Rig Sizing - Text
Rig Sizing - Text
Rig Sizing - Text
1.
Fundamentals .................................................................................................................................... 2
1.1. Types of Rigs ............................................................................................................................ 2
2. Hoisting System................................................................................................................................ 3
2.1. Hoisting Design Considerations ............................................................................................... 5
2.2. Power Requirements of the Drawworks................................................................................... 7
3. Drilling Line Design Considerations .............................................................................................. 12
3.1. Ton-Miles (Mega joules) Of A Drilling Line ......................................................................... 12
3.2. Evaluation Of Total Service And Cut-Off Practice................................................................ 15
4. ROTATING EQUIPMENT............................................................................................................ 16
5. Circulating System.......................................................................................................................... 17
5.1. Volumetric Efficiency ............................................................................................................ 18
5.2. HORSEPOWER ..................................................................................................................... 18
5.3. Pump Output ........................................................................................................................... 19
5.4. Pump Factors .......................................................................................................................... 19
5.5. Centrifugal Pumps .................................................................................................................. 20
5.6. Mud Handling Equipment ...................................................................................................... 20
6. Pressure Cont rol Equipment ........................................................................................................... 21
7. Derrick Capacity and Substructure ................................................................................................. 23
8. Total Power Requirements ............................................................................................................. 27
__________________________________________________________________________________
1
Network of Excellence in Training
Rig Sizing
1.
FUNDAMENTALS
A drilling rig is a device used to drill, case and cement water, oil and gas wells.
The correct procedure for selecting and sizing a drilling rig is as follows:
1. Design the well
2. Establish the various loads to be expected during drilling and testing and use the highest. This
point establishes the DEPTH RATING OF THE RIG.
3. Compare the rating of existing rigs with the design load
4. Select the appropriate rig and its components.
1.1.
Types of Rigs
The major components that need to be selected and sized for the purpose of rig sizing are:
1. Hoisting
2. Rotating Equipment
3. Circulating System
4. Tubular Goods
__________________________________________________________________________________
2
Network of Excellence in Training
5. Pressure Control
6. Derrick Capacity And Substructure
7. Power Requirements
2.
W/4
W/4
W/4
W/4
W/4
W/4
Fastline
Deadline
Travelling Block
Hook
Drawworks
Drilling
Lines
Deadline
Anchor
__________________________________________________________________________________
3
Network of Excellence in Training
Hence during hoisting operations, if there are 10 lines between the crown and travelling block, the
fastline line travels 10 times faster than the travelling block in order to spool or unspool drilling line
from the hoisting drum.
The DEAD LINE ANCHOR anchors the last line coming from the crown block and also stores
drilling line on a reel. This allows new lengths of line to be fed into the system to replace the worn
parts of the line that have been moving on the pulleys of the crown block or the travelling block. The
worn parts are regularly cut and removed, Slip and Cut Practice. Slipping the line, then cutting it off
helps to increase the lifetime of the drilling line.
Travelling Block: a diamond-shaped block containing a number of sheaves which is always less
than those in the crown block. The drilling line is wound continuously on the crown and Travelling
blocks, with the two outside ends being wound on the hoisting drum and attached to the deadline
anchor respectively, figure 3.
The Hook: connects the Kelly or topdrive with the travelling block. The hook carries the entire
drilling load, figure 3.
Drilling Line
The drilling is basically a wire rope made up of strands wound around a steel core. Each strand
contains a number of small wires wound around a central core.
The drilling line is of the round strand type with Langs lay. The drilling line has a 6x19 construction
with Independent Wire Rope Core (IWRC). This construction implies that there are 6 strands and each
strand containing 19 filler wires.
The size of the drilling line varies from to 2 .
__________________________________________________________________________________
4
Network of Excellence in Training
2.1.
The procedure for carrying out hoisting design calculations are as follows:
1. Determine the deepest hole to be drilled
2. Determine the worst drilling loads or casing loads
3. Use these values the select the drilling line, the derrick capacity and in turn the derrick
1.
Static derrick loading (SDL)= fast-line load + hook load + dead-line load
Referring to figure 1 and for a system consisting of four lines supporting the hook load, then under static
conditions:
Fast- line load (FL) = Hook load /4
Dead-line load (DL) = Hook load /4
Hl
HL 3
+ HL +
= HL
4
4
2
Equation 1
__________________________________________________________________________________
5
Network of Excellence in Training
SDL =
( N + 2)
HL
N
Equation 2
where
N = number of lines strung to travelling block
HL = hook load
2.
a.
EF =
K (1 K n )
N (1 K )
FL =
HL
NxEF
Equation 3
Equation 4
where
K = sheave and line efficiency per sheave
Deadline- load is given by:
HL x KN
DL =
N x EF
Equation 5
If the breaking strength of the drilling line is known, then a design factor, DF, may be
calculated as follows:
nominal strength of wire rope (lb)
DF =
fast-line load (lb)
B.
