RCC Construction, RCC Mixes, RCC Instrumentation & RCC Dams Studied
RCC Construction, RCC Mixes, RCC Instrumentation & RCC Dams Studied
RCC Construction, RCC Mixes, RCC Instrumentation & RCC Dams Studied
QHW SHAW
PhD THESIS
CHAPTER 2
2.
2.1.
INTRODUCTION
The research and investigations addressed in this Thesis relate entirely to the
behaviour and performance of Roller Compacted Concrete in dams. In view of the
fact that many of the observations made and the hypotheses presented relate to the
nature of RCC as a material and the methods applied for construction, it is
considered appropriate to provide the reader with some background on RCC in
these areas. Consequently, Chapter 2 presents a background for RCC construction,
describing the typical composition of RCC, isolating specifically the high-paste
RCC that is of particular interest, the methods applied for construction and their
influence on instrumentation readings and the instruments installed.
Each of the five dams whose instrumentation data are investigated during the
course of this study is subsequently introduced.
2.2.
2.2.1
BACKGROUND
2.1
University of Pretoria
QHW SHAW
PhD THESIS
MODERN RCCS
Modern RCCs are primarily designed in accordance with two different approaches(2):
The overall approach, which relies on the dam body for water-tightness
through high quality concrete and treatment to ensure well-bonded layer and
lift joints.
The majority of RCC dams contain mineral admixtures, most commonly fly ash, as
an active constituent of the concrete.
Beyond the basic requirements of strength, a modern RCC mix is defined by the
paste/mortar (p/m) and the sand/aggregate (s/a) ratios, the maximum size
aggregate (MSA) and the modified Vebe time. These parameters essentially relate to
the achievable density (and impermeability), the achievable compaction ratio and
the tendency of the constituent materials to segregate during handling. Under
construction conditions, the aforementioned properties determine workability and
the difference between permeable, stoney RCC, with planes of weakness and a
cohesive, seamless watertight and dense RCC. For the overall approach, mixes
are designed for maximum density, with a paste/mortar ratio of at least 0.37 being
required to achieve a density of 98.5% of the theoretical maximum solid density.
In modern RCC practice, a tendency to use a MSA of 37.5, or 40 mm has developed,
as larger sizes demonstrate a tendency to segregate in an RCC mix during handling
operations. While early RCC testing suggested that a lower sand/aggregate ratio
was optimal for RCC, compared to conventional vibrated concrete (CVC), practical
experience in the interim has demonstrated that quality control and the
maintenance of RCC consistency is much more realistically achieved in an RCC
with a sand/aggregate ratio exceeding 0.35.
The workability of RCC is determined by testing with the Vebe apparatus, which is
modified to include a surcharge mass of 19.1 kg. For workable RCC, the modified
Vebe time should lie between 10 and 20 seconds. For high-workability RCC, a
modified vebe time of 8 to 15 seconds is usually specified. In the case of lean RCC,
the modified Vebe time generally exceeds 30 seconds.
2.2
University of Pretoria
QHW SHAW
PhD THESIS
With a very significant number of approaches attempted during the early years of
development, three primary concepts emerged for the design and construction of
RCC dams:
The lean RCC dam; for which the cementitious materials content is <
100 kg/m3. For such mixes, often only Portland cement is used without
mineral admixtures, or pozzolanic material.
The RCD method (roller compacted dam) unique to Japan; for which the
cementitious materials content is generally 125 kg/m3, but only the hearting
zone of the dam is RCC.
The high-paste RCC dam; for which the cementitious materials content is >
150 kg/m3.
In the case of high-paste RCC, the RCC material itself provides the watertight
barrier and must be designed for an in-situ permeability equivalent to that of
traditional dam mass concrete. The RCC and the associated construction methods
must further be designed to ensure effective bond between layers. Various facing
systems are applied for high-paste RCC dams, but with the simple objective of
creating a good and durable surface finish. Transverse joints are induced at predetermined intervals, which are generally wider than is the case on a conventional
vibrated mass concrete dam.
