"IMPROVING OVERALL EFFICIENCY OF THE CUTTING MACHINES BY IMPLETATION OF PILLARS OF TPM"project Done at Godrej&boyce........
"IMPROVING OVERALL EFFICIENCY OF THE CUTTING MACHINES BY IMPLETATION OF PILLARS OF TPM"project Done at Godrej&boyce........
"IMPROVING OVERALL EFFICIENCY OF THE CUTTING MACHINES BY IMPLETATION OF PILLARS OF TPM"project Done at Godrej&boyce........
UNIVERSITY OF MUMBAI
A PROJECT REPORT ON
SUBMITTED BY
YASHRAJ V. RANE
HARSHAD V. SURYAWANSHI
KALPESH D. KHOCHARE
AMOL P. SHETKE
DHIRAJ B. WAGHMARE
GUIDED BY
PROF L. R. SURYAWANSHI
1
Bharati Vidyapeeth College Of Engineering
`
(INTERNAL GUIDE)
DEPARTMENT OF MECHANICAL ENGINEERING
2009-2010
A PROJECT REPORT ON
1
Bharati Vidyapeeth College Of Engineering
`
HARSHAD V. SURYAWANSHI
KALPESH D. KHOCHARE
AMOL P. SHETKE
DHIRAJ B. WAGHMARE
GUIDED BY
PROF L. R. SURYAWANSHI
(INTERNAL GUIDE)
APRIL-2010
CERTIFICATE
DATE :
2
Bharati Vidyapeeth College Of Engineering
`
YASHRAJ.V.RANE (4760)
HARSHAD.V.SURYAWANSHI (4761)
AMOL.P.SHETKE (4762)
DHIRAJ.B.WAGHMARE (4766)
1
Bharati Vidyapeeth College Of Engineering
`
A PROJECT REPORT ON
Is
Submitted By
KALPESH.D.KHOCHARE (4759)
YASHRAJ.V.RANE (4760)
HARSHAD.V.SURYAWANSHI (4761)
AMOL.P.SHETKE (4762)
DHIRAJ.B.WAGHMARE (4766)
1
Bharati Vidyapeeth College Of Engineering
`
Signature Signature
Name : Name:
(External examiner) (Internal
examiner)
2
Bharati Vidyapeeth College Of Engineering
`
1
Bharati Vidyapeeth College Of Engineering
`
ACKNOWLEDGEMENT
At the very onset of this project, we would like to take this opportunity to express our
heartfelt gratitude to the people whose unstinting help and co-operation has made this study a
success.
We would like to express our appreciation to Mr. Neel Shrivastava (Department Head)
& Mr. F. R. Bava-Adam (Divisional Personnel) for granting us permission to complete our
project in their prestigious organization
We are thankful to Prof. Mr. L. K. Suryawanshi, our project guide who co-operated
every now and then and took every effort to make this project a grand success. Humble thanks
to our teachers and project co-coordinator Prof. Mr. R.K. Agrawal for their keen guidance.
Finally we thank all people, our colleagues who offered their valuable time, guidance,
suggestions and assistance directly to us to carry out this educative report
1
Bharati Vidyapeeth College Of Engineering
`
Abstract
2
Bharati Vidyapeeth College Of Engineering
`
Table Of Contents
1
Bharati Vidyapeeth College Of Engineering
`
11 BIBLIOGRAPHY 56-56
FIGURES
1
Bharati Vidyapeeth College Of Engineering
`
2
Bharati Vidyapeeth College Of Engineering
`
TABLES
TABLE NO. TABLE NAME PAGE NO.
3
Bharati Vidyapeeth College Of Engineering
`
2
Bharati Vidyapeeth College Of Engineering
`
CHAPTER -1
3
Bharati Vidyapeeth College Of Engineering
`
INTRODUCTION TO COMPANY
2
Bharati Vidyapeeth College Of Engineering
`
In the year 1997, Godrej & Boyce celebrated their centenary year. This
dynamic organization has progressed tremendously since its inception and has been gaining
strength consistently. Quality is the hallmark of all the Godrej products and any product with
the 'Godrej' mark represent quality, dependability & satisfaction to its customers. What now
is a gainful industrial organization was a brainchild of Mr. Ardeshir GODREJ, which through
the help dedicated men with tremendous foresight and finely honed engineering and
marketing skills, has become one of the biggest houses in India.
