Working Group 7: Earthquake Resistant Structures
Geneva, 25 September 2015
SeismicAssessmentandRetrofittingofStructures:
Eurocode8Part3andtheGreekCodeonSeismicStructural
Interventions
Prof. Stephanos E. Dritsos, University of Patras, Greece
CONTENT
Introduction
Performance Levels or Damage Levels
Elements Behaviour
Documentation
Methods of Analysis
Seismic Strengthening Strategies - Methods of Strengthening the
Whole Structure
Composite Elements
2
INTRODUCTION
EUROCODES
European Standard (EN) for the Design
EN 1990 Eurocode 0:
Basis of Structural Design
EN 1991 Eurocode 1:
Actions on structures
EN 1992 Eurocode 2:
Design of concrete structures
EN 1993 Eurocode 3:
Design of steel structures
EN 1994 Eurocode 4:
Design of composite steel and concrete
structures
EN 1995 Eurocode 5:
Design of timber structures
EN 1996 Eurocode 6:
Design of masonry structures
EN 1997 Eurocode 7:
Geotechnical design
EN 1998 Eurocode 8:
Design of structures for earthquake
resistance
EN 1999 Eurocode 9:
Design of aluminium structures
Eurocode 8- Design of structures for earthquake resistance
1: 1998-1
General rules, seismic actions and rules for buildings
2: 1998-2
Bridges
3: 1998-3
Assessment and retrofitting of buildings
4: 1998-4
Silos, tanks and pipelines
5: 1998-5
Foundations, retaining structures and geotechnical
aspects
6: 1998-6
Towers, masts and chimneys
5
CODE ENVIRONMENT
EUROPE
1983
1995
1996
CEB Bul. No. 162, Assessment of
Concrete Structures and Design Procedures
for Upgrading (Redesign).
EC 8-Part 1.4, Eurocode 8: Design
Provisions for Earthquake Resistance of
Structures: Part 1-4: Strengthening and
Repair of Buildings
fib Bul.No24, Seismic Assessment and
Retrofit of Reinforced Concrete Buildings.
2005
EC 8-Part3, Eurocode 8: Design of Structures for
Earthquake Resistance. Part 3: Assessment
and Retrofitting of Buildings. Draft No 5.
2006
GCSI, Greek Code of Structural Interventions.
2007
2008
2012
ATC 40.
Seismic Evaluation
and Retrofit of Concrete Buildings.
FEMA 356.
Prestandard and Commentary for the
Seismic Rehabilitation of Buildings.
2000
2003
U.S.A.
GCSI, Draft
ASCE/SEI 41, ASCE Standards Seismic
Rehabilitationof Existing Buildings.
ASCE/SEI 41, Supplement1,
Update ASCE/SEI 41.
WEAKNESSES OF EXISTING OLD STRUCTURES
UNDER SEISMIC ACTIONS
(a)
The structural system of many old buildings was designed with architectural
excesses. Lack of regularity (geometry, strength or stiffness) in plan or
in elevation.
(b) A number of approximations and simplifications were adopted in the analysis.
Computers were not in use, 3D analysis was impossible, 2D rarely used. Beams
and columns were considered independent elements.
(c)
Critical matters concerning the behaviour of structures under earthquake
actions were ignored.
Ductility
Capacity design
Inadequate code provisions for detailing of concrete elements (minimum
stirrups,lower limit for compressive reinforcement, upper limit for tensile
reinforcement)
(d) Design for seismic actions much lower than that now accepted for new structures.
ESTIMATED SEISMIC CAPACITY OF CONCRETE BUILDINGS:
OLD/NEW ~ 1/3
7
QUESTIONS
Which structures have the priority to be strengthened and how to identify them?
Is it possible (or is it worth) strengthening these structures and to what extent?
Is this preferable when compared to the demolition and reconstruction solution?
What resources (materials, methods, techniques) are available to intervene and
under what standards are they to be applied?
