I&c Control System
I&c Control System
ABWR DCD
R4
Rev. 0
ABWR
Chapter 7
Table of Contents
List of Tables..................................................................................................................... 7.0-iii/iv
List of Figures ..........................................................................................................................7.0-v
7.0
7.1
7.2
7.3
7.4
7.5
7.6
Table of Contents
7.0-i
Rev. 0
ABWR
7.6.3
7.7
7.6.2.1
Neutron Monitoring System .......................................................... 7.6-21
7.6.2.2
Process Radiation Monitoring System........................................... 7.6-24
7.6.2.3
HP/LP System Interlock Function ................................................ 7.6-27
7.6.2.5
Wetwell-to-Drywell Vacuum Breaker System................................. 7.6-29
7.6.2.6
Containment Atmospheric Monitoring System............................ 7.6-29
7.6.2.7
Suppression Pool Temperature Monitoring System .................... 7.6-31
COL License Information.................................................................................... 7.6-34
7B
7C
7.0-ii
Table of Contents
Rev. 0
ABWR
Chapter 7
List of Tables
Table 7.1-1
Table 7.1-2
Table 7.2-1
Table 7.2-2
Table 7.4-1
Table 7.5-1
Table 7.5-2
Table 7.5-3
Table 7.5-4
Table 7.5-5
Table 7.5-6
Table 7.5-7
Table 7.5-8
Table 7.5-9
Table 7.6-1
Table 7.6-2
Table 7.6-3
Table 7.6-4
Table 7.6-5
Table 7.7-1
Table 7A-1
List of Tables
7.0-iii /iv
Rev. 0
ABWR
Chapter 7
List of Figures
Figure 7.1-1
Figure 7.1-2
Figure 7.2-1
ABWR SSLC Control Power Scheme (See also Figure 8.3-3) ......................... 7.2-50
Figure 7.2-2
Figure 7.2-3
Division 1 Trip Logic Turbine Stop Valve Closure and Turbine Control
Valve Fast Closure.............................................................................................. 7.2-52
Figure 7.2-4
Figure 7.2-5
Figure 7.2-6
Figure 7.2-7
Figure 7.2-8
SCRAM Solenoids and Air Header Dump Valves Power Distribution ........... 7.2-57
Figure 7.2-9
Figure 7.2-10
Figure 7.3-1
Figure 7.3-2
Figure 7.3-3
Figure 7.3-4
Figure 7.3-5
Figure 7.3-6
Figure 7.3-7
Reactor Building Cooling Water System IBD (Sheets 119) .......................... 7.3-97
Figure 7.3-8
Figure 7.3-9
Figure 7.3-10
Figure 7.4-1
Figure 7.4-2
Figure 7.4-3
List of Figures
7.0-v
Rev. 0
ABWR
Figure 7.6-2
Figure 7.6-3
Figure 7.6-4a
Figure 7.6-4b
Figure 7.6-5
Figure 7.6-6
Figure 7.6-7
Figure 7.6-8
Figure 7.6-9
Figure 7.6-10
Figure 7.6-11
Suppression Pool Temperature Monitoring System IED (Sheets 1-3) .......... 7.6-49
Figure 7.6-12
Suppression Pool Temperature Monitoring System IBD (Sheets 16) ......... 7.6-49
Figure 7.6-13
Figure 7.6-14
Figure 7.7-1
Figure 7.7-2
Rod Control and Information System IED (Sheets 1-5) ................................. 7.7-91
Figure 7.7-3
Figure 7.7-4
Figure 7.7-5
Figure 7.7-6
Figure 7.7-7
Figure 7.7-8
Figure 7.7-9
Figure 7.7-10
7.0-vi
List of Figures
Rev. 0
ABWR
Figure 7.7-12
Steam Bypass and Pressure Control System IED (Sheets 1-2) ........................ 7.7-94
Figure 7.7-13
Steam Bypass and Pressure Control System IBD (Sheets 1-5) ........................ 7.7-94
Figure 7.7-14
Fuel Pool Cooling and Cleanup System IBD (Sheets 18)............................. 7.7-94
Figure 7A-1
Figure 7A-2
Figure 7C-1
List of Figures
7.0-vii/viii
Rev. 0
ABWR
7.1-1
Rev. 1
ABWR
System. The equipment arrangement for these systems and other supporting systems is
shown in Figure 7.1-2.
7.1.1.2 Reactor Protection (Trip) System (RPS)
The Reactor Protection (trip) System instrumentation and controls initiate an
automatic reactor shutdown via insertion of control rods (scram) if monitored system
variables exceed preestablished limits. This action avoids fuel damage, limits system
pressure and thus restricts the release of radioactive material.
[The RPS and ESF (Subsection 7.1.1.3) Systems can be tested during reactor operation. Subsection
7.1.2.1.6 identifies testing, which, if, changed, requires NRC Staff review and approval prior to
implementation. The applicable portions for this restriction are shown on Subsection 7.1.2.1.6
itself. ]*
7.1.1.3 Engineered Safety Features (ESF) Systems
7.1.1.3.1 Emergency Core Cooling Systems (ECCS)
Instrumentation and controls provide automatic initiation and control of specific core
cooling systems such as High Pressure Core Flooder (HPCF) System, Automatic
Depressurization System (ADS), Reactor Core Isolation Cooling(RCIC) System and the
Low Pressure Flooder mode of the Residual Heat Removal (RHR) System provided to
cool the core fuel cladding following a design basis accident.
7.1.1.3.2 Leak Detection and Isolation System
Instrumentation and controls monitor selected potential sources of steam and water
leakage or other conditions and automatically initiate closure of various isolation valves
if monitored system variables exceed preestablished limits. This action limits the loss of
coolant from the reactor coolant pressure boundary (RCPB) and the release of
radioactive materials from either the RCPB or from the fuel and equipment storage
pools.
7.1.1.3.3 Wetwell and Drywell Spray Mode of RHR
Instrumentation and controls provide manual initiation of wetwell spray and drywell
spray (when high drywell pressure signal is present) to condense steam in the
containment and remove heat from the containment. The drywell spray has an
interlock such that drywell spray is possible only in the presence of a high drywell
pressure condition.
Introduction
Rev. 0
ABWR
7.1-3
Rev. 1
ABWR
or low reactor water level from the Recirculation Flow Control System), the RCIS System
controls the fine motion control rod drive (FMCRD) motors such that all operable
control rods are driven to their full-in position. This provides a method, diverse from
the hydraulic control units (HCUs), for scramming the reactor.
7.1.1.4.2 Standby Liquid Control System (SLCS)
Instrumentation and controls are provided for the manual initiation of an independent
backup system (SLCS) which can shut the reactor down from rated power to the cold
condition in the event that all withdrawn control rods cannot be inserted to achieve
reactor shutdown. In addition, should the FMCRD fail to shut down the reactor
during an ATWS event as described in Subsection 7.1.1.4.1, then instrumentation and
controls are provided for the automatic initiation of SLCS.
7.1.1.4.3 Residual Heat Removal (RHR) System/Shutdown Cooling Mode
Instrumentation and controls provide manual initiation of cooling systems to remove
the decay and sensible heat from the reactor vessel.
7.1.1.4.4 Remote Shutdown System
Manual instrumentation and controls are provided outside the main control room to
assure safe shutdown of the reactor in the event that the main control room should
become uninhabitable.
7.1.1.5 Safety-Related Display Instrumentation
Safety-related display instrumentation is provided to inform the reactor operator of
plant conditions and equipment status so that it can be determined when a manual
safety action should be taken or is required.
7.1.1.6 Other Safety-Related Systems
7.1.1.6.1 Neutron Monitoring System (NMS)
The Neutron Monitoring System (NMS) monitors the core neutron flux from the
startup source range to beyond rated power. The NMS provides logic signals to the
Reactor Protection System (RPS) to automatically shut down the reactor when a
condition necessitating a reactor scram is detected. The NMS is composed of the
following subsystems:
7.1-4
(1)
(2)
(3)
Introduction
Rev. 0
ABWR
(4)
(5)
Introduction
7.1-5
Rev. 0
ABWR
The safety design basis for a safety system states in functional terms the unique design
requirements that establish the limits within which the safety objectives shall be met.
The general functional requirement portion of the safety design basis presents those
requirements which have been determined to be sufficient to ensure the adequacy and
reliability of the system from a safety viewpoint. Many of these requirements have been
incorporated into various codes, criteria, and regulatory requirements.
7.1.2.1.1 Safety Design Bases for Safety Systems
Safety systems provide actions necessary to assure safe plant shutdown to protect the
integrity of radioactive material barriers and/or prevent the release of radioactive
material in excess of allowable dose limits. These safety systems consist of components,
groups of components, systems, or groups of systems. A safety system may have a power
generation design basis which states in functional terms the unique design
requirements which establish the limits within which the power generation objective for
the system shall be set.
7.1.2.1.2 Specific Regulatory Requirements
The plant systems have been examined with respect to specific regulatory requirements
and industry standards which are applicable to the instrumentation and controls for the
various systems. Applicable requirements include specific parts or entities from the
following:
(1)
(2)
(3)
The specific regulatory requirements identified in the Standard Review Plan which are
applicable to each system instrumentation and control are specified in Table 7.1-2. For
a discussion of the degree of conformance, see the analysis subsection for the specific
system.
7.1.2.1.3 Non-Safety Design Bases
Non-safety-related (including power-generation) systems are reactor support systems
which are not required to protect the integrity of radioactive material barriers nor
prevent the release of radioactive material in excess of allowable dose limits. The I&C
portions of these systems may, by their actions, prevent the plant from exceeding preset
limits which would otherwise initiate action of the safety systems.
7.1-6
Introduction
Rev. 0
ABWR
Introduction
The first of these is the manual scram test. The manual scram test verifies the ability to
de-energize the scram pilot valve solenoids without scram by using the manual scram
pushbutton switches. By depressing the manual scram button for one trip logic, half of
the scram solenoids are de-energized. After the first trip logic is reset, the second trip logic
is tripped manually to complete the test for the two manual scram buttons. In addition
to control room and computer printout indications, scram group indicator lights indicate
that the actuator trip logics have de-energized the scram pilot valve solenoids.
7.1-7
Rev. 0
ABWR
On the back panels, a separate, manual pushbutton switch in each of the four divisions
provides a means to manually trip all trip actuators in that division. This sealed-in
division manual trip is equivalent to a sealed-in automatic trip from the same division
of trip logic. (An alternate manual scram can be accomplished by depressing any two or
more of the four divisional manual trip pushbuttons.)
7.1-8
(2)
The second test includes calibration of the Neutron Monitoring System (NMS) by means
of simulated inputs from calibration signal units. Calibration and test controls for the
NMS are located in the Control Building equipment room. They are under the
administrative control of the control room operator and can be done either manually or
automatically (see Subsection 7.6.1.1 for the calibration procedure).
(3)
The third test is the single rod scram test which verifies the capability of each rod to scram.
It is accomplished by operating switches for the particular control rod drive. Timing
traces can be made for each rod scrammed. Prior to the test, a physics review is conducted
to assure that the rod pattern during scram testing will not create a rod of unacceptable
reactivity worth.
(4)
The fourth test checks calibration of analog sensor inputs at the analog inputs of the
remote multiplexing units. With a division-of-sensors bypass in place, calibrated,
variable ramp signals are injected in place of the sensor signals and monitored at the
SSLC control room panels for linearity, accuracy, fault response, and downscale and
upscale trip response. The test signals are adjustable manually from the control room and
also are capable of performing an automatic sequence of events. When surveillance
testing during plant shutdown, trip coincidence and actuated device operation can be
verified by simultaneous trip tests of coincident channels. Pressure transmitters and level
transmitters are located on their respective local panels. The transmitters can be
individually valved out of service and subjected to test pressure to verify operability of the
transmitters as well as verification of calibration range. To gain access to the field
controls on each transmitter, a cover plate or sealing device must be removed. Access to
the field controls is granted only to qualified personnel for the purpose of testing or
calibration adjustments.
(5)
The fifth test is the sensor check. Digital inputs are tested by varying the monitored
variable (e.g., stop valve closure, control valve fast closure, main steamline isolation
valve closure) or by substituting a test source for the sensor from the process variable and
varying the source. In those cases where the sensor is disconnected from the process
variable, an out-of-service alarm will be indicated in the main control room. Analog
input is checked by cross comparison of the instrument channels measuring the same
variable.
(6)
The sixth test is an integrated self-test provision built into the microprocessors within the
SSLC. It consists of an online, continuously operating, self-diagnostic monitoring
network, and an offline semi-automatic (operator initiated, but automatic to
Introduction
Rev. 0
ABWR
completion), end-to-end surveillance program. Both online and offline functions operate
independently within each of the four divisions. There are no multi-divisional
interconnections associated with self-testing.
The primary purpose of the self-test is to improve the availability of the SSLC by
optimizing the time to detect and determine the location of a failure in the functional
system. It is not intended that the self-test eliminate the need for the other five manual
tests. However, most faults are detected more quickly than with manual testing alone.
The self-test function is classified as safety-related. Its hardware and software are an
integral part of the SSLC and, as such, are qualified to Class 1E standards.
The hierarchy of test capability is provided to ensure maximum coverage of all
EMS/SSLC functions, including logic functions and data communications links.
Testing shall include:
(a)
Introduction
7.1-9
Rev. 0
ABWR
The continuous surveillance monitoring also includes power supply voltage levels,
card-out-of-file interlocks, and battery voltage levels on battery-backed memory
cards (if used). Out-of-tolerance conditions will result in an inoperative (out-ofservice) condition for that particular system function.
Automatic system self-testing occurs during a portion of every periodic
transmission period of the data communication network. Since exhaustive tests
cannot be performed during any one transmission interval, the test software is
written so that sufficient overlap coverage is provided to prove system performance
during tests of portions of the circuitry, as allowed in IEEE 338.
The Essential Multiplexing System (EMS) is included in the continuous,
automatic self-test function. Faults at the Remote Multiplexing Units (RMUs) are
alarmed in the main control room. Since the EMS is dual in each division, selftest supports automatic reconfiguration or bypass of portions of EMS after a
detected fault, such that the least effect on system availability occurs.
(b)
(ii)
Serial and parallel I/O, including manual control switches, limit switches,
and other contact closures.
A separate test sequence for each safety system is operator-selectable; testing will
proceed automatically to conclusion after initiation by the operator. Surveillance
testing is performed in one division at a time. The surveillance test frequency is
given in Chapter 16.
7.1-10
Introduction
Rev. 0
ABWR
The STC injects test patterns through the EMS communications links to the
RMUs. It then tests the RMUs ability to format and transmit sensor data through
and across the EMS/SSLC interface, in the prescribed time, to the load drivers.
Under the proper bypass conditions, or with the reactor shut down, the load drivers
themselves may be actuated.
All testing features adhere to the single-failure criterion, as follows: (1) No single
failure in the test circuitry shall incapacitate an SSLC safety function. (2) No
single failure in the test circuitry shall cause an inadvertent scram, MSIV
isolation, or actuation of any safety systems served by the SSLC.]*
7.1.2.2 Reactor Protection (Trip) System (RPS)Instrumentation and Controls
(1)
(b)
(c)
(d) Detect conditions that threaten the fuel assembly or reactor coolant
pressure boundary from inputs derived from variables that are true,
direct measures of operational conditions.
(e)
(f)
If a single random failure can cause a control system action that causes
a plant condition that requires a reactor scram but also prevents action
7.1-11
Rev. 0
ABWR
by some RPS channels, the remaining portions of the RPS shall meet the
functional requirements (items a, b and c above), even when degraded
by a second random failure.
(h) Loss of one power supply shall neither directly cause nor prevent a
reactor scram.
(i)
(j)
(k)
Not used
(l)
No single failure within the RPS shall prevent proper RPS action when
required to satisfy Safety Design Bases as described by a, b, and c above.
7.1-12
(q)
(r)
Introduction
Rev. 0
ABWR
(s)
(b)
(c)
(ii)
(iii) Provision for manual control of the ECCS in the main control
room.
Specific Regulatory Requirements:
Specific regulatory requirements applicable to the instrumentation and
controls for the ECCS are shown on Table 7.1-2.
(2)
Introduction
7.1-13
Rev. 0
ABWR
None.
7.1.2.3.2 Leak Detection and Isolation System (LDS)Instrumentation and Controls
(1)
(b)
(c)
Provide an isolation control system which will ensure that isolation of the
containment and/or reactor vessel will occur once initiated.
(f)
(g)
7.1-14
Introduction
Rev. 0
ABWR
(b)
(c)
(b)
Sense wetwell and drywell pressure and permit manual system initiation
in order to provide condensation of steam in the wetwell and drywell air
volumes during a transient or accident event.
(c)
Manually control the wetwell and drywell spray subsystem in the main
control room.
(d) Indicate performance of the wetwell and drywell spray subsystem in the
main control room.
Specific Regulatory Requirements:
Specific regulatory requirements applicable to the containment spray system
are listed in Table 7.1-2.
(2)
Non-safety-Related Bases
None.
Introduction
7.1-15
Rev. 0
ABWR
(2)
(b)
7.1-16
Introduction
Rev. 0
ABWR
(b)
(2)
Introduction
7.1-17
Rev. 0
ABWR
(b)
(2)
7.1-18
Introduction
Rev. 0
ABWR
(2)
Provide alternate and diverse method for inserting control rods using
fine motion control rod drive (FMCRD) electric motors.
(b)
(c)
Provide assurance that the ARI shall be highly reliable and functional in
spite of a single failure.
(d) Provide assurance that the ARI shall operate when necessary (FMCRD
motors shall be connected to the emergency diesel generators).
(e)
Introduction
7.1-19
Rev. 0
ABWR
Enable the system to remove the residual heat (decay heat and sensible
heat) from the reactor vessel during normal shutdown.
(b)
Provide manual controls for the shutdown cooling system in the main
control room and at the remote shutdown panel.
(c)
(2)
Provide cooling for the reactor during the shutdown operation when the
vessel pressure is below approximately 931.63 kPa G.
(b)
Rev. 0
ABWR
(b)
Capability for subsequent cold shutdown of the reactor through the use
of suitable procedures.
Specific Regulatory Requirements:
Specific regulatory requirements applicable to the remote shutdown
system are listed in Table 7.1-2.
(2)
(2)
Introduction
7.1-21
Rev. 0
ABWR
The SRNM Subsystem shall generate a high neutron flux trip signal or a
short period trip signal that can be used to initiate scram in time to
prevent fuel damage resulting from anticipated or abnormal
operational transients.
(b)
(c)
Neutron sources and neutron detectors together shall result in a signalto-noise ratio of at least 2:1 and a signal count rate of at least three counts
per second with all control rods fully inserted in a cold unexposed core.
7.1-22
(a)
(b)
(c)
Rev. 0
ABWR
(d) Provide a continuous measure of the time rate of change of neutron flux
(reactor period) over the range from 100 s to () infinity and (+)
infinity to +10 s.
(e)
(f)
Generate rod block whenever the period exceeds the preset value.
(g)
Except for annunciators, the loss of a single power bus shall not disable
the monitoring and alarming functions of all the available monitors.
(2)
Introduction
7.1-23
Rev. 0
ABWR
(2)
Signals to the APRM that are proportional to the local neutron flux at
various locations within the rector core.
(b)
(c)
7.1-24
Introduction
Rev. 0
ABWR
(b)
(c)
(d) A simulated thermal power signal derived from each APRM channel
which approximates the dynamic effects of the fuel.
(e)
(f)
(2)
Introduction
(a)
(b)
(c)
Rev. 0
ABWR
(2)
(b)
Issue a rod block signal if the preset setpoint is exceeded by this signal
which is proportional to the average neutron flux level signal.
Monitor the gross radiation level in the main steamlines tunnel area and
in the ventilation discharge ducting of the primary and secondary
containment structures.
(b)
(c)
(d) Provide channel trip inputs to the RPS and LDS on high radiation in the
MSL tunnel area. If the protection system logic is satisfied, the following
shall be initiated:
(i)
Reactor scram.
(ii)
7.1-26
(e)
(f)
Rev. 0
ABWR
(g)
(2)
Provide channel trip inputs to the safety system and logic control (SSLC)
system for logic voting and subsequent initiation of protective actions.
(b)
(c)
(f)
(2)
Introduction
7.1-27
Rev. 0
ABWR
(2)
7.1-28
Introduction
Rev. 0
ABWR
(2)
Regulatory Requirements
Specific regulatory requirements applicable to those systems are listed in
Table 7.1-2.
Introduction
7.1-29
Rev. 0
ABWR
7.1-30
Associated circuits installed in accordance with IEEE 384, Section 5.5.2(1), are
subject to the requirements of Class 1E circuits for cable derating,
environmental qualification, flame retardance, splicing restrictions, and
raceway fill unless it is demonstrated that Class 1E circuits are not degraded
below an acceptable level by the absence of such requirements.
Introduction
Rev. 0
ABWR
(2)
The method of identification used (IEEE 384, Section 6.1.2) will preclude the
need to frequently consult any reference material to distinguish between Class
1E and non-Class 1E circuits, between non-Class 1E circuits associated with
different redundant Class 1E systems, and between redundant Class 1E
systems.
(3)
(4)
7.1-31
Rev. 0
ABWR
setpoints are within the instrument best accuracy range. The established setpoints
provide margin to satisfy both safety requirements and plant availability objectives.
7.1.2.10.10 Regulatory Guide 1.118Periodic Testing of Electric Power and Protection
Systems
The I&C systems are consistent with the requirements of Regulatory Guide 1.118, with
the following clarifications of the regulatory guide requirements:
(1)
(2)
Introduction
Rev. 0
ABWR
7.1-33
Rev. 0
ABWR
GESSAR II Design
ABWR Design
General
Comparisons for
All Safety
Systems:
Reactor
Protection
System (RPS):
Neutron monitoring system IRM trip. Neutron monitor SRNM (combined SRM
& IRM) trip.
Added total core flow rapid decrease trip
to NMS APRM trip.
Emergency Core
Cooling System
(ECCS):
LPCS: Division 1
7.1-34
Introduction
Rev. 0
ABWR
Table 7.1-1 Comparison of GESSAR II and ABWR I&C Safety Systems (Continued)
I & C System
GESSAR II Design
ABWR Design
Leak Detection
and Isolation
System (LD&IS):
MSPLCS deleted.
Flammability
Control System:
Independent system.
Standby Gas
Treatment
System:
Emergency
Diesel Generator
System:
Reactor Building
Cooling Water:
Containment
Atmospheric
Control System:
High Pressure
Nitrogen Gas
Supply:
Alternate Rod
Insertion (ARI)
Function:
(Not applicable)
Standby Liquid
Control System
(SLCS):
Introduction
7.1-35
Rev. 0
ABWR
Table 7.1-1 Comparison of GESSAR II and ABWR I&C Safety Systems (Continued)
I & C System
GESSAR II Design
ABWR Design
RHR/Shutdown
Cooling Mode:
Remote
Shutdown
System (RSS):
RCIC controls available at RSS panel RCIC controls replaced with HPCF
controls at RSS panel.
Safety Related
Display
Instrumentation:
Neutron
Monitoring
System (NMS):
Process
Radiation
Monitoring
System (PRMS):
Drywell Vacuum
Relief System:
Containment
Atmospheric
Monitoring
System (CAMS)
Suppression
4 thermocouples in each of the 4
Pool Temperature containment quadrants.
Monitoring
4 x 4 = 16 total T/Cs.
System:
7.1-36
Introduction
Applicable Criteria
Reference Standard
(RG, IEEE, ISA)
10CFR
50.55
GDC
2
10
12
13
15
16
19
20
21
22
23
24
25
28
29
33
34
35
38
41
44
ABWR
Introduction
279
X
X
X
Rev. 0
7.1-37
Applicable Criteria
Reference Standard
(RG, IEEE, ISA)
10CFR
50.55
GDC
2
10
12
13
15
16
19
21
22
23
24
25
28
29
33
34
35
38
41
44
279
RHR/Shutdown Cooling
Containment Atmospheric
Monitoring
X
X
X
X
X
X
X
X
X
X
X
X
Rev. 0
20
ABWR
7.1-38
Table 7.1-2 Regulatory Requirements Applicability Matrix for I&C Systems (Continued)
Introduction
3.23
1.23
3.22
3.21
3.18
3.15
3.13
II-K
RG 1.97
4.2
26
279
338
384
279
279
Reference Standard
(RG, IEEE, ISA)
II-F
X
X
Rev. 0
279
22
II-E
RG 1.22
21
20
279
II-D
RG 1.47
12
279
BTP
567.02 1.151
1.118
567.04 1.105
1.97
1.75
1.62
Applicable Criteria
1.22
Regulatory Guide
ABWR
Introduction
Table 7.1-2 Regulatory Requirements Applicability Matrix for I&C Systems (Continued)
7.1-39
3.23
3.22
3.21
RHR/Shutdown Cooling
X
X
Process Radiation
Monitoring
Containment Atmospheric
Monitoring
Suppression Pool
Temperature Monitoring
Rev. 0
Introduction
Control Systems
(Non-Class 1E)
3.18
3.15
3.13
1.23
II-K
RG 1.97
II-F
1
II-E
4.2
26
279
II-D
3
22
20
279
RG 1.22
12
279
21
3
279
567.02 1.151
1.118
338
567.04 1.105
1.97
1.75
BTP
RG 1.47
384
1.62
279
Reference Standard
(RG, IEEE, ISA)
1.22
Applicable Criteria
279
Regulatory Guide
ABWR
7.1-40
Table 7.1-2 Regulatory Requirements Applicability Matrix for I&C Systems (Continued)
Rev. 0
ABWR
SSLC LOGIC
DIVISION I
SELF-TEST PROGRAM
SSLC LOGIC
DIVISION II
SELF-TEST PROGRAM
SSLC LOGIC
DIVISION III
SELF-TEST PROGRAM
SSLC LOGIC
DIVISION VI
SELF-TEST PROGRAM
PROCESS
COMPUTER INTERFACE
PROCESS
COMPUTER INTERFACE
PROCESS
COMPUTER
SYSTEM
PROCESS
COMPUTER INTERFACE
PROCESS
COMPUTER INTERFACE
FIBER-OPTIC
TRANSMISSION
7.1-41
CLASS 1E
125 VDC
120 V CVCF
DIV.
SENSOR
I
TRIPS
II
TO
III
TLUs
DTM
DIV.
I
II
III
DTM
SENSOR
TRIPS
TO SLUs
1 & 2
DIV.
I
II
III
DTM
SENSOR
TRIPS
TO SLUs
3 & 4
PLANT
SENSOR
DATA
FROM
EMS I
DIV.
SENSOR
II
TRIPS
III
TO
IV
TLUs
DTM
TLU
DIV. I
DIV. II
DIV. III
SENSOR TRIPS
FROM DTMs IN
OTHER DIVISIONS
RPS
MSIV
TRIP OUTPUTS
TO LOAD DRIVERS/
SOLENOIDS
RPS
MSIV
TRIP OUTPUTS
TO LOAD DRIVERS/
SOLENOIDS
DIV.
I
III
DTM
SENSOR
TRIPS
TO SLUs
1 & 2
NBS(ADS)
RHR B
LDS
RCW
RSW
EPDS
D/G
SGTS
AC
HVAC
SENSOR TRIPS
FROM DTMs IN
OTHER DIVISIONS
RPS
MSIV
TRIP OUTPUTS
TO LOAD DRIVERS/
SOLENOIDS
SENSOR
TRIPS
TO SLUs
3 & 4
E
S
F
NBS(SRV)
HPCF B
LDS
HECW
E
S
F
2
I
III
IV
PLANT
SENSOR
DATA
FROM
EMS III
DIV.
SENSOR
I
TRIPS
II
TO
IV
ATMOSPHERIC CONTROL
DIESEL GENERATOR
ELECTRICAL POWER DISTRIBUTION SYSTEM
ENGINEERED SAFETY FEATURES
HVAC EMERGENCY COOLING WATER
HEATING, VENTILATING & AIR CONDITIONING
LEAK DETECTION & ISOLATION SYSTEM
MAIN STEAM ISOLATION VALVE
NUCLEAR BOILER SYSTEM
CLASS 1E
125 VDC
DTM
DTM
DIV.
I
II
TLUs
DIV. I
DIV. II
DIV. IV
RPS
LDS (MSIV)
SPTM
SENSOR TRIPS
FROM DTMs IN
OTHER DIVISIONS
RPS
MSIV
TRIP OUTPUTS
TO LOAD DRIVERS/
SOLENOIDS
SENSOR TRIPS
FROM DTMs IN
OTHER DIVISIONS
SENSOR
TRIPS
TO SLUs
1 & 2
SLU 1
RHR C
LDS
RCW
RSW
EPDS
D/G
SGTS
AC
SENSOR
TRIPS
TO SLUs
3 & 4
SLU 3
SLU 2
E
S
F
NBS(SRV)
HPCF C
HECW
SLU 4
E
S
F
2
DIV. I
DIV. II
DIV.
I
II
DTM
I
II
IV
DIV. IV
INITIATION / ISOLATION
OUTPUTS
TO EMS/ACTUATORS
NMS =
PRRM =
RCIC =
RCW =
RHR =
RPS =
RSW =
SGTS =
SPTM =
NOTES:
1. NMS AND PRRM (NOT SHOWN) ARE
STANDALONE SYSTEMS WITH
TRIP OUTPUTS TO RPS AND ESF
CONTROLLERS OF SSLC.
2. POWER SOURCES (PER DIVISION)
EMS:
CLASS 1E, 125 VDC
ESF 1/ESF 2: CLASS 1E, 125 VDC
RPS/MSIV:
CLASS 1E, 120 V CVCF
NMS/PRRM: CLASS 1E, 120 V CVCF
Fi
712 A i
t fI t f i
S f t S t
L i t SSLC C t ll
Figure 7.1-2
Assignment
of Interfacing
Safety
System
Logic to SSLC Controllers
Introduction
AC
=
D/G
=
EPDS =
ESF =
HECW =
HVAC =
LDS =
MSIV =
NBS =
120 V CVCF
INITIATION / ISOLATION
OUTPUTS
TO EMS/ACTUATORS
ABBREVIATIONS:
DTM = DIGITAL TRIP MODULE
EMS = ESSENTIAL MULTIPLEXING SYSTEM
SLU = SAFETY SYSTEM LOGIC UNIT
TLU = TRIP LOGIC UNIT
SLU 4
E
S
F
II
III
IV
TLU
SLU
4
E
S
F
NBS(SRV)
RCIC
LDS
HECW
INITIATION/ISOLATION OUTPUTS
TO EMS/ACTUATORS
SLU 3
SLU 2
DIV. I
DIV. III
DIV. IV
DIV.
I
III
DTM
SLU 1
RPS
LDS (MSIV)
SPTM
SENSOR TRIPS
FROM DTMs IN
OTHER DIVISIONS
DIV. III
SENSOR
TRIPS
TO SLUs
3 & 4
Rev. 0
DIV.
SENSOR
I
TRIPS
III
TO
IV
TLUs
TLU
DIV. I
DIV. III
DIV. IV
DIV. II
CLASS 1E
125 VDC
120 V CVCF
DTM
DIV. I
DIV.
II
III
DTM
SLU 3
SLU 2
DIV. II
DIV. III
DIV. IV
SENSOR TRIPS
FROM DTMs IN
OTHER DIVISIONS
DIV. IV
SENSOR
TRIPS
TO SLUs
1 & 2
SLU 1
NBS(ADS)
RHR A
LDS
RCW
RSW
EPDS
D/G
AC
HVAC
RPS
LDS (MSIV)
SPTM
DIV. II
DIV. III
DIV. IV
DIV.
II
III
DTM
TLU
RPS
LDS (MSIV)
SPTM
SENSOR TRIPS
FROM DTMs IN
OTHER DIVISIONS
PLANT
SENSOR
DATA
FROM
EMS II
CLASS 1E
125 VDC
120 V CVCF
ABWR
7.1-42
PLANT
SENSOR
DATA
FROM
EMS IV
Rev. 0
ABWR
120 VACtaken from the four divisional safety system logic and control
(SSLC) power supply buses discussed in Section 8.3. Each bus supplies power
for one division of RPS logic. Two of the four buses also provide 120 VAC
power through the two divisions of RPS scram logic circuitry to the A and B
solenoids of the scram hydraulic control units (HCUs) of the Control Rod
Drive System.
(2)
125 VDCtaken from two of the four divisional SSLC battery buses discussed
in Section 8.3. Each bus provides 125 VDC power through one of the two
divisions of RPS scram logic circuitry to the solenoid of one of the two air
header dump valves of the Control Rod Drive System.
SSLC power sources are shown in Figure 7.2-1. Scram and air header dump power
distribution is shown in Figure 7.2-8.
7.2-1
Rev. 0
ABWR
Sensor Channels
Equipment within a sensor channel includes primarily sensors (transducers or
switches), multiplexers and digital trip modules (DTMs). The sensors within
each channel monitor plant variables (Subsection 7.2.1.1.4.2) send either
analog or discrete output to remote multiplexer units (RMUs) within the
associated division of Essential Multiplexing System (EMS). Each division of
the EMS performs analog-to-digital conversion on analog signals and sends
the digital or digitized analog output values of all monitored variables to the
DTM within the associated RPS sensor channel. The DTM in each sensor
channel compares individual monitored variable values with trip setpoint
values and for each variable sends a separate, discrete (trip/no trip) output
signal to all four divisions of trip logics.
All equipment within a sensor channel is powered from the same division of
Class 1E power source. However, different pieces of equipment may be
powered from separate DC power supplies. Within a sensor channel, sensors
themselves may belong to the RPS or may be components of another system.
Signal conditioning and distribution performed by the RMUs is a function of
the EMS and is discussed in Section 7A.2.
7.2-2
Rev. 0
ABWR
(2)
(3)
7.2-3
Rev. 0
ABWR
scram solenoids and scram solenoid 120 VAC power source such that, when in
a tripped state, the load drivers will cause de-energization of the scram
solenoids (scram initiation). All load drivers within a division interconnect
with load drivers in all other divisions into two separate two-out-of-four scram
logic arrangements (Figure 7.2-8).
Normally closed relay contacts are arranged in the scram logic circuitry
between the air header dump valve solenoids and air header dump valve
solenoid 125 VDC power source such that, when in a tripped state (coil deenergized), the relays will cause energization of the air header dump valve
solenoids (air header dump initiation). All relays within a division
interconnect with relays in all other divisions into two separate two-out-of-four
air header dump logic arrangements (Figure 7.2-8).
(4)
(5)
7.2-4
(1)
(2)
(3)
Rev. 0
ABWR
(4)
(5)
(6)
(7)
(8)
Not Used
(9)
(b)
7.2-5
Rev. 0
ABWR
comprise the APRM trip logic output to the RPS. These conditions are
high neutron flux, high simulated thermal power, APRM inoperative,
oscillation power range monitor (ORPM) trip, reactor core flow rapid
coastdown. The specific condition within the NMS that caused the
APRM trip output is not detectable within the RPS.
(c)
(2)
Reactor Pressure
Reactor pressure is measured at four physically separated locations by
locally mounted pressure transducers. Each transducer is on a separate
instrument line and provides analog equivalent output through the EMS
to the DTM in one of four RPS sensor channels. The pressure
transducers and instrument lines are components of the NBS.
(b)
(c)
Drywell Pressure
Drywell pressure is measured at four physically separated locations by
locally mounted pressure transducers. Each transducer is on a separate
instrument line and provides analog equivalent output through the EMS
to the DTM in one of the four RPS sensor channels of the NBS.
Rev. 0
ABWR
(3)
(4)
(5)
Not Used
(6)
(b)
7.2-7
Rev. 0
ABWR
Manual Scram
Two manual scram switches or the reactor mode switch provide the
means to manually initiate a reactor scram independent of conditions
within the sensor channels, divisions of trip logics and divisions of trip
actuators. Each manual scram switch is associated with one of the two
divisions of actuated load power.
In addition to the scram initiating variables monitored by the RPS, one
bypass initiating variable is also monitored.
7.2-8
Rev. 0
ABWR
(3)
(4)
7.2-9
Rev. 0
ABWR
A non-coincident NMS trip will occur in each division of trip logic when any
single APRM or SRNM trip signal is received from the NMS. The noncoincident NMS trip is automatically bypassed when the reactor is in the run
mode. When the reactor is in the shutdown, refuel or startup mode, the noncoincident NMS trip can be manually bypassed in each division by a separate,
manual, keylock non-coincident NMS trip disable switch.
Main Steamline Isolation Trip (Figure 7.2-4)
A MSL isolation trip will occur in each division of trip logic when either the
inboard or outboard MSL isolation valve is closed in any two or more
unbypassed sensor channels. When the reactor is in the shutdown, refuel or
startup mode, the MSL isolation trip function is automatically bypassed in
each division of trip logic when reactor pressure in the associated sensor
channel is below the bypass setpoint. This bypass permits plant operation
when the MSIVs are closed during low power operation.
Low Control Rod Drive (CRD) Charging Header Pressure Trip (Figure 7.2-6)
A low CRD charging header pressure trip will occur in each division of trip
logic when CRD charging header pressure is low in any two or more
unbypassed sensor channels. This bypass is allowed only whenever the reactor
mode switch is either in Shutdown or Refuel mode position. When the
reactor is in the shutdown or refuel mode, the low CRD charging header
pressure trip can be manually bypassed in each division of trip logic by
separate, manual, keylock CRD charging header pressure trip bypass switches.
This bypass allows RPS reset after a scram while CRD charging header pressure
is below the trip setpoint. Each division of trip logic sends a separate rod
withdraw block signal to the RC&IS when this bypass exists in the division.
Turbine Stop Valve Closed and Turbine Control Valve Fast Closure Trips
(Figure 7.2-3)
A turbine stop valve closed trip will occur in each division of trip logic when
the turbine stop valve is closed in any two or more unbypassed sensor
channels. A turbine control valve fast closure trip will occur in each division of
trip logic when either the fast acting solenoid valve is closed or the HTS oil
pressure is below the trip setpoint in any two or more unbypassed sensor
channels. Both of these trips are automatically bypassed in each division of trip
logic when turbine first-stage pressure in the associated sensor channel is
below the bypass setpoint. Each division of trip logic sends a separate recirc
pump trip initiating signal to the recirc system when these trips occur in the
division.
7.2-10
Rev. 0
ABWR
Manual Scram
A sealed-in manual scram of all HCUs and associated control rods will occur
when both manual scram pushbuttons are armed and depressed or when the
reactor mode switch is placed in the shutdown position. Depressing only one
armed scram pushbutton will result in a sealed-in half scram (de-energization
of one division of actuated loads). The scram initiating input received from
the mode switch shutdown contacts is automatically bypassed after a sufficient
time delay (10 s) to allow for scram seal-in and full insertion of all control rods.
7.2-11
Rev. 0
ABWR
Reset Logic
A single, manual, three-position, toggle switch provides means to reset the
manual scram seal-in circuitry in both divisions of manual scram controls. If
either of the manual scram pushbuttons is still depressed when a reset is
attempted, the reset will not have any effect.
A separate, manual, pushbutton associated with each division of trip actuators
provides means to reset the seal-in at the input of all trip actuators in the same
division. If the conditions that caused the division trip have not cleared when
a reset is attempted, the reset will not have any effect. After a single division
trip, reset is possible immediately; however, if a full scram has occurred, reset
is inhibited for 10 seconds to allow sufficient time for scram completion.
As a consequence of a full scram, the CRD charging header pressure will drop
below the trip setpoint, resulting in a trip initiating input to all four divisions
of trip logic. While this condition exists, reset of the manual scram circuitry is
possible; however, the four divisions of trip logic cannot be reset until the CRD
charging pressure trip is manually bypassed in all four divisions and all other
trip initiating conditions have cleared.
Rev. 0
ABWR
each RPS variable with separate redundant logic and wiring, the RPS has been protected
from a credible single failure. For additional information on redundancy of RPS
subsystems, refer to Subsection 7.2.1.1.4.2. For information on the protection provided
within SSLC and RPS against common-mode failure of the redundant channels, refer
to Appendix 7C.
Redundancy of the RPS logic power supply is provided. There are four Class 1E
uninterruptible power sources which supply electrical power, one to each division of the
RPS. A loss of one power supply will neither inhibit protective action nor cause a scram.
7.2.1.1.4.5 Actuated Devices
The devices actuated by the RPS trip and scram logic include the 120 VAC powered A
and B scram solenoids of the HCUs and the 125 VDC powered air header dump valves.
The A solenoids of the HCUs are energized by one division of power and the B
solenoids by another division of power. When any single RPS division is in a tripped
state or when only one of the manual scram pushbuttons is depressed, all of either the
A or the B solenoids will be de-energized, resulting in a half-scram condition. A full
scram of the pair of control rods associated with a particular HCU will occur when both
the A and B solenoid of the HCU are de-energized. The HCUs and associated control
rod pairs are divided into four groups. The RPS supplies power to each group from
separate RPS power distribution circuits. The combination of control rods within each
group is such that hot shutdown can be achieved even in the event of failure to scram
of an entire rod group.
The solenoid of one of the air header dump valves is energized by one division of power
and the solenoid of the other air header dump valve is energized by another division of
power. When the solenoid of either of the air header dump valves is energized, the air
header will be released, resulting in insertion of all control rods. The arrangement of
RPS power distribution circuits and actuated devices is shown in Figure 7.2-1.
