FOR
HASANG HYDROPOWER PLANT PROJECT
February 2013
LOCATION MAP
NipponKoeiCo.,Ltd.
i|Page
EXECUTIVE SUMMARY
1. INTRODUCTION
This Report has been prepared in accordance with the Agreement for Consulting Services up to PPA
Conclusion for Hasang Hydropower Plant Project (hereinafter referred to as Project) between PT.
Binsar Natorang Energi (hereinafter referred to as BNE) and Nippon Koei Co., Ltd. (hereinafter
referred to as NK) signed on December 27, 2012.
2. HYDROLOGY
The probable 100-year flood discharge at the weir site in the Feasibility Study (=539 m3/sec) is
underestimated. It is recommended that the Creagers coefficient at the Hasang weir site shall be 20
at minimum. By applying the coefficient of 20, the 100-year flood discharge at the Hasang weir site
shall be around 1,000 m3/sec at minimum.
Runoff coefficient at the Project under the Average Scenario is as large as 0.67 assuming that mean
annual basin rainfall is 2,500 mm. From hydrological points of view, the Average Scenario with mean
annual runoff depth of 1,681 mm seems to be overestimated. This might cause risk of overestimation
of expected annual energy production. In this respect, it is recommended that the Moderate Scenario
having the mean annual runoff depth of 1,574 mm shall be applied to estimation of annual energy
production of the Project.
3. GEOLOGY
From the geomorphologic and geological viewpoints, it is suggested to; i) adjust the axis of the intake
weir, ii) adjust the location of the de-sander and connecting waterway route, iii) chick and monitor the
possibility of the landslides, iv) add the work adit for construction of the headrace tunnel, v) adjust
alignment of the penstock route, vi) adjust the location of headrace tunnel inlet, vii) provide surface
drains at the cut & cover section, and viii) to make gentler the excavated slope gradients.
4. POWER GENERATION
The project layout proposed in the Feasibility Study is not optimal with the respect of the penstock
length. With this penstock length, the fly wheel effect of the generators (GD2) is required to be
increased to an un-practicable or un-economical level to ensure the stability of penstock and to avoid
excessive pressure rise. Preliminary comparison of the alternatives indicates that the most
recommendable option is to provide newly a surge tank between the head pond and the powerhouse.
The surge tank will be of an exposed cylinder which stands on a ridge above the powerhouse.
Preliminary examination indicates that the tanks diameter will be about 10m and exposed height
about the ground yard will be about 65m. The tank will be of steel, or pre-stressed concrete instead.
NipponKoeiCo.,Ltd.
ii|Page
With taking account of the hydrological duration, the river maintenance flow (or duty flow) and the
loss above, the saleable mean annual energy of the Project for checking the project feasibility would
be:
ComparisonofAnnualEnergy
Description
Unit
1.
Hydrology Series
Base Case
Low Case
Reg No. 38
Average
Moderate
Moderate
2.
m3/s
1.0
1.0
6.7
3.
Installed Capacity
GW
42.45
42.45
42.45
4.
GWh
288.3
260.5
190.7
5.
Availability
98.5
98.5
98.5
6.
GWh
284.0
256.7
187.9
7.
GWh
5.7
5.1
3.8
8.
Spillage Loss
GWh
2.8
2.6
1.9
9.
GWh
275.5
249.0
182.3
Plant Factor
74.1
67.0
49.0
10.
Base Case and Low Case correspond to Annex 17.3 and 17.4 of the Feasibility Study, respectively.
Reg. No. 38 corresponds to the case when the Government Regulation No.38, 2011 is strictly applied to Low
Case.
Source: based on energy simulation in Feasibility Study and Review Team
5. DESIGN ISSUES
Design issues which may cause substantial impact to the project cost are seen in the following table.
DesignIssueswhichmaysubstantiallycauseImpacttoProjectCost
No.
1
Item
Access Road
Re-route
Pavement width
Removal of boulders
Debris barrier
NipponKoeiCo.,Ltd.
Description
In F/S, the existing road will be widened and paved in the
same route to construct the access road. However, several
sections of them are very steep in longitudinal gradient and
too small horizontal radius. Construction of new road by reroute or improvement of vertical alignment for these
sections will be necessary.
Typical width of pavement is 6.0 m in the Feasibility
Study. It can be reduced to 4.5 m. For passing vehicle each
other, preparation of a passing bay every 500 m interval is
recommendable.
The ridge in the left bank in which the intake is located is
rather thin. After excavation of abutment of the intake weir
and the intake, the remaining sound rock become be very
thin. As the countermeasure, change of layout of the weir
axis is recommended.
There are many big boulders at the intake weir site. Almost
of all of them are derived from the construction works of
the hydropower station in upstream. These boulders shall
be removed to downstream prior to start of the construction
works as much as possible.
In order to prevent entering boulders in front of the power
iii|Page
Headrace Tunnel
Tunnelling in soft materials
Work adit
5
Crossing structures
Penstock
New provision of surge tank
NipponKoeiCo.,Ltd.
iv|Page
Slope protection
Enlargement of powerhouse
penstock.
Geology around penstock site is composed on top soil and
weathered tuff and erodible by water. All excavated surface
shall be protected by wet rubble
masonry/shotcrete/sodding.
Probable flood of 100-year shall be revised to 1,000 m3/s,
then the elevation of the powerhouse yard shall be set to
ensure safety against this flood.
Location of the draft gate can be shifted to upstream to
minimize the powerhouse structure.
Elevation of the erection bay of P/H and the end of Access
Road are set at EL. 351.75. On the other hand, the upstream
end of the tailrace wall is set at EL. 355.00. Flood water
will flow into the Powerhouse through the erection bay. A
guide wall along the Access Road is required.
There seems no sufficient space for removal of the rotor
and shaft assembly from the generator. In case horizontalshaft turbine is used for this project, the space between the
units shall be widened by at least 2 m and the space
between Unit 3 and the powerhouse side wall by at least 2
m. Size of the control room and the switchgear room seems
not enough.
If double-pi connection is employed, two more
transmission line bays become necessary.
If double-pi connection is employed, two more
transmission line bays become necessary.
It is conceived that the selected option in the Feasibility
Study to provide the new Kampung Pajak substation and
the Project is connected to there is technically the best
solution. Single-pi connection has problem in reliability of
transmission, and thus not recommendable. Meanwhile
Double-pi connection requires necessity of 4 circuits, and
the price of transmission line becomes high.
Source: NK
7. COST ESTIMATE
Impacts to the direct cost due to review result of design in compliance with NKs recommendations
are roughly estimated. Total project cost to which the above cost impacts are incorporated is as below.
NipponKoeiCo.,Ltd.
v|Page
SummaryofProjectCost
Item
Amount
(mil. US$)
Direct Cost
Civil Works
Hydro-mechanical Works (incl. Penstock)
Electro-mechanical Works
Transmission Line
Total Direct Cost
Indirect Cost
Client Administration
Engineering
Land Acquisition and EIA Cost
Technical Management Services
Insurance
Taxes (VAT on all local items)
Total Indirect Cost
Total Project Cost (without IDC)
Total Project Cost (with IDC)
46.53
10.46
25.95
15.53
98.47
4.92
4.92
4.26
2.84
4.92
11.17
33.03
131.50
154.67
8. PROJECT FEASIBILITY
The possible cost increase may affect the project profitability; the return on equity (ROE) may go
down by 3% from the FS Base Case. If one considers the possible energy decrease, ROE further may
go down by 2 %. As a whole, there is a concern that ROE might nose down to the level the investors
can hardly accept, as demonstrated below.
Analysis Cases
Energy
Tariff
ROE
FS Base Case
110.0 USDm
275.5 GWh
USc7.5/kWh
14.4%*
Cost Up
131.5 USDm
275.5 GWh
USc7.5/kWh
11.2%
131.5 USDm
249.0 GWh
USc7.5/kWh
9.4%
FS has computed ROE (return on equity) to be 14.92% for the base case with USc7.5/kWh tariff, while the
Review Work does 14.4% under the same assumptions.
In order to compensate such possible profitability decrease, the investors should examine higher tariff
for energy sales, assuming 15.0% of the required ROE:
Analysis Cases
Energy
Tariff
ROE
Cost Up
131.5 USDm
275.5 GWh
USc9.06/kWh
15.0%
131.5 USDm
249.0 GWh
USc10.03/kWh
15.0%
NipponKoeiCo.,Ltd.
vi|Page
It is recommended that the Moderate Scenario shall be applied instead. Based on this, the
salable annual mean energy of the Project will be 249.0 GWh, which is of about 10% decrease
compared to 275.5 GWh in the Feasibility Study.
The project cost without IDC will be 131.5 US$m which is about 20% increase compared to
110.0 US$m in the Feasibility Study.
The possible energy decrease and cost increase above may cause profitability decrease. To
compensate this, higher tariff should be examined.
The observed daily flow records at the Pulao Dogom station from 2000 to date shall be analyzed
for prediction of monthly energy generation through in-depth review and scrutiny of the flow
data.
Detailed survey shall be conducted to confirm possibility of landslide f at the de-sander site and
the powerhouse site.
Additional topographic survey and geological investigation shall be conducted along the newly
proposed penstock alignment and at the surge tank area.
Comparative study shall be conducted to confirm the optimal selection of type and number of
the units of turbine-generator.
NipponKoeiCo.,Ltd.
vii|Page
CONSULTING SERVICES
UP TO
PPA CONCLUSION
FOR
HASANG HYDROPOWER PLANT PROJECT
INTRODUCTION .............................................................................................
General..................................................................................................................
Background...........................................................................................................
Objectives of Task-1 in Services ..........................................................................
Scope of Task-1 in Services ..................................................................................
1
1
3
3
HYDROLOGY ...................................................................................................
General.................................................................................................................. 5
Design Flood Discharges ...................................................................................... 5
Inflow.................................................................................................................... 10
GEOLOGY..........................................................................................................
3.1 Geologic Components and their General Features ...............................................
3.2 Headworks ............................................................................................................
3.3 Desander ...............................................................................................................
3.4 Inlet of Headrace Tunnel ......................................................................................
3.5 Tunnel Section of Waterway .................................................................................
3.6 Outlet of Headrace Tunnel and Cut & Cover Section of Waterway .....................
3.7 Head Pond.............................................................................................................
3.8 Penstock ................................................................................................................
3.9 Powerhouse...........................................................................................................