Which is the best method of intervention in a specific structure?
Which is the design framework to assess the seismic capacity of an existing
structure and document choices for retrofitting or strengthening?
What are the quality control procedures for intervention works?
8
REDESIGN
A MUCH MORE COMPLICATED ISSUE
THAN THE DESIGN OF NEW STRUCTURES
Limited knowledge, poorly documented for the subject
Lack of codes or other regulations
The configuration of the structural system of an existing structure may not
be permitted. However it exists
High uncertainty in the basic data of the initial phase of documentation.
Hidden errors or faults
Use of new materials which are still under investigation!
Low (or negative) qualifications or experience of workmanship
9
Why we need a new design framework in addition to the
existing one for new structures?
Existing Structures:
(a) Reflect the state of knowledge at the time of their construction
(b) May contain hidden gross errors
(c) May have been stressed in previous earthquakes
(or other accidental actions) with unknown effects
Structural assessment and redesign of an existing structure due to
a structural intervention are subjected to a different degree of
uncertainty than the design of a new structure
Different material and structural safety factors are required
Different analysis procedures may be necessary depending on the
completeness and reliability of available data
Usually, analytical procedures (or software) used for the design of
new structures are not suitable to assess existing structures. New
structures designed according to new codes necessarily fulfil specific code
requirements for being analysed acceptably with conventional analytical
10
procedures, e.g. linear elastic analysis
THREE MAIN OBJECTIVES
Assess the seismic capacity of an existing structure
Decide the necessary intervention work
Design the intervention work
11
ASSESSMENT PROCEDURE
1st stage
Document the existing structure
2nd stage
Assessment of the (seismic) capacity of the structure
3rd stage
Decide if structural intervention required
4th stage
Design the structural intervention
5th stage
Design in progress
Construct the intervention work
12
PERFORMANCELEVELS
OR
DAMAGELEVELS
13
What is failure?
Action effects > Resistance
Distinguishing elements for Ductile" and Brittle"
Brittle: Verified in terms of forces (known as M, N, V)
Ductile: Verified in terms of deformation
Let
M Rd 150 KNm M sd 200 KNm
In a study of a new building this is never accepted
However in an existing building this is very possible to occur
Questions: What level of damage will there be?
What are the consequences?
Is this acceptable?
14
DamageLevels
Performance Levels or Limit States (LS)
LS Level A Limitation Damage (DL)
Immediate Occupancy (other Codes e.g.
FEMA): Minimal damage, elements have not
substantially yielded
LS Level B of Significant Damage (SD)
Life Safety (other Codes e.g. FEMA): Building
with serious damage accepted as the design
of new buildings
LS Level C of Near Collapse (NC)
Collapse prevention (other Codes e.g. FEMA):
Extensive and serious or severe damage, building
is very close to collapse
15
PERFORMANCE LEVELS
Acceptable Performance Levels or Level of Protection (e.g. State of Damage)
of the Structure:
Level A: Immediately Occupancy (IO) or Damage Limitation (DL)
Very light damage
Structural elements retain their strength and stiffness
No permanent drifts
No significant cracking of infill walls
Damage could be economically repaired
Level B: Life Safety (LS) or Significant Damage (SD)
Significant damage to the structural system however retention
of some lateral strength and stiffness
Vertical elements capable of sustaining vertical loads
Infill walls severally damaged
Moderate permanent drifts exist
The structure can sustain moderate aftershocks
The cost of repair may be high. The cost of reconstruction should be
examined as an alternative solution
16
PERFORMANCE LEVELS
Level C: Collapse Prevention (CP) or Near Collapse (NP)
Structure heavily damaged with low lateral strength and stiffness
Vertical elements capable of sustaining vertical loads
Most non-structural components have collapsed
Large permanent drifts
Structure is near collapse and possibly cannot survive a moderate
aftershock
Uneconomical to repair. Reconstruction the most probable solution
17
PERFORMANCE LEVELS
Gradual pushing (static horizontal loading) of structure up to failure
V3
V2
1 2 3
V1
3
3
3 2 1
Points (vi, i)
(Base shear)
Performance Levels
Capacity curve
V3
V2
V1
(Top displacement)
1 2 3
Light
Significant Heavily
damage
18
SEISMIC ACTIONS
What is the design seismic action?
