Aksa Startup Checklist

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Coolant heater operational

Generator set start-up checklist

Leak check

Open & enclosed generator sets

DCA dosing cartridges fitted & valves open

This checklist should be used to validate the completion of


generator set start-up procedure. A check-list should be
completed for each generator set of a multiple installation.

Remote mounted radiator systems


Radiator, engine & pipework checked for leaks

Project Details

Coolant heater operational

Project Name ...

Fans, pumps and controls checked

....

Leak check

Customer (End User)......

DCA dosing cartridges fitted & valves open

....

Heat exchanger & cooling tower systems

Address ....

System, engine & pipework checked for leaks


Coolant heater operational

Secondary cooling system checked

...

Fans, pumps and controls checked

Customer representative....

DCA dosing cartridges fitted & valves open

Tel. No ..

Legionnella dosing checked where applicable

Email.

Bulk storage facility

Generator set serial number.Set no.

Isolating valves correctly positioned

Control type...

Transfer pump & controls operational

Control serial number..

Pipeline / tank heating system operational

System control type (if applicable)

Fill point alarm operational


Leaks check

Generator set environment and services

Storage facility secure

Isolating and solenoid valves checked


Tank filled
Spillage containment & alarms operational

Transfer pump operational


Leak check

Safety Checks

No loose materials near set


Air ducts clear and clean
Access & egress routes unobstructed & labelled
Control & maintenance positions unobstructed
Room secure no unauthorised access
Personnel warned of start-up process

Fire valves & release tested and operational

Isolating valves correctly positioned


Regulator set to correct pressure
Gas leak detection equipment operational
Double shut-off device operational
Leak test complete
Purging complete

Fire alarm / suppression system

Set mounted radiator

Fire alarm / suppression system operational

Belts & guards checked for security / slipping

Gas Fuel System

Cooling System
Radiator, engine & pipework checked for leaks

Day tank

Observations....

Set clean and fully assembled

Diesel Fuel System

Generator set model...

Ensure starting is inhibited until start-up is required

Record dosing chemical & concentration.............................

Generator set details

Precommissioning work & checklist complete


Surroundings clean & clear from obstruction
Lighting / heating, etc., systems operational

Suppression system lock-off operational

Operator instructed in fire system operation


1


Control system calibrations checked

Phase rotation checked

Paralleling sets phase coincidence check

Generator set switchgear manual operation correct


Local stop / emergency stop control checked

Remote start / stop / emergency stop checked

Lubrication system
Engine oil pan filled to correct level
Oil make up system operational

Generator set voltage & frequency correct to order

Starting system
Battery starting
Batteries installed, filled and connected
Battery charger commissioned

Generator set load test

Compressed air / hydraulic starting


Isolating valves correctly positioned
Compressor operational
HP & LP air / hydraulic pressures checked
Condensate drained

Note: Load test is carried out on customers site load


unless agreed in writing prior to start-up. Artificial load
bank test will be performed using resistive load unless
otherwise specified.
Load test completed using customers load

Record load achievedkW

Load bank test (if applicable)

Exhaust system
Check security of pipework & muffler
Check cowl and/or rain cap are operational
Check water drain pipework and valves correct
Leak check
Check for exhaust gas recirculation

Check load bank voltage & power capability

Check cables installed correctly & tightened


Energise auxiliary supplies and check functionality
Load test completed
Result sheet completed

Record load achievedkW


Record power factor

Ventilation & attenuation


Check louvers are clear and operational
Forced ventilation system operational if applicable
Check for hot air recirculation

System start-up completion

Generator set remote controls checked


Generator set system controls checked
Customer remote indication / controls checked

Utility supply energised


Voltage / phase rotation checked
Indications correct
All covers in position

Master control operational

Comments on any item that may affect acceptance:

Paralleling switchgear
Auxiliary supplies energised
Indications correct
All covers in position

Automatic operations checked

Changeover switchgear / transfer switch


Auxiliary supplies energised

Electrical HV/MV/LV rules and procedures in place

Paralleling switchgear operational

Control systems
Generator set local controls checked

All safety shutdowns and warnings operational

Changeover / transfer switch operational

Electrical system
Auxiliary supplies energised

Generator set operational

Checklist completed by .
Date...
Print Name

Initial start-up
Manual start-up, idle & full speed checks complete

Company..

Note: Completion of this checklist does not relieve the installer of contract obligations.