Daily Progress Report
Daily Progress Report
Daily Progress Report
9-Dec-15
Area
131- Limestone Clay Mix Storage
321-Raw Mill
421-Preheater
431-Kiln
431-Kiln
Atox mill housing inner welding now completed. Outside welding in-progress
2 Nos. pieces of Calciner erected
Shell inspection in-progress
Bearing scrapping in-progress
Civil
Mechanical
b) Potential issues
Grid Station
Issue
Consequences
Excavation of Switch Yard yet not started due to shortage/limited earth Completion of Civil Works in Switch Yard will be
moving machines
delayed
Embeded Parts of Cable Trenches e.g Angle for Grating
Embeded Part required till Dec 08,2015
Anchor Bolts of Foundations in Switch Yard
Mechanical
Manpower required to M/s Mughal Engineering
Sand
Crush
Cement
Diesel
Oxygen Cylinder
DA Cylinder
Fon Gas Cylinder
Unit
ton
ton
ton
liter
Nos.
Nos.
Nos.
NYA
Locals
Expats
LCL
Total
Manpower
Contractor
43
Alghazi
6
INDEC
11
Cambridge
Al Farooq
TNI
SCS
EMI
FLS
LOYA
60
Manpower
60
37
246
23
168
316
149
4
6
1009
e) Civil Activates
Area
100 -Raw Material
Handling
Equipment
131-Limestone/Clay Mix Storage
Coal Shed
Excavation
(cum)
-
Formwork
(sqm)
56.16
-
Block
Concrete (cum) masonry/Finishing(S
qm)
16.5
15.2
-
400 - Clinker
Production Area
441-Clinker Cooler
500 - Cement
Grinding Area
600 - Cement
Storage and
Dispatch Area
800 - Electrical
Departments Area
Ancillary Building
Dinning Hall
Labour Block
Total Quantities
1.56
7.8
1.272
13.308
3.25
80.304
2.65
142.364
13
92
10.6
3
150.3
60
60
-
f) Mechanical Activities
Area
Equipment
500 - Cement
Grinding Area
600 - Cement
Storage and
Dispatch Area
Total Quantities
Embedment
fabrication
(ton)
0
Embedment
Padding and Structure
installation (ton) leveling (ton) erection (ton)
0.08
0.08
Equipment erection
(ton)
8.7
8.7
g) Mining Activates
Total Overburdened Remove Today (cum)
Target Date
15,548
728,673
3,200,000
1-Jun-16