Which return period should be selected for the seismic action?
Should this be the same as for new structures?
Design Levels
Occurrence probability
in 50 years
Collapse prevention
(CP)
Life safety
(LS)
Immediately occupancy
(IO)
2%
Return period 2475 years
CP2%
LS2%
DL2%
10%
Return period 475 years
CP10%
LS10%
DL10%
20%
Return period 225 years
CP20%
LS20%
DL20%
50%
Return period 70 years
CP50%
LS50%
DL50%
Usual design of new buildings
Design of important structures (remain functional during earthquake)
Minimum acceptable seismic action level
Instead, do nothing due to economic, cultural, aesthetic
and functional reasons
19
Performance Levels according to the Greek Code
of Structural Interventions (Greek.C.S.I.)
Seismicactivity
probabilityof
exceedanceinthe
conventionaldesignlife
of50years
MinimalDamage
(ImmediateOccupancy)
SevereDamage
(LifeSafety)
CollapsePrevention
10%
(Seismicactions
accordingto 81)
50%
(Seismicactions =
0.6x81)
The public authority defines when the 50% probability is not permitted
20
ELEMENTSBEHAVIOUR
21
ELEMENT BEHAVIOR
Ductile
Brittle
Flexure controlled
Shear controlled
Sd Rd
deformation demand
deformation capacity
Seismically Primary
Sd Rd
strength demand
strength capacity
Seismically Secondary
Secondary seismic element
More damage is acceptable for the same Performance Level
Considered not participating in the seismic action resisting system.
Strength and stiffness are neglected
Able to support gravity loads when subjected to seismic displacements
22
REINFORCEDCONCRTETESTRUCTURES
ElementsCapacityCurve
d
m
y
ef
upl
M y Ls
3 y
y
Fy
K
y
Fy
y
23
Elements Capacity
Chord rotation at yielding of a concrete element
Beams and columns
Walls of rectangular,
T- or barbell section
The value of the total chord rotation capacity of concrete elements under cyclic loading
The value of the plastic part of the chord rotation capacity of concrete elements under cyclic loading
24
Inequality of Safety
is the design action effect
Sd Rd
is the design resistance
u ) / 2
Rd
1 y u
Rd 2
u
Rd
Rd
u
Rd
Rd
C Level (NC)
concern deformations,
Rd
concern forces
,
d
Rd
B Level (LS)
A Level (IO)
For ductile components/mechanisms (e.g. flexural)
For brittle components/mechanisms (e.g. shear)
dR
R,
d
S
u, dS
(G.S.I. Code)
d
S R
ELEMENTS SAFETY VERIFICATION
primary elements
secondary elements
Rd 1,8
Rd 1, 0
Rd 1,8
Rd 1,8
for primary elements
for secondary elements
25
ELEMENTS SHEAR CAPACITY
Beams and Columns
rectangular web cross section
circular cross section
Shear Walls
Short Columns (LV/h)2
26
DOCUMENTATION
27
ASSESSMENT PROCEDURE
1st stage
Document the existing structure
2nd stage
Assessment of the (seismic) capacity of the structure
3rd stage
Decide if structural intervention required
4th stage
Design the structural intervention
5th stage
Design in progress
Construct the intervention work
28
Documentation of an Existing Structure
Strength of materials
Reinforcement
Geometry (including foundation)
Actual loads
Past damage or wear and tear or defects
Knowledge Levels (KL)
Confidence factors (Other safety factors for existing
materials and elements)
New safety factors for new materials
29
KnowledgeLevels(KL)
Full Knowledge
KL3
Normal Knowledge
KL2
Limited Knowledge
KL1
Inadequate: May allowed only for secondary elements
30
DOCUMENTATION
Knowledge Levels and Confidence Factors
KL1: Limited Knowledge
KL2: Normal Knowledge
KL3: Full Knowledge
=
1.35
=
1.20
=
31
1.00
Knowledge Levels (KL) for Materials Data
Assessment methods fc:
Concrete (G.C.S.I.)
