Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty., 554 U.S. 527 (2008)
Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty., 554 U.S. 527 (2008)
Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty., 554 U.S. 527 (2008)
Syllabus
NOTE: Where it is feasible, a syllabus (headnote) will be released, as is
being done in connection with this case, at the time the opinion is issued.
The syllabus constitutes no part of the opinion of the Court but has been
prepared by the Reporter of Decisions for the convenience of the reader.
See United States v. Detroit Timber & Lumber Co., 200 U. S. 321, 337.
ET AL.
Syllabus
sumptively reasonable only where FERC has had an initial opportunity to review the contracts without applying the Mobile-Sierra presumption and therefore that the presumption should not apply to
contracts entered into under market-based tariffs. The court alternatively held that there is a different standard for overcoming the
Mobile-Sierra presumption when a purchaser challenges a contract:
whether the contract exceeds a zone of reasonableness.
Held:
1. The Commission was required to apply the Mobile-Sierra presumption in evaluating the contracts here. Sierra held that a rate set
out in a contract must be presumed to be just and reasonable absent
serious harm to the public interest, regardless of when the contract is
challenged. FPC v. Texaco Inc., 417 U. S. 380, distinguished. Also,
the Ninth Circuits rule requiring FERC to ask whether a contract
was formed in an environment of market dysfunction is not supported by this Courts cases and plainly undermines the role of contracts in the FPAs statutory scheme. Pp. 1519.
2. The Ninth Circuits zone of reasonableness test fails to accord
an adequate level of protection to contracts. The standard for a
buyers rate-increase challenge must be the same, generally, as the
standard for a sellers challenge: The contract rate must seriously
harm the public interest. The Ninth Circuit misread Sierra in holding that the standard for evaluating a high-rate challenge and setting
aside a contract rate is whether consumers electricity bills were
higher than they would have been had the contract rates equaled
marginal cost. Under the Mobile-Sierra presumption, setting aside
a contract rate requires a finding of unequivocal public necessity,
Permian Basin Area Rate Cases, 390 U. S. 747, 822, or extraordinary
circumstances, Arkansas Louisiana Gas Co. v. Hall, 453 U. S. 571,
582. Pp. 1923.
3. The judgment below is nonetheless affirmed on alternative
grounds, based on two defects in FERCs analysis. First, the analysis
was flawed or incomplete to the extent FERC looked simply to
whether consumers rates increased immediately upon conclusion of
the relevant contracts, rather than determining whether the contracts imposed an excessive burden down the line, relative to the
rates consumers could have obtained (but for the contracts) after
elimination of the dysfunctional market. Sierras excessive burden
on customers was the current burden, not just the burden imposed at
the contracts outset. See 350 U. S., at 355. Second, it is unclear
from FERCs orders whether it found respondents evidence inadequate to support their claim that petitioners engaged in unlawful
market manipulation that altered the playing field for contract negotiations. In such a case, the Commission should not presume that a
Syllabus
contract is just and reasonable. Like fraud and duress, unlawful
market activity directly affecting contract negotiations eliminates the
premise on which the Mobile-Sierra presumption rests: that the contract rates are the product of fair, arms-length negotiations. On remand, FERC should amplify or clarify its findings on these two
points. Pp. 2326.
471 F. 3d 1053, affirmed and remanded.
SCALIA, J., delivered the opinion of the Court, in which KENNEDY,
THOMAS, and ALITO, JJ., joined, and in which GINSBURG, J., joined as to
Part III. GINSBURG, J., filed an opinion concurring in part and concurring in the judgment. STEVENS, J., filed a dissenting opinion, in which
SOUTER, J., joined. ROBERTS, C. J., and BREYER, J., took no part in the
consideration or decision of the cases.
Its Consequences
10
11
12
13
14
2 In a holding not challenged before this Court, the Ninth Circuit con
cluded that the contracts at issue did not contain Memphis clause[s],
471 F. 3d 1053, 1079 (2006) (citing United Gas Pipe Line Co. v. Memphis
Light, Gas and Water Div., 358 U. S. 103 (1958)), see supra, at 5, that
would have precluded application of the Mobile-Sierra presumption.
15
Rate Authority
16
17
3 We
18
19
20
4 The
21
22
23
6 The
dissent claims that we have misread the FPA because its provi
sions do not distinguish between rates set unilaterally by tariff and
rates set bilaterally by contract. Post, at 2. But the dissents interpre
tation, whatever plausibility it has as an original matter, cannot be
squared with Sierra, which plainly distinguished between unilaterally
and bilaterally set rates, and said that the only relevant consideration
for the Commission in the latter case is whether the public interest is
harmed. And the circumstances identified in Sierra as implicating the
public interest refer to something more than a small dent in the con
sumers pocket, which is why our subsequent cases have described the
standard as a high one.
At the end of the day, the dissent simply argues against the settled
understanding of the FPA that has prevailed in this Court, lower
courts, and the Commission for half a century. Although the dissent is
correct that we have never used the phrase Mobile-Sierra doctrine in
our cases, that is probably because the understanding of it was so
uniform that no circuit split concerning its meaning arose until the
Ninth Circuits erroneous decision in these cases. If one searches the
Commissions reports, over 600 decisions since 2000 alone have cited
the doctrine, see Brief for Electric Power Supply Association et al. as
Amici Curiae 15, and the Courts of Appeals have used the term Mo
bile-Sierra doctrine (or Sierra-Mobile doctrine) over 75 times since
1974. If there were ever a context where long-settled understanding
should be honored it is here, where a statutory decision (subject to
revision by Congress) has been understood the same way for many
years by lower courts, by this Court, by the federal agency the statute
governs, and hence surely by the private actors trying to observe the
law.
24
25
26
Opinion of GINSBURG, J.
