Editor in Chief: Project News: 2 - 4 Technical Section
Editor in Chief: Project News: 2 - 4 Technical Section
Editor in Chief: Project News: 2 - 4 Technical Section
N e w s
M a g z i n e
U S B R L
HIM PRABHAT
Editor in Chief
Contents
MohitSinha
Prologue : 1
Officer/USBRL
Editorial Board
Project News : 2 - 4
R.K.Choudhary
Technical Section
Achal Jain
Chief Engineer/North
Sandeep Gupta
Chief Engineer/South
Associate Editors
Social
Rajesh Agarwal
Executive Director/Projects/KRCL
Anand Prakash
Executive Director/IRCON
/kjrh ds gsekuo: 21
c<+rspyks : 21
Creative Editor
Sangrah Maurya
PROLOGUE
USBRL Project, as all of us are aware, is a railway line which will link rest of the country to Kashmir Valley a valley which has been hailed and
sung over centuries by poets as Paradise on Earth. But traditional wisdom also says that path to paradise is not easy to follow, building road for all others to
follow is much more difficult. It requires knowledge and skills to build and is full of hardships. This is what officers, eengineers,
ngineers, supervisors and staff have
silently borne while they have completed 136 km out of 271 km of the entire project. To accomplish this roads have been built and camps have been
established. Over years, bridges have been built and tunnels have been bored through mountains to lay a railway line. Each one of them are gems of technical
performance.
Those who are involved in this project, have in its course, endured isolation, extreme weather and difficult living condition s. This was possible by
sheer grit and determination of a handful of men and women and their families. This technical newsletter aims to give a voice to these engineers and their
teams a means to share their experience.
SurinderKaul
Chief Administrative Officer / USBRL
My association with Himalayas began early my childhood when I frequently travelled with my father through Gharwal and Kumaon Hills (now in
the State of Uttarakhand). While he would be discharging his official duties as a revenue officer, my sister and I would spe
spend
nd days in dak bungalows with our
mother watching streams flowing by in valleys down below or gazing at a bus or a truck winding around a distant mountain road. Here every bend springs
surprise leaving you spell bound by sheer power of nature. Every day you are awestruck be its enormity and complexity. Litt le could I have guessed that I
would be a member of a team entrusted with building a railway line across the same serene but difficult mountain landscape.
This magazine envisages to capture experiences technical and non-technical, challenges of project ranging from scientific to mundane, survival and
art of it, and the happenings around the project. In short, it traverses an eco-system which is Udhampur Srinagar Baramulla Rail Link Project or USBRL
Project.
This is the inaugural issue and like all beginnings this is a small step. As the time will pass thi
thiss will become a corner where memories will be kept.
Posterity will have a place to check how we did our work in office and after office hours. How engineers overcame technical challenges deep inside tunnels
or while building abutments on steep cliff faces over deep gorges or how did they would control slopes sometimes as crumbly as an apple pie. How their
families adapted to life in projects in such hostile environment. How they were blessed with endlessly beautiful sunrises an
and
d sunsets over snowy peaks or how
they weathered heavy thunderous downpours. How they spent hours in confines of their vehicles caught in middle of nowhere wh en road was blocked after a
landslide. How everyone got cut off in an unprecedented snowfall in Banihal for days without water, electric supply and supplies of food and how they were
forced to stay in beds for days just to keep warm. Or that lost snake who chanced in the guest house at Reasi. Just about eeverything.
verything. It will be the endeavour
of this magazine to see that every creative spark is nursed. I am sure that we shall be able to tell generation that come how this line was built and how t o build
more of them with Himalayas protecting our country in a fond embrace.
Experience of building an enormous bridge on river C
Chenab
henab and accommodating part of a yard of a railway station inside a tunnel are included in
this issue. Then a primer on earthquakes is a must for building anything in these mountains. Areas of interest in Laddakh rregion
egion will excite the travel bug of
readers while a short story and poems by members of USBRL team and their family members add colour and variety to otherwise ters e technical slant of this
magazine. Project news showcases progress being made and life around the project.
We shall look ahead towards a long and wonderful association with the entire USBRL panorama.
MOHIT SINHA
Editor-in-Chief
P R O J E C T
N E W S
# 2
# 3
Sub-Committee-I (Railways) of
the
Public
Accounts
Committee(2013-14), Headed by
Sh.PrakshJavadekar, visited the
project area and discussed the
Audit Report No. -19 on USBRL
Project on 24th and 25th Oct. They
were appraised about the status of
project and difficulties being
faced during execution.
Key
Officers of Northern Railway of
concern department and CMD of
IRCON and KRCL were also
present.