- Combination of indirect (non-destructive) methods.
- Calibrate with destructive methods involving taking samples (e.g. cores).
- Pay attention to correct correlation between destructive and non-destructive methods.
- Final use of calibrated non-destructive methods throughout the structure
Required number of specimens
- Not all together, i.e. spread out over all floors and all components
- At least 3 cores per alike component per two floors, definitely for the "critical"
floor level
Additional methods (acoustic or Schmidt Hammer or extrusion or rivet for
fc < 15 MPa)
- Full knowledge/storey: 45% vertical elements/25% horizontal elements
- Normal knowledge/storey: 30% vertical elements/25% horizontal elements
- Limited knowledge/storey: 15% vertical elements/7.5% horizontal elements
Steel
Visual identification and classification is allowed. In this case, the KL is32
32
considered KL2
Knowledge Levels for Details Data
Data Sources:
1. Data from the original study plans that has proof of implementation
2. Data from the original study plans which has been implemented
with a few modifications identified during the investigation
3. Data from a reference statement (legend) in the original study plan
4. Data that has been established and/or measured and/or acquired reliably
5. Data that has been determined indirectly
6. Data that has been reasonably obtained from engineering judgement
33
Knowledge Levels for Details Data (G.C.S.I.)
DATA ORIGIN
ORIGINAL
DESIGN
DRAWINGS
Exist
NOTES
DATA
TYPE AND
GEOMETRY OF
FOUNDATION OR
SUPERSTRUCTURE
Do
not
exist
KL1
Data that is derived from a
drawing of the original design
that is proved to have been
applied without modification
(1)
Data that is derived from a
drawing of the original design
that has been applied with few
modifications
(2)
Data that is derived from a
reference (e.g. legend in a
drawing of the original design)
(3)
Data that has been determined
and/or measured and/or surveyed
reliably
(4)
Data that has been determined by
an indirect but sufficiently
reliable manner
(5)
Data that has been reasonably
assumed using the Engineers
judgment
(6)
KL2
KL3
THICKNESS, WEIGHT
etc. OF INFILL
WALLS, CLADDING,
COVERING, etc.
KL1
KL2
KL3
REINFORCEMENT
LAYOUT AND
DETAILING
KL1
KL2
KL3
34
METHODSOFANALYSIS
35
METHODS OF ANALYSIS
In Redesign other analysis methods are required
Elastic analysis methods currently in use (for new buildings) have a
reliability under specific conditions to make sure new buildings to be
met.
In most cases, these conditions are not met in the old buildings.
