Second Surveillance Audit Report: Agrasen Engineering Industries LTD.
Second Surveillance Audit Report: Agrasen Engineering Industries LTD.
Second Surveillance Audit Report: Agrasen Engineering Industries LTD.
Report No
R/91/072/004
Page No.
The Quality Centre, 16a Loyalty Road, North Rocks, Sydney, NSW 2151, Australia
Audit Date(s)
1 of 3
23rd April2000
AUDITED
SITE(S):
G 516 to 518, Road no. 9 A, V. K. I. Area, Jaipur 302 013. Rajasthan, India.
STANDARD:
CLIENT:
ISO-9002 : 1994
As above
SCOPE OF AUDIT / CAPABILITY
Scope :
Report No
Page No.
The Quality Centre, 16a Loyalty Road, North Rocks, Sydney, NSW 2151, Australia
Clause
ISO
9001 & 2
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
4.13
4.14
4.15
4.16
4.17
4.18
4.19
4.20
Clause Title
Management Responsibility
Quality System
Contract Review
Design Control
Document & Data Control
Purchasing
Control of Customer Supplied Product
Product Identification & Traceability
Process Control
Inspection & Testing
Control of Insp., Measuring & Test Equip.
Inspection & Test Status
Control of Non-Conforming Product
Corrective & Preventive Action
Handl., Storage, Packag., Pres., & Delivery
Control of Quality Records
Control of Quality Audit
Training
Servicing
Statistical Techniques
Clause Status:
S = Satisfactory,
Ma = Major,
R/91/072/004
Clause
Status
*
S
S
S
NA
Mi
Mi
NA
S
S
S
S
S
S
S
S
S
Mi
S
NA
S
Audit Date(s)
2 of 3
23rd April2000
Comments:
It was verified that all previous CARs raised were closed within the agreed time frame.
The dates on which these CARs were closed by the client has been noted on the individual CAR.
During this surveillance audit, 3 additional CARs have been identified and await closure.
Corrective actions and target dates for completion have been provided by the client. No abnormal
use of the ISC logo was noticed. Also Customer complaints register was being maintained and
corrective/preventive actions were found to have been taken.
FORM 5 AUDREP 1
ISSUE 1 REV 2
Report No
R/91/072/004
Page No.
3 of 3
23rd April2000
Audit Date(s)
SUMMARY OF AUDIT
Second Surveillance Audit of Quality System of Agrasen Engineering Industries Ltd. - Jaipur, was
conducted on the above date by International Standards Certifications in accordance with the
requirements outlined in ISO Standard 10011.1. The purpose of the audit was to verify compliance of
the implemented system to the requirements of the Company Quality Manual, associated procedures
and ISO 9002:1994.
The System Audit Plan and the Audit Attendance Register identifying those present during the entry
and exit meetings are recorded and kept in file.
The Management has appreciated the improvements identified during the audit. The auditors observed
that of 3 CARs were raised in this audit. Corrective action and their completion dates have been
provided for CARs. The details of CARs raised are as follows:
4.5 Documents and Data Control
The System does not ensure that
a) Binding of the Quality Manual Edition 2 is suitable for change/revision.
b) Documents are issued in full as authorised by the approving authority. (QM Sec. 4.10 was issued to
S.V.).
c) Amendment sheet shows correct amendment status of documents.(Viz. Amendment sheet dtd.
14.1.2000 shows amendment dtd. 05.04.2000)
4.6 Purchasing
The System does not ensure that
a) Sub Contractor is included in the subcontractor/Vendor list only after registration as per procedure.
b) Purchase order is placed only on approved Sub Contractor as per Procedure.
(Viz. P.O. placed on Garg Bardena Store.
4.17 Control of Internal Quality Audit
The System does not ensure that
Internal Audit NCs are properly verified for corrective action before close out.
(NC regarding non conforming product disposition was closed by saying new format is developed, no
new format was found included in Master list of format.)
CONCLUSION
The basics of the system were found to have been maintained. Immediate future efforts will be required
in coming months to improve the system further. The auditor observed that since no major nonconformity has been identified in this surveillance audit, the certification continues until next
surveillance audit.