# 3 Social Gathering of officers and their families at Officers Rest House, Jammu
# 5
# 4
MOU signed
between
Northern
Railway and
IRCON for
Railway
Electrification
work of
BanihalBaramulla
section of
USBRL
# 8
7 67th
Independence day was celebrated at
CAO/USBRLs office at Satyam Comples, Jammu. Flag Hoisting
by Sh.R.K.Chaudhary, CEE/USBRL
# 9
Lining for tunnel T43 and T46 has been completed by KRCL.
4
# 11
# 12
Banganga Bridge
T E C H N I C A L
Power Supply Arrangements in Kashmir Valley
1.
Introduction:
Challenges/Constraints:
3.
6.
LT Distribution:
No Over Head Distribution lines have been used for Quarters and Service
buildings at Railway stations on this project. All 33 kV, 11 kV and LT Net work
have been laid through under-ground cables which is reliable as the break-down on
account of birdage, kite flying, damage of insulators by stone throwing, breakage
under snowfall etc have been eliminated. It has also improved ambiance
aesthetically. For this initiative also, Railway Board has issued the guidelines, for
laying of under-ground cables for new constructions in place of Over Head lines in
residential and Service buildings areas.
7. Conclusion:
The above initiatives have not only improved the electrical systems on this
project but also eliminated many maintenance problems, improved reliability of
systems, resolved right of way problem and achieved economy besides having
issued policy guidelines by Railway Board.
The series will continue. In next issue Tunnel Ventilation and E&M System of
T-80 will be covered and further issue SCADA system for Tunnel T-80 will be
covered.
By
R.K.Chaudhary
Chief Electrical Engineer/USBRL
Introduction
This topic covers the selection of type of bridge, introduction of bridge , special
design features and the team involved in the construction of Chenab Bridge
The Indian Railways has undertaken a mega project of construction of a new
Railway line in J&K state from Udhampur to Baramulla. The alignment is a culmination of
large number of Tunnels and Bridges in highly rugged and mountainous terrain with most
difficult Himalayan Geology. The alignment crosses deep gorges of Chenab River near 11
km upstream of Salal Hydro Power Dam, located in Reasi District of J & K.
Being the alignment near upstream of the Dam and initially lack of accessibility to
the bridge site, selection of type of the bridge to be constructed there was a great challenge
to this project team; because of too much height of formation level as well as span.
Earlier such a mega bridge on the most typical geology was not constructed in India
and therefore, engineers were very cautious about selection of type and shape and span
arrangement of the bridge. On this issue, a number of meetings were held to discuss the
various alternatives. At the last, a brain storming session comprising of experienced Civil
Engineers available in India, including Professors of IITs and Roorkee, was organized on to
decide the type, shape and span arrangement of the bridge. Consequently, steel structure
in Arch over river Chenab was the most preferred choice of the members owing to steels
ability to absorb earthquake forces without damage unlike concrete structure. The thrust of
the arch also stabilizes the side slopes of the river. It is easier to construct, maintain and
rehabilitate the steel structure compared to other structures.
55M + 2 X
65M + 10 x 48M + 65M
+55M + 40M + 9X50M +
40M
2.
1315.00
BakkalEnd:
By
Kamlesh Kumar
Deputy Chief Engineer/Chenab Bridge/USBRL
3.
:
:
:
:
:
:
:
:
1315 meters
MBG
120 years
100 Kmph
359 m
467 meters
25000 MT
266 kmph
+35 to 50 degrees
vertical
to
sub-
4.
a.
b.
Use of Concrete filled trusses: A steel arch is comparatively very light and would face stability problems against wind as maximum
wind pressure at Deck level recorded was 150 kg/m 2. Concrete filled trusses will help in improving stability of the arch, and also give
benefit of composite action between the steel arch and filled concrete thereby making the design more efficient. This feature is being
used for the first time in India. In this regard, a mock up trial of 9.0 m segment of Arch section was conducted at the site in March,
2010 under supervision of Technical Advisory Group (TAG) comprising of eminent Civil Engineers. They suggested to fill high
slump concrete in the Arch Box and established the composite action between filled concrete and Arch through studs fixed inside
surface in the box.
Structural Redundancy: This Bridge is vulnerable from security point of view as any damage to the bridge will not only cut of f the link
between two regions of Jammu and Kashmir but is also likely to provide wide pub licity to the anti-social elements. Hence a provision has
been made in the design for the following situations: If an element is removed
either from truss of the
arches or from steel
spandrel columns it would
still be possible to run the
traffic over the bridge at a
restricted speed of 30
kmph.
