pathway resulting from these
changes.
1.4
DESIGN REVIEW
A. Work Planning: There is a review phase for design which may be iterative based on UW-IT
approval of design. The Designer shall:
1.
Provide AP placement design narrative in Microsoft Word (latest file format) doc format or
Adobe Portable Document Format (PDF) and drawings in Autodesks AutoCAD DWG and
Ekahua Site Survey Files latest file format;
pg. 3
1.5
Contact the Project Manager for access instructions to the Wi-Fi Information Form in a
Microsoft Excel document stored on a UW-IT maintained Microsoft Sharepoint site. The
designer is to complete the Designers portion of this Wi-Fi Information Form.
PRE-DESIGN MEETING
PRE-INSTALLATION WALKTHROUGH
A. The Designer shall attend a pre-installation walkthrough with the Contractor and a UW-IT
representative. This walk-through shall occur prior the Contractors commencement of
installation. UW-IT may waive this requirements on a per-project basis.
A. The design shall provide for coverage in both the 2.4 and 5 GHz bands with a minimum SNR
of 25dB and minimum receive signal strength of -65 dBm. These coverage levels will be
verified post-installation and the designer will be responsible to provide design solutions for
any deficiencies;
B. All areas designated for coverage shall provide sufficient cell overlap such that users can roam
through the area of coverage without loss of connectivity;
C. Every client should be able to receive signals from a minimum of 2 Access points at the same
time while receiving a signal of at least -70 dBm.
D. Capacity Coverage
1. The designer will identify areas that require capacity coverage on the floor plans, with
specific estimated capacities identified in the wireless narrative;
2. Within capacity coverage areas additional APs should be designed with a target of no
more than 20 users per AP based on occupancy estimates;
3. If the user density exceeds 16 sq. ft. per user, special design may be required beyond
20 users (not devices) per AP. The following background information on UW-ITs
typical configuration is provided to assist the designer in these circumstances:
a.
b.
pg. 4
40MHz channel width is generally used in the 5GHz band, but may be disabled in
very high capacity areas to provide additional discrete channels.
E. Air Monitors
1. An Aruba Air Monitor (AM) overlay shall be designed only for facilities used by:
a.
UW Medicine,
b.
c.
2. Where installed one AM should generally be included for every five to seven Wireless
Access Points (APs) on each floor, such that monitoring coverage is provided for the
entire area in both bands.
3. AMs shall not be placed directly adjacent to APs.
F. The designer providing a wireless design for approval shall submit a complete AP placement
design package to the Owners Representative for review and coordination prior to bid. The
design shall include a text in Microsoft Word doc format with the following information:
1. areas that do not require coverage, with the rationale;
2. areas where capacity coverage is required, with the rationale and number of expected
simultaneous users;
3. all special physical accessibility and aesthetic requirements, such as AP location
restrictions based on building appearance or areas where standard AP install
procedures cannot be followed;
4. each AP that is attached to surfaces other than the ceiling, or is mounted 10 feet or
more above finished floor with a rationale;
5. any materials which could significantly attenuate 802.11 signals in either the 2.4 or 5
GHz band, with the type of material in question and the location of the material;
6. appropriate diagrams from Ekahu Site Survey should be included to help illustrate the
narrative ;
7. at completion of construction work, the narrative must be amended with any changes
made to the original design based on conditions encountered.
G. The Designer shall on the contract documents provide AP/AM location documentation in
Autodesk AutoCAD latest file format DWG format. The designer shall receive a DWG
template file from UW-IT. The document provided by the designer shall include the following
information:
a. A block object with attributes which represents each AP location. This block is defined
in the DWG template file and must be taken from there;
b. Text label with values taken from AP object attributes which include:
c. The AP name (e.g., SAV.102.AP01 or UWSS.B056.AP04). The name must follow the
convention described in the Design Requirements.
d. The mounting style. Acceptable values for this attribute include: WALL, CEILING,
ENCLOSURE, BELOW ENCLOSURE, NEMA, HARDLID.
H. AP and AM icons and labels must be separated into drawing layers in the E-COMM layer name
space. Only layers defined in the UW-IT supplied template may be used.;
pg. 5
The layer colors must not be altered from the template colors, and the AP and AM block
objects must not be altered in any way;
J. The Designer shall modify the available on-line Wi-Fi Information Form after the design is
accepted by UW-IT. Instructions for accessing and completing this form shall be provided by a
UW-IT representative.