Equation 6
Lowering Operations
During lowering of pipe, the efficiency factor and fast- line load are given by
__________________________________________________________________________________
6
Network of Excellence in Training
N x KN x (1 - K)
(EF) LOWERING =
(1-KN)
Equation 7
W x KN x (1 - K)
(FL) LOWERING =
(1-KN)
Equation 8
2.2.
Efficiency factor
0.874
0.842
0.811
0.782
Hence for a 20,000 ft well, the drawwork should have 2000 HP. A more rigorous way of calculating the
horse power requirements is as follows:
a)
Equation 9
where
VL = velocity of travelling block
N = number of lines strung
b)
Equation 10
In the Imperial system, power is quoted in horse-power and the above equation becomes:
HL x VL
Drum output = ------------ horsepower
EF x 33,000
Equation 11
Solution
(1)
Weight of string in air
__________________________________________________________________________________
8
Network of Excellence in Training
260,250 lb
= 0.847 x 260,250
=
(2)
220,432 lb
Hook load
= weight of string in mud
+ weight of travelling block, etc
= 220,432 + 23,500
= 243,932 lb
(3)
Deadline load
HL K10
243,932 x 0.961510
= - =
N EF
10 x 0.81
= 20,336 lb
HL
243,932
Fast-line load = =
N x EF
10 x 0.81
= 30,115 lb
(4)
Dynamic crown load
__________________________________________________________________________________
9
Network of Excellence in Training
= DL + FL + HL
= 20,336 + 30,115 + 243,932
= 294,383 lb
(5)
breaking strength
=
fast-line load
Design factor
228,000
=
30,115
(6)
= 7.6
FL
DF
HL
269,130
= = = 33,226 lb
N x EF
10 x 0.81
228,000
= = 6.9
33,226
HLxVw
1
x(
)
EF
33,000
= 500,000 x 120 x 1
0.81 x 33000
= 2245 HP
Power at drum
2245
__________________________________________________________________________________
11
Network of Excellence in Training
Gear ratio
Motor speed
Drum speed
Drum speed
= 143 rpm
Gear ratio
1200
=
477.5
= 2.5
Assuming the motor speed is 1200 rpm, which is a reasonable speed for a motor rated to 3000 HP.
3.
3.1.
The drilling line, like any other drilling equipment, does work at any time it is
involved in moving equipment in or out of the hole. The amount of work done varies
depending the operation involved. This work causes the wireline to wear and if the line
is not replaced it will eventually break.
The amount of work done need to be calculated to determine when to change the
drilling line. The following gives equations for calculating the work done on the
drilling line:
a)
Equation 12
where
M
Ls
D
We
C
__________________________________________________________________________________
12
Network of Excellence in Training
Wdc
Wdp
L
b)
c)
Equation 13
Tc = (T2 - T1 )
where
T2 = WD for 1 round trip at d2 where coring stopped before coming out of the hole.
T1 = WD for 1 round trip at depth d1 , where coring started
d)
D (Ls+D) x Wcs
MD
[ + ]
10,560,000
2,640,000
Equation 15
where
Wcs
Ls
M
D
__________________________________________________________________________________
13
Network of Excellence in Training
D (LS+D) We
D (M+C/2)
Tr = + ton-miles
10,560,000
2,640,000
M
C
= 23.500 lb
= (L x Wdc - L x Wdp) BF
= (500 x 150 - 500 x 19.5) x 0.847
= 55,267
D
Ls
We
= 10,000 ft
= 93 ft
=19.5 x BF = 167.52 lb/ft
Therefore,
Tr
(b)
Ts
1
=
2
D x (Ls + D) x Wcs
DxM
[ + ]
10,560,000
2,640,000
Wcs
Ls
= 40 ft
Ts
1
10,000 x (40 +10,000)
= [
+
2
10,560,000
10,000 x 23,500
]
2,640,000
__________________________________________________________________________________
14
Network of Excellence in Training
(233.5 + 89.0)
= 161.3 ton-miles
(c)
DF
(d)
Tc
= 2 (T2 - T1 )
where T2 = round trip time at 10,180 ft, where coring stopped, and T1 = round trip time at 10,000
ft, where coring started. Therefore,
T2
T1
Therefore,
Tc
= 2 x (360.8 - 351.6)
= 18.4 ton-miles
(e)
Td
= 3 x (T2 - T1 )
= 3 x (360.8 - 351.6)
= 27.6 ton-miles
3.2.
Portions of the drilling line on the crown and travelling blocks sheaves and on the hoisting drum carry the
greatest amount of work and is subjected to a great deal of wear and tear. These parts must be cut and
removed at regular times other wise the drilling line will fail by fatigue. The process is called slip and
cut practice.