If one of the columns/steel
Pier collapses, the deck
would not collapse. It
would be possible to
restore the bridge for
normal operation after
carrying
out
required
repairs.
Artistic view of Chenab Bridge
5.
Blast load: The Bridge is designed for the Blast Load also. No standard code for Blast load on steel structure is available in the word.
Therefore, design criteria for Blast laod was decided after conducting study on the model of M S Plate of different size and thickness
supported on two I section with different inter separation distances. The explosive charge was detonated a t a distance from I section.
The response of the metal plate was determined using Autodene 3D software. Accordingly, parameters for design were decided by the
committee set up for the study.
Project Team: Agencies involved in the construction of Chenab Bridge are as under:
By
Hussain Khan
Executive Engineer/D-II/USBRL/Project
Bayonne Bridge
Status: World's fifth longest bridge. Longest in the world at the time of its
completion.
Type: Roadway-bridge; Type of Super-structure: Two Hinged spandrelbraced trussed arch.
Span Configuration :Main span of 510.54 meters (1,675 ft) and total
length of 1762-metre (5780 ft)
Carriageway/Track: The bridge carries 4 lanes of the NY 440 and NJ
440.
River: Kill Van Kull Strait.City :New Jersey, USA.
Opened :November 15, 1931; Cost $13M,US
Chenab Bridge
Status : world's Seventh longest spanning arch bridge (after Completion)
Type : Rail bridge
Type of Super-structure: Through concrete filled truss steel arch
Bridge.
Span Configuration :Main span of 467 meters (1532 ft) and total length
of 1315 meter (4315 ft)
Carriageway/Track: The bridge is 17 meter wide (over arch), carrying
single line Railway Track.
River: ChenabRiver.City :Katra, India.
Opened :under construction ; Cost : 5120 M,
10
Wushan Bridge
Status: world's eighth longest spanning arch bridge. (present)
Type : Road Bridge
Type of Super-structure: Concrete filled steel tube arch Bridge.
Span Configuration :
Main span of 460 meters (1510 ft) and total length of 616 meter (2021 ft)
Carriageway/Track: The bridge carries 4 lanes of road traffic,
River: Yangtze River.
City Chongqing, China.
Opened : 2005
Miugzhou Bridge
Status: world's ninth longest spanning arch bridge.
Type : Road Bridge
Type of Super-structure: Double leg half throughSteel box arch Bridge.
Span Configuration: Main span of 450 metres (1476 ft) and total length
of 650 metre (2132 ft).
River :YongjiangRiver.
Location Ningbo (Zhejiang) china.
Opened : 2011
Xinguang Bridge
Status: world's eleventh longest spanning arch bridge.
Type : Road Bridge
Type of Super-structure: steel arch Bridge.
Span Configuration: Main span of 428 metres (1404 ft).
River:Zhu Jiang River.
Location: Guanzhou, Guangdong, china.
Opened : 2008
Cost: 48 M $.
11
10
Part 1
PART 1
CAUSES AND ORIGIN OF EARTHQUAKE.
1.
Introduction
The magnitude 6.2 quake hit the island on Sunday (June 2),
damaging roads and infrastructure
Fig 1
By
Sangrah Maurya
Deputy Chief Engineer/Design/USBRL Project
The crust and the uppermost mantle, which constitute the hard
and rigid outer layer of the Earth is called lithosphere.
Part of the upper mantle that is hot and weak is called
12
asthenosphere
11
3.
Fig 2
Fig 3
Fig 4
Fig5a
Fig5b
Fig6a
Fig6b
Fig 7
12
4.
Fig 8
F IG 9
C. SOURCES OF EARTHQUAKE FIG 11
Sources of earthquakes if marked on global map are located along
the boundaries of these continental plates. Earthquake zones an d
volcanoes follow a pattern. They occur along the boundaries (edges)
of tectonic plates (form an outline).
Fig 10
PLATE TECTONIC THEORY-HOW THE CONTINENT MOVED
These plates are in motion; the lateral relative motion of the plates
varies from zero to 100 mm annually.
The current theory is that the continents moved due to the
movement of tectonic plates.
Tectonic plates = movable slabs of rock that make up the Earth
As already explained above lithosphere is cooler and more rigid, while
asthenosphere is hotter and flows more easily. The basic principal of plate
tectonic is that lithosphere is divided into separate and distinct plates,
which rides on fluid like asthenosphere.
Figure12 on next page shows major plates of earth and arrow indicates
their relative motion.
Fig 11
14
13
Fig 12
Sub-duction is defined as a process that takes place at
convergent boundary, by which one tectonic plate moves
under another tectonic plate and sinks into the mantle, point
A in figure below
Fig 13
or rub against each other then they are called transform boundaries e.g.