7.2.1.1.4.6 Separation
Four independent sensor channels monitor the various process variables listed in
Subsection 7.2.1.1.4.2. The redundant sensor devices are separated so that no single
failure can prevent a scram. The arrangement of RPS sensors mounted in local racks is
shown in Figure 7.2-2. Locations for local RPS racks and panels are shown on the
instrument location drawings provided in Section 1.7. Divisional separation is also
applied to the Essential Multiplexing System (EMS), which provides data highways for
the sensor input to the logic units. Physically separated cabinets are provided for the
four scram logics. Fiber-optic cable routing from remote multiplexing units (RMUs) to
control room equipment is shown in raceway plans provided by reference in
Section 1.7. The criteria for separation of sensing lines and sensors are discussed in
Section 7.1.
Reactor Protection (Trip) System (RPS)Instrumentation and Controls
7.2-13
Rev. 0
ABWR
The mode switch, low CRD accumulator charging pressure trip and other selected
bypass switches scram reset switches and manual scram switches are all mounted on the
principal control console. Each device is mounted in a metal enclosure and has a
sufficient number of barrier devices to maintain adequate separation between
redundant portions of the RPS.
The outputs from the logic cabinets to the scram pilot solenoids are run in separate
rigid conduits with no other wiring. The four wire ways match the four scram groups
shown in Figure 7.2-8. The groups are selected so that the failure of one group to scram
will not prevent a reactor shutdown. The scram group conduits have unique
identification and are separately routed as Division II and III conduits for the A and B
solenoids of the scram pilot valves, respectively. This corresponds to the divisional
assignment of their power sources.
Signals which must run between redundant RPS divisions are electrically/physically
isolated by isolators to provide separation.
RPS inputs to annunciators, recorders, and the computer are arranged so that no
malfunction of the annunciating, recording, or computing equipment can functionally
disable the RPS. Direct signals from RPS sensors are not used as inputs to annunciating
or data-logging equipment. Electrical isolation is provided between the primary signal
and the information output by fiber-optic cable interfaces.
7.2.1.1.5 Environmental Considerations
Electrical equipment for the RPS is located in the drywell, control structure,
containment, and in the Turbine Building. The environmental conditions for these
areas are shown in Section 3.11.
7.2.1.1.6 Operational Considerations
7.2.1.1.6.1 Reactor Operator Information
(1)
Indicators
Scram group indicators extinguish when an actuator logic prevents output
current from the 120 VAC power source to the scram pilot valve solenoid
associated with the actuator logic.
Recorders (which are not part of the RPS) in the main control room also
provide information regarding reactor vessel water level, and reactor power
level.
(2)
7.2-14
Annunciators
Rev. 0
ABWR
Each RPS trip channel input is provided to the Containment Cooling System
(CCS) annunciator system through isolation devices. Trip logic trips, manual
trips, and certain bypasses also signal the annunciator system.
All RPS instrument channel trips shall initiate an annunciation of the variable,
causing the trip in the control room to alert the plant operator of a trip
condition. The final output trips for each RPS division shall have separate
single annunciation of the tripped condition of each RPS division. All
bypassed RPS instrument channels or division logics whose bypassed
condition is not a normal condition of operation shall also be annunciated. As
an annunciator system input, a channel trip also sounds an audible alarm
which can be silenced by the operator. The annunciator window lights latch
in until reset manually. Reset is not possible until the condition causing the
trip has been cleared.
(3)
Computer Alarms
A computer printout identifies each tripped channel; however, status
indication at the RPS trip channel device may also be used to identify the
individual sensor that tripped in a group of sensors monitoring the same
variable.
Upon detection of a status change of any of the preselected sequential events
contacts, the sequence-of-events log shall be initiated and shall signal the
beginning of an event. This log will include both NSSS and BOP inputs.
Changes of state received 5 milliseconds or more apart are sequentially
differentiated on the printed log, together with time of occurrence, which
shall be printed in hours, minutes, seconds, and milliseconds. Use of the alarm
typewriter and computer is not required for plant safety. The printout of trips
is particularly useful in routinely verifying the correct operation of pressure,
level, and valve position switches as trip points are passed during startup,
shutdown, and maintenance operations.
SHUTDOWN
7.2-15
Rev. 0
ABWR
(2)
(a)
(b)
(c)
REFUEL
Enables same trip bypasses and NMS trip functions as shutdown mode.
(3)
STARTUP
Enables same trip and bypass functions as REFUEL mode except when
CRD charging pressure trip bypass is disabled.
(4)
RUN
Disables all trip bypasses enabled by any of the other three modes.
Disables SRNM trip and non-coincident NMS trip and deselects lower
NMS neutron flux trip setpoint.
Mode switch position is also provided for use by other systems, including NMS, RC&IS
and LDS.
7.2.1.1.7 Setpoints
Instrument ranges are chosen to cover the range of expected conditions for the variable
being monitored. Additionally, the range is chosen to provide the necessary accuracy
for any required setpoints and to meet the overall accuracy requirements of the
channel.
(1)
7.2-16
Rev. 0
ABWR
(2)
(3)
(4)
7.2-17
Rev. 0
ABWR
(6)
(7)
(8)
7.2-18
Rev. 0
ABWR
minimize the possibility of fuel damage and to reduce energy transfer from
the core to the coolant. The drywell high-pressure scram setting is selected to
be as low as possible without inducing spurious scrams.
(9)
7.2-19
Rev. 0
ABWR
7.2-20
Conditions
Rev. 0
ABWR
Variables
The generating station variables which are monitored cover the protective
action conditions that are identified in Subsection 7.2.1.1.4.2.
(3)
Sensors
A minimum number of LPRMs per APRM are required to provide adequate
protective action. This is the only variable that has spatial dependence
(IEEE-279, Paragraph 3.3).
(4)
Operational Limits
Operational limits for each safety-related variable trip setting are selected with
sufficient margin to avoid a spurious scram. It is then verified by analysis that
the release of radioactive material following postulated gross failure of the fuel
or the reactor coolant pressure boundary is kept within acceptable bounds.
Design basis operational limits in Chapter 16 are based on operating
experience and constrained by the safety design basis and the safety analyses.
(5)
(6)
(7)
7.2-21
Rev. 0
ABWR
generators, the fourth division alternate power originates from the first
division diesel.
Environmental conditions for proper operation of the RPS components are
covered in Section 3.11 for inside and outside the containment.
(8)
Unusual Events
Unusual events are defined as malfunctions or accidents and other events
which could cause damage to safety systems. Chapter 15 (Accident Analyses)
describes the following credible accidents and events: floods, storms,
tornados, earthquakes, fires, LOCA, pipe break outside the containment, and
feedwater line break. A discussion of each of these events, as applicable to the
subsystems of the RPS, follows:
(a)
Floods
The buildings containing RPS components have been designed to meet
the probable maximum flood (PMF) at the site location. This ensures
that the buildings will remain watertight under PMF; therefore, none of
the RPS functions are affected by flooding. Internal flooding sources are
covered in Section 3.4.
(b)
(c)
Earthquakes
The structures containing RPS components, except the turbine
building, have been seismically qualified (Sections 3.7 and 3.8) and will
remain functional during and following a safe shutdown earthquake
(SSE). Since reactor high pressure and power trips are diverse to the
turbine scram variables, locating these sensors in the turbine enclosure
does not compromise the ability of the RPS to provide protective action
when required.
(d) Fires
To protect the RPS in the event of a postulated fire, the RPS trip logics
are contained within the four separate independent SSLC cabinets. The
separation of the cabinets and their individual steel construction assures
7.2-22
Rev. 0
ABWR
that the RPS functions will not be prevented by a postulated fire within
any of the divisional panels. Incombustible or fire retardant materials
are used as much as possible. The use of separation and fire barriers
ensures that even though some portion of the system may be affected,
the RPS will continue to provide the required protective action (Section
9.5).
(e)
LOCA
The following subsystem components are located inside the drywell and
would be subjected to the effects of a design basis LOCA:
(i)
(ii)
(iii) Reactor vessel pressure and reactor vessel water level instrument
taps and sensing lines which terminate outside the drywell; and
drywell pressure taps
These items have been environmentally qualified to remain functional during
and following a LOCA as discussed in Section 3.11.
(f)
(g)
Feedwater Break
This condition will not affect the RPS.
(h) Missiles
Missile protection is described in Section 3.5.
(9)
Performance Requirements
The minimum performance requirements are provided in Chapter 16.
A logic combination (two out of four) of instrument channel trips actuated by
abnormal or accident conditions will initiate a scram and produce
independent logic seal-ins within each of the four logic divisions. The trip
conditions will be annunciated and recorded on the process computer. The
trip seal-in will maintain a scram signal condition at the CRD System terminals
until the trip channels have returned to their normal operating range and the
seal-in is manually reset by operator action. Thus, once a trip signal is present
long enough to initiate a scram and the seal-ins, the protective action will go
to completion.
7.2-23
Rev. 0
ABWR
(2)
7.2-24
Rev. 0
ABWR
scram. For turbine generator trips, the stop valve closure scram and turbine
control valve fast closure scram provide a greater margin to the nuclear system
pressure safety limit than does the high pressure scram. Chapter 15 identifies
and evaluates accidents and abnormal operational events that result in
nuclear system pressure increases. In no case does pressure exceed the RCPB
safety limit.
(3)
(4)
7.2-25
Rev. 0
ABWR
(5)
(6)
(b)
7.2-26
Rev. 0
ABWR
(7)
7.2-27
Rev. 0
ABWR
The RPS logic circuit is designed so that an automatic scram will be initiated
when the required number of sensors for any monitored variable exceeds the
scram setpoint.
Separate racks are provided for the RPS instrumentation for each division and
are installed in different locations.
(8)
Rev. 0
ABWR
The number of operable channels for the essential monitored variables is given in
Table 7.2-2. The minimums apply to any untripped trip system. A tripped trip system
may have any number of inoperative channels. Because reactor protection
requirements vary with the mode in which the reactor operates, the table shows
different functional requirements for the RUN and STARTUP modes. These are the
only modes where more than one control rod can be withdrawn from the fully inserted
position.
In case of a loss-of-coolant accident, reactor shutdown occurs immediately following the
accident as process variables exceed their specified setpoint. Operator verification that
shutdown has occurred may be made by observing one or more of the following
indications:
(1)
(2)
(3)
The pressure in the hydraulic oil lines to the control valves drops and pressure
sensors signal the RPS to scram. At the same time, the turbine logic pressure
controller initiates fast opening of the turbine bypass valves to minimize the
pressure transient. Turbine stop valve closure and turbine control valve fast
closure initiates the recirculation pump trip (RPT) logic, which trips the
recirculation pumps at power levels greater than 40%.
(5)
The reactor will scram unless the unit load is less than some preselected value
(typically 40%), below which the control valve fast closure pressure transient
does not threaten the fuel thermal limits.
(6)
7.2-29
Rev. 0
ABWR
(2)
7.2-30
Rev. 0
ABWR
(c)
(3)
(4)
7.2-31
Rev. 0
ABWR
(6)
(7)
Rev. 0
ABWR
(2)
(3)
(4)
(5)
7.2-33
Rev. 0
ABWR
(6)
(7)
(8)
(9)
Rev. 0
ABWR
coolant pressure boundary. Any monitored variable which exceeds the scram
setpoint will initiate an automatic scram and not impair the remaining
variables from being monitored (i.e., if one channel fails, the remaining
portions of the RPS will function).
(12) Criterion 29Protection Against Anticipated Operational Occurrences
The system will initiate a reactor scram in the event of anticipated operational
occurrences.
7.2.2.2.3 Conformance to Industry Codes and Standards
7.2.2.2.3.1 IEEE-279, Protection Systems for Nuclear Power Generating Stations
The Reactor Protection (trip) System conforms to the requirements of this standard.
The following is a detailed discussion of this conformance.
(1)
(2)
(3)
(4)
7.2-35
Rev. 0
ABWR
(6)
(7)
7.2-36
Rev. 0
ABWR
Multiple failures resulting from a single credible event could cause a control
system action (closure of the turbine stop or control valves) resulting in a
condition requiring protective action and concurrent prevention of operation
of a portion of the RPS (scram signal from the turbine stop or control valves)
[Subsection 7.2.1.1.4.2(6)]. The reactor vessel high-pressure and high-power
trips provide diverse protection for this event.
(8)
(b)
(c)
(ii)
(ii)
(f)
Other variables that could affect the RPS scram function itself, are thus
monitored to induce scram directly include:
(g)
7.2-37
Rev. 0
ABWR
Rev. 0
ABWR
Most sensors have a provision for actual testing and calibration during reactor
operation. The exceptions are defined as follows:
(a)
During plant operation, the operator can confirm that the MSIV and
turbine stop valve limit switches operate during valve motion. Precise
calibration of these sensors requires reactor shutdown.
(b)
(c)
7.2-39
Rev. 0
ABWR
Transmitters are normally tested during reactor operation by crosscomparison of channels. However, transmitters, level switches, and pressure
switches may be valved out of service and returned to service under
administrative control procedures. Since only one sensor is valved out of
service at any given time during the test interval, protective capability for the
RPS trip variables is maintained through the remaining redundant instrument
channels.
(12) Operating Bypasses (Paragraph 4.12)
The following RPS trip variables have no provision for an operating bypass:
(a)
(b)
(c)
(f)
(g)
7.2-40
Rev. 0
ABWR
For each of these operating bypasses, separate signals are provided from the
mode switch to each division of RPS logic to assure that all of the protection
system criteria are satisfied.
An operating bypass of the turbine stop valve and control valve fast closure trip
is provided whenever the turbine is operating at a low initial power level (i.e.,
with the mode switch in SHUTDOWN, REFUEL, or STARTUP positions). The
purpose of the bypass is to permit the RPS to be placed in its normal energized
state for operation at low-power levels with the turbine stop valves not fully
open.
Special provision has been made to effect bypass of any one of the four MSIV
closure RPS trip channels. This permits flexibility for testing and allows
continued reduced power operation in the event of possible malfunction of
the MSIVs such that up to two of the four steamlines can be closed off, for test
purposes or otherwise, without resulting in a full reactor scram condition,
provided the load has been reduced to limit reactor pressure and steam flow.
The remaining three main steamlines automatically revert to two-out of-three
logic such that closure of a second MSIV will result in a half-scram condition.
This special bypass of any one channel will be automatically removed if a
sensor channel bypass (described in Subsection 7.2.2.2.3.1(11) is imposed on
any other channel.
In general, whenever the applicable conditions for instrumentation scram
bypasses are not met, the RPS shall automatically accomplish one of the
following:
(a)
(b)
(c)
7.2-41
Rev. 0
ABWR
channel bypasses are indicated by lights for each division on the main control
room panels.
(14) Access to Means for Bypassing (Paragraph 4.14)
All instrumentation valves associated with the individual RPS trip and bypass
sensors are either locked open or locked closed, depending upon their
normal state. The operator has administrative control of the sensor
instruments and valves.
All manual bypasses (previously discussed) are controlled by keylock switches
under administrative control of the operator. The mode switch itself is keylock
operative, since its position affects the operating bypass logic.
(15) Multiple Setpoints (Paragraph 4.15)*
All RPS trip variables are fixed except for the following, which are individually
addressed.
The trip setpoint of each SRNM channel is generally fixed. However, there is
also the scram initiated by intermediate high neutron flux level corresponding
to 5E + 5 counts per second. This is only activated in a noncoincidence scram
mode by a switch in the RPS SSLC cabinet. The conditions under which such
trip is to be activated are included in plant operating procedures.
In the RUN mode, the APRM System simulated thermal-power trip varies
automatically with recirculation flow (Section 7.6).
In modes other than RUN, the APRM setdown function automatically selects
a more restrictive scram trip setpoint at a fixed 15%. The devices used to
prevent improper use of the less restrictive setpoints are designed in
accordance with criteria regarding performance and reliability of protection
system equipment.
Operation of the mode switch from one position to another bypasses various
RPS trips and channels and automatically alters NMS trip setpoints in
accordance with the reactor conditions implied by the given position of the
mode switch. All equipment associated with these setpoint changes are
considered part of the protection system and are qualified Class 1E
components.
(16) Completion of Protective Action Once it is Initiated (Paragraph 4.16)
Rev. 0
ABWR
It is only necessary that the process sensors remain in a tripped condition for
a sufficient length of time to trip the digital trip modules and operate the sealin circuitry, provided the two-out-of-four logic is satisfied. Once this action is
accomplished, the trip actuator logic proceeds to initiate reactor scram
regardless of the state of the process sensors that initiated the sequence of
events. The same holds true for the manual scram pushbuttons.
(17) Manual Actuation (Paragraph 4.17)
Two manual scram pushbutton controls are provided on the principal control
room console to permit manual initiation of reactor scram at the system level.
Both switches must be depressed to initiate a scram. Backup to these manual
controls is provided by the SHUTDOWN position of the reactor system mode
switch. Failure of the manual scram portion of the RPS cannot prevent the
automatic initiation of protective action, nor can failure of an automatic RPS
function prevent the manual portions of the system from initiating the
protective action.
No single failure in the manual or automatic portions of the system can
prevent either a manual or automatic scram.
(18) Access to Setpoint Adjustments, Calibration, and Test Points (Paragraph 4.18)
The RPS design permits the administrative control of access to all setpoint
adjustments, module calibration adjustments and testpoints. These
administrative controls are supported by provisions within the safety system
design, by provisions in the generating station design, or by a combination of
both.
(19) Identification of Protective Actions (Paragraph 4.19)
When any one of the redundant sensor trip modules exceeds its setpoint value
for the RPS trip variables, a main control room annunciator is initiated to
identify the particular variable. In the case of NMS trips to the RPS, the
specific variable or variables that exceed setpoint values are identified as a
function of the NMS.
Identification of the particular trip channel exceeding its setpoint is
accomplished as a typed record from the process computer system.
When any manual scram pushbutton is depressed, a main control room
annunciation is initiated and a process computer system record is produced
to identify the tripped RPS trip logic.
7.2-43
Rev. 0
ABWR
(b)
(c)
7.2-44
Rev. 0
ABWR
and identify the contained logic channels. Redundant racks are identified by
the identification marker plates of instruments on the racks.
7.2.2.2.3.2 Conformance to Other IEEE Standards
(1)
(2)
(2)
(3)
(4)
7.2-45
Rev. 0
ABWR
(2)
(3)
(4)
(5)
Turbine Trip
Initiation of turbine trip by the turbine system closes the turbine stop valves
initiating a reactor scram. The stop valve closure scram anticipates a reactor
pressure or power scram due to turbine stop valves closure. Any additional
increase in reactor vessel pressure will be prevented by the SRVs, which will
open to relieve reactor vessel pressure and close as pressure is reduced. The
RCIC and HPCF System will automatically actuate and provide vessel makeup
water if low water level occurs.
7.2-46
Rev. 0
ABWR
7.2-47
Rev. 0
ABWR
010.3 MPa G
Pressuretransmitter/trip
module
Drywell high
pressure
00.036 MPaG
Pressuretransmitter/trip
module
Reactor vessel
low water
Level 3
00.033 MPa G
Leveltransmitter/trip
module
Pressure
transmitter/
trip module
Turbine stop
valve closure
Fully open
to
fully closed
Position switch
Turbine control
valve fast closure
010.98 MPa G
Pressureswitch
Main steamline
isolation valve
closure
Fully open
to
fully closed
Positionswitch
Neutron Monitoring
System
APRM or SRNM
Trip/No Trip
Main steamline
high radiation
0.01-104mGy/h
Gamma
detector
4 to 110C
Temperaturetransmitter/trip
module
Turbine first-stage
pressure
7.2-48
Pressuretransmitter/
trip module
Rev. 0
ABWR
# Sensors
(SRNM)*
4
10
64
7.2-49
ABWR
7.2-50
DIV II
DIV IV
CHARGER
CHARGER
480V
120V
480V
120V
RECTIFIER
STATIC SW
INVERTER
STATIC SW
SSLC
BUS
G1
TO AIR
HEADER
DUMP "A"
VALVE
120 VAC
RECTIFIER
STATIC SW
TO AIR
HEADER
DUMP "B"
VALVE
INVERTER
STATIC SW
SSLC
BUS
H1
Rev. 0
120 VAC
125
VDC
120 VAC
SSLC
BUS
TO SSLC DIVIV
LOGIC SUPPLY
FOR: RPS, MSIV
Figure 7.2-1 ABWR SSLC Control Power Scheme (See also Figure 8.3-3)
INVERTER
STATIC SW
J1
120 VAC
TO SSLC DIVI
LOGIC SUPPLY
FOR: RPS, MSIV
125
VDC
RECTIFIER
STATIC SW
INVERTER
STATIC SW
F1
480V
120V
125
VDC
RECTIFIER
STATIC SW
CHARGER
480V
120V
125
VDC
SSLC
BUS
CHARGER
DIVISION W OF
TRIP ACTUATORS
(TYPICAL OF
TWO DIVISIONS)
(TYPICAL OF ALL
FOUR DIVISIONS)
ABWR
DIV X SSLC
120 VAC BUS
DIV X SSLC
125 VDC BUS
REACTOR MODE
DIV W
MANUAL SWITCHES
ANALOG
TRANSDUCERS
NON-COINCIDENT
NMS DISABLE
CRD CHARGING HEADER
PRESSURE TRIP BYPASS
DIGITAL
TRANSDUCERS
AND/OR
SWITCHES
ANALOG
TRANSDUCERS
DIGITAL
TRANSDUCERS
AND/OR
SWITCHES
CHAN w TRIPS
R
M
U
M
U
X
D
T
M
TO DIV X TLU
(CHAN w TRIPS)
TO DIV Y TLU
(CHAN w TRIPS)
TO DIV Z TLU
(CHAN w TRIPS)
TO COMPUTER,
RECORDERS,
DISPLAYS, ETC.
= ISOLATED INTERCONNECTION
= MULTIPLE INTERCONNECTION
TRIPS FROM
NMS DIV W
TRIPS FROM
NMS DIV X
TRIPS FROM
NMS DIV Y
TRIPS FROM
NMS DIV Z
CHANNEL
BYPASSES
T
L
U
MANUAL
SCRAM
RESET
SWITCH
M
L
U
TO TWO OF ACTs
(AHD A VALVE POWER)
TO ANNUNCIATORS,
COMPUTER, ETC.
TO DIV Y MLU
(SCRAM AND RESET)
TO OTHER SYSTEMS
FROM ONE ACT
(REACTOR MODE,
(RESET PERMISSIVE)
RPS STATUS, ETC.)
TO ANNUNCIATORS,
COMPUTER, ETC.
DIV W
TRIP
B
P
U
TO TWO OF ACTs
(A SOLENOID POWER)
TO DIV Y SLU
(SHUTDOWN SCRAM)
DIV W
MANUAL SWITCHES
TLU BYPASS
SENSORS BYPASS
MSLI SPECIAL BYPASS
TO DIV X TLU
(REACTOR MODE)
TO DIV Y TLU
(REACTOR MODE)
TO DIV Z TLU
(REACTOR MODE)
SHUTDOWN SCRAM
TO DIV X BPU
(BYPASS PERMISSIVES)
TO DIV Y BPU
(BYPASS PERMISSIVES)
TO DIV Z BPU
(BYPASS PERMISSIVES)
TO ANNUNCIATORS,
COMPUTER, ETC.
O
L
U
A
C
T
TO A OR B SOLENOIDS
FOR TWO ROD GROUPS
(SCRAM SOLENOID POWER)
TO ALL OTHER ACTs
(SCRAM SOLENOID POWER)
TO ONE AHD VALVE
OR ALL OTHER ACTs
(AHD VALVE POWER)
TO ANNUNCIATORS,
COMPUTER, ETC.
TO ANNUNCIATORS,
COMPUTER, ETC.
MANUAL TRIP
TRIP RESET
RESET PERMISSIVE
7.2-51
REACTOR
MODE
SWITCH
MANUAL
SCRAM A
SWITCH
Rev. 0
SENSOR CHANNEL W
(TYPICAL OF ALL FOUR CHANNELS)
DIVISION OF
MANUAL CONTROLS
Rev. 0
ABWR
Rev. 0
ABWR
CHANNEL A LOGIC
MAIN STEAM LINE ISOLATION TRIP SPECIAL BYPASS
(TYPICAL OF ALL FOUR CHANNELS)
3/4
7.2-53
Rev. 0
ABWR
DIVISION
DIVISION
DIVISION
DIVISION
1
2
3
4
APRM/OPRM
APRM/OPRM
APRM/OPRM
APRM/OPRM
NOT TRIPPED
NOT TRIPPED
NOT TRIPPED
NOT TRIPPED
3/
4
NMS DIVISION I
COINCIDENT NOT
TRIPPED
DIVISION
DIVISION
DIVISION
DIVISION
1
2
3
4
SRNM
SRNM
SRNM
SRNM
NOT TRIPPED
NOT TRIPPED
NOT TRIPPED
NOT TRIPPED
3/
4
DIVISION
DIVISION
DIVISION
DIVISION
1
2
3
4
DIVISION
DIVISION
DIVISION
DIVISION
1
2
3
4
SRNM
SRNM
SRNM
SRNM
NMS DIVISION I
NON-COINCIDENT
NOT TRIPPED
NOT TRIPPED
NOT TRIPPED
NOT TRIPPED
NOT TRIPPED
Figure 7.2-5 Division 1 Trip Logic Coincident and Non-Coincident NMS Trips
7.2-54
Rev. 1
ABWR
7.2-55
Rev. 0
ABWR
7.2-56
A SOLENOIDS
GROUP 1 HCUs
GROUP 2 HCUs
GROUP 3 HCUs
GROUP 4 HCUs
B SOLENOIDS
B SOLENOIDS
B SOLENOIDS
B SOLENOIDS
d
B
SSLC DIV II
125 VDC
BUS RETURN
7.2-57
Figure 7.2-8 SCRAM Solenoids and Air Header Dump Valves Power Distribution
Rev. 0
A SOLENOIDS
A SOLENOIDS
A SOLENOIDS
ABWR
SSLC DIV II
125 VDC BUS
SSLC DIV II
120 VAC BUS
Rev. 0
ABWR
7.2-58
Rev. 0
ABWR
(2)
(3)
(4)
(5)
(6)
(7)
Reactor Building Cooling Water (RCW) System and Reactor Service Water
(RSW) System
(8)
(9)
(2)
(3)
7.3-1
Rev. 0
ABWR
(4)
The purpose of ECCS instrumentation and controls is to sense the need for ECCS
action and to initiate appropriate response from the system in the event of an accident
requiring its action.
The ECCS instrument channels detect a need for core cooling systems operation, the
logic makes appropriate decisions, and the trip actuators initiate the appropriate
equipment operation.
7.3.1.1.1.1 High Pressure Core Flooder System Instrumentation and Controls
(1)
System Identification
The I&C components for the HPCF System, except as noted in this subsection,
are located outside the drywell. Pressure and level transducers used for HPCF
initiation are part of the Nuclear Boiler System and are located on racks
outside the drywell. The system is arranged to allow a design flow functional
test during normal reactor power operation. The piping and instrumentation
diagram (P&ID)is shown in Section 6.3 and the interlock block diagram
(IBD)is shown on Figure 7.3-1.
(2)
(3)
Equipment Design
The HPCF System is designed to operate from preferred offsite power sources
or from the Division 2 and 3 diesel generators if offsite (preferred) power is
not available.
(a)
Initiating Circuits
Reactor vessel low water level is monitored by four level transmitters
(one in each of the four electrical divisions) that sense the difference
between the pressure due to a constant reference leg of water and the
pressure due to the actual height of water in the vessel. Each level
transmitter provides an input to local multiplexer units which perform
signal conditioning and analog-to-digital conversion. The formatted,
digitized sensor input is multiplexed with other sensor signals over an
7.3-2
Rev. 0
ABWR
optical fiber data link to the logic processing units in the main control
room. All four transmitter signals are fed into the two-out-of-four logic
for each of the two divisions (II & III). The initiation logic for HPCF
sensors is shown in Figure 7.3-1.
Drywell pressure is monitored by four pressure transmitters in the same
four-division configuration described above. Instrument sensing lines
that terminate outside the drywell allow the transmitter to communicate
with the drywell interior. Each drywell high-pressure trip channel
provides an input into two-out-of-four trip logic shown in Figure 7.3-1.
The HPCF System is initiated on receipt of a reactor vessel low water
level signal (Level 1.5) or drywell high-pressure signal from the trip
logic. The HPCF System reaches its design flow rate within 36 seconds of
receipt of initiation signal. Makeup water is discharged to the reactor
vessel until the reactor high water level is reached. The HPCF System
then automatically stops flow by closing the injection valve if the high
water level signal is available.
This valve will reopen if reactor water level subsequently decreases to the
low initiation level. The system is arranged to allow automatic or manual
operation. The HPCF initiation signal from the NBS also initiates the
standby diesels in the respective divisions.
An AC motor-operated valve and a check valve are provided in both
branches of the pump suction. The pump suction can be aligned
through one branch to the condensate storage tank or aligned through
the other branch to the suppression pool. The control arrangement is
shown in Figure 7.3-1. Reactor grade water in the condensate storage
tank is the preferred source. On receipt of an HPCF initiation signal, the
condensate storage tank suction valves are automatically signaled to
open (they are normally in the open position unless the suppression
pool suction valves are open). If the water level in the condensate
storage tank falls below a preselected level, first the suppression pool
suction valves automatically open and then the condensate storage tank
suction valves automatically close. Four level transducers (one in each
electrical division) are used to detect low water level in the condensate
storage tank. Any two-out-of-four transducers can cause the suppression
pool suction valves to open and the condensate storage tank valves to
close. The suppression pool suction valves also automatically open if
high water level is detected in the suppression pool. Four level
transducers (one in each electrical division) monitor this water level and
7.3-3
Rev. 0
ABWR
(c)
7.3-4
Rev. 0
ABWR
Actuated Devices
All motor-operated valves in the HPCF System are equipped with
remote-manual functional test feature. The entire system can be
manually operated from the main control room.
Motor-operated valves are provided with limit switches to turn off the
motor when the full open or closed positions are reached. Torque
switches also control valve motor forces while the valves are seating.
The HPCF valves must be opened sufficiently to provide design flow rate
within 36 seconds from receipt of the initiation signal.
The HPCF pump discharge line is provided with an AC motor-operated
injection valve. The control scheme for this valve is shown in
Figure 7.3-1. The valve opens on receipt of the HPCF initiation signal.
The pump injection valve closes automatically on receipt of a reactor
high water level (Level 8) signal.
Two pressure transmitters and associated control room interfaces are
installed in each pump discharge pipeline to verify that pumps are
operating following an initiation signal. The pressure signals are used in
the Automatic Depressurization Subsystem to verify availability of high
pressure core cooling.
(f)
Separation
Separation within the ECCS is such that no single design basis event, in
conjunction with an additional single failure, can prevent core cooling
when required. Control and electrically driven equipment wiring is
segregated into three separate electrical divisions, designated I, II and
III (Figure 8.3-1). HPCF is a two-division system utilizing Divisions II and
III. HPCF control logic, cabling, manual controls and instrumentation
are arranged such that divisional separation is maintained. System
separation and diesel loading are shown in Table 8.3-1.
(g)
Testability
The high-pressure core flooder (HPCF) instrumentation and control
system is capable of being tested during normal unit operation to verify
the operability of each system component. Testing of the initiation
transmitters which are located outside the drywell is accomplished by
valving out each transmitter, one at a time, and applying a test pressure
7.3-5
Rev. 0
ABWR
Operational Considerations
Under abnormal or accident conditions where the system is required,
initiation and control are provided automatically. Operator action may
be initiated at any time, but is not necessary after automatic initiation.
Pressure in the HPCF pump suction line is monitored by a pressure
transmitter to permit the determination of suction head and pump
performance. Numerous other indications pertinent to the operation
and condition of the HPCF system are available to the control room
operator as shown in Figures 6.3-1 (HPCF P&ID) and 7.3-1 (HPCF IBD).
See Chapter 16 for setpoints and margins.
(j)
7.3-6
Rev. 0
ABWR
System Identification
Automatic safety/relief valves (SRVs) are installed on the main steamlines
inside the drywell. The valves can be actuated in two ways: (1) they will relieve
pressure by actuation with electrical power or (2) by mechanical actuation
without power. The suppression pool provides a heat sink for steam relieved
by these valves. Relief valve operation may be controlled manually from the
control room to hold the desired reactor pressure. Eight of the SRVs are
designated as Automatic Depressurization Subsystem (ADS) valves and are
capable of operating from either ADS logic or safety/relief logic signals. The
safety/relief logic is discussed in Paragraph (4). Automatic depressurization
by the ADS is provided to reduce the pressure during a loss-of-coolant accident
in which the HPCF and RCIC Systems are unable to restore vessel water level.
This allows makeup of core cooling water by the low pressure makeup system
(RHR/LP flooding mode).
(2)
(3)
Equipment Design
The Automatic Depressurization Subsystem (ADS) consists of redundant trip
channels arranged in two separate logics that control two separate solenoidoperated gas pilots on each ADS valve. Either pilot valve can operate its
associated ADS valve. These pilot valves control the pneumatic pressure
applied by accumulators and the High-Pressure Nitrogen Gas Supply System.
The operator can also control the SRVs manually. Separate accumulators are
included with the control equipment to store pneumatic energy for relief valve
operation.
The ADS accumulators are sized to operate the SRV one time at drywell design
pressure or five times at normal drywell pressure, following failure of the
pneumatic supply to the accumulator. Sensors provide inputs to local
multiplexer units which perform signal conditioning and analog-to-digital
7.3-7
Rev. 0
ABWR
conversion. The formatted, digitized sensor inputs are multiplexed with other
sensor signals over an optical data link to the logic processing units in the
main control room. All four transmitter signals are fed into the two-out-of-four
logic for each of two divisions, either of which can actuate the ADS. Station
batteries and SSLC power supplies energize the electrical control circuitry.
The power supplies for the redundant divisions are separated to limit the
effects of electrical failures. Electrical elements in the control system energize
to cause the relief valves to open.
(a)
7.3-8
Rev. 0
ABWR
7.3-9
Rev. 0
ABWR
This allows pneumatic pressure from the accumulator to act on the gas
cylinder operator. The gas cylinder operator opens and holds the relief
valve open. Lights in the main control room indicate when the solenoidoperated pilot valves are energized to open a safety/relief valve. Linear
variable differential transformers (LVDTs) mounted on the valve
operators verify each valve position to the Performance Monitoring and
Control System (PMCS), and the annunciators.
The ADS Division I control logic actuates a solenoid pilot valve on each
ADS valve. Similarly, the ADS Division II control logic actuates a second
separate solenoid pilot valve on each ADS valve. Actuation of either
solenoid-pilot valve causes the ADS valve to open to provide
depressurization.
Manual reset circuits are provided for the ADS initiation signal and the
two parameter sensor input logic signals. An attempted reset has no
effect if the two-out-of-four initiation signals are still present from each
parameter (high drywell pressure and low-low reactor water level).
However, a keylocked inhibit switch is provided for each division which
can be used to take one ADS division out of service for testing or
maintenance during plant operation. This switch is ineffective once the
ADS timers have timed out and thus cannot be used to abort and reclose
the valves once they are signalled to open. The inhibit mode is
continuously annunciated in the main control room.
Manual actuation pushbuttons are provided to allow the operator to
initiate ADS immediately (no time delay) if required. Such initiation is
performed by first rotating the collars surrounding the pushbuttons for
each of two channels within one of the two divisions. An annunciator will
sound to warn the operator that the ADS is armed for that division. If the
two pushbuttons are then depressed, the ADS valves will open, provided
the ECCS pump(s) running permissives are present. Though such
manual action is immediate, the rotating collar permissives and duality
of button sets combined with annunciators assure manual initiation of
the ADS to be a deliberate act.
A control switch is available in the main control room for each SRV,
including the ones associated with the ADS. Each switch is associated
with one SRV. The eighteen SRVs are divided into three groups of six for
pressure relief operation and are powered by Division I, II or III of the
Class 1E 125 VDC busses. The three electrical divisions maintain
electrical separation consistent with the required operability, though its
function is not required for safety. The switches are three-position
7.3-10
Rev. 0
ABWR
Actuated Devices
Safety/relief valves are actuated by any one of four methods:
(i)
ADS Action
Automatic action after high drywell pressure followed by
29 seconds at low water level (L1) or low water level (L1) for
8 minutes (ADS high drywell pressure bypass timer) and
29 seconds (ADS timer), plus makeup pumps running, resulting
7.3-11
Rev. 0
ABWR
Manual
Manual action by the operator (either by ADS system level
actuation, or by individual SRV operating switches).
Separation
Separation of the ADS is in accordance with criteria stated in Section 7.1.
ADS is a Division I (ADS 1) and Division II (ADS 2) system, except that
only one set of relief valves is supplied. Each ADS relief valve can be
actuated by any one of three solenoid pilot valves supplying nitrogen gas
to the relief valve gas piston operators. One of the ADS solenoid pilot
valves is operated by Division I logic and the other by Division II logic.
The third solenoid pilot is used for non-ADS operation. Control logic
manual controls and instrumentation are mounted so that Division I and
Division II separation is maintained. Separation from Divisions III and
IV is likewise maintained.
(g)
Testability
The ADS has two complete control logics, one in Division I and one in
Division II. Each control logic has two circuits, both of which must
operate to initiate ADS. Both circuits contain time delay logic to give the
HPCF System an opportunity to restore water level. The ADS instrument
channels signals are verified by cross comparison between the channels
which bear a known relationship to each other. Indication for each
instrument channel is available on displays associated with the SSLC.
The logic is tested continuously by automatic self-test circuits. The STS
(the sixth test), discussed in RPS testability (Subsection 7.1.2.1.6) is also
applicable here for the ADS. The instrument channels are automatically
verified every ten minutes. Testing of ADS does not interfere with
automatic operation if required by an initiation signal. The pilot
solenoid valves can be tested when the reactor is not pressurized.
7.3-12
Rev. 0
ABWR
Operational Considerations
The instrumentation and controls of the ADS are not required for
normal plant operations. When automatic depressurization is required,
it will be initiated automatically by the circuits described in this section.
No operator action is required for at least 30 minutes following initiation
of the system.
A temperature element is installed on the SRV discharge piping several
feet from the valve body. The temperature element provides input to a
multipoint recorder and interfaces with the PMCS computer in the
control room to provide a means of detecting SRV leakage during plant
operation. When the temperature in any SRV discharge pipeline
exceeds a preset valve, an alarm is sounded in the main control room.
The alarm setting is enough above normal rated power drywell ambient
temperatures to avoid spurious alarms, yet low enough to give early
indication of SRV leakage.
Refer to Chapter 16 for setpoints and margin.
(j)
(4)
7.3-13
Rev. 0
ABWR
Function
The instrumentation and controls (I&C) for the Reactor Core Isolation
Cooling (RCIC) System provide control for the pump/turbine valves, and
accessories during the following conditions:
(a)
(b)
When the reactor vessel is isolated and yet maintained in the hot standby
condition.
(c)
(2)
Classification
The RCIC System is classified as a safety-related system and is designed to
assure that sufficient reactor water inventory is maintained in the reactor
vessel to permit adequate core cooling to take place.
7.3-14
Rev. 0
ABWR
(3)
Power Sources
The RCIC System is powered by the Division I 125 VDC system, except, for the
isolation valves for steam supply. Inboard isolation valves are powered by
480 VAC Division I and outboard valves are powered by 125 VDC Division II.
(4)
Equipment
When actuated, the RCIC System pumps demineralized water from the
condensate storage tank to the reactor vessel. The suppression pool provides
an alternate source of water. The RCIC System includes a 100% capacity
steam-driven turbine which drives a 100% capacity pump assembly, turbine
and pump accessories, piping, valves, and instrumentation necessary to
implement several flow paths. The arrangement of equipment and control
devices is shown in Figure 5.4-8 (RCIC P&ID).
Level transducers used for the initiation and tripping and pressure
transducers for isolation of the RCIC System are provided by the Nuclear
Boiler System and are shared by other system channels within each division.
They are located on instrument panels outside the drywell but inside the
containment. The only operating components of the RCIC System that are
located inside the drywell are the inboard steamline isolation valve and the
steamline warmup line isolation valve.
The rest of the RCIC System normal I&C components are located in the
Reactor Building. Cables connect the sensors (via the multiplexed optical data
links described in Appendix 7A) to control circuitry in the main control room.
Control system details are shown in Figure 7.3-3.
A design flow functional test of the RCIC System may be performed during
normal plant operation by drawing suction from the suppression pool and
discharging through a full flow test return line to the suppression pool. The
discharge valve to the reactor vessel remains closed during the test and reactor
operation remains undisturbed. All components of the RCIC System are
capable of individual functional testing during normal plant operation.
Control system decisions will provide automatic return from test to operating
mode if RCIC System initiation is required. There are three exceptions:
(i)
(ii)
7.3-15
Rev. 0
ABWR
opening (an alarm sounds when either of these valves leaves the
fully open position).
(iii) Breakers have been manually racked out of service. This condition
is indicated in the main control room.
(a)
Initiating Circuits
The RCIC System is initiated upon receipt of a high drywell pressure
signal or a reactor vessel low water level signal. High drywell pressure is
monitored by four shared pressure transmitters (one from each
division) in the Nuclear Boiler System. Reactor vessel low water level is
monitored by four shared level transducers (one from each of the four
electrical divisions) in the NBS that sense the pressure difference
between a constant reference leg of water and the actual height of water
in the vessel.
Each transducer supplies a signal to a local multiplexer unit which
performs signal conditioning and analog-to-digital conversion
(Appendix 7A). The formatted, digitized sensor inputs are multiplexed
with other sensor signals over an optical data link to the logic processing
units in the main control room. All four transmitter signals are fed into
the two-out-of-four logic for RCIC initiation.
The sensing lines for the transducers are physically separated from each
other and tap off the reactor vessel at each of the four quadrants of the
containment structure associated with the appropriate electrical
divisions.
