Evaluation of Common Delay Causes of Construction Projects in Singapore
Evaluation of Common Delay Causes of Construction Projects in Singapore
Evaluation of Common Delay Causes of Construction Projects in Singapore
1027-1034
Journal of Civil Engineering and Architecture, ISSN 1934-7359, USA
DAVID
PUBLISHING
1. Introduction
The characteristic of construction industry is
uncertainties, unpredictability and susceptible to
understandings leading to delays. Delays in
construction can affect the overall project participants
adversely. It is the common interest of all parties to
avoid the delay as much as possible at the first place
and to minimize then even if the delays arise. Davision
and Mullen [1] gave the concept of delay as the
extension of time beyond planned completion dates
traceable to the contractors. While, Aibinu and Jagboro
[2] defined the concept of delay as situation when the
contractor and the project owner jointly or severally
contribute to the non-completion of the project within
the original or the stipulated or agreed contractor
period. The duration of project is normally specified by
the owner and contractors have responsible to ensure
the completion of the project within the owners time
frame. Construction researcher and practitioners have
recently begun to emphasize the need for developing
2. Literature Review
Delay is generally acknowledged as the most
common, costly, complex and risky problem
encountered in construction project. Construction
1028
3. Methodology
The data collection process involved two stages. The
first stage consisted of literature reviews for
information on the causes of delay in other countries
and non-structured interviews of 15 key players
involved in the implementation process. The purpose
of interviewing the key players was essentially to
validate a preliminary set of construction delay causes
gleaned from the literature and to determine from their
experience other factors which cause construction
a x
i
i 0
4 x i
i 0
100%
(1)
1029
where
ai = constant expressing weight given to ith response:
i = 0, 1, 2, 3, 4
xi = variable expressing frequency of ith response
i = response category index of 0, 1, 2, 3, 4 illustrated
as follows:
x0 = frequency of very often response and
corresponds to a1 = 4;
x1= frequency of often response and corresponds to
a2 = 3;
x2 = frequency of moderate response and
corresponds to a3 = 2;
x3 = frequency of not often response and
corresponds to a2 = 1;
x4 = frequency of seldom response and corresponds
to a1= 0;
The respondent to the survey has to select one
weight (level of significance) for each factor causing a
delay. There are 5 level of weight, ranging from 0
(seldom to cause delay response) to 4 (very often to
cause delay response). The summations of all of the
respondents answers are averaged using the Eq. (1).
Eq. (1) was used to calculate the severity index for all
disputes factors. The index was ranked for domestic
and international funded public works projects. The
severity index was categorized into five levels. The
0-15.5% was categorized as non severe; 15.5-38.5% is
categorized as somewhat non-severe; 38.5-63.5% is
categorized as moderately severe; 63.5-88.5% is
categorized as severe; and 88.5-100% is categorized as
most severe. The categorizations reflect the scale of the
respondents answers to the questionnaire. The severity
index of a category was the average severity indexes of
all its related problems. As an example I, the average
weighted perceived significance was computed as
follows:
1 a x a x a x a x
I { 1 1 2 2 3 3 4 4 }100%
4
a1 a2 a3 a4
(2)
All the collected information from the survey were
examined and verified for their correctness. Data
1030
rs 1
6 d12
N ( N 2 1)
(3)
where
rs = Spearmans rank correlation coefficient between
two parties.
d = The difference in ranking between ranks
assigned to variables for each cause (owner and
consultants,
owner-contractors,
consultantscontractors), and
N = The number of pairs of rank, equals to 35 and 4
for all the delay factor and for the main categories of
delays, respectively.
The classification of construction delays were
caused by several factors. Based on literature reviews
Organization
Percentage
of responses
83
88
95
67
83
Number of projects
40
42
82
1031
Owner
Rank
1
5
10
31
24
11
12
20
13
9
2
1
27
2
33
32
6
4
23
4
3
7
8
19
35
34
22
36
3
14
29
17
15
16
26
21
30
28
25
I (%)
52.5
65.9
54.1
26.4
44.6
52.0
55.1
58.1
56.8
59.5
54.5
76.4
29.1
70.3
31.4
25.0
60.5
73.3
69.9
34.5
43.2
42.2
56.4
44.9
16.9
13.9
34.8
24.0
50.8
57.1
47.0
47.3
46.3
46.6
52.7
51.0
53.4
48.6
58.4
Consultant
Rank
2
5
14
31
25
17
13
9
11
7
1
1
30
3
29
32
6
2
4
4
26
27
12
24
34
35
28
33
3
10
21
22
23
20
16
17
15
19
8
Main contractor
I (%)
Rank
56.3
2
68.2
5
63.9
9
29.7
33
52.4
21
59.1
14
58.4
15
55.4
20
58.1
16
61.5
11
57.1
1
72.0
3
43.6
29
77.7
2
33.4
32
33.8
31
62.8
10
66.9
6
66.2
7
47.7
4
78.4
1
71.3
4
60.1
12
57.4
17
20.6
34
16.6
35
65.9
8
11.5
36
49.6
3
59.5
13
49.3
25
51.7
23
56.4
19
52.0
22
48.0
27
48.6
26
34.8
30
50.0
24
45.6
28
1032
Spearman
coefficient
Main
categories
Owners-Main
0.8
contractors
Main
0
contractors-Consultants
Owners-Consultants
0.8
rank
correlation
delay All
factors
delay
0.61
0.89
0.65
Index
86.5
78.4
77.7
73.3
71.3
86.5
77.7
73.3
72.3
68.2
76.4
73.3
70.3
69.9
65.9
78.4
77.7
72
71.3
68.9
1033
5. Conclusions
The conclusion can be drawn from studied and the
results of the analysis of the survey delay problems in
building projects in Singapore as follows.
This study has identified and classified 35 related
factors of common delay in building projects in
Singapore. These common delay factors among owners
consultants and main contractors. The main delay
category can be classified into 4 main categories:
contract and specification, financial, environment and
other common.
All main delay categories and their related delay
factors were found to have frequency of very often
response on the relationship among construction
practitioners, Nonetheless, the degree of severity do
vary.
Financial
delay
category
was
evaluated
as
1034
Acknowledgment
Author would like to thank the Ministry of
Education, Culture, Sports, Science and Technology
(Japan) for providing partially financial support
through Grant-in-Aid for Scientific Research
(Research Project No.18206048).
Reference
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]