The most recent achievement by Godrej was made when it acquired the ISO 9000,
ISO 9001 and ISO 14000 certificate, which former reinforced the rest of not only the Indian
market but also the global market in the product of Godrej Today Godrej employee over
15,000 people and has grown in to a multi-core professionally managed group with far
reaching service and distribution network. "Economy and Services” are being the main motto
of Godrej they have already diversified in to field of Indian industry thus helping in the
economic growth of the country.
Century old brand name, 'Godrej', it now also provides electronic security systems
products and is angered with the supply and installation of the electronics safes, electronics
3
Bharati Vidyapeeth College Of Engineering
`
security alarm systems, access control systems, closed circuit television systems and very
highly sophisticated advanced electronic surveillance systems.
2
Bharati Vidyapeeth College Of Engineering
`
This division is located in Plant 15 and it designs and fabricates a large range of
custom-made sophisticated equipment for chemicals, petrochemicals and fertiliser industries
1
Bharati Vidyapeeth College Of Engineering
`
such as heat exchangers, boiler shells, tower internals, etc., as well as equipment for nuclear
and aerospace applications such as parts of atomic reactor, cryogenic engines and projects of
ISRO (Indian Space Research Organisation).
♦ Heat exchanger.
♦ Aerospace Division.
2
Bharati Vidyapeeth College Of Engineering
`
Product range –
• Heavy Walled Reactors
• Equipment Internals
• Fractionating / Distillation Columns
• High Pressure Shell & Tube Heat Exchangers Custom built
Equipment
2
Bharati Vidyapeeth College Of Engineering
`
2
Bharati Vidyapeeth College Of Engineering
`
Machine shop department is one of the vital departments in the ‘Process Equipment
Division’. It possesses machines that are required for machining the various components
of the pressure vessel assembly. The department produces components that are related to
the heat exchanger of the pressure vessel assembly. The machine shop department is a
service department and works in tandem with other departments of the plant.The
components produced in machine shop department can be given as follows: -
♦ Tube sheets
♦ Baffles
♦ Tie rods
♦ Spacers
♦ Flanges
The various machines used in the machine shop department can be given as
follows:
♦ ARBOGA 1
♦ ARBOGA 2
3
Bharati Vidyapeeth College Of Engineering
`
♦ HARTFORD 1
♦ HARTFORD 2
♦ BATLIBOI
♦ KOLB
♦ MODULAR LATHE
4
Bharati Vidyapeeth College Of Engineering
`
♦ BECO LATHE
♦ NEW LATHE
♦ VTL6 (FARREL)
5
Bharati Vidyapeeth College Of Engineering
`
table. The spindle head can be swivelled at an angle. This machine is adapted for
machining grooves, slots and flat surfaces.
6
Bharati Vidyapeeth College Of Engineering
`
CHAPTER-2
7
Bharati Vidyapeeth College Of Engineering
`
INTRODUCTION TO PROJECT
8
Bharati Vidyapeeth College Of Engineering
`
Fig 6:
Fig 7
9
Bharati Vidyapeeth College Of Engineering
`
10
Bharati Vidyapeeth College Of Engineering
`
data entry and program storage. The speed is easily set, controlled and monitored before
and during the cutting process.
Behringer Saws, Inc. provides a full range of sawing and turnkey pre- and post-cut
material handling productivity-enhancing products. Behringer supplies world-class
quality automatic bandsaws to corporations, service centers, job shops and manufacturers
throughout the world. The company also offers the Behringer Eisele brand of manual,
semi-automatic and automatic miter circular cold saws, high performance circular cold
saws utilizing bi-metal or carbide saw blades and CNC miter circular sawing systems.
Also, the Vernet Behringer line of structural fabricating equipment includes high
performance drilling, punching, shearing, notching and marking machines along with
beam coping and drilling and sawing lines.
For more information on the HBP-800AXL and HBP-800XL Bandsaws, contact
Behringer Saws, Inc., 721 Hemlock Road, Morgantown, PA 19543. Call toll-free at 888-
234-7464.
