01311-Construction Schedule B
01311-Construction Schedule B
01311-Construction Schedule B
CONTENTS:
Work Included......................................................................................................... 1
1.02
1.03
Reference Standards................................................................................................ 1
1.04
1.05
Part 2 - Products.............................................................................................................................. 1
Part 3 - Execution............................................................................................................................ 1
(06/23/03)
3.01
3.02
PART 1 - GENERAL
1.01
WORK INCLUDED
A.
1.02
RELATED REQUIREMENTS
A.
1.03
REFERENCE STANDARDS
Not used
1.04
QUALITY ASSURANCE
Not used
1.05
PART 2 - PRODUCTS
Not used
PART 3 - EXECUTION
3.01
SCHEDULE OF OPERATIONS
The Contractor shall submit to the Engineer a Preliminary Progress Schedule and a
Critical Path Method (CPM) Schedule (along with updates) as described below:
A.
(06/23/03)
Section 01311 - 1
B.
Critical Path Method (CPM) Schedule - The Contractor shall submit an acceptable
CPM Schedule to the Engineer within thirty (30) calendar days after the receipt of
the Notice to Proceed. Subsequent revisions to said schedule shall be submitted as
set forth hereinafter. The requirement for the CPM Schedule is included to assure
adequate planning and execution of the work and to assist the Engineer in
appraising the reasonableness of the proposed schedule and evaluating progress of
the work. The CPM Schedule submitted under this Specification shall utilize a
critical path method (CPM) format, either the precedence or arrow diagramming
method with schedule showing completion of contract completion date, with
neither Contractor nor the City owning "float." No more than one (1) progress
payment will be made prior to submission and acceptance of the CPM Schedule.
1.
Section 01311 - 2
2.
The critical path shall be shown on all reports and on the graphic network
diagram. The activities that constitute the critical path shall be identified.
3.
(06/23/03)
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
slack or float
k.
l.
4.
5.
b.
Section 01311 - 3
c.
6.
C.
Section 01311 - 4
ii.
iii.
Schedule Review - Once each month, on a date mutually agreed upon, but no later
than seven (7) working days after the monthly schedule progress report date, a jobsite meeting will be held to review the Construction Schedule and job progress.
The Contractor shall also attend weekly meetings scheduled by the Engineer to
review the progress of the work in the preceding week and in the subsequent work,
coordinate the work with public agencies or other contractors as required, and allow
the Engineer to plan his activities for testing, inspection, etc.
(06/23/03)
D.
E.
3.02
1.
When delay in completion of any work item or sequence of work items results
in an estimated extension of project completion by either twenty (20) working
days or by five percent (5%) of the remaining duration of time to complete the
Contract, whichever is less.
2.
3.
When the schedule does not represent actual prosecution and progress of the
work.
4.
When any change to the sequence of activities, the completion date for major
portions of the work, or when changes occur which affect the critical path.
5.
Cash Flow Projection - A cash flow projection shall be submitted with the
Construction Schedule. This cash flow projection shall be revised and resubmitted
when revisions of the Construction Schedule will result in changes to the projected
cash flow.
(06/23/03)
Schedule Revisions - The conditions under which the Engineer will require
revisions of the Construction Schedule include the following:
When change orders are initiated, delays are experienced or the Contractor, desires
to revise the logic, the Contractor shall submit to the Engineer a written Time
Impact Analysis illustrating the influence of each change, delay, or Contractor
request on the current contract schedule completion date. Each Time Impact
Analysis shall include a fragment (fragmentary network analysis) demonstrating
how the Contractor proposes to incorporate the change order, delay, or Contractor
request into the Detailed Network. The analysis shall demonstrate the time impact
based on the date of occurrence of the change, delay, etc., the status of construction
at the point in time, and the event time computation of all affected activities. The
event times used in the analysis shall be those included in the latest update copy of
the Detailed Network or as adjusted by mutual agreement.
Section 01311 - 5
B.
Activity time delays will not automatically mean that an extension of contract time
is warranted or due the Contractor. It is possible that a strike or contract
modification will not affect existing critical activities or cause non-critical activities
to become critical, i.e., a strike or modification may result in only absorbing a part
of the available total float that may exist within an activity chain of the network,
thereby not causing any affect on the contract completion date or time. Float or
slack is not for the exclusive use of or benefit of the Owner, Engineer, or the
Contractor. Extensions of time or performance will be granted only to the extent
that the equitable time adjustments for the activity or activities affected exceeds the
total float along the activity chain involved at the time the change was ordered or
delay occurred.
C.
Each Time Impact Analysis shall be submitted in triplicate and within fifteen (15)
calendar days after a delay occurs or notice of direction for a change is given to the
Contractor. In cases where the Contractor does not submit a Time Impact Analysis
for a specific change order delay, or Contractor request within the specified period
of time, then it is mutually agreed that particular change order, delay or Contractor
request has no time impact on the contract completion date and no time extension is
required. Approval or rejection of each Time Impact Analysis is by the Engineer
and Owner and shall be made within fifteen (15) calendar days after receipt of each
Time Impact Analysis unless subsequent meetings and negotiations are necessary.
Upon approval, a copy of the time Impact Analysis signed by the Engineer and
Owner will be returned to the Contractor. Upon mutual agreement by both parties,
fragmentary network(s) illustrating the influence of change orders, delays, and/or
Contractor requests will be incorporated into the detailed Network during the first
update after agreement is reached.
End of Section
Section 01311 - 6
(06/23/03)