The RCIC System is initiated automatically after receipt of either of the
two parameters just described and produces the design flow rate within
30 seconds. The system then functions to provide design makeup water
flow to the reactor vessel until the amount of water delivered to the
reactor vessel is adequate to restore vessel level. The RCIC turbine will
shut down automatically upon receipt of high reactor water level (twoout-of-four). The controls are arranged to allow manual startup,
operation, and shutdown.
The RCIC turbine is functionally controlled as shown in Figure 7.3-3
(RCIC IBD). The turbine governor limits the turbine speed and adjusts
the turbine steam control valve so that design pump discharge flow rate
is obtained. The flow signal used for automatic control of the turbine is
derived from a differential pressure measurement across a flow element
in the RCIC System pump discharge line.
7.3-16
Rev. 0
ABWR
Turbine overspeed
(ii)
(c)
7.3-17
Rev. 0
ABWR
Rev. 0
ABWR
Actuated Devices
All automatic valves in the RCIC System are equipped with remote
manual test capability so that the entire system can be operated from the
control room. Motor-operated valves are equipped with limit and torque
switches. Limit switches turn off the motors when movement is
complete. In the closing direction, torque switches turn the motor off
when the valve has properly seated. Thermal overload devices are used
to trip motor-operated valves during testing only (for more information
on valve testing, see Subsection 3.9.3.2). All motor-operated and airoperated valves provide control room indication of valve position. The
system is capable of initiation independent of AC power.
To assure that the RCIC System can be brought to design flow rate within
30 seconds from receipt of the initiation signal, the following maximum
operating times for essential RCIC valves are provided by the valve
operation mechanisms:
RCIC turbine steam supply valve:
15 s
15 s
15 s
The operating time is the time required for the valve to travel from the
fully-closed to the fully-open position or vice versa. A normally closed
steam supply valve is located in the turbine steam supply pipeline just
upstream of the turbine stop valve. The control scheme for this valve is
shown in Figure 7.3-3 (RCIC IBD). Upon receipt of an RCIC initiation
signal this valve opens and remains open until closed by a high water
level signal, or by operator action from the main control room.
Two normally open isolation valves, one inboard and one outboard, are
provided in the steam supply line to the turbine. The valves
Engineered Safety Feature Systems, Instrumentation and Control
7.3-19
Rev. 0
ABWR
7.3-20
Rev. 0
ABWR
The auxiliary systems that support the RCIC System are the nonsafety-related Gland Subsystem (which prevents turbine steam
leakage) and the Lube Oil Cooling Water Subsystem. An RCIC
initiation signal activates the vacuum pump of the barometric
condenser and opens the cooling water supply valve, thereby
initiating the gland seal and lube oil cooling functions. These
systems remain on until manually turned off. However, the cooling
water supply valve will close automatically on receiving a two-out-offour high reactor water level signal.
(f)
Separation
The RCIC System is basically a Division I system but includes both
Division I and Division II valves for isolation. Therefore, part of the RCIC
logic (the outboard isolation logic) is Division II. In order to maintain
the required separation, RCIC trip channel and logic components,
instruments, and manual controls are mounted so that separation from
Division II is maintained.
All power and signal cables and cable trays are clearly identified by
division and safety classification.
(g)
Testability
The RCIC System may be tested to design flow during normal plant
operation. The system is designed to return to the operating mode if
system initiation is required during testing. Water is drawn from the
suppression pool and discharged through a full flow test return line to
the suppression pool. The discharge valve from the pump to the reactor
is tested separately and closed during the system flow test so that reactor
operation remains undisturbed.
Verification of sensor signals is accomplished by cross comparison
between the redundant channels. Each is monitored on the SSLC
displays. Additional testing of the initiation sensors which are located
outside the drywell may be accomplished by valving out each sensor and
applying a test pressure source. This verifies the calibration range in
addition to the operability of the sensor. The logic is tested every
10 minutes by automatic self-test circuits. The automatic self-test system
(the sixth test) discussed in Subsection 7.1.2.1.6 is also applicable here
for the RCIC System. With a division-of-sensors bypass in place,
calibrated, variable ramp signals are injected in place of the sensor
signals and monitored at the SSLC control room panels for linearity,
accuracy, fault response, and downscale and upscale trip response.
7.3-21
Rev. 0
ABWR
(5)
Environmental Considerations
The only RCIC control components located inside the drywell that must
remain functional in the environment resulting from a loss-of-coolant
accident are the control mechanisms for the inboard isolation valve and the
steamline warmup line isolation valve. The RCIC I&C equipment located
outside the drywell is selected in consideration of the environments in which
it must operate. All safety-related RCIC instrumentation is seismically qualified
to remain functional following a safe shutdown earthquake (SSE)
(Section 3.10).
(6)
Operational Considerations
Normal core cooling is required in the event that the reactor becomes isolated
from the main condenser during normal operation by a closure of the main
steamline isolation valves. Cooling is necessary due to the core fission product
decay heat. Steam pressure is relieved through the SRVs to the suppression
pool. The RCIC System maintains reactor water level by providing the makeup
water. Initiation and control are automatic.
The following indications are available in the main control room for operator
information:
Indication
RCIC steamline supply pressure
RCIC valve (test bypass to suppression pool) position
RCIC pump discharge pressure
RCIC pump discharge flow
RCIC pump discharge minimum flow
RCIC turbine speed
RCIC turbine exhaust line pressure
RCIC turbine exhaust diaphragm pressure
Indicating Lamps
Position of all motor-operated valves
Position of all solenoid-operated valves
7.3-22
Rev. 0
ABWR
Turbine trip
Significant sealed-in circuits
Pump status
System status (power, test, isolation)
Annunciators
Annunciators are provided as shown in the RCIC system IBD (Figure 7.3-3)
and the RCIC System P&ID (Figure 5.4-8).
(7)
Setpoints
The reactor vessel low water level setting for RCIC System initiation is selected
high enough above the active fuel to start the RCIC System in time to prevent
the need for the use of the low pressure ECCS. The water level setting is far
enough below normal levels that spurious RCIC System startups are avoided
(see Chapter 16 for actual setpoints and margin).
System Identification
The Low Pressure Flooder (LPFL) Subsystem is an operating mode of the
Residual Heat Removal (RHR) System (RHR System and its operating modes
are discussed in Chapter 5). Because the LPFL Subsystem is designed to
provide water to the reactor vessel following the design basis LOCA, its
controls and instrumentation are discussed here.
(2)
(3)
Equipment Design
Figure 5.4-10 (RHR P&ID) shows the entire RHR System, including the
equipment used for LPFL operation. Control and instrumentation required
for the operation of the LPFL mode are safety-related.
The instrumentation for LPFL operation controls all necessary valves in the
RHR System. This ensures that the water pumped from the suppression pool
by the main system pumps is routed directly to the reactor. These interlocking
features are described in this subsection.
7.3-23
Rev. 0
ABWR
LPFL operation uses three pump loops, each loop with its own separate vessel
injection path. Figure 5.4-10 (RHR P&ID) shows the location of instruments,
control equipment, and LPFL components. Except for the shutdown cooling
inboard suction isolation valves and the testable check valves for Divisions II
and III, the components pertinent to LPFL operation are located outside the
drywell.
Motive power for the RHR System pumps is supplied from AC buses that can
receive standby AC power. The three pumps are powered from Division I, II,
and III ESF buses, which also provide power to the RCIC (Division I) and
HPCF (Divisions II and III) Systems. Motive power for the automatic valves
comes from the bus that powers the pumps for that division, except for the
special case involving isolation valves. Control power for the LPFL Subsystem
components comes from the divisional Class 1E AC buses. Logic power is from
the SSLC power supply for the division involved. Trip channels for the LPFL
Subsystem are shown in Figure 7.3-4.
The LPFL Subsystem is arranged for automatic and remote-manual operation
from the control room.
(a)
Initiating Circuits
The LPFL Subsystem is initiated automatically on receipt of a high
drywell pressure or low reactor water level signal (Level 1), and a low
reactor pressure permissive to open the injection valve. The LPFL may
also be initiated manually.
Reactor vessel low water level (Level 1) is monitored by eight level
transmitters from the Nuclear Boiler System (NBS) which are mounted
on instrument racks in the drywell. These transmitters sense the
difference between the pressure due to a constant reference leg of water
and the pressure due to the actual height of water in the vessel. The
multi-division transmitters are shared with other systems within the
respective divisions. Four transmitters provide signals (one from each
division) to RHR Divisions I and III. The other four transmitters provide
similar signals to RHR Division II.
Drywell pressure is monitored by four pressure transmitters from the
NBS which are mounted on instrument racks in the containment. These
transmitters are also shared with other system channels within the
respective divisions. The sensors provide inputs to local multiplexer
units which perform signal conditioning and analog-to-digital
conversion (Appendix 7A). The formatted, digitized sensor inputs are
multiplexed with other sensor signals over an optical data link to the
7.3-24
Rev. 0
ABWR
logic processing units in the main control room. The four signals from
each parameter are combined, through appropriate optical isolators, in
two-out-of-four logic for each division of the RHR/LPFL System. This
assures that no single failure event can prevent initiation of the
RHR/LPFL Systems. The initiation logic for the RHR System (including
LPFL) is shown in Figure 7.3-4.
The LOCA signals which trigger the initiation logic also initiate starting
of the respective division diesel generator.
The LPFL injection valve actuation logic requires a reactor low pressure
permissive signal for automatic actuation on reactor low water (Level 1)
or high drywell pressure. The reactor pressure logic is a two-out-of-four
network of shared sensor channels from the NBS and is similar in
arrangement to the initiation logic just described.
Manual opening of the injection valve also requires the two-out-of-four
reactor low pressure permissive.
(b)
The valves in the suction paths from the suppression pool are
normally open and require no automatic action to line up suction.
(ii)
7.3-25
Rev. 0
ABWR
7.3-26
Rev. 0
ABWR
within 36 seconds of the receipt of the accident signals and the low
reactor pressure permissive.
Two pressure transmitters and associated control room interfaces are
installed in each pump discharge pipeline to verify that pumps are
operating following an initiation signal. The pressure signals are used in
the Automatic Depressurization Subsystem to verify availability of core
cooling systems.
All automatic valves used in the LPFL function are equipped with
remote-manual test capability. The entire system can be operated from
the control room. Motor-operated valves have limit switches to turn off
the motor when the full open or close positions are reached. Torque
switches are also provided to control valve motor forces when valves are
seating. Thermal overload devices are used to trip motor-operated valves
during periodic tests and to provide alarms. Such overload devices are
bypassed for safety events. Valves that have vessel and containment
isolation requirements are discussed in Subsection 7.3.1.1.2.
The RHR System pump suction valves from the suppression pool are
normally open. To reposition the valves, a keylock switch must be turned
in the control room. On receipt of an LPFL initiation signal, the reactor
Shutdown Cooling System (SCS) valves and the RHR test line valves are
signaled to close (although they are normally closed) to ensure that the
RHR System pump discharge is correctly routed. Included in this set of
valves are the valves that, if not closed, would permit the main system
pumps to take suction from the reactor vessel itself (a lineup used during
normal SCS operation).
The LOCA or manual initiation signal also sends a close signal to the
normally closed heat exchanger bypass valves along with an open signal
to the normally open heat exchanger outlet valves. This action assures
proper orientation of these valves for the LOCA event.
(f)
Separation
Separation of the RHR/LPFL I&C is in accordance with criteria stated
in Subsection 8.3.1.4.2. LPFL circuits are unique to their assigned
division except for the two-out-of-four initiation logics, which interface
through optical isolators. All local cabling and equipment are located
within divisionally assigned quadrants within the Reactor Building.
(g)
Testability
7.3-27
Rev. 0
ABWR
Operational Considerations
The pumps, valves, piping, etc., used for the LPFL are used for other
operating modes of the RHR System. Initiation of the LPFL mode is
automatic and no operator action is required for at least 30 minutes. The
operator may control the RHR pumps and injection valves manually
after LPFL initiation to use RHR capabilities in other modes if the core
is being cooled by other emergency core cooling systems.
Temperature, flow, pressure, and valve position indications are available
in the control room for the operator to assess LPFL operation. Valves
have indications for full-open and full-closed positions. Pumps have
indications for pump running and pump stopped. Alarm and indication
devices are shown in Figures 5.4-10 and 7.3-4.
(j)
7.3-28
Rev. 0
ABWR
System Identification
The instrumentation and control for the Leak Detection and Isolation System
(LDS) consists of temperature, pressure, radiation and flow sensors with
associated instrumentation and logic used to detect, indicate, and alarm
leakage from the reactor primary pressure boundary. In certain cases, also
initiate closure of isolation valves to shut off leakage external to the
containment.
Manual isolation control switches are provided to permit the operator to
manually initiate (at the system level) isolation from the control room. In
addition, each power-operated isolation valve is provided with a separate
manual control switch in the control room which is independent of the
automatic and manual leak detection isolation logic.
Paragraph (3), below, provides a description of the various input variables and
sensing methods used to monitor the variables and provide the inputs to the
LDS System for initiation of the isolation function. Each variable is recorded
and/or indicated in the main control room.
(2)
7.3-29
Rev. 0
ABWR
(3)
Level 3This low level setting is the RPS low water scram setting.
Level 3 is set high enough to indicate inadequate vessel water
makeup possibly indicative of a breach in the reactor coolant
pressure boundary (RCPB) or process piping containing reactor
coolant, yet far enough below normal operation levels to avoid
spurious isolation due to expected system transients. In addition to
scram, trip of 40% of the Reactor Recirculation System (RRS) ten
pumps and closure of the RHR shutdown cooling isolation valves
are initiated at Level 3.
(ii)
Level 2The next lower setting (the setting for initiation of RCIC)
is selected to avoid the release of radioactive material in excess of
radiological limits outside the containment. The Level 2 setpoints
are low enough so that the RCIC System will not be falsely initiated
after a scram due to vessel low water level, provided feedwater flow
has not been terminated. Conversely, the Level 3 setpoints are
high enough so that for complete loss of feedwater flow, the RCIC
System flow will be sufficient to avoid initiation of systems at Level
1-1/2. The remaining six RRS pumps are tripped and containment
isolation valves (except drywell cooling isolation valves and MSIVs)
are closed at Level 2. The RCIC System is shut down and/or
isolated on high reactor water Level 8.
(iii) Level 1-1/2The MSIVs are closed and the standby diesels and
HPCF are started at Level 1-1/2. Level 1-1/2 shall be set low
enough to prevent actuations of the above items on loss of
feedwater pumps with reactor coolant makeup by the RCIC
System. Level 1-1/2 shall be set high enough so that the HPCF
System prevents a Level 1 actuation signal on loss of feedwater
without RCIC operation.
(iv) Level 1Automatic Depressurization Subsystem (ADS) operation
is initiated at Level 1 (given a concurrent high drywell pressure
7.3-30
Rev. 0
ABWR
(c)
7.3-31
Rev. 0
ABWR
(f)
(g)
7.3-32
Rev. 0
ABWR
CUW suction line from the reactor, flow in the CUW return lines to the
reactor, and flow in the blowdown line to the main condenser are
monitored. The temperature-compensated flow output in the suction
line is compared with the flow outputs from the discharge lines by
electronic equipment which trips on high differential flow. The
Division II channel trip will close the inboard CUW isolation valves and
Division I channel trip will close the CUW outboard isolation valves.
(h) Drywell Pressure Monitoring
Drywell pressure is monitored by four divisional pressure transmitters
relative to containment pressure. These transmitters are provided by the
Nuclear Boiler System and are shared with other systems. The
transmitters are mounted in local panels within the Reactor Building.
Instrument sensing lines that connect the transmitters with the drywell
interior physically interface with the containment system.
Four channels (one in each of the four divisions) provide signals to LDS
isolation logic.
(i)
(j)
(k)
7.3-33
Rev. 0
ABWR
Rev. 0
ABWR
(r)
7.3-35
Rev. 0
ABWR
(t)
(ii)
Four divisional signals for each low reactor vessel water Level 1, 1.5,
2, and 3 signals
(4)
7.3-36
Rev. 0
ABWR
(5)
(b)
7.3-37
Rev. 0
ABWR
will override the individual manual controls to close all system isolation
valves regardless of manual control switch position.
Direct operator action is required (via a logic reset) to manually reset
the trip condition. (The initiating signal must be cleared before the
logic can be reset.) The isolation valve cannot be reopened until the trip
logic is reset. For detailed logic, see Figure 7.3-5.
(6)
(7)
Main Steamline
Redundancy is provided by the instrumentation to monitor each
essential variable as follows:
(i)
(ii)
7.3-38
Rev. 0
ABWR
(v)
(ii)
(ii)
7.3-39
Rev. 0
ABWR
(i)
(ii)
Manual Control
Redundancy and freedom from spurious manual initiation is provided
by four selector pushbuttons (one in each of four divisions) for manual
system level main steamline isolation. The isolation circuits for RHR,
CUW, RCIC, etc., likewise have manual initiation switches for each
division of the system(s).
Diversity is provided for manual isolation by system level manual
isolation switches and independent valve control switches.
(f)
(g)
Actuated Devices
(a)
The main steamline isolation valves are spring and pneumatic closing,
piston-operated valves (Figure 5.4-7). They close by spring power on loss
of pneumatic pressure to the valve operator. This is a fail-safe design.
The control arrangement is shown in the LDS/IBD (Figure 7.3-5).
Closure time for the valves is set between 3 and 5 seconds. Each valve is
controlled by three-way solenoid-operated pilot valves, powered by
120 VAC. Position limit switches are provided for logic interfaces and
valve position indication.
(b)
7.3-40
Rev. 0
ABWR
(c)
(9)
Separation
Electrical and mechanical separation complies with the criteria presented in
Subsection 8.3.1.4.2.
(10) Testability
Pressure or differential pressure type sensors, used for monitoring level,
pressure, or flow, may be valved out of service one at a time and functionally
tested using a test pressure source. A remotely actuated check-source is
provided with each detector or group of detectors for test purposes.
(11) Environmental Considerations
The physical and electrical arrangement of the LDS was selected so that no
single physical event would prevent achievement of isolation functions. Motor
operators for valves inside the drywell are of the totally enclosed type; those
outside the containment have weather-proof enclosures. Solenoid valves used
as air pilots are provided with watertight enclosures. All cables and operators
are capable of operation in the most unfavorable ambient conditions
anticipated for normal operations. Temperature, pressure, humidity, and
radiation are considered in the selection of all equipment, including sensors
and control room equipment, for the system. Cables used in high radiation
areas have radiation-resistant insulation. Shielded cables are used where
necessary to eliminate interference from magnetic fields.
Special consideration has been given to isolation requirements during a lossof-coolant accident inside the drywell. Components of the LDS that are
located inside the drywell and that must operate during a LOCA are the
cables, control mechanisms and valve operators of isolation valves inside the
drywell. These isolation components are required to be functional in a LOCA
environment (Section 3.11). Electrical cables are selected with insulation
Engineered Safety Feature Systems, Instrumentation and Control
7.3-41
Rev. 0
ABWR
designed for this service. Closing mechanisms and valve operators are
considered satisfactory for use in the isolation control system only after
completion of environmental testing under LOCA conditions or submittal of
evidence from the manufacturer describing the results of suitable prior tests.
(12) Operational Considerations
The LDS is on continuously to monitor containment leakage during normal
plant operation. The system will automatically function to isolate a reactor
coolant leak external to the containment and prevent unacceptable
radiological releases from the containment following detection of a leakage
within the containment. No operator action is required following system
initiation.
The following information is alarmed and/or indicated in the control room.
Indication is provided by instruments, displays, recorders, status lights,
computer readout or annunciator alarms:
All bypasses
Valve overrides
Test status
Rev. 0
ABWR
cooling valves and CUW head spray valve whenever the reactor pressure is
above a preset value. This signal is provided as an interlock and is not provided
for containment or reactor vessel isolation.
(13) Parts of System Not Required for Safety
The non-safety-related portions of the LDS include the circuits that drive
annunciators and the computer. Other instrumentation considered nonsafety-related are those indicators which are provided for operator
information.
7.3.1.1.3 RHR/Wetwell and Drywell Spray Cooling ModeInstrumentation and Controls
(1)
System Identification
Wetwell/drywell spray cooling (WDSC) is a manually-initiated operating
mode of the RHR System (see Figure 5.4-10 P&ID). It is designed to provide
the capability of condensing steam in the wetwell air volume and the
containment atmosphere and removing heat from the suppression pool water
volume.
(2)
(3)
Equipment Design
Control and instrumentation for the following equipment is required for this
mode of operation:
(a)
(b)
(c)
7.3-43
Rev. 0
ABWR
Wetwell and drywell spray operation uses two pump loops, each loop with its
own separate discharge valve. All components pertinent to wetwell and drywell
spray operation are located outside of the drywell.
Motive and control power for the two loops of wetwell and drywell spray I&C
equipment are the same as those used for RHR B and RHR C.
The drywell spray cooling mode can be manually initiated from the control
room if the RHR injection valve is fully closed and the drywell pressure is
above a setpoint, allowing the operator to act in the event of a LOCA. In the
absence of high drywell pressure conditions, the drywell spray valves cannot be
opened.
The wetwell spray cooling can be manually initiated in the control room. The
operator relies on the instrumentation that provides indication of the wetwell
air space temperature condition when initiating this mode. No interlock is
provided.
(a)
Initiating Circuits
Drywell Spray B: Drywell pressure is monitored by four shared pressure
transmitters mounted in instrument racks in the containment.
Signals from these transmitters are routed to the local multiplexer units
which convert analog to digital signals and send them through fiber
optic links for logic processing in the control room. Any two-out-of-four
signals provide the permissive to initiate the WDSC.
Initiation logic for drywell spray B is identical to drywell spray C.
Wetwell Spray B: The initiation of wetwell spray is manual and does not
have an interlock. The operator bases judgment on the instrumentation
indication of the condition of the wetwell air space temperature.
Operation of wetwell spray B is identical to wetwell spray C.
(b)
Logic Sequencing
The operating sequence of wetwell and drywell spray following receipt
of the LPFL initiating signals is as follows:
(i)
(ii)
Rev. 0
ABWR
(iv) Service water supply and discharge valves to the RHR heat
exchanger are signaled to open.
(v)
The heat exchanger outlet valve opens and the heat exchanger
bypass valve is signaled to close.
Actuated Devices
Figure 7.3-4 shows functional control arrangement of the Wetwell and
Drywell Spray System.
The RHR B and C loops are utilized for wetwell and drywell spray.
Therefore, the pumps and valves are the same for the LPFL and wetwell
7.3-45
Rev. 0
ABWR
and drywell spray except that each has its own discharge valve. See
Subsection 7.3.1.1.4 (LPFL Actuated Devices) for specific information.
(f)
Separation
Separation of the WDCS RHR is in accordance with criteria stated in
Subsection 8.3.1.4.2.
Wetwell and drywell spray is a Division II (RHR B) and Division III
(RHR C) system. Manual controls, logic circuits, cabling, and
instrumentation for containment spray are arranged such that divisional
separation is maintained.
(g)
Testability
The Wetwell and Drywell Spray System is capable of being tested up to
the last discharge valve during normal operation. Drywell and wetwell
pressure channels are tested by cross-comparison between related
channels. Any disagreement between the display readings for the
channels would indicate a failure. The instrument channel trip setpoint
is verified by automatic self-test functions in the SSLC which simulate
programmed trip setpoints and monitor the response. Testing for
functional operability of the control logics is accomplished by the
automatic self-test system (Subsection 7.1.2.1.6). Other control
equipment is functionally tested during manual testing of each loop.
Indications in the form of panel lamps and annunciators are provided in
the control room.
Operational Considerations
Wetwell and drywell spray is a mode of the RHR System, and is not
required during normal operation.
Temperature, flow, pressure, and valve position indications are available
in the control room for the operator to assess wetwell and drywell spray
operation (except for the wetwell spray which does not have pressure).
Alarms and indications are shown in Figures 5.4-10 (RHR P&ID) and
7.3-4 (RHR IBD).
See Chapter 16 for setpoints and margin.
7.3-46
Rev. 0
ABWR
(j)
System Identification
Suppression pool cooling is an operating mode of the RHR System. It is
designed to provide the capability of removing heat from the suppression pool
water volume. The system is automatically initiated upon receipt of a high
temperature signal from the suppression pool temperature monitoring system
(SPTM) or may be manually initiated when necessary.
(2)
(3)
Equipment Design
Control and instrumentation for the following equipment is required for this
mode of operation:
Suppression Pool Cooling (SPC) uses three pump loops, each loop with its
own separate discharge valve. All I&C components pertinent to suppression
pool cooling operation, except suppression pool temperature monitoring, are
located outside of the drywell.
The Suppression Pool Cooling (SPC) mode is automatically initiated on high
suppression pool temperature or manually initiated from the control room.
This mode is put into operation to limit the water temperature in the
suppression pool such that the temperature immediately after a blowdown
7.3-47
Rev. 0
ABWR
does not exceed the established limit when reactor pressure is above the limit
for cold shutdown.
(a)
Initiating Circuits
Initiating suppression pool cooling is automatic upon receipt of high
suppression pool temperature signals from the SPTM system. SP cooling
may also be initiated manually by the control room operator during
normal operation, abnormal transients, or post LOCA events. Initiation
of suppression pool cooling A is identical to that of B and C.
(b)
(ii)
(iii) RHR service water discharge valves to the RHR heat exchanger are
opened.
(iv) If performed following LPFL initiation, the injection valves are
manually closed and SP valves are opened.
(v)
(c)
The SPC mode will continue to operate until the operator closes
the SPC discharge valves or when reactor low water level reoccurs,
in which case the injection valve will auto-open and the SP
discharge valve will auto-close.
Rev. 0
ABWR
(e)
Actuated Devices
Figure 7.3-4 shows the interlock block diagram of the SPC mode.
The RHR A, B, and C loops are utilized for SPC. Therefore, the pump
and valves are the same for LPFL and SPC, except that each mode has its
own discharge valves.
(f)
Separation
Separation of the SPC-RHR is in accordance with criteria stated in
Subsection 8.3.3.6.2.
Suppression pool cooling is a Division I (RHR A), Division II (RHR B)
and Division III (RHR C) system. Automatic and manual control, logic
circuits, and instrumentation for suppression pool cooling are arranged
such that divisional separation is maintained.
(g)
Testability
Suppression pool cooling is capable of being tested during normal
operation.
Testing for functional operability of the control logic can be
accomplished by the automatic system self-test.
Indications in the form of panel indicators and annunciators are
provided in the control room.
Operational Considerations
Suppression pool cooling is a mode of the RHR System and can be used
during normal power operation to limit suppression pool temperature.
Temperature, flow, pressure, and valve position indications are available
in the control room for the operator to assess SPC operation. Alarms and
indications are shown in Figure 7.3-4.
Alarm setpoints for high suppression pool (SP) temperatures are
provided in the SP temperature monitoring system. The SP cooling
system is manually or automatically initiated if a persistent increase of SP
temperature occurs.
7.3-49
Rev. 0
ABWR
(j)
System Identification
The Standby Gas Treatment System (SGTS) processes gaseous effluent from
the primary and secondary containments when required to limit the discharge
of radioactivity to the environment during normal and abnormal operation. It
also controls the exfiltration of fission products by maintaining a negative
pressure in the secondary containment, and by filtering the effluent prior to
discharge to the atmosphere following a LOCA or fuel handling accident.
System drawings are given in Figures 6.5-1 and 7.3-6.
(2)
(3)
Equipment Design
Process gas flow is controlled manually by a motor-driven butterfly valve
located on the upstream of the filter train.
The relative humidity of the air entering the charcoal adsorber is sensed by a
humidity element downstream of the electric space heaters. A controller
operates the space heaters to maintain the relative humidity of the air at 70%
or less. The switch initiates an alarm in the control room upon high air
temperature.
Temperature sensors determine the charcoal bed temperature. A switch
actuates a control room annunciator upon high temperature in the charcoal.
(a)
Initiating Circuits
The SGTS is initiated automatically upon detection of a LOCA (high
drywell pressure or low reactor water level), or by high radiation in the
fuel handling area or secondary containment HVAC exhaust air. It can
also be initiated manually from the main control room.
7.3-50
Rev. 0
ABWR
(c)
Actuated Devices
Control devices actuated by the SGTS are shown on the interconnection
block diagram, Figure 7.3-6.
(f)
Separation
The control and logic circuits of the filter trains are physically and
electrically separated to reduce the probability that a single physical
event may prevent operation of the SGTS. Electric cables for redundant
instrumentation and controls on the two divisions of the SGTS are
routed separately.
7.3-51
Rev. 0
ABWR
(g)
Testability
Control and logic circuitry used in the controls for the active
components of the SGTS can be individually checked by applying test or
calibration signals to the sensors and observing trip or control responses.
Operation of dampers and fans from manual switches verifies the ability
of damper mechanisms to operate. The automatic control circuitry is
designed to initiate SGTS operation if a fuel-handling accident or LOCA
occurs during a test.
Operational Considerations
The SGTS fans can be started and dampers opened or closed on a system
level or individual basis by manipulating switches in the main control
room, thus providing the operator with means independent of the
automatic initiation functions.
The SGTS is designed so that, once initiated, the dampers continue to
operate to the end of their strokes and the fans continue to run, even if
the condition that caused initiation is restored to normal.
The operator must manually operate switches in the main control room
to shut down a standby gas treatment unit which has been automatically
started.
Initiation of the SGTS is annunciated in the main control room so that
the operator is immediately informed of the condition. The status of
fans and dampers is indicated by lights on the control panel.
The SGTS is designed to start both filter trains automatically and
simultaneously. When both units are operating, the operator may place
one of the two trains on standby. Should the operating unit fail, the
standby unit can be automatically initiated.
(j)
7.3-52
Rev. 0
ABWR
are those indicators which are provided for operator information, but
are not essential to correct operator action.
7.3.1.1.6 Emergency Diesel Generator Support Systems
Division I, II, and III diesel generator system control and instrumentation is discussed
in Subsection 8.3.1.1.8.
The diesel generator auxiliary systems are described in subsections of Chapter 9 and are
listed below:
(a)
(b)
(c)
7.3.1.1.7 Reactor Building Cooling Water System and Reactor Service Water System
Instrumentation and Controls
(1)
System Identification
The control system for the Reactor Building Cooling Water (RCW) System
and Reactor Service Water System operates to maintain the flow of cooling
water to operate auxiliaries which are required for normal plant operation
and normal or emergency reactor shutdown, as well as to those auxiliaries
whose operation is desired following a LOCA but not essential to safe
shutdown.
The RCW/RSW System is comprised of three divisions as shown in Figure 9.21. Control system details for both RCW and RSW Systems are shown in the
interlocking block diagram (Figure 7.3-7). The RSW System is also comprised
of three divisions as shown in Figure 9.2-7.
(2)
Power Sources
The power for RCW System instrumentation and controls is supplied from
Division I, II, and III 125 VDC and 120 VAC essential power buses.
(3)
Equipment Design
During normal operation, RCW water flows through the safety-related and
non-safety-related equipment except the RHR and emergency diesel
exchangers.
7.3-53
Rev. 0
ABWR
During all plant operating modes, one RCW pump is normally operating in
each division, so that in the event of LOCA, the RCW Systems required to shut
down the plant safely are already in operation.
Isolation of the non-safety-related section of each division of the RCW System
from the safety-related section is accomplished by motor operated valves in the
inlet and outlet lines to the non-safety-related section. Flow sensors are located
in the inlet lines.
(a)
Initiating Circuits
During normal operation, all RCW and RSW divisions supply both safetyrelated and non-safety-related cooling loads. Except for instrument air
and CRD oil cooling, the non-safety-related loads are automatically
isolated upon a LOCA. All non-safety-related loads are isolated on
occurrence of RCW surge tank low level (two-out-of-three logic).
Isolation can also be initiated manually from the control room.
All of the safety-related portions of the RCW System are started
automatically (standby pumps start and standby valves open) upon a
LOCA and/or LOPP (as defined in Subsection 8.3.1.1.7). The
containment isolation valves are closed automatically upon receipt of
the LOCA signal or may be closed manually from the control room.
(b)
(ii)
7.3-54
Rev. 0
ABWR
Actuated Devices
The automatically actuated isolation valves in the RCW and RSW System
are provided with electric motor operators. The valve limit switches turn
off the motor when the valves are fully open and permit torque switches
to control valve motor forces while the valves are seating in the closed
direction. Other valves have torque limits in the open direction except
at breakaway and torque limits on closing.
(f)
Separation
RSW System trip channels, logic circuits, manual controls, cabling and
instruments are mounted so that Division I, II, and III separation is
maintained in accordance with Subsection 8.3.3.1 criteria.
(g)
Testability
The RCW and RSW System have the capability of being tested during
normal plant operation.
RCW System control and logic circuits can be individually checked by
applying test or calibration signals and observing the system response.
The control circuitry is designed to restore the system to the required
operation if a LOCA occurs during a test.
Safety Interfaces
7.3-55
Rev. 0
ABWR
The safety interfaces for the RCW System Division I, II, and III controls
are as follows:
(j)
Divisions I, II and III RCW pump manual start signals from the
main control room (MCR) and Divisions I and II. RCW pump
manual start signal from the Remote Shutdown System (RSS).
Division I, II and III RCW pump running signals to the MCR and
Divisions I and II RCW pump running signals to the RSS.
Division I and II RCW flow signals to the MCR and Divisions I and
II RCW flow signal to the RSS.
Overload and power failure signals from all RCW and RSW pumps
to the MCR annunciator.
RCW surge tank low and high level signals to the MCR
annunciator.
Operational Considerations
The RCW and RSW Systems are capable of operating at a variety of
cooling load conditions as required for all plant operating modes,
including normal and emergency conditions.
Cooling water is required for the operation of the RHR, HECW, FPC,
CAM, and Emergency Diesel Generator Systems.
When the plant is in the hot standby or cooldown mode, safety-related
RCW cooling water is required for the RHR heat exchangers. Refer to
Subsection 7.3.1.1.4 for a discussion of the manual or automatic
operation of the RHR heat exchanger inlet and outlet isolation valves.
Process operating parameters and equipment status information are
provided in the control room for the operator to accurately assess system
performance. Alarms are also provided to indicate malfunction in the
system. Refer to IBD Figure 7.3-7 for specific indication of equipment
status in the control room. See Chapter 16 for setpoints and margin.
7.3-56
Rev. 3
ABWR
(k)
System Identification
The HVAC Emergency Cooling Water System (HECW) supplies
demineralized chilled water to the cooling coils of the control building safetyrelated electrical equipment rooms and main control room coolers, and the
diesel generator zone air conditioning systems. The system is composed of
three divisions, each containing two refrigerators and chilled water pumps .
The Control Building Chilled Water System instrumentation and controls are
shown on P&ID Figure 9.2-3 and the corresponding logic on Figure 7.3-9.
(2)
(3)
Equipment Design
The HECW System consists of three mechanically (and electrically) separate
systemsDivisions A, B, and C. The system is designed to provide chilled water
to the cooling coils of the Control Building Control Room Habitability Area
HVAC and Safety-related Equipment Area HVAC and Reactor Building Safetyrelated Electrical Equipment HVAC Systems..
The HECW System is designed to operate during both accident conditions
and normal plant operation and during all modes of operation for the cooling
systems it serves.
Each division of the HECW System consists of two chilled water pumps and
refrigerator units; each refrigerator unit includes the condenser, evaporator,
centrifugal compressor, refrigerant pipings and package chiller controls. The
system condenser is cooled by the RCW System.
7.3-57
Rev. 3
ABWR
Initiating Circuits
The HECW System operation is initiated automatically when the
controls in the main control room are set for automatic operation and
any of the HVAC systems it serves are started. The HECW System can also
be started manually from the main control room.
(b)
(c)
Rev. 3
ABWR
Actuated Devices
One refrigerator and chilled water pump in each division is running at
all times during all modes of plant operation.
The chilled water pumps and refrigerator units are started automatically
or by remote manual switch. Status lights in the control room are also
provided for this equipment.
High and low surge tank level switches actuate the opening and closing
of the demineralized water makeup valve and high-high and low-low
tank level switches annunciate an alarm in the control room.
The refrigerator capacity is controlled to maintain the chilled water
temperature at the refrigerator outlet constant. This is done by adjusting
the suction valve and hot-gas bypass within the refrigerator.
(f)
Separation
The instrumentation, controls, and sensors of each operating division
have sufficient physical and electrical separation to prevent
environmental, electrical, or physical accident consequences from
inhibiting the systems from performing each protective action. Physical
separation is maintained by use of separate cabinets and racks for each
division, and by housing redundant chiller equipment in separate
cubicles.
Electrical separation is maintained by separate independent sensors and
circuitry.
(g)
Testability
Manual initiation of the HECW System is possible from the control
room. Redundant standby components can be periodically tested,
manually, to ensure system reliability while the other system is operating.
Surge tank operation can be checked by varying the tank level and
observing the level at which the demineralized water makeup valve starts
to open and close and when the level alarm annunciates. Automatic
initiation of the standby system can be tested by simulating the trip
action of the operating refrigerator system.
7.3-59
Rev. 0
ABWR
Operational Consideration
The HECW System operation is initiated in the control room by a
manual master control switch. Once the system is started, it will
continuously operate under all modes of plant operation to supply
chilled water to the cooling coils.
Running lights, alarms, flow and temperature indicators, and valve
position indicators are available in the control room for the operator to
accurately monitor the HECW System operation. Chilled water pumps
have running lights. A common trouble alarm is provided for each
chiller unit. Surge tank high-high and low-low levels are alarmed. Motoroperated valves have position indicators. Chilled water flows have
position indicators.
System Identification
The High Pressure Nitrogen Gas Supply (HPIN) System provides compressed
nitrogen of the required pressure to the ADS SRVs, the MSIVs (for testing
only), instruments and pneumatically operated valves in the PCV and other
nitrogen-using components in the reactor building (see P&ID in Figure 6.7-1
and the interconnection block diagram in Figure 7.3-10).
(2)
7.3-60
Rev. 0
ABWR
Equipment Design
The HPIN System is separated into non-safety-related and safety-related
sections.
The non-safety-related portion of the system includes an inlet filter, piping,
and valves to all nitrogen users.
The safety-related portion of the system includes two banks of high pressure
nitrogen bottles and associated piping, valves, and controls.
When low nitrogen gas pressure is detected in the lines to the ADS
accumulators, the safety-related portion of the system is isolated from the nonsafety-related portion by isolation valves which automatically cut off the
normal nitrogen gas supply and open the emergency nitrogen gas bottle
supply to the ADS accumulators.
In addition to valves that isolate non-safety-related equipment from safetyrelated equipment, the HPIN System is provided with containment isolation
valves where the HPIN System lines enter the containment.
The valves are manually operated from individual control switches in the
control room.
(a)
Initiating Currents
During normal operation, nitrogen gas pressure is controlled and
measured in a pressure control valve followed by a pressure transmitter.
The pressure control valve setpoint is high enough to ensure that
adequate nitrogen pressure is delivered to all the served accumulators
and valves.
Automatic closure of the isolation valve from the normal nitrogen gas
supply and the opening of the isolation valve from the emergency
nitrogen gas bottle is initiated by low nitrogen pressure sensed in the
lines to the ADS accumulators.
(b)
7.3-61
Rev. 0
ABWR
(c)
Actuated Devices
Nitrogen is admitted to the system and the non-safety-related portion
isolated by operating valves controlled by pressure switches in the HPIN
System. These valves can also be operated from the main control room.
All isolation valves can be manually operated from the main control
room. Each valve is provided with indicating position lights in the main
control room which verify the open and closed positions of the valve.
(f)
Separation
The HPIN System is separated into two divisions, each having storage
bottles and racks and piping to the ADS accumulators.
Physical separation of Division A and Division B systems is obtained by
closing valves which interconnect the divisions during normal
operation.
Electrical separation is maintained by separate sensors and circuits
independent of each other.
7.3-62
Rev. 0
ABWR
(g)
Testability
The HPIN System can be tested at any time by isolating the system from
the normal nitrogen source and allowing the nitrogen pressure to
decrease. At the proper pressure, valves will open, admitting nitrogen
from the high pressure storage bottles; other valves will close, isolating
the non-safety-related portions of the system.
Operational Considerations
The HPIN System, when required for emergency conditions, is initiated
automatically with no operator action required.
Running lights, valve positions, indicating lights, and alarms are
available in the control room for the operator to accurately assess the
HPIN System operation. Common trouble alarms are available in the
main control room for the system. Isolation valves have indicating lights
for full-open and full-closed positions.
Conditions
The plant conditions which require protective action involving the systems of
this section and other sections are examined in Chapter 15.
(2)
Variables
The plant variables that are monitored to provide automatic protective actions
are discussed in the initiating circuits sections for each system. For additional
information, see Chapter 15, where safety analysis parameters for each event
are cited.
7.3-63
Rev. 0
ABWR
(3)
(4)
Operational Units
Prudent operational limits for each safety-related variable trip setting are
selected to be far enough above or below normal operating levels so that a
spurious ESF System initiation is avoided. Analysis then verifies that the release
of radioactive materials, following postulate gross failures of the fuel or the
nuclear system process barrier, is kept within established limits. Operational
limits contained in the Technical Specifications for the ECCS and LDS are
based on operating experience and constrained by the safety design basis and
the safety analyses.
(5)
(6)
7.3-64
Rev. 0
ABWR
(7)
Flood
The buildings containing ESF Systems and ECCS components have been
designed to meet the probable maximum flood (PMF) at the site
location. This ensures that the buildings will remain watertight under
PMF conditions including wind-generated wave action and wave runup.
(b)
Storm (Tornado)
The buildings containing ESF components have been designed to
withstand meteorological events described in Subsection 3.3.2.