3.10 Suggestions and Recommendations .....................................................................
17
17
20
24
27
28
34
35
35
37
40
41
41
41
45
4.1
4.2
4.3
NipponKoeiCo.,Ltd.
viii|Page
5
5.1
5.2
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
48
48
48
53
55
56
57
60
60
7.1
7.2
7.3
62
62
62
62
8.1
8.2
8.3
64
64
64
64
9.1
9.2
10
10.1
10.2
10.3
67
67
67
70
11
11.1
11.2
11.3
11.4
73
73
73
74
76
12
PROJECT FEASIBILITY ................................................................................ 78
12.1 Financial Analysis ................................................................................................ 78
12.2 Possible Effects from Cost and Energy Change ................................................... 79
13
NipponKoeiCo.,Ltd.
ix|Page
ANNEX
COMMENTS ON TECHNICAL PROPOSAL BY POSCO ENGINEERING
List of Tables
Table 1.2.1
Table 1.2.2
Table 1.2.3
Table 1.4.1
Table 1.4.2
Table 2.2.1
Table 2.2.2
Table 2.2.3
Table 2.3.1
Table 2.3.2
Table 2.3.3
Table 3.5.1
Table 3.6.1
Table 4.1.1
Table 4.2.1
Table 4.3.1
Table 5.1.1
Table 6.1.1
Table 11.1.1
Table 11.3.1
Table 11.4.1
Table 11.4.2
Table 12.2.1
Chronicle ................................................................................................... 1
Most Recent Studies .................................................................................. 2
Salient Features ......................................................................................... 2
Scope of Task-1 in Services ....................................................................... 3
Documents for Review .............................................................................. 4
Estimated Probable Flood Discharge at Pulao Dogom Station ................. 6
Estimated Probable Flood Discharges at Hasang Weir Site (F/S) ............. 6
Estimated Probable Flood Discharges at Hasang Weir Site (Pre-F/S) ...... 7
Comparison of Runoff Depth of Annual Mean Discharges
at Hasang Weir Site ................................................................................. 11
Plausible Range of Runoff Estimated from Water Balance ..................... 12
Comparison of Runoff Coefficient at Hasang Weir Site ......................... 14
Geologic Description of Core Sample of Drilling PB-T1 ....................... 31
Summary of Laboratory Tests at Cut & Cover Site ................................. 34
Two Scenarios for Energy Simulation ..................................................... 41
Alternatives for Penstock Stability .......................................................... 43
Mean Annual Energy ............................................................................... 46
Main Access Roads to be Upgraded and/or Newly Built ........................ 47
Main Civil Structures of the Project ........................................................ 48
Summary of Project Cost in Feasibility Study ........................................ 73
Main Unit Rates for Civil Works in Feasibility Study ............................ 74
Impact to Cost Estimate due to Design Review ...................................... 76
Summary of Project Cost......................................................................... 77
Updated Financial Stream with Higher Tariff ......................................... 79
List of Figures
Figure 1.2.1
Figure 2.2.1
Figure 2.2.2
Figure 2.2.3
Figure 2.2.4
Figure 2.3.1
Figure 2.3.2
NipponKoeiCo.,Ltd.
x|Page
Figure 2.3.3
Figure 2.3.4
Figure 3.1.1
Figure 3.1.2
Figure 3.1.3
Figure 3.1.4
Figure 3.2.1
Figure 3.2.2
Figure 3.2.3
Figure 3.2.4
Figure 3.2.5
Figure 3.2.6
Figure 3.3.1
Figure 3.4.1
Figure 3.5.1
Figure 3.5.2
Figure 3.5.3
Figure 3.5.4
Figure 3.5.5
Figure 3.5.6
Figure 3.8.1
Figure 3.9.1
Figure 4.2.1
Figure 4.2.2
Figure 6.2.1
Figure 6.2.2
Figure 6.2.3
Figure 6.2.4
Figure 6.2.5
Figure 6.3.1
Figure 6.3.2
Figure 6.4.1
Figure 6.5.1
Figure 6.5.2
Figure 6.6.1
Figure 6.6.2
Figure 6.6.3
NipponKoeiCo.,Ltd.
xi|Page
Figure 6.6.4
Figure 6.8.1
Figure 6.8.2
Figure 10.1.1
Figure 10.2.1
Figure 10.2.2
Figure 10.2.3
Figure 10.3.1
Figure 10.3.2
Figure 10.3.3
List of Photos
Photo 3.2.1
Photo 3.2.2
Photo 3.2.3
Photo 3.3.1
Photo 3.5.1
Photo 3.5.2
Photo 3.5.3
Photo 3.5.4
Photo 3.8.1
Photo 3.8.2
Photo 3.9.1
Photo 6.2.1
Photo 6.2.2
NipponKoeiCo.,Ltd.
xii|Page
1.
INTRODUCTION
1.1
General
This Report has been prepared in accordance with the Agreement for Consulting Services up to PPA
Conclusion for Hasang Hydropower Plant Project (hereinafter referred to as Project) between PT.
Binsar Natorang Energi (hereinafter referred to as BNE) and Nippon Koei Co., Ltd. (hereinafter
referred to as NK) signed on December 27, 2012.
The Report presents background and objective of the Services, and the review results of the existing
studies for the Project including the issues such as general hydrology and geology, hydropower
planning and design/specifications, cost estimation, facility renewal planning, operation planning,
saleable power, construction time schedule and contractual systems.
1.2
Background
BNE was established by PT. Titan Multi Power and LG International Corp. as the Special Purpose
Company for an Independent Power Producer of the Project. The Project is a run-of-river hydropower
along the left bank of the Kualu river, running south-east of the Lake Toba down to the Malakka Strait.
Location map of the Project is attached in the opening page of this Report.
Promotion of the Project by BNE started in 2010 and following progress has been so far made.
Table1.2.1Chronilcle
Event
Month
Year
March
2010
July
April
September
2011
December
March
April
May
September
October
December
2012
Source: Agreement for Consulting Services up to PPA Conclusion for the Project
The Project was first identified in the hydropower potential studies in Indonesia by NK in 1983 and
1999. After that, several alternative studies were conducted. The most recent studies are the
Feasibility Study by Poyry Energy Ltd. in 2012 the Pre-Feasibility Study by PT. Wahana Adya in
2011.
NipponKoeiCo.,Ltd.
1|Page
Table1.2.2MostRecentStudies
Study
Outline
Feasibility Study
in 2012
by Poyry Energy Ltd.
Pre-Feasibility Study
in 2011
by PT. Wahana Adya
The feasibility study was prepared on the basis of the alternative L2-1
which was selected in the pre-feasibility study.
7 alternative layouts were examined, and as the result the alternative L2-1
(free surface tunnel + power channel + shorter penstock + surface type
powerhouse) was selected as the most promising layout.
The Project was optimized in the Feasibility Study as a straightforward run-of-river type development
of 42.45MW installed capacity. The Feasibility Study reassessed the seven (7) alternatives which had
been studied in the Pre-Feasibility Study, then concluded that the alternative L2-1 was the most
attractive for development, of which layout is seen in the following figure.
Figure1.2.1LayoutAlternativesinPreviousStudies
Salient features of the Project proposed in the Feasibility Study are summarized in the following table.
Table1.2.3SalientFeatures
Description
Project Name
Project Scheme
Location
Type
Catchment Area
Mean Annual Flow
Maximum Plant Discharge
Net Head
Installed Capacity
Annual Energy Output
Project Cost
Salient Features
Hasang Hydro Power Plant (HPP) Project
IPP (Independent Power Producer to PLN)
Aek Kualu-River Area, Nassau subdistrict, Toba Samosir Regency, North
Sumatera, Republic of Indonesia
Run-of-River
501 km2
26.7 m3/s
27.5 m3/s
189.27 m
3 x 14.150MW = 42.450 MW
275.53 GWh
US$ 129.4 mil.
NipponKoeiCo.,Ltd.
2|Page
The Consulting Services up to PPA Conclusion for the Project of which the Agreement was
concluded between BNE and NK on December 27, 2012 (hereinafter referred to as Services) consist
of the following tasks:
-
Task-1:
Task-2:
Task-3:
Task-4:
Task-5:
Task-6:
1.3
to review the existing studies, relevant data and information thereon in order to have clear and
objective understanding of the development plan of the Project, and
to recommend the tariff components A, B, C, D and E based on the main financial indicators
analyzed.
1.4
NipponKoeiCo.,Ltd.
Description
3|Page
The existing studies which were provided by BNE to NK for the review in Task-1 are the Feasibility
Study Report in 2012 and the Pre-Feasibility Study Report in 2011 for the Project. The Structures of
the respective reports provided are as seen in the following table.
Table1.4.2DocumentsforReview
Title
Feasibility Study Report
in 2012
by Poyry Energy Ltd.
Pre-Feasibility Study Report
in 2011
by PT. Wahana Adya
Pre-F/S Report for 150kV T/L
in 2012
by Wiratman & Associates
Report Structure
Vol. 1 Executive Summary
Vol. 2 Main Report
Vol. 3 Drawings
Vol. 4 ESIA
Vol. 5 Annex
Vol. 2 Main Report
Vol. 3 Drawings
Vol. 1 Executive Summary
Vol. 2 Main Report
Vol. 3 Attachment
Vol. 4 Drawings
Source: BNE
NK conducted the desktop review on the documents above, and performed a site reconnaissance
survey on 17th and 18th January 2013 at the Project site to confirm the actual conditions especially of
geology. NK reported the interim results of their review to BNE in the progress meetings held in
biweekly basis then compiled those comments in the relevant chapters in this Report.
Besides the above, NK received form BNE the electronic files of Technical Proposal on the Project
prepared by LG International and POSCO Engineering. NKs Comments on this document is
presented in Annex of this Report.
NipponKoeiCo.,Ltd.
4|Page
2.
2.1
HYDROLOGY
General
Hydrological study in the Feasibility Study Report (in Chapter 6 Meteorology, Hydrology and
Sedimentation, Volume 2 Main Report) has been well carried out in detail despite very limited
availability of long-term hydrological data in the Kualu River basin where the Hasang HPP Project is
located. Major outcomes of hydrological study which might affect the project cost and energy
generation were carefully reviewed based on experiences of various hydrological analyses in past
hydropower and water resources development projects in Indonesia. Highlighted are as follows:
-
2.2
NipponKoeiCo.,Ltd.
5|Page
In the Feasibility Study Report, the estimated probable flood peaks at the Pulao Dogom station is
given as follows (see Table 6-7 in the Feasibility Study Report):
Table2.2.1EstimatedProbableFloodDischargesatPulaoDogomStation
Return Interval
(year)
10
25
30
50
100
200
Finally probable flood discharges at the Hasang weir site are estimated using the well-known
Creagers equation for flood regionalization as listed below (see Table 6-8 in the Feasibility Study
Report).
Table2.2.2EstimatedProbableFloodDischargesatHasangWeirSite(F/S)
Return Interval
(year)
10
25
30
50
100
200
Creagers Coefficient
11.59
12.52
12.71
13.22
13.93
14.63
As shown above, the 100-year flood at the weir site which was used as the design flood discharge for
hydraulic design of civil structures is estimated to be 539 m3/sec.
Figure below shows the relationship between 100-year flood discharges in Sumatra Island applied in
various hydropower development projects and catchment areas thereof. Besides, the Creagers curves
with coefficients of 20 and 30 as well as the 100-year flood discharge at the Hasang weir site are also
plotted for reference.
NipponKoeiCo.,Ltd.
6|Page
Source: Potted Floods from Hydro Inventory Study, July 1997, PT.PLN
Figure2.2.1100yearFloodsinSumatra
The Creagers curve is commonly applied to assist in quick estimation of probable flood peak
discharges and evaluation of estimated probable flood discharges through comparison of the same
probable flood discharges applied in other schemes. Along this line, in the Hydro Inventory Study in
1997 recommended to apply Creagers coefficient of 30 for Sumatera Island for preliminary study of
hydropower development schemes from the conservative aspect.
As is apparent from the figure above, the 100-year flood discharge at the Hasang weir site seems
slightly small compare to other 100-year flood discharges applied in various hydropower schemes.
The Creagers coefficient at the Hasang weir site is as small as 13.93 as shown in the table above.
It is recommended that the Creagers coefficient at the Hasang weir site shall be 20 at minimum. By
applying the coefficient of 20, the 100-year flood discharge at the Hasang weir site shall be around
1,000 m3/sec at minimum.
Pre-Feasibility Study
After review of the Feasibility Study Report, the Pre-Feasibility Study Report becomes available. A
different approach from the Feasibility Study was made for estimation of probable flood discharges.
Probable flood discharges were estimated by applying the Nakayasu unit hydrograph method by use
of probable basin rainfalls as summarized below.
Table2.2.3EstimatedProbableFloodDischargesatHasangWeirSite(PreF/S)
Return Interval
(year)
5
10
25
50
100
200
NipponKoeiCo.,Ltd.
7|Page
As shown above, the 100-year flood discharge at the Hasang weir site was proposed to be 1,372.92
m3/sec in the Pre-Feasibility Study Report. Besides, the estimated 100-year flood discharge was
evaluated by Creagers coefficient as shown below. It is noted that plotted probable flood discharges
are of specific discharges expressed by the unit of m3/sec/km2.