Description of machine: -
Stainless steel and tool steel. Tempered steel, special alloys and aluminum. In
different thicknesses, shapes and diameters. Singly, in bundles of fixed lengths. Whatever
you aim to saw, our HBP, HBV and HBM high-performance and automatic bandsaw
series offer the solution you are looking for. In every cutting range. Despite their
outstanding performance, our machines are all designed to offer maximum operating
simplicity and space savings. And like everything from BEHRINGER, they are
unbeatable in terms of speed, precision and quality.
11
Bharati Vidyapeeth College Of Engineering
`
12
Bharati Vidyapeeth College Of Engineering
`
The vise used to hold the material being cut is a quick-positioning type and can be
adjusted easily to any angle. An adjustable work piece stop is provided for rapid
positioning of production work pieces.
13
Bharati Vidyapeeth College Of Engineering
`
Table No: 01
14
Bharati Vidyapeeth College Of Engineering
`
Fig 9
The RUM is the latest generation of CNC profile cutting machine that combines
the quality of construction of the MAXI machine with the advantages of the price/output
ratio of RUR machine. Standard equipment of the RUM includes all available automation
facilities.
Basic equipment
fully welded beam without bolted joints
linear bearing in cross axis
AC servomotors
digital synchronization in longitudinal axis
BURNY 10 LCD Plus control system with touch screen
membrane keyboard
floating cutting heads
electric ignition
capacitive height control of oxy-fuel torch
automatic gas console
torch selection from control panel
15
Bharati Vidyapeeth College Of Engineering
`
CUTTING TORCH:
A cutting torch head is used to cut metal. It is similar to a welding torch, but can be
identified by having three pipes that go to a 90 degree nozzle and by the oxygen-blast
trigger.
Only iron and steel can be cut using this method. The metal is first heated by the
flame until it is cherry red. Once this temperature is attained, oxygen is supplied to the
heated parts by pressing the "oxygen-blast trigger". This oxygen reacts with the metal,
forming iron oxide and producing heat. It is this heat which continues the cutting process.
The cutting torch only heats the metal to start the process; further heat is provided by the
burning metal.
16
Bharati Vidyapeeth College Of Engineering
`
17
Bharati Vidyapeeth College Of Engineering
`
18
Bharati Vidyapeeth College Of Engineering
`
Table No: 02
Key features:
Burny 1250 control system includes a fully-integrated Burny 2.5 CNC Shape
Cutting Control, Plasma process controls and a servopak 120 watt pulse with
modulated drive
CNC Width 2000mm
Track length to be advised
Maximum Cutting Speed 6000mm/min
Maximum Cutting Thickness with gas 300mm
Single sided drive
Combined gas and plasma post with ESAB Cool jet Cutting Post
Operational Manuals
Mains input would require 240 volts single phase
Photographs taken on site PRIOR to any work commencing.
19
Bharati Vidyapeeth College Of Engineering
`
20
Bharati Vidyapeeth College Of Engineering
`
CHAPTER-3
21
Bharati Vidyapeeth College Of Engineering
`
LITERATURE REVIEW
Literature Review:
AN INTRODUCTION TO TOTAL PRODUCTIVE MAINTENANCE
(TPM):
In today’s industrial scenario huge losses/wastage occur in the manufacturing shop
floor. This waste is due to operators, maintenance personal, process, tooling problems
and non-availability of components in time etc.
Other forms of waste includes idle machines, idle manpower, break down
machine, rejected parts etc are all examples of waste.
The quality related waste are of significant importance as they matter the company
in terms of time, material and the hard earned reputation of the company. There are also
other invisible wastes like operating the machines below the rated speed, start up loss,
break down of the machines and bottle necks in process.
Zero oriented concepts such as zero tolerance for waste, defects, break down and
zero accidents are becoming a pre-requisite in the manufacturing and assembly industry.
In this situation, a revolutionary concept of TPM has been adopted in many industries
across the world to address the above said problems. chapter deals in length about this
TPM.
22
Bharati Vidyapeeth College Of Engineering
`
Pillars of TPM
Fig 11
23
Bharati Vidyapeeth College Of Engineering
`
1. METHODS:
Time to process Raw-material.
Lack of proper understanding.
1. PEOPLE:
Lack of availability of designers.
Conflicting mindsets of designers.
Inadequate skill-mapping.
Lack of motivation & understanding.
1. MANPOWER:
Dedicated personnel for planning.
Lesser no. of designers involved.
Dynamics of self-help groups.