K. The Designer shall provide Ekahau Site Survey electronic files used to create and/or validate
the design. This file should be properly configured with applicable wall, building and other
elements and settings to ensure an accurate RF module of the proposed design. The file shall
also be configured with the applicable coverage, capacity and signal requirements for the
project.
2.2
A. Normally, any wireless access point must be mounted between 8 and 10 feet above finished
floor (so as to be accessible by a standard eight-foot ladder for service). A mount between 10
and 15 feet AFF may be permitted if approved by UW-IT. If any other alternative placement is
required, it must be approved by UW-IT prior to bid or completion of the design;
B. If wall mounted the project documents shall show:
1. an appropriate mounting bracket certified for use by Aruba must be utilized;
2. at least 6 of clearance between top of AP and ceiling must be provided.
3. the orientation of the AP should be considered, especially noting APs with integrated
down-tilt antenna.
C. If ceiling mounted on a suspended acoustical ceiling tile system the project documents shall
show:
1. an appropriate mounting bracket certified for use by Aruba must be utilized;
2. attachment to the main beam (rather than cross t) must be done where reasonable.
D. The design should reflect that all APs are to be mounted between 8 and 10 feet above finish
floor.
1.
Wall mounted Aps shall be designed with a minimum 6 inches of clearance between
the top of the AP and the ceiling.
2.
APs located on suspended ceilings shall located on the main beam (rather than cross
tees.)
3.
All alternative placements shall be approved by the Owner and UW-IT be for
completion of the design.
2. CCC is the official building code, in all capital letters (e.g., SAV for Savery Hall and
UMSS for the SS wing of UWMC). This code shall be provided by UW-IT on the Wi-Fi
Information Form;
pg. 6
Wireless access points (WAPS), support brackets and antennas will be furnished by Owner and
presented as such in the documents unless directed differently by the UW CPO Project manager.
Wireless technology is rapidly changing resulting in updated products that may replace the existing
UW standard during the time it takes to design and bring a project to the stage where WAPS
should be ordered. As a result products need to be verified by the A/E with UW-IT prior to
specifying and by the CPO PM/CM prior to ordering.
Documents should reflect that the Owner is to be notified of the need to order 90 days prior to the
scheduled install of WAPS and related products.
Design shall specify a complete bill of materials.
pg. 7
BRACKETS
The designer shall verify the current products required with a UW-IT Wireless Engineer:
1. For dropped ceiling mounting of AP-214, AP-215, AP-225:
Aruba AP-220-MNT C-2
2. For wall mounting or Hard Lid Mounting of AP-214, AP-215, AP-224:
Aruba AP-220-MNT-W2(Mount Kit)
3. Appropriate mounting hardware for all other uses and access points.
4.3
ENCLOSURES
The designer shall verify the current products required with a UW-IT Wireless Engineer:
A. Aruba AP-225, AP-215 and AP-275 equipment have built-in internal antennas.
B. Aruba AP-224, AP-214 and AP-274 equipment require external antennas.
C. The design must specify the choice of antennae and if they are not an Aruba Networks
product, detailed information about the product.
POST-INSTALLATION
pg. 8
DESIGN VERIFICATION
A. The Designer must provide a heat-map review of the final wireless installation to satisfy
Owner's criteria and the coverage and capacity requirements described in
this document using the following criteria:
1. The site survey shall be conducted using Ekahau Site Survey (ESS).
2. Where possible an active survey shall be conducted. If an active survey is not practical due
to network availability, a passive survey may be permissible upon approval of UW-IT.
3. All UW access points, including those installed as part of the project
must be properly
4. ESS shall also be configured with the proper design criteria (e.g. min.
sample is taken from each area. For room exceeding 400 square feet,
the surveyor shall walk the perimeter of the room, taking at least one
sample at each corner.
7. Surveyor shall verify that each installed AP is providing service based on
the survey results
(confirming MAC address for each AP).
8. The Ekahau survey files shall be furnished to UW-IT for review and as part
of the final as- built documentation. All surveyed floors will be included
in a single Ekahau project file.
B.
The Designer must provide a printed and electronic report providing the
results of the survey, including a narrative of areas found deficient.
C. The Designer must provide a copy of the electronic Ekahau Site Survey file.
D. The Designer must provide AutoCAD files with the final wireless design and
layout, reflecting all final AP placement locations.
E. The Designer may be required by UW-IT to attend a follow-up meeting to
discuss the
project.