Statement
Statement
STATEMENT
afety
ervices
SS
Direct.com
Method Statements
Method statements are used as a means of demonstrating that the hazards
and risks associated with a particular task or series of tasks have been
properly considered and evaluated. Method statements should outline the
appropriate risk control strategies that are required to be implemented in order
to ensure the health, safety and welfare of the workforce and others affected
by the works. A method statement can only be prepared once the potential
hazards have been identified and the risks assessed. This therefore requires
the completion of a properly considered risk assessment for each activity, or
series of activities, which identifies not only the hazards, but also the required
controls measures that are necessary to manage the residual risks.
The following method statement template can be used to formulate and
structure method statements for specific tasks and activities, though it should
be noted that every situation would require a site-specific method statement.
Generic method statements cannot be prepared, as every site/situation will
differ to a larger or lesser extent. The template has been developed so that all
of the information required for a method statement can be set out in a logical,
easy to understand format. This aids not only those preparing and reviewing
method statements, but it also helps in the communication of the information
contained within the method statement to those who are carrying out the work.
The pages following the template provide further information and guidance on
the type of information that should be included within a method statement.
When preparing method statements, reference should be made to the controls
and requirements of the risk assessments, together with other guidance
contained within HSE publications and guidance. Method statements should
address all of the major issues whilst avoiding irrelevant material, which is not
applicable to the specific situation.
The requirement for method statements (or safe systems of work) is not new.
Section 2 of the Health and Safety at Work etc Act 1974 requires all
employers to ensure safe systems of work, a safe place of work and a safe
working environment etc.
afety
ervices
SS
Direct.com
Ref No.:
Project Name:
Henrietta Road
Site Address/
Location:
Personnel involved:
Project Ref:
Ash/11/01
Start Date/Time:
July 2011
Finish Date/Time:
August 2011
Name
Scott Propert
Barry Propert
Matthew Propert
David Propert
Guy Comley
Brian Kimber
Role/Trade
Works Supervisor:
Scott Propert
Role:
Director
Tel:
07885406310
Key Materials
Required:
(ie: access platforms/winches/ladders etc)
Other Essential
Equipment:
Specific Identified
Residual Hazards:
Specific Staff
Training
Requirements:
afety
ervices
SS
Direct.com
1. Plan the works and select the required plant and equipment. Have
induction from site supervisor.
2. Pre start procedures:
Disconnection of services (outside of work area) prior to work start,
without interruption to live services to any other buildings. Live drains
which are not be damaged should remain live. Stoppers should be
placed into disused manholes to prevent blockages from demolition
materials. A water supply should remain for dust suppression of
demolition materials.
3. Sequence of demolition work remove all non hazardous materials
from buildings and place in designated skips. Remove all asbestos,
non-notifiable material, by firstly dampening with water and place in
licence skip.
Sequence of
Operations:
(Specifying methods of
working, tools, materials and
equipment utilised)
4. Erect scaffold to all houses and remove tiles. Place aside on pallets.
Remove roof timbers. Set aside for salvage/waste. Remove Ashlar
stone and set aside for salvage/waste. Dismantle and remove scaffold.
Remove floor boards and joists with 360 excavator fitted with grapple.
Set aside for salvage/waste.
5. Remove remaining Ashlar stone and set aside for salvage/waste. All
remaining hardcore will be removed from site for recycling.
6. Remove ground floor joists with 360 excavator fitted with grapple, set
aside for salvage/waste.
7. Dismantle all outbuildings separating waste with 360 excavator fitted
with grapple.
8. Clean remaining area ready for archaeological dig.
9. Upon completion meet with client to check that completion of works had
been achieved and carry out further works if required.
10.
(If none, state none.)
Temporary Supports
and Props needed to
facilitate the works:
Method of Access
and Egress to the
work area:
Fall Protection
Measures:
afety
ervices
SS
Direct.com
Hazardous
Substances:
(Attach COSHH Assessments
and MSDS)
Applicable:
Very Toxic
Harmful/
Irritant
Corrosive
Dangerous
for the
environment
Oxidising
Highly
flammable
Explosive
No
No
No
No
No
No
No
(Detail any limits on the loadings applicable to temporary plant/equipment or fixed elements of the
structure where the work is taking place.)
SWL's:
Other:
1. Hi-Viz
Required Personnel
Protective Equip.:
Emergency
Procedures:
First Aid
Facilities:
2. Coveralls
Safety
Boots
Hard Hats
Safety
Gloves
Hearing
Protection
Respiratory
Protection
Eye
Protection
Yes
Yes
Yes
Yes
Yes
Yes
3.
FIRE If minor, immediately sound alarm and alert all those present within
the premises and tackle same with on site fire extinguishers. Call 999 if
not brought under immediate control. If major, evacuate building and call
999. Report in accident book and RIDDOR. Notify H&S Advisor to
investigate. ACCIDENT Report immediately to site supervisor. Action to
be taken as per company Health and Safety Policy.
Name of On-Site First Aider:
Site Office
All lorries will use a Banksman to enter and leave site, making sure all
wheels are clean and loads are safe.
afety
ervices
SS
Direct.com
All work will be undertaken by qualified competent persons with experience of the
type of work described above, and in all cases in full accordance with safety
procedures specified in the companies Health and Safety Policy.
Prepared by:
Position:
Date:
Reviewed by:
Position:
Date:
afety
ervices
SS
Direct.com
We (the undersigned) have read and understood the attached method statement and
will comply with the specified requirements and control measures. If the work activity
changes or deviates from that originally envisaged, we will seek further advice and
request an amended method statement.
Name (Print)
Signature
Date
afety
ervices
SS
Direct.com
Details of supervisory personnel on site who will be responsible for the work.
2.
Where applicable details of Safety Consultant and their name and telephone number.
3.
Details of any personnel not involved on site but who can be contacted regarding design or other specialist
information if necessary.
4.
Work sequences.
5.
Stabilisation of the works during their progress e.g., any temporary props, struts or supports that are
required.
6.
The method of executing the works, which will include methods of lifting, fixing, holding or bolting.
7.
Methods to prevent any falls from heights. Full details should be given i.e. working platforms, handrails,
safety harnesses or other means of preventing falling.
8.
Access and egress to the job, i.e. by ladders, mobile work access platforms, hoists etc. Also specify the
location of any ladders or other means of access.
9.
Methods of protecting materials falling from heights i.e. toe boards, debris/brick guards, boarding on
platforms etc.
10. The description of plant to be used in the execution of the work, its safe working load and details of any
tests, certificates, inspections/registers which are applicable.
11. Details of what to do in case of emergency. This would include details of first aid and names of qualified first
aiders.
12. Details of storage and the stacking of items on site together with any delivery procedures and any assembly
work that is going to be carried out.
13. Detailed calculations for any loading of platforms, props, temporary works or supports that are to