36
METHODS OF ANALYSIS
Same as those used for design new construction (EC8-Part 1)
Lateral force analysis (linear)
Modal response spectrum analysis (linear)
Non-linear static (pushover) analysis
Non-linear time history dynamic analysis
q-factor approach
37
PERFORMANCE LEVELS
Gradual pushing (static horizontal loading) of structure up to failure
V3
V2
1 2 3
V1
3
3
3 2 1
Points (vi, i)
(Base shear)
Performance Levels
Capacity curve
V3
V2
V1
(Top displacement)
1 2 3
Light
Significant Heavily
damage
38
CAPACITY DEMAND
d
acceptable curve
acceptable demand curve
T1
T2
2
=
2 d g
4
T1
T2
code elastic spectrum
demand curves
elastic spectrum
V = d W
0.90
1.20
0.80
1.35
inelastic spectrum
39
SAFETY VERIFICATION
Checking a Structures Capacity
Sufficient for Level A
Insufficient
Safe Behaviour
Unsafe behaviour
Sufficient for Level B
Sufficient for Level C
Demand Curve
(Required Seismic Capacity)
40
SeismicStrengtheningStrategies
MethodsofStrengtheningtheWhole
Structure
41
SEISMIC STREGHTENING STRATEGIES
(d) Enhancing strength and stiffness
Base Shear
(c) Enhancing strength and ductility
(b2) As (b1) plus some strength increase
(s) Required seismic capacity
(a) Initial capacity
(b1) Retrofitting local weakness and enhancement of ductility
Displacement
Safe Design
Unsafe Design
42
SEISMIC STRENGHTENIG METHODS
Strength
&
Ductility
Strength
Add New Walls
(a) Infill walls
(b) Externally attached to the
structural system
(specific design)
Steel or
Concrete
Bracing
Adding RC
Wing Walls
Ductility
Jackets
(a) of RC
(b) of steel elements
(c) of composite materials
Strength & Stiffness
43
The relative effectiveness of strengthening
44
AddingSimpleInfill
Addition of walls from: a) Unreinforced or reinforced concrete
(cast in situ or prefabricated)
b) Unreinforced or reinforced masonry
No specific requirement to connect infill to the existing frame
Modelling of infills by diagonal strut
Low ductility of infill. Recommended m 1,5
WARNING
Additional shear forces are induced in the columns and beams of the frame
45
Strengtheningofexistingmasonryinfills
Reinforced shotcrete concrete layers applied to both sides of the wall
Minimum concrete thickness 50 mm
Minimum reinforcement ratio vertical = horizontal = 0,005
Essential to positively connect both sides by bolting through the wall
No need to connect to existing frame as it is an infill
All new construction must be suitably connected to the existing foundation
46
46
FrameEncasement
Reinforcedwallsareconstructedfromonecolumntoanotherenclosingtheframe
(includingthebeam)withjacketsplacedaroundthecolumns.Note,allnew
constructionmustbesuitablyconnectedtotheexistingfoundation
New column
New wall
Existing column
New column
Existing column
New wall
47
New wall
Existing column
New wall
Existing column
Jacket
Infilling new shear walls
Existing column
Existing column
New wing wall
New wing wall
Jacket
Addition of new wing walls
48
Existing vertical element configuration (PLAN)
49
Strengthening proposal
50
51
52
53
Schematic arrangement of connections between
existing building and new wall
Addition of new external walls
54
Addition of a bracing system
55
56
57
Temporary support and stiffening of the damaged soft floor
58
COMPOSITEELEMENTS
59
STRUCTURAL DESIGN OF INTERVENTIONS
Greek Retrofitting Code (GRECO) Ch. 8
Concrete
Steel
FRP
8.1Generalrequirements
Interfaceverification
8.2Interventionsforcriticalregionsoflinearstructuralelements
