Topic 1 Introduction To Project Scheduling
Topic 1 Introduction To Project Scheduling
Scheduling
Topic 1 (Introduction to Project
Scheduling)
Instructor: Dr. Abid Nadeem
Qatar University
Civil Engineering Department
Fall 2012
Lecture Handouts Acknowledgement: Dr. Saleh Mubarak
Fall 2012
Slide No. 2
Types of Management
Types of Management
General management
Program management
Portfolio management
Project management
Specialty management
Slide No. 3
Introduction to Project
Management
Important definitions from the Project
Management Institute, PMI, PMBOK, 4th
edition, 2008:
Project: A temporary endeavor undertaken to
create a unique product, service, or result
Slide No. 4
Introduction to Project
Management (Contd)
Program: A group of related projects managed in
coordinated way to obtain benefits and control not
available from managing them individually. Programs
may include elements of related work outside of the
scope of the discrete projects in the program
Programs may be:
Temporary/one-time programs
Slide No. 5
Introduction to Project
Management (Contd)
Portfolio is a collection of projects or programs
and other work that are grouped together to
facilitate effective management of that work to
meet strategic business objectives. The
projects or programs of the portfolio may not
necessarily be dependent or directly related
Programme in the UK terminology
Fall 2012
Slide No. 6
The Hierarchy
Portfolio
Program
Project
Project
Subproject
Fall 2012
Program
Project
Subproject
Project
Tasks
Subproject
Slide No. 7
Project Management
Project Management
is the application of
knowledge, skills,
tools, and techniques
to project activities
to meet the project
requirements
Fall 2012
Cost /
Budget
Time /
Schedule
Scope /
Quality
Slide No. 8
Document Management
Project administration,
Risk Management
Quality management,
Procurement management,
Safety management,
Other
Project controls
Fall 2012
Slide No. 9
Slide No. 10
Project Planning
Project planning serves as a foundation for several
related functions such as cost estimating, scheduling,
and other functions related to executing the project.
The plan can include elements that has to do with
scope, design and alternate designs, cost, time,
finance, land, procurement, operations, etc.
The plan can take different shapes and have different
contents depending on:
Fall 2012
Slide No. 11
What?
Why
How?
Where?
Who?
By whom?
How much?
Slide No. 12
Schedule
when
The Plan
Fall 2012
Slide No. 13
Project Control
Project scheduling, like cost estimating, is a prediction
of future occurrence; time or money
Once project execution starts, actual performance may
not, and usually do not, follow the prediction (called
the baseline when it become an official part of the
contract)
Here comes Project Control to track both schedule and
cost, find variances (where, how much, and why), and
take corrective action to bring the project back to the
plan
Fall 2012
Project Scheduling Dr. Mubarak
Slide No. 14
2.
3.
4.
5.
6.
Fall 2012
Slide No. 15
Fall 2012
Slide No. 16
The Scheduler.....
Is the scheduler:
an engineer / architect?
a computer whiz?
a mathematician?
an artist? or
a communicator?
Slide No. 17
The Scheduler
The three types of knowledge:
1.
2.
3.
Fall 2012
Slide No. 18
The Human
Factor
Fall 2012
The
Technology
The
Management
Slide No. 19
Question
Do all projects (of all types and sizes) have a
need for CPM scheduling?
Does the need vary?
Fall 2012
Slide No. 20
Quiz Exercise 1
Are the following statements true or false:
1. There are no two projects in construction that are identical
2. Every construction project needs a CPM schedule
3. Planning and scheduling are two names for the same function
4. Projects in a portfolio are necessarily related
5. Projects in a program are necessarily related
6. All programs have specific limited lifespan
7. The maintenance of a large office building is considered a project
8. The renovation of a large office building is considered a project
9. The maintenance of city bridges can be a program
Fall 2012
Slide No. 21
Slide No. 22
Fall 2012
Slide No. 23
Fall 2012
Slide No. 24
Factors to Be Considered in
Defining Activities
1.
2.
3.
Size / Duration
4.
Timing / Chronology
5.
6.
Responsibility
7.
Phase
8.
Contractual restrictions
Fall 2012
Slide No. 25
Definition
Activity: A basic unit of work as part of the
total project that is easily measured and
controlled
Fall 2012
Slide No. 26
Duration = 0
Fall 2012
Slide No. 27
100000
Tampa
Office
Bldg
Level 0
Site Work
Mechanical
/ Electrical
Interior
finishes
Beams/
Girders
One-way
Slab and
beam
Waffle
Slabs
123140
Concrete
123130
Post-tension
cable
Flat Slabs
123400
123113
123114
Work Breakdown
Structure, WBS,
Example
Reshores
Fall 2012
123112
160000
125000
123300
Shores
Level 5
Soffit and
edges
123111
Rebar
123120
Scaffold
(tables)
Level 4
123110
Falsework
Level 3
123200
Posttensioned
Slabs
123100
124000
123000
Elevated
Slabs
122000
Shear
Walls
Level 2
Columns
121000
150000
140000
Exterior
closure
Building
shell
Foundation/
Substructure
Level 1
130000
CIP Stairs
120000
110000
Slide No. 28
Level
03 00 00 Concrete
03 10 00 Concrete Forming and Accessories
03 11 00 Concrete Forming
03 11 13 Structural Cast-in-Place Concrete Forming
03 11 13.13 Concrete Slip Forming
03 11 13.16 Concrete Shoring
03 11 13.19 Falsework
1
2
3
4
5
5
5
4
5
4
4
Slide No. 29
Fall 2012
Slide No. 30
Activitys Durations
second opinion
Fall 2012
Slide No. 31
External relationships
Imposed constraints
Fall 2012
Slide No. 32
Non-work days
Fall 2012
Slide No. 33
Additional Step 1:
Review and Analyze
1. Review and analyze the schedule:
Fall 2012
Slide No. 34
Additional Step 2:
The Implementation
2. Implementation of the schedule: Taking the
schedule from paper to action
Management commitment
Fall 2012
Slide No. 35
Additional Step 2:
The Implementation
Fall 2012
Slide No. 36
Additional Step 3:
Monitor and Control
3. Monitor and Control:
Reporting / Documentation
Fall 2012
Slide No. 37
Additional Step 4:
Database Feedback
4. Database Revisions and Feedback
Archiving
Fall 2012
Slide No. 38
Cost loading
Resource leveling
Fall 2012
Slide No. 39
Stored in the
Resource
Dictionary
Activity
Install8CMUfor4thfloorexteriorwall
Duration
5
days
Workhours
8
perday
Resource
Foreman
Mason
Helper
Crane(1hour/day)
CMU(includingmortar,
grout,andrebar
How
Cost/unit
many?
1
$40.00
3
$32.00
2
$27.50
0.125
$800.00
2300
$4.00
Hour
Hour
Hour
Day
Extended
Cost
$1,600.00
$3,840.00
$2,200.00
$500.00
Each
$9,200.00
Unit
ActivityTotal
Fall 2012
Cost loading:
Cost = $17,340
$17,340.00
Slide No. 40
2.
3.
4.
5.
Slide No. 41
Design
Design review
Construction
Myths/Misconceptions
About Scheduling
I should get a very accurate schedule I bought the
most expensive software in the market!
I hired a computer specialist to handle Primavera!
CPM schedules are bunch of nonsense. We do it just
because the owner required it.
We dont need an expensive system
it is all up here
Fall 2012
Slide No. 43
Quiz Exercise 2
Are the following statements True or False:
1. There is one standard way to break down the project into
activities for the purpose of creating a schedule
Fall 2012
Slide No. 44