Superficial damage may occur to miscellaneous station property during
a postulated tornado, but this will not impair the protection system
capabilities.
(c)
Earthquake
The structures containing ESF components have been seismically
qualified (Sections 3.7 and 3.8) and will remain functional during and
following a safe shutdown earthquake (SSE). Seismic qualification of
instrumentation and electrical equipment is discussed in Section 3.10.
(d) Fire
To protect ESF Systems in the event of a postulated fire, the redundant
portions of the systems are separated by fire barriers. If an internal fire
were to occur within one of the sections of a main control room panel
or in the area of one of the local panels, the ESF System functions would
not be prevented by the fire. The use of separation and fire barriers
ensures that, even though some portion of the system may be affected,
the ESF System will continue to provide the required protective action.
The Remote Shutdown System provides redundancy in the event of
significant exposure fires in the control room.
The plant Fire Protection System is discussed in Section 9.5.
7.3-65
Rev. 0
ABWR
(e)
LOCA
The following ESF System instrument taps and sensing lines are located
inside the drywell and terminate outside the drywell. They could be
subjected to the effects of a design basis LOCA:
Drywell pressure
(8)
Rev. 0
ABWR
and figures are included in Chapter 7 as appropriate. Subsection 1.7.2 provides keys for
the interpretation of symbols used in these documents.
7.3.2 Analysis
7.3.2.1 Emergency Core Cooling SystemsInstrumentation and Controls
7.3.2.1.1 General Functional Requirements Conformance
Chapters 15 and 6 evaluate the individual and combined capabilities of the emergency
cooling systems. For the entire range of nuclear process system break sizes, the cooling
systems provide adequate removal of decay heat from the reactor core.
Instrumentation for the ECCS must respond to the potential inadequacy of core
cooling regardless of the location of a breach in the reactor coolant pressure boundary.
Such a breach inside or outside the containment is sensed by reactor low water level.
The reactor vessel low water level signal is the only ECCS initiating function that is
completely independent of breach location. Consequently, it can actuate the HPCF,
RCIC, ADS and LPFL Systems.
The other major initiating functiondrywell high pressureis provided because
pressurization of the drywell will result from any significant nuclear system breach
anywhere inside the drywell.
Initiation of the Automatic Depressurization Subsystem (ADS) occurs when reactor
vessel low water level and drywell high pressure are sensed, or when the 8 minute
drywell high pressure bypass timer runs out. Therefore it is not required that the
nuclear system breach be inside the containment. This control arrangement is
satisfactory in view of the automatic isolation of the reactor vessel for breaches outside
the drywell and because the ADS is required only if the HPCF and/or RCIC System fail
to maintain adequate reactor water level.
No operator action is required to initiate the correct responses of ECCS. However, the
control room operator can manually initiate every essential operation of the ECCS.
Alarms and indications in the control room allow the operator to assess situations that
require the ECCS and verify the responses of each system. This arrangement limits
safety dependence on operator judgment, and design of the ECCS control equipment
has appropriately limited response.
The redundancy of the control equipment for the ECCS is consistent with the
redundancy of the cooling systems themselves. The arrangement of the initiating
signals for the ECCS is also consistent with the arrangement of the systems themselves.
No failure of a single initiating trip channel can prevent the start of the cooling systems
when required or inadvertently initiate these same systems.
Engineered Safety Feature Systems, Instrumentation and Control
7.3-67
Rev. 0
ABWR
The control schemes for each ECCS component are designed such that no single
control failure can prevent the combined cooling systems from providing the core with
adequate cooling This is due to the redundancy of components and cooling systems
(i.e., HPCF, RCIC, ADS, and the three divisions of LPFL).
The control arrangement used for the ADS is designed to avoid spurious actuation
(Figure 7.3-2). The ADS relief valves are controlled by two trip systems per division, both
of which must be in the tripped state to initiate depressurization. Within each trip
system, both drywell pressure high trip or time out of the 8 minute drywell high pressure
bypass timer and low reactor water level trip are required to initiate a trip system.
The only equipment protective devices that can interrupt planned ECCS operation are
those that must act to prevent complete failure of the component or system. In no case
can the action of a protective device prevent other redundant cooling systems from
providing adequate cooling to the core.
Controls for ECCS are located in the control room and are under supervision of the
control room operator.
The environmental capabilities of instrumentation for the ECCS are discussed in the
descriptions of the individual systems. Components that are located inside the drywell
and are essential to ECCS performance are designed to operate in the drywell
environment resulting from a LOCA. Safety-related instruments located outside the
drywell are also qualified for the environment in which they must perform their safetyrelated function.
Special consideration has been given to the performance of reactor vessel water level
sensors, pressure sensors, and condensing chambers during rapid depressurization of
the nuclear system (see Reference 7.3-1).
Effectiveness of emergency core cooling following a postulated accident may be verified
by observing the following indications:
7.3-68
(1)
Annunciators and status lights for HPCF, RCIC, LPFL, and ADS sensor
initiation logic trips
(2)
(3)
(4)
(5)
Rev. 0
ABWR
10CFR50.55a (IEEE-279):
The ECCS incorporates two divisions of HPCF, one division of steam-driven
RCIC, two divisions of ADS and three divisions (three loops) of LPFL
(RHR/low pressure flooders). This automatically actuated network of Class 1E
redundant high pressure and low pressure systems assures full compliance
with IEEE-279.
All components used for the ECCS are qualified for the environments in
which they are located (Sections 3.10 and 3.11). All systems which make up the
ECCS network are actuated by two-out-of-four logic combinations of sensors
which monitor drywell pressure and reactor water level. There are a total of
eight water level sensors and four drywell pressure sensors which are supplied
by the Nuclear Boiler System. These instruments are shared by the ECCS as
well as the RPS and other systems which require actuation signals from these
essential variables. However, each system receives all four signals as input to its
own unique voting logic incorporated in the safety system logic and control
(SSLC) network. If individual channels are bypassed for service or testing, the
voting logic reverts to two-out-of-three.
The containment is divided into four quadrants, each housing the electrical
equipment which, in general, corresponds to the mechanically separated
division assigned to each section (i.e., mechanical divisions A, B, C, and D
correspond with electrical Divisions I, II, III, and IV, respectively). Some
exceptions are necessary where a given mechanical division has more than one
electrical division within the quadrant. For example, the ADS valves have
redundant solenoid operators which require separate divisional power
interfaces. However, electrical separation is maintained between the
redundant divisions.
Each of these electrical divisions contains one of the drywell pressure sensors
and two of the reactor water level sensors which contribute to the two-out-offour voting logic. All of these signals are multiplexed and passed through
fiber-optic medium before entering the voting logic of the redundant
divisions involved in the systems which make up the ECCS network.
7.3-69
Rev. 0
ABWR
Criteria: GDCs 2, 4, 13, 15, 19, 20, 21, 22, 23, 24, 29, 33, 34, and 35.
(b)
(3)
7.3-70
Rev. 0
ABWR
Subsection 7.3.1.1.1. The ECCS fully complies with this regulatory guide
using the following two clarifying interpretations:
(b)
(i)
(ii)
(c)
7.3-71
Rev. 0
ABWR
each safety/relief valve has a manual keylock operation switch. There are
no interlocks between the manual actuation switches and their actuation
operators. The ECCS fully complies with this regulatory guide.
(e)
(f)
Rev. 0
ABWR
(g)
(4)
BPT ICSB 3Isolation of Low Pressure Systems from the High Pressure
Reactor Coolant System
Item B-5 of this BTP provides exception to the recommendations for the
ECCS. However, the RHR/LPFL injection lines are designed consistent
with Item B-3 in that a check valve is in series with the motor-operated
injection valve (see RHR P&ID, Figure 5.4-10).
The Nuclear Boiler System provides reactor pressure sensors, one from
each electrical division, which are arranged in two-out-of-four logic
permissives to automatically close the LPFL injection valves should
reactor pressure exceed the low pressure system design pressure.
Therefore, the ECCS is in full compliance with this BTP.
(b)
(c)
7.3-73
Rev. 0
ABWR
(5)
(b)
(c)
(f)
(g)
7.3-74
Rev. 0
ABWR
criteria in order of the listing on the table, and discusses the degree of conformance for
each. Any exceptions or clarifications are so noted.
(1)
10CFR50.55a (IEEE-279)
The LDS is a four-division system which is redundantly designed so that failure
of any single element will not interfere with a required detection of leakage or
isolation.
All components used for the safety isolation functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11). Most
initiation parameters are represented by all four divisions which actuate the
isolation functions via two-out-of-four logic permissives. Most of the sensors
are provided by the Nuclear Boiler System. These instruments are shared by
the ECCS, as well as the RPS and other systems which require actuation signals
from these essential variables. However, each system receives all four signals as
input to its own unique voting logic incorporated in the safety system logic and
control (SSLC) network. If individual channels are bypassed for service or
testing, the voting logic reverts to two-out-of-three.
The containment is divided into four quadrants, each housing the electrical
equipment which, in general, corresponds to the mechanically separated
divisions assigned to each section (i.e., mechanical divisions A, B, C, and D
correspond with electrical Divisions I, II, III and IV, respectively). Some
exceptions are necessary where a given mechanical division has more than one
electrical division within the quadrant. For example, the MSIVs have
redundant solenoid operators which require separate divisional power
interfaces. However, electrical separation is maintained between the
redundant divisions.
All of these signals are multiplexed and passed through fiber optic medium
before entering the voting logic of the redundant divisions involved in the
isolation valve logic. Separation and isolation are thus preserved both
mechanically and electrically in accordance with IEEE-279 and Regulatory
Guide 1.75. For further information see Subsection 9A.5.5.7.
Other requirements of IEEE-279 such as testing, bypasses, manual initiation,
logic seal-in, etc., are described in Subsection 7.3.1.1.2.
7.3-75
Rev. 0
ABWR
(2)
Criteria: GDCs 2, 4, 13, 16, 19, 20, 21, 22, 23, 24, 29, 34, 35, 38, 41, and
44.
(b)
(3)
(b)
(c)
(f)
(g)
Rev. 0
ABWR
(4)
(b)
(5)
(b)
These and all other TMI action plan requirements are addressed in
Appendix 1A.
7.3.2.3 RHR/Wetwell and Drywell Spray ModeInstrumentation and Controls
7.3.2.3.1 General Functional Requirements Conformance
When the RHR System (Loop B and C) is in the WDSC mode, the pumps take suction
from the suppression pool, pass it through the RHR heat exchangers, and inject it into
the wetwell and drywell atmosphere.
In the event that wetwell and/or drywell pressure exceeds a predetermined limit, after
a predetermined interval following a LOCA, the RHR System flow may be manually
diverted to the wetwell and drywell spray mode. The flow of the RHR pump will pass
through the wetwell and drywell spray nozzles, to quench any steam and cool
noncondensables in the interval following a LOCA.
7.3.2.3.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the WDSC mode of the RHR System and the associated codes and
standards applied in accordance with the Standard Review Plan. The following analysis
7.3-77
Rev. 0
ABWR
lists the applicable criteria in order of the listing on the table, and discusses the degree
of conformance for each. Any exceptions or clarifications are so noted.
(1)
10CFR50.55a (IEEE-279)
The WDSC mode of the RHR System is a two-loop, two-division system which
is redundantly designed so that failure of any single element will not interfere
with the required safety action of the system.
All components used for the safety functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11). This mode
of the RHR System (unlike the LPFL mode which is automatically actuated by
LOCA) is automatically actuated should high pressure conditions occur in the
drywell and wetwell air space.
The containment is divided in four quadrants, each housing the electrical
equipment which, in general, corresponds to the mechanically separated
division assigned to each section (i.e., mechanical division A, B, C, and D
correspond with the electrical Divisions I, II, III, and IV, respectively). The
WDSC mode utilizes mechanical Divisions B and C with electrical Divisions II
and III, respectively. Electrical separation is maintained between the
redundant divisions.
The suppression cooling mode pool is designed in accordance with all
requirements of IEEE-279 as described in Subsection 7.3.1.1.3.
A clarification should be made with regard to IEEE-279, Section 4.19. The
parent RHR System annunciates activity at the loop level (i.e., RHR LOOP A,
B, C ACTIVATED). However, the individual mode of the RHR System is not
separately annunciated.
(2)
7.3-78
(a)
Criteria: GDCs 2, 4, 13, 19, 20, 21, 22, 23, 24, 29, 38, and 44.
(b)
Rev. 0
ABWR
System which is part of the ECCS and helps to assure fuel design limits
are not exceeded.
The following clarification should be made with respect to GDC 23: The
RPS is designed to fail in a safe state (i.e., deenergize to actuate). This is
also true for most isolation valves, including the MSIVs. However, the
RHR and RCIC isolation valves are designed to fail as is in that these
are motor-operated vales and require power to both open and close. In
addition, should the RHR or RCIC System be in operation when valve
power is lost, it is essential these valves remain open so the systems can
continue their safety functions.
(3)
(b)
(c)
(f)
(g)
The WDSC mode conforms with all the above-listed RGs assuming the same
interpretations and clarification identified in Subsections 7.3.2.1.2 and
7.1.2.10.
With regard to RG 1.105, there are no initiation setpoints, since the WDSC
mode is not automatically initiated. However, an interlock is provided such
that the drywell spray valves cannot be opened unless a high drywell pressure
signal is present.
The wetwell spray valves do not have an interlock. The operator relies on the
instrumentation that provides indication of the wetwell air space pressure
condition when initiating this mode.
7.3-79
Rev. 0
ABWR
(4)
(b)
(5)
7.3-80
Rev. 0
ABWR
(1)
10CFR50.55a (IEEE-279)
The SPC mode of the RHR System is a three-loop, three-division system which
is redundantly designed so that failure of any single element will not interfere
with the required safety action of the system.
All components used for the safety functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11).
The containment is divided into four quadrants, each housing the electrical
equipment which, in general, corresponds to the mechanically separated
divisions assigned to each section (i.e., mechanical Divisions A, B, C, and D
correspond with electrical Divisions I, II, III, and IV, respectively). The SPC
mode utilizes mechanical Divisions A, B, and C with electrical Divisions I, II,
and III, respectively. Electrical separation is maintained between the
redundant divisions.
The suppression cooling mode pool system is designed in accordance with all
requirements of IEEE-279 as described in Subsection 7.3.1.1.4.
A clarification should be made with regard to IEEE-279, Section 4.19. The
parent RHR System annunciates activity at the loop level (i.e., RHR LOOP A,
B, C ACTIVATED). However, the individual mode of the RHR System is not
separately annunciated.
(2)
Criteria: GDCs 2, 4, 13, 19, 20, 21, 22, 23, 24, 29, 38, and 44.
(b)
(3)
7.3-81
Rev. 0
ABWR
In accordance with the Standard Review Plan for Section 7.3, and with Table
7.1-2, the following RGs are addressed for the SPC mode:
(a)
(b)
(c)
(f)
(g)
The SPC mode complies with all the above listed RGs, except RG 1.105,
assuming the same interpretations and clarifications identified in
Subsections 7.3.2.1.2 and 7.1.2.10 except when the injection valve, and the
suppression pool return, are in the manual override mode. The only interlock
is the LOCA signal which closes the SPC valve to effect automatic transfer to
the LPFL mode.
(4)
(b)
(5)
7.3-82
Rev. 0
ABWR
These and all other TMI action plan requirements are addressed in
Appendix 1A.
7.3.2.5 Standby Gas Treatment SystemInstrumentation and Controls
7.3.2.5.1 Conformance to General Functional Requirements
The Standby Gas Treatment System (SGTS) limits the release to the environment of
halogens and particulates from the leakage air exhaust of the secondary containment
during accident conditions.
7.3.2.5.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the SGTS and the associated codes and standards applied in
accordance with the Standard Review Plan. The following analysis lists the applicable
criteria in order of the listing on the table, and discusses the degree of conformance for
each. Any exceptions or clarifications are so noted.
(1)
10CFR50.55a (IEEE-279)
The SGTS has two electrical divisions and is redundantly designed so that
failure of any electrical component will not interfere with the required safety
action of the system.
Two completely redundant systems consisting of filter trains, fan, and
associated piping are provided.
All components used for the safety functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11).
The SGTS is automatically initiated from isolation signals originating in the
LDS. The system also has full manual actuation capability.
The SGTS utilizes mechanical Divisions B & C with electrical Divisions II & III,
respectively. Electrical separation is maintained between the redundant
divisions.
The SGTS is designed to meet all the requirements of IEEE-279. Detailed
system design descriptions are given in Subsection 7.3.1.1.5.
(2)
Criteria: GDCs 2, 4, 13, 19, 20, 21, 22, 24, 29, 41 and 43.
7.3-83
Rev. 0
ABWR
(b)
(3)
(b)
(c)
(f)
(g)
(b)
7.3-84
Rev. 0
ABWR
(5)
10CFR50.55a (IEEE-279)
The Emergency Diesel Generator Support System, as identified in
Subsection 7.3.1.1.6, is the diesel generator jacket water system, the diesel
generator starting air system, the diesel generator lubrication system, the
diesel fuel transfer system, and the diesel combustion air intake and exhaust
system. Redundancy is provided to assure that single failure of any electrical
component will not interfere with the required safety action of more than one
of three generator systems. The fuel tanks and their interfaces with the diesels
is described in Chapter 9.
All components used for the safety functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11)
A safety analysis is provided for each support system in Chapter 9.
(2)
7.3-85
Rev. 0
ABWR
(b)
(3)
(b)
(c)
(f)
(g)
The diesel generator support systems conform with all the above listed RGs,
assuming the same interpretations and clarifications identified in
Subsections 7.3.2.1.2 and 7.1.2.10.
(4)
(b)
7.3-86
Rev. 0
ABWR
(5)
7.3.2.7 Reactor Building Cooling Water System and Reactor Service Water System
Instrumentation and Controls
7.3.2.7.1 Conformance to General Functional Requirements
The Reactor Building Cooling Water (RCW) System and the Reactor Service Water
System operate during all modes of plant operations. Should low water level occur in
the RCW surge tank, all isolation valves to non-safety-related components close
automatically. If the operator determines later that the non-safety-related components
are operable, cooling flow can be restored by remote manual operation of the
component isolation valves. If a break occurs in the Control Building Basement, water
level sensors close isolation vavlves in both systems in that division.
7.3.2.7.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the RCW and RSW Systems and the associated codes and standards
applied in accordance with the Standard Review Plan. The following analysis lists the
applicable criteria in order of the listing on the table, and discusses the degree of
conformance for each. Any exceptions or clarifications are so noted.
(1)
10CFR50.55a (IEEE-279)
The RCW and the RSW Systems have three independent electrical divisions
and are redundantly designed so that failure of any single electrical
component in a system division will not interfere with the required safety
action of the affected system.
During normal operation, all divisions of the RCW and the RSW Systems
supply safety-related and non-safety-related cooling loads. An RCW surge tank
low level signal (two-out-of-three logic) causes the non-safety-related RCW
loads to be automatically isolated. A LOCA signal will isolate all RCW nonsafety-related loads except the instrument air and CRD oil coolers. This
isolation can also be initiated manually from the control room. Neither of the
above signals will affect the RSW System.
All components used for the safety-related functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11).
7.3-87
Rev. 0
ABWR
The RCW and the RSW Systems utilize mechanical Divisions A, B, and C,
corresponding with electrical Divisions I, II, and III, respectively. Electrical
separation is maintained between the redundant divisions in each system.
The RCW and the RSW Systems are designed to meet all applicable
requirements of IEEE-279. Detailed system design descriptions are given in
Subsection 7.3.1.1.7 and in Section 9.2.
(2)
(3)
(a)
Criteria: GDCs 2, 4, 13, 19, 20, 21, 22, 23, 24, 29, 34, 35, 38 and 44.
(b)
(b)
(c)
(f)
The RCW System conforms with all the above listed RGs, assuming the same
interpretations and clarifications identified in Subsections 7.3.2.1.2 and
7.1.2.10.
(4)
7.3-88
Rev. 0
ABWR
In accordance with the Standard Review Plan for Section 7.3, and with
Table 7.1-2, only BTPs 21 and 22 are considered applicable for the RCW
System. They are addressed as follows:
(a)
(b)
(5)
10CFR50.55a (IEEE-279)
The essential HVAC Systems (HVAC) have two independent electrical
divisions and are redundantly designed so that failure of any single electrical
component will not interfere with the required safety action of the system.
Certain non-safety-related HVAC equipment required to operate during a loss
of offsite power is connected to the onsite power distribution system except
when a LOCA signal exists. The balance of the non-safety-related HVAC
equipment is connected to the normal offsite power distribution system.
7.3-89
Rev. 0
ABWR
All components used for the safety functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11).
The HVAC System utilizes mechanical Divisions A & B corresponding with
electrical Divisions I & II, respectively. Electrical separation is maintained
between the redundant divisions.
The HVAC System is designed to meet all applicable requirements of IEEE279. Detailed system design descriptions are given in Subsection 7.3.1.1.8 and
in Chapter 9.
(2)
(3)
(a)
Criteria: GDCs 2, 4, 13, 19, 20, 21, 22, 23, 24, and 29.
(b)
(b)
(c)
(f)
The HVAC conforms with all the above listed RGs, assuming the same
interpretations and clarifications identified in Subsections 7.3.2.1.2 and
7.1.2.10.
(4)
7.3-90
Rev. 3
ABWR
In accordance with the Standard Review Plan for Section 7.3, and with
Table 7.1-2, only BTPs 21 and 22 are considered applicable for the HVAC
System. They are addressed as follows:
(a)
(b)
(5)
10CFR50.55a (IEEE-279)
The HVAC Emergency Cooling Water (HECW) System has three
independent electrical divisions and is redundantly designed so that failure of
any single electrical component will not interfere with the required safety
action of the system.
The HECW System is manually actuated, but is designed to run continuously
during reactor operation. Should a loss of station power or a LOCA event
7.3-91
Rev. 3
ABWR
occur, the system power sources will automatically switch over to the
emergency diesels. Thus, continuous operation is assured for all plant
conditions.
All components used for the safety functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11).
The HECW System utilizes mechanical Divisions A, B and C corresponding
with electrical Divisions I, II, and III, respectively. Electrical separation is
maintained between the redundant divisions.
The HECW System is designed to meet all applicable requirements of IEEE279. Detailed system design descriptions are given in Subsection 7.3.1.1.9 and
in Chapter 9.
(2)
(3)
(a)
Criteria: GDCs 2, 4, 13, 19, 20, 21, 22, 23, 24, 29, and 44.
(b)
(b)
(c)
(f)
The HECW System conforms with all the above listed RGs, assuming the same
interpretations and clarifications identified in Subsections 7.3.2.1.2 and
7.1.2.10.
7.3-92
Rev. 0
ABWR
(4)
(b)
(5)
10CFR50.55a (IEEE-279)
The HPIN System has two independent electrical divisions and mechanical
divisions and is redundantly designed so that failure of any single electrical
component will not interfere with the required safety action of the system.
One division supplies emergency nitrogen to four ADS valve accumulators
7.3-93
Rev. 0
ABWR
and the other division; to the remaining four ADS valve accumulators. This
level of redundancy is adequate because only the initial LOCA
depressurization requires more than four ADS valves and the Class-1E
accumulators have sufficient capacity for one valve actuation at drywell design
pressure and five actuations at normal drywell pressure.
All components used for the safety-related functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11).
The HPIN System is designed to meet all applicable requirements of
IEEE 279. Detailed system design descriptions are given in
Subsection 7.3.1.1.10 and in Chapter 6.
(2)
(3)
(a)
Criteria: GDCs 2, 4, 13, 19, 20, 21, 22, 23, 24, and 29.
(b)
(b)
(c)
(f)
The HPIN System conforms with all the above listed RGs, assuming the same
interpretations and clarifications identified in Subsections 7.3.2.1.2 and
7.1.2.10.
(4)
7.3-94
Rev. 0
ABWR
In accordance with the Standard Review Plan for Section 7.3, and with
Table 7.1-2, only BTPs 21 and 22 are considered applicable for the HPIN
System. They are addressed as follows:
(a)
(b)
(5)
7.3-95
Rev. 1
ABWR
7.3.4 References
7.3-1
7.3-2
Rev. 0
ABWR
7.3-97 /98
Rev. 0
ABWR
(2)
(3)
(4)
See Subsection 7.1.2.4 which addresses the design basis information required by
Section 3 of IEEE-279.
7.4.1.1 Alternate Rod Insertion FunctionInstrumentation and Controls
The alternate rod insertion (ARI) function is accomplished independently and
diversely from the Reactor Protection System (RPS). Independent sensors (i.e., ECCS
sensors) provide reactor trip signals, via the Recirculation Flow Control System (RFCS),
both to ARI valves (part of the Control Rod Drive System) and to the Rod Control and
Information System (RCIS). The ARI valves (separate from the scram valves), cause
reactor shutdown by hydraulic scram of the control rods. The RCIS, acting upon the
same ARI signals that are provided to ARI valves, causes reactor shutdown by
electromechanical (i.e., through the usage of FMCRD motors) insertion of control
rods.
The RCIS, including the active run-in function of the FMCRD motors and the ARI
valves, are not required for safety, nor are these components qualified in accordance
with safety criteria. However, the FMCRD components associated with hydraulic scram
are qualified in accordance with safety criteria.
The inherent diversity of ARI provides mitigation of the consequences of anticipated
transient without scram (ATWS) events.
7.4.1.2 Standby Liquid Control SystemInstrumentation and Controls
(1)
Function
The instrumentation and controls for the SLCS are designed to initiate and
continue injection of a liquid neutron absorber into the reactor when
manually or automatically called upon to do so. This equipment also provides
7.4-1
Rev. 0
ABWR
the necessary controls to maintain this liquid chemical solution well above
saturation temperature in readiness for injection. The system P&ID is shown
in Figure 9.3-1. The interlock block diagram (IBD) is shown in Figure 7.4-1.
(2)
Classification
The SLCS is a backup method to shut down the reactor to cold subcritical
conditions by independent means other than the normal method by the CRD
System. Thus, the system is considered a safe shutdown system. The SLCS
process equipment, instrumentation, and controls essential for injection of
the neutron absorber solution into the reactor are designed to withstand
Seismic Category I earthquake loads. Any nondirect process equipment,
instrumentation, and controls of the system are not required to meet Seismic
Category I requirements; however, the local and control room mounted
equipment is located in seismically qualified panels.
(3)
Power Sources
The power supply to one motor-operated injection valve, storage tank
discharge valve, and injection pump is powered from Division I, 480 VAC. The
power supply to the other motor-operated injection valve, storage tank outlet
valve, and injection pump is powered from Division II, 480 VAC. The power
supply to the tank heaters and heater controls is connectable to a standby AC
power source. The standby power source is Class 1E from an onsite source and
is independent of the offsite power. The power supply to the main control
room benchboard indicator lights and the level and pressure sensors is
powered from a Class 1E instrument bus.
(4)
Equipment
The SLCS is a special plant-capability event system. No single active
component failure of any plant system or component would necessitate the
need for the operational function of the SLCS. It is included for a number of
special consideration events:
(a)
Plant capability to shut down the reactor without control rods from
normal operation (Chapter 15).
(b)
Plant capability to shut down the reactor without control rods from a
transient incident (Chapter 15).
Although this system has been designed to a high degree of reliability with
many safety system features, it is not required to meet the safety design basis
requirements of the safety-related systems.
7.4-2
Rev. 0
ABWR
(5)
Initiating Circuits
The SLCS is automatically initiated upon receiving an ATWS signal. The SLCS
is initiated manually in the main control room by turning a keylocking switch
for system A or a different keylocking switch for system B to the START
position.
(6)
(7)
(8)
7.4-3
Rev. 0
ABWR
(9)
Actuated Devices
When the SLCS is automatically initiated to inject a liquid neutron absorber
into the reactor, the following devices are actuated:
(a)
(b)
(c)
(b)
(c)
Rev. 0
ABWR
The following items are located in the control room for operation
information:
(i)
Analog Indication
Storage tank level
System pressures
(ii)
Status Lights
Pump or storage tank outlet valve overload trip or power loss
Position of injection line manual service valve
Position of storage tank outlet valve and in-test status
Position of test tank discharge manual service valve
SLCS manually out of service
Pump auto trip
(iii) Annunciators
The SLCS annunciators indicate:
Manual or automatic out-of-service condition of SLCS A
and/or B due to:
- Operation of manual out-of-service switch
- Storage tank outlet valve in test status
Systems Required for Safe Shutdown
7.4-5
Rev. 0
ABWR
The following items are located locally at the equipment for operator
utilization:
(i)
Analog Indication
Storage tank level
System pressures
Storage tank temperature
(ii)
Indicating lamps
Pump status
Storage tank operating heater status
Storage tank mixing heater status
(15) Setpoints
The SLCS has setpoints for the various instruments as follows:
(a)
The high and low standby liquid temperature switch is set to activate the
annunciator at temperatures outside the range allowed for correct
chemical balance of the boron concentration.
(b)
The high and low standby liquid storage tank level switch is set to activate
the annunciator when the level is outside its allowable limits.
(c)
The low standby liquid storage tank level switches are set to trip the
operating pumps when the level is low.
(d) The thermostatic controller and operating heater assure that the
temperature of the liquid is maintained within the range allowed for
correct chemical balance of the boron concentration.
The Technical Specifications for the SLCS are in Chapter 16.
7.4-6
Rev. 0
ABWR
Function
The SDC mode of the RHR System is used during the normal or emergency
reactor shutdown and cooldown. The RHR System P&ID is Figure 5.4-10 and
the RHR System IBD is Figure 7.3-4.
The initial phase of the SDC mode is accomplished following insertion of the
control rods and steam blowdown to the main condenser which serves as the
heat sink.
Reactor shutdown cooling has three independent loops. Each loop consists of
pump, valves, heat exchanger, and instrumentation designed to provide decay
heat removal capability for the core. This mode specifically accomplishes the
following:
(a)
(b)
The RHR mode can accomplish its design objective by a preferred means by
directly extracting reactor vessel water from the vessel shutdown nozzle and
routing it to a heat exchanger and back to the vessel. Cooling water is returned
to the vessel via the feedwater line (Loop A) and via the core cooling injection
nozzles (Loops B and C).
(2)
Classification
Electrical components for the reactor SDC mode of the RHR System are
safety-related and are classified as Class 1E.
(3)
Power Sources
This system utilizes normal plant power sources. These include 6900 VAC for
the pumps, 480 VAC/120 VAC instrument buses, and as backed up by DC
7.4-7
Rev. 0
ABWR
sources. If for any reason the normal plant sources become unavailable, the
system is designed to utilize the emergency buses and sources.
(4)
Equipment
The reactor water is cooled by taking suction from the three SDC suction
nozzles. The water is pumped through the system heat exchanger and back to
the reactor vessel via the feedwater lines (Loop A) and the LPFL injection
nozzles (Loops B and C).
If it is necessary to discharge a complete core load of reactor fuel to the fuel
pool, a means is provided for making a physical intertie between the Spent
Fuel Pool Cooling and Cleanup (SFPC) System and the RHR heat exchangers.
This increases the cooling capacity of the SFPC System to handle the heat load
for this situation. The fuel pool intertie is applied only to Loops B and C (see
Figure 5.4-10 for RHR System P&ID).
(5)
Initiating Circuits
The reactor Shutdown Cooling System is initiated by manual operator actions.
(6)
(7)
(a)
(b)
The RHR heat exchangers and service water are lined up for cooling.
(8)
Redundancy
The reactor SDC System contains three loops. Any two of the three loops is
sufficient to satisfy the cooling requirements for emergency shutdown
cooling. Each loop has it own suction line with three suction valves in series.
In the event one of the suction valves fails closed, normal shutdown cooling is
not available for that loop. The remaining two loops will provide the shutdown
cooling.
7.4-8
Rev. 0
ABWR
Actuated Devices
All valves in the SDC System are equipped with remote manual switches in the
main control room. The only automatically activated modes of the RHR are
the LPFL mode for the ECCS and the suppression pool cooling mode, as
described in Subsections 7.3.1.1.1.4 and 7.3.1.1.4, respectively. Other modes
of RHR are described in Subsections 7.3.1.1.3 and 7.3.1.1.4.
(10) Separation
Since various modes of operation of the RHR System perform safety-related
functions (LPFL suppression pool cooling and wetwell and drywell spray
cooling), any of the system equipment performing safety-related functions
satisfies the appropriate safety separation criteria. The SDC mode of operation
can utilize two diverse techniques. Separation between components utilizes
three completely independent loops and thus satisfies safety separation
criteria in order to accomplish its design basis.
(11) Testability
The reactor SDC pumps (RHR) may be tested to full capacity during normal
plant operation. All valves except those isolated by reactor pressure interlock
in the system may be tested during normal plant operation from the remote
manual switches in the main control room.
The logic is tested by automatic self-test. The sixth test, discussed in
Subsection 7.1.2.1.6, is also applicable here for the reactor SDC mode
function of RHR System.
(12) Environmental Considerations
The only reactor SDC control component located inside the drywell that must
remain functional in the environment is the control mechanism for the
inboard isolation SDC valve. The control and instrumentation equipment
located outside the drywell is selected in consideration of the normal and
accident environments in which it must operate.
The RHR equipment is seismically qualified and environmentally classified as
discussed in Sections 3.2, 3.10, and 3.11.
Systems Required for Safe Shutdown
7.4-9
Rev. 0
ABWR
7.4-10
(1)
(2)
The plant is not experiencing any transient situations. Even though the loss of
offsite AC power is considered unlikely, the remote shutdown panel or
facilities are powered from Class 1E power system buses E and F so that backup
AC power would be automatically supplied by the plant diesel generator.
Manual controls of the diesel generator are also available locally.
(3)
The plant is not experiencing any accident situations. No design basis accident
(including a LOCA) shall be assumed, so that complete control of engineered
safeguard feature systems from outside the main control room shall not be
required.
(4)
(5)
(6)
The initial event that causes the main control room to become inaccessible is
assumed to be such that the reactor operator can manually scram the reactor
before leaving the main control room. If this was not possible, the capability
Rev. 0
ABWR
of opening the RPS logic input power breakers from outside the main control
room can be used as a backup means to achieve initial reactor reactivity
shutdown.
(7)
The main turbine pressure regulators may be controlling reactor pressure via
the bypass valves. However, in the interest of demonstrating that the plant can
accommodate even the loss of the turbine controls, it is assumed that this
turbine generator control panel function is also lost. Therefore, main
steamline isolation is assumed to occur at a specified low turbine inlet pressure
and reactor pressure is relieved through the relief valves to the suppression
pool.
(8)
(9)
It shall be assumed that the event causing the evacuation will not cause any
failure of the DC or AC control power supplies to the remote shutdown panels
or any failure of the DC or AC power feeds to the equipment whose functions
are being controlled from the remote shutdown panels.
The above initial conditions and associated assumptions are very severe and
conservatively bound any similar postulated situation.
7.4.1.4.3 Remote Shutdown Capability Description
(1)
The capability described provides remote control for reactor systems needed
to carry out the shutdown function from outside the main control room and
bring the reactor to hot shutdown and subsequent cold shutdown through
suitable procedures.
(2)
It provides a variation to the normal system used in the main control room
permitting the shutdown of the reactor when feedwater is unavailable and the
normal heat sinks (turbine and condenser) are lost.
(3)
Reactor pressure will be controlled and core decay and sensible heat rejected
to the suppression pool by relieving steam pressure through the automatic
activation of relief valves. Reactor water inventory will be maintained by the
HPCF System. During this phase of shutdown, the suppression pool will be
cooled by operating the RHR System in the SPC mode.
(4)
Manual operation of the relief valves will cool the reactor and reduce its
pressure at a controlled rate until reactor pressure becomes so low that HPCF
System operation is discontinued.
7.4-11
Rev. 0
ABWR
(5)
The RHR System will then be operated in the SDC mode using the RHR
System heat exchanger in the reactor water circuit to bring the reactor to the
cold low pressure condition.
7.4-12
Rev. 0
ABWR
(2)
(ii)
(ii)
(iii) Indicating lights for all valve (with RSS interface) positions and for
the HPCF pump B stop/run
(3)
(ii)
7.4-13
Rev. 0
ABWR
(ii)
The following functions have transfer and control switches located at the
remote shutdown control panels:
Four air-operated safety relief valves (SRVs) (The valves are 125 VDC
solenoid pilot operated.). Three of these valves have switches on the
Division I panel, the fourth valve has switches on the Division II panel.
(b)
(ii)
7.4-14
The following function has transfer and control switches located at the
Division 2 remote shutdown control panel: one air-operated relief valve.
(The valve is 125 volt DC solenoid pilot operated.)
Rev. 0
ABWR
(5)
(ii)
(6)
(ii)
Indicating lights for valve positions and for pump stop/run (A,B)
(ii)
RCW heat exchanger service water inlet valve (A,D,G and B,E,H)
RCW heat exchanger service water outlet valve (A,D,G and B,E,H)
(ii)
Indicating lights for all valve positions and RSW pump stop/run
conditions are provided on both RSS panels.
7.4-15
Rev. 0
ABWR
(7)
(ii)
(ii)
(8)
The following FCS equipment function has transfer and control switches
located on both remote shutdown panels as indicated:
(i)
(9)
7.4-16
Rev. 0
ABWR
(b)
7.4.2 Analysis
7.4.2.1 Alternate Rod Insertion Function
7.4.2.1.1 General Functional Requirements Conformance
The alternate rod insertion (ARI) function is accomplished by the Rod Control and
Information System (RCIS) and the Fine-Motion Control Rod Drive (FMCRD)
Subsystem. This function provides an alternate method of driving control rods into the
core which is diverse from the hydraulic scram system.
The RCIS and the active run-in function of the FMCRD motors are not required for
safety, nor are these components qualified in accordance with safety-related criteria.
However, the FMCRD components associated with hydraulic scram are qualified in
accordance with safety criteria.
The subsystem's inherent diversity provides mitigation of the consequences of (ATWS)
anticipated transient without scram events. This capability is discussed in
Subsection 7.7.1.2.2.
The ARI design is in full compliance with the design considerations cited in
NEDE-31906-P-A (Reference 7.4-1).
7.4.2.1.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the ARI function and the associated codes and standards applied.
In addition to GDCs 13 and 19 (applied to non-safety-related system/ functions in
accordance with the SRP, Section 7.7), GDC 25 and Reg. Guide 1.75 are also addressed
relative to the shutdown characteristics of the subsystem and its interface with the
essential power buses. The following analysis lists the applicable criteria in order of the
listing on the table, and discusses the degree of conformance for each. Any exceptions
or clarifications are so noted.
(1)
10CFR50.55a (IEEE-279)
Although the ARI is not Class 1E, the portions of the FMCRD used for the
hydraulic scram function are qualified as Class 1E. These functions are
7.4-17
Rev. 0
ABWR
(3)
(b)
7.4-18
Rev. 0
ABWR
breaker coordination, and thus meets the intent of position C-1 of Reg.
Guide 1.75.
In addition, each FMCRD inverter has current limiting features to limit
the FMCRD motor fault current. Continuous operation of all the
FMCRD motors at the limiting fault current of the inverter shall not
degrade operation of any Class 1E loads (i.e., the diesel generators shall
be of appropriate design capacity).
7.4.2.2 Standby Liquid Control System (SLCS) Instrumentation and Controls
7.4.2.2.1 General Functional Requirements Conformance
Redundant positive displacement pumps, injection valves, storage tank outlet valves,
and control circuits (Subsection 7.4.1.2) constitute all of the active equipment required
for injection of the sodium pentaborate solution. Indicator lights provide indication on
the reactor control bench board of system status. Testability and redundant power
sources are described in this subsection and Subsection 7.4.1.2.
Chapter 15 examines the system-level aspects of the SLCS under applicable plant events.
Loss of plant instrument air or cooling water will not, by itself, prevent this reactor
shutdown capability.
7.4.2.2.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the Standby Liquid Control System (SLCS) and the associated
codes and standards applied in accordance with the Standard Review Plan. The
following analysis lists the applicable criteria in order of the listing on the table, and
discusses the degree of conformance for each. Any exceptions or clarifications are so
noted.
(1)
10CFR50.55a (IEEE-279)
The SLCS is manually actuated (or automatically actuated for ATWS events)
and serves as a backup method for shutting down the reactor when no control
rods can be inserted from the full power setting. It is not necessary for the
SLCS to meet the single-failure criterion because it is considered redundant
to (and therefore kept independent of) the control rod scram system.
There are two channels of control circuits, discharge pumps and motors,
storage tank discharge valves and injection valves. These two channels are
independent of each other so that failure in one channel will not prevent the
other from operating. No components of the SLCS are required to operate in
the drywell environment. An isolation check valve is the only component
7.4-19
Rev. 0
ABWR
located inside the drywell. Other SLCS equipment are designed to remain
functional following an SSE.
The SLCS design is similar to the GESSAR II design, except the explosive
(squib) injection valves are replaced with motor-operated injection valves. It is
designed to meet all applicable portions of IEEE-279 as clarified above.
(2)
(3)
(a)
(b)
(b)
(c)
(f)
As indicated in Paragraph (1), the SLCS is not required to meet the singlefailure criterion (RG 1.53) since it is designed to be redundant (and diverse)
from the control rod scram system. However, the two channels of active
components assure that no single failure of these components will prevent the
SLCS from accomplishing its safety function. Passive components which are
not redundant include the boron tank, injection pipeline, etc.
With that clarification, the SLCS (in combination with the rod scram system)
fully meets the intent of the Regulatory Guides listed above.
(4)
7.4-20
Rev. 0
ABWR
In accordance with the Standard Review Plan for Section 7.3 and with
Table 7.1-2, only BTPs 21 and 22 are considered applicable for the SLCS. They
are addressed as follows:
(5)
(a)
(b)
Valves
Manual control and position indication is provided in the main control room.