Figure2.2.2ChartofCreagersNumber
The estimated 100-year flood discharge at the Hasang weir site is plotted close to on the Creagers
curve with coefficient of 30. It was concluded in the Pre-Feasibility Study that the estimated 100-year
flood discharge is applicable to feasibility design.
Conclusion
From the review result above, it is concluded that the probable 100-year flood discharge at the weir
site in the Feasibility Study (=539 m3/sec) is underestimated. It is recommended that the Creagers
coefficient at the Hasang weir site shall be 20 at minimum. By applying the coefficient of 20, the 100year flood discharge at the Hasang weir site shall be around 1,000 m3/sec at minimum.
In the Feasibility Study, the construction pits for Phase 1 is proposed to be safe against a 25-year
flood. Thus both upstream and downstream cofferdams will be constructed (see Sub-section 12.3.4).
NipponKoeiCo.,Ltd.
8|Page
The designed 25-year flood discharge of 484 m3/sec at the weir site s also evaluated in terms of the
Creagers curve. Figure below is the plots of design 20-year flood discharges in various hydropower
schemes. It is assumed the no significant difference is expected between 20-year flood discharges and
25-year flood discharge at Hasang weir site, since no 25-year flood discharges are available.
As seen in the figure, it appears that the design 25-year flood discharge is plotted on the Creagers
curve with coefficient of 10, which is judged as a little underestimated for 20-year floods in Sumatra
Island.
Source: Potted Floods from Hydro Inventory Study, July 1997, PT.PLN
Figure2.2.320yearFloodsinSumatra
10,000
1,000
2
C=10
100
Masagn-2 2
10
10
100
1,000
10,000
100,000
Source:
Figure2.2.42yearFloodsinSumatra
NipponKoeiCo.,Ltd.
9|Page
Figure above is the plots of design 2-year flood discharges in various hydropower schemes. As seen
C=10 is the upper envelope curve of 2-year floods in Sumatra Island.
The above indicates that the designed flood discharge for the river diversion of 484 m3/sec at the weir
site proposed in the Feasibility Study, of which Creagers coefficient is about 10, is still applicable,
but should be regarded as the probable 2- to 5-year flood discharge, not of 25-year.
2.3
Inflow
Moderate scenario: The duration curve at the weir site is estimated based on the duration curve
derived from the Pulao Dogom station in the period of 2000-2006 (2002 and 2005 excluded) to
down-scaled to match the annual mean discharge of 25 m3/sec, which is derived from water
balance analysis results ranging from 17 m3/sec to 30 m3/sec as a realistic value.
Optimistic scenario: The duration curve deprived from the observed river discharges from
December 2010 to November 2011 at the Hasang weir site is assumed to be representative
for long-term runoff conditions. Annual mean discharge is computed to be 28.5 m3/sec. It is
said that the year 2011 was a hydrological wet year, although annual rainfall data was not
collected during the feasibility study.
Considering hydrological conditions under both scenarios, an additional scenario was proposed as the
Average of both scenarios (named Average scenario). This scenario is to compute flow duration curve
by means of an arithmetical average of both flow duration curves. The computed annual mean
discharge in the Average scenario is 26.7 m3/sec. The average flow duration curve was used for
purpose of optimization and forms the basis for the base case of the economic and financial
analyses. The moderate duration curve was used as a conservative scenario for the sensitivity analysis
(see Sub-section 10.2.1 in the Feasibility Study Report).
The annual runoff depth is computed by dividing the accumulated annual runoff volume by the
drainage area. The annual runoff depth is computed by the following equation:
Rd (mm) = Md (m3/sec) x 60 (sec) x 60 (min) x 24 (hour) x 365 (day) / (Ca (km2) x 103)
where,
Rd: Annual runoff depth
NipponKoeiCo.,Ltd.
10|Page
Optimistic Scenario
28.5 m3/sec
1,794 mm
Average Scenario
26.7 m3/sec
1,681 mm
As indicated above, the flow duration curve under the Optimistic scenario is only deprived from the
observed flow data at the Hasang weir site from December 2010 to November 2011. Monthly rainfall
records in 2010 and 2011 at both Bor-Bor and Silaen stations were collected. No records are available
at the remaining two stations of Bukit Likma and Maranti (see Sub-section 6.4.1). Annual basin
rainfall from December 2010 to November 2011is estimated by arithmetical mean of two stations of
Bor-Bor (2,253 mm) and Silaen (1,960 mm). The estimated annual basin rainfall is 2,107 mm.
Annual rainfall loss and runoff coefficient are computed to be 313 mm (= 2,107 1,794) and
0.85 (= 1,794 / 2,107). From the hydrological viewpoints, it can be said that the estimated annual
rainfall loss is apparently very small and the runoff coefficient is very large, comparing to
empirical ranges of such values reflected by hydro-meteorological characteristics in Indonesia.
As for both the Moderate and Average scenarios, annual basin mean rainfall at the Hasang weir
site is unknown because of difficulty for estimation thereof.
Under such being the case, annual water balance analysis was carried out in the feasibility study in
order to estimate plausible range of mean annual runoff depth at the Hasang weir site as described
below. This approach is reasonable from the viewpoints of hydrological analysis.
NipponKoeiCo.,Ltd.
11|Page
Furthermore, the estimated mean annual basin rainfall with vertical precipitation gradient was
increased by 1.25 applying as the gauge correction factor considering that most rainfall gauges are
under-catching due to the windfield close to the measurement device. The upper range of mean
annual basin rainfall was thus estimated to be 2,663 mm (= 2,130 x 1.25), although the rainfall
amount of 2,130 mm was assumed to be the lower range.
As for AET in the above, AET was assumed to be a linear function of potential evapotranspiration
PET as shown below. The factor f varies in the order of 0.7 to 0.9.
AET = f x PET
As described in Sub-section 6.4.3.2 in the Feasibility Study Report, PET was estimated to be 1,162
mm. Therefore the range of AET was estimated from 813 mm (= 1,162 x 0.7) to 1,046 mm (= 1,162 x
0.9).
The results of water balance analysis were summarized in Table 6-6 in the Feasibility Study Report as
quoted below.
Table2.3.2PlausibleRangeofRunoffEstimatedfromWaterBalance
Based on the above, plausible ranges of the mean annual runoff depth as well as mean annual basin
rainfall at the Hasang weir site are illustrated below.
NipponKoeiCo.,Ltd.
12|Page
Figure2.3.1PlausibleRangeofMeanAnnualRunoffDepthatHasangWeirSite
As indicated above, the feasibility study concluded that the mean annual basin mean rainfall varies
from 2,130 mm to 2,663 mm and the mean annual runoff depth is in the range between 1,084 mm and
1,850 mm. The average of mean annual basin rainfall is estimated to be 2,397 mm by means of
arithmetical mean of upper and lower mean basin rainfalls.
On the other hand, the figure focused below is an isohyetal map of mean annual rainfall in Sumatra
that is prepared by BMG. The catchment area of the Hasang weir site is illustrated on the map. As
seen in this map, the mean annual basin rainfall at the Hasang weir site is around 2,500 mm.
Source: BMG
Figure2.3.2IsohyetalMapofMeanAnnualRainfallinSumatraIsland
NipponKoeiCo.,Ltd.
13|Page
The table below shows the comparison of runoff coefficients at the Hasang weir site for three
scenarios assuming that the mean annual basin rainfall at the site is 2,500 mm. Runoff coefficient
becomes 0.67 under the Average Scenario.
Table2.3.3ComparisonofRunoffCoefficientatHasangWeirSite
Scenario
Mean Runoff
Runoff Depth
Basin Runoff
Runoff Coefficient
Moderate Scenario
25 m3/sec
1,574 mm
2,500 mm
0.63
Optimistic Scenario
28.5 m3/sec
1,794 mm
2,500 mm
0.72
Average Scenario
26.7 m3/sec
1,681 mm
2,500 mm
0.67
Source: based on Project for Master Plan Study of Hydropower Development in Indonesia, 2011, JICA
Figure2.3.3RelationshipbetweenRunoffCoefficientandMeanAnnualBasinRainfallinVarious
RiverBasinsinSumatraIsland
As shown above, runoff coefficients become large exceeding 0.6 in the river basins where mean
annual rainfalls are larger than 3,000 mm. As for the river basins same as the Kualu River basin at the
Hasang HPP Project with mean annual basin rainfall from 2,130 mm to 2,660 mm, runoff coefficient
varies from 0.45 to 0.6.
NipponKoeiCo.,Ltd.
14|Page
Source: based on Project for Master Plan Study of Hydropower Development in Indonesia, 2011, JICA
Figure2.3.4RelationshipbetweenRunoffCoefficientandMeanAnnualRunoffDepthinVarious
RiverBasinsinSumatraIsland
Together with the above, runoff coefficients in river basins in Sumatera are evaluated in terms of
mean annual runoff depth. As shown above, runoff coefficient is in the range from 0.45 to 0.6 for the
river basins same as the Kualu River basin at the Hasang HPP Project with mean annual runoff depth
from 1,084 mm to 1,850 mm.
Runoff coefficient at the Hasang HPP Project under the Average Scenario is as large as 0.67 assuming
that mean annual basin rainfall is 2,500 mm. From hydrological points of view, the Average Scenario
with mean annual runoff depth of 1,681 mm seems to be overestimated. This might cause risk of
overestimation of expected annual energy production. In this respect, it is recommended that the
Moderate Scenario having the mean annual runoff depth of 1,574 mm shall be applied to
estimation of annual energy production of the Project.
NipponKoeiCo.,Ltd.
15|Page
of annual and monthly energy generation outputs in advance based on the long-term series of monthly
inflows.
Furthermore, in Section 8.3 Planned Energy Supply and Planned Discharge of Article 8 in the
Model PPA, it is mentioned that At least three months prior to the Scheduled Commercial Operation
Date, SELLER shall submit PLN its desired Planned Energy Supply and Planned Discharge for the
first Contract Year. This means SELLER should predict monthly energy generation for coming
three months. In this respect, the estimated likely variation of monthly energy production could be
very informative.
Considering the availability of flow data, the observed daily flow records at the Pulao Dogom station
from 2000 to date would be usable for prediction of monthly energy generation through in-depth
review and scrutiny of the flow data.
NipponKoeiCo.,Ltd.
16|Page
3.
3.1
GEOLOGY
Geologic Components and their General Features
According to a published geological map Geological Map of Pematang Siantar Quadrangle, the
following geologic units are distributed on and around the project area.
-
Alluvium (Qh)
Toba Tuff Unit (Qvt)
Peutu Formation, Parapat Member (Tmppt)
Tapanuli Group Undifferentiated (Put)
Although different locations of the project areas are shown in existing reports (see Figure 3.1.1), the
bedrock of the project area seems to be Toba Tuff Unit (Qvt) and Tapanuli Group Undifferentiated
(Put).
Switch Yard,
Page 7-5,
Volume 2,
Pre-FS
report,
Attachment 7-1,
Pre-FS report
Figure3.1.1ProjectAreaonGeologicalMap
Most of project area is underlain by the Toba Tuff Unit (Qvt); Rhyodacic crystal-vitric ash flow
(pyroclastic flow) and air-fall (aeolian deposit) of late Pleistocene. The Unit is roughly divided into
Aeolian deposit VOLCANIC ASH and Pyroclastic flow IGNIMBRITE as shown in existing
reports (see Figure 3.1.2).
NipponKoeiCo.,Ltd.
17|Page
Figure3.1.2SchematicGeologicSection
The distribution of the Aeolian deposit seems to be limited in the area of the tunnel outlet and cutfill section of waterway. The aeolian deposit looks originally soft and further softened due to
weathering, and N values of most of shallow sections are N=10 or less.