San Andreas fault in California. These are also called as conservative
fault as they neither create nor destroy Lithosphere. These faults end
abruptly and are connected on both ends to other faults, Figure 14.
created): when plates slides apart from each other e.g. mid ocean
ridges. Divergent boundaries within continents prod uce rift which
produces rift valley they also form volcanic island as molten lava rises to
fill the gap created as plates move apart.
14
Convergent boundaries
Figure 14
Fig 14
Figure below shows the boundary between two oceanic plates, the
African and South American plate (in the southern Atlantic basin) and
the Eurasian and North American plates (in the northern Atlantic
basin) kindly also refer to fig no 12 above. The two plates are moving
apart, hence constitute the Divergent Boundary. Two plates are
Eurasian Plate
African Plate
16
15
San
Andreas
Fault
San Andreas is a transform fault and extends roughly 1300 Km. it forms
a tectonic boundary between North American Plate and Pacific Plate.
This fault is responsible for notable earthquake of magnitude up to 7.9
in California (Fig below)
Pacific Plate
10. Earthquakes
After having understood geodynamics in brief, lets get back to our main topic i.e. Earthquake.
Earthquake or quake or tremor or temblor describes a seismic event either natural or man generated that generates seismic wa ves. These are caused
mainly by rupture of geological faults, but other events like volcano, landslide or nuclear test may also cause earthquake.
As seen above the plates move past each other along the fault line. Had the common boundaries of these plates been smooth then the plates could have
drifted past against each other without any resistance. Unfortunately most fault surfaces have irregularities or asperities along their surface, which results in high
frictional resistance along the fault plane or even locking. If the fault is locked, whereas there is continuous relative mot
motion
ion between the plates, leads to stress
accumulation which is stored as strain energy in the volume around the fault plane. As the plates moves the stress accumulates until it touches the threshold value
causing breaking of asperity. This breaking of asperity results in sudden sliding along the fault line aand
nd release of all accumulated strain energy.
17
16
SOME FACTS
Asperity
Defined as unevenness of surface, roughness, ruggedness
to be concluded
Earth has been balanced on one of the horns of holy cow. Tired of
holding the earth on one horn the cow shifts the earth to her other
horn. This is done by bouncing the earth from one horn to other.
This bouncing causes earthquake.
Poseidon, cause and God of earthquake in Greek mythology, struck
the ground with a trident when he is in bad mood. This causes
earthquake. He also uses earthquake to punish and inflict fear upon
people as revenge
In Japanese mythology, Namazu is a giant catfish which causes
earthquakes. Namazu lives in the mud beneath the earth, and is
guarded by the god Kashima who restrains the fish with a stone.
When Kashima lets his guard fall, Namazu thrashes about, causing
violent earthquakes.
In Norse mythology (North Germany), earthquakes were explained
as the violent struggling of the god Loki. When Loki, god of
mischief and strife, murdered Baldr, god of beauty and light, he was
punished by being bound in a cave with a poisonous serpent placed
above his head dripping venom. Loki's wife Sigyn stood by him
with a bowl to catch the poison, but whenever she had to empty the
bowl the poison dripped on Loki's face, forcing him to jerk his head
away and thrash against his bonds, which caused the earth to
tremble
LIGHTER MOMENTS
17
2.
The design consultant, M/s SJVNL has provided design of supports and
construction sequence for wider section tunnels having finished area of 87.96
m2. The design is worked out based on the consideration of rock mass of
poor to very poor quality. The rock load for the given size of opening and
geological conditions is estimated to be about 6.17 kg/cm2 (i.e. equivalent to
28 m of rock load).
The support elements are described as below:
At two ends of the yard, loop lines enter into the tunnels which necessitate wider
section of tunnels to accommodate double lines. The 55m long wider tunnel T40/41 from portal P-2 side has its portal at chainage 92/370m (Katra end). The
rock cover above portal is about 16 m and there after it increases to 37 m up at
chainage 92/300 m. Similarly the 70 m long wider tunnel T-42/43(Qazigund end)
from portal P-1 side has its portal at chainage 93/315m. The rock cover above
portal is about 19m and thereafter it increases to 37 m up at chainage 93/360m.
Rajesh K
DyChief Engineer
Konkan Railway Corporation Limited
Rajesh Agarwal
Executive Director/Projects
Konkan Railway Corporation Limited
Design Details:
2.3
Rock bolts:
Pattern rock bolts 32 mm dia., 8-10 m long were proposed at overt.