1. POLICIES:
Government oriented(Time-consuming) paper work.
Lack of finance to create larger SHG’s.
Investment.
1. PLACE:
Time & cost incurred.
24
Bharati Vidyapeeth College Of Engineering
`
25
Bharati Vidyapeeth College Of Engineering
`
26
Bharati Vidyapeeth College Of Engineering
`
CHAPTER-4
27
Bharati Vidyapeeth College Of Engineering
`
28
Bharati Vidyapeeth College Of Engineering
`
METHODOLOGY
1. Recognition of problems:
Every development process starts with recognition or identification of need.
Recognition of need is to outcome of either the requirement of the discontent of the
existing system.
2. Definition of problem:
The difference the statements of need the identification of the problem lies in the fact
of the problem is more specific. Definition of problem must include all inputs ,
parameters, functional requirement and constraints of the system.
29
Bharati Vidyapeeth College Of Engineering
`
After detail study of TPM tools, we have obtained number of alternatives and by
evaluation we shortlisted the number alternatives and decided whether all alternatives
should be accepted or not. By pillars of TPM, we selected process, manpower and
machinery as an area of development.
Synthesis is a process of selecting the mechanism so as to get desired output by given
input.
It involves number of iterations. By synthesis we decided to synchronize the first three
operations.
4. Investigation:
Once the number of alternatives are shortlisted in the evaluation step it becomes
necessary to convert these alternatives in to practical needs. Investigation does this. It
usually involves preparation of making prototype, considering trial run etc.
Initially we are trying to synchronize cutting operations.
The following operations we are going to perform to increase production and efficiency
of machines.
Elimination of all unnecessary operations.
Sensors of measurement of jobs.
Designing the process wherever required.
1. Final Design:
On successful synchronization of all processes, we will make final design and decide
parameters for smooth functioning of developed process with increased productivity.
The design will be based on following parameters.
30
Bharati Vidyapeeth College Of Engineering
`
Investment needed.
Rate of production.
Production cost per unit.
Return of investment.
31
Bharati Vidyapeeth College Of Engineering
`
32
Bharati Vidyapeeth College Of Engineering
`
CHAPTER-5
33
Bharati Vidyapeeth College Of Engineering
`
ANALYSIS
Today, with competition in industry at an all time high, TPM may be the only
thing that stands between success and total failure for some companies. It has been
proven to be a program that works. It can be adapted to work not only in industrial plants,
but also in construction, building maintenance, transportation, and in a variety of other
situations. Employees must be educated and convinced that TPM is not just another
"Program of the month" and that management is totally committed to the program and the
extended time frame necessary for full implementation. If everyone involved in a TPM
program does his or her part, an unusually high rate of return compared to resources
invested may be expected.
As shown below we have shown the information with the help of Time Study
charts with proper description of whatever the losses affecting the production. On the
basis of Time Study charts we have drawn the pie-charts.
We have developed an OEE chart (Overall Equipment Efficiency) and collected
all the Time Study data and implemented it on OEE chart. From these OEE charts we
have listed following major losses:
34
Bharati Vidyapeeth College Of Engineering
`
Setting of JOB
Measurement
Scheduled/Planned Stoppages
Non Availability of Material
Non Availability of EOT Crane
35
Bharati Vidyapeeth College Of Engineering
`
Table No: 03
36
Bharati Vidyapeeth College Of Engineering
`
37
Bharati Vidyapeeth College Of Engineering
`
38
Bharati Vidyapeeth College Of Engineering
`
2. Measurement 83 14.28
3. Operator non availability 35 4.30
4. Crane waiting time 15 2.58
Table No: 04
39
Bharati Vidyapeeth College Of Engineering
`
40
Bharati Vidyapeeth College Of Engineering
`
41
Bharati Vidyapeeth College Of Engineering
`
Table
No: 05
42
Bharati Vidyapeeth College Of Engineering
`
Fig 17: OEE Chart for CNC GAS CUTTING MACHINE - SUAG
43
Bharati Vidyapeeth College Of Engineering
`
Fig 18: Bar Chart for CNC GAS CUTTING MACHINE - SUAG
Table No: 06
Fig 19: Pie Chart for CNC GAS CUTTING MACHINE - SUAG
44
Bharati Vidyapeeth College Of Engineering
`
CHAPTER -6
45
Bharati Vidyapeeth College Of Engineering
`
SUGGESTION
REASON
Break-down maintenance
SOLUTION
2. Setting time
REASON
46
Bharati Vidyapeeth College Of Engineering
`
SOLUTION
3. Measurement
REASON
Sensors assembly has to be done near to the machine blade so measurement time will
be minimum.