In early RCC dam construction, a particular problem was recognised as low bond
between successive placement layers. Whilst a relatively high shear friction angle
could generally be assured between layers under all circumstances, low cohesion
and tensile strengths were compounded by high permeability when a new layer was
placed on an excessively mature existing layer. Development in the interim has
included the use of set retarding admixtures and the use of sloped and noncontinuous layer placement methods to ensure the freshness of the underlying RCC
layer when the subsequent layer is placed.
While such practices are only
implemented where required as part of the dam design, the result is a seamless
bond between successive RCC placement layers, with joint properties equivalent to
the parent RCC properties.
2.2.3
In the case of lean RCC, the material itself is not designed for impermeability and
consequently the requirements for aggregate gradings are not necessarily as
prescriptive as would be the case for CVC, although density is always important in
the case of a dam.
Lean RCC is also often referred to as a dry consistency mix RCC. With similar water
contents to high-paste RCC, i.e. 100 125 litres/m3, aggregate contents are
obviously relatively high. To ensure consistency and ease of compaction under
construction conditions, lean mix RCC often contains a high proportion of aggregate
fines (often around 8% of the total aggregate content)(3) that form part of the paste
fraction.
2.3
University of Pretoria
QHW SHAW
PhD THESIS
Portland
Cement
Fly Ash
Water
Coarse
Aggregate
Fine
Aggregate
Air
60 - 70
0 - 40
100 - 125
1500
825
21
113
545
300
12
Ignoring the aggregate fines, the typical lean mix above would contain
approximately 140 litres of paste per m3 of concrete. Including 8% fines in the
aggregates, the total paste would be of the order of 200 litres.
In view of the fact that high-paste RCC is designed for impermeability, maximum
density is important and consequently a continuous aggregate grading is applied.
For the latest high-workability RCC mixes, more restrictive aggregate specifications
than required for CVC are applied, with lower compacted void ratios and tighter
restrictions in respect of aggregate shaping and flakiness. For all high-paste RCC,
aggregates of suitable quality for use in a 30 MPa concrete are required.
A typical high-paste RCC comprises the following materials proportions:
Constituents
By Mass
(kg/m3)
By Volume
(litres/m3)
Portland
Cement
Fly Ash
Water
Coarse
Aggregate
Fine
Aggregate
Retarder
60 - 70
140 - 150
100 - 125
1400
800
21
63
113
510
290
RCC CONSTRUCTION
A number of different approaches exist for RCC placement, but the essential
principle is to place and compact 300 mm (compacted) layers as rapidly as
practically possible, creating a monolithic mass either by placing successive layers
before the first set of the previous layer, or by binding layers together with a
bedding mortar, or concrete. RCC is generally placed continuously between
upstream and downstream formwork and the abutments, with no expansion joints
and with induced joints at predetermined intervals to accommodate long-term
shrinkage and creep and thermal contraction due to temperature drop loads.
While it is optimal to place RCC as continuously as possible, without interruptions,
practical circumstances and breakdowns often necessitate breaks, when a cold
joint is formed and the compacted RCC surface must be green-cut and treated
with mortar, or grout before placement above is resumed.
2.4
University of Pretoria
QHW SHAW
PhD THESIS
Compaction is achieved
with 10 to 15 tonne,
single-drum
vibratory
rollers generally applying 4
passes in either direction
to achieve the target
compaction. The behaviour
of lean RCC and highpaste RCC under vibratory
compaction
are
quite
different; with the former
consolidating to form a
hard and flat surface and
the latter producing a
live surface, particularly
when the set is retarded, into which the
2.5
University of Pretoria
2.2.5
QHW SHAW
PhD THESIS
DOWNSTREAM
FACE
INSERTED PLATES
CRACK DIRECTORS TO BE
INSTALLED IN EVERY 4th
LAYER ON INDUCED JOINT
Figure 2.1: Induced Joints Cut into RCC every 4th Layer
2.6
University of Pretoria
QHW SHAW
PhD THESIS
FRONT-END LOADER
REMOVE
TIMBER PLANK
UNCOMPACTED RCC
PLASTIC SHEET
WITH PERFORATED PIPE
7t DOUBLE DRUM
VIBRATORY ROLLER
UNCOMPACTED RCC
University of Pretoria
QHW SHAW
PhD THESIS
INSTALLED
CRACK DIRECTORS
ALIGNMENT OF
INDUCED JOINTS
VIBRATING
BLADE
FRESHLY
COMPACTED
RCC
GALVANISED
STEEL SHEET
250
GALVANISED
STEEL SHEET
2.8
University of Pretoria
QHW SHAW
PhD THESIS
University of Pretoria
QHW SHAW
PhD THESIS
joint inducers are only installed in every second, or fourth layer in the dams
investigated as part of this study, their presence will not reduce the overall
resistance of the RCC mass to thermal expansion, nor will it cause any perceptible
increase in the overall compressibility of the full joint, but it will undoubtedly give
rise to increased local compression across the actual de-bonded section of the joint
2.3.