2.4
Steel Ribs:
Steel ribs ISHB 300 X 250 built up with additional flange plates (10mm
thick and 300 mm wide) were proposed. The space between the ribs was
required to be filled with backfill concrete or shotcrete using RCC lagging.
2.5
Temporary Concrete Invert:
Temporary concrete invert 30 cm thick was to be provided in the heading to
close the supporting ring in 1st and 2nd stage of excavation. This was to be
removed/sacrificed at the time of benching.
2.6
Final Support:
This was to be provided after the rock movements have stabilized.
Reinforced Concrete lining 530mm thick is proposed for final lining.
19 18
The main challenge was to execute the planned design for this wider section tunnels
in very poor and unstable strata.
To start with, the work of tunnel no T40/41 continued through single track section
from Katra end towards Qazigund direction, up to its interface with proposed wider
section tunnel. Once this location was reached, the excavation for wider section was
started in Heading for a length of 1.2 m to erect two ribs. After the fore poling, the
excavation was carried out from left to right to achieve full width of tunnel. The
excavated surface was shotcreted with steel fiber reinforced shotcrete (SFRS) to
provide initial support. Subsequently, pattern rock bolts of 32 mm diameter of 8-10
m long were provided.
20
As the proposed steel ribs ISHB 300 X 250 were not available in the market,
a built up section with ISHB 200 X 200 with 10 mm thick plate welded on
both flanges was used. These sections were brought to required profile by
cold bending method so that the steel property does not change. The sections
became heavier for erection as compared to the sections used for single line
tunnel with smaller ISHB, thus it warranted use of heavier crane for erection.
The curvature of steel rib was maintained by measuring versine on inner
surface with a 2 m overlapping chord along the profile at regular interval.
After placing of concrete lagging between ribs and completing backfill
concrete, next cycle was taken up.
The above advance was continued for 37m. Now the tunnel face was
reaching the fragmented strata with overlying loose overburden material.
Due to very poor strata a cavity was formed at this location which was
subsequently grouted and filled from the top. Further excavation was carried
out from outside i.e., P2 portal side, in heading and the break thorough of
tunnel was achieved on 07th Mar 2013.
Having gained this experience, similar work was carried out from Portal P1
for tunnel T42/43. The strata here too were covered with slope debris. The
excavation started in heading from outside at chainage 93/315m towards
Qazigund side and first rib was erected on 6th March 2013
When the excavation reached chainage 93/322m, a huge cavity was formed
leading to skylight on 20th of March 2013. This cavity was tackled from
inside the tunnel as well as from the top by grouting and filling with
concrete. The work proceeded in heading up to tochainage 93/385m which
was interface of single-line and double-line section. The breakthrough in
heading of tunnel T-42/43 is achieved on 27th August 2013. Further, the
benching excavation of this tunnel was carried out from 4th September 2013
and completed on 5th October 2013.
The above works were completed under difficult conditions where in field
engineers had to carry out certain modifications to the excavation scheme
proposed by Design Consultants.
19
21
20
S O C I A L
transmission provided by parents. After the child comes out of the womb
and enters the bigger world to the role of genetics is added, the role of
nature (including environment in various aspects) directly on a continuous
basis and they together produce GUNAS that in turn make ones nature or
trait.
Tamas are present in all human beings in varying degrees. The mixture of
three Gunas is peculiar and unique to each person. One is born with it. The
By
SunainaWalia
D/o ShParamjit Singh
AXEN/C/Reasi
Buy cake mix of your choice. You can buy chocolate cake mix. Then follow the
instructions given on the box of cake mix, to bake the cake. You have to make two cakes
one for the head and one for the ears. For the head, use a round cake pan. For ears, use a
separate pan big enough to cut out the ears. After the cakes are ready take a knife, and
carefully trim the top of both cakes. For the head, you dont have to do anything , so just
put it on a clean surface. For the ears take a knife and make the round ears. Now take a
toothpick and insert one on the side of one ear. Now insert the toothpicks into the side of
the head. Repeat this for the other ear. Now get some ready-made icing. Take a Ziploc bag
and cut a hole in the corner. Line the ears and head with the icing. Make eyes and the nose
with the same icing. After this is done put inside a fridge to let icing set and then cake is
ready to be cut !!