1. Scheduled/Planned Stoppages.
2. Non Availability of Material.
3. Start up Loss[mock-up].
1. Scheduled/Planned Stoppages
REASON
47
Bharati Vidyapeeth College Of Engineering
`
SOLUTIONS
REASON
SOLUTIONS
2. Start up Loss[mock-up]
REASON
SOLUTIONS
48
Bharati Vidyapeeth College Of Engineering
`
1. Special Cleaning staff to be provided for cleaning of the m/c before operator reports
on the m/c during each shift.
2. Special Fixture to be made to avoid Test Run.
49
Bharati Vidyapeeth College Of Engineering
`
CHAPTER -7
50
Bharati Vidyapeeth College Of Engineering
`
DESIGN
Introduction
A rack is a device for locating, holding and supporting a workpiece
or plates during a manufacturing operation. Rack are essential part of
production processes as they are required for material handling of a
particular materials.
There are many standard material handling devices such as belt
conveyor,trolley etc. which are widely used in workshops and industries
and are usually kept in stock for general applications.
Rack are normally designed for a definite operation to process a specific
workpiece and are designed and manufactured individually.
51
Bharati Vidyapeeth College Of Engineering
`
52
Bharati Vidyapeeth College Of Engineering
`
53
Bharati Vidyapeeth College Of Engineering
`
54
Bharati Vidyapeeth College Of Engineering
`
55
Bharati Vidyapeeth College Of Engineering
`
sides. The length of each of the two equal sides id called leg. As a rule, the leg length h is
equal to the plate thickness.
56
Bharati Vidyapeeth College Of Engineering
`
or
P = 1.414 hlτ
CHAPTER -8
57
Bharati Vidyapeeth College Of Engineering
`
SCOPE
ADVANTAGES:
2. High accuracy.
3. Smooth operation.
DISADVANTAGES:
58
Bharati Vidyapeeth College Of Engineering
`
CHAPTER -9
59
Bharati Vidyapeeth College Of Engineering
`
BEFORE
Table No: 07
60
Bharati Vidyapeeth College Of Engineering
`
Fig No: 23
AFTER
DATE OF PERFORMANCE MEASUREMENT TIME
22/04/2010 15
23/04/2010 24
Table No: 08
Fig No: 24
61
Bharati Vidyapeeth College Of Engineering
`
Table No: 09
62
Bharati Vidyapeeth College Of Engineering
`
Table No: 10
BEFORE
DATE OF PERFORMANCE AVAILABILITY OF MATERIAL
11/9/2009 30
25/09/2009 20
Table No: 11
Fig No: 25
AFTER
DATE OF PERFORMANCE AVAILABILITY OF MATERIAL
22/04/2010 12
63
Bharati Vidyapeeth College Of Engineering
`
23/04/2010 15
Table No: 12
Fig No: 26
Improved OEE of CNC GAS CUTTING M/C-SUAG
64
Bharati Vidyapeeth College Of Engineering
`
65
Bharati Vidyapeeth College Of Engineering
`
Table No: 13
Table No: 14
CONCLUSION
66
Bharati Vidyapeeth College Of Engineering
`
involved in the machine’s life cycle. Improved behavior comes from new learning.
Continuous improvement is born of continuous learning.” Research and case studies indicate
that TPM implementation can have significant positive impact on manufacturing
performance.
After the implementation of TPM, it can be seen that from above Results that O.E.E.
of the machines improved by 3% to 7%.
BIBLIOGRAPHY:
67
Bharati Vidyapeeth College Of Engineering
`
COMPANY GUIDE:
Trivesh pooniwala.(Dy.Manager-
maintenance)P.E.D.pooni@godrej .com,
www.godrej.com
REFERENCES:
WEBSITE:
1. www.wekipedia.com
2. www.google.com
3. www.scribd.com
4. www.3brooks.com/tmp/2110.pdf
68
Bharati Vidyapeeth College Of Engineering
`
69