MOS POS Linkedin Discussion
MOS POS Linkedin Discussion
Comments
Emil Modoran, loreto jr saldana and 6 others like this
16 comments Jump to most recent comment
YOUSEF
YOUSEF RASHIDINEJAD
Process Engineer, Sulfur Technologist at Agip KCO
Dear Mojtaba
About your Q1: SOS time period is depend how long does it take until unit getting stabel, for example for a pump flow rate it will take about maximum 30
sec. but in order to stablized the copressors suction, or discharge pressure it may take about 5 to 10 mini or more but not more than 30 min.
but for MOS we do not need any time preriod and timing is depend to how important that element is and how long does it take to repair, so for that the
Supervisor or SUPT. of the plant will deside.
Q2: As I explain in part one for start up of some equipment we need to put SOS, but MOS has been put for any Trip signal from instruments in order alow
instrumnetation to check and calibrate, do PM and CM on that. but should be carefull about Voting system. because some of voting system assume the
inhibit as a fault and 2nd inhibit my cause trip. for prevent to have such problem should force the trip comand.
Q3: It is explain in Q1, depend how long take time for normalize.
Q4: for MOS need just put the inhibit or force for the instrument which need to be fix. this could have effect on equipment, Train or overal plant. depend
how iportant is it and where is the location. For example if it is located on hipps will effect all plant, if located on one non essentila equipment will trip only
that equipment.
o
Like (4)
o
Flag as inappropriate
o
July 2, 2013
mourad B., Mojtaba Habibi and 2 others like this
Mojtaba
Mojtaba Habibi
Process Engineer at Wood Group
Dear Mr.RASHIDINEJAD,
Thanks a lot for your time and help.
1. If MOS specified time is elapsed while we have not finished with your works, should we expect any difficulty, problem or hazard?
2. How to specify MOS for specific equipment?
3. What do you mean by PM and CM?
4. Could you please explain more about "should be carefull about Voting system. because some of voting system assume the inhibit as a fault and 2nd
inhibit my cause trip. for prevent to have such problem should force the trip comand."?
Many thanks.
Best,
Mojtaba
o
o
o
Like
Flag as inappropriate
July 2, 2013
Richard
Richard Hord
Retired Union Carbide/Dow Chemical
Where I worked this violates Procedures. To do this would require some Paperwork and Signatures.
o
Like (2)
o
Flag as inappropriate
o
July 2, 2013
mourad B., Philippe N. like this
Jonter
Jonter Siregar
Greg Dunnells
Senior Petrochemicals Staff Consultant
There are several ways to do this. If it is truly a startup function, then you can do something like a mode switch, which allows you to start up the process.
For maintenance, typically you would turn off the interlock - but only with proper procedures and authorizations in place.
The proper way to do these things is during a hazards evaluation (hazop, etc) where you look at the hazards that the interlock is mitigating, and decide
whether or not it is truly a safety issue.... or not.
The tendency of late, is to make everything a "safety interlock" which may or may not be true. It is truly safety only if, there is a danger of someone
getting injured or a major environmental problem. There are other types of interlocks, such as process, which are intended to avoid a non-safety problem.
The ISA standards have all of the details on how to do these sorts of things.
o
Like (2)
o
Flag as inappropriate
o
July 5, 2013
Mike E., mourad B. like this
John
John Lewicki
CONSULTANT at n/a-freelance
Please don,t forget the
o
o
o
liability insurance, if you screw up, they won,t pay, so it comes down to need , planning and execution.
Like
Flag as inappropriate
July 6, 2013
WASIM
WASIM YASIN, ASP, BE Chem
Operations| Pre-commissioning| Commissioning| Process Safety Managment Professional
Q1: No such timer to be provided as you never know that whether job would have been completedor not by the time it resets the logic. Yes, indication
(Panel Bulb) to be provided so that boardmen should not forget the bypassed securities.