Three independent loops assure that no single failure in the valve electrical
circuitry can result in loss of capability to perform a safety function.
Interlocks are provided to close the valves if a low reactor water level signal is
present or if high reactor pressure exists.
(2)
Instrumentation
Indicators are provided for RHR pump inlet and discharge pressures, heat
exchanger outlet flow, discharge line level, and heat exchanger inlet and
discharge temperatures.
(3)
Alarms
The following system functional alarms apply to all modes of the RHR System
and to each of the three RHR loops except as noted:
(a)
7.4-21
Rev. 0
ABWR
(b)
(c)
(f)
(g)
(j)
(k)
(l)
(4)
(q)
(r)
(s)
Pumps
Manual controls and stop and start indicators are provided in the control
room. Interlocks are provided to trip the pumps if the shutdown suction valves
are not open and no other suction path exists.
Chapter 15 considers the operation and the system-level qualitative aspects of
this system.
Loss of plant instrument air or cooling water will not, by itself, prevent reactor
shutdown capability.
7.4-22
Rev. 0
ABWR
criteria in order of the listing on the table, and discusses the degree of conformance for
each. Any exceptions or clarifications are so noted.
(1)
10CFR50.55a (IEEE-279):
The SDC mode of the RHR System is a three-loop, three-division system which
is redundantly designed so the failure of any single element will not interfere
with the required safety action of the system. As an operating mode of the
RHR System, the system is designed to meet the same requirement as the
ECCS.
All components used for the safety isolation functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11). However,
this mode of the RHR System (unlike the LPFL mode which is automatically
actuated by LOCA) is manually actuated providing reactor pressure and water
level are at permissible levels.
The containment is divided into four quadrants, each housing the electrical
equipment which, in general, corresponds to the mechanically separated
divisions assigned to each section (i.e., mechanical Divisions A, B, C, and D
correspond with electrical Divisions I, II, III, and IV, respectively). The SC
mode utilizes mechanical Divisions A, B, and C with electrical Divisions I, II,
and III, respectively. Electrical separation is maintained between the
redundant divisions.
A clarification should be made with regard to IEEE-279, Section 4.19. The
parent RHR System annunciates activity at the loop level (i.e., RHR LOOP
A,B,C ACTIVATED). However, the individual mode of the RHR System is not
separately annunciated.
Those portions of IEEE-279 which relate to automatically initiated systems are
not applicable to the manually actuated shutdown cooling mode of the RHR
System. However, the system is designed in accordance with all other
requirements of IEEE-279 as described in Subsection 7.4.1.3.
(2)
(b)
7.4-23
Rev. 0
ABWR
(3)
(b)
(c)
(f)
(g)
The SCM conforms with all the above-listed RGs, assuming the same
interpretations and clarifications identified in Subsections 7.3.2.1.2 and
7.1.2.10.
With regard to RG 1.105, there are no actuation setpoints, since the SC mode
is manually initiated. However, reactor pressure and level interlocks are
provided to assure the mode cannot be actuated under the wrong conditions.
These interlocks are derived from shared signals in the Nuclear Boiler System.
(4)
BTP ICSB 3 Isolation of Low Pressure Systems from the High Pressure
Reactor Coolant System
The SDC mode of the RHR System has both inboard and outboard
HP/LP isolation valves on both the suction and injection ends of the
system. The injection end is the same as the LPFL mode and meets the
requirements of B.3 as discussed in Paragraph (4a) of
Subsection 7.3.2.1.2.
The three separate SCM suction lines each have motor-operated HP/LP
isolation valves on both the inboard and outboard sides of the drywell
wall.
Rev. 0
ABWR
There are four sensors (originating from the NBS and shared with other
systems) which monitor reactor pressure and are combined in two-outof-four logic to provide the high reactor pressure interlock signal.
Reactor water Level 3 is also monitored in similar fashion to produce the
low reactor level interlock signal. These two sets of two-out-of-four
signals are combined in OR combination to close each valve
(Figure 7.3-4). Each loop also has a separate signal to isolate on RHR
equipment area ambient high temperature.
The inboard valves receive their interlock signals from Divisions I, II,
and III, while the corresponding outboard valves receive their interlock
signals from Divisions II, III, and I, respectively.
Thus, independence and diversity are utilized in the design in
accordance with measure B.2 of this BTP.
(5)
(b)
(c)
7.4-25
Rev. 0
ABWR
The RSS provides instrumentation and controls outside the main control room to allow
prompt hot shutdown of the reactor after a scram and to maintain safe conditions
during hot shutdown. It also provides capability for subsequent cold shutdown of the
reactor through the use of suitable procedures.
7.4.2.4.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the Remote Shutdown System (RSS) and the associated codes and
standards applied in accordance with the Standard Review Plan. The following analysis
lists the applicable criteria in order of the listing on the table, and discusses the degree
of conformance for each. Any exceptions or clarifications are so noted.
(1)
10CFR50.55a (IEEE-279)
The Remote Shutdown System (RSS) consists of two panels (Division I and
Division II) which are located in separate rooms in the Reactor Building.
The RSS provides remote control capability as defined by the following
interfaces:
System
Total Channels
RSS Interface
A, B, C
A, B
B, C
A, B, C, D
A, B
A, B, C
A, B
A, B, C
A, B
I, II, III, IV
I, II
B, C
The RSS is designed such that it does not degrade the capability of the interfacing
systems. All equipment is qualified as Class 1E, consistent with the safety-related
interfaces.
Separation and isolation is preserved both mechanically and electrically in accordance
with IEEE-279 and Regulatory Guide 1.75.
With regard to Paragraph 4.2 of IEEE-279, a single-failure event is assumed to have
occurred to cause the evacuation of the control room. The RSS is not designed to
7.4-26
Rev. 0
ABWR
accommodate additional failures for all scenarios. The effects of such failures are
analyzed as follows:
The loss of one complete RHR loop could extend the time needed for the reactor to
reach the emergency shutdown conditions. However, the ability of the RSS to ultimately
facilitate such conditions is not impaired. An analysis was performed for this scenario
using the nominal decay heat curve. The results showed that the time to reach 100 C
with only one RHR loop available varied from 38 to 51.4 hours as the temperature of
the ultimate heat sink varied from 29 to 35C.
In the event of a complete loss of Division II, safe shutdown can be achieved by
depressurizing the reactor with the three SRVs in Division I to the point at which RHR
shutdown cooling can be initiated. This assumes that the operator reaches the RSS
panels in a timely manner (i.e., within 10 minutes after scram). No core uncovering is
expected even though no high pressure coolant makeup capability is available.
In the event of a complete loss of Division I, the reactor can be depressurized with one
SRV in Division II. Therefore, the time required to reach low pressure conditions will
be extended. However, the probability of an event requiring control room evacuation
in addition to a failure resulting in loss of Division I (external to the control room) is so
low that it is not considered credible.
Other sections of IEEE-279 which relate to testability of sensors, etc., are not applicable
to the RSS of itself, but are applicable to the primary systems which interface with the
RSS. All other applicable criteria of IEEE-279 are met by the RSS.
(2)
(3)
(a)
(b)
7.4-27
Rev. 0
ABWR
(b)
(c)
With regard to Regulatory Guide 1.53, a single failure is assumed to have occurred
which caused the need to evacuate the control room. The RSS is not designed to
accommodate an additional failure for all scenarios. The result of postulated worst case
additional failures is discussed in (1) above. Otherwise, the RSS conforms with the
above listed Reg. Guides assuming the same interpretations and clarifications identified
in Subsections 7.3.2.1.1 and 7.1.2.10.
(4)
(5)
7.4.3 References
7.4-1
7.4-28
Rev. 0
ABWR
Cannot open
Closes (A)
Cannot open
Closes (A)
Reactor
injection
Cannot
open
Closes (A)
Closes (M)
Closes (M)
Closes (A)
Closes (A)
Closes (A)
Closes (A)
Radwaste discharge
outboard*
Valve function
Reactor injection
Closes (A)
Closes (A)
7.4-29
Rev. 0
ABWR
7.4-30
Rev. 0
ABWR
Variable Types
Regulatory Guide 1.97 defines five types and three categories of plant
variables for accident monitoring instrumentation. A discussion of these
classifications is provided below. Each variable has been defined as to both
type and classification. Plant variables are divided into types according to the
purpose of the indication to the plant operator. Any one variable may belong
to more than one type.
(a)
Type A
Type A are those variables to be monitored that provide the primary
information required to permit the control room operators to take the
specified manual actions for which no automatic control is provided and
that are required for safety systems to accomplish their safety functions
for design basis accident events.
Primary information is information that is essential for the direct
accomplishment of the specified safety function. It does not include
those variables that are associated with contingency (or backup) action
that may also be identified in written procedures or guidelines.
Type A variables are limited to those variables which are necessary
(primary) to alert the control room operator of the need to perform
preplanned manual actions for safety systems to perform their safety
functions, such as, initiating suppression pool cooling and containment
spray to permit the systems to perform safety functions for which no
automatic system controls are provided. Variables that require actions
specified by the Emergency Procedure Guidelines (EPGs) in response to
7.5-1
Rev. 0
ABWR
Type B
Type B are those variables that provide information to the control room
operators to indicate whether plant safety functions are being
accomplished, including reactivity control, core cooling, maintaining
reactor coolant system integrity, and maintaining containment integrity.
(c)
Type C
Type C are those variables that provide information to the control room
operators to indicate that barriers to fission product release have the
potential for being breached or have been breached. These barriers are
the fuel cladding, primary coolant pressure boundary, and primary
containment.
The sources of potential breach are limited to the energy sources within
the cladding, coolant boundary, or containment.
(d) Type D
Type D are those variables that provide information to the control room
operators to indicate the successful operation of individual safety
systems or other systems important to safety.
Type D variables should provide information to permit the control room
operators to ascertain the operating status of each individual safety
system and other systems important to safety to that extent necessary to
determine if each system is operating or can be placed in operation to
help mitigate the consequences of an accident.
7.5-2
Rev. 0
ABWR
(e)
Type E
Type E are those variables monitored to determine the magnitude of
release of radioactive materials and to assess the continuation of such
releases.These variables should permit the control room operators to
monitor the effluent discharge paths and environs within the site
boundary to ascertain if there have been significant releases (planned or
unplanned) of radioactive materials and to continually assess such
releases.
In particular, Type E variables monitor:
(i)
(ii)
Categories of Variables
The design and qualification criteria for the instrumentation used to measure
the various variables are divided into three categories that provide a graded
approach to instrumentation criteria, depending on importance to safety of
the variables.
In general, Category 1 provides for full qualification, redundancy, and
continuous real-time display and requires onsite (standby) power. Category 2
provides for qualification but is less stringent in that it does not (of itself)
include seismic qualification, redundancy, or continuous display and requires
only a high-reliability power source (not necessarily standby power).
Category 3 is the least stringent. It provides for high-quality commercial-grade
equipment that requires only offsite power.
(a)
Category 1 represents the most stringent criteria and is used for key
variables. Key variables are those parameters that most directly indicate
the accomplishment of a safety function. All Type A variables are
considered to be Category 1. For Types B and C, the key variables are
Category 1, while backup variables are generally Category 3.
(b)
7.5-3
Rev. 0
ABWR
(c)
(3)
Equipment Qualification
(b)
Redundancy
(c)
Power Sources
Quality Assurance
(f)
(g)
Range
Interfaces
(j)
(k)
Human Factors
(l)
Direct Measurement
Type A Variables
Information Systems Important to Safety
Rev. 0
ABWR
Normal operations
(ii)
(Table 5.7-4)
(Table 5.7-5)
(Table 5.7-6)
(v)
(Table 5.7-7)
Special Events
7.5-5
Rev. 0
ABWR
The required manual actions are summarized in Table 7.5-8 along with
the associated variables.
The EPGs were also reviewed to determine if there are other variables
not specifically identified by Chapter 15 which are associated with
required operator actions. Table 7.5-8 includes these additional
variables and actions which result from a review of the following
guidelines included in Appendix 18A:
(i)
RPV Control
(ii)
Rev. 0
ABWR
Drywell Pressure
Requirements for monitoring of drywell pressure are specified for both
narrow range (from about -34.32 kPaG to + 34.32 kPaG) and wide range
(from 0 to 110% of design pressure). The narrow range monitoring
requirement is satisfied in the existing safety-related design by the four
divisions of drywell pressure instruments which provide inputs to the
initiation of the reactor protection (trip) system (RPS) and the
emergency core cooling systems (ECCS). The requirement for
unambiguous wide range drywell pressure monitoring are satisfied with
two channels of drywell pressure instrumentation integrated with two
channels of wetwell pressure instrumentation. Given the existence of (1)
the normal pressure suppression vent path between the drywell and
wetwell and (2) the wetwell to drywell vacuum breakers, the long-term
pressure within the drywell and wetwell will be approximately the same.
Therefore, if the two wide range drywell pressure indications disagreed,
the operator could refer to the wetwell containment pressure
indications to determine which of the two drywell pressure indications is
correct. In order to provide full range pressure comparisons between
the drywell wide range and wetwell pressure instruments, the drywell
7.5-7
Rev. 0
ABWR
pressure instrument range is 689.4 kPa. This value exceeds the required
value of 110% of design pressure.
(b)
(c)
7.5-8
Rev. 0
ABWR
of the wide range level (WRL) sensors (i.e., the water level is in the fuel
zone range) and the two channels of fuel zone level instrumentation
disagree, the EOPs instruct the operator to use the lower of the two and
return the water level back up into the range of the WRL
instrumentation. Using the four divisions of WRL instruments, an
unambiguous indication of vessel water level can be determined, despite
a postulated failure of a single instrument channel or division, and the
operator could safely continue the execution of appropriate accident
instigation activities as defined by the EOPS.
(d) BWR Core Temperature
Regulatory Guide 1.97 requires BWR core temperature
(thermocouples) as a diverse indication of adequate core cooling.
General Electric and the BWR Owners Group have taken exception to
this requirement for diverse indication based upon studies regarding the
relationship between reactor water level and adequate core cooling. It is
General Electrics view that no instrumentation other than RPV water
level indication is required to assure indication of adequate core
cooling.
(e)
(f)
7.5-9
Rev. 0
ABWR
7.5-10
Rev. 0
ABWR
(k)
(l)
7.5-11
Rev. 0
ABWR
Regulatory Guide 1.97 suggests two ranges for suppression pool water
level (i.e., bottom of ECCS suction to 1.5m above normal water level and
top of vent to top of weir wall [BWR 6, Mark III Containment]). The
ABWR provides:
(i)
(ii)
Two (2) wide range wetwell level instruments are sufficient to control
water level at the high level and at the low level by using the highest
reading and the lowest reading instruments, respectively, should the
instruments disagree. In addition, The low end measurement to the
centerline of the ECCS suction piping is considered sufficient since this
level measurement is low enough to allow control of the pump vortex
limits.
(Note: See drywell water level for instrument range overlap).
(o)
7.5-12
Rev. 0
ABWR
7.5-13
Rev. 0
ABWR
Category 2
Category 3
1. Equipment Qualification
The instrumentation is qualified in accordance Same as Category 1
with Regulatory Guide 1.89, Qualification of
Class 1E Equipment for Nuclear Power
Plants, and the methodology described in
NUREG-0588, Interim Staff Position on
Environmental Qualification of Safety-Related
Electrical Equipment.
No specific provision
No specific provision
No specific provision
No specific provision
7.5-14
No specific provision
Rev. 0
ABWR
Category 2
Category 3
2. Redundancy
No single failure within either the
No specific provision
accident-monitoring instrumentation, its
auxiliary supporting features, or its power
sources concurrent with the failures that are a
condition or result of a specific accident
should prevent the operators from being
presented the information necessary for them
to determine the safety status of the plant and
to bring the plant to and maintain it in a safe
condition following that accident. Where
failure of one accident-monitoring channel
results in information ambiguity (that is, the
redundant displays disagree) that could lead
operators to defeat or fail to accomplish a
required safety function, additional
information should be provided to allow the
operators to deduce the actual conditions in
the plant. This is accomplished by providing
additional independent channels of
information of the same variable (addition of
an identical channel) or by providing an
independent channel to monitor a different
variable that bears a known relationship to the
multiple channels (addition of a diverse
channel). Redundant or diverse channels are
electrically independent and physically
separated from each other and from
equipment not classified important to safety
in accordance with Regulatory Guide 1.75,
Physical Independence of Electric Systems,
up to and including any isolation device.
Within each redundant division of a safety
system, redundant monitoring channels are
not needed except for steam generator level
instrumentation in two-loop plants.
No specific provision
7.5-15
Rev. 0
ABWR
Category 2
Category 3
The instrumentation is
energized from a
high-reliability power
source, not necessarily
standby power, and
backed up by batteries
where momentary
interruption is not
tolerable.
No specific provision
3. Power Source
The instrumentation is energized from station
standby power sources as provided in
Regulatory Guide 1.32, Criteria for SafetyRelated Electric Power Systems for Nuclear
Power Plants, and is backed up by batteries
where momentary interruption is not
tolerable.
4. Channel Availability
The instrumentation channel is available prior
to an accident except as provided in
Paragraph 4.11, Exception, as defined in
IEEE-279, 1971, Criteria for Protection
Systems for Nuclear Power Generating
Stations, or as specified in the technical
specifications.
No specific provision
The out-of-service
interval is based on
normal technical
specification
requirements on out-ofservice for the system it
serves where
applicable or where
specified by other
requirements.
5. Quality Assurance
The recommendations of the following
regulatory guides pertaining to quality
assurance are followed:
Same as Category 1 as
modified by the
following:
Since some
instrumentation is less
important to safety
than other
instrumentation, it is not
necessary to apply the
same quality assurance
measures to all
instrumentation. The
quality assurance
requirements that are
implemented provide
control over activities
affecting quality to an
extent consistent with
the importance to safety
of the instrumentation.
7.5-16
The instrumentation is
of high-quality
commercial grade and
is selected to withstand
the specific service
environment.
Rev. 0
ABWR
Category 2
Category 3
7.5-17
Rev. 0
ABWR
Category 2
Category 3
Same as Category 1
7. Range
If two or more instruments are needed to
Same as Category 1
cover a particular range, overlapping of
instrument span is provided. If the required
range of monitoring instrumentation results in
a loss of instrumentation sensitivity in the
normal operating range, separate instruments
are used.
Same as Category 1
8. Equipment Identification
[See also item 11]
Types A, B, and C instruments designated as
Categories 1 and 2 are specifically identified
with a common designation on the control
panels so that the operator can easily discern
that they are intended for use under accident
conditions.
Same as Category 1
No specific provision
No specific provision
9. Interfaces
7.5-18
Same as Category 1
Same as Category 1
Rev. 0
ABWR
Category 2
Category 3
Same as Category 1
Same as Category 1
Same as Category 1
No specific provision
Same as Category 1
Same as Category 1
Same as Category 1
Same as Category 1
Same as Category 1
7.5-19
Rev. 0
ABWR
Category 2
Category 3
Same as Category 1
Same as Category 1
7.5-20
Rev. 0
ABWR
Range Required
Type
Category
Discussion Section
Neutron Flux
Boron Concentration
01000 ppm
93.3C to 1260C
0 to10.35 MPaG
B,C,D
Drywell Pressure
B,C,D
Subsection 7.5.2.1(2)(a)
Top to Bottom
B,C
Subsection 7.5.2.1(2)(e)
B,C
Subsection 7.5.2.1(2)(c)
Subsection 7.5.2.1(2)(n)
Subsection 7.5.2.1(2)(n)
(None specified)
Subsection 7.5.2.1(2)(o)
Containment Area
Radiation
C,E
Subsection 7.5.2.1(2)(f)
Wetwell Pressure
A,B,C
Subsection 7.5.2.1(2)(b)
Primary Containment
Isolation Valve Position
Subsection 7.5.2.1(2)(g)
Coolant Gamma
370 Bq to 370Bq/ml or
C
TID-14844 Source Term in
Coolant Volume
Coolant Radiation
RHR Flow
HPCF Flow
4.4C to 176.7C
RCIC Flow
Subsection 7.5.2.1(2)(d)
Subsection 7.5.2.1(2)(h)
Subsection 7.5.2.1(2)(m)
7.5-21
Rev. 0
ABWR
Category
Discussion Section
Subsection 7.5.2.1(2)(o)
SRV Position
Feedwater Flow
Plant Specific
4.4C to 140C
A, D
Subsection 7.5.2.1(2)(i)
Drywell Atmosphere
Temperature
4.4C to 226.7C
Subsection 7.5.2.1(2)(j)
Drywell/Wetwell
Hydrogen Concentration
030 Volume%
Subsection 7.5.2.1(2)(k)
Drywell/Wetwell
Oxygen Concentration
010 Volume%
Subsection 7.5.2.1(2)(k)
Wetwell Atmosphere
Temperature
4.4C to 226.7C
Subsection 7.5.2.1(2)(l)
Secondary Containment
Airspace (effluent)
Radiation Noble Gas
37 pBq/cm3 to
37MBq/cm3
Containment Effluent
37 pBq/cm3 to
RadioactivityNoble Gas 0.37Bq/cm3
4.4C to 93.3C
Emergency Ventilation
Damper Position
Purge FlowsNoble
Gases and Vent Flow
Rate
37 PBq/cm3 to 0.37
E
Bq/cm3
0110% Vent Design Flow
Identified Release
PointsParticulates and
Halogens
37 nBq/cm3 to 3.7
E
mBq/cm3
0110% Vent Design Flow
Variable
Cooling Water
Temperature to ESF
System Components
7.5-22
Range Required
Rev. 0
ABWR
Category
Airborn Radiohalogens
and Particulates
37 Bq/cm to 37Bq/cm
Meteorological Data
(Wind Speed, Wind
Direction, and
Atmospheric Stability)
0360
09.8 m/s
On Site Analysis
Capability (Primary
Coolant, Sump and
Space Containment Air
Grab Sampling)
Refer to Regulatory
Guide 1.97
Variable
Range Required
3
Secondary Containment
Area Temperature
Secondary Containment
Area Radiation
10 3 Gy/h to
102 Gy/h
Discussion Section
Portable Instruments *
Wetwell Pressure
7.5-23
Rev. 0
ABWR
Event Description
NSOA
Event Figure
No.
Tier 2 Section No.
Manual Action
Variables*
15A.6-7
15A.6.3.3 Event 7
PRPV, LRPV
15A.6-8
15A.6.3.3 Event 8
15A.6-9
15.4.5
PRPV, LRPV
15A.6-10
15.3.2
PRPV, LRPV
15A.5-11
15.3.1
PRPV, LRPV
15A.6-12
15.2.4
15A.6-13
15.2.4
15A.6-14
15.2.7
PRPV, LRPV
15A.6-15
15.1.1
,PRPV, LRPV
15A.6-16
15.1.2
PRPV, LRPV
15A.6-17
15.1.3
PRPV, LRPV
15A.6-18
15.2.1
PRPV, LRPV
15A.6-19
15.2.3
15A.6-20
15.2.5
PRPV, LRPV
15A.6-21
15.2.2
TSP ,PRPV,LRPV
15A.6-22
15.2.6
7.5-24
Rev. 0
ABWR
NSOA Event
Figure No.
Tier 2 Section
No.
Manual Action
Variables*
15A.6-23
15.5.1
15A.6-24
15.1.4
TSP,PRPV,LRPV
15A.6-25
15.4.1
15A.6-26
15.2.3
TSP,PRPV,LRPV
15A.6-27
15.2.2
TSP,PRPV,LRPV
7.5-25
Rev. 0
ABWR
NSOA Event
Figure No.
Tier 2 Section
No.
Manual Action
Variables*
15A.6-28
15.4.8
None
15A.6-29
15.4.9
PRPV,LRPV,
15A.6-30
15.4.2
None
15A.6-31
15.7.4
R2C
15.6.5
H2C,O2C , LRPV ,
LSP ,PRPV ,PDW
15A.6-33
15.6.4
TSP ,PRPV,LRPV
15A.6-38
15.4.4
PRPV,LRPV
15.4.5
,LRPV
15.3.2
LRPV
15A.6-41
15.3.1
PRPV,LRPV
15A.6-42
15.2.9
TRPV
15A.6-43
15.1.6
TRPV
15.1.2
PRPV,LRPV
15A.6-45
15.1.3
PRPV,LRPV
15A.6-46
15.2.1
TSP,PRPV,LRPV
15A.6-48
15.2.3
TSP ,PRPV,LRPV
15A.6-49
15.2.2
TSP ,PRPV,LRPV
15A.6-50
15.4.7
None
15A.6-51
15.3.3
PRPV,LRPV
15A.6-52
15.3.4
PRPV,LRPV
7.5-26
Rev. 0
ABWR
Tier 2 Section
No.
Manual Action
Variables*
15A.6-53
15.7.5
None
15A.6-54
15.8
TSP,PRPV,LRPV,
PDW
15A.6-55
15A.6.6.3
TSP,LSP,LRPV,PRPV
Event 55
15A.6-56
15A.6.6.3
TSP,,LRPV,PRPV
Event 56
Event Description
7.5-27
Rev. 0
ABWR
Variable*
Source
TSP
PRPV,LRPV
Manual Depressurization
PRPV,LRPV
H2C,O2
N/A for
ABWR
,TSP
,LRPV
TSP ,PRPV
TSP , LSP
LSP ,PRPV
TDW ,TRPV (or PRPV)
LSP ,PRPV
Lc ,PWW
TDW
PWW,LSP
PWW,LSP
PWW,LSP
T2C,R2C,L2C
RE
PRPV,LRPV
PRPV,LRPV
Rc, LRPV, Lc
7.5-28
Rev. 0
ABWR
TDW
Drywell Temperature
TRPV
PRPV
RPV Pressure
PWW
Wetwell Pressure
LRPV
RPV Level
LSP
Neutron Flux
H2C
O2C
PDW
T2C
TemperatureSecondary Containment
R2C
L2C
RE
LC
Drywell Level
RC
7.5-29/30
Rev. 0
ABWR
HP/LP interlocks
A number of observations are cited relative to the evaluation of the instrumentation and
control (I&C) portions of the subject systems:
(1)
The systems themselves and their I&C portion serve design bases that are both
safety and power generation.
(2)
(3)
Some systems provide protective functions in selective minor events and are
not required for other major plant occurrences.
(4)
Some systems have only a small portion of their I&C participating in safety
functions.
(5)
The HP/LP interlocks in this section are an integral part of various modes of
the RHR System functions described in other sections.
(6)
Thi d
7.6-1
t d ith F
M k
403
Rev. 0
ABWR
MRBM Subsystems of the NMS are discussed in Section 7.7. The LPRM and the APRM,
together, are also called the Power Range Neutron Monitor (PRNM).
(1)
System Identification
The purpose of the Neutron Monitoring System (NMS) is to monitor power
generation and, for the safety function part of the NMS, to provide trip signals
to the Reactor Protection System (RPS) to initiate reactor scram under
excessive neutron flux (and power) increase condition (high level) or
neutron flux fast rising (short period) condition. The NMS also provides
power information of operation and control of the reactor to the Plant Process
Computer System (PCS) and the rod block monitor. A block diagram showing
a typical NMS division is shown in Figure 7.6-4a. The operating ranges of the
various detectors are shown in Figure 7.6-4b.
(2)
(3)
Power Sources
The power sources for each system are discussed in the individual circuit
descriptions.
General Description
The startup range neutron monitor (SRNM) monitors neutron flux from the
source range (1.E+3 neutron/cm2) to 15% of the rated power. The SRNM
Subsystem has 10 SRNM channels, each having one fixed in-core regenerative
fission chamber sensor (Figures 7.6-1 and 7.6-2).
7.6-2
Rev. 0
ABWR
(2)
Power Sources
SRNM channels are powered as listed below:
Channels
A,E,J
Bus A (Division I)
B,F
C,G,L
D,H
Loss of a power supply bus will cause the loss of the SRNM channels in a division, but
will result in loss of only one division of instrumentation.
(3)
Physical Arrangement
The 10 detectors are all located at fixed elevation slightly above the midplane
of the fuel region, and are evenly distributed throughout the core. The SRNM
locations in the core, together with the neutron source locations, are shown
in Figure 7.6-1. Each detector is contained within a pressure barrier dry tube
inside the core, with signal output exiting the bottom of the dry tube
undervessel. Detector cables then penetrate the primary containment and are
connected to preamplifiers located in the Reactor Building. The SRNM
preamplifier signals are then transmitted to the SRNM DMC (digital
measurement and control) units in the control room. The DMC units provide
algorithms for signal processing, flux, and power calculations, period trip
margin and period calculations, and provide various outputs for local and
control console displays, recorder, and to the plant process computer system.
There are also the alarm and trip digital outputs for both high flux and short
period conditions, and the instrument inoperative trip to be sent to the RPS
and RCIS separately. The electronics for the SRNMs and their bypasses are
located in four separate cabinets.
(4)
Signal Processing
Over the 10-decade power monitoring range, two monitoring methods are
used: (1) for the lower ranges the counting method which covers from
1.E+3 neutron/cm2 to 1.E+9 neutron/cm2, and (2) for the higher ranges, the
Campbelling technique (mean square voltage, or MSV) which covers from
1.E+8 neutron/cm2 to 1.E+13 neutron/cm2 of neutron flux. In the counting
range, the discrete pulses produced by the sensors are applied to a
7.6-3
Rev. 0
ABWR
Trip Functions
The SRNM scram trip functions are discussed in Section 7.2; rod block trip
functions are discussed in Subsection 7.7.1.2. The SRNM channels also
provide trip signals indicating when a SRNM channel is upscale, down-scale,
inoperative, or bypassed. The SRNM trips are shown in Table 7.6-1.
(6)
7.6-4
Rev. 0
ABWR
(7)
(8)
Testability
Each SRNM channel is tested and calibrated using the procedures listed in the
SRNM instruction manual. Each SRNM channel can be checked to ensure
that the SRNM high flux and period scram functions are operable.
(9)
Environmental Considerations
The wiring, cables, and connectors located within the drywell are designed for
continuous duty in the conditions described in Section 3.11.
The SRNM preamplifiers which are located in the Reactor Building, and the
monitors, which are located in the control room, are designed to operate
under design basis normal and abnormal conditions in those areas. The
SRNM System components are designed to operate during and after certain
design basis events such as earthquakes, accidents, and anticipated
operational occurrences. Environmental qualification is discussed in
Section 3.11.
General Description
The local power range monitor (LPRM) monitors local neutron flux in the
power range. The LPRM provides input signals to the APRM Subsystem
(Subsection 7.6.1.1.2.2) and to the plant computer system
(Subsection 7.7.1.5). See Figures 7.6-1 and 7.6-2.
7.6-5
Rev. 0
ABWR
(2)
(3)
Physical Arrangement
The LPRM Subsystem consists of 52 detector assemblies, each assembly
consisting of four fission chamber detectors evenly spaced at four axial
positions along the fuel bundle vertical direction. The assemblies are
distributed throughout the whole core in evenly spaced locations such that
each assembly is located at every fourth intersection of the water channels
around fuel bundles not containing a control rod blade. The LPRM detector
location is illustrated in Figure 7.6-3.
The LPRM detector is a fission chamber with a polarizing potential of
approximately 100 VDC. The four detectors comprising a detector assembly
are contained in a common tube that houses the automatic traversing in-core
probe (ATIP) calibration tube. The enclosing housing tube contains holes to
allow coolant flow for detector cooling. The whole assembly is installed or
removed from the top of the reactor vessel, with the reactor vessel head
removed. It is referred to as the top entry LPRM assembly. The upper end of
the assembly is held under the top fuel guide plate with a spring plunger. A
permanently installed in-core guide tube and housing is located below the
lower core plate to confine the assembly and to provide a sealing surface
under the reactor vessel.
(4)
Signal Processing
The LPRM detector outputs are connected by coaxial cables from under the
vessel pedestal region and routed through the primary containment
penetration, and through the Reactor Building to be processed for signal
conditioning analog-to-digital conversion function in the control room. The
LPRM signals are connected to the APRM units in the control room, where
the signals are amplified. Such amplified voltage is proportional to the local
neutron flux level. The LPRM signals are then used by the APRM to produce
APRM signals. The 208 LPRM detectors are separated and divided into four
groups to provide four independent APRM signals. Individual LPRM signals
are also transmitted through dedicated interface units (for isolation) to
various systems such as the RCIS, and the plant process computer.
7.6-6
Rev. 1
ABWR
(5)
Trip Functions
The LPRM channels provide alarm signals indicating when an LPRM is
upscale, down-scale, or bypassed. However, such signals are not sent to the
RPS for scram trip or RCIS for rad block.
(6)
(7)
Redundancy
The LPRM detector assemblies are divided into groups. The redundancy
criteria are met in the event of a single failure under permissible APRM bypass
conditions. A scram signal can be generated in the Reactor Protection System
(RPS) as required if the inoperative trip of the APRM is generated as
described in (6).
(8)
Testability
LPRM channels are calibrated using ATIP and data from previous full-power
runs, and are tested using procedures in the applicable instruction manual.
(9)
Environmental Considerations
The detector and detector assembly are designed to operate up to 8.27 MPaG
at an ambient temperature of 302C. The wiring, cables, and connector
located within the drywell are designed for continuous duty. The LPRMs are
capable of functioning during and after certain design basis events, including
earthquakes and anticipated operational occurrences (Sections 3.10 and
3.11).
General Description
7.6-7
Rev. 0
ABWR
(a)
(b)
(2)
Power Sources
APRM channels are powered as listed below:
Channels
A
Bus A (Division I)
The trip units and LPRM channels as well as the OPRM channel associated with each
APRM channel receive power from the same power supply as the APRM channel.
(3)
7.6-8
Signal Conditioning
Rev. 0
ABWR
(a)
APRM
APRM channel electronic equipment averages the output signals from a
selected set of LPRMs. The averaging circuit automatically corrects for
the number of unbypassed LPRM amplifiers providing input signals.
Assignment of LPRMs to the APRM channels is shown in Figure 7.6-1.
The LPRM detector in the bottom position of a detector assembly is
designated Position A. Detectors above A are designated B and C, and
the uppermost detector is designated D.
Reactor core flow signals derived from core plate pressure drop signals
are used in the APRM to provide the flow biasing for the APRM rod
block and thermal power trip setpoint functions. There is also the Core
Flow Rapid Coastdown trip logic in the APRM unit which utilizes the
core flow and thermal power information. The core flow signal is also
used to provide the flow biassing for the MRBM rod block setpoint
functions.
(b)
OPRM
The OPRM utilizes the same set of LPRM signals used by the APRM that
this OPRM channel resides with. Assignment of LPRMs to the four
OPRM channels is identical to that referred to in Figure 7.6-1 which
shows the assignment of LPRMs to APRM channels. Figure 7.6-13 shows
the detailed LPRM assignments to the four OPRM channels, including
the assignment of LPRMs to the OPRM cells. With this configuration,
each OPRM cell receives four LPRM inputs from four LPRM strings at
the four corners of the 4X4 fuel bundle square. For locations near the
periphery where one corner of the square does not include an LPRM
string, the OPRM cells use the inputs from the remaining three LPRM
strings. The overall axial and radial distribution of these LPRMs between
the OPRM channels are uniform. Each OPRM cell has four LPRMs from
all four different elevations in the core. LPRM signals may be input to
more that one OPRM cell within an OPRM channel. The LPRM signals
assigned to each cell are summed and averaged to provide an OPRM
signal for this cell.
The OPRM trip protection algorithm consists of trip logic depending on
signal oscillation magnitude an signal oscillation period. For each cell,
the peak to average value of the OPRM signal is determined to evaluate
the magnitude of oscillation and to be used in the setpoint algorithm.
The OPRM signal sampling and computation frequency is well above the
7.6-9
Rev. 0
ABWR
Trip Function
APRM System trips including OPRM trips are summarized in Table 7.6-2. The
APRM scram trip function is discussed in Section 7.2. The APRM rod block
trip function is discussed in Subsection 7.7.1.2. The APRM channels also
provide trip signals indicating when an APRM channel is upscale, downscale,
bypassed, or inoperative.
For the OPRM trip function, the response signal of any one OPRM cell that
satisfies the conditions and criteria of the trip algorithm will cause a trip of the
associated OPRM channel. Figure 7.6-14 illustrates the trip algorithm logic.
The OPRM trip function does not have its own inoperative trip for insufficient
number of total LPRM inputs in the channel. It follows the APRMs
inoperative trip of insufficient number of LPRMs.
(5)
APRM
One APRM channel may be bypassed at any time. The trip logic will in
essence become two-out-of-three instead of two-out-of-four.
The APRM also sends an interlock signal to the SSLC similar to the
SRNM ATWS Permissive signal (Table 7.6-2). If this signal is a high
level indicating the power is above the setpoint, this will allow the SSLC
to permit ATWS protection action.
(b)
OPRM
The OPRM channel bypass is controlled by the bypass of the APRM
channel it resides with. Bypass of the APRM channel will bypass the
OPRM trip function within this APRM channel. The OPRM also has its
own separate automatic bypass functions: the OPRM trip output from
any cell is bypassed if: (1) the APRM reading of the same channel is
below 30% of rated power or the core flow reading is above 60% of rated
flow; (2) the number of LPRM inputs to this OPRM cell is less than two.
Any LPRM input to an OPRM cell is automatically bypassed if this LPRM
reading is less than 5% of full scale LPRM reading. There is no
requirement as to how many cells per OPRM channel has to be active
since this is controlled by the total number of active LPRMs to the APRM
channel.
7.6-10
Rev. 0
ABWR
(6)
Redundancy
(a)
APRM
There are four independent channels of the APRM monitor neutron
flux, each channel being associated with one RPS division. Any two of
the four APRM channels which indicate an abnormal condition will
initiate a reactor scram via the RPS two-out-of-four logic. The
redundancy criteria are met so that in the event of a single failure under
permissible APRM bypass conditions, a scram signal can be generated in
the RPS as required.
(b)
OPRM
There are four independent and redundant OPRM channels. The above
APRM redundancy condition also applies to OPRM since each OPRM is
a subsystem of each of the four APRM channels. The OPRM trip outputs
also follow the two-out-of-four logic as the APRM since the OPRM trip
outputs are combined with other APRM trip outputs in each APRM
channel to provide the final trip outputs to the RPS. In addition, each
LPRM string with four LPRM detectors provides one LPRM input to
each of the four independent and redundant OPRM channels. This
provides core regional monitoring by redundant OPRM channels.
(7)
Testability
APRM channels are calibrated using data from previous full-power runs and
are tested by procedures in the instruction manual. Each APRM channel can
be tested individually for the operability of the APRM scram and rod-blocking
functions by introducing test signals. This includes the test for the OPRM trip
function. A self-testing feature similar to that described for SSLC is also
provided.
(8)
Environmental Considerations
All APRM equipment is operated in the environments described in
Section 3.11. The APRM is capable of functioning during and after the design
basis events in which continued APRM operation is required (Sections 3.10
and 3.11).
7.6-11
Rev. 0
ABWR
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
Function Identification
The low pressure modes of the RHR System which connect to the reactor
coolant pressure boundary (RCPB) and the instrumentation which protects
them from overpressurization are discussed in this section. Such high
pressure/low pressure (HP/LP) interfaces with the reactor vessel are
exclusive to the RHR System for the ABWR. The RHR P&ID is shown on
Figure 5.4-10. The RHR IBD may be found on Figure 7.3-4.
7.6-12
Rev. 0
ABWR
(2)
Power Sources
The power for the interlocks is provided from the essential power supplies
used for the RHR System and its various modes of operation.
(3)
Equipment Design
Refer to Table 7.6-3 for a list of HP/LP interfaces and the rationale for valve
interlock equipment.
(4)
Circuit Description
At least two valves are provided in series in each of these lines. The RHR
shutdown cooling supply valves have independent sets of interlocks to prevent
the valves from being opened when the primary system pressure is above the
subsystem design pressure or when reactor water level is below Level 3. These
valves also receive a signal to close when reactor pressure is above system
pressure, or reactor water level is below Level 3. An additional interlock is
RHR equipment area ambient temperature (not shown on Table 7.6-3).
The RHR shutdown cooling/LPFL injection valve is interlocked to prevent
valve opening whenever the reactor pressure is above the subsystem design
pressure, and automatically closes whenever the reactor pressure exceeds the
subsystem design pressure. This valve must operate for long-term cooling, and
has a remote testable check valve downstream. The check valve position can
be confirmed at any time.
(5)
(6)
(7)
7.6-13
Rev. 0
ABWR
and diverse interlocks to prevent the valves from being opened under the
following conditions (Subsection 7.4.2.3.2 (4a)):
(8)
(a)
(b)
(c)
Actuated Devices
The motor-operated valves are the actuated devices.
(9)
Separation
Separation is maintained in the instrumentation portion of the HP/LP
interlocks by assigning the signals for the electrically controlled valves to ESF
separation divisions. The pressure and level sensors are supplied from the
Nuclear Boiler System and are shared with other systems. There is one sensor
from each of the four divisions, whose signal is passed through optical isolators
and then the two-out-of-four voting logic (in combination with the signals
from the other three divisions). The resultant signal is used to actuate each
valve. Each division has its own isolation and two-out-of-four voting logic
hardware (sheet 2 of RHR IBD, Figure 7.3-4).
(10) Testability
Since the HP/LP interlock valves are specifically designed to close under all
conditions for normal reactor pressure, they cannot be tested during reactor
operation. However, the sensors and logic can be tested during reactor
operation in the same manner that the LPFL sensors and logic are tested.
Refer to Subsection 7.3.1.1.1.4, 3(g) for a discussion of typical LPFL testing.