The Pyroclastic flow seems to be distributed on the foundations of major structures, except for the
tunnel outlet and cut-fill section of waterway. The pyroclastic flow is originally slightly to
moderately welded and consolidated (20 MPa to 40 MPa) with sparsely joints, while softened at
shallow portions due to weathering (5 MPa to 20 MPa). Cooling joints generally develop in highly
welded tuff, but cooling joints in tuff is sparse (30 cm to 1 m interval) in the project area, since the
degree of welding is not so high. Highly to completely portion of the pyroclastic flow is soft, like
residual soil, and there is no distinct difference in its view and property from the weathered portions
of the aeolian deposit.
Although strategic relation is not clear, the Aeolian deposit is distributed on high elevation. The
distribution area of the Aeolian deposit and pyroclastic flow along the downstream section of the
headrace tunnel is estimated as shown in Figure 3.1.3.
NipponKoeiCo.,Ltd.
18|Page
Aeolian deposit
Pyroclastic flow
Figure3.1.3EstimatedDistributionofAeolianDepositandPyroclasticFlow
Another geological unit of clay stone to silt stone, which seems to be Tapanuli Group
Undifferentiated (Put) of Paleozoic, is distributed on the foundation of the head pond. The clay
stone to silt stone was found at Drill hole W-1 as shown in Figure 3.1.4. The Tapanuli Group seems
to be distributed on steep mountains, surrounding the project area, as well as downstream areas where
conceivable quarry site is located. The rock is hard and assumed unconfined compression strength is
40 MPa in an intact portion, while the rock pieces show flaky nature.
Aeolian deposit of
Toba Tuff Unit
Tapanuli
Group
Pyroclastic flow of
Toba Tuff Unit
Figure3.1.4EstimatedDistributionofTapanuliGroup
The above-mentioned bedrock is covered with unconsolidated sediments; Alluvium (Qh). The
unconsolidated sediments are roughly divided into talus deposits and recent river deposit. The talus
NipponKoeiCo.,Ltd.
19|Page
deposits are mainly distributed on gentle slopes, and the deposits generally consist of poorly sorted
clay to silt with weathered rock fragments. The recent river deposits are distributed along river course
where river gradient is not so steep, and the deposits generally consist of silt to sand with rather fresh
rock fragments.
3.2
Headworks
On the upstream section of the weir, boulder- to cobble-size excavated materials are
accumulated on the left side of the river course, and the water flow on the meandering section is
blocked as shown in Figure 3.2.1 and Photo 3.2.1. Although it is difficult to forecast the feature
change of water course, there is possibility that no water will flow to the intake gate of the
present design, if accumulation of the sediments continues on the left side of the upstream
section. A possible solution is to change to be straight along the thin ridge on the left abutment
as shown in Figure 3.2.2. Cost increase for excavation of the thin ridge seems not to be much,
since the ridge should be excavated for the new alignment of waterway route.
On the downstream section the weir, boulder- to cobble-size excavated materials are
accumulated on the previous river course, and rive water course is changed to the left side,
resulting in erosion of the left bank, where paddy field was located as shown in Figure 3.2.1 and
Photo 3.2.2. Due to the erosion of the left bank on the downstream of the weir, alignment of the
waterway and desander will be shifted to the mountain side as shown in Figure 3.2.2.
Waterway
route
No water flow
Recent
S di
Weir axis
Photo 2.1
Change of water
course with erosion of
paddy
Photo 2.2
Recent
Figure3.2.1LocationofRecentSedimentsandChangeofWaterCourse
NipponKoeiCo.,Ltd.
20|Page
Recent
Sediments
Photo3.2.1UpstreamviewofHeadworksSite(seeFigure3.2.1forlocation)
Recent
Sediments
Photo3.2.2DownstreamViewofHeadworksSite(seeFigure3.2.1forlocation)
Alternative
waterway route
Waterway
Weir axis
Alternative
weir axis
Figure3.2.2Locationofrecentsedimentsandchangeofwatercourse
NipponKoeiCo.,Ltd.
21|Page
Figure3.2.3LocationsofDrillHolesandTestPitsinHeadworksSite
-
Concrete structures of the weir and intake will be emplaced on slightly weathered pyroclastic
flow (Ignimbrite) for the most of the weir foundation as it shown in FS report (see Figure 3.2.4).
Soft materials on shallow depth, such as top soil, talus deposits, and completely to highly
weathered Ignimbrite, will be removed from the foundation of concrete. Moderately weathered
Ignimbrite will lie on some parts of the foundation, and it seems that the partial appearance of
moderately weathered rocks is not a big problem in terms of strength of the foundation. Since
continuous outcrops of highly to moderately weathered Ignimbrite are seen beside the river as
shown in Photo 3.2.3, suitable foundation of the weir and intake structures will be distributed at
shallow portions on the both abutment.
Figure3.2.4GeologicalSectionofHeadworksSite
NipponKoeiCo.,Ltd.
22|Page
Continuous outcrop
Photo3.2.3OutcroponThinRidgeofLeftabutment
-
At dill hole BH-D6, recent river deposits is distributed up to 12 m deep (EL.543.246 m).
Although assumed rock line is shown around EL.548.00 on the design drawing HS-11-003,
there is possibility that recent river deposits are distributed deeper portion (e.g. 5 m deeper than
the assumed rock line) as shown in Figure 3.2.5. The actual rock line might be much deeper as
shown in Figure 3.2.4. It is better to emplace concrete onto the rock foundation at the cut-off
portion of the weir structure mainly for the preventing. If the foundation rocks lie on deeper
portion, the excavation to the foundation rocks will be difficult due to seepage water. In such
case, another issue that increases of excavation volume and concrete volume will be arisen, and
another measure for preventing leakage should be taken, instead of deep excavation. Since
grouting in recent river deposit is considered not effective; only waste of cement, and thereby, a
watertight measure in recent river deposits by grouting is not applicable. Sheet piling may also
be not applicable, since penetration of piles in recent river deposits with many boulders is so
difficult. An applicable measure may be to extend seepage path by means of adding concrete
slab to the upstream.
EL.543
m
Figure3.2.5SectionofWeirandAssumedDepthofFoundationRocks
NipponKoeiCo.,Ltd.
23|Page
The recent river deposits seem to have enough bearing capacity and shear strength as foundation
of the weir structure, if the materials are dominant in sand and gravel. In case that soft clay and
silt appear on excavated weir foundation, the soft materials should be removed and replaced
with concrete.
Water hose
Casing
Drilling rod
Overburden
Leakage, which
should not occur
Overburden
Bedrock
Leakage, which
should not occur
Bedrock
Packer
Test section
Test section
Water intake to
be measured
Water intake to
be measured
Open-mouse test
(permeability test)
Lugeon test
(packer test)
Figure3.2.6PossibleLeakagePathonPermeabilityTests
3.3
Desander
NipponKoeiCo.,Ltd.
24|Page
The facilities will be shifted to mountain side in order to layout then on stable foundation. Although
the cost for excavation will increase due to the shift of facilities, it is recommendable to avoid the risk
of erosion from a viewpoint of long-term stability of the facilities.
Figure3.3.1Locationsofdrillholesandtestpitsindesandersite
Stability of foundation of facilities
Although the sediment trap facility and connecting waterway are not big structures, stability (mainly
bearing capacity and shear strength) of the foundations will be checked, after final layout of the
facilities are fixed. In order to utilize geological investigation results properly, it is required to show
the simplified logs of drill holes and pits on the design drawings. There is no data of the result on
existing design drawings. Although assumed rock lines are shown in some parts of HS-13-001 to HS13-004, no evidence for the estimation of the line is shown in the drawings.
Protection against erosion of foundation of facilities
Although the layout of facilities will be reviewed and re-designed as mentioned in the previous clause,
the risk of erosion due to meandering of the river should be taken into account, because of the
following situations.
-
If it is foreseen that further erosion will affect the foundation of the facilities, slope protection on the
river side of the slopes will be planned. The slope protection may be concrete wall, masonry, or
gabion fixed with stiff foundation for preventing scouring at the bottom.
NipponKoeiCo.,Ltd.
25|Page
Drilling result at BH-D4 and BH-D5 indicates completely to highly weathered tuff is distributed
to a depth of 20 m or more. The upper portions of the tuff look like soil and might be re-worked
materials.
Horseshoe-shaped lines are seen and trees look disturbed on the slopes as shown in Photo 3.3.1,
and which geomorphology is similar to what develops in landslide areas.
So far, the identified landslide feature has not been confirmed as a real landslide and it can be said as
risk at present. On the existing report, there is no description on landslides, and consequently, it is
foreseen that no check on landslides have been done yet. Landslides might exist on other locations in
project areas. If landslides really exist and activate during and after construction, certain damage to
facilities might occur. The possibility of existence of real landslides can be judged somehow in detail,
with further site investigations to be conducted, and the result will be used for clarifying the degree of
the risk and necessity of measures.
White
tree trunk
Sky
Landslide feature
Vegetation
White
tree trunk
Vegetation
Disturbance of trees
Terrace
Old scarp
Sediment
New scarp
River
Photo3.3.1Sedimenttrapfacilitysite
NipponKoeiCo.,Ltd.
26|Page
3.4
3.4.1 Geomorphology
The inlet of headrace tunnel is located on a small ridge, it is judged to be a suitable location from the
following conditions.
-
In case that the location of inlet is shifted to mountain side due to the re-layout of sediment trap
facility, the new location should be in a suitable area where there is no adverse condition in terms of
uneven earth pressure and erosion/debris flow.
Depth to assumed
rock line is 6.7 m
Depth to assumed
rock line is about 2 m
Distance is
about 8 m
H:V=1:1
Distance is
H:V=3:1 about 8 m
Overwriting on a part of
Drawing HS-03-001
Overwriting on a part of
Drawing HS-3-002
Figure3.4.1DifferentDepthtoAssumedRockLineamongDrawingsatInletSite
The location of the inlet portal will be shifted to mountain side from what shown in the design
drawings, in order to secure enough rock cover above the tunnel crown at the inlet.
NipponKoeiCo.,Ltd.
27|Page
3.5
3.5.1 Geomorphology
The headrace tunnel route lies on undulated hilly area. According to Drawing HS-03-002 of FS report,
the height elevation on the route is about 645 m with earth cover above the tunnel of about 90 m and
the lowest elevation is about 580 m with earth cover of about 25 m, except for inlet and outlet portal
section as shown in Figures 3.5.1 and 3.5.2. A straight water course lies on the location of the lowest
elevation as shown in Figure 3.5.1 and Photo 3.5.1. This water course may form a lineament,
although air-photo observation is required for the identification of the lineament.
Issues, relating to the thickness of the earth cover and the linear water course, will be described in the
next sub-clause, together with the geological conditions.
Figure3.5.1PlanofHeadracetunnel
Earth cover of
about 90 m
Earth cover of
about 25 m
Figure3.5.2SectionofHeadracetunnel
NipponKoeiCo.,Ltd.
28|Page
Photo3.5.1ConditionofWaterCourseonLowestPortiononHeadraceTunnel
Photo3.5.2UpperLayerofTuff(soft,likesoil)
NipponKoeiCo.,Ltd.
29|Page
Photo3.5.3Ignimbrite(Moderatelyhard,sparselyjointed)
Photo3.5.4LowerLayerofTuff(Moderatelyhard,densejointsbydrilling)
Groundwater level
Tuff
Ignimbrite
Tuff
Figure3.5.3GeologicalSectionofHeadraceTunnel
The upper layer of Tuff is soft and not a good foundation of tunnel, and the present design of
downstream section of tunnel (cut and fill with concrete culvert) seems suitable.
Ignimbrite and the lower layer of Tuff is moderately hard and sparsely jointed, and no serious
problem in tunnel excavation is foreseen in terms of strength of the rocks.
Points on engineering geology to be noted are as follows.
NipponKoeiCo.,Ltd.
30|Page
On the core samples of recent drilling PB-T1, two layers of palaeosoil were found, together with
palaeo-weathered zones as shown in Table 3.5.1.