By
Tapashyu Shree Student-II,
DPS/JAMMU
D/o
ShKamlesh
Kumar,
Dy/CE/Chenab
c<+rspyks
djusgSa] dqNdkerks c<+rspyks]
ns'k dh ekVhdkslykedjrspyksA
,dmn~ns';] ,d y{; dh vksj c<+rspyks]
ns[kdjviusygwdk ,d&,ddrjk]
blikouekVhdksflaprspyksA
djukgS] cqjkb;ksadk [kkrekrks c<+rspyksA
ns'k dh [kfrjej&feVusdknkokrksgjdksbZdjrkgSA
gks [kwuesaftldsej&feVusdk ne] ml ohjdkslykedjrspyksA
fn[kkvksaviuscktqvksa dh rkdrdks]
cukvks ,slknskviusilhusls]
tksM+djgj ,d iRFkjdkscukvksa]
,d ,slhlqanjnqfu;k] ftllsjks'kugks] gjbUlku dh eqLdku]
,slkdkedjrspyksA
DjusgS] dqNdkrks c<+rspyks]
ns'k dh ekVhdkslykedjrspyksA
tquwu&,&vktknhlcds [kwuesaughagksrhA
;wa 'kgknrikus dh vkjtwalc ds [kwuesaughagksrhA
xje [kwudknkokrksgjtokudjrkgSA
mckykykl ds tksyk[kksaesa] oks xehZlcds [kwuesaughagksrhA
t; fgUnA
/kjrh ds gsekuo
/kjrh ds gsekuo /kjrh dh jkfrdksns[kksA
Ikzfriypyrhghjgrh] bllspyukrqelh[kksA
Lfjrkcgrhghjgrh] iFkLo;acukrhjgrhA
iFkesapV~VkuHkysgh] ijxfrmldhD;k #drh \
fnu&jkrlnkgksrkgS]O;ko/kku u blesagksA
_rq&pdzpykdjrkgS] ir>M+ clUrfQjgksrkA
lq[k&nq%[k dkvkuk&tkuk] txrhdkjksuk&xkukA
gj {k.kpyrkghjgrk] ;g gSbfrgkliqjkukA
fQjlq[k esaD;kbrjkuk] nq%[k ikdjD;keqj>kuk \
{k.kHkaxqjekuo&thou] fQjD;kjksuk] D;kxkuk \
Tkksvk;sgSa] tk;saxs] lansgughadqNblesaA
tks le; lqyHkgedksgS] mldksd`rkFkZgedjysaA
txrkgStxnh'oj ds] gkFkksadk ,d f[kykSukA
fuekZ.k&/oalosdjrs] gedksblesaD;kdjuk \
tksHkkjgekjsfljij] mldksgelnkfuHkk;saA
ihNs u dHkhge ns[ksa] vkxsgh c<+rstk;saA
ds0ds0feJk
[email protected]
lqjdksV]dkSM+h]
la/khjdqekj
dfu0vfHk0
22mieq[;vfHk;[email protected]
fj;klh
21
there and when the ant saw the clothes she said, these
clothes are very big for me to stitch, can you stitch these for
me? The elephant stitched them in 15 min. Then elephant
said, to make it stand we have to bring some strong logs of
wood from the main forest. I will go and bring them here,
and then we will together make the tent stand. Till the time
you clean and decorate your house. OK said the ant and
then the elephant left for the main forest. In the meantime the
ant decorated and cleaned the house, placed the table and
chair and cooked the food for the party.
When the elephant came they both together made
the tent stand and then the ant placed the tables and chairs in
the tent for sitting and also decorated with yellow rose, white
and blue silk cloth. Almost everything was ready and there
were only fifteen minutes left for the party and for the guests
to come.
Then the ant in the house and elephant in
the big tent, they both checked that everything is done and
everything was all right or not and everything was all right.
Just then the guests started coming.
The party went on and on and do you know the
party continued till what time. Party went on till 11:50 pm,
means only 10 min left for 12:00 am. As it was too late the
entire guest started going home. Then suddenly all the lights
of the tent were switched off and when they were switched
on, everybody was in with a beautiful cake. Oh! It was
elephants Birthday. All the guest gave their best wishes to
the elephant. The elephant thought, I am very foolish, I
forgot my own Birthday. They all sang Birthday song for
him and enjoyed very much.
Party
23
22
Ladakh opened for International Tourism. These areas are among the
outstanding feature of Himalayan Panorama. It could be yet another
destination for the tourists. These areas are relatively more distinct for
cultural and adventure tourism.
another
route
areas
Khalsi-Dumkhar-Dah-Sanjak-Chiktan-
Introduction.