Q.2: Normally, these are provided for Lower Limit of securities such Low level, low flow, low pressure, low ratio, low speed etc as in startup phase these
securities would be below their lower limits & would not let the plant startup. Once the plant has crossed these lower limits by a significant pre-defined
value these should be taken in service ASAP.
o
Like
o
Flag as inappropriate
o
September 9, 2013
WASIM
WASIM YASIN, ASP, BE Chem
Operations| Pre-commissioning| Commissioning| Process Safety Managment Professional
Q1: No such timer to be provided as you never know that whether job would have been completedor not by the time it resets the logic. Yes, indication
(Panel Bulb) to be provided so that boardmen should not forget the bypassed securities.
Q.2: Normally, these are provided for Lower Limit of securities such Low level, low flow, low pressure, low ratio, low speed etc as in startup phase these
securities would be below their lower limits & would not let the plant startup. Once the plant has crossed these lower limits by a significant pre-defined
value these should be taken in service ASAP.
Greg
Greg Dunnells
Senior Petrochemicals Staff Consultant
I agree with Wasim. This is an operations management decision. Typically a bypass authorization expires when the shift changes, and has to be reauthorized.
Mojtaba
Mojtaba Habibi
Process Engineer at Wood Group
Dear Mr.RASHIDINEJAD,
Regarding to 2OO3 voting instrumentation MOS:
I think if there is any need for maintenace of any of these 3 transmitters this mean for that particular transmitter something is wrong and from MOS
viewpoint this means fault. So for this case the 2OO3 logic should automically be changed to 1OO2 logic once MOS is enabled for one of the faulty
transmitters. Also I think simultaneous MOS for more than one transmitters should be prohibited. Correct me if I am wrong.
Best,
Mojtaba
Jan
Jan Dauwerse
process stop coordinator / shift supervisor at SABIC
Hello Mojtaba.
there are different levels of switches. It depends on the effect of the damage when the switch doesn't work. Do you have only financial damage or is it
possible that people get hurt or even die. Is it a problem for the envirement or reputation. The highes level has the biggest impact. The level of importance
is analized by engeneers, manager operations and production. We yuse a foult tree for this analise. Normally we are allowed to overide these switches for
less than 24 hours a year. Only the manager operations is allowed to approve to overide. The middle level has lessel impact and we are allowed to overid
for a period of a week a year. The manager operations or his assistant are allowed to approve this overid. The lowest level doesn't have much impact.
There is no time limit to overid and the shift supervisor can approve this overid.
A SOS is a part of the design of the plant and doesn't have a time limit. When a system is not working, like during a turn around, there is no level of
importance. A switch must work during the time a potential danger is coming out of the process.
During running a plant you have to test the switches on time base. It can be possible that you have to overide a switch during this test. There is also a
difference inside the process. When you run a reactor the high temperature switches must have an other high limit than if you do a regeneration of this
reactor.
The only way of keeping the plant save is to keep a good administration of all the overrides. The shift supervisor will check this list every day.
Jan
Jan Dauwerse
process stop coordinator / shift supervisor at SABIC
Hello Mojtaba.
there are different levels of switches. It depends on the effect of the damage when the switch doesn't work. Do you have only financial damage or is it
possible that people get hurt or even die. Is it a problem for the envirement or reputation. The highes level has the biggest impact. The level of importance
is analized by engeneers, manager operations and production. We yuse a foult tree for this analise. Normally we are allowed to overide these switches for
less than 24 hours a year. Only the manager operations is allowed to approve to overide. The middle level has lessel impact and we are allowed to overid
for a period of a week a year. The manager operations or his assistant are allowed to approve this overid. The lowest level doesn't have much impact.
There is no time limit to overid and the shift supervisor can approve this overid.
A SOS is a part of the design of the plant and doesn't have a time limit. When a system is not working, like during a turn around, there is no level of
importance. A switch must work during the time a potential danger is coming out of the process.
During running a plant you have to test the switches on time base. It can be possible that you have to overide a switch during this test. There is also a
difference inside the process. When you run a reactor the high temperature switches must have an other high limit than if you do a regeneration of this
reactor.
The only way of keeping the plant save is to keep a good administration of all the overrides. The shift supervisor will check this list every day.