Table3.5.1GeologicdescriptionofcoresampleofdrillingPBT1
Depth (m)
- 27.0
27.0 - 27.2
27.2 - 28.2
28.2 - 30.0
30.0 - 30.2
30.2 - 47.5
47.5 - 47.7
47.7 - 48.2
48.2 - 48.6
48.6 - 50.0
Geological description
Slightly weathered Ignimbrite
Palaeo-topsoil
Palaeo-soil
Highly weathered Ignimbrite
Moderately weathered Ignimbrite
Slightly weathered Ignimbrite
Palaeo-topsoil
Palaeo-soil
Highly weathered Ignimbrite
Moderately to slightly weathered Ignimbrite
In case that palaeo-topsoil and weathered zones have been eroded before sedimentation of the
next flow unit, no clear boundary of the units can be identified.
Considering the above-mentioned condition, there is possibility that soft materials might be
encountered during tunnel excavation.
Based on the condition of the soft materials in core sample of drilling PB-T1, stability of the
tunnel can be secured with applying typical section for rock class IV in Drawing HS-14-004.
In case that much softer and thicker palaeo-soil is encountered in tunnel, steel supports might be
required to secure the tunnel stability.
As mentioned in the previous sub-clause, earth cover at middle section of the tunnel (around
Chainage 1+750) is thin, about 25 m thick.
Referring to the result of drilling at BH-T4, the upper-half section of the earth cover may be soft
materials, and the lower half may be highly to moderately weathered Ignimbrite.
The tunnel stability seems to be secured by applying a proper support pattern among typical
sections shown in Drawing HS-14-004. But, serious situations might occur, if the tunnel section
is in the following adverse conditions.
-
A case that a weak zone (such as a fault or sheared zone) lies along straight water course
(see Figure 3.5.1)
A case that palaeo-topsoil or other soft materials is distributed at the tunnel elevation
NipponKoeiCo.,Ltd.
31|Page
A case that groundwater fills the weak zone (if the groundwater is pressurized with
massive cover of the upper flow unit, situation will be much worse).
Although possibility of worse situation with combination of the above-mentioned cases seems to
be low, it is recommendable to study about measures to cope with conceivable worse situations.
Groundwater level
-
In general, abrupt flush out of groundwater into tunnel cause serious accident during tunnel
excavation.
In case of the Headrace tunnel, possibility of abrupt flush out of groundwater is not so high,
because of the following conditions.
-
A high permeable layer such as the layer of palaeo-soil, is distributed on the tunnel route.
Confined and high-pressure groundwater exists in the layer as shown in Figure 3.5.5.
If there is indication of the abrupt flushing, such as increase of seepage water from tunnel
face, pilot drilling may be carried out to release the confined groundwater gradually as
shown in Figure 3.5.5.
1 km
Figure3.5.4CatchmentAreaofHeadraceTunnel
NipponKoeiCo.,Ltd.
32|Page
Confined groundwater
Free groundwater
Free groundwater
Pilot drilling
Figure3.5.5ForeseeableGroundwaterCondition
Considering risks on geological conditions and others during construction, such as trouble of
machinery, it is recommendable to consider in detail about installation of work adit as mentioned in
Clause 15.2.6.1 (page 228), FS report in order to reduce the risk of extension of construction period,
since the tunnel excavation is a critical path in construction schedule.
Possible locations of the work adits and access roads are shown in Figure 3.5.6. Inclination of the
adits will be 5% to 10%, and the half of section of adits will be constructed with open excavation. A
straight water course, along which a weak zone might be distributed, will be considered as a risk.
Possible location
: Work adit
Figure3.5.6PossibleLocationsofWorkAditsandAccessRoads
NipponKoeiCo.,Ltd.
33|Page
3.6
BH-T6
TP-W1
TP-W2
TP-W3
TP-W4
Depth (m)
3.50-4.00
9.50-10.00
13.50-14.00
17.50-18.00
5.00-5.50
11.00-11.50
13.50-14.00
17.50-18.00
1.50
2.00
1.00
2.00
1.50
1.00
2.00
Average
Maximum
Minimum
Water
Content
(%)
Specific
gravity
35.26
35.52
34.41
26.29
24.95
36.54
24.91
31.86
37.38
38.53
33.20
40.29
34.37
36.21
38.29
33.87
40.29
24.91
2.63
2.52
2.58
2.56
2.27
2.40
2.56
2.53
2.59
2.54
2.50
2.60
2.55
2.49
2.58
2.53
2.63
2.27
Shear Strength
C
(kg/cm2) (degree)
0.33
0.18
0.33
0.33
0.15
0.14
0.28
0.26
0.25
0.37
0.37
0.26
0.37
0.29
0.24
0.28
0.37
0.14
10.69
11.00
14.22
15.72
7.46
6.89
10.98
7.33
20.37
11.09
22.36
14.17
19.62
16.41
15.64
13.60
22.36
6.89
To apply gentler excavated slope gradient on the upper portions of high slopes, where softer
materials are distributed.
To install surface drain ditches on berms and natural slopes above the excavation area as well as
connecting drain between drain ditches on the berms
NipponKoeiCo.,Ltd.
34|Page
To cover the slope surface with shotcrete, etc. to prevent surface erosion and surface collapse
due to the erosion
To apply nailing with steel bars to prevent surface sliding by unifying soft portions on the slopes
To protect the lower portions of the excavated slopes with concrete wall or masonry wall to
prevent erosion on the bottom of the slopes
The above-mentioned measures i) and ii) will be added on design drawing, and measures iii) to
v) will be adopted during construction, based on the observation of the actual condition of the
excavated slope surface.
3.7
Head Pond
3.8
Penstock
35|Page
The aeolian deposit is originally soft and the deposit is accordingly weathered up to deep portion. At
the drilling point BH-P1, N values of the deposit are less than 10 to a depth of 12 m.
The other section of the Penstock is underlain by pyroclastic flow. The thickness of completely
weathered zone, which shows N=10 or less, is variable; 2 m to 10 m thick.
Aeolian deposit of
Toba Tuff Unit
Tapanuli
Group
Pyroclastic flow of
Toba Tuff Unit
Figure3.8.1EstimatedDistributionofTapanuliGroup
Surface protection measures should be taken in order to prevent erosion of the embankment.
Rip-rap materials will be embanked on the surface.
NipponKoeiCo.,Ltd.
36|Page
Under drain of pipe culvert should be inclined 3% or more to prevent sedimentation in the pipe.
Screen will be installed at the inlet, so that the pipe is not plugged with big rock fragments.
It is
Photos3.8.1and3.8.2GullyErosionafterExcavationofAccessRoadtoPowerhousesite
3.9
Powerhouse
NipponKoeiCo.,Ltd.
37|Page
Direction of
platy joints
Photo3.9.1OutcropsofModeratelyHardIgnimbriteatPowerhouseSite
Points on engineering geology are mainly on slope stability as mentioned below.
Stability of excavated slope on soil foundation
Gradient of excavated slope behind the Powerhouse are H:V=1:5 for all permanent and temporary
slopes as shown in Drawings HS-20-001 and HS-20-002. As clarified with drilling investigation at
BH-S1 and BH-S2, soft materials of 10 m thick or more are distributed on the slope behind the
Powerhouse, slope gradient on the upper portion of permanent slopes will be much gentle to secure
the stability. It is required to consider geological investigation result for the design of excavated
slopes.
Rock slide due to platy joints (cooling joints) dipping to river side
On the outcrops on the riverbed, platy joints are seen as shown in Photo 3.9.1. The platy joints seem
to be developed during cooling of welded tuff. The joints dip to river on the slope behind the
Powerhouse, and thereby, plane slide of rock mass is foreseeable on the excavated slopes. Joint
condition and slope stability of excavated rock mass should be carefully observed, and necessary
measure such as rock bolts will be taken, when indication of instability is found.
Landslide features on the left bank of the Kualu River, just upstream of the powerhouse site
Possible landslide features are identified on the topo-map as shown in Figure 3.9.1, although no
detailed site reconnaissance has been done. In case that the landslides really exit and activated during
and after construction, big amount of materials may be moving to the downstream and might
endanger the powerhouse facilities. The water course where spillway is planned may be the boundary
of the landslide masses. Water, to be flowing along spillway, might infiltrate into ground and activate
the landslides.
NipponKoeiCo.,Ltd.
38|Page
It is recommendable to carry out detailed investigation on landslide. The first step of the investigation
is site reconnaissance to clarify the evidence of the landslides. If certain evidences are found, further
investigation such as some more detailed topo-mapping and drilling investigation with laboratory test
and monitoring will be done as the second step for proper measures.
Possible
landslide
features
Figure3.9.1PossibleLandslideFeaturesjustupstreamofPowerhouseSite
NipponKoeiCo.,Ltd.
39|Page
Because of a big amount of recent sedimentation, river course is changed. Taking account of the thin
ridge on the left bank also, it is recommendable to consider changing the location of the intake as well
as the alignment of weir axis.
b)
The recent sediments also affected downstream course of weir site, where the de-sander is planned.
Some of the area of the de-sander seems to be eroded due to the change of the river course, and there
is no enough space to layout the facility. It may be necessary to shift the de-sander to the mountain
side to meet geomorphology changed recently.
c)
Possible landslide features are identified at the sites of de-sander and powerhouse. Although those
features have not been confirmed as real landslides, it is recommendable to check the possibility, in
order to minimize the risk of the landslides.
d)
Several issues are arisen on engineering geology of headrace tunnel. Although the issues are not so
serious, it is possible to encounter difficulty in tunnel excavation due to combination of several issues.
Considering that the tunnel construction is the critical path in construction schedule, it is
recommendable to consider to add work adit.
e)
Several issues are arisen on engineering geology of penstock route. In order to minimize risks
relating to penstock, it is recommendable to consider changing alignment of the penstock.
f)
Others
The re-study or re-design on the following issues may be done for smooth construction works.
-
NipponKoeiCo.,Ltd.
40|Page
4.
POWER GENERATION
4.1
General
In the Feasibility Study, the energy simulation was carried out based on the hydrological analysis and
the feasibility design for the following two scenarios.
Table4.1.1TwoScenariosforEnergySimulation
Scenario
Hydrological Duration
Base Case
Conservative Case
288.32 GWh
260.53 GWh
Hereinafter discussed are NKs comments on the input parameters for the energy simulation adopted
in the Feasibility Study, and possible impact to such simulation due to review result of the hydrology
as well as the project layout of the Study.
4.2
Project Layout
Before we examine the energy simulation, we need to discuss if the project layout proposed in the
Feasibility Study is optimal or not. The most critical issue is the penstock length of the Project.
Tw
LV
gH
Tm
0 .00274 GD 2 N 2
Pt
Tw 2
Tm
2
where,
Tw : Starting up time of water column (s)
L : Length of waterway (penstock) (m)
V : velocity of water (m/s)
g : Acceleration of gravity (m/s2)
H : Design head (m)
NipponKoeiCo.,Ltd.
41|Page
NipponKoeiCo.,Ltd.
42|Page
Alt-2-1 is to add GD2 so as to allow slow closing of the guide vane to prevent severe pressure rise. To
limit the maximum pressure rise at 35 %, the required GD2 in case of the original layout is 106 t-m,
which is judged still applicable. Cost of the additional weight of the generator is roughly estimated at
US$ 9 mil.
Alt-2-2: To adopt Pelton type turbines instead of Francis type turbines
Alt-2-2 is to adopt the Pelton type turbines, instead of the Francis type turbines. Although this type is
essentially a high head turbine, the planned discharge and the head of the Project are plotted near the
boundary, but within the application range, of the Pelton type turbines. The Pelton type turbines are
equipped with jet deflectors which allow slow closure of the needle.
Disadvantage of the Pelton type turbines is that they must be installed above the highest probable
taiwater level which may sacrifice the available head. Also the efficiency at the peak discharge is
lower than the one of the Francis type turbines. Loss of energy due to these reasons is roughly
estimated at 5.5% of the total energy. This is equivalent with additional cost of US$ 4 mil.