Opened for tourism in 1974, with a tourist arrival of 527 the first year,
increased many folds since then. Tourist arrival has been recorded 11, 05,547 by
August 2013 end. The tourism industry is now an important and major socio-
festivals is the most popular festival in this area. These are considered rare
climatic and topographical conditions have made it a paradise for the adventure
lovers. Ladakh is a paradise for the trekkers, mountaineers, bikers, river runners
and motor safari. Ladakh is a complete tourist destination with choice of Cultural,
Spiritual, Adventure, Wild life and Health tourism. Some of the world record
attractions such as the highest motor able road of the world, the largest brackish
lake in Asia, the longest glacier outside pole, the world highest observatory are
great attraction and inspiration for the visitors. Some of the rarest species of wild-
lifeviz black necked crane, snow leopard, Himalayan Lynx etc. are confined to
Ladakh.
By
Hussain Khan
Executive Engineer/D-II/USBRL/Project
come out in their colorful traditional dress and festival moods to celebrate the
festivals. Preceding to the Drogpas villages the village which fall enroute are
and which tourists can also easily visit. There is a very good road leading
right up toDrogpa villages and tourist can stay overnight in some private
guest houses and or at some identified camping site at Khaltsi, Dhomkhar,
Skurbuchan, Achinathang, Hanu Do, Biama and Dha village.
CHANGTHANG (NYOMA DIVISION)
Over this region the tourist can travel on the following identified tour circuits.
1.
2.
3.
4.
24
23
Leh-Upshi-Depring-Puga-Tsomoriri Lake-Korzok
Leh-Upshi-Mahey bridge-Puga-Tsomoriri Lake-Korzok.
Leh-Karu-Changla-Durbuk-Tangtse-Lukhung-Spangmik-MaanMerak.
Leh-Upshi-Mahey-Nyoma-Loma bends.
The upland plateaus of Changthang in Nyoma Sub-Division are possibly the most
attractive areas in the District as far as scenic beauty, brackish lakes and Wild Life
are concerned. The vast pastures with their gently flowing streams and the lakes
amidst the spectacularly colored mountains are quite unlike anything a tourist see
anywhere in India.
THE PANGONG LAKE
This lake is situated at an altitude of 14,100ft. in the Eastern sector of Ladakh, at a
distance of 150 km from Leh
acrossChangla pass (17,000ft.).This lake is one of the largest and most beautiful
natural brackish lakes in the country
the traditional silk route. The caravans travelling Central Asia and Kashmir
through Nubra valley used to stay at those villages. Panamik was the most
important place for haltage of Caravan. It served as last major village
where the Caravans landed the facility of feedback, before they negotiate
Saseer and Karakoram passes towards Central Asia. The famous hot spring
of Panamik also served them as a source for bath, drinking water and
therapeutic purpose. Panamik has still got charms and potentiality to serve
waterfall across it combined with scenic view strengthen its beauty and
hospitality. Major attraction of Nubra is the highest motor able road
Khardongla pass (18,380ft.) majestic peaks and glaciers enchanting valleys
THE TSOMO RIRI LAKE
This lake is situated at a elevation of 15,000 ft. above the sea level, at a distance of
240 km from Leh in the South-eastern sector of Ladakh. It is like a pearl shaped
and contains large mineral deposits. Korzok village is situated on the South-west
bank of this lake. KorzokGonpa and its inhabitants nomads by tradition are most
outstanding features of this area.
NUBRA DIVISION
This valley is popularly known as Ldumra or the valley of orchard/flowers. It is
comparatively thicker than those of the other areas of Ladakh. Shrubs, bushes and
trees grow in abundance wherever there is any source of water. Due to this reason
Nubra has acquired its right name- Ldumra. Shayok and Siachan rivers forms fairly
large drain in Nubra. Nubra is a broad valley with lofty mountains on its all sides.
Valley assumes greater attractions at the site where both the rivers meet. The
formation of Central part of Nubra also takes place there. Diskit is the Sub-Division
Headquarter. OfNubra.DiskitGonpa is also situated at a height of about 200 mtrs.
Above the village, on the spur of rocky mountain and at the most commanding
point having clear view of the entire central part of
25
24
humped camel safari, river rafting, trekking and Sunbathe in the sand dunes
at Hunder are also a great attraction for the tourists.
INTRODUCTION
Cold environment forces the body to work harder to maintain its
core temperatures. The bodys energy is used to keep the internal
temperature warm. Thus blood will shift from extremities such as hands,
feet, legs & arms to the core of the body like chest & abdomen. Thus
allowing the exposed areas to cool rapidly & increases risk of frostbite &
hypothermia.
A significant amount of body heat can be lost through the exposed
head & neck area, especially in children.
Normal body temperature is around 98.60 F (370C).Hypothermia
happens when a persons body temperature drops below 950 F (350C).