RCC INSTRUMENTATION
2.3.1
GENERAL
The instrumentation installed in the dams addressed in this study was designed to
fulfil two specific purposes; to monitor the overall performance of the dam structure
with a view to ensuring continued dam safety and to monitor the behaviour of the
constituent RCC.
The dam safety instrumentation comprised pendulums,
displacement survey systems, load cells, pore pressure meters and seepage
measurement weirs, while the RCC-specific instrumentation comprised long-basestrain-gauge-temperature-meters (LBSGTMs), strain gauges, temperature gauges
and thermocouples.
Instrumentation installed in RCC was generally developed for use in soils and for
monitoring geotechnical structures, etc. Accordingly, it is of a robust construction
and only instruments and measurement systems that have proved accurate and
reliable in conditions in which heavy equipment operates are installed in RCC
dams.
2.3.1
THE INSTRUMENTS
2.10
University of Pretoria
QHW SHAW
PhD THESIS
The first gauges used by DWA were tested under the direct action of a 10 tonne
vibratory roller(6) and were demonstrated to remain operational and to continue
providing accurate measurement no matter how roughly they were treated. The
continued operation of the vast majority of these gauges at Wolwedans Dam after
some 20 years is testament to their robustness.
The Geokon Model 4210 gauge used for measuring strain is a particularly robust,
all-stainless steel-cased instrument that is designed for direct installation into
concrete with large aggregate and indicates a measurement sensitivity of
0.4 microstrain and an accuracy of 1%. The gauge also measures temperature
and the gauge readings must be adjusted to indicate actual concrete strain.
2.11
University of Pretoria
2.3.2
QHW SHAW
PhD THESIS
INSTRUMENT INSTALLATION
2.12
University of Pretoria
2.4.
QHW SHAW
PhD THESIS
The central focus of the work presented in this Thesis is the data recovered from
instrumentation installed in the Wolwedans and Knellpoort Dams in South Africa,
ine Dam in Turkey and Wadi Dayqah Dam in Oman. On the basis of the
interpretation of this data, the behaviour of the constituent RCC is observed over
periods varying from several months to several years. Behavioural observations
from Changuinola 1 Dam, currently under construction in Panama, are also
addressed herein.
2.5.
WOLWEDANS DAM
2.5.1.
INTRODUCTION
Wolwedans Dam was completed in early 1990 and was the first RCC dam in the
world to rely fully on three-dimensional arch action for stability. The dam is 70 m
high, has a crest length of 270 m, an upstream face arch radius of 135 m and
comprises approximately 200 000 m3 of concrete. The dam was constructed with
induced joints at 10 m spacings, de-bonding every 4th layer with inducers installed
during placement and the RCC was placed in October and November of 1988 and
between May and November of 1989. The first season involved the placement of the
bottom 15 m of the dam, while the second encompassed the placement of the
remaining 55 m. RCC placement for Wolwedans was achieved over a total period of
approximately 7.5 months, with a peak daily rate of 2994 m3 (7).
The dam first filled to capacity during 1992 and the induced joints were grouted
during late winter in 1993. With a full storage volume of 64% of the Mean Annual
Runnoff (MAR), a high supply assurance requirement and a relatively high
catchment rainfall, Wolwedans Dam is subject to consistently high water levels.
The dam has spilt on several occasions to date and discharged a relatively large
flood just two years after completion.