__________________________________________________________________________________
15
Network of Excellence in Training
4.
Equation 16
__________________________________________________________________________________
16
Network of Excellence in Training
5.
The heart of the circulating system is the mud pumps. There are two types of pumps used in the oil
industry: Duplex and Triplex.
A basic pump consists of a piston (the liner) reciprocating inside a cylinder. A pump is described as
single acting if it pumps fluid on the forward stroke (Triplex pumps) and double acting if it pumps fluid
on both the forward and backward stokes (Duplex). Figure 7 shows a triplex mud pump.
Figure 7 Triplex Mud Pump, Courtesy of National Oilwell
__________________________________________________________________________________
17
Network of Excellence in Training
Pump Liners: Pump liners fit inside the pump cavity. These affect the pressure rating and flow rate from
the pump. For a given pump, a liner has the same OD but with different Ids. The smaller liner (small
ID) is used in the deeper part of the well where low flow rate is required but at much higher operating
pressure.
The horse power requirements of the pump depends on the flow rate and the pressure. The operating
pressure depends on flow rate, depth and size of hole, size of drillpipe and drillcollars, mud properties
and size of nozzles used. A full hydraulics program needs to be calculated to determine the pressure
requirement of the pump.
The size of the pump is determined by the length of its stroke and the size of the liner.
5.1.
Volumetric Efficiency
Drilling mud usually contain little air and is slightly compressible. Hence the piston moves through a
shorter stroke than theoretically possible before reaching discharge pressure. As a result the volumetric
efficiency is always less than one; typically 95% for triplex and 90% for duplex.
In addition due to power losses in drives, the mechanical efficiency of most pumps is about 85%.
5.2.
HORSEPOWER
The following equations can be used to calculate the power output of a mud pump:
(psi)
Equation 17
Equation 18
Equation 19
__________________________________________________________________________________
18
Network of Excellence in Training
5.3.
Pump Output
Equation 20
Equation 21
5.4.
Equation 22
Equation 23
Pump Factors
In practice, it convenient to express the pump output in terms of how many gallons or
barrels for every stroke of the pump. The equations for the two types of pumps are:
For duplex
Nc x 1s x (2 x dl2 - dr2 ) x Ev
Fp =
42 x 294
Equation 24
For triplex
Fp =
1s x dl2 x Ev
42 x 98.03
Equation 25
where
Nc = number of cylinders
1s = length of stroke, inch
dl = liner diameter, inch
dr = rod diameter, inch=
Ev = volumetric efficiency, fraction
__________________________________________________________________________________
19
Network of Excellence in Training
= 1200 gpm
= 2000 psi
Centrifugal Pumps
This type uses an impeller for the movement of fluid rather than a piston reciprocating inside
a cylinder. Centrifugal pumps are used to supercharge mud pumps and providing fluid to
solids control equipment and mud mixing equipment.
5.6.
Rig sizing must incorporate mud handling equipment as these equipment form the heart of the circulation
system and determine the speed of drilling and the quality of hole drilled.
The equipment includes:
1. Shale Shakers: size, number of type
The type of mud (i.e. oil-based or water-based) determines the type of the shaker required and the motion
of the shaker. Deep holes require more than the customary three shakers.
__________________________________________________________________________________
20
Network of Excellence in Training
2. Mud Pits
The number and size of pits is determined by the size and depth of hole. Other factors include: size of rig
and space available, especially on offshore rigs. The size of a mud pit is usually 8-12 ft wide, 20-40 ft
long and 6-12 ft high.
Volumes Of Tanks
bbl/in in round tank = (diameter in feet) 2 /85.7
bbl/in in square tank = 0.143 (length, ft) x (width, ft)
cu.ft/in in square tank = 0.0833 (length, ft ) x (width, ft)
m3/cm in round tank
3. Mud degasser
4. Centrifuges and mud cleaners
5. Desanders and desilters
The selection of the above equipment determines the loading on the derrick.
6.
BOPs equipment are selected base on the maximum expected wellbore pressures. The pressure rating,
size and number of BOP components must be determined by the Drilling engineer prior to drilling the
well. This is the sizing exercise.
Select:
1. Diverter if required, usually for offshore operations during the drilling of top or surface hole.
Make sure the diverter discharge line is 12 or above.
2. Annular preventer
3. Ram preventers (determine minimum size of rams required to suit the drillstring)
4. Blind or Shear rams
5. Choke manifold
6. HCR valves
7. Choke and Kill lines
8. Accumulator and BOP Control System (Koomey Unit)
9. Drilling spools: used as an element between rams to provide mud exit lines such as choke and kill
lines. Drilling spools can be flanged, studded or clamp-on type.
