01311-Construction Schedule B

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

SECTION 01311 - CONSTRUCTION SCHEDULE B

CONTENTS:

Part 1 - General ............................................................................................................................... 1


1.01

Work Included......................................................................................................... 1

1.02

Related Requirements ............................................................................................. 1

1.03

Reference Standards................................................................................................ 1

1.04

Quality Assurance ................................................................................................... 1

1.05

Measurement and Payment ..................................................................................... 1

Part 2 - Products.............................................................................................................................. 1
Part 3 - Execution............................................................................................................................ 1

(06/23/03)

3.01

Schedule of Operations ........................................................................................... 1

3.02

Time Impact Analysis for Changes, Delays, Time Extensions,


and Contractor Requests ......................................................................................... 5

Section 01311 TOC 1

SECTION 01311 - CONSTRUCTION SCHEDULE B

PART 1 - GENERAL
1.01

WORK INCLUDED
A.

1.02

RELATED REQUIREMENTS
A.

1.03

Provide a schedule of major construction activities.

Section 01340, "Submittals"

REFERENCE STANDARDS
Not used

1.04

QUALITY ASSURANCE
Not used

1.05

MEASUREMENT AND PAYMENT


Not used

PART 2 - PRODUCTS
Not used
PART 3 - EXECUTION
3.01

SCHEDULE OF OPERATIONS
The Contractor shall submit to the Engineer a Preliminary Progress Schedule and a
Critical Path Method (CPM) Schedule (along with updates) as described below:
A.

(06/23/03)

Preliminary Progress Schedule - The Contractor shall submit to the Engineer,


within ten (10) working days after date of the contract award, a Preliminary
Progress Schedule covering the Contractor's activities during the first ninety (90)
calendar days of the contract. The Preliminary Progress Schedule shall be subject
to favorable review by the Engineer, and shall be amended as required by the
Engineer.

Section 01311 - 1

B.

Critical Path Method (CPM) Schedule - The Contractor shall submit an acceptable
CPM Schedule to the Engineer within thirty (30) calendar days after the receipt of
the Notice to Proceed. Subsequent revisions to said schedule shall be submitted as
set forth hereinafter. The requirement for the CPM Schedule is included to assure
adequate planning and execution of the work and to assist the Engineer in
appraising the reasonableness of the proposed schedule and evaluating progress of
the work. The CPM Schedule submitted under this Specification shall utilize a
critical path method (CPM) format, either the precedence or arrow diagramming
method with schedule showing completion of contract completion date, with
neither Contractor nor the City owning "float." No more than one (1) progress
payment will be made prior to submission and acceptance of the CPM Schedule.
1.

The CPM Schedule system shall consist of diagrams and accompanying


mathematical analyses. The diagrams shall show elements of the project in
detail and an entire project summary. Diagrams shall show the order and
interdependence of activities and sequence in which the work is to be
accomplished as planned by the Contractor. The basic concept of a network
analysis diagram shall be followed to show how the start of a given activity is
dependent on the completion of preceding activities and its completion restricts
the start of following activities. Detailed network activities shall include, in
addition to construction activities, the submittal and approval of samples and
equipment, fabrication of special material and equipment and their installation
and testing. Cost value of each activity shall be included. All activities of the
Owner and the Engineer that affect progress and required contract dates for
completion of all or parts of the work shall be shown. The selection and
number of activities shall be subject to favorable review by the Engineer.
Summary networks shall be time-scaled. Duration shall be in working days
and shall not exceed fifteen (15) working days, except for submittal and
delivery items. Where the duration of continuous work exceeds fifteen (15)
working days, work items in the Construction Schedule shall be subdivided by
location, approximate stationing or other sub-element of the work.
The graphic network diagram shall include for each activity, the description,
activity number, the estimated duration in working days, and all activity
relationship lines. The network diagram shall be drawn for the early start of all
activities. If the precedence technique is utilized, the schedule report shall
include a calendar in working days, a network report sorted by early start and a
logic table report sorted by preceding work item. If the arrow technique is
utilized, the schedule report shall include a calendar in working days, a
network report sorted by early start, a network report sorted by I-J numbers,
and a network sorted by slack time and I-J numbers.

Section 01311 - 2

2.

The critical path shall be shown on all reports and on the graphic network
diagram. The activities that constitute the critical path shall be identified.

3.

The mathematical analysis of the network diagram shall include a tabulation of


each activity. The following information shall be furnished as a minimum for
each activity:
(06/23/03)

(06/23/03)

a.

preceding and following event numbers

b.

activity description and number

c.

estimated duration of activities

d.

earliest start date (by calendar date)

e.

earliest finish date (by calendar date)

f.

actual start date (by calendar date)

g.

actual finish date (by calendar date)

h.

latest start date (by calendar date)

i.

latest finish date (by calendar date)

j.

slack or float

k.

percentage of activity completed

l.

cost value of each activity

4.

The program shall be capable of accepting revised completion dates as


modified by approved time adjustments and re-computations of all tabulation
dates and float accordingly.

5.

Submission and review of the system shall be as follows:


a.

The complete network analysis system, consisting of the detailed network


mathematical analysis and network diagrams, shall be submitted within
thirty (30) calendar days after receipt of Notice to Proceed.

b.

The Contractor shall participate in a review and evaluation of the proposed


network diagrams and analysis by the Engineer. Any revisions necessary
as a result of this review shall be resubmitted for review by the Engineer
within ten (10) calendar days. When completed, the favorably reviewed
schedule shall then be the schedule to be used by the Contractor for
planning, organizing, and directing the work, and for reporting progress.
If the Contractor thereafter desires to make significant changes in his
method of operating and scheduling, he shall notify the Engineer in
writing stating the reasons for the change.