The composition of the high-paste Wolwedans RCC mix was as follows(7):
Constituents
By Mass
(kg/m3)
By Volume
(litres/m3)
Portland
Cement
Fly Ash
Water
Coarse
Aggregate
Fine
Aggregate
Air
58
136
100
1510
625
18.5
63.5
100
565
240
13
Ignoring aggregate fines, the Wolwedans RCC comprised 182 litres of paste and 805
litres of aggregates. The blend of 75% crusher and 25% pit sand contained only
1.3% of fines and accordingly, the paste volume was only increased by 3 litres/m3.
With a low sand/aggregate ratio of just 0.3, the paste/mortar ratio was
correspondingly high, at almost 0.44.
2.13
University of Pretoria
QHW SHAW
2.14
PhD THESIS
Figure 2.4:
Layout of Wolwedans Dam(7)
University of Pretoria
2.5.2.
QHW SHAW
PhD THESIS
WOLWEDANS INSTRUMENTATION
Being one of the first two structures of its type and dependent on arching for
stability, a very comprehensive network of structural and thermal monitoring
instrumentation was installed within the body of Wolwedans Dam (see Figure 2.11
at the end of this Chapter and Figures C1 to C4 in Appendix C). Virtually all of
the instrumentation installed during construction is still functional and a central,
remotely interrogated control system allows real-time monitoring of the dams
performance and behaviour.
LBSGTMs were installed across all induced joints at four different levels and these
instruments formed the core of the system for monitoring the thermal/structural
behaviour of the dam structure. With a lowest foundation elevation of RL 33 m and
a NOC elevation of RL 103 m, instrumentation was installed at elevations
RL 40.25 m, RL 52.25 m, RL 66.25 m and RL 84.25 m.
The lowest level of instrumentation was installed approximately at mid-height of the
first RCC cast during October and November 1988.
The second level of
instrumentation was installed just 4.25 m above the bottom level of the RCC placed
during 1989. The third level of instrumentation was installed at approximately mid
height, 33 m above lowest foundation level. The top level of instrumentation was
installed at the level of the top gallery, implying that instruments were installed 2 m
from an external surface on one side and 2.75 m from the gallery on the other.
2.5.3.
In view of the fact that the dam structure at Wolwedans was constructed in two
distinct parts(7), separated by a substantial break, it is not considered that the full
structure behaves entirely monolithically with respect to temperature and hydration
2.15
University of Pretoria
QHW SHAW
PhD THESIS
heat dissipation. Two specific issues are considered of importance in this regard;
construction of the first part during the summer months and initiation of the latter
part in winter and the fact that the instrumentation installed at elevation
RL 40.25 m suggests that almost all of the hydration heat from the bottom section
had been dissipated by the time that the construction of the upper section was
initiated. Correspondingly, the instrumentation data at elevations RL 40.25 m and
RL 52.25 m are likely to have been influenced significantly by the extended
interruption in construction that occurred at RL 48 m.
With only 2 rows of LBSGTMs and surface cover of just 2 m to the outside and
2.75 m to the gallery, it is considered that the readings in the highest level of
instrumentation (RL 84.25 m) will substantially reflect surface zone temperatures
and effects. In the third level of instrumentation (RL 66.25 m), however, foundation
restraint will not be a significant influence, while the dam wall thickness is
approximately 21 m, which the instrumentation records demonstrated to be
sufficient to limit the core temperature variation over a typical annual cycle to
approximately 2oC, while still allowing all of the hydration heat to be dissipated
within 2 years after dam completion.
The induced joints at Wolwedans Dam were grouted in two phases, between July
and November 1993. With the impounded water level dropped by 8 m during the
latter part of the period, grouting to mid dam height (RL 66.25 m) was completed
over the winter months of June to August. With the dam filled to capacity once
more, the top half of the structure was subsequently grouted over the Spring and
early Summer months of September to November. It is significant to note that while
a net upstream crest movement of the order of 2.5 mm was recorded when the
water level was drawn down, equivalent displacements in the upper gallery were of
the order of only 0.5 mm and no associated movement was really apparent on any
of the induced joint instruments. At the time that the induced joints were grouted,
it is apparent from the displacement data records that the dam crest was displaced
downstream by a maximum of well over 10 mm, indicating that the structure was
already subject to a significant temperature drop and that the grouting merely filled
open joints and did not serve a significant purpose in alleviating the impact of longterm temperature-related loading.