Alt-2-3: To adopt the pressure regulator (pressure relief valve)
Alt-2-3 is to attach pressure regulators (pressure relief valves) to the Francis type turbines to release
the excessive pressure rise induced by any rapid closing. This option, however, is not recommended
as high reliability is required for the devices. If malfunction occurs, the whole system of the Project
will be jeopardized.
Comparison of the alternatives are seen in Table 4.2.1.
Table4.2.1AlternativesforPenstockIssues
1
Alt.1-1
Alt.1-2
2
Alt.2-1
Alt.2-2
Alt.2-3
Alternatives
Stability of Penstock
To shift the head pond to
the river side
To provide a surge tank
between the head pond
and the powerhouse
Pressure Rise
To add GD2 so as to
allow slow closing of
guide vane
To adopt Pelton type
turbines instead of
Francis type turbines
To adopt the pressure
regulator (pressure relief
valve)
Advantage
Disadvantage
Assessment
No substantial impact is
caused to energy
production.
No substantial impact is
caused to energy
production.
No substantial impact is
caused to energy
production.
No substantial impact is
caused to project cost.
No substantial impact is
caused to energy
production.
In case of malfunction of
Pressure Regulator, the
system will be
jeopardized.
Source: NK
Preliminary comparison of impact to project cost and energy production as well as the risk above
reveals that Alt. 1-2 is the most recommendable option.
NipponKoeiCo.,Ltd.
43|Page
Figure4.2.1LayoutofAlt.11
Figure4.2.2LayoutofAlt.12
NipponKoeiCo.,Ltd.
44|Page
4.3
Power Generation
4.3.3 Loss
The energy loss, which is physical and/or imaginary energy not being delivered to the off-take point,
is reasonably taken into account in the Feasibility Study. The total loss assumed was 4.5% to the
theoretical maximum energy generation after deducting the river maintenance flow. It is composed of
reasonable figures; 1.5% for outage, 1% for sediment removal, and 2% for station use.
It is of paramount important for the investors to understand that the river maintenance flow would
bring about fatal damage to the Project profitability, if it is of the 95% dependable river runoff.
NipponKoeiCo.,Ltd.
45|Page
Unit
1.
Hydrology Series
Base Case
Low Case
Reg No. 38
Average
Moderate
Moderate
2.
m3/s
1.0
1.0
6.7
3.
Installed Capacity
GW
42.45
42.45
42.45
4.
GWh
288.3
260.5
190.7
5.
Availability
98.5
98.5
98.5
6.
GWh
284.0
256.7
187.9
7.
GWh
5.7
5.1
3.8
8.
Spillage Loss
GWh
2.8
2.6
1.9
9.
GWh
275.5
249.0
182.3
Plant Factor
74.1
67.0
49.0
10.
Base Case and Low Case correspond to Annex 17.3 and 17.4 of the Feasibility Study, respectively.
Reg. No. 38 corresponds to the case when the Government Regulation No.38, 2011 is strictly applied to Low
Case.
Source: based on energy simulation in Feasibility Study and Review Team
NipponKoeiCo.,Ltd.
46|Page
5.
5.1
General
The Feasibility Study identified that a total of approximately 7 km of exiting unpaved/partly paved
road will need to be upgraded and 5 km of new permanent access roads will be newly built. Among
them, the main roads to be upgraded and/or newly built are as follows.
Table5.1.1MainAccessRoadstobeUpgradedand/orNewlyBuilt
Route
Janji to Sipultak
Sipultak to Halilogoan (Head Pond)
Harilogoan to Dolok Barimbing
Dolok Barimbig to Powerhouse
Access to road to weir site
Length
1.8km
1.95km
2km
1.2km
1.5km
Existing Condition
Mostly unpaved
Unpaved
Unpaved
Unpaved
To be newly constructed
5.2
Access Road
The followings are commented as the result of the site reconnaissance and the desktop review.
-
Access to Parsoburan from Medan through the existing road is good, betterment will not be
required. However, notice and permission of police and related organization should be made and
obtained when transportation of heavy equipment.
According to the present design, the access road from Janji to near the head pond, the existing
road will be widened and paved in the same route. However, several sections of the existing
road are very steep in longitudinal gradient and too small horizontal radius. Thus, trailer to
transport heavy equipment cannot pass. Construction of new road by re-route or improvement of
vertical alignment for these sections will be necessary. Additional land acquisition will be
required. In addition, loading capacity of bridge and box culvert should be checked.
The above access road is belonging to Kabupaten Road at the moment, it is recommended to be
clear responsibility of repair and maintenance during construction and after construction
(operation stage).
New access road from the head pond to the powerhouse will be constructed in the same route of
the existing access road which was used in the investigation stage. However, this road is also too
steep, it should be re-routed.
Application of Type-1 and Type-2 shown in HS-30-004 should be clear. Typical width of
pavement is 6.0 m. It can be reduced to 4.5 m. For passing vehicle each other, preparation of a
passing bay every 500 m interval is recommendable.
NipponKoeiCo.,Ltd.
47|Page
6.
6.1
General
The Feasibility Study formulated the Project with the following main civil structures.
Table6.1.1MainCivilStructuresoftheProject
Main Structures
Intake Weir
Power Intake
Intake Channel
De-sander
Headrace Tunnel
Headrace Channel
Head Pond and Spillway
Penstock
Powerhouse
Description
A fixed overflow weir, including two sediment flushing gates at the
left bank
At the left bank, equipped with trash rack
A free flow system for a design discharge of 25 m3/s
Consisting of three surface basins and flushing facilities to remove
particles >0.3mm
2.76 km long, concrete lining at invert and walls
1.15km long open channel, U-shape, 4.0mW x 4.0mH
NOL: EL.555.0m, design discharge of spillway at 27.5m3/s
1.67km long, 2.3m dia.
Surface type equipped with 3 x 13.4MW Francis units, transformers
and switchyard, TWL: EL.347.9m
Hereinafter discussed are NKs comments on the design of the civil structures adopted in the
Feasibility Study.
6.2
NipponKoeiCo.,Ltd.
48|Page
Photo6.2.1SituationatIntakeWeirandPowerIntake
Alternative
waterway route
Waterway
Weir axis
Alternative
weir axis
Figure6.2.1ProposedLayout
NipponKoeiCo.,Ltd.
49|Page
These boulders shall be removed to downstream prior to start of the construction works as much as
possible.
In order to prevent entering such boulders in front of the power intake. It is recommended to construct
some debris barrier structure in the upstream. (refer to Figure 6.2.2.)
Victoria Fall
Photo6.2.2ConstructionWorksinUpstream
Figure6.2.2DebrisBarrierStruture
NipponKoeiCo.,Ltd.
50|Page
The design flood water levels estimated from the original 100-year flood are given in Sub-section
12.3.5.3 in the Feasibility Study Report as summarized below.
-
Due to the underestimate of 100-year flood discharge, design flood water levels in the above shall be
increased to some extent. Therefore it is necessary to make hydraulic calculation design again.
According to the feasibility report (see Sub-section 12.3.5.3), the crest elevation of embankment at the
intake weir was determined at 561.5 m a.s.l. with a freeboard of 0.6 m given during the Safety Flood
(561.5 = 560.9 + 0.6). Therefore the crest elevation of embankment shall be increased applying the
same freeboard from the safety viewpoint of Hasang weir.
Besides the above, due to an increase of the 100-year flood discharge from 539 m3/sec to 1,000 m3/sec,
the following design water levels and associated hydraulic design calculation shall be carried out by
use of HEC-RAS software as applied in the feasibility design.
-
Tail water levels (see Sub-section 12.3.5.1): Figure 12-7, Figure 12-8, Table 12-3
Weir capacity (see Sub-section 12.3.5.2): Figure 12-8
Check for un-submerged flushing conditions (see Sub-section 12.3.5.4)
Stilling basins (see Sub-section 12.3.5.5)
NipponKoeiCo.,Ltd.
51|Page
Two sets of radial gate are proposed at the weir site in the feasibility study, one of which is with a flap
gate. Due to an increase of the 100-year flood discharge, maximum flood water level in time of the
increased 100-year flood would increase from the designed water level in the feasibility study.
It might cause submergence of pin structures of radial gate. It is recommended to review on selection
of gate type through hydraulic design. If risk of submergence occurs, slide gate shall be recommended
to avoid submergence from the safety viewpoint of gate operation.
Figure6.2.3ContractionJointofOverflowWeir
Piping
Safety against piping for several sections of foundation should be checked. (refer to Figure 6.2.4)
In the left abutment, outcrop of Ignimbrite is observed and it is rather weathered and soft. In the
present design, abutment wall is designed, it is reasonable but buck-fill materials should be
impervious materials and cut-off wall maybe requested in order to align the grout curtain line up to
abutment continuously, also. The same recommendation is given in the left abutment.
NipponKoeiCo.,Ltd.
52|Page
Figure6.2.4CurtainGroutLineandStudyofPiping
Others
If key cut-off is shifted upstream by about 2.0 m,
the grouting works can be done from the toe of
Weir after concrete placement and shorten the
construction period. The curtain grout maybe
omitted if further geological investigation proves
that the permeability of the foundation rock is low.
Figure6.2.5CurtainGroutLine
6.3
NipponKoeiCo.,Ltd.
53|Page
special treatment of the foundation such as replacement of concrete with poor soil will be required.
(refer to Figure 6.3.1). Possibility of landslide is also an issue as discussed in chapter 3.3.
Figure6.3.1LocationofGeologicalInvestigation
6.3.3 De-sander
The de-sander has three (3) basins in the Feasibility Study, meanwhile two (2) basins de-sander is
conceivable to simplify the structures.
Structure of the inlet of the de-sander is rather complicated, simple structure is desirable.
The stoplog in front of gate at the inlet is not necessary always because this gate is opened in normal
condition and maintenance/repair will be done easily. In the contrary, a gate will be necessary at the
end of the de-sander, otherwise, water come into the sand trap basin from downstream during flushing
operation and flushing will be not done effectively.
Flushing channel under the de-sander is recommended to be constructed with embedded steel liner
which is act as form work because this structure is small and complicated.
Typical section of the Flushing Channel to the river is recommended to wider section and with energy
killer.
NipponKoeiCo.,Ltd.
54|Page
Figure6.3.2CommentsonDesander
6.4
Headrace Tunnel
NipponKoeiCo.,Ltd.
55|Page
Figure6.4.1ConcreteLiningofHeadraceTunnel
6.5
Headrace Channel
NipponKoeiCo.,Ltd.
56|Page
Figure6.5.1ExcavationSlopeandEmbankment
Figure6.5.2CrossDrainandBridge
6.6
Protective measure such as shot-crete or sodding against erosion on the excavated slope is
required.
NipponKoeiCo.,Ltd.
57|Page
Access Road shall be extended to gate and raking operation yard. (refer to Figure 6.6.1)
Operation yard of Head Pond Release Gate shall be widen and accessible. (refer to Figure 6.6.1)
Gravel Sluice Valve should be protected and accessible. (refer to Figure 6.6.3)
Figure6.6.1HeadPondGateOperationYard
6.6.2 Spillway
-
Guide wall of the spillway at the beginning shall be higher. (refer to Figure 6.6.2)
Application criteria of standard section of Type -2, 3, 4 and 5 are not clear. Type-3 should be
applied at the end portion only. (refer to Figure 6.6.4)
As for embankment materials, excavated site materials, mainly weathered tuff, is not suitable.
Excavated tunnel muck (ignimbrite) and/or river deposit are recommendable.
NipponKoeiCo.,Ltd.
58|Page
Figure6.6.2CommentsonHeadPond
Figure6.6.3EmbankmentandCrossDrainofSpillway
Figure6.6.4TypicalSectionofSpillway
NipponKoeiCo.,Ltd.
59|Page
6.7
Penstock
Alignment of the Penstock shall be straight, especially at the end portion as much as possible.
