Villa Construction
Villa Construction
Villa Construction
Samahita Residences
Villa Construction
Project Management
Process
Contents
3.0
Construction Phase
Section
1.0
Villa Construction Project Management
EXECUTIVE SUMMARY
Following correct Project Management process will ensure the design and construction
of your villa to be a relatively smooth process resulting in a well built, quality finished
home, completed within a year to a pre determined budget.
This document details the Project Mangement process and procedures implemented
and executed by Sterling Project Management during the build process from concept
design through to construction.
Once the land has been procured and funds established with the purpose to build a
villa, the Project Manager should be engaged to facilitate and manage the entire
process including but not limited to the following :
Section
2.0
Villa Construction Project Management
DESIGN PHASE (PRE- CONSTRUCTION)
At the beginning of the design phase, if you do not already have your own architect or
design team, we recommended engagement of Rarin Design as they have been
integral to the planning and establishment of the development, have already designed
several villas, and have a long established working relationship ourselves and the
Developers of Samahita. We can manage the appointment directly or introduce Rarin
Design if you prefer.
The design phase comprises five main areas:
1. Concept design
2. Build permission design and Build Permit application & approval
3. Co-ordination and completion of full design
4. Tendering, pricing and cost analysis
5. Contractor selection and contract signing.
1. Concept Design
This is the first stage where the Owner decides on the size and style of villa and
the Architect produces some basic floor plan layouts. Once the layout is agreed,
the Architect can then produce some 3D coloured perspectives which show
elevations of the villa on the land. The time to develop and agree a concept
design could be from 2-4 weeks. The Architect will make the concept floor plans
gratis, but will require engagement of services to complete the coloured concept
perspectives and all services thereinafter.
In normal circumstances a topographical survey would be required to determine
the land contours before commencement of the villa design, however at
Samahita a survey of all the plots has already been carried out by the
Developer.
Structural engineer
Electrical system
TV system
Practical completion
Construction can commence once the Contract has been signed and a
mobilization payment of 15% of contract value is paid to Contractor. The
mobilization payment is like a loan, as each month it gets paid back by the
Contractor as a proportion of the work complete.
Design Phase Schedule & Costs
The length of the design phase from time of agreeing the concept to signing of
contracts is 3-4 months and can be broken down into the following:
Architectural Fees:- 300,000 baht 350,000 baht (depends on size of villa and
includes all structural and MPE design)
Section
3.0
Villa Construction Project Management
CONSTRUCTION PHASE
The Construction Phase can be subdivided into several main segments:
1.
2.
3.
4.
5.
Site Establishment
Construction Management
Contract Management & Cost Control
Programme Management
Final Completion and Handover
1. Site Establishment
Construction can start about a week after the contracts are signed and mobilisation
payment made to the Contractor. Site Establishment and set out is the first step of
the Construction Phase and includes but is not limited to the following activities:
Boundary survey to establish correct position of chanote markers and
verify location of boundaries.
Set out villa footprint in relation to the boundary setback and determine the
floor levels.
Survey and setout of foundations.
Connection to temporary power and water.
Establish site office, amenities, materials store any temporary
accommodation.
2. Construction Management
Construction Management can be described as Quality Control of the construction
and is achieved through dual management of the site works and document control:
i.
ii.
Documents Control:
o Drawing distribution register
o Site instructions and summary register
o Non-conformance reports
o Corrective action reports
o Request for Information (RFI)
o Diary notes
The Contractor will make monthly progress claims based on the work which has
been completed, so there is little risk of the Contractor defaulting, having been over
paid. In addition, for each monthly claim a proportion of the mobilization payment is
deducted, plus 5% retention is deducted. Half the retention is paid back on Practical
Completion and the remaining half is paid back at the end of the 12 months defect
liability period.
4. Programme Management
This includes the preparation & management of the project schedule, time control
and the evaluation of any extension of time claims.
The schedule can be split into structural work and architectural finishing work. The
structure can take 3-4 months to complete, depending on size of villa, slope of the
land and access for materials, the structural work sequence goes as follows:
o
o
o
o
o
o
o
o
o
Samahita has a lot of rock, therefore there is the potential that some excavation in
rock may be necessary, this could result in some additional cost and extension of
time, because rock is considered a latent ground condition.
Once the structure is complete, work will commence to the architectural finishing.
First the block walls are built and rendered, this activity can overlap with the
structural work in multi level buildings. Then the following tasks are completed:
o
o
o
o
o
o
o
o
o
o
o
o
o
steep hillside or flatter ground, however as a guide the cost range is approximately THB
21,000/sqm to THB 25,000/sqm.
Not included in the Contractors contract price is the kitchen & appliances, furniture
(loose & built-in), landscaping, curtains and blinds, connection to internet and
telephone, audiovisual such as subscription to satellite TV.
Project Management fees for the construction phase are 60,000 baht per month.
Should there be any questions to any of the information above, please do not hesitate
to call Shane from Sterling Project Management on mobile phone 0848 496 255 or
email at [email protected].