2.6.
KNELLPOORT DAM
2.6.1.
INTRODUCTION
Knellpoort Dam is also in South Africa and was designed in parallel with
Wolwedans, but construction was initiated earlier and completed over a shorter
period, as concrete volumes were relatively small. Although this 50 m high dam is
defined as an arch/gravity structure, arching is only incurred under extreme
loading conditions and, as an off-channel storage dam, with a large capacity
compared to the natural catchment inflow, hydrostatic loadings are generally low.
2.16
University of Pretoria
QHW SHAW
PhD THESIS
The main part of the dam is aligned on a circular arch and has a vertical upstream
face and a downstream face sloped at 0.6 horizontal to 1 vertical. The left flank
comprises a straight conventional gravity structure. The combined crest length
measures 200 m.
The 60 000 m3 of concrete comprising Knellpoort Dam was placed over a single
winter season during 1988. Induced joints were aligned radially at a 10 m spacing
on the upstream face, de-bonding every 4th layer with inducers installed during
RCC placement.
Portland
Cement
Fly Ash
Water
Coarse
Aggregate
Fine
Aggregate
Air
61
142
108
1610
685
19.5
66
108
555
245
6.5
Ignoring aggregate fines, the Knellpoort RCC comprised approximately 195 litres of
paste and 800 litres of aggregates. Again, a low sand/aggregate ratio of just 0.3
gives rise to a high paste/mortar ratio of 0.44.
A basic layout of Knellpoort Dam is provided in Figure 2.5.
2.17
University of Pretoria
QHW SHAW
2.18
PhD THESIS
Figure 2.5:
Layout of Knellpoort
Dam(8)
University of Pretoria
QHW SHAW
PhD THESIS
Knellpoort Dam was constructed primarily over a particularly cold winter in 1988.
The temperature at which the RCC at any particular location in the dam body was
placed, or effectively insulated by RCC placed above, was frequently below 15C. In
view of the fact that the long-term temperature at the core of the dam structure
varies seasonally between 13 and 16C, the difference between the average longterm core temperature and the average built-in temperature is minimal, as
indicated in Figure 2.6.
35
RCC TEMPERATURE ( C)
30
25
"CORE" TEMPERATURE
LONG-TERM MINIMUM TEMPERATURE
20
15
PLACEMENT, OR "BUILT-IN" TEMPERATURE
10
1988
1989
1991
1990
1992
1993
1994
DATE
2.19
University of Pretoria
2.7.
INE DAM
2.7.1.
INTRODUCTION
QHW SHAW
PhD THESIS
Portland
Cement
Fly Ash
Water
Coarse
Aggregate
Fine
Aggregate
Air
By Mass
(kg/m3)
85
105
115
1406
791
By Volume
(litres/m3)
27
46
115
516
290
Fines
(l/m3)
Aggregate
(l/m3)
Paste/
Mortar
Sand/
Aggregate
49
806
0.40
0.36
D10 Mix
Net Paste
(l/m3)
193
2.20
University of Pretoria
Constituents
QHW SHAW
PhD THESIS
Portland
Cement
Fly Ash
Water
Coarse
Aggregate
Fine
Aggregate
Air
By Mass
(kg/m3)
75
95
120
1590
586
By Volume
(litres/m3)
24
41
120
586
218
11
Fines
(l/m3)
Aggregate
(l/m3)
Paste/
Mortar
Sand/
Aggregate
36
804
0.46
0.27
D05 Mix
Net Paste
(l/m3)
185
INE INSTRUMENTATION
As previously mentioned, the RCC for ine Dam was placed between October and
April of each year from 2004. Each season saw the placement of approximately
300 000 m3 of RCC, with the levels listed in Table 2.1 being achieved at the end of
each placement in April. The surface of the RCC at this level was subsequently
exposed to the elements, until placement resumed the following October.