Interventionswithacapacityobjectiveagainstflexurewithaxialforce
Interventionswiththeobjectiveofincreasingtheshearcapacity
Interventionswiththeobjectiveofincreasinglocalductility
Interventionswiththeobjectiveofincreasingthestiffness
8.3Interventionsforjointsofframes
Inadequacyduetodiagonalcompressioninthejoint
Inadequacyofjointreinforcement
8.4Interventionsforshearwalls
Interventionswithacapacityobjectiveagainstflexurewithaxialforce
Interventionswiththeobjectiveofincreasingtheshearcapacity
Interventionswiththeobjectiveofincreasingtheductility
Interventionswiththeobjectiveofincreasingthestiffness
8.5Frameencasement
Additionofsimpleinfill
Convertingframestotoshearwalls
Strengtheningofexistingmasonryinfill
Additionofbracing,conversionofframestoverticaltrusses
8.6Constructionofnewlateralshearwalls
Stirrups
Foundationsfornewshearwalls
Diaphragms
8.7Interventionsforfoundationelements
60
EXPERIMENTAL WORK
(UNIVERSITY OF PATRAS)
61
Damage to a specimen with shotcrete and dowels
62
Damage to a specimen with poured concrete, smooth
interface without dowels
63 63
Addition of a new concrete layer
to the top of a cantilever slab
64
Beam strengthened with a new concrete layer
Interface failure due to inadequate anchorage
of the new bars at the supports
65
BASIC DESIGN CONSIDERATION
Repaired/Strengthened Element
Multi Phased Element
Composite Element
Influence of Interface Connection
66
DESIGN FRAMEWORK
Into the existing framework for new constructions
Supplemented by:
Control of Sufficient Connection Between
Contact Surfaces
Determination of Strength and Deformation
Capacity of the Strengthened Element
- As a Composite Element (Multi-Phased Element)
67
CONTROL OF A SUFFICIENT CONNECTION
BETWEEN CONTACT SURFACES
Sd Rd
interface
Sd
Interface Shear Force
interface
Rd
Interface Shear Resistance
68
INTERFACE SHEAR FORCES: V
Viinterface
FAB FCD
j
(a) strengthening in the tensile zone
int erface
sd
Viinterface
FAB FCD
j
(b) strengthening in the compressive zone
69
Technological
guidelinesfor
repairsand
strengthening:
70
Roughening by sandblasting
71
Use of a scabbler to improve frictional resistance by removing
the exterior weak skin of the concrete to expose the aggregate
72
Concrete jacketing in practice
73
74
Total jacket
75
Inserting intermediate links in sections with a high
aspect ratio
76
Inserting intermediate stirrups in square sections
NO
YES
135 bend to form hooks
77
Bar buckling due to stirrup ends opening
78
Welding of jackets stirrup ends
79
INTERFACE SHEAR RESISTANCE: V
int erface
Rd
Mechanisms
Friction and Adhesion
Dowel Action
Clamping Action
Welded Connectors
80
UNREINFORCED INTERFACES
/fud
4
rough interface with adhesion
sf
s fu
1,14
/ s fu
fud
(N/mm )
f
0 ,5
fud
rough interface without adhesion
sf
s fu
smooth interface with adhesion
f
0 ,5
fud
sf
0,81 0,19
s fu
fu 0.4(f c2 c )1/ 3
0
0
0.1
0.2
0.3
0.4
0.5
0.6
0.5sfu
sfu
sf
s (mm)
(CEB Bul. No. 162, 1983)
Concrete-to-concrete adhesion
(GRECO, 2012)
Roughened interface concrete-to-concrete
friction
81
REINFORCED INTERFACES
Additional Friction
When a Steel Bar Crosses an Interface, a Clamping Action May Occur if:
Surface of Existing Concrete has been Roughened
The Steel Bar is Adequately Anchored
(Tassios and Vintzeleou, 1987)
(1) When Shear Stress is Applied
(2) Slip Occurs
(3) Contact Surface Opens (one surface
rides up over the other due to roughness)
(4) Tensile Strength is Activated in the
Steel Bar