Arrangement of diameter (average 2.3 m) is recommended to first one-third : 2.5m, second onethird : 2.3 m and last one-third :2.1m.
Water Hammer (Pressure Rise) by emergency stop of turbine is not considered to design of the
Penstock. Water Hammer at the emergency closing of turbine should be calculated.
6.8
NipponKoeiCo.,Ltd.
60|Page
Figure6.8.1PowerhouseLayout
Figure6.8.2CofferingofPowerhouse
NipponKoeiCo.,Ltd.
61|Page
7.
7.1
Hereinafter discussed are NKs comments on the design of the hydro-mechanical works adopted in
the Feasibility Study.
7.2
Penstock
The length of standard erection piece should be longer as far as possible to minimize the number of
site welding joint. Unit pipe length should be decided from the available plate width in Indonesia.
The wider plate is preferable to make longer unit pipe.
The required plate thickness should be studied taking the local stress at saddle support into
consideration.
The method of supporting should be studied to lengthen the supporting span of penstock more than 12
m to minimize the number of concrete saddles. The ring girder support is advantageous compared
with the saddle support proposed in FS report.
According to the direction of vertical bend, a half block may be adopted for the anchor block.
Instead of trifurcation, a manifold type branch should be studied from the point of view of hydraulics
and alignment of the penstock.
Stainless steel plate should be adopted instead of stainless clad plate taking account of less
marketability of stainless clad plate.
Considering the construction time, the comparison study should be made between the erection using
winch and the direct unloading by the mobile crane, although an access road is required along the
penstock line in case of erection by mobile crane.
Taking account of the construction time, three sections should be considered for the erection of steel
penstock to shorten the duration of construction.
As for the upper part of penstock, the application of readymade steel pipe might be considerable, if
such pipe is available in Indonesia market with lower cost compared with the cost of ordered pipe.
7.3
Hydro-mechanical Equipment
62|Page
The gate leaf with flap gate is complicated for operation and maintenance. The flap should be
cancelled. For the river maintenance flow, it is preferable to install the required gate of capacity with
small dimensions. Or the spillway gate will be opened partially to discharge.
The box culvert should also be studied as an alternative plan of sediment flushing.
NipponKoeiCo.,Ltd.
63|Page
8.
8.1
General
Hereinafter discussed are NKs comments on the design of the electro-mechanical works adopted in
the Feasibility Study.
8.2
Considering the penstock length of 1,669 m in the Feasibility Study, it is considerable that type of
turbine would be changed to; i) Pelton turbine, or ii) Francis turbine with a pressure regulator
(pressure relief valve) in order to decrease the momentary pressure rise in the penstock and turbine
for economical design. However, taking account of ensuring stability of the penstock for frequency
control, it is suggested to shorten the penstock length by providing a surge tank as discussed in
chapter 4.2.
Horizontal-shaft Francis type turbine was proposed in the Feasibility Study for 207 m head and 14.5
MW output. In accordance with normal design practice, vertical-shaft Francis turbine is usually
selected for these ratings. Horizontal-shaft Francis turbine will have a disadvantage for the
powerhouse layout to arrange the required additional space for removal of the rotor and shaft
assembly from the generator.
Three (3) numbers of units are proposed in the Feasibility Study. Generally speaking, less number of
the turbine - generator units would be more economical, which depends on balance of reduction of
cost and energy. It is suggested that suitable number of units shall be confirmed along with change of
the turbine type.
8.3
Equipment Layout
8.3.1 Powerhouse
Installation Space between Uits
Referring to Drawing No. HS-20-005, there seems no sufficient space for removal of the rotor and
shaft assembly from the generator.
In case horizontal-shaft turbine is used for this project, the space between the units shall be widened
by at least 2 m and the space between Unit 3 and the powerhouse side wall by at least 2 m.
Control Room
Size of the control room is 10m x 4m. Space seems not enough. At least the size shall be doubled.
NipponKoeiCo.,Ltd.
64|Page
Panels of only 14 Protection and 15 Synchronisation are shown on the drawing. However,
operator console, mimic board, programmable controller, energy meters, low voltage panels, logging
printers etc. shall be needed.
In PLNs normal practice, SCADA is to be introduced, and sometimes independent communication
room may be needed.
Swichgear Room
Size of the switchgear room is 8m x 3.65m. Space seems not enough. Panels of only Low voltage
distribution board are shown on the drawing. The spaces between such Low voltage distribution
board are at present 0.9m only. This shall be doubled.
Location/space for 11kV cubicles shall be confirmed.
8.3.2 Switchyard
Size of the switchyard is 115 x 80m. The size of the switchyard is large enough. However, if
double-pi connection (4 circuits towers) mentioned in Pre-FS Report for 150kV TL, is employed, two
more transmission line bays become necessary.
NipponKoeiCo.,Ltd.
65|Page
9.
9.1
Comparison of different options to connect the Project with the existing transmission line system in
North Sumatra was once studied by PLN. As the result, the option to provide an interconnection point
to 150 kV transmission line at Kampung Pajak (between Aek Kanopan substation and Rantau Prapat
substation) was found to be the most suitable option for PLN. The Feasibility Study Report of the
Project (Apr., 2012) envisaged a double circuit ACSR 240 mm2 150 kV transmission line of 34.5 km
length would lead from the Project to the new Kampung Pajak substation which PLN would finance
for construction.
In the Pre-Feasibility Study for 150 kV transmission line for the Project (Sep., 2012) by BNE, the
interconnection point was again studied among the alternatives, then connecting to the existing tower,
not to the new substation, at Kampung Pajak was proposed.
9.2
Transmission Line
Connecting to Porsea, Aek Kanopan, or Rantau Prapat substations will need new transmission lines of
long distance, and apparently not feasible. It is conceived that the selected option in the Feasibility
Study to provide the new Kampung Pajak substation and the Project is connected to there is
technically the best solution, even though the construction cost of the new substation becomes
necessary. Installing circuit breakers at the connecting point of the new transmission line from the
Project to the existing line is preferable for the point of view of protection and operation.
This option was by some reasons discarded in the Pre-Feasibility Study for 150 kV transmission line,
and connection to the existing tower at Kampung Pajak by Single-pi connection or Double-pi
connection was proposed.
Single-pi connection has problem in reliability of transmission, and thus not recommendable.
Meanwhile Double-pi connection requires necessity of 4 circuits, and the price of transmission line
becomes high.
Hence, it is recommended that the comparison of construction of new Kampung Pajak substation and
Double-pi connection (4 circuits towers) are to be made again for the final decision. At present, there
may be increase of demands of rural area in Kampung Pajak.
It is noted that, if the new transmission line from the Project is connected to the existing line by a
double-pi connection without circuit breakers, every stoppage of the Hasang power plant (by fault or
maintenance) may affect the existing transmission line operation.
NipponKoeiCo.,Ltd.
66|Page
10.
10.1 General
The Feasibility Study Report of the Project describes that the overall construction period would be 36
months (including a buffer of 3 months) assuming a start of the works on 1st January 2013. The
critical path runs through the early site establishment of access road to the tunnel portals, the timely
commencement of tunnel excavation followed by lining and finishing and connection to the cut &
cover section, water filing and commissioning.
Figure10.1.1ConstructionMasterScheduleinFeasibilityStudy
Electricity during construction cannot be supplied from PLN system because capacity of power
supply at the site is not enough, the Contractor should be prepared generator at each work site.
On January 18, 2013, the proposed quarry site for aggregate located about 3 km far from the
Head Pond was inspected. Quality and quantity of this site are deemed to be satisfied the
requirements. Further, investigation to confirm quality, quantity and thickness of overburden by
boring is recommended.
Spoil Bank located upstream of the Intake Weir Site is rather dangerous. If land slide/slope
failure happen on Spoil Bank, slid materials come into Intake Weir, it is better to locate
downstream of Intake Weir site.(refer to Figure 10.2.1)
NipponKoeiCo.,Ltd.
67|Page
Location of Spoil bank mentioned above and Site Installation are better to change.(refer to
Figure 10.2.1)
Site installation/storage areas are requested to Gate & Penstock and Electro-mechanical Works
as fabrication yard and temporary storage. Top of the spoil banks are available.(refer to Figure
10.2.1)
Figure10.2.1SiteInstallationWorks
Intake Weir
-
The construction of the dividing wall requires the coffering for foundation excavation and
concreting, although this structure might be omitted in case of change the weir location.
The right downstream toe portion of the overflow section in the first stage river diversion and
the left downstream toe portion of the overflow section in the second stage river diversion are
overlapped with cofferdam and impossible to construct. It is recommended to construct the right
downstream toe portion of the overflow section together with the left side wall of the overflow
section and the layout of the second stage coffering shall be moved to downstream. (refer to
Figure 10.2.2)
The cofferdam will be constructed to close to the excavation of the Intake Weir and foundation
of river deposit. Countermeasure for leakage water will be required, blanket embankment of
impervious materials in front of the cofferdam and/or construction of sump pits and pumping up
are recommendable measure.
For transportation of Form, Re-bar and concreting, a Tower crane or Jib crane will be needed.
NipponKoeiCo.,Ltd.
68|Page
Figure10.2.2CofferingofIntakeWeir
Headrace Waterway
-
Details of inlet and outlet for the tunnel works should be clear. These will subject to the concrete
works of channel after completion of tunnel works. .(refer to Figure 10.2.3)
Figure10.2.3AccesstoHeadraceTunnel
NipponKoeiCo.,Ltd.
69|Page
Transmission Line
-
When connect to the existing 150kV Transmission Line at Kampung Pajak, stop of operation of
T/L is necessary, detail discussion with PLN is recommendable.
Construction periods of the access road are deemed to be short taking our comment in the
Chapter 4 into consideration and detail study is recommended. The construction of the access
Road is the first activity of the project and governs the all construction works.
Intake Weir
-
By shifting of Curtain Grout line in the Intake Weir mentioned in 4)-11), grouting period will be
free from the concreting works
Headrace Tunnel
-
Progress rates of the tunnel works in the schedule are not same as the text. Following progress
rates of tunnel works are considered to be reasonable or rather optimistic,
Excavation with supporting
Invert concrete
Sidewall concrete
: 100m/month
: 300 m/month or more
: 192m/month
Based on the above rates, the schedule of tunnel works without additional work adit is shown in
Figure 10.3.2. However, no geological risk is considered. The proposed schedule will be hardly
kept and delayed by 2-3 months.
On the other hand, an additional work adit will be constructed easily and does not require high
cost from the topography as shown in Figure 10.3.1. If the work adit is prepared, an delay by
geological risk and other reasons can be mitigated. The construction schedule with work adit is
shown in Figure 10.3.3.
Others
-
Design and fabrication schedules of the Hydro and Electro-mechanical Works shall be
considered and presented.
NipponKoeiCo.,Ltd.
70|Page
Figure10.3.1WorkAdit
Figure10.3.2ConstructionScheduleofHeadraceTunnelwithoutWorkAdit
NipponKoeiCo.,Ltd.
71|Page
Figure10.3.3ConstructionScheduleofHeadraceTunnelwithWorkAdit
NipponKoeiCo.,Ltd.
72|Page
11.
COST ESTIMATE
11.1 General
The cost estimate for the Project in the Feasibility Study Report was based on a price level of the first
quarter (Q1) of 2012. The costs estimated for each item were based on quantities and unit rates, or as
a mark-up on percentage basis.
The cost estimate was provided for the main components of the direct and indirect costs as follows.