2.21
QHW SHAW
Figure 2.7:
Illustrative Layout of
ine Dam(11)
University of Pretoria
PhD THESIS
2.22
University of Pretoria
QHW SHAW
PhD THESIS
This thermal analysis will not be addressed in detail in this study, as the related
results have no specific relevance. However, it is important to note that a very good
correlation was evident between the temperatures within the dam predicted by the
finite element thermal model and those measured on the prototype structure and
this is illustrated in Chapter 4.
Table 2.1: RCC Progress at ine Dam
Placement Period
Level Achieved
(m ASL)
147.50
166
187
208.25
232
February 2005
265 (completed)
April 2006
University of Pretoria
QHW SHAW
PhD THESIS
April 2007
April 2008
February 2010
Figure 2.8: ine Dam Construction Progress continued
2.8.
2.8.1.
INTRODUCTION
Construction of Wadi Dayqah Dam in Oman was recently completed (2009). The
dam comprises an 80 m high RCC gravity structure and a 40 m high rockfill saddle
embankment. With a crest length of a little under 400 m, the RCC structure
comprises a total concrete quantity of approximately 650 000 m3 and the RCC was
essentially placed between February and December 2008. The dam is aligned on a
curve, with a radius of 500 m to the upstream face and induced joints are arranged
2.24
University of Pretoria
QHW SHAW
PhD THESIS
Portland
Ground
Cement Limestone
Water*
Coarse
Aggregate
Fine
Aggregate
Retarder
126
54
137
1200
944
1.76
41
21
103
455
378
1.5
Fines
(l/m3)
Aggregate
(l/m3)
Paste/
Mortar**
Sand/
Aggregate
51
833
0.31
0.45
*-
the free water content was 103 litres/m3, but an additional quantity of 34 litres was
required due to aggregate absorption.
** -
including aggregate fines increases the paste to 217.5 litres/m3 and the p/m to 0.40.
2.25
University of Pretoria
Constituents
QHW SHAW
Portland
Ground
Cement Limestone
PhD THESIS
Water*
Coarse
Aggregate
Fine
Aggregate
Retarder
112
48
131
1227
960
1.76
37
19
96
463
384
1.5
Fines
(l/m3)
Aggregate
(l/m3)
Paste/
Mortar**
Sand/
Aggregate
52
847
0.29
0.45
*-
the free water content was 96 litres/m3, but an additional quantity of 35 litres was
required due to aggregate absorption.
** -
including aggregate fines increases the paste to 205.5 litres/m3 and the p/m to 0.38.
2.8.2.
The instrumentation installed in Wadi Dayqah RCC gravity dam in Oman was less
comprehensive than was the case for the previous examples. With the same types
of instruments, only a single LBSGTM was installed across each of the induced
joints in the centre of the section at two elevations, namely 135 mASL and
150 mASL. Five levels of concrete temperature meters and external temperature
gauges were also installed on three specific cross sections; one in the spillway
section and one on the non-overspill section on either flank. The typical layouts of
the temperature meters and the LBSGTMs are illustrated on Figures 2.13 and 2.14
at the end of this Chapter.
2.8.3.
Placement of the RCC for Wadi Dayqah Dam took place between February 2008 and
July 2009 in temperatures varying between 25 and 45C.
However, as a
consequence of the dam having a spillway with Roberts crest splitters, a
substantial slowing in the pace of construction occurred once the base of the
spillway crest was reached in November 2008. The vast majority of the RCC
comprising the dam was accordingly placed in just 10 months.
With a better picture of the behaviour expectations of the RCC and a relatively
small budget for instrumentation, it was considered most appropriate to install a
single LBSGTM across all joints in the centre of the dam section at two levels. With
this configuration, it was understood that only the behaviour of the core zone RCC
would be monitored.
2.26
University of Pretoria
QHW SHAW
2.27
PhD THESIS
Figure 2.9:
Illustrative Layout of
Wadi Dayqah Dam(13)
University of Pretoria
QHW SHAW
PhD THESIS
Whereas all of the other dams for which instrumentation data were reviewed
contain high-paste RCC for which a relatively high proportion of fly ash was used,
the RCC of Wadi Dayqah comprised a relatively low cement content (112 kg/m3) in
combination with a ground limestone filler (48 kg/m3) and a 0.44 sand/aggregate
ratio. Furthermore, 34% of the sand fraction comprised crushed limestone. As a
consequence, the final RCC contained over 13% fines.