10. For air drilling, rotating heads are used to allow well control while the pipe is rotating.
__________________________________________________________________________________
21
Network of Excellence in Training
Kelly cock
Drop in valve (check valve)
Float valve (either flapper or spring- loaded ball valve)
Full opening safety valves
BOPs are rated by API as 3M (3000 psi), 5M, 10 M and 15 M. For HPHT, BOPS are either 15 M
or 20 M.
All the above equipment must be rated to the highest pressure to be expected at the well during a kick
or during controlled testing and production.
In subsea operations, the BOP stack is installed at seabed. The stack has several back up units in case
of failure, for example two annulars are used so that if one failed the other can be used. This back-up
system principle is applied to all the BOP components. The subsea stack for HPHT operation may not
be part of the rig contract and may have to be rented out separately, egg a 20K stack.
__________________________________________________________________________________
22
Network of Excellence in Training
7.
The derrick provides the necessary height and support to lift loads in and out of the well. The derrick
must be strong enough to support the hook load, deadline and fastline loads, pipe setback load and
wind loads.
There are two types of derricks:
1. Standard Derrick: is a bolted structure that must be assembled part by part, usually used on
offshore platforms.
Derricks installed on floating structures such as ships and semisubmersibles are designed to withstand
extra dynamic stresses due to rolling, pitching and heaving of the support and due to stresses from
winds. The space available between the rig floor and the crown block must be higher to handle the
wave- induced vertical movements of the floating support.
2. Mast or Portable derrick: This type is pivoted at its base and is lowered to the horizontal by the
use of drawers after completing the well and the rig is ready to move to another location. the
mast dismantles into a number of pin-jointed sections, each of which is usually a truck load.
The mast is usually used on land operations where the complete rig must be moved between well
locations. at the new location, the sections are quickly pined together and the mast is raised to the
vertical by the drawworks.
The derrick consists of four legs connected by horizontal structural members described as girts. the
derrick is further strengthened by bracing members connecting the girts.
The derrick sits on a substructure on which drilling equipment is mounted. The substructure is
composed of derrick supports and rotary supports.
The derrick supports consist of four posts and exterior bracing between the supports. the rotary
supports consist of beams and braces to support the rotary table and pipeset back load.
The height of the substructure above the ground varies according to the size of the substructure and
the size and rating of the wellhead and BOPs. For a base size of 30 ft , the height is 10- 14 ft.
Hl
HL 3
+ HL +
= HL
4
4
2
( N + 2)
HL
N
where
N = number of lines strung to travelling block
HL = hook load
The wind load is given by : 0.004 V2 (units lb/ft2 )
where V is wind speed in miles/hour
The above result must be multiplied by the WIND LOAD AREA which is given in API 4A for different
derrick sizes in order to obtain the load in lb..
Solution
(1)
__________________________________________________________________________________
24
Network of Excellence in Training
260,250 lb
(2)
0.847 x 260,250
220,432 lb
Hook load
= weight of string in mud
+ weight of travelling block, etc
= 220,432 + 23,500
HL
= 243,932 lb
(3)
Deadline load
HL K10
= x
N
EF
243,932 x 0.961510
10 x 0.81
= 20,336 lb
Fast-line load
HL
=
N x EF
243,932
10 x 0.81
= 30,115 lb
(4)
__________________________________________________________________________________
25
Network of Excellence in Training
Design factor =
breaking strength
fast-line load
228,000
= - = 7.6
30,115
(6)
HL
HL
=
N x EF
476.645
10 x 0.81
= 58,845 lb
228,000
DF
=
------= 3.9
58,845
(7) Dynamic derrick loading during running casing = FLL + HL + DLL
Deadline load
HL K10
= N
EF
476,645 x 0.9615 10
=
10 x 0.81
= 39,738
__________________________________________________________________________________
26
Network of Excellence in Training
Hence the derrick capacity must be approximately 750,000 lb to allow fo r extra loading such as wind ,
pipe setback load etc.
8.
The total power requirement of a rig is the sum of the power requirement of:
1.
2.
3.
4.
5.
Drawworks
mud pumps
Rotary system
Auxiliary power requirements for lighting etc.
life support system
The above total power may not be required in a continuous but in an intermittent mode.
The actual power required will depend on the drilling job being carried out. The maximum power used
is during hoisting and circulation. The least power use d is during wireline operations.
The majority of rigs in current use require between 1000 3000 horsepower.
The power on modern rigs is most commonly generated by diesel-electric power units. The power
produced is AC current which is then converted to DC current by the use of SCR (Silicon Controlled
Rectifier) . The current is delivered by cables to electric motors attached directly to the equipment
involved such as mud pumps, rotary table, Drawworks etc.
__________________________________________________________________________________
27
Network of Excellence in Training