(11) Environmental Considerations
The instrumentation and controls for the HP/LP interlocks are qualified as
Class 1E equipment. The sensors are mounted on local instrument panels and
the control circuitry is housed in control panels in the control room.
(12) Operational Considerations
The HP/LP interlocks are strictly automatic. There is no manual bypass
capability. If the operator initiates the RHR System, the interlocks will prevent
RHR System exposure to high reactor pressure.
(13) Reactor Operator Information
7.6-14
Rev. 0
ABWR
The status of each valve providing the HP/LP boundary is indicated in the
control room. The state of the sensors is also indicated in the control room.
(14) Setpoints
See Chapter 16 for setpoints and margin.
7.6.1.4 Not Used
7.6.1.5 Wetwell-to-Drywell Vacuum Breaker SystemInstrumentation and Controls
This system is described in Chapter 6.
7.6.1.6 Containment Atmospheric Monitoring (CAM) SystemInstrumentation and
Controls
(1)
System Identification
The CAM System (Figures 7.6-7 and 7.6-8) consists of two independent but
redundant Class 1E divisions (I and II), which are electrically and physically
separated. Each CAM division has the capability of monitoring the total
gamma-ray dose rate and concentration of hydrogen and oxygen (H2/O2) in
the drywell and/or the suppression chamber during plant operation, and
following a LOCA event.
There are two radiation monitoring channels per division; one for monitoring
the radiation level in the drywell and the other for monitoring the radiation
level in the suppression chamber. Each monitoring channel consists of an ion
chamber detector, a digital log radiation monitor, and a recorder. Each
radiation monitoring channel provides alarm indication in the control room
on high radiation levels and also if the channel becomes inoperative.
Each divisional H2/O2 monitoring channel consists of valves, pumps, and
pipes used to extract samples of the atmosphere in the drywell or the
suppression chamber and feed the extracted air sample into an analyzer and
monitor for measurement, recording, and for alarm indication on high
concentration of gas levels.
The piping used for the gas extraction is made of stainless steel and utilizes
heat tracing to keep the pipes dry and free of moisture condensation.
(2)
Power Sources
Each CAM Subsystem is powered from divisional 120 VAC instrument bus.
The same Class 1E divisional 120 VAC power source also supplies the heat
tracing blanket used for the sampling lines.
7.6-15
Rev. 0
ABWR
(3)
Initiating Circuits
Each divisional gamma radiation monitoring channel can be energized
manually by the operator or automatically by the LOCA signal. For the manual
mode, the gamma radiation monitor is on continuously during plant
operation and remains on until power is turned off by the operator.
In the power off mode, the channel will be activated automatically in the
presence of a LOCA (high drywell pressure or low reactor water level).
Each divisional H2/O2 monitoring subsystem (except for the two sampling
pumps) is powered continuously during plant operation. One pump is
controlled by an operator and is used during reactor operation and the other
is turned on by the LOCA signal to allow measurement during an accident.
The heat tracing used in each H2/O2 sample line is temperature controlled to
prevent moisture condensation in the pipes.
Each divisional H2/O2 analyzer and monitor can selectively measure the
atmosphere in the drywell or the suppression chamber.
Division I and II LOCA signals are provided to the CAM System from the RHR
System. These signals are based on two-out-of-four logic signals for the high
drywell pressure or low reactor water level.
(4)
(5)
Divisional Separation
The two CAM Subsystems are electrically and physically separated so that no
single design basis event is capable of damaging equipment in more than one
CAM division. No single failure or test, calibration, or maintenance operation
can prevent function of more than one division.
(6)
7.6-16
Rev. 0
ABWR
(7)
Environmental Consideration
The CAM System is qualified Seismic Category I and is designed for operability
during normal and post-accident environments.
(8)
Operational Considerations
The following information is available to the reactor operator:
(a)
(b)
(9)
7.6-17
Rev. 0
ABWR
The SPTM system IED is shown on Figure 7.6-11. Control system logic is shown on the
IBD (Figure 7.6-12).
7.6.1.7.2 Power Sources
The instrumentation and controls of the SPTM System are powered by four divisionally
separated 120 VAC buses (Divisions I, II, III and IV).
7.6.1.7.3 Equipment Design
The SPTM System configuration is shown in Figures 7.6-9 and 7.6-10. There are eight
temperature circumferential sensor locations (Figure 7.6-9), which are chosen based
upon the following considerations:
(1)
(2)
Each SRV is in direct sight of two sets of temperature sensors within 9 meters.
(3)
The sensors are not in direct paths of jet impingement such as horizontal vent
flow and SRV quencher discharge.
(4)
The sensors can be located without structural interference from the two
equipment and personnel access tunnels.
7.6-18
(1)
Sensors are located away from jet paths from horizontal vents and SRV
discharge.
(2)
Sensors are located at least 1m away from any wall or 160 mm structural
member.
(3)
Rev. 0
ABWR
(4)
(5)
Sufficient sensors are located to measure the average bulk suppression pool
temperature under accident conditions when the pool level drops to a level
where complete condensation of vent flow and SRV discharge is still assured
(i.e., 610 mm above the top of the first row of horizontal vents).
Electrical wiring for each sensor is terminated, for sensor replacement or maintenance,
in the wetwell. This termination is sealed for moisture protection from condensation or
wetwell sprays. Division I, II, III and IV sensors are wired through Division I, II, III or IV
electrical penetrations, respectively. Division I, II, III or IV sensor signals are wired to
the Remote Shutdown System all sensor signals multiplexed to the main control room
via the respective Division I, II, III or IV essential multiplexers.
7.6.1.7.4 Signal Conditioning
The suppression pool temperatures within a division are average to determine a mean
temperature of the pool. The average is corrected for failed sensors. Sensors exposed to
air temperature are also excluded.
7.6.1.7.5 Trip Function
The SPTM system provides trip signals for each of the four divisions (for two-out-of-four
logic) indicating when the suppression pool temperature has exceeded the high limit.
7.6.1.7.6 Bypasses and Interlocks
The SPTM System has no bypasses and interlocks. A division of sensors can be bypassed
to allow maintenance.
7.6.1.7.7 Control Action
The SPTM System initiates RHR suppression pool cooling, RCW load shedding and RPS
scram signaling. It also provides measurement, indication, and recording, and initiates
alarms in the main control room and in the remote shutdown panel.
7.6.1.7.8 Divisional Separation
The four SPTM System divisions are electrically separated so that no single design basis
event is capable of damaging equipment in more than one division. No single failure or
test, calibration, or maintenance operation can prevent function of more than one
division.
7.6-19
Rev. 0
ABWR
Rev. 0
ABWR
7.6.2 Analysis
7.6.2.1 Neutron Monitoring SystemInstrumentation and Controls
The analysis for the trip inputs from the Neutron Monitoring System (NMS) to the
Reactor Protection (trip) System are discussed in Subsection 7.2.2.
The automatic traversing in-core probe (ATIP) is a non safety-related subsystem of the
NMS and is analyzed along with the other non safety subsystems in Subsection 7.7.2.
This analysis section covers only the safety-related subsystems of the NMS. These include
the following:
(1)
(2)
(b)
(2)
7.6-21
Rev. 0
ABWR
(b)
10CFR50.55a (IEEE-279)
The safety-related subsystems of the neutron monitoring system consist of four
divisions which correspond and interface with those of the RPS. This
independence and redundancy assure that no single failure will interfere with
the system operation.
The 10 SRNM channels are divided into four divisions and independently
assigned to three bypass groups such that up to three SRNM channels are
allowed to be bypassed at any time while still providing the required
monitoring and protection capability.
There are 52 LPRM assemblies evenly distributed in the core. There are four
LPRM detectors on each assembly, evenly distributed from near the bottom of
the fuel region to near the top of the fuel region (Figure 7.6-3). A total of 208
detectors are divided and assigned to four divisions for the four APRMs. Any
single LPRM detector is only assigned to one APRM division. Electrical wiring
and physical separation of the division is optimized to satisfy the safety-related
system requirement. With the four divisions, redundancy criteria are met,
since a scram signal can still be initiated with a postulated single failure under
7.6-22
Rev. 0
ABWR
(3)
(a)
(b)
(b)
(c)
(f)
(g)
7.6-23
Rev. 0
ABWR
(4)
(b)
(5)
7.6-24
Rev. 0
ABWR
criteria in order of the listing on the table, and discusses the degree of conformance for
each. Any exceptions or clarifications are so noted.
(1)
10CFR50.55a (IEEE-279):
Each safety-related PRM subsystem, except for the drywell sump discharge
radiation monitor, utilizes four redundant divisional channels in a two-out-offour voting logic to initiate the protective action. This redundancy satisfies the
single-failure criterion such that a failure of a single element will not interfere
with the system to perform its intended safety function. The drywell sump
discharge radiation monitor consists of one channel per drywell sump, and is
used to terminate the transfer of the liquid waste to the Radwaste Building
when the high radiation level is detected in the discharged liquid waste.
Failure of this channel to isolate the drain line is not considered detrimental
to plant safety or operation. Failure of the radiation channel will be indicated
by the monitor and the operator will be alerted in time to take corrective
action.
All components used for the safety-related functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11).
Electrical separation is maintained between the redundant divisions. All
applicable requirements of IEEE-279 are met by the safety-related subsystem
of the PRM System.
(2)
(3)
(a)
CriteriaGDCs 2, 4, 13, 16, 19, 20, 21, 22, 23, 24, and 28.
(b)
(b)
7.6-25
Rev. 0
ABWR
(c)
(f)
(g)
(b)
(5)
7.6-26
Rev. 0
ABWR
10CFR50.55a (IEEE-279)
The HP/LP interlocks are an integral part of the RHR System, which is
designed to meet the requirements of IEEE-279 as discussed in
Subsections 7.4.2.3.2 and 7.3.2.1.2.
(2)
7.6-27
Rev. 0
ABWR
(b)
(3)
(b)
(c)
(f)
(g)
(4)
7.6-28
(a)
(b)
(c)
Rev. 0
ABWR
10CFR50.55a (IEEE-279)
The CAMS consists of two divisions which are redundantly designed so that
failure of any single element will not interfere with the system operation.
Electrical separation is maintained between the redundant divisions.
All components used for the safety-related functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11).
The system can be actuated manually by the operator, or it is automatically
initiated by a LOCA signal (high drywell pressure or low reactor water level).
7.6-29
Rev. 0
ABWR
The CAMS does not actuate nor interface with the actuation of any other
safety-related system. Therefore, any portion of IEEE-279 which pertains to
such interfaces is not applicable. All other applicable requirements of
IEEE-279 are met with the CAMS.
(2)
(b)
(3)
(b)
(c)
(f)
(g)
Rev. 0
ABWR
(b)
(5)
(b)
7.6-31
Rev. 0
ABWR
criteria in order of the listing on the table, and discusses the degree of conformance for
each. Any exceptions or clarifications are so noted.
(1)
10CFR50.55a (IEEE-279)
The SPTM System consists of four divisions which are redundantly designed
so that failure of any single element will not interfere with the system
operation. There are four levels of temperature monitoring within each
division. Electrical separation is maintained between the redundant divisions.
All components used for the safety-related functions are qualified for the
environments in which they are located (Sections 3.10 and 3.11).
The SPTM system continuously operates during plant operation. It does,
however, automatically initiate RHR for suppression pool cooling, initiates
RCW for load shedding to increase suppression pool cooling and generates
four divisional trip signals for RPS. Therefore, the portions of IEEE 279 which
pertain to actuation of safety functions apply through RHR and RPS. All other
applicable requirements of IEEE 279 are met with the SPTM system.
(2)
CriteriaGDCs 2, 4, 13, 16, 19, 20, 21, 22, 23, 24, 29 and 38.
(b)
ConformanceWith regard to GDC 20, 21, 22, 23, 24 and 29, the SPTM
System generates four division trip signals for RPS and RPS generates the
scram signal for the reactor trip.
With regard to GDC 38, the SPTM is not designed to control or remove
heat from the containment. It monitors the suppression pool
temperatures, generates operator displays, initiates alarms, and
automatically initiates the suppression pool cooling mode of RHR. The
SPC mode of the RHR System is sufficient to remove heat from the
suppression pool (Subsections 7.3.1.1.4 and 7.3.2.4).
Conformance with the above listed GDCs is met as a whole, or in part, as
applicable. All GDCs are generically addressed in Subsection 3.1.2.
(3)
7.6-32
Rev. 0
ABWR
In accordance with the Standard Review Plan for Section 7.6, and with
Table 7.1-2, the following RGs are addressed for the SPTM System:
(a)
(b)
(c)
(f)
(g)
The SPTM System is in conformance with all RGs listed, assuming the same
interpretations and clarifications identified in Subsections 7.3.2.1.2 and 7.1.2.10. For
RG 1.22, actuation is through RPS as stated in Subsection 7.6.2.7.2(1). A generic
assessment of RG 1.97 is provided in Section 7.5.
(4)
(b)
(5)
7.6-33
Rev. 0
ABWR
In accordance with the Standard Review Plan for Section 7.6, and with
Table 7.1-2, the following TMI action plan requirements are addressed for the
SPTM System:
(a)
(b)
The SPTM System provides safety-related instrumentation for use during and after
LOCA events. However, these TMIs are addressed generically in Appendix 1A. An
assessment of RG 1.97 is presented in Section 7.5.
7.6-34
Rev. 0
ABWR
Action
45%
power*
Scram
(bypassed in RUN)
35% power
Rod Block
(bypassed in RUN)
11 seconds
Scram
(bypassed in RUN &
REFUEL) (no scram
function in counting
range)
21 seconds
Rod Block
(bypassed in RUN)
SRNM Period
Withdrawal Permissive
56 seconds
Warning (bypassed in
RVN)
SRNM Inop
Module interlock
disconnect HV
voltage low
Electronics Criteria
Failure
SRNM Downscale
3 cps
Rod Block
All Modes**
SRNM Noncoincidence
Upscale Flux Trip
5E+5 cps
Scram (activated by
manual switch in RPS)
SRNM Noncoincidence
Upscale Flux Alarm
1E + 5 cps
* This scram setpoint is functionally equivalent to the upscale scram on the last
range of BWR/5 IRM, at the 120/125 level.
This rod block setpoint is functionally equivalent to the upscale rod block on
the last range of BWR/5 IRM, at the 108/125 level.
Scram action only active in MSV range, which is defined as above 1 x 10-4%
power.
Conditions for activation will be defined in the technical specifications.
** All SRNM channels within each division have to indicate a power level below
the setpoint in order to remove the permissive.
7.6-35
Rev. 0
ABWR
Action
118% power
13% power
Flow biased
10% power
Flow biased
Scram
APRM Inoperative
2. Module interlocks
disconnect
3. Electronics Critical Failure
APRM Downscale
5% Decrease*
6%
All Modes
fixed*
120% (flow)
Growth Rate-Based
Trip (S3)
S=S3=(P11.0) x DR3+1.0
DR3=1.3
Scram
Amplitude-Based
Maximum Trip (Smax)
S=Smax=1.30
Scram
Period-Based
Trip (SP)
S=SP=1.10**
Scram
* The trip signal is based on a flow-dependent equation. If the flow decreases too fast, the trip
signal will reach the fixed trip setpoint and initiate scram. The thermal power signal is only
used as a criteria to determine scram bypass condition.
APRM has to indicate a power level below the setpoint in order to remove the permissive.
P1 is the last peak reading measured after the signal S exceeds S1. Other
Pre-Trip condition parameters of the algorithm are:
S1=1.10,
S2=0.92,
T1=0.31 to 2.2 s,
(For details see Figure 7.6-14).
T2=0.31 to 2.2 s.
7.6-36
NP=10.
Rev. 0
ABWR
Type
Valve
Parameter
Sensed
RHR Shutdown
Cooling Supply
MO
MO
E11-F010
E11-F011
Reactor pressure,
low level
Prevents valve
opening until
reactor pressure is
low and level is
above Level 3.*
RHR Shutdown
Cooling/LPFL
Injection
Check
MO
E11-F006
E11-F005
N/A
Reactor pressure
N/A
Prevents valve
opening until
reactor pressure is
low.
Purpose
7.6-37
Rev. 0
ABWR
7.6-38
Utilization
Rev. 0
ABWR
7.6-39
Rev. 0
ABWR
Rev. 0
ABWR
7.6-41
Rev. 0
ABWR
7.6-42
Rev. 0
ABWR
25.4 mm
TIP
CALIBRATION
TUBE
914.4 mm
C
914.4 mm
POWER RANGE
DETECTOR
ASSEMBLY
LENGTH
OF ACTIVE
FUEL
3708.4 mm
914.4 mm
A
LPRM
DETECTOR
457.2 mm
BAF
ELEVATION
7.6-43
Rev. 0
ABWR
DETECTOR
DETECTOR
DETECTOR
DETECTOR
(2 or 3)
(SAFETY-RELATED)
DETECTOR
(SAFETY-RELATED)
FROM CORE PLATE
P TRANSMITTER
SRNM PREAMP
(SAFETY-RELATED)
APRM (DMC)
(SAFETY-RELATED)
SRNM (DMC)
(SAFETY-RELATED)
FROM INTERFACE
UNIT
INTERFACE
UNIT (I/O)
DEDICATED
INTERFACE
MRBM
INTERFACE
UNIT (I/O)
IN-CORE INSTRUMENT
CALIBRATION SYSTEM
NMS BOUNDARY
RC&IS
TRIP
RPS/SSLC
TRIP
MAIN
CONTROL
ROOM
PANEL
RC&IS
(ATLM)
RECIRC
CONTROL
PROCESS
COMPUTER
Figure 7.6-4a
Basic Configuration of a Typical Neutron Monitoring System Division
7.6-44
Rev. 0
ABWR
SRNM
LPRM
APRM
OPERATION
1014
POWER
100
1010
0.1
0.01
109
E-3
108
106
E-5
STARTUP
107
E-4
COUNTING RANGE
1011
1012
10
HEATING
1013
105
E-6
E-7
SOURCE
E-8
104
7.6-45
Rev. 0
ABWR
7.6-46
Rev. 0
ABWR
16
TEMPERATURE SENSORS
(REFER TO TABLE BELOW)
331
SRV QUENCHERS
TE
J
X
N
286
342
18
TE
306
TE
TE U
B
L TE
241
90
234
C
81
FOR ELEVATION
SEE FIGURE 7.6-10
54
270
TE
126
TE
R 198
162
106 ( 5 TYPICAL)
TE
151
196
180
16
61
106
151
196
241
286
331
DIVISION I
TE-001A,E,J,N
DIVISION II
DIVISION III
TE-001C,G,L,R
TE-002B,F,K,P
TE-003B,F,K,P
TE-004A,E,J,N
TE-005A,E,J,N
TE-002D,H,M,S
TE-003D,H,M,S
TE-004C,G,L,R
TE-005C,G,L,R
TE-006B,F,K,P
TE-007B,F,K,P
TE-008A,E,J,N
DIVISION IV
TE-006D,H,M,S
TE-007D,H,M,S
TE-008C,G,L,R
7.6-47
NWL
LWL
75 [3]
(7100) [280]
(7050) [278]
(7000) [276]
300 [12]
TMSL 1500 [59]
(6700) [264]
TE-002F
TE-001E
(5960) [235]
TE-002K
TE-001J
(3280) [129]
(2130) [84]
(1610) [63]
(0) [0]
125 [5]
Rev. 0
TE-001A
TE-001N
1000
[39]
1000
[39]
1300
(51)
VIEW X-X FROM FIGURE 7.6-9, TYPICAL OF DIVISION I AND II SENSORS AT AZIMUTHAL LOCATIONS 16 AND 61, DIVISION
III AND IV SENSORS ARE NOT SHOWN. DRAWING NOT TO SCALE. ALL DIMENSIONS ARE IN MM.
Figure 7.6-10 Suppression Pool Temperature Monitoring System Sensor and Envelope Definition
TE-002B
TE-002P
ABWR
7.6-48
HWL
Rev. 0
ABWR
7.6-49
Rev. 0
ABWR
61
B C
C D
B C
C D
B C
A D
B A
A D
B A
A D
1
53
A B
D A
A B
D A
A B
D A
D C
C B
D C
C B
D C
C B
10
11
12
13
B C
C D
B C
C D
B C
C D
B C
C D
A D
B A
A D
B A
A D
B A
A D
B A
15
16
17
18
19
20
A B
D A
A B
D A
A B
DA
A B
D A
D C
C B
D C
C B
D C
C B
D C
C B
21
29
C B
14
37
D A
7
45
22
23
24
25
26
27
B C
C D
B C
C D
B C
C D
B C
C D
A D
B A
A D
B A
A D
B A
A D
B A
28
21
29
30
33
34
D A
A B
D A
A B
D A
A B
D A
D C
C B
D C
C B
D C
C B
36
37
38
39
40
C D
B C
C D
B C
C D
B C
B A
A D
B A
A D
B A
A D
41
5
32
C B
35
13
31
12
20
42
43
44
D A
A B
D A
C B
D C
C B
28
36
44
A B
LPRMs PROVIDING INPUT TO OPRM CHANNELS A, B, C, D
D C
52
60
OPRM CELL
i
i : CELL NUMBER
ABWR
If St>=S1
no
yes Set
t0=t
no
yes Set
tp1=t
P1=St
If St>=S(t-dt)
& St>=S(t+dt)
If t>3(tp2-tp1)
scan t
scan t
If St<=S(t-dt)
& St<=S(t+dt)
yes Set
tp2=t
no
no
no
If St<=S(t-dt)
& St<=S(t+dt)
& St<S2
yes
yes If St>=S3
or St>=Smax
If Tl<(tp2-tp1)<Th
yes
Nominal Values of Parameters:
S1 = 1.1
S2 = 0.92
DR3 = 1.3
Smax = 1.3
Tl
= 0.31 s
Th = 2.2 s
S3 = (P1-1.0) x DR3 +1.0
dt
= 0.050 s
St = (Filtered Flux) / (Time Averaged Flux)
(Filtered Flux : no high frequency noises,
Time Averaged Flux: Filtered w/ 6 s time constant)
scan t
no
If St<=S(t-dt)
If St>=S(t-dt)
&
St<=S(t+dt)
& St>=S(t+dt)
Set
t=tp2
Set
tp3=t
yes
If Tl<(tp3-tp2)<Th
issue trip
no
Rev. 0
scan t
no
Set
scan t N=0
t0=t
scan t
no
If Tmin<T0<Tmax
no
no
If St>=S(t-dt)
& St>=S(t+dt)
yes
Set
tp1=t
If St<=S(t-dt)
& St<=S(t+dt)
yes
Set
tp2=t
If St>=S(t-dt)
& St>=S(t+dt)
yes
Set
tp3=t,
T0=tp3-tp1
yes
If N>=1
yes
scan t
Set Tref=To
Set N=N+1
yes
If N>Np
no
If St>=Sp
yes
issue trip
no
7.6-51/52
no
Rev. 0
ABWR
Thi d
7.7-1
t d ith F
M k
403
Rev. 0
ABWR
systems are described and evaluated in other portions of this document, only the nonsafety-related sensors for those systems are described in this subsection.
(1)
System Identification
The purpose of the NBS instrumentation is to monitor and provide control
input for operation variables during plant operation.
The non-safety-related instruments and systems are used to provide the
operator with information during normal plant operation, or provide control
input for non-safety-related functions.
(2)
Classification
The systems and instruments discussed in this subsection are designed to
operate under normal and peak operating conditions of system pressures and
ambient pressures and temperatures and are classified as non-safety-related.
However, mechanical interface of non-safety-related instruments with safetyrelated instrument piping is either classified as essential passive to avoid
compromise of the Class 1E sensing capability (e.g., a pressure-containing
body of a non-1E transmitter on a Class 1 instrument line is classified as
essential passive and is environmentally qualified), or redundant sensing lines
(four total) are provided with 2/4 safety system logic to show compliance with
NRC Regulatory Guide 1.151.
(3)
Power Sources
The non-safety-related instruments discussed in this subsection are powered
from the non-Class 1E instrument buses.
(4)
Equipment Design
For instruments which are located below the process tap, the sensing lines will
slope downward from the process tap to the instrument, so that air traps are
not formed.
Where it is impractical to locate the instruments below the process tap, the
sensing lines descend below the process connection before sloping upward to
a high point vent located at an accessible location.
The purpose of this is to permit venting of non-condensable gases from the
sensing line during calibration procedures.
(5)
7.7-2
Rev. 0
ABWR
(b)
(c)
7.7-3
Rev. 0
ABWR
(7)
7.7-4
Rev. 0
ABWR
the core support assembly. The differential pressure of the core plate is
indicated locally and recorded in the main control room.
Another differential pressure device indicates the reactor internal pump
developed head by measuring the pressure difference between the pressure
above and below the pump deck.
(8)
(b)
Pressure transmitters and trip actuators used for RCIC and LPFL are
discussed in Subsection 7.3.1.1.
(c)
(d) Pressure transmitters that are used for pressure recording are discussed
in Section 7.5.
(9)
Pressure between the inner and outer reactor vessel head seal ring is sensed
by a pressure transmitter. If the inner seal fails, the pressure at the pressure
transmitter is the vessel pressure, and the associated trip actuator will trip and
actuate an alarm. The plant will continue to operate with the outer seal as a
backup, and the inner seal can be repaired at the next outage when the head
is removed. If both the inner and outer head seals fail, the leak will be detected
by an increase in drywell temperature and pressure.
7.7-5
Rev. 0
ABWR
The shutdown range water level, narrow range water level, wide range
water level, fuel zone water level, and reactor well water level are
indicated in the main control room.
(b)
(c)
(d) The reactor pressure is indicated in the main control room and at two
local racks in the containment by a pressure gauge.
7.7-6
Rev. 0
ABWR
(e)
(f)
(g)
(16) Setpoints
The annunciator alarm setpoints for the reactor head seal leak detection, SRV
seat leak detection, and feedwater corrosion product (turbidity) monitor are
set so the sensitivity to the variable being measured will provide adequate
information.
Tables 2 and 3 of Figure 5.1-3 show the relative indicated water levels at which
various automatic alarms and safety actions are initiated. The following list
tells where various level measuring functions are discussed and their setpoints
are referenced.
(a)
Level transmitters and trip actuators for initiating scram are discussed in
Subsection 7.2.1.1.
(b)
(c)
Level transmitters and trip actuators used for initiating HPCF, RCIC,
LPFL and ADS and the level actuators used to shut down the HPCF
pump and RCIC turbine are discussed in Subsection 7.3.1.1.
(d) Level trips to initiate various alarms and trip the main turbine and the
feedpumps are discussed in Subsection 7.7.1.4
7.7.1.2 Rod Control and Information SystemInstrumentation and Controls
(1)
System Identification
The main objective of the Rod Control and Information System (RCIS) is to
provide the capability to control the fine motion control rod drive (FMCRD)
motors of the Control Rod Drive (CRD) System (explained in Sections 4.6.1
and 4.6.2) to permit changes in core reactivity so that reactor power level and
power distribution can be controlled.
7.7-7
Rev. 0
ABWR
(ii)
(b)
(c)
Provides FMCRD status and control rod position and status data to other
plant systems which require such data (e.g., the plant process computer
system).
(d) Provides for automatic control rod run-in of all operable control rods
following a scram.
(e)
(f)
(g)
(h) Insures that the pattern of control rods in the reactor is consistent with
specific control rod pattern restrictions. This function is performed by
the Rod Worth Minimizer (RWM) Subsystem of the RCIS and is effective
only when reactor power is below the low power setpoint.
(i)
7.7-8
Rev. 0
ABWR
(j)
Initiates the Run Back signals to adjustable speed drives (ASDs) of the
Recirculation Flow Control System, through hard-wire connections to
ASDs, whenever an all-rods-in condition is detected in the RCIS.
(k)
(l)
The RCIS IED is shown in Figure 7.7-2. This drawing depicts the major
components of the RCIS, their interconnections and interfaces with other
ABWR systems.
(2)
System Description
The RCIS is a dual redundant system consisting of two independent channels
for normal monitoring of control rod positions and executing control rod
movement commands. Each channel receives separate input signals and both
channels perform the same function. Disagreement between the two channels
results in rod motion inhibit.
The RCIS consists of several different types of cabinets (or panels), which
contain special electronic/electrical equipment modules and a dedicated
operator interface on the main control panel in the control room. There are
four types of electronic/electrical cabinets that make up the RCIS:
(a)
(ii)
7.7-9
Rev. 0
ABWR
(c)
(4)
Classification
The RCIS is not classified as a safety-related system, as it has a control design
basis only and is not required for the safe and orderly shutdown of the plant.
A failure of the RCIS will not result in gross fuel damage. The rod block
function of the RCIS, however, is important in limiting the consequences of a
rod withdrawal error during normal plant operation. An abnormal operating
transient that might result in local fuel damage is prevented by the rod block
function of the RCIS.
The RCIS is single-failure proof with high reliability and availability. In
accordance with the non-safety-related system application procedure section
of the plant general system application requirement document, the RCIS is
classified as a non-safety-related, Class 3, power generation system.
7.7-10
Rev. 0
ABWR
(5)
Power Sources
(a)
Normal
The incoming three-phase AC power for the stepping motor driver
modules and the rod brake controller power supplies is derived from the
Division I Class 1E AC power bus.
The power for all RCIS equipment, except as noted above, is derived
from two separate, nondivisional uninterruptible AC power sources
(UPS) (Subsection 8.3.1 and 8.3.1.1.4).
Each of the two RACCs has redundant auxiliary electrical power supplies
and cooling fans, as required, for proper operation of their associated
subsystems.
The RCC contains the necessary redundant power supplies for channels
A and B of the rod server modules, file control modules, electrical
equipment, and cooling fans (if required).
(b)
Alternate
On loss of normal auxiliary power, the Division I station diesel generator
provides backup power to Division I Class 1E bus.
(6)
RCIS Scope
The RCIS scope includes the following equipment:
(a)
(b)
(c)
(d) The dedicated RCIS operators interface and the communication links
from the equipment to this interface.
(7)
7.7-11
Rev. 0
ABWR
(b)
Gathers rod status and rod position data, and provides signals for logic
control and performance monitoring to the RCIS.
(c)
Provides for rapid control rod insertion (scram) so that no fuel damage
results from any abnormal operating transient. This function is
independent of the RCIS.
The CRD System components which are required for the orderly shutdown of the plant
are designed to meet requirements for a safety-related system. The components that are
required for positioning the control rods to control power generation meet the design
requirements of a control system. The RCIS classification is identified under
Subsection 7.7.1.2 (4).
The control rods are moved by (1) the fine motion control rod drive (FMCRD) motors
(motor-driven positioning) for normal insertion and withdrawal of the control rods on
receiving drive motion signals from the RCIS and (2) hydraulic-powered rapid control
rod insertion (scram) for abnormal operating conditions in response to signals received
from the Reactor Protection System.
7.7-12
Rev. 0
ABWR
The hydraulic power required for scram is provided by high pressure water stored in
individual Hydraulic Control Units (HCUs) and each HCU contains a nitrogen
gas/water accumulator charged to a high pressure along with the necessary valves and
components to scram two control rods except for the one HCU that is connected to only
one control rod.
7.7.1.2.1 Control Rod Drive Control System Interfaces
(1)
Introduction
When an operator selects a control rod for motion (Figure 7.7-3), the
operator first selects the manual rod movement mode at the dedicated RCIS
operator panel, by depressing the manual mode switch to place the RCIS in
manual mode. Then the operator depresses the select pushbutton for either
single rod movement or for ganged rod movement. The operator must then
select a specific rod (or a gang) to be moved at the normal operational manual
mode CRT display under the control of the Performance Monitoring and
Control System (PMCS).
A CRT display generated by PMC presents to the operator a full core array of
all 205 control rods in addition to 52 local power range monitors (LPRMs)
schematically as a group of boxes.
Each box represents a control rod containing the core coordinates and
vertical rod position of that rod in white numbers on a black background. The
vertical rod position information is normally not visible but becomes visible in
response to actuation of various rod status and position requestor poke points.
The core coordinates are always visible to the operator.
The CRT display provides the operator with a capability to move a single rod
or a ganged selection. For this discussion, the operator selects a single rod for
withdrawal. Four rod movement commands (poke points) serve as a means to
initiate all rod movements controlled from this display. They are identified as
SINGLE ROD, ROD GANG, STEP or CONTINUOUS, and IN or
OUT.
The operator first identifies the rod status from the rod status requestor
information display, then makes a decision for either a withdrawal or an
insertion of a control rod and sets up the display. The operator can request
rod status information by actuating poke points on the CRT for the required
rod.
7.7-13
Rev. 0
ABWR
(2)
Withdrawal Cycle
Following is a description of steps the operator performs at the RCIS
dedicated operators interface panel in selecting a rod for movement in the
manual mode. The operator depresses the manual rod movement mode
switch, which enables the RCIS for manual mode. The operator then verifies
indicator/alarm status at the control panel for the following conditions:
(a)
(b)
(c)
Verifies status of channel bypass conditions for RWM, RACS, and ATLM.
(f)
(g)
Rev. 0
ABWR
This setup and action by the operator sends rod coordinates and other setup
data to the PMCS. The data representing a single rod to be withdrawn is coded
and stored in PMCS memory. The PMCS addresses the RCIS and sends the
coded messages. The coded messages are received at the RCIS and stored in
the Rod Position and Information Subsystem memory. The operator has an
option to stop the rod movement by using the light pen. Touching the
SINGLE ROD poke point a second time causes rod motion stop signals to be
sent to the RCIS interface.
The information displayed to the operator at this time is the vertical position
of the rod selected and it remains displayed until a new selection is made or
the rod is deselected. The display array boxes representing all other rods in
the core at this time dim to approximately half brightness.
The CRT display stores information in memory during the initial setup and
transmits the information to the PMCS. When the operator initializes the last
poke point (ROD SELECTED), the information stored in memory addressing
the manual rod movement command signals in the PMCS are downloaded, as
two independent signals, into channels A and B of the RCIS Rod Action and
Position Information (RAPI) Subsystems.
The RCIS receives the two independent streams of data signals transmitted
from the PMCS. The data are received and loaded into memory at the RAPI
Subsystems (channel A/B). Both channel A/B are identical and perform the
same functions. If there is a disagreement between A and B, the logic issues a
rod motion inhibit signal. The operator has the capability to bypass certain
functions in the manual mode.
The PMCS also sends data to the Automated Thermal Limit Monitor (ATLM)
of the RCIS on the calculated fuel thermal operating limits and corresponding
initial LPRM values when an ATLM setpoint update is requested.
The logic of the ATLM subsystem issues a rod block signal that is used in the
RAPI System logic to enforce a rod block that prevents violation of the fuel
thermal operating limits. The ATLM interfaces with and receives signals from
the RAPI Subsystem control logic for rod position data, other plant data and
control signals.
The ATLM interfaces with Recirculation Flow Control (RFC) System and
when it trips, a signal is sent to the RFCS which would cause a flow increase
block.
The ATLM also receives input signals, based upon the LPRMs and APRMs of
the Neutron Monitoring System (NMS). The RAPI Subsystem logic enforces
Control Systems Not Required for Safety
7.7-15
Rev. 0
ABWR
ATLM rod block signals to the RCIS rod server modules located in the remote
communication cabinets. Either channel of an ATLM subsystem can
independently cause a rod withdrawal block.
The Rod Worth Minimizer (RWM) Subsystem logic issues rod block signals
that are used in the Rod Action Control Subsystem rod block logic to assure
that absolute rod pattern restrictions are not violated (e.g., the ganged
withdrawal sequence restrictions). The logic of the RWM also receives rod
position data and control status signals from the logic of the RAPI Subsystem
and feeds back RWM status signals.
The RCIS responds to data signals originating from the CRT displays of the
PMCS for operator requested rod withdrawal or insertion commands.
The RAPI Subsystem of the RCIS enforces rod blocks based upon signals
internal or external to the system.
The internal signals include those signals from any of the above MRBM,
ARBM, RWM. If there is any disagreement between the two channel logic of
the RAC and/or the RAPI subsystems of the RCIS, rod block signals are
transmitted to the rod server module and sent to the PMCS.
External input signals which could cause rod blocks originate from the SRNM
and PRNM Subsystems or from the four divisions of the essential multiplexing
system, reflecting the status of separation switches of the FMCRDs.
After performing the required validity checks within each subsystem and
verifying that there are no rod block conditions existing, the RAPI Subsystem
of the RCIS transmits command data signals (representing the selection of a
single rod for withdrawal via the RCIS multiplexing system channel A and
channel B) to a dual channel file control module (FCM) located in a remote
communication cabinet. The selected rod command withdrawal signals are
received at the dual channel FCM and routed via channel A and channel B of
the dual channel rod server modules (RSMs) and then are loaded into data
buffers A and B of the inverter controller.
The FCM also interfaces with instrumentation of the FMCRD (a subsystem of
the control rod drive system), collects data associated with the position reed
switches and converts the synchro A and synchro B analog data into digital
data for use in the RSM logic and transmission (via the RCIS multiplexing
system) to the RAPI Subsystem logic.
The RSM, which consists of two rod server processing channels and one
inverter controller, interfaces with the rod position instrumentation through
7.7-16
Rev. 0
ABWR
its two processing channels and with the associated stepper motor driver
module of the FMCRD System via the inverter controller. After receiving the
proper command signals for a single rod to be withdrawn continuously, the
inverter controller sends the proper motor power control information to the
stepper motor driver module. In turn, the stepper motor driver module sends
power pulses to the FMCRD motor.
Each of the rod server processing channels A and B also interfaces with the rod
brake controller to provide brake disengagement and/or engagement signals
required for normal rod movement. This is based on two-out-of-two logic
where both channels A and B of the RSM should agree, and on one-out-of-two
logic for ARI and scram following functions.
Each rod server processing channel of the RCIS obtains rod position status
information signals via hardwired interfaces with its associated FMCRD
synchro and obtains additional rod position and status information via
hardwired interfaces with the reed switches included in the FMCRD. The reed
switch based position signals are mainly used for recording FMCRD scram
timing analysis data. Each rod server processing channel exchanges the
continuous synchro position information and transmits the data to the RAPI
Subsystem of the RCIS for usage in its logic. This data is also used to provide
position status signals to the PMCS and to the RCIS dedicated interface panel.
(3)
Insert Cycle
An operator action to insert a rod while in the manual mode would be
processed in a similar manner as above, except that signals for an insertion of
the rod would be decoded at the rod server module (RSM). On receiving the
correct signals from the RSM, the stepper motor driver module would provide
power pulses to the FMCRD motor such that control rod insertion would
result.
(4)
7.7-17
Rev. 0
ABWR
sequence (RRPS) and keeping track of the current control rods positions,
prompts the operator to the selection of the next gang.
When the RCIS is in manual mode and ganged rod movement mode has also
been chosen, if the operator selects a specific rod in a gang, the logic will
automatically select all associated rods in that gang.
When the automatic mode is active, the RCIS responds to signals for rod
movement request from the APR System. In this mode, the APR simply
requests either reactivity insertion or withdrawal. The RCIS responds to this
request by using the RRPS and the current rods positions and automatically
selects and executes the withdrawal/insert commands for the next gang.
In order for the automatic rod movement feature of the RCIS to be active, the
power generation control system must be in the automatic mode, the
automatic power regulator system must be in the automatic mode, and the
switch on the RCIS dedicated operator interface for automatic rod movement
mode must be depressed. The operator has an option of discontinuing the
automatic operation by placing either the PGCS/APR or RCIS mode switches
back to manual mode.
(5)
The ganged rod mode consists of one or two sets of fixed control rod
gang assignments. The two sets of rod gang assignments correspond to
sequences A and B of the ABWR ganged withdrawal sequence, as
specified in the reactivity control document.
(b)
The system allows up to 26-rod gangs, for control rods in rod groups 1,
2, 3, and 4, to be withdrawn simultaneously when the reactor is in the
startup mode. These withdrawals are permitted only under the following
conditions:
(i)
(ii)
(iii) Groups 1-4 may only be withdrawn before groups 5-10 are in the
full-in position.
7.7-18
Rev. 0
ABWR
(iv) The other three groups (of groups 1-4) that are not selected must
be either full-in or full-out. Groups 1-4 are withdrawn from the fullin position to the full-out position before another group is moved.
(v)
(1, 2, 3, 4)
(b)
(1, 2, 4, 3)
(c)
(2, 1, 3, 4)
(d) (2, 1, 4, 3)
(e)
(3, 4, 1, 2)
(f)
(3, 4, 2, 1)
(g)
(4, 3, 1, 2)
(h) (4, 3, 2, 1)
No sequences other that those indicated above are allowed within
the logic of the RCIS. The logic of the RCIS also ensures that, when
single rod movements of rods in groups 1-4 are made, they are in
accordance with the above restrictions (e.g., if one of the rods from
group 1 is withdrawn, all the other group 1 rods are to be
withdrawn before withdrawal of rods in another group is
permitted).
(vi) The RCIS logic enforces additional ganged withdrawal sequence
restrictions when the reactor power level is below the low power
level setpoint as follows:
(a)
(b)
(c)
7.7-19
Rev. 0
ABWR
7.7-20
Rev. 0
ABWR
(7)
Rod separation, only for those rod(s) for which separation is detected.
(b)
(c)
SRNM period alarm (all control rods, but not applicable when reactor
in RUN mode).
(d) SRNM downscale alarm or SRNM upscale alarm or APRM set down
upscale alarm (all control rods, but not applicable when in RUN mode).
(e)
SRNM inoperative (all control rods, but not applicable when reactor is
in RUN mode).
(f)
(g)
Flow-biased APRM rod block (all control rods, only applicable when
reactor in RUN mode).
(h) APRM inoperative (all control rods, only applicable when reactor in
RUN mode).
(i)
(j)
Low CRD charging header pressure trip function bypass switches of the
reactor protection system are in a bypass position (all control rods).