Opinion of GINSBURG, J.
precedent.
I
Under the Federal Power Act (FPA), 41 Stat. 1063, 16
U. S. C. 791a et seq., wholesale electricity prices are
established in the first instance by public utilities, either
via tariffs or in contracts with purchasers. 824d(c).
Whether set by tariff or contract, all rates must be filed
with the Commission. See ibid. Section 205(a) of the FPA
provides, All rates and charges . . . shall be just and
reasonable, and any such rate or charge that is not just
and reasonable is hereby declared to be unlawful. 16
U. S. C. 824d(a). Pursuant to 206(a), if FERC determines that any rate . . . or that any rule, regulation,
practice, or contract affect[ing] such rate . . . is unjust [or]
unreasonable . . . , the Commission shall determine the
just and reasonable rate, . . . rule, regulation, practice, or
contract to be thereafter observed and in force, and shall
fix the same by order. 16 U. S. C. 824e(a). These provisions distinguish between the rate-setting roles of utilities
(which initially set rates) and the Commission (which may
override utility-set rates that are not just and reasonable),
but they do not distinguish between rates set unilaterally
by tariff and rates set bilaterally by contract. However the
utility sets its prices, the standard of review is the same
rates must be just and reasonable.
The Court purports to acknowledge that [t]here is only
one statutory standard for assessing wholesale electricity
rates, whether set by contract or tariffthe just-andreasonable standard. Ante, at 16. Unlike rates set by
tariff, however, the Court holds that any freely negotiated contract rate is presumptively just and reasonable
unless it seriously harms the public interest. Ante, at 1.
According to the Court, this presumption represents a
differing application of [the] just-and-reasonable standard, but not a different standard altogether. Ante, at 6.
1 See also, e.g., Arkansas Louisiana Gas Co. v. Hall, 453 U. S. 571,
582 (1981) (Arkla) ([T]he clear purpose of the congressional scheme
for rate filing is to gran[t] the Commission an opportunity in every
case to judge the reasonableness of the rate); Permian Basin Area Rate
Cases, 390 U. S. 747, 784 (1968) ([T]he Commission has plenary
authority to limit or to proscribe contractual arrangements that contravene the relevant public interests).
2 The Court repeatedly quotes the following snippet from the 75-page
opinion in Permian Basin: The regulatory system created by the Act is
premised on contractual agreements voluntarily devised by the regulated companies; it contemplates abrogation of these agreements only
in circumstances of unequivocal public necessity. 390 U. S., at 822
(cited ante, at 5, 22, 24). Like FPC v. Sierra Pacific Power Co., 350
U. S. 348 (1956), however, Permian Basin made this statement in the
course of rejecting a low-rate challenge. Read in context, the Courts
reference to unequivocal public necessity is a loose restatement of
Sierra, which required evidence of injury to the public interest, and
which underscored how rarely a utility will be able to demonstrate that
a contract price is so low as to adversely affect the public interest.
390 U. S., at 820821 (quoting Sierra, 350 U. S., at 355). The Courts
expansive reading of the unequivocal public necessity statement
cannot be squared with Permian Basins discussion of the Commissions
authority to review rates set by contract: Although the Natural Gas
Act is premised upon a continuing system of private contracting, the
Commission has plenary authority to limit or to proscribe contractual
arrangements that contravene the relevant public interests. 390 U. S.,
at 784 (citation omitted). Nor can it be reconciled with Permian Basins
rejection of the producers arguments (1) that the Commission wrongly
invalidated existing contracts by imposing a ceiling on rates, see id., at
781784, and (2) that the Commission was compelled to adopt contract
prices as the basis for computing area rates, see id., at 792795.
10
11
and reasonable rates through the expedient of a heavyhanded presumption. This is not to say that the Commission should abrogate any contract that increases rates, but
to underscore that the agency is obliged at each step of its
regulatory process to assess the requirements of the broad
public interests entrusted to its protection by Congress.
Permian Basin, 390 U. S., at 791.
IV
Even if, as the Court holds today, the Mobile-Sierra
presumption is merely a differing application of the
statutory just-and-reasonable standard, FERCs orders
must be set aside because they were not decided on this
basis.
The FERC orders repeatedly aver that the agency is
applying a public interest standard different from and
distinctly more demanding than the statutory standard.
See, e.g., App. 1198a ([T]he burden of showing that a
contract is contrary to the public interest is a higher burden than showing that a contract is not just and reasonable. . . . The fact that a contract may be found to be unjust and unreasonable under [205 and 206] does not in
and of itself demonstrate that the contract is contrary to
the public interest under the Supreme Court cases).
Indeed, the Commissions misunderstanding of our cases
is so egregious that the sellers, concerned that the orders
would be overturned, asked the Commission for clarification that the public interest standard of review does not
authorize unjust and unreasonable rates. Id., at 1506a,
1567a. FERC clarified as follows:
[I]f rates . . . become unjust and unreasonable and
the contract at issue is subject to the Mobile-Sierra
standard of review, the Commission under court
precedent may not change the contract simply because
it is no longer just and reasonable. If parties marketbased rate contracts provide for the public interest
12
13
4 The
14
for such a standard but rather evidence an intent that the contracts
may be changed only pursuant to the public interest standard of
review. Under the public interest standard, to justify contract modification it is not enough to show that forward prices became unjust and
unreasonable due to the impact of spot market dysfunctions (footnote
omitted)); id., at 1527a (Complainants were required to meet the
public interest standard of review, not the just and reasonable standard
of review which could have taken into account the causal connection
between the spot market prices and forward bilateral market prices);
id., at 1534a (The Staff Report did not make any findings regarding
the justness and reasonableness of any contract rates and any such
findings would not be relevant here because the just and reasonable
standard is not applicable).
15