When your body gets cold it will try to prevent losing more heat by:
Shivering, restricting blood flow to skin & releasing hormones to
generate heat. However, these responses use up energy and may not
be enough to maintain body temperature if you are exposed to cold for
long time. When the body runs out of energy, it gradually begins to shut
down. Shivering stops and heart beat starts to slow down leading to
reduced blood supply to vital organs.
SIGNS OF HYPOTHERMIA:
By
Dr.Steven George
Dy.CMO/KRCL/Reasi
26
25
Route length
Udhampur -Katra
25
Katra- Qazigund
128*
Qazigund -Baramulla
118
Ruling gradient
1 in 100
1 in80
1 in 100
Bridges
38
62
811
911
4210
13008
( km)
Max Curvature
Tunnels Length
( km)
Tunnels (No)
% Tunnels Length
Longest tunnel
5o
2.75 o
2.75 o
85 m
359 m
22 m
45 m
1488
10.9
7310
105
115.9
29
38
11.27 km
43.6
79.84
3.15 km.
20 m
Total
271
40 m
0
12 m
The Jammu Udhampur Srinagar Baramulla Rail Link Project was envisioned with a view to provide a reliable and alternate transportation system in
the state of Jammu and Kashmir and to connect the state and the Kashmir valley with rest of the Indian Railway Network. With the above vision,
Government of India planned a 326 km. long Railway Line. The Project was declared as a National Project in year 2008.
The Jammu-Udhampur-Katra-Quazigund-Baramulla Railway line is the biggest project in the construction of a mountain railway since independence.
From Jammu to Baramulla, length of the new rail line is 326 km. and it passes through the young Himalayas, one of the most geologically complicated
and challenging terrains in the world. The Geology, tectonic thrusts and faults, drainage and ground water of the region have great bearing on the
construction of this project.
Sites are remotely located, inaccessible and therefore difficult from logistic and topographic consideration.
Providing access to the work sites involves construction of large network of Access Roads, the most challenging job for completion of this project. In
particulars the stretch between river Chenab and Banihal is passing through a virgin territory and require construct of about 200 km of access road.
The alignment crosses deep gorges of Chenab River near Salal Hydro Power Dam, which necessitates construction of long span bridges. The Chenab
Bridge, 359 m above river bed, will be the highest bridge in the world, and longest span for BG Rail line with arch span of 467 m.
The project also involved construction of Pir-Panjal tunnel, the longest transportation tunnel of Indian Railways across PirPanjal range connecting
Jammu & Kashmir provinces of J&K State. The tunnel is located between the Banihalrailway stations in South and Qazigund in NorthTotal length of the
tunnel is 11.2 km with overburden of 1100 m. This tunnel had been completed and Section from Banihal to Quazigund opened to public by Honble
Prime Minister on 26.6.2013.
The stretch betweenKatra to Qazigund representing 128 km length is the most difficult part of this project. Almost 80% of length of this stretch is in
tunnel and 10% on bridges and rest on embankment.
Some of the special features of this stretch are:
Alignment in this stretch passes through the worlds one of the most difficult terrain, both in terms of logistics and geological strata.
Various type of geological formation are met with in this stretch having altogether different characteristic / properties.
Alignment running across major tectonic features such as Reasi Thrust, MurreeThrust,Panjal Thrust & Local faults
The structural discontinuities occurring in the form of faults, thrusts, shears and joints are likely to pose problems in the construction activities
along the rail alignment
Adverse climatic condition due to heavy snowfall in winter resulting in sub-zero temperature and reduced working period.
World most advance and modern technology is being used for construction.
26
Project Alignment
Station
Baramulla
Sopore
Hamre
Pattan
Mazhom
Km
118
110
103
94
86
Budgam
72
Pampore
54
Srinagar
Kakpora
Awantipora
Panzgam
Bijbehara
Anantnag
Sadura
60
49
38
32
25
18
11
Qazigund
154/0
Arpinchla
120
Banihal
Sumber
Sangaldan
Basindadhar
136
108
89
71
Dugga
61
Salal A
50
Katra
25
Salal B
Reasi Road
Chakrakwal
Udhampur
Ramnagar
Road
52
43
9
55/0
43
Manwal
32
Bajalta
11
Sanger
Jammu Tawi
22
0
Disclaimer
Him Prabhat, USBRL technical news magazine is published in good faith and can-not be held responsible in any way for inaccuracies in report / content that appear
in this publication and the views of the contributors may not be those of the editors. The opinions expressed by this magazine are not necessarily the views of the
editors/publisher, but of the individual writers. Unless specifically mention the articles and statements published in this magazine do not necessarily reflects the
views or policies of Northern Railway, Ministry of Railways or Govt. of India.
28
27