Three further factors are considered of importance in respect of the measured
behaviour of the RCC at Wadi Dayqah Dam and these are the rounded particle
shape of the natural gravel coarse aggregate, the high water absorption
characteristics of the aggregates (approximately 35 litres/m3) and the fact that the
RCC temperature was artificially cooled by approximately 15C before placement.
2.9.
CHANGUINOLA 1 DAM
2.9.1.
INTRODUCTION
University of Pretoria
QHW SHAW
PhD THESIS
inducers installed in every 2nd layer after compaction and the downstream face
slope varies from 0.5 H to 1 V in the centre to 0.7 H to 1 V on the flanks.
For Changuinola 1, a high-workability RCC is being applied, with a first set
retarded typically to 20 hours. The mix strength requirements are determined
primarily by a target direct vertical tensile strength of 1.2 MPa and peak RCC
placement rates should exceed 120 000 m3 per month.
The composition of the high-workability RCC mix applied for Changuinola 1 is
follows:
Constituents
Portland
Cement
Fly Ash
Water
Coarse
Aggregate
Fine
Aggregate
Retarder
By Mass
(kg/m3)
70
145
119
1282
888
3.44
By Volume
(litres/m3)
22
60
119
462
334
Fines
(l/m3)
Aggregate
(l/m3)
Paste/
Mortar
Sand/
Aggregate
35
799
0.375
0.42
Net Paste
(l/m3)
201
Including the aggregate fines within the paste increases the p/m to 0.44.
2.9.2.
CHANGUINOLA 1 INSTRUMENTATION
2.29
University of Pretoria
2.9.3.
QHW SHAW
PhD THESIS
With almost 3 m of rainfall per annum on site and a wet month containing 25 days
of rain and a dry month 16 days, the weather conditions on site represent a very
significant factor in relation to the construction of Changuinola 1 Dam. While RCC
dam construction offered very significant advantages in respect of the river
diversion, compared to other dam types, the final programme and the shear size of
the river implied that the structure was constructed to approximately 40 m height
in two sections, with a formed joint in between (see Plate 2.16). Another factor of
specific relevance in the case of Changuinola 1 Dam is the temperate climatic
conditions, with average monthly temperatures varying only by 4C year-round.
2.10.
INSTRUMENTATION LAYOUTS
2.10.1.
WOLWEDANS DAM
2.30
University of Pretoria
RL 98.0 m
QHW SHAW
PhD THESIS
4000
200 MM DIA PENDULUM
SHAFT
Long-Base-Strain-GaugeTemperature Meters
RECESS FOR
PENDULUM
RL 66.25 m
THIRD LEVEL
OF INSTRUMENTS
RECESS FOR
PENDULUM
MAIN DRAINAGE
GALLERY
FIRST LEVEL
RL 40.25 m
OF INSTRUMENTS
PIEZOMETER &
TEMPERATURE
GAUGES
200 MM DIA
PENDULUM
SHAFT
2.31
University of Pretoria
2.10.2.
QHW SHAW
PhD THESIS
INE DAM
Figure 2.12 illustrates the typical instrumentation installed in ine Dam. The
layouts for the instrumentation at El 147.5 mASL, El 184.25 mASL & El 208.5
mASL are included in Appendix C.
El 232.00 mASL
El 208.25 mASL
El 185.25 mASL
El 147.50 mASL
2.32
University of Pretoria
QHW SHAW
PhD THESIS
2.33
University of Pretoria
QHW SHAW
PhD THESIS
2.34
University of Pretoria
2.11.
QHW SHAW
PhD THESIS
REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
Geoconsult. Gibb. ARQ. ine RCC Dam. Phase 2 Design Report. Vol.4 of
4. Drawings. zkar Construction. Ankara, Turkey. January 2000.
[12]
Vinci & CCC Construction JV. Wadi Dayqah Dam. Quality Control
Records. Quriyat, Oman. February 2008.
[13]
Wadi Dayqah Dam JV. Wadi Dayqah Dam. Drawings for Construction.
Sultanate of Oman. M.R.M.E.W.R. Muscat, Oman. August 2006.
2.35