Section 01311 - 3

c.

6.

C.

Section 01311 - 4

The Contractor shall submit at monthly intervals a report of the actual


construction progress. Each monthly report shall cover a period of
approximately thirty (30) days ending around the 30th of each month. The
monthly reports shall be submitted within ten (10) calendar days of the end
of the reporting period.
i.

If the project is proceeding on schedule, the monthly update report


may consist of a marked-up copy of the graphical network diagram.
This submittal shall clearly indicate the status of any minor shifts
in sequence or schedule and the estimated completion date or
percent complete of all activities currently in progress. The
contract completion date shall also be indicated. The Contractor
shall submit a narrative report relating to status of construction, the
schedule, and factors that may affect the remainder of the schedule.
The report shall show the activities or portions of activities
completed during the reporting period. The report shall state the
percentage of the work actually completed and scheduled as of the
report date and the progress along the critical path in terms of days
ahead or behind the allowable dates.

ii.

If, in the opinion of the Engineer, the project is behind schedule,


the monthly report shall include a revised network diagram and/or
mathematical analysis showing the Contractor's proposed revised
schedule. An analysis of the effect that the delay has on progress
along other paths shall also be included in the report. The
Contractor shall also submit a narrative report with each updated
analysis which shall include but not be limited to a description of
current and anticipated problem areas, delaying factors and their
impact, and an explanation of corrective actions taken or proposed.

iii.

A minimum of eight (8) copies of the periodic reports shall be


submitted to the Engineer, who shall return two (2) copies to the
Contractor after their approval.

To the extent that the favorably reviewed initial Construction Schedule, or


revisions thereto, indicate anything not jointly agreed upon, it shall be deemed
to be not favorably reviewed by the Engineer. Any omission of work from the
detailed schedule, otherwise required for Contract compliance, will not excuse
the Contractor from completing such work within any applicable completion
date. The CPM Schedule shall be generated by computer methods.

Schedule Review - Once each month, on a date mutually agreed upon, but no later
than seven (7) working days after the monthly schedule progress report date, a jobsite meeting will be held to review the Construction Schedule and job progress.
The Contractor shall also attend weekly meetings scheduled by the Engineer to
review the progress of the work in the preceding week and in the subsequent work,
coordinate the work with public agencies or other contractors as required, and allow
the Engineer to plan his activities for testing, inspection, etc.
(06/23/03)

D.

E.

3.02

1.

When delay in completion of any work item or sequence of work items results
in an estimated extension of project completion by either twenty (20) working
days or by five percent (5%) of the remaining duration of time to complete the
Contract, whichever is less.

2.

When delays in submittals or deliveries make re-planning or rescheduling of


the work necessary.

3.

When the schedule does not represent actual prosecution and progress of the
work.

4.

When any change to the sequence of activities, the completion date for major
portions of the work, or when changes occur which affect the critical path.

5.

When Contract modification necessitates schedule revision, the Contractor


shall submit a schedule analysis of all change order work with his proposal.

Cash Flow Projection - A cash flow projection shall be submitted with the
Construction Schedule. This cash flow projection shall be revised and resubmitted
when revisions of the Construction Schedule will result in changes to the projected
cash flow.

TIME IMPACT ANALYSIS FOR CHANGES, DELAYS, TIME EXTENSIONS, AND


CONTRACTOR REQUESTS
A.

(06/23/03)

Schedule Revisions - The conditions under which the Engineer will require
revisions of the Construction Schedule include the following:

When change orders are initiated, delays are experienced or the Contractor, desires
to revise the logic, the Contractor shall submit to the Engineer a written Time
Impact Analysis illustrating the influence of each change, delay, or Contractor
request on the current contract schedule completion date. Each Time Impact
Analysis shall include a fragment (fragmentary network analysis) demonstrating
how the Contractor proposes to incorporate the change order, delay, or Contractor
request into the Detailed Network. The analysis shall demonstrate the time impact
based on the date of occurrence of the change, delay, etc., the status of construction
at the point in time, and the event time computation of all affected activities. The
event times used in the analysis shall be those included in the latest update copy of
the Detailed Network or as adjusted by mutual agreement.

Section 01311 - 5

B.

Activity time delays will not automatically mean that an extension of contract time
is warranted or due the Contractor. It is possible that a strike or contract
modification will not affect existing critical activities or cause non-critical activities
to become critical, i.e., a strike or modification may result in only absorbing a part
of the available total float that may exist within an activity chain of the network,
thereby not causing any affect on the contract completion date or time. Float or
slack is not for the exclusive use of or benefit of the Owner, Engineer, or the
Contractor. Extensions of time or performance will be granted only to the extent
that the equitable time adjustments for the activity or activities affected exceeds the
total float along the activity chain involved at the time the change was ordered or
delay occurred.

C.

Each Time Impact Analysis shall be submitted in triplicate and within fifteen (15)
calendar days after a delay occurs or notice of direction for a change is given to the
Contractor. In cases where the Contractor does not submit a Time Impact Analysis
for a specific change order delay, or Contractor request within the specified period
of time, then it is mutually agreed that particular change order, delay or Contractor
request has no time impact on the contract completion date and no time extension is
required. Approval or rejection of each Time Impact Analysis is by the Engineer
and Owner and shall be made within fifteen (15) calendar days after receipt of each
Time Impact Analysis unless subsequent meetings and negotiations are necessary.
Upon approval, a copy of the time Impact Analysis signed by the Engineer and
Owner will be returned to the Contractor. Upon mutual agreement by both parties,
fragmentary network(s) illustrating the influence of change orders, delays, and/or
Contractor requests will be incorporated into the detailed Network during the first
update after agreement is reached.

End of Section

Section 01311 - 6

(06/23/03)

You might also like