7.7-21
Rev. 0
ABWR
(k)
(l)
Automated Thermal Limit Monitor (ATLM) rod block (all control rods,
only applicable above the low power setpoint).
(m) Multi-channel Rod Block Monitor (MRBM) rod block (all control rods,
only applicable above the low power setpoint).
(n) ATLM trouble (all control rods, only applicable above the low power
setpoint).
(o)
RWM trouble (all control rods, applicable below the low power
setpoint).
(p) MRBM inoperative (all control rods, only applicable above the low
power setpoint).
(q)
(r)
(s)
(t)
The RCIS enforces all rod blocks until the rod block condition is cleared. The
bypass capabilities of the RCIS permit clearing certain rod block conditions
that are caused by failures or problems that exist in only one channel of the
logic.
(8)
RCIS Reliability
The RCIS has a high reliability and availability due to the total dual channel
configuration in its design that allows its continual operation, when
practicable, in the presence of component hardware failures. This is achieved
by the operator being able to reconfigure the operation of the RCIS through
bypass capabilities while the failures are being repaired.
7.7-22
Rev. 0
ABWR
The expected system availability during its 60-year life exceeds 0.99. The
expected reliability is based upon the expected frequency of an inadvertent
movement of more than one control rod. The expected frequency of an
inadvertent movement of more than one control rod, due to failure, is less
than or equal to once in 100 reactor operating years.
The RCIS design assures that no credible single failure or single operator
error can cause or require a scram or require a plant shutdown. The RCIS
design preferentially fails in a manner which results in no further normal rod
movement.
(9)
7.7-23
Rev. 0
ABWR
7.7-24
Rev. 0
ABWR
The status and extent of the bypass functions are identified on the RCIS
dedicated operator interface panel and the PMCS CRT displays at the main
control panel.
Bypass conditions allow continuation of normal rod movement capability by
bypassing failed equipment in one RCIS channel. After repair or replacement
of the failed equipment is completed, the operator can restore the system or
subsystem to a full two-channel operability. The operator has the capability to
invoke bypass conditions within the following system or subsystems:
(a)
(b)
(c)
(f)
(g)
7.7-25
Rev. 0
ABWR
scram time performance based on the scram timing data received from the
RCIS.
In an alternate design, the scram time recording and analysis functions are
performed by two separate panels called scram time test panel (STTP) and
scram time test recording/analysis panel (STR/AP). The STTP function is to
directly interface with FMCRD reed switches and gather all FMCRD status and
scram information. The function of STR/AP is to receive FMCRD information
from STTP, process and analyze FMCRD scram time data, generate scram time
test reports, and communicate FMCRD reed-switch-based status data to other
plant systems.
(12) ATLM Algorithm Description
The ATLM is a microprocessor based subsystem of the RCIS that executes two
different algorithms for enforcing fuel operating thermal limits. One
algorithm enforces operating limit minimum critical power ratio (OLMCPR),
and the other the operating limit minimum linear heat generation rate
(OLMLHGR). For the OLMCPR algorithm, the core is divided into
48 regions, each region consisting of 16 fuel bundles. For the OLMLHGR
algorithm, each region is further vertically divided up into four segments.
During a calculation cycle of ATL (about 100 msec), rod block setpoints
(RBS) are calculated for OLMCP monitoring (48 values) and for OLMLHGR
monitoring (48 x 4 values). Then the calculated setpoints are compared with
the real time averaged LPRM readings for each region/segment. The ATLM
issues a trip signal if any regionally averaged LPRM reading exceeds the
calculated RBS. This trip signal causes a rod block within the RCIS and also a
flow change block in the Recirculation Flow Control System (RFCS).
Provided below is a summary description of OLMCPR and OLMLHGR RBS
calculation methodology.
(a)
(7.7-1)
where:
RBSo
7.7-26
Rev. 0
ABWR
LPRMi
Ao
RMCPRi
OLMCPR
(7.7-2)
where:
RBSm(X)
LPRMi(X)
B(X)
Mp
MAPRATi(X) =
7.7-27
Rev. 0
ABWR
In Equations 7.7-1 and 7.7-2 above, initial refers to values that are
downloaded from the 3D Predictor Monitor subsystem of the PMCS. A
download is requested by the ATLM whenever changes in reactor power
and/or core flow exceed a preset limit. A download can also be manually
requested by the operator.
7.7.1.2.2 System Interfaces
(1)
(b)
(c)
(d) Scram Timing position reed switches which include reed switches at 0%,
10%, 40%, 60%, +100% rod insertion for each FMCRD
(2)
(e)
(f)
(g)
7.7-28
Rev. 0
ABWR
(b)
7.7-29
Rev. 0
ABWR
The preselected control rods for a SCRRI function are selected at the
RCIS CRT displays of the performance monitoring and control system
in the main control room. The preselected SCRRI rod data are stored in
memory in the RAPI Subsystem of the RCIS. The total control rod worth
for the preselected control rods is designed to bring down the reactor
power rod line from the 100% power rod line to the 80% power rod line.
The RCIS dedicated operation interface also provides control switches
that require two manual operator actions for the operator to manually
initiate the SCRRI function.
For manual or automatic initiation of the SCRRI function, the RCIS
dedicated operator interface provides status indications and alarm
annunciators in the control room.
The total delay time from the recirculation pump trip to the start of
control rod motion, for the preselected control rods, is less than or equal
to 2 seconds.
(c)
(3)
7.7-30
Rev. 0
ABWR
validated feedwater temperature. These signals are used as part of the validity
checks when performing an ATLM operating limit setpoint update.
The RCIS can obtain these signals from the FWCS via the multiplexing system
communication links to the RCIS channels.
(4)
(b)
(c)
SRNM inoperative
(f)
APRM downscale
(g)
(j)
Whether or not some of the signals result in a rod block depends on reactor
mode switch status which is provided to the RCIS from the reactor protection
system via the essential multiplexing system.
Each of the four divisions of NMS provides APRM, LPRM and core flow signals
to the two channels of logic in the RAPI Subsystem for determining whether
reactor power is above or below the low power setpoint and usage by ATLM.
The four divisions of the NMS provide the same signals to both channels of
the RCIS. These signals meet the isolation and separation requirements of
interfacing the Class 1E NMS with the non-Class 1E RCIS.
Each of the two MRBM non-safety subsystems of the NMS provide their rod
block signals to the RCIS. The RCIS, in return, provides ATLM status signals
and coordinates of the selected rods to MRBM.
7.7-31
Rev. 0
ABWR
(5)
(6)
7.7-32
Rev. 0
ABWR
(b)
(c)
The RCIS provides for the activation of the following annunciation at the
main control panel.
(a)
(b)
(c)
Low power transient zone (i.e., reactor power above but nearing the
LPSP).
(f)
(g)
ATLM trouble.
(b)
(c)
7.7-33
Rev. 0
ABWR
(e)
(f)
(g)
(j)
(k)
(l)
(3)
(q)
(r)
The dedicated operators interface panel of the RCIS provides logic and
operator controls, so that the operator can perform the following functions:
(a)
(b)
(c)
(f)
(g)
(h) Manually initiate CRD brake test, CRD coupling check and CRD step test
functions.
NOTE: Interlock logic may prevent certain combinations of bypasses from being
activated even though the above bypass controls have been activated.
7.7-34
Rev. 0
ABWR
(4)
The CRT displays, which are part of the PMCS, provide information to the
operator on demand.
The following status and controls are available through the CRTs:
(a)
(b)
(c)
Selected gang (or selected single rod) plus the four LPRM readings of
the closest LPRM strings to the selected gang or selected single rod. If
the closest LPRM reading at a given level is inoperable, as determined by
the Neutron Monitoring System LPRM status information, an INOP
status is displayed instead of actual LPRM reading.
Identification of: (d through v)
(f)
(g)
(j)
(k)
(l)
(m) Control rods for which uncoupled condition has been detected.
(n) Control rods for which drift condition has been detected.
(o)
Control rods for which abnormal movement (other than drift) has been
detected.
(r)
(s)
(t)
7.7-35
Rev. 0
ABWR
(u) All detected conditions that have resulted in rod withdrawal block
conditions being active, when applicable.
(v)
Identification
The objective of the Recirculation Flow Control (RFC) System is to control
reactor power level, over a limited range, by controlling the flow rate of the
reactor core water.
The RFC System consists of three redundant process controllers, adjustable
speed drives (ASDs), switches, sensors, and alarm devices provided for
operational manipulation of the ten reactor internal pumps (RIPs) and the
surveillance of associated equipment. Recirculation flow control is achieved
either by manual operation or by automatic operation if the power level is
above 70% of rated. The reactor internal pumps can be driven to operate
anywhere between 30% to 100% of rated speed with the variable voltage,
variable frequency power source supplied by the ASDs. 30% rated speed
corresponds to the minimum operating speed to be used during initial pump
startups. The instrument electrical diagram (IED) is provided in Figure 7.7-5
and the interlock block diagram (IBD) is provided in Figure 7.7-7.
7.7-36
Rev. 0
ABWR
(2)
Classification
This system is a power generation system and is classified as not required for
safety.
(3)
Power Sources
(a)
Normal
Each processing channel of the triply redundant digital processor
receives its respective power input from an uninterruptible,
independent source of the instrument and control power supply system.
Other system equipments such as the transmitters, input conditioners,
voters, output device drivers, control room displays, etc., will also derive
their required power sources from the same redundant uninterruptible
power supply system.
Variable voltage, variable frequency electrical power is generated by the
adjustable speed drives (ASDs) for use by the induction motors in the
RIPs. Four medium voltage power buses are used to provide input power
to the ten ASDs. These buses are fed from the unit auxiliary transformers
connecting to the main turbine-generator. Two of the buses each
provide power directly to a pair of ASDs. The other two buses each
provide power to a motor-generator (M-G) set which, in turn, supplies
power to three ASDs operating in parallel (see one-line diagram for AC
power distribution provided as Figure 8.3-2).
The allocation of the RIP equipment on the four power buses is such
that on loss of any single power bus, a maximum of three RIPs are
affected. At least one circuit breaker is provided along each circuit path
to protect power equipment from being damaged by overcurrent.
(b)
7.7-37
Rev. 0
ABWR
(4)
Normal Operation
Reactor recirculation flow is varied by modulating the recirculation internal
pump speeds through the voltage and frequency modulation of the adjustable
speed drive output. By properly controlling the operating speed of the RIPs,
the recirculation system can automatically change the reactor power level.
Control of core flow is such that, at various control rod patterns, different
power level changes can be automatically accommodated. For a rod pattern
where rated power accompanies 100% flow, power can be reduced to 70% of
full power by full automatic or manual flow variation. At other rod patterns,
automatic or manual power control is possible over a range of approximately
30% from the maximum operating power level for that rod pattern. Below
70% power level, only manual control of power (i.e., by means of manual flow
setpoint control) is available.
An increase in recirculation flow temporarily reduces the void content of the
moderator by increasing the flow of coolant through the core. The additional
neutron moderation increases reactivity of the core, which causes reactor
power level to increase. The increased steam generation rate increases the
steam volume in the core with a consequent negative reactivity effect, and a
new (higher) steady-state power level is established. When recirculation flow
is reduced, the power level is reduced in the reverse manner. The RFC System,
operating in conjunction with the main turbine pressure regulator control,
provides fully automatic load following.
The RFC System is designed to allow both automatic and manual operation.
In the automatic mode, either total automatic or semi-automatic operation is
possible. Fully automatic, called Master Auto mode, refers to the automatic
load following (ALF) operation in which the master controller receives a load
demand error signal from the main turbine pressure regulator. The load
demand error signal is then applied to a cascade of lead/lag and proportionalintegral (PI) dynamic elements in the master controller to generate a flow
demand signal for balancing out the load demand error to zero. The flow
demand signal is forwarded to the flow controller for comparing with the
sensed core flow. The resulting flow demand error is used to generate a
suitable gang speed demand to the ASDs. The speed demand to the individual
ASDs causes adjustment of RIP motor power input, which changes the
operating speed of the RIP and, hence, core flow and core power. This process
continues until both the errors existing at the input of the flow controller and
master controller are driven to zero. Fully automatic control is provided by the
master controller when in the automatic mode. The flow controller can
remain in automatic even though the master controller is in manual.
7.7-38
Rev. 0
ABWR
The reactor power change resulting from the change in recirculation flow
causes the pressure regulator to reposition the turbine control valves. If the
original demand signal was a load/speed error signal, the turbine responds to
the change in reactor power level by adjusting the control valves, and hence
its power output, until the load/speed error signal is reduced to zero.
In the semi-automatic mode, the operator sets the total core flow demand and
the RFC System responds to maintain a constant core flow. Core flow control
is achieved by comparing the core flow feedback, which is calculated from the
core plate differential pressure signals, with the operator-supplied core flow
setpoint.
In total manual control, the operator can directly manipulate the pump
speeds. Pump speeds can be controlled individually or collectively. When
individually controlled, pump speed demand is obtained through the
operator console and transmitted directly to the individual adjustable speed
drive (ASD) for pump frequency control. In collective manual operation, a
common speed setpoint is used for controlling each RIP which has been
placed in the GANG speed control mode.
(5)
Startup Operations
The RFC System is also used to control the startup of the reactor internal
pumps. To minimize thermal shock to the reactor vessel, the RFC System will
prevent startup of an idle RIP if the temperature of the vessel bottom coolant
is not within 80C of the saturated water temperature corresponding to the
steam dome pressure. The vessel bottom temperature, supplied by the Reactor
Water Cleanup (CUW) System, is compared with the saturated water
temperature derived from the wide range dome pressure signal, to determine
the actual temperature difference.
Startup of the RFC System begins by sequentially bringing each RIP up to the
minimum operating limit (30% of rated speed). It is not permitted to raise a
particular pumps speed above the minimum limit until all desired pumps
have started and reached the minimum speed. This restriction is imposed to
avoid overdriving the ASDs against an excessive starting load which can be
developed by the higher pump speed/head.
(6)
Abnormal Conditions
The RFC System provides logic to initiate actions which can mitigate the effect
of certain expected operational transients. These include RIP speed runbacks
to some decreased flow conditions, pump trips (RPTs), or commands to the
7.7-39
Rev. 0
ABWR
RCIS demanding rod motion block or rod insertion for stability and
protection control. These trip functions are shown in Figure 7.7-7
(7)
(8)
Equipments
(a)
7.7-40
Rev. 0
ABWR
The RIPs provide recirculation flow through the lower plenum and up
through the lower grid, the reactor core, steam separators, and
downcomers. The flow rate is variable over a range from minimum flow
established by the pump characteristics to above the maximum flow
required to obtain rated reactor power.
(b)
RIP Motors
The RIP motors are the variable speed, four-pole, AC induction wet
motor type. The operating speed of the pump motor depends on the
variable-voltage/variable-frequency output of the ASDs. The RIP motors
are cooled by water from the primary side of the reactor motor heat
exchangers (RMHXs). Heat in the secondary side of the heat exchanger
is removed by the Reactor Building Cooling Water System. There is one
heat exchanger per motor.
A clean purge flow is provided by the Control Rod Drive System to
inhibit reactor water from entering the motor cavity region, thereby
preventing any impurity buildup. Also, anti-reverse rotation devices are
installed on the motor shaft to prevent possible motor damage due to
reverse pump flow.
(c)
7.7-41
Rev. 0
ABWR
7.7-42
Rev. 0
ABWR
In the ALF mode, the master controller receives a load demand signal
from the Steam Bypass and Pressure Control (SB&PC) System in
response to any combination of local operator load setpoint inputs,
automatic generation control inputs, or grid load changes indicated by
grid frequency variation.
The master controller functionally provides (1) a function generator
which schedules a gain adjustment in accordance with the size of the
load demand error, (2) a lead/lag compensator which improves steam
flow response by means of zero/pole modification, and (3) a P-I
controller which acts on the load demand error signal to balance the
turbine outputs with the load demand.
All calculations required to support the control system algorithms, as
well as the trip protective functions, are performed in parallel by three
processing channels of the FTDC.
(f)
Fault-Tolerant Voters
For each discrete and analog RFC System output, fault tolerance
objective is achieved by performing a two-out-of-three vote on the three
FTDC channel outputs.
For the critical RFC System outputs, such as the final processor output
on the RIP speed demand, voter failure logic is provided to monitor the
proper function of the speed demand voters. This is done by comparing
the final speed demand with the demand ringback signals. Pump speed
will lockup in the as-is condition if voter failure condition is detected. In
addition, annunciation logic is provided to detect failures in the voter
failure logic.
(g)
7.7-43
Rev. 0
ABWR
Testability
The FTDC, analog and discrete output voters, core flow measurement systems,
ASDs and RIPs are continuously functioning during normal power operation.
Any abnormal operation of these components can be detected during
operation. In addition, the FTDC is equipped with self-test and online
diagnostic capabilities for identifying and isolating failure of process sensors,
I/O cards, buses, power supplies, processors, and interprocessor
communication paths. These online tests and diagnosis are performed
without disturbing the normal control functions of the RFC system.
7.7-44
Rev. 0
ABWR
The recirculation pump power supplies are located outside of the wetwell in
the Reactor Building.
The logic, control unit and instrumentation terminals are located in the main
control room and subject to the normal control room environment as listed
in Section 3.11.
(11) Operational Considerations
The FTDC, which commands RIP speed changes, is located in the main
control room. Provisions are made to allow either automatic or manual
operation for each control loop (master, flow and speed). All transfers
between the manual and automatic operations are designed to be bumpless.
RFCS control modes, as well as setpoint changes, can be initiated by either the
operator or by the PMCS, depending on whether the local or the auto
system control has been selected.
When in local control, the operators control, panel provides the operator the
capability to select the operating mode of the system and to initiate certain
manual actions, and to increment/decrement switches which adjust setpoints
at a preset rate of change.
(12) Reactor Operator Information
Indications and alarm are provided to keep the operator informed of the
system operational modes and equipment status, thereby allowing him to
quickly determine the origin of any abnormal conditions.
Control room indications include both dedicated displays and on-demand
displays from the Process Monitoring and Control System. These indications
include the digital recirculation flow controller process variables, the
recirculation pump speed and POWER SUPPLY operating status, and the core
flow measurement system outputs. Also, indicating lights are provided to
indicate the control system configuration and the trip function status.
Alarms are provided to alert the control room operator of any malfunction in
the processor inputs, RIPS, adjustable speed drives or the pump motor cooling
systems, and automatic trips of protective functions.
(13) Setpoints
The subject system has no safety setpoints.
7.7-45
Rev. 0
ABWR
System identification
The Feedwater Control System (FWCS) controls the flow of feedwater into the
reactor pressure vessel to maintain the water level in the vessel within
predetermined limits during all plant operating modes. The range of water
level is based upon the requirements of the steam separators (this includes
limiting carryover, which affects turbine performance, and carryunder, which
affects reactor internal pump operation).
The FWCS may operate in either single or three-element control modes. At
feedwater and steam flow rates below 25% of rated (when steam flow is either
negligible or else measurement is below scale), the FWCS utilizes only water
level measurement in the single-element control mode. When steam flow is
negligible, the Reactor Water Cleanup (CUW) System dump valve flow can be
controlled by the FWCS in single-element mode in order to counter the effects
of density changes during heatup and purge flows into the reactor. At higher
flow rates, the FWCS in three-element control mode uses water level, main
steamline flow, main feedwater line flow, and feedpump suction flow
measurements for water level control. The FWCS control structure is shown in
the IED control algorithm detail in Figure 7.7-8. The interlock block diagram
(IBD) is provided in Figure 7.7-9.
(2)
Classification
The FWCS is a power generation (control) system with operation range
between high water level (L8) and low water level (L2) trip setpoints. It is
classified as non-safety-related.
(3)
Power Sources
The triply redundant FWCS digital controllers and process measurement
equipment is powered by non-Class 1E redundant uninterruptible power
supplies (UPS). No single power failure shall result in the loss of any FWCS
function.
(4)
Equipment
The Feed Water Control System consists of the following elements:
(a)
7.7-46
Rev. 0
ABWR
(b)
(c)
Steam flow transmitters, which provide the total flow rate of steam
leaving the vessel.
(d) Feedpump suction flow transmitters, which provide the suction flow rate
of each feedpump.
(5)
(e)
(f)
Adjustable speed drives (ASD) for the reactor feedwater pump (RFP).
(6)
(7)
7.7-47
Rev. 0
ABWR
algorithms take the square root of the differential pressure and provide
feedwater flow rate signals to the FTDCs for validation into one feedwater flow
measurement per line. These validated measurements are summed in the
FTDCs to give the total feedwater flow rate into the vessel. The total feedwater
flow rate is indicated on the main control panel and recorded in the main
control room.
Feedpump suction flow is sensed at a single flow element upstream of each
feedpump. The suction line flow element differential pressure is sensed by a
single transmitter and sent to the FTDCs via the NEMS. The NEMS signal
conditioning algorithms take the square root of the differential pressure and
provide the suction flow rate measurements to the FTDCs. The feedpump
suction flow rate is compared to the demand flow for that pump, and the
resulting error is used to adjust the actuator in the direction necessary to
reduce that error. Feedpump speed change via adjustable speed drives and
low flow control valve position control are the flow adjustment techniques
involved.
(8)
Feedwater/Level Control
Three modes of feedwater flow control, and thus level control, are provided
which are selectable from the main control room.
Single-element control
Three-element control
Manual control
Each FTDC will execute the control software for all three of the control
modes. Actuator demands from the triply redundant FTDCs will be sent over
the NEMS to field voters which will determine a single demand to be sent to
each actuator. Each feedpump speed or control valve demand may be
controlled either automatically by the control algorithms in the FTDCs or else
manually from the main control panel through the FTDCs.
Three-element automatic control is provided for normal operation. Threeelement control utilizes water level, feedwater flow, steam flow, and feedpump
flow signals to determine the feedpump demands. The total feedwater flow is
subtracted from the total steam flow signal yielding the vessel flow mismatch.
The flow mismatch summed with the conditioned level error from the master
level controller (proportional + integral) provides the demand for the master
flow controller. The master flow controller output provides the demand for
the feedpump flow loops, which send either a pump speed demand signal or
7.7-48
Rev. 1
ABWR
flow control valve signal through a linearizing function generator and then to
the feedpump flow control actuator.
In the single-element control mode, which is employed at lower feedwater
flow rates, only a conditioned level error is used to determine the feedpump
demand. The master level controller (proportional + integral) conditions the
level error and sends it directly to the feedpump actuator linearizing function
generator and then to the feedpump flow control actuator itself. When the
reactor water inventory must be decreased, during very low steam flow rate
conditions, the CUW System dump valve is controlled by the FWCS in single
element control. Reactor water is dumped through the CUW System to the
condenser.
Each feedpump flow control actuator can be controlled manually from the
main control panel by selecting the manual mode for that feedpump. In
manual mode, the operator may increase or decrease the demand that is sent
directly to the linearizing function generator of the chosen feedpump flow
control actuator.
(9)
Interlocks
The level control system also provides interlocks and control functions to
other systems. When the reactor water level reaches the Level 8 trip setpoint,
the FWCS simultaneously annunciates a control room alarm, sends a trip
signal to the Turbine Control System to trip the turbine generator, and sends
trip signals to the Condensate, Feedwater and Condensate Air Extraction
(CF&CAE) System to trip all feed pumps and to close the main feedwater
discharge valves and feedpump bypass valves. This interlock is enacted to
protect the turbine from damage from high moisture content in the steam
caused by excessive carryover while preventing water level from rising any
higher. This interlock also prevents overpressurization of the vessel by
isolating the condensate pumps from the vessel.
Upon detection of a loss of feedwater heating, the FWCS will send a signal to
the Recirculation Flow Control System which will signal the Rod Control and
Information System (RCIS) for initiation of automatic selected control rod
run-in (SCRRI). This is done to minimize reactivity transient resulting from
introduction of cold feedwater in such an event.
As an Anticipated Transient Without Scram (ATWS) mitigation measure, the
FWCS issues signals to runback feedwater flow upon receipt of an ATWS trip
signal from the Safety System and Logic Control (SSLC) System.
7.7-49
Rev. 0
ABWR
The FWCS will send a signal to the main steamline condensate drain valves to
open when steam flow rate is below 40% of rated flow. This also protects the
turbine from damage caused by excessive moisture in the steam line.
The FWCS will send a Level 4 trip signal to the Recirculation Flow Control
(RFC) System when reactor water level reaches this low level setpoint. The
RFC System use this signal in determining the need for performing a
recirculation runback when a feed pump trip occurs. The RFC runback will
aid in avoiding a low water level scram by reducing the reactor steaming rate.
The FWCS will send a Level 3 trip signal to RFC System to trip four reactor
internal pumps (RIPs).
(10) Feedwater Flow Control
Feedwater flow is delivered to the reactor vessel through a combination of
three adjustable speed motor-driven feedpumps which are arranged in
parallel. During planned operation, the feedpump speed demand signal from
the FTDCs is sent to a field voter which sends a single demand signal to the
feed pump speed control systems. Each adjustable speed drive can also be
controlled by its manual/automatic transfer station which is part of the
Feedwater and Condensate System. A low flow control valve (LFCV) is also
provided in parallel to a common discharge line from the feedpumps. During
low flow operation, the LFCV demand signal from the FTDCs are sent to a
field voter which sends a single demand signal to the LFCV control system.
The LFCV can also be controlled by the manual/automatic transfer station
which is part of the feedwater and condensate system.
The feedpump flow control actuator demand outputs from the field voters are
rung back to the FTDCs so that they may be compared with the FTDC
demand outputs. If there is difference between the field voter outputs and the
FTDC demand outputs, an actuator lockup signal is sent to the feedpump
flow control actuators via a lockup voter and an annunciator is initiated in
the control room. If the lockup voter receives a majority of redundant
lockup input signals, the actuator demand will be kept as is until the
lockup condition is resolved. The lockup voter output signal is also rung
back to the FTDCs so that a lockup voter failure can be recognized and an
annunciator sounded in the control room.
(11) Testability
The FTDC self-test and online diagnostic test features are capable of
identifying and isolating failures of process sensors, I/O cards, buses, power
supplies, processors and inter-processor communication paths. These features
7.7-50
Rev. 0
ABWR
can identify the presence of a fault and determine the location of the failure
down to the module level.
The FWCS components and critical components of interfacing systems are
tested to assure that specified performance requirements are satisfied.
Preoperational testing of the FWCS is performed before fuel loading to assure
that the system will function as designed and that stated system performance
is within specified criteria. Startup testing is performed to assure that stated
system performance is within specified criteria and that the system will operate
properly with other reactor control systems to achieve specified objectives.
(12) Environmental Conditions
The FWCS is not required for safety purposes, nor is it required to operate
after the design basis accident. This system is required to operate in the
normal plant environment for power generation purposes only.
(13) Operational Consideration
The FTDCs are located in the main control room where, at the operators
discretion, the system can be operated either in manual or automatic.
Manual control of the individual feedpumps and the LFCV is available to the
operator in the main control room via the feedwater and condensate system
controls.
In the event of low water level due to loss of feedwater, the RPS will cause plant
shutdown, and emergency core cooling will be initiated to prevent lowering of
vessel water level below an acceptable level.
(14) Reactor Operator Information
Indicators and alarms, provided to keep the operator informed of the status
of the system, are as noted in previous subsections.
(15) Setpoints
The FWCS has no safety setpoints.
7.7.1.5 Process Computer System (PCS)Instrumentation and Controls
(1)
System Identification
The PCS includes two subsystems, the Performance Monitoring and Control
Subsystem (PMCS) and the Power Generation Control Subsystem (PGCS).
Between them, the two subsystems perform the process monitoring and
7.7-51
Rev. 0
ABWR
control and the calculations that are necessary for the effective evaluation of
normal and emergency power plant operation. The PCS is designed for high
reliability utilizing redundant, network combined processing equipment
which is capable of processing data, servicing subsystems, providing
supervisory control over digital control systems and presenting data to the
user.
The purpose of the PCS is to increase the efficiency of plant performance by:
(a)
(b)
(c)
(f)
Classification
The Process Computer System (PCS) is classified as a non-safety-related system
and has no safety-related design basis. However, it is designed so that the
functional capabilities of safety-related systems are not affected by it.
(3)
Power Sources
The power for the PCS is supplied from two vital ac power supplies. These are
redundant, uninterruptible non-Class 1E 120 Vac power supplies. No single
power failure will cause the loss of any PCS function.
7.7-52
Rev. 0
ABWR
(4)
Equipment
The PCS is composed of the following features and components:
(a)
(b)
(c)
A random access type processor memory that has a memory parity check
feature capable of stopping computer operation subsequent to
completing an instruction in which a parity error is detected. The
processor memory has suitable shutdown protection to prevent
information destruction in the event of loss of power or incorrect
operating voltage.
Bulk memory for storing all programs and all data. Capability is provided
to protect selectable portions of bulk memory against information
destruction caused by an inadvertent attempt to write over the programs
or by a system power failure.
(f)
Peripheral I/O equipment that is used to read data into and out of the
computer.
(g)
Process I/O hardware that accepts both analog and digital inputs.
Intermittent signals and pulse type inputs are sensed by automatic
priority interrupt.
(h) Means to permit the operator to enter information into the computer
and request various special functions during routine operation.
Diagnostic alarms, displays and associated function selection switches
permit the operator to communicate with the processors.
(i)
7.7-53
Rev. 0
ABWR
(5)
Testability
The PCS has self-checking provisions. It performs diagnostic checks to
determine the operability of certain portions of the system hardware and
performs internal programming checks to verify that input signals and
selected program computations are either within specific limits or within
reasonable bounds.
(6)
Environmental Considerations
(See Subsection 3.8.4.3.2)
(7)
The local power density for every fuel assembly is calculated using plant
inputs of pressure, temperature, flow, LPRM levels, control rod
positions, and the calculated fuel exposure.
(b)
(c)
After calculating the power distribution within the core, the computer
uses appropriate reactor operating limit criteria to establish alarm trip
settings (ATS) for each LPRM channel. These settings are expressed as
maximum acceptable LPRM values to which the actual scanned LPRM
readings are compared. The scanned LPRM, when exceeding the ATS,
will sound an alarm and thereby assist the operator to maintain core
operation within permissible thermal limits established by the
prescribed maximum fuel rod power density and minimum critical
power ratio criteria. LPRM calibration constants are periodically
calculated.
7.7-54
Rev. 0
ABWR
Flux level and position data from the automatic traversing incore probe
(ATIP) equipment are read into the computer. The computer evaluates
the data and determines gain adjustment factors by which the LPRM
amplifier gains can be altered to compensate for exposure-induced
sensitivity loss. The LPRM amplifier gains are not to be physically altered
except immediately prior to a whole core calibration using the ATIP
system. The gain adjustment factor computations help to indicate to the
operator when such a calibration procedure is necessary.
(g)
(8)
The computer provides online capability to determine monthly and ondemand isotopic composition for each fuel bundle in the core. This
evaluation consists of computing the weight of one neptunium, three
uranium, and five plutonium isotopes, as well as the total uranium and
total plutonium content. The isotopic composition is calculated and
summed accordingly by bundles and batches.
General
7.7-55
Rev. 0
ABWR
(ii)
(c)
Trend Logging
An analog trend capability is provided for logging the values of the
operator-selected analog inputs and calculated variables. The
periodicity of the log is limited to a nominal selection of intervals, which
can be adjusted as desired by program control.
Alarm Logging
The alarm logs required by the associated process programs are printed.
Alarm printouts inform the operator of computer system malfunctions,
system operation exceeding acceptable limits, and unreasonable, offnormal, or failed input sensors.
(9)
7.7-56
Rev. 0
ABWR
values for temperatures, power outputs, and flows associated with the main
generator and turbines and with the Feedwater, Recirculation, and Reactor
Water Cleanup Systems. The BOP monthly log contains monthly averages and
accumulations for plant gross and net power outputs, load distributions,
turbine heat rates, and fuel burnup. BOP performance calculations include
flow calculations, electrical calculations, thermodynamic calculations,
Nuclear Boiler System performance calculations, turbine cycle performance
calculations, condenser calculation, feedwater heaters and moisture
separators performance calculations, and unit performance calculations.
7.7.1.5.1 Performance Monitoring and Control Subsystem
General The PMCS provides nuclear steam supply (NSS) performance and
prediction calculations, video display control, point log and alarm processing and
balance of plant (BOP) performance calculations.
NSS Performance Module The NSS performance module provides the reactor core
performance information. The calculations performed are as follows:
The local power density for every fuel assembly is calculated using plant inputs of
pressure, temperature, flow, LPRM levels, control rod positions, and the calculated
fuel exposure.
Total core thermal power is calculated from a reactor heat balance. Iterative
computational methods are used to establish a compatible relationship between the
core coolant flow and core power distribution. The results are subsequently
interpreted as power in specified axial segments for each fuel bundle in the core.
After calculating the power distribution within the core, the computer uses
appropriate reactor operating limit criteria to establish alarm trip settings for each
LPRM channel. These settings are expressed as maximum acceptable LPRM values
to which the actual scanned LPRM readings are compared. The scanned LPRM,
when exceeding the alarm trip settings, will sound an alarm and thereby assist the
operator to maintain core operation within permissible thermal limits established
by the prescribed maximum fuel rod power density and minimum critical power
ratio criteria. LPRM calibration constants are periodically calculated.
7.7-57
Rev. 0
ABWR
new reactor operating level. The range of surveillance and the rapidity with which
the computer responds to the reactor changes permit more rapid power
maneuvering with the assurance that thermal operating limits will not be exceeded.
Flux level and position data from the automatic fixed in-core probe (AFIP)
equipment are read into the computer. The computer evaluates the data and
determines gain adjustment factors by which the LPRM amplifier gains can be
altered to compensate for exposure-induced sensitivity loss. The LPRM amplifier
gains are not to be physically altered except immediately prior to a whole core
calibration using the AFIP system. The gain adjustment factor computations help to
indicate to the operator when such a calibration procedure is necessary.
Using the power distribution data, a distribution of fuel exposure increments from
the time of the previous power distribution calculation is determined and is used to
update the distribution of cumulative fuel exposure. Each fuel bundle is identified
by batch and location, and its exposure is stored for each of the axial segments used
in the power distribution calculation. These data are printed out on operator
demand. Exposure increments are determined periodically for each quarter-length
section for each control rod. The corresponding cumulative exposure totals are
periodically updated and printed on operator demand.
Video Display Control The video display control functions of the PMCS provides a
major portion of the plant man-machine interface (MMI). This MMI consists of the
input and output of all of the other PMCS modulated displayed on video display units
(VDUs) in the main control room and at various other locations throughout the plant.
Same of the VDUs are fitted with on-screen control devices for controlling non-safetyrelated systems and equipment.
Point Log and Alarm Module
General The Point Log and Alarm functions provide alarms and point data in the
form of logs, summaries and group point displays, and a user interface to control point
processing, logging, and alarming.
Analog Variable AlarmsThe processor is capable of checking each analog input
variable against two types of limits for alarming purposes:
7.7-58
Rev. 0
ABWR
The alarming sequence consists of an audible alarm, a console alarm, and a descriptive
message for the variables that exceed process alarm limits. The processor provides the
capability to alarm on the main control room annunciator system in the event of
abnormal PCS operation.
Status Alarm The status alarm of a point shall be updated with a time-after
occurrence equal to the processing cycle of the point plus two seconds. A printed record
of system alarms is provided which includes point description and time of occurrence.
Alarm Logging The alarm logs required by the associated process programs are
printed. Alarm printouts inform the operator of computer system malfunctions, system
operation exceeding acceptable limits and unreasonable, off-normal or failed input
sensors.
Trip/Scram Data Recall Logging The processor measures and stores the values of a
set of analog variables at predefined intervals to provide a history of data. An ondemand request permits the operator to initiate printing of this data and to terminate
the log printout when desired.
Trend Logging An analog trend capability is provided for logging the values of the
operator-selected analog inputs and calculated variables. The periodicity of the log is
limited to a nominal selection of intervals, which can be adjusted as desired by program
control.
Balance of Plant Performance Calculation Programs
The balance of plant (BOP)programs perform calculations and logging of plant
performance data not directly related to the nuclear system. The data stored by the BOP
program is printed out on logs. The BOP periodic log gives hourly and daily values for
temperatures, power outputs, and flows associated with the main generator and
turbines, and with the Feedwater Control and Reactor Water Cleanup/Shutdown
Cooling Systems. The BOP monthly log contains monthly averages and accumulations
for plant gross and net power outputs, load distributions, turbine heat rates, and fuel
burnup. The BOP performance calculations include flow calculations, electrical
calculations, thermodynamic calculations, Nuclear Boiler System performance
calculations, condenser calculation, feedwater heaters and moisture separators
performance calculations and unit performance calculations.
7.7.1.5.2 Power Generation Control Subsystem
The Power Generation Control Subsystem (PGCS) is a top level controller that
monitors the overall plant conditions, issues control commands to non-safety-related
systems, and adjusts setpoints of lower level controllers to support automation of the
normal plant startup, shutdown, and power range operations. The PGCS is a separate
Control Systems Not Required for Safety
7.7-59
Rev. 0
ABWR
function of the Process Computer System. The PGCS contains the algorithms for the
automated control sequences associated with plant startup, shutdown and normal
power range operation. The PGCS issues reactor command signals to the automatic
power regulator (APR). The reactor power change algorithms are implemented in the
APR.
In the automatic mode, the PGCS issues command signals to the turbine master
controller which contains appropriate algorithms for automated sequences of turbine,
feedwater, and related auxiliary systems. Command signals for setpoint adjustment of
lower level controllers and for startup/shutdown of other systems required for plant
operation are executed by the PGCS. The operator interfaces with the PGCS through a
series of breakpoint controls to initiate automated sequences from the operator control
console. For selected operations that are not automated, the PGCS prompts the
operator to perform such operations. In the semi automatic mode, the PGCS provides
guidance messages to the operator to carry out the startup, shutdown, and power range
operations.
The PGCS is classified as a power generation system and is not required for safety.
Safety-related events requiring control rod scram are sensed and controlled by the
safety-related Reactor Protection System which is completely independent of the PGCS.
The PGCS interfaces with the operator's console to perform its designated functions.
The operator's control console for PGCS consists of a series of breakpoint controls for
a prescribed plant operation sequence. When all the prerequisites are satisfied for a
prescribed breakpoint in a control sequence, a permissive is given and, upon
verification by the operator, the operator initiates the prescribed sequence. The PGCS
then initiates demand signals to the various system controllers to carry out the
predefined control functions. (NOTE: For non-automated operations that are required
during normal startup or shutdown (e.g., change of reactor mode switch status),
automatic prompts are provided to the operator. Automated operations continue after
the operator completes the prompted action manually.)
7.7.1.5.3 Safety Evaluation
The Process Computer System is designed to provide the operator with certain
categories of information and to supplement procedure requirements for control rod
manipulation during reactor startup and shutdown. The system augments existing
information from other systems such that the operator can start up, operate at power
and shut down in an efficient manner. The PGCS function provides signals to the APR
as explained in Subsection 7.7.1.5.2. However, this is a power generation function.
Neither the Process Computer System nor its PGCS function initiate or control any
engineered safeguard or safety-related system.
7.7-60
Rev. 0
ABWR
Description
The ATIP is comprised of three TIP machines, each with a neutron-sensitive
sensor attached to the machines flexible cable. Other than the sensor itself,
each machine has a drive mechanism, a 20-position index mechanism,
associated guide tube, and other parts. While not in use, the sensor is normally
stored and shielded in a storage area inside the TIP room in the reactor
building. During operation, the ATIP sensors are inserted, either manually or
automatically, via guide tubing and through desired index positions to the
designated LPRM assembly calibration tube. Each ATIP machine has
designated number and locations of LPRM assemblies to cover, such that the
ATIP sensor can travel to all LPRM locations assigned to this machine via the
index mechanism of this machine. The LPRM assignments to the three
machines are shown in Figure 7.7-10.
Flux readings along the axial length of the core are obtained by first inserting
the sensor fully to the top of the calibration tube and then taking data as the
sensor is withdrawn continuously from the top. Sensor flux reading, sensor
axial positions data in the core, and LPRM location data are all sent to an ATIP
control unit located in the control room, where the data can be stored. The
data are then sent to the process computer for calibration and performance
calculations. The whole ATIP scanning sequence and instructions are fully
automated, with manual control available.
7.7-61
Rev. 0
ABWR
The index mechanism allows the use of a single sensor in any one of twenty
different LPRM assemblies. There is a common LPRM location that allows all
three ATIP scanning. This is for ATIP cross-machine calibration.
To protect against inadvertent radiation exposure from the ATIP System, the
ATIP electronics and drive mechanism have built-in relay switches and
mechanical motor stop switches to prevent the TIP detector from withdrawal
into the drive mechanism. Alarm warnings are installed near the TIP room
and the access way to the drywell to prevent personnel radiation exposure
from the TIP (Subsection 12.3.2.3).
(2)
Classification
The ATIP is non-safety-related as shown in Table 3.2-1. The subsystem is an
operational system and has no safety function.
(3)
Power Supply
The power for the ATIP is supplied from the instrument AC power source.
(4)
Testability
The ATIP equipment is tested and calibrated using heat balance data and
procedures described in the instruction manual.
(5)
Environmental Considerations
The equipment and cabling located in the drywell are designed for
continuous duty (Section 3.11).
(6)
Operational Considerations
The ATIP can be operated during reactor operation to calibrate the LPRM
channels. The subsystem has no safety setpoints.
System Identification
The MRBM Subsystem logic issues a rod block signal that is used in the RCIS
logic to enforce rod blocks that prevent fuel damage by assuring that the
minimum critical power ratio (MCPR) and maximum linear heat generation
7.7-62
Rev. 0
ABWR
rate (MLHGR) do not violate fuel thermal safety limits. Once a rod block is
initiated, manual action is required by the operator to reset the system.