Table11.1.1SummaryofProjectCostinFeasibilityStudy
Item
Amount
(1,000 US$)
Direct Cost
Civil Works
Hydro-mechanical Works (incl. Penstock)
Electro-mechanical Works
Transmission Line
Total Direct Cost
Indirect Cost
Client Administration
Engineering
Land Acquisition and EIA Cost
Technical Management Services
Insurance
Taxes (VAT on all local items)
Total Indirect Cost
Total Project Cost (without IDC)
Total Project Cost (with IDC)
35,745
10,411
24,948
10,350
81,454
4,073
4,073
4,260
2,840
4,073
9,246
28,564
110,018
129,398
Remark
5% of Direct Cost
5% of Direct Cost
Provided by the Client
Provided by the Client
5% of Direct Cost
Hereinafter discussed are NKs comments on the bill of quantities and unit prices for the direct costs
adopted in the Feasibility Study, and impact to the cost estimate due to review result of design in
compliance with NKs recommendations which are described in the preceding chapters.
NipponKoeiCo.,Ltd.
73|Page
Unit
US$/m3
US$/m3
US$/m3
US$/m3
US$/m3
US$/m2
US$/ton
Assessment
Sufficient
Sufficient
Adequate
Sufficient
Adequate
Sufficient
Adequate
74|Page
The unit prices set in the Feasibility Study seem to be sufficient or adequate.
NipponKoeiCo.,Ltd.
75|Page
Description
Cost Impact
(US$ m.)
3.23
1.
2.
2.1
17.01
98.47
1)
2)
2.2
1)
2)
3)
4)
5)
2.3
1)
2)
3)
4)
2.4
1)
2)
3)
2.5
1)
2)
2.6
1)
2)
3)
4)
2.7
1)
2)
3)
2.8
1)
2)
3)
4)
5)
6)
2.9
1)
Chapter
in this Report
11.2.1
0.20
-0.30
5.2
5.2
0.20
0.06
0.01
0.10
1.00
6.2.1
6.2.2
6.2.2
6.2.4
6.2.5
0.10
0.03
0.05
0.03
6.3.1
6.3.1
6.3.3
6.3.3
0.10
0.05
0.50
6.4.1
6.4.2
10.3
1.10
0.50
6.5.1
6.5.2
0.10
0.20
0.10
0.20
6.6.1
6.6.1
6.6.2
6.6.2
3.00
0.00
0.10
4.2.3
4.2.3
6.7.1
0.10
-0.09
0.02
0.10
0.04
1.00
6.8.1
6.8.2
6.8.2
8.3.1
8.3.2
8.3.2
5.18
13.78
9.2
76|Page
Total project cost to which the above cost impacts are incorporated is as below.
Table11.4.2SummaryofProjectCost
Item
Amount
(mil. US$)
Direct Cost
Civil Works
Hydro-mechanical Works (incl. Penstock)
Electro-mechanical Works
Transmission Line
Total Direct Cost
Indirect Cost
Client Administration
Engineering
Land Acquisition and EIA Cost
Technical Management Services
Insurance
Taxes (VAT on all local items)
Total Indirect Cost
Total Project Cost (without IDC)
Total Project Cost (with IDC)
46.53
10.46
25.95
15.53
98.47
4.92
4.92
4.26
2.84
4.92
11.17
33.03
131.50
154.67
Remark
5% of Direct Cost
5% of Direct Cost
Same as F/S
Same as F/S
5% of Direct Cost
Same assumption as F/S
NipponKoeiCo.,Ltd.
77|Page
12.
PROJECT FEASIBILITY
8,550 IDR
9,740 IDR
0.72 EUR
0.76 EUR
80 JPY
93 JPY
110.0 USDm
131.5 USDm
Hydrology =
Average
Moderate
275.5 GWh
249.0 GWh
20.7 USDm
18.7 USDm
Energy
Tariff
ROE
FS Base Case
110.0 USDm
275.5 GWh
USc7.5/kWh
14.4%*
Cost Up
131.5 USDm
275.5 GWh
USc7.5/kWh
11.2%
131.5 USDm
249.0 GWh
USc7.5/kWh
9.4%
FS has computed ROE (return on equity) to be 14.92% for the base case with USc7.5/kWh tariff, while the
Review Work does 14.4% under the same assumptions.
NipponKoeiCo.,Ltd.
78|Page
In order to compensate such possible profitability decrease, the investors should examine higher tariff
for energy sales, assuming 15.0% of the required ROE:
Analysis Cases
Energy
Tariff
ROE
Cost Up
131.5 USDm
275.5 GWh
USc9.06/kWh
15.0%
131.5 USDm
249.0 GWh
USc10.03/kWh
15.0%
The financial stream is re-analyzed as demonstrated in Table 12.2.1. This financial stream
corresponds to both of the Cost Up case and the Cost Up & Energy Less case above with the new
average tariffs of USc 9.0625/kWh and USc 10.0266/kWh respectively.
Table12.2.1UpdatedFinancialStreamwithHigherTariff
Year CAPEX
OPEX
Cost Revenue
Equity
Debt
Outstanding
Loan begin Interest
Repay
Outstanding
Loan end
Deprec
Gross
Income
Profit
ROE
65.75
65.75
21.90
46.93
43.86
3.07
46.93
-68.82
Tax
-21.89
39.45
39.45
13.15
31.44
73.24
5.13
78.36
-44.58
-13.14
26.30
26.30
8.75
24.26
95.91
6.71
102.62
-33.01
-8.75
1.94
1.94
24.96
102.62
7.18
10.26
92.36
7.31
8.53
2.13
3.45
1.98
1.98
24.96
92.36
6.47
10.26
82.10
7.31
9.21
2.30
3.96
2.02
2.02
24.96
82.10
5.75
10.26
71.83
7.31
9.88
2.47
4.47
2.06
2.06
24.96
71.83
5.03
10.26
61.57
7.31
10.56
2.64
4.97
2.10
2.10
24.96
61.57
4.31
10.26
51.31
7.31
11.24
2.81
5.48
-13.6%
2.14
2.14
24.96
51.31
3.59
10.26
41.05
7.31
11.92
2.98
5.99
-8.0%
10
2.18
2.18
24.96
41.05
2.87
10.26
30.79
7.31
12.59
3.15
6.50
-3.9%
11
2.23
2.23
24.96
30.79
2.16
10.26
20.52
7.31
13.27
3.32
7.00
-0.7%
12
2.27
2.27
24.96
20.52
1.44
10.26
10.26
7.31
13.94
3.48
7.51
1.7%
13
2.32
2.32
24.96
10.26
0.72
10.26
0.00
7.31
14.61
3.65
8.01
3.7%
14
2.36
2.36
24.96
7.31
15.28
3.82
18.78
6.8%
15
2.41
2.41
24.96
7.31
15.24
3.81
18.74
8.8%
16
2.46
2.46
24.96
7.31
15.19
3.80
18.71
10.3%
17
2.51
2.51
24.96
7.31
15.14
3.78
18.67
11.3%
18
2.56
2.56
24.96
7.31
15.09
3.77
18.63
12.1%
2.61
9.33
16.64
6.57
0.74
0.19
7.13
12.4%
20
2.66
2.66
24.96
6.57
15.73
3.93
18.37
12.9%
21
2.72
2.72
24.96
6.57
15.68
3.92
18.33
13.3%
22
2.77
2.77
24.96
6.57
15.62
3.91
18.29
13.7%
23
2.83
2.83
24.96
6.57
15.57
3.89
18.25
13.9%
24
2.88
2.88
24.96
22.08
5.52
16.56
14.1%
25
2.94
2.94
24.96
22.02
5.51
16.52
14.3%
26
3.00
3.00
24.96
21.97
5.49
16.47
14.5%
27
3.06
3.06
24.96
21.91
5.48
16.43
14.6%
28
3.12
3.12
24.96
21.84
5.46
16.38
14.7%
29
3.18
3.18
24.96
21.78
5.45
16.34
14.8%
30
3.25
3.25
24.96
21.72
5.43
16.29
14.8%
31
3.31
3.31
24.96
21.65
5.41
16.24
14.9%
32
3.38
3.38
24.96
21.59
5.40
16.19
15.0%
33
3.45
3.45
24.96
21.52
5.38
16.14
15.0%
78.70
216.92
740.61
326.69
118.28
350.99
19
TTL
6.72
138.22
43.79
102.62
777.42
54.42
102.62
689.70
142.57
79|Page
13.
As a result of review on the existing studies of the Project, this Report concludes that;
-
Average Scenario, which was applied as the inflow duration curve at the Hasang weir site in the
Feasibility Study seems to be overestimated. This might cause risk of overestimation of
expected annual energy production. It is recommended that the Moderate Scenario shall be
applied instead. Based on this, the salable annual mean energy of the Project will be 249.0
GWh, which is of about 10% decrease compared to 275.5 GWh in the Feasibility Study.
Some design considerations, which were not taken into account in the Feasibility Study, are
required to ensure technical feasibility of the Project. One of the most critical issues is
unbalance of 1,669 m long penstock against 207m head in the Feasibility Study, which may
hinder stable speed regulation, and may cause excessive pressure rise in the penstock. It is
recommended to consider a surge tank to be constructed between the head tank and the
powerhouse to overcome this issue. The other issue is type of transmission line. Single-pi
connection has problem in reliability of transmission, and thus not recommendable. It is
recommended to adopt the double-pi connection instead.
Taking account of those and other design considerations in the Report, the project cost without
IDC will be 131.5 US$m which is about 20% increase compared to 110.0 US$m in the
Feasibility Study.
The possible energy decrease and cost increase above may cause profitability decrease. To
compensate this, higher tariff should be examined.
To estimate likely variation of annual and monthly energy generation outputs, the observed
daily flow records at the Pulao Dogom station from 2000 to date shall be analyzed for prediction
of monthly energy generation through in-depth review and scrutiny of the flow data.
To confirm possibility of landslide at the de-sander site and the powerhouse site, detailed survey
shall be conducted. The first step shall be site reconnaissance to clarify the evidence of the
landslides. If certain evidences are found, further investigation such as some more detailed
topo-mapping and drilling investigation with laboratory test and monitoring shall be conducted
as the second step for proper measures.
To examine the optimum layout of the penstock and the surge tank, additional topographic
survey and geological investigation shall be conducted along the newly proposed penstock
alignment.
To confirm the optimal selection of type and number of the units of turbine-generator,
comparative study shall be conducted.
NipponKoeiCo.,Ltd.
80|Page
ANNEX
COMMENTS ON TECHNICAL PROPOSAL BY POSCO ENGINEERING
No.
1
2
3
4
5
6
7
8
9
10
POSCOs Proposal
100-yer frequency flood is estimated at
713m3/s.
1-year frequency flood is used for the river
diversion.
Locations of the intake weir and power
intake are adjusted.
Desander is composed of 2 sets of basin.
Inlet of the headrace tunnel is shifted to the
mountain side.
Alignment of the headrace tunnel is
adjusted to shorten the cut & cover section.
Dimension of excavation section of the
head race tunnel is reduced.
Rock support class ratio is changed.
Work adit is not considered for tunnel
construction.
The head pond is shifted to the direction to
the river.
11
12
13
14
15
NipponKoeiCo.,Ltd.
NKs Comment
This seems to be underestimated as
explained in Chap. 2.2 in this Report.
Common practices suggest to adopt 2- to 5year frequency flood, as explained in Chap.
2.2 in this Report.
Acceptable as explained in Chap. 6.2.
Acceptable as described in Chap. 6.3 in this
Report.
This is acceptable as explained in Chap. 3.4
in this Report.
This seems to be possible but need more
consideration. NK did not observe the core
of the additional bore hole.
This seems to be acceptable.
This seems to be acceptable.
Provision of the work adit is suggested as
explained in Chap. 10.3. in this Report.
This seems to be possible but need more
consideration. Original ground lines and
assumed rock lines should be put in the
sections so that design adequacy can be
checked.
Maybe need more consideration. NK does
not have sufficient knowledge on the site
conditions there.
Check of penstock stability and required
GD2 should be included.
Check of the water hammer analysis with
required GD2 should be included.
Powerhouse dimensions in the Feasibility
Study are not sufficient, as explained in
Chap. 8.3 in the Report.
Daily discharge in the Feasibility Study is
overestimated as explained in Chap. 2.3 in
this Report.
81|Page