(5) Compression Stress (c) is Mobilized
at the Interface
Clamping Action
(6) Frictional Resistance is Activated
82
Reinforced Interfaces
Frictional resistance
/fud
sf
s fu
f
0 ,5
fud
1,14
/ s fu
fud
sf
s fu
f
0 ,5
fud
sf
0,81 0,19
s fu
fud 0.4(f cd2 (cd d f yd ))1/ 3
0
0.5sfu
sfu
sf
(GRECO, 2012)
83
Reinforced Interfaces
V
Dowel action
84
Shear Resistance
for Dowel Action as a function of the interface slip
3
V 4
V
sd
sd
sd 0 ,1d u 1,80d u
0 ,5
Vud
Vud
Vud
Vsd
5db
3db
0,5Vud
db
6db
s
s
0.1d
0,1d=0.005d
u
0.1s
uu
b d
Vud 1.3 d b2
=0,1d b
sduduu=0,05d
b
fc f y
A minimum concrete cover is
necessary for full activation
of dowel action
85
Use of steel dowels and roughening the surface of an original column
Most popular in practice to achieve a sufficient connection at the interface
86
Reinforced Interfaces
Bent Connecting Steel Bars
87
Bent Bar Model
(Tassios, 2004)
When
hs
occur at the interface one leg of the
bent bar is elongated by
Ts
new bar
old bar
s
the other is shortened
s/ 2
Tensile and Compressive Leg Stresses are mobilized:
sb
s/ 2
s
s
f yb
and sb s
2h s
2h s 2h s
s
Force is Transferred between Reinforcements:
Ts
Ts Asb Es (s / 2h s ) Tsy 2Asb f yb
88
Force Transferred Interface Slippage
1.2
1.0
Tsy 2 Asb f yb
Ts /Tsy
0.8
0.6
hs = 60 mm
0.4
hs = 120 mm
0.2
0.0
0.0
0.1
0.2
0.3
0.4
0.5 0.6
s (mm)
0.7
0.8
0.9
Mechanism is mobilized for very small Slippage
1.0
89
Superposition of shear resistance mechanisms
Vf+c
Vf
Vf+c,u
V fi
Sf,u 2 mm
S [mm]
a) Adhesion and friction
Sf
S [mm]
Stot,u
S [mm]
b) Clamping action
Vtot
Vd
Vtot,u
Vd,u
Sd,u
S [mm]
c) Dowel action
d) Superposition of all actions
Vtot D Vd f V f
90
Full interaction
Partial interaction
Independent action
91
CAPACITY OF MULTI-PHASED ELEMENT
existing
element
new
element
(a)
(b)
(c)
Distribution of Strain With Height of Cross Section
92
Possible strain and stress distributions
93
CAPACITY CURVES
F
Monolithic Element
Action effect
Fy,
Fy,
Strengthened Element
Fres,
Fres,
y, y,
uu
=
Deformation
,
y
Fy,
Fy,
r =
y
=
u, u,
94
MONOLITHIC BEHAVIOUR FACTORS
For the Stiffness:
kk
the stiffness of the strengthened element
the stiffness of the monolithic element
For the Resistance:
kr
the strength of the strengthened element
the strength of the monolithic element
For the Displacement:
k y
the displacement at yield of the strengthened element
the displacement at yield of the monolithic element
k y
the ultimate displacement of the strengthened element
the ultimate displacement of the monolithic element
(EI)strengthened = kk (EI)M
Rstrengthened = kr RM
i,strengthened = ki i,M
95
Addition of a new concrete layer
to the top of a cantilever slab
96
Monolithic Factors
Approximations according to G.C.S.I.
For slabs:
kk = 0,85
kr = 0,95
ky = 1,15
ku = 0,85
ky = 1,25
ku = 0,80
ky = 1,25
ku = 0,75
For concrete jackets:
kk = 0,80
kr = 0,90
For other elements:
kk = 0,80
kr = 0,85
97
Monolithic Factors
Influence of Interface Connecting Conditions in Case of
Concrete Jackets
Monolithic coefficient of resistance
1.00
1.050
0.95
1.025
0.90
1.000
0.85
0.975
Kr
Kk
Monolithic coefficient of stiffness
0.80
0.75
0.950
0.925
first crack
0.70
steel yield
0.900
0.65
failure
0.875
first crack
steel yield
failure
0.850
0.60
0.0
1.0
2.0
3.0
4.0
5.0
Friction coefficient
For =1.4
0.0
1.0
2.0
3.0
4.0
5.0
Friction coefficient
kk = 0.80 and kr = 0.94
kk = 0.70 and kr = 0.80
(EC8, Part 1.4)
kk = 0.80 and kr = 0.90
(G.C.S.I.)
98