The MRBM microcomputer-based logic receives input signals from the local
power range monitors (LPRMs) and the average power range monitors
(APRMs) of the NMS. It also receives core flow data from the NMS, and
control rod status data from the rod action and position information
subsystem of the RCIS to determine when rod withdrawal blocks are required.
The MRBM averages the LPRM signals to detect local power change during
the rod withdrawal. If the averaged LPRM signal exceeds a preset rod block
setpoint, a control rod block demand will be issued. The MRBM monitors
many 4-by-4 fuel bundle regions in the core in which control rods are being
withdrawn as a gang. Since it monitors more than one region, it is called the
multi-channel rod block monitor. The rod block setpoint is a core-flow biased
variable setpoint. The MRBM is a dual channel system not classified as a safety
system.
(2)
Classification
The MRBM is non-safety-related. Its activating interface is through the Rod
Control and Information System (RCIS), which is also a non-safety-related
system.
(3)
Power Supply
The power supply for the MRBM is from the non-divisional 120 VAC UPS bus.
(4)
Testability
The MRBM is a dual channel, independent subsystem of the NMS. One of the
MRBM channels can be bypassed for testing or maintenance without affecting
the overall MRBM function. Self-test features are employed to monitor failures
in the microprocessor system. Test capabilities allow for calibration and trip
output testing.
(5)
Identification
7.7-63
Rev. 0
ABWR
Classification
The APR is classified as power generation system and is not required for safety.
Safety events requiring control rod scram are sensed and controlled by the
safety-related RPS, which is completely independent of the APR. The RPS is
discussed in Section 7.2.
(3)
Power Sources
The APR System digital controllers are powered by redundant uninterruptible
non-Class 1E power supplies and sources. No single power failure shall result
in the loss of any APR System function.
(4)
Normal Operation
The APR System interfaces with the operators console to perform its designed
functions. The operators control panel for automatic plant startup, power
operation, and shutdown functions is part of the PGCS. This control panel
consists of a series of breakpoint controls for a prescribed plant operation
sequence. When all the prerequisites are satisfied for a prescribed breakpoint
in a control sequence, a permissive is given and, upon verification by the
7.7-64
Rev. 0
ABWR
operator, the operator initiates the prescribed control sequence. The PGCS
then initiates demand signals to various system controllers to carry out the
predefined control functions. [Note: For non-automated operations that are
required during normal startup or shutdown (e.g., change of Reactor Mode
Switch status), automatic prompts are provided to the operator. Automated
operations continue after the operator completes the prompted action
manually.] The functions associated with reactor power control are
performed by the APR System.
For reactor power control, the APR System contains algorithms that can
change reactor power by control rod motions, or by reactor coolant
recirculation flow changes, but not both at the same time. A prescribed
control rod sequence is followed when manipulating control rods for reactor
criticality, heatup, power changes, and automatic load following. Each of these
functions has its own algorithm to achieve its designed objective. The control
rod sequence can be updated from the process computer based on inputs
from the reactor engineer. A predefined trajectory of power-flow is followed
when controlling reactor power. The potentially unstable region of the powerflow map is avoided during plant startup, automatic load following, and
shutdown. During automatic load following operation, the APR System
interfaces with the SB&PC System to coordinate main turbine and reactor
power changes for optimal performance.
(5)
Abnormal Operation
The normal mode of operation of the APR System is automatic. If any system
or component conditions are abnormal during execution of the prescribed
sequences, the PGCS will be automatically switched into the manual mode and
any operation in progress will be stopped. Alarms will be activated to alert the
operator. With the APR System in manual mode, the operator can manipulate
control rods and recirculation flow through the normal controls. A failure of
the APR System will not prevent manual controls of reactor power, nor will it
prevent safe shutdown of the reactor.
(6)
Equipment
The APR System control functional logic is performed by redundant,
microprocessor-based fault-tolerant digital controllers (FTDC). The FTDC
performs many functions. It reads and validates inputs from the Non-Essential
Multiplexing System (NEMS) interface once every sampling period. It
performs the specific power control calculations and processes the pertinent
alarm and interlock functions, then updates all system outputs to the NEMS.
To prevent computational divergence among the redundant processing
channels, each channel performs a comparison check of its calculated results
7.7-65
Rev. 0
ABWR
with the other redundant channels. The internal FTDC architecture features
redundant multiplexing interfacing units for communications between the
NEMS and the FTDC processing channels.
(7)
Testability
The FTDC input and output communication interfaces are continuously
functioning during normal power operation. Abnormal operation of these
components can be detected during operation. In addition, the FTDC is
equipped with self-test and online diagnostic capabilities for identifying and
isolating failure of input/output devices, buses, power supplies, processors,
and interprocessor communication paths. These online tests and diagnosis
can be performed without disturbing the normal control functions of the APR
System.
(8)
Environmental Considerations
The APR System is not required for safety purposes, nor is it required to
operate during or after any design basis accident. The system is required to
operate in the normal plant environment for power generation purposes only.
The APR System equipment is located in the main control room and subject
to the normal control room environment as listed in Section 3.11.
(9)
(10) Setpoints
The APR System has no safety setpoints.
7.7.1.8 Steam Bypass & Pressure Control SystemInstrumentation and Controls
(1)
7.7-66
Identification
Control Systems Not Required for Safety
Rev. 0
ABWR
The primary objective of the Steam Bypass & Pressure Control (SB&PC)
System is to control reactor vessel pressure during plant startup, power
generation and shutdown modes of operation. This is accomplished through
control of the turbine control and/or steam bypass valves, such that
susceptibility to reactor trip, turbine-generator trip, main steam isolation and
safety/relief valve opening is minimized.
Command signals for the turbine control valves and the steam bypass valves
are generated by a triplicated FTDC using feedback signals from vessel
pressure sensors. For normal operation, the turbine control valves regulate
steam pressure. However, whenever the total steam flow demand from the
pressure controller exceeds the effective turbine control valve steam flow
demand, the SB&PC sends the excess steam flow directly to the main
condenser, through the steam bypass valves.
Ability of the plant to follow grid-system load demands is enabled by adjusting
reactor power level, by varying reactor recirculation flow (manually or
automatically), or by moving control rods (manually or automatically). In
response to the resulting steam production changes, the SB&PC adjusts the
turbine control valves to accept the steam output change, thereby controlling
steam pressure. In addition, when the reactor is automatically following gridsystem load demands, the SB&PC permits an immediate steam flow response
to fast changes in load demand, thus utilizing part of the stored energy in the
vessel.
(2)
Classification
The SB&PC System is a power generation system and is non-safety related.
(3)
Power Sources
The SB&PC controls and bypass valves are powered by redundant
uninterruptable non-Class 1E power supplies and sources. No single power
failure will result in the loss of SB&PC System function. Upon failure of two or
more channels in the controller, the turbine will trip.
(4)
7.7-67
Rev. 0
ABWR
During plant startup and heatup, the SB&PC System provides for automatic
control of the reactor vessel pressure. Independent control of reactor pressure
and power is permitted, during reactor-vessel heatup, by varying steam bypass
flow as the main turbine is brought up to speed and synchronized.
The SB&PC System also controls pressure during normal (MSIVs open)
reactor shutdown to control the reactor cooling rate.
(5)
(6)
Equipment
The SB&PC System control functional logic is performed by triplicated
microprocessor-based FTDC similar to those used for the feedwater and
recirculation flow control systems. It is therefore possible to lose one complete
processing channel without impacting the system function. This also facilitates
taking one channel out of service for maintenance or repair while the system
is online. The IED and IBD are provided as Figures 7.7-12 and 7.7-13,
respectively.
Controls and valves are designed such that steam flow is shut off upon loss of
control system electrical power or hydraulic system pressure.
The pressure control function provides ABWR automatic load following by
forcing the turbine control valves to remain under pressure control
supervision, while enabling fast bypass opening for transient events requiring
fast reduction in turbine steam flow.
7.7-68
Rev. 0
ABWR
(b)
(c)
I&C Interface
The external signal interfaces for the SB&PC System are as follows:
(a)
Narrow range dome pressure signals from the SB&PC System to the
Recirculation Flow Control System.
(b)
Equivalent load or steam flow feedback signal from the Turbine Control
System (which is also a triplicated fault-tolerant digital controller).
(c)
(d) Bypass hydraulic power supply trouble signal from the Turbine Bypass
System to the SB&PC System.
(e)
(f)
Displayed variables and alarms from the SB&PC System to the main
control room panel operator interface.
(g)
Narrow and wide range pressure signals, MSIV position signals from the
Nuclear Boiler System to the SB&PC System.
(h) Bypass valve position, servo current, position error and valve open and
closed signals from the Turbine Bypass System.
(i)
Emergency bypass valve fast opening signals and bypass valve flow
demand signals from the SB&PC System to the Turbine Bypass System.
(j)
(k)
7.7-69
Rev. 0
ABWR
(l)
Testability
The FTDC input and output communication interfaces are continuously
functioning during normal power operation. Abnormal operation of these
components can be detected during operation. In addition, the FTDC is
equipped with self-test and online diagnostic capabilities for identifying and
isolating failure of input/output devices, buses, power supplies, processors,
and interprocessor communication paths. These online tests and diagnoses
can be performed without disturbing the normal control functions of the
SB&PC system.
(9)
Environmental Considerations
The SB&PC System is not required for safety purposes, nor is it required to
operate during or after any design basis accident. The system is required to
operate in the normal plant environment for power generation purposes only.
The SB&PC System equipment is located in the main control room and
subject to the normal control room environment (Section 3.11).
Rev. 0
ABWR
System Description
The NEMS provides distributed control and instrumentation data
communication networks to support the monitoring and control of
interfacing plant power generation (non-safety-related) systems. [The EMS
performs the same function for the protection (safety-related) systems.] The
NEMS provides all the electrical devices and circuitry (such as multiplexing
7.7-71
Rev. 0
ABWR
(b)
(c)
Receives signals via fiber optics, then multiplexes and prepares them for
use in interfacing non-safety-related equipment as required.
(d) Formats and transmits processed control signals via fiber optics to
actuator circuits, and then converts the fiber optic control signals to
electrical signals for the actuator circuits.
(2)
System Interface
The NEMS interfaces with the following systems, which are all non-safetyrelated:
Reactor
Nuclear Boiler (non-safety-related portion)
Reactor Recirculation
Rod Control
7.7-72
Rev. 0
ABWR
7.7-73
Rev. 0
ABWR
Heater Drain
Lubricating Oil
Turbine Gland Steam
Extraction
Main Generator
HVAC-Reactor Building
HVAC-Other Buildings
Electrical Power Distribution (non-safety-related portion)
Annunciator
(3)
Classification
The NEMs, of itself, is neither a power generation system nor a protection
system. It is a support system utilized for assimilation, transmission and
interpretation of data for power generation (non-safety-related) systems and
their associated sensors, actuators and interconnections. It is classified as nonsafety-related.
(4)
Power Sources
The NEMS receives its power from three separate non-Class 1E distribution
panels from the non-Class 1E 120 VAC UPS. This redundancy allows the
NEMS to supply triplicated logic functions such that any single failure in the
system power supplies will not cause the loss of the validated outputs to the
interfacing actuators and to the monitors and displays.
(5)
Equipment
The hardware and firmware architectures for the NEMS are the same as
those of the EMS, which are described in Appendix 7A [see the response to
NRC Requests (10) and (11) of Section 7A.2].
(6)
Testability
The EMS test features described in Appendix 7A, Section 7A.2, Items (3), (4)
and (6) are generally equivalent for the NEMS, except that the NEMS does not
interface with, nor rely upon, the SSLC [see the response to NRC Request (6)
7.7-74
Rev. 0
ABWR
of Section 7A.2]. Also, the NEMS self-test features include the analog faulttolerant voting system unique to the control systems employing logic.
(7)
Environmental Considerations
The NEMS is not required for safety purposes, nor is it required to operate
after the design basis accident. Its support function serves power generation
purposes only and it is designed to operate in the normal plant environment.
(8)
Operational Considerations
The system automatically initiates for both cold and warm starts. No operator
actions are required in that the system is capable of self-starting following
power interruptions, or any other single failure, including any single
processor failure. After repairs or replacements are performed, the system
automatically re-initializes to normal status when power is restored to any unit
and automatically resets any alarms.
(9)
Operator Information
The self-test provisions are designed to alert the operator to system anomalies
via interfaces with the process computer and the annunciator. Problems
significant enough to cause system channel failures are annunciated
separately from those which allow continued operation. The circuitry is
designed such that no control output or alarm is inadvertently activated
during system initialization or shutdown. For such events, control outputs
change to predetermined fail-safe outputs.
System Identification
The Fuel Pool Cooling and Cleanup System is non-safety-related.
Instrumentation and control is supplied to monitor and control the fuel pool
temperature. The filter/demineralizer portion is non-safety-related. The
instrumentation is for plant equipment protection.
The Fuel Pool Cooling and Cleanup System operates continuously on all plant
modes. Evaporative losses in the system are replaced by the condensate system.
If the heat load should become excessive, the Residual Heat Removal System
is operated in parallel with this system to remove the excess heat load when
the reactor is in shutdown condition. The arrangement of equipment and
control devices is shown in the P&ID (Figure 9.1-1). The interlock block
diagram is shown in Figure 7.7-14.
7.7-75
Rev. 0
ABWR
(2)
Power Sources
Although the system is non-safety-related, it is considered to be a plant
investment protection (PIP) load. Each of the two channels receives its power
from separate PIP buses, backed by the combustion turbine generator. DC
control power also comes from separate battery backed buses.
(3)
Equipment Design
The cooling loop components of the Fuel Pool Cooling System have been
designed to Seismic Category I requirements.
(a)
Circuit Description
Temperature indication (alarm high) and level indication (alarm both
high and low) are provided for the pools. The surge tank is also provided
with level indication, alarm high and low.
Surge tank low-low level trip will automatically shut off the fuel pool
pumps as described in Section 9.1.
The filter/demineralizer controls are carried out by a process control
subsystem. Discussion of circuit design is not presented, since the total
failure or malfunction of the subject control subsystem does not involve
any safety function or ramification. The logic provided within the
controller activates and carries out process activities such as
backwashing, precoating, and filtering, based on the process variable
condition.
(b)
(c)
(d) Testability
7.7-76
Rev. 0
ABWR
The system is designed to remove decay heat load in the fuel pool during
normal plan operation or at all other times. It is therefore fully testable
at any time.
(e)
Environment Considerations
Environmental conditions are the same for the normal condition and
the accident condition because there are no high-energy systems in the
area (Section 3.11).
(f)
Operational Considerations
There are no special operating considerations.
Subsection
9.5.1
Offgas/Radwaste
Drywell Cooling
9.4.8
Sampling
9.3.2
Instrument Air
9.3.6
Makeup Water
9.2.3
Atmospheric Control
6.2.5
7.7.2 Analysis
The purpose of this subsection is to:
(1)
(2)
7.7-77
Rev. 0
ABWR
In response to item (1) above, the following is cited: upon considering the design basis,
descriptions, and evaluations presented here and elsewhere throughout the document
relative to the subject system, it can be concluded that these systems do not perform any
safety-related function.
Design Basis: Refer to Subsection 7.1.1.
Description: Refer to Subsection 7.7.1.
The individual system analysis in this section concludes that the subject systems are not
required for any plant safety action.
For consideration of item (2), above, it is necessary to refer to the safety evaluations in
Chapter 15. In that chapter it is first shown that the subject systems are not utilized to
provide any DBA safety function. Safety functions, where required, are provided by
other qualified systems. For expected or abnormal transient incidents following the
single operator error (SOE) or single component failure (SCF) criteria, protective
functions are also shown to be provided by other systems. The expected or abnormal
transients cited are the limiting events for the subject systems.
7.7.2.1 Nuclear Boiler SystemReactor Vessel Instrumentation
7.7.2.1.1 General Functional Requirements Conformance
The reactor vessel instrumentation of the Nuclear Boiler System (NBS) is designed to
provide redundant or augmented information to the existing information required
from the engineered safeguards and safety-related systems. None of this non-safetyrelated instrumentation is required to initiate or control any engineered safeguard or
safety-related system function.
7.7.2.1.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the non-safety-related control systems and the associated codes
and standards applied in accordance with Section 7.7 of the Standard Review Plan for
BWRs. The following analysis lists the applicable criteria in order of the listing on the
table, and discusses the degree of conformance for each. Any exceptions or
clarifications are so noted.
(1)
(2)
7.7-78
(b)
Rev. 0
ABWR
In accordance with the Standard Review Plan for Section 7.7 and with
Table 7.1-2, only RG 1.151(Instrument Sensing Lines) need be addressed for
the ABWR.
(a)
(b)
7.7-79
Rev. 0
ABWR
the scram and normal rod control functions prevents failures in the rod control and
information circuitry from affecting the scram circuitry. The scram circuitry is discussed
in Section 7.2. The effectiveness of a reactor scram is not impaired by the
malfunctioning of any one control rod drive circuitry. It can be concluded that no single
failure in the RCIS can result in the prevention of a reactor scram, and that repair,
adjustment, or maintenance of the RCIS components does not affect the scram
circuitry.
Chapter 15 examines the various failure mode considerations for this system. The
expected and abnormal transients and accident events analyzed envelope the failure
modes associated with this systems components.
7.7.2.2.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the non-safety-related control systems and the associated codes
and standards applied in accordance with Section 7.7 of the Standard Review Plan for
BWRs. The following analysis lists the applicable criteria in order of the listing on the
table, and discusses the degree of conformance for each. Any exceptions or
clarifications are so noted.
(1)
(2)
(b)
7.7-80
Rev. 0
ABWR
Although not required to meet single-failure criteria, each processing channel of the
triply redundant digital processor receives its respective power input from an
uninterruptible, independent source of the instrument and control power supply
system. The allocation of the RIP equipment on four power buses is such that, on loss
of any single power bus, a maximum of three can be affected.
System single failure or single operator errors are evaluated in the transient analysis of
Chapter 15. It is shown that no malfunction in the RFC System can cause a transient
sufficient to cause significant damage to the fuel barrier or exceed the nuclear system
pressure limits.
7.7.2.3.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the non-safety-related control systems and the associated codes
and standards applied in accordance with Section 7.7 of the Standard Review Plan for
BWRs. The following analysis lists the applicable criteria in order of the listing on the
table, and discusses the degree of conformance for each. Any exceptions or
clarifications are so noted.
(1)
(2)
(b)
7.7-81
Rev. 0
ABWR
The system digital controllers and process measurement equipment are powered by
non-Class 1E redundant uninterruptible power supplies. No single power supply failure
shall result in the loss of any FDWC System function.
Chapter 15 examines the various failure modes for this system relative to plant safety
and operational effects.
7.7.2.4.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the non-safety-related control systems and the associated codes
and standards applied in accordance with Section 7.7 of the Standard Review Plan for
BWRs. The following analysis lists the applicable criteria in order of the listing on the
table, and discusses the degree of conformance for each. Any exceptions or
clarifications are so noted.
(1)
(2)
(b)
7.7-82
Rev. 0
ABWR
7.7-83
Rev. 0
ABWR
table, and discusses the degree of conformance for each. Any exceptions or
clarifications are so noted.
(1)
(2)
(b)
In accordance with the Standard Review Plan for Section 7.7 and with Table 7.1-2, only
RG 1.151 (Instrument Sensing Lines) need be addressed for the ABWR. The APR
System does not have any direct interface with the instrument lines; therefore, this
guide is not applicable.
7.7.2.8 Steam Bypass and Pressure Control SystemInstrumentation and Controls
7.7.2.8.1 General Functional Requirements Conformance
The Steam Bypass & Pressure Control (SB&PC) System is a power generation system in
that it inputs information to the Automatic Power Regulator, which, in turn, controls
reactor power by manipulating control rods (via the RCIS) or recirculation flow (via the
RFC System). The protective scram function is entirely separate (via the RPS).
The SB&PC is classified as non-safety-related and does not interface with any
engineered safeguard or safety-related system.
7.7.2.8.2 Specific Regulatory Requirements Conformance
Table 7.1-2 identifies the non-safety-related control systems and the associated codes
and standards applied in accordance with Section 7.7 of the Standard Review Plan for
BWRs. The following analysis lists the applicable criteria in order of the listing on the
table, and discusses the degree of conformance for each. Any exceptions or
clarifications are so noted.
(1)
(2)
7.7-84
(b)
Rev. 0
ABWR
In accordance with the Standard Review Plan for Section 7.7 and with
Table 7.1-2, only RG 1.151 (Instrument Sensing Lines) need be addressed
for the ABWR.
(a)
(b)
7.7-85
Rev. 0
ABWR
(2)
(b)
7.7-86
Rev. 0
ABWR
Subsection
9.5.1
Offgas/Radwaste
Drywell Cooling
9.4.8
Sampling
9.3.2
Instrument Air
9.3.6
Makeup Water
9.2.3
Atmospheric Control
6.2.5
5.4.8
7.7-87
Rev. 0
ABWR
Design Center
Maximum
(Units)
(a) Operating
10
20
50
(b) Non-operating
20
60
90
%RH
95
%RH
0.11
MPa
(1) Temperature
10
(b) Non-operating
50
0.09
0.1
(4) Radiation:
(5) Seismic:
7.7-88
Rev. 0
ABWR
LEVEL 3
BOTTOM OF
DRYER SKIRT
LEVEL 2
LEVEL 1
WIDE RANGE
LEVEL 4
NARROW RANGE
LEVEL8
LEVEL 7
SHUTDOWN RANGE
INSTRUMENT
READOUT RANGE
INSTRUMENT
TAP RANGE
7.7-89
Rev. 0
ABWR
7.7-90
Rev. 0
ABWR
0
I
J
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
270
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
61
A B
C
12
20
28
36
180
44
53
45
37
90
29
21
13
52
60
7.7-91
ABWR
7.7-92
REACTOR
ENGINEER
INPUTS
PLANT / AUTOMATION
STATUS INFORMATION
OPERATOR
INPUTS
PERFORMANCE
& PREDICTION
INFORMATION
PLANT / AUTOMATION
STATUS
PLANT COMPUTER PERFORMANCE
MONITORING & PREDICTION FUNCTIONS
CORE
MANAGEMENT
3 D CORE
PERFORMANCE
MONITORING &
PREDICTION
(PROCESS COMPUTER)
PLANT
STATUS
DATA
PLANT STATUS
DATABASE
MANAGEMENT
REACTOR
POWER
CONTROL
STATUS
POWER
CONTROL
MODE
SELECTION
APPROPRIATE
SETPOINTS
(E.G. DESIRED
HEATUP RATE)
AUTOMATIC
POWER
CONTROL
PERMISSIVES
PLANT
STATUS
DATA
HEATUP
RANGE
MODE
REACTOR
POWER
UP
MODE
POWER RANGE
CONTROL MODE
(INCLUDING
AUTOMATIC
LOAD FOLLOWING)
REACTOR
POWER
DOWN
MODE
REACTOR
SHUTDOWN
MODE
REACTOR
DEPRESSURIZATION
& COOLDOWN
MODE
Rev. 0
PLANT STATUS
INPUTS VIA
PLANT
COMPUTER DATA
ACQUISITION
EQUIPMENT
AUTO ROD
MOVEMENT
COMMANDS
AUTO
ROD
MOVEMENT
PERMISSIVE
AFC
DEMAND
CORE
FLOW
DEMAND
SPEED
DEMAND
RFCS MODE
(E.G.,AUTOMATIC
CORE FLOW
CONTROL
OR SPEED
CONTROL)
LOAD
SETPOINT,
LOAD LIMIT
EHC
MODE
VALIDATED
TURBINE
SPEED
VALIDATED
REACTOR
PRESSURE
ROD CONTROL
AND
ROD
CONTROL
&
INFORMATION
INFORMATION
SYSTEM
SYSTEM
AUTOMATIC
POWER
REGULATOR
FUNCTIONS
EHC
(PRESSURE
CONTROL
SYSTEM)
TURBINE
CONTROL
VALVE
ACTUATORS
BYPASS
CONTROL
VALVE
ACTUATORS
LOAD
DEMAND
ERROR
RECIRCULATION
FLOW CONTROL
SYSTEM (RFCS)
ASD'S (FOR CONTROL OF
SPEED OF THE 10 RIPS)
Figure 7.7-11 Simplified Functional Diagram of the Automatic Power Regulation System
PRESSURE
REGULATOR
SETPOINT,
BYPASS VALVE
POSITION
DEMAND
Rev. 0
ABWR
7.7-93/94
Rev. 0
ABWR
7.8-1/2
Thi d
t d ith F
M k
403
Rev. 0
ABWR
(2)
Thi d
t d ith F
7A-1
M k
403
Rev. 0
ABWR
Response (1)The list is provided as Table 7A-1. It was obtained by extraction from the
multiplexer I/O database which reflects information available on the system P&ID and IBD
drawings.
NRC Request (2)For the components cited above, describe the means of remote or local control
(other than by cutting wires or jumpering) that may be employed should the multiplexer fails.
Response (2)All Class-1E multiplex hardware is designed to meet the single-failure criteria.
Systems which employ such hardware have redundant channels such that no single failure of any
MUX unit could jeopardize any safety system action. In addition, local control is provided, via the
Remote Shutdown System, to bring the reactor to shutdown conditions in event of multiple safety
system failures or evacuation of the control room. The Remote Shutdown System is hard-wired and
therefore provides diversity to the MUX interfaces.
NRC Request (3)Describe the multiplexer pre-operational test program.
Response (3)The pre-operational test program will test the multiplexers concurrently with
instrumentation and control functional loop checks. As each input to a remote multiplexing unit
(RMU) is simulated using a suitable input device, the required outputs shall be verified correct. In
this manner, all hardware and software are confirmed concurrently.
Equipment verifications of the individual multiplexing units are performed at the factory and
typically include detailed component level tests which require special test apparatus and technical
expertise. Any malfunctioning not found during factory testing will be detected during preoperational tests of instrument loops.
Testing shall include instrument loop checks, calibration verification tests and response time
verification tests as described in ANSI/IEEE-338. If possible, the entire instrument loop shall be
tested from sensor to output device(s). Otherwise, suitable input devices shall be used to simulate
process inputs and the system outputs verified to be acceptable.
In addition to the testing described above, tests shall be developed to verify system redundancy and
electrical independence.
NRC Request (4)Describe the test and/or hardware features employed to demonstrate fault
tolerance to electromagnetic interference.
Response (4)One major deterrence to electromagnetic interference (EMI) in the multiplexing
system is the use of fiber optic data links as the transmission medium. Optical fiber, being a nonelectrical medium, has the inherent properties of immunity to electrical noise (EMI, RFI, and
lightning), point-to-point electrical isolation, and the absence of conventional transmission line
effects. Fiber optic multiplexing is also unaffected by the radiated noise from high voltage
conductors, by high frequency motor control drives, and by transient switching pulses from
electromagnetic contactors or other switching devices.
7A-2
Rev. 0
ABWR
However, the electrical-to-optical interface at the transmitting and receiving ends must still be
addressed to ensure complete immunity to EMI. The control equipment containing the electrical
circuitry use standard techniques for shielding, grounding, and filtering and are mounted in
grounded equipment panels provided with separate instrument ground buses. Panel location,
particularly in local areas, is carefully chosen to minimize noise effects from adjacent sources. The
use of fiber optic cables ensures that current-carrying ground loops will not exist between the control
room and local areas.
The use of redundancy provides the other major deterrence to EMI effects. The safety-related
multiplexing system uses redundant optical channels within each separated electrical division. The
systems are independent and will run asynchronously with respect to each other with no
communication between divisions. However, data communication and transfer is synchronized
within each division itself. This arrangement provides fault tolerance to EMI or other noise
occurring in isolated locations.
During normal operation, multiplexing system performance will be monitored by online tests such
as parity checks, data checks (boundary and range), and transmission timing. If response time
requirements permit, error correcting algorithms may be applied to mask noise effects. Periodic
surveillance using offline tests such as bit error rate will be used to verify overall system integrity.
As part of the pre-operational test program [see Request (3)], the system will be subjected to EMI
testing. EMI and RFI test measurements will be developed using the guidelines described in
ANSI/IEEE-C63.12, American National Standard for Electromagnetic Compatibility Limits
Recommended Practice. For testing susceptibility to noise generation from portable radio
transceivers, tests will be developed from ANSI/IEEE-C37.90.2, IEEE Trial-Use Standard,
Withstand Capability of Relay Systems to Radiated Electromagnetic Interference from
Transceivers. Section 5.5.3 of this standard describes tests for digital equipment using clocked logic
circuits.
With the system connected, each multiplexing unit (one at a time) will be required to demonstrate
immunity to the defined conducted and radiated tests. Units shall also comply with standard surge
withstand capability tests, as follows:
(a)
(b)
The interconnecting fiber optic links of the multiplexing system and SSLC are not subject to EMI
effects.
7A-3
Rev. 1
ABWR
For design guidance and additional test development guidance, the following military standards
shall be used:
(a)
(b)
Due to the comprehensive nature of these documents, their applicability to ground, airborne, and
shipboard equipment, and the differences in requirements for the Army, Navy and Air Force, the use
of these standards shall be limited to the susceptibility requirements and limits for class A3
equipment and subsystems (ground, fixed). Within these limits, the guidelines for Army
procurements only shall be used. Tests for transmitting and receiving equipment, power generators,
and special purpose military devices are not applicable.
[To facilitate achieving EMC compliance, system and equipment grounding and shielding
practices will follow the guidance of the standards listed below:
(a)
IEEE Std. 518, Guide for the Installation of Electrical Equipemnt to Minimize
Electrical Noise Inputs to Controllers from External Sources.
(b)
NRC Request (5)Describe the interconnection, if any, of any Class 1E multiplexer to non-Class
1E devices such as the plant computer.
Response (5)The interconnection of Class 1E multiplexers to non-Class 1E devices is done using
fiber optic cable. The fiber optic cable will provide the necessary isolation.
The plant process computer is connected to a buffer module (memory storage module). Information
is stored in this module by the 1E MUX units for access by the process computer, thus preventing
any interruption by the Non 1E process computer on the 1E MUX units.
NRC Request (6)Describe the online test and/or diagnostic features that may be employed,
including any operator alarms/indicators and their locations.
Response (6)The EMS self-test system relies on the Safety System Logic and Control (SSLC) test
control unit, though it has also its own local self-test system. Local self-test in each EMS unit
continues to provide diagnostic readout even if the test control unit fails.
A continuously operating self-test system checks all data transmission and provides operators with
fault information and fault location through dedicated alarms and computer output. The self-test
system operation or its failure cannot harm the operation of the safety systems.
Figure 7A-1 shows the general concept of the EMS interface with the test control unit. The online
test and diagnostic features including operator alarms and location are detailed as follows:
Rev. 1
ABWR
Self-test locates a fault down to the processing module level and provides positive local
identification of the failed device.
Detection of fatal (affects signal transmission) and non-fatal (does not affect signal
transmission) errors is annunciated and relayed to the computer. Operators are informed on
the type of malfunction and its location.
Local self-test is continuous. System end-to-end test is initiated in one division at a time by
communication between test units in each division.
The logic returns to its original state after the test sequence is completed. Indications of test
status (normal or in-test) and results (pass, fail) is provided.
The test function does not degrade system reliability. The test circuitry is physically and
electrically separated and isolated from the functional circuitry insofar as possible. Testing will
not cause actuation of the driven equipment.
Automatic initiation signals from plant sensors override an automatic test sequence and
perform the required safety function.
Failure of the test control unit does not affect the safety system functional logic.
7A-5
Rev. 0
ABWR
(2)
System Configuration
In each protection division, RMUs are located in local plant areas to acquire sensor data
and transmit it to the control room for processing. The RMUs also receive processed
signals from the control room for command of safety system actuators. CMUs are located
in the control room to transmit and receive data for the logic processing units of the safety
protection system (RPS and ESF). Response time constraints may dictate RPS outputs be
hardwired (not multiplexed) to the load drivers.
All interconnections are fiber optic data links. Within each division, the system uses
redundant links (either in a hot standby configuration or a bi-directional, reconfigurable
arrangement) for greater reliability.
The safety-related multiplexing systems in each division are separated and independent.
Hardware Configuration
(1)
7A-6
RMU
(a)
(b)
(c)
Input modules acquire safety-related analog and digital data from process
transmitters and equipment status contact closures, respectively. Analog input
modules perform signal conditioning and A/D conversion. Digital input modules
perform signal conditioning (filtering, voltage level conversion).
(d)
(e)
Rev. 1
ABWR
(2)
(f)
CPU and memory modules coordinate I/O and communication functions and
perform peripheral tasks such as self-test and calibration.
(g)
Front panel interface (isolated from safety-critical signal path) permits technician
access to calibration and diagnostic functions.
CMU
(a)
Same as RMU.
(b)
Same as RMU.
(c)
(d)
(e)
Communications interface modules acquire serial data from control room logic
processing units. The data is formatted and inserted via a fiber optic interface into
the multiplexed data stream out to the RMUs. The modules also receive
multiplexed serial data from the RMUs, demultiplex the data, and transmit it to
the control room logic processing units via an optical serial link.
(f)
Same as RMU.
(g)
Same as RMU.
[The development of the essential multiplexing as a deterministic, dual redundant, fiber optic
ring structure shall follow the Fiber Distributed Data Interface (FDDI) protocol as described in
the following American National Standards Insitute (ANSI) reference documents:
(a)
(b)
ANSI X3.148, :Fiber Distributed Data Interface (FDDI) - Token Ring Physical
Layer Protocol (PHY).
(c)
ANSI X3.139, Fiber Distributed Data Interface (FDDI) - Token Ring Media
Access Control (MAC).
7A-7
Rev. 1
ABWR
The multiplexing system is a real-time control application configured as a fiber optic local
area network.
(2)
Because time response for some functions is critical to safety, system timing must be
deterministic and not event-driven. A typical industry standard communications
protocol that is likely to be used is FDDI (Fiber Distributed Data Interface), a tokenpassing, counterrotating ring structure with data rates to 100M bit/s. Hardware
communications interfaces to this protocol are available, thus reducing the need for
special software development.
(3)
The safety-critical system functions are analog and digital data acquisition, signal
formatting, signal transmission, demultiplexing, and control signal outputs to
actuators. Peripheral functions are self-test features and system calibration (e.g.,
adjustment of A/D converters).
(4)
During system initialization or shutdown and after loss of power, control outputs to
actuators must fail to a safe state (fail safe or fail-as-is, as appropriate for the affected
safety system). System restart shall not cause inadvertent trip or initiation of safetyrelated equipment (i.e., system output shall depend only on sensed plant inputs).
(5)
High quality software is the most critical aspect of microprocessor-based designs for safety systems.
The software must be of easily proven reliability so as not to degrade the reliability and availability
of the overall system. When installed as firmware, the software should become, in effect, another
high quality hardware component of the control equipment, especially, since the program in ROM
is protected from being changed by external sources.
Software development will, in general, follow Regulatory Guide 1.152, which endorses ANSI/IEEE
ANS-7-4.3.2. These documents emphasize an orderly, structured, development approach and the
use of independent verification and validation to provide traceable confirmation of the design.
Validation must verify a predictable and safe response to abnormal as well as normal test cases. A
software-based design must also support the testability, calibration and bypass requirements of
IEEE-279.
7A-8
Rev. 1
ABWR
To meet the above requirements, the software will be developed as a structured set of simple modules.
Each module will perform a prescribed task that can be independently verified and tested. Modules
shall have one entry and one exit point. The software requirements specification and design
specification will define structures of external files used and interfaces with other programs. In place
of a formal operating system, an executive control program or real-time kernel will monitor,
schedule, and coordinate the linking and execution of the modules. The integration of the modules
into the control program will be another activity to be independently verified and validated.
The overall program structure will be a hierarchy of tasks. Separate modules will be created for
safety-critical tasks, calibration functions, and self-test functions, with self-test running in the
background at the lowest priority. Highest priority functions will always run to completion. The use
of interrupts will be minimized to prevent interference with scheduled tasks.
On detection of faults, retry or rollback to the last known correct state will be permitted within system
time constraints. If the fault is permanent and potentially unsafe, the system shall recover (or fail)
to a safe state and the operator shall be alerted. The redundant multiplexing channels shall be
repairable online if one channel fails. All processor memory not used for or by the operational
program shall be initialized to a pattern that will cause the system to revert to a safe state if executed.
The software shall permit online calibration and testing with the outputs to the safety systems
bypassed.
The software design shall prevent unauthorized access or modification.
Software development to achieve program operation as described above and to document and verify
this operation shall conform to the following standards:
(1)
(2)
(3)
(4)
(5)
NRC Request (12)Provide an explicit discussion of how the systems conform to the provisions of
IEEE-279, Section 4.17.
Response (12)The multiplexing system for safety systems only acquire data from plant sensors
(pressure, level, flow, etc.) and equipment status contact closures (open, close, start, stop, etc.) that
provide automatic trip or initiation functions for RPS and ESF equipment.
7A-9
Rev. 0
ABWR
Manual initiation inputs for protective action are implemented by direct, hardwired or optical
connections to the safety system logic (e.g., ECCS, containment isolation). Initiation outputs for
ECCS and isolation functions (except MSIV) are multiplexed to the actuators. Manual scram
(reactor trip) is provided by breaking the power source to the scram pilot valve solenoids external to
the multiplexing system and safety system logic. Manual reactor trip and manual MSIV closure in
each division are available even with multiplexing system failure, since these outputs are not
multiplexed to the actuators.
However, because the multiplexing system design is fault tolerant (replicated in four divisions and
redundant within each division) [see the responses to Requests (4), (10), and (11)], a single failure
will not degrade data communications in any division.
Therefore, the requirements of IEEE-279, Section 4.17, are satisfied, since a single failure will not
prevent initiation of protective action by manual or automatic means.
The last sentence of Section 4.17 states that manual initiation should depend upon the operation
of a minimum of equipment. The first paragraph has shown that reactor trip and MSIV initiation
do not depend at all on the multiplexing system. ECCS initiation and isolation initiation other
than MSIV do not depend on multiplexing for sending inputs to the logic and depend on the
operation of only one channel of multiplexing in each division to send outputs to actuators.
NRC Request (13)Provide an explicit discussion of how the systems conform to IEEE 279,
Paragraph 4.7.2, as supplemented by Regulatory Guide 1.75 and IEEE 384.
Response (13)The safety-related multiplexing system, which is part of the protection system, has
no direct interaction with the control systems. Sensor and equipment status data are multiplexed
only to protection system logic. However, two signals are sent from the protection system logic to the
Recirculation Flow Control System: Reactor Water Level 2 Trip and Recirculation Pump Trip. The
signals are transmitted via fiber optic data links, which are not part of the multiplexing system. An
isolating buffer (gateway) transfers these signals to the non-safety-related multiplexing network of
the control systems.
Fiber optic transmission lines are not subject to credible electrical faults such as short-circuit
loading, hot shorts, grounds or application of high AC or DC voltages. Adjacent cables are not
subject to induced fault currents or to being shorted together. The effects of cable damage are
restricted to signal loss or data corruption at the receiving equipment. Cables and control equipment
of different systems or assigned to different divisions are kept separated only to prevent simultaneous
physical damage.
Thus, the multiplexing system conforms to IEEE-279, paragraph 4.7.2, in that no credible failure
at the output of an isolation device can prevent the protection system channel from meeting
minimum performance requirements specified in the design bases.
7A-10
Rev. 0
ABWR
To meet the requirements of IEEE-384 and Regulatory Guide 1.75, the protective covering of the
fiber optic cables are flame retardant. The cables are passed through physical, safety class barriers,
where necessary, for separation of Class 1E circuits and equipment from other Class 1E equipment
or from non-Class 1E equipment. The fiber optic multiplexing network is independent in each
protection division and does not transmit or receive data between divisions. However, the
multiplexing equipment is kept physically separate to minimize the effects of design basis events.
NRC Request (14)Provide confirmation that system level failures of any multiplexer system
detected by automated diagnostic techniques are indicated to the operators consistent with
Regulatory Guide 1.47. (i.e., bypass and inoperable status indication)
Response (14)Each safety-related multiplexing system contains online self-diagnostics
implemented in software and hardware that will continuously monitor system performance. Within
each control station, the following typical parameters are monitored: (1) status of the CPU, (2)
parity checks, (3) data plausibility checks, (4) watchdog timer status, (5) voltage levels in control
unit circuitry, (6) memory (RAM and ROM) checks, and (7) data range and bounds checks.
Hardware is provided prior to transmission and following reception to detect transmission errors at
the Remote Multiplexing Units and the Control Room Multiplexing Units. Self-test will indicate
faults to the module board replacement level.
Each multiplexing system has dual channels for fault tolerance and is provided with automatic
reconfiguration and restart capability. A detected fault is automatically annunciated to the
operator at both the system and individual control station level. If one transmission loop is
completely out of service, that will also be annunciated. Total shutdown of a multiplexing system
is indicated by a separate alarm; however, individual control stations are repairable online without
taking the entire system down.
The above actions indicate conformance to Regulation Guide 1.47, Section C.1 (Automatic system
level indication of bypass or deliberately induced inoperability).
After repair, the system automatically re-initializes to normal status when power is restored to any
unit and automatically resets any alarms. Power loss to any control station is separately monitored
and annunciated to aid in troubleshooting and to alert the operator when power is deliberately
removed from a unit when being serviced. Power loss will cause the fault or out-of-service alarms
described previously to activate. This indicates conformance to Regulation Guide 1.47, Section C.2
[Automatic activation of indicating system of C.1 when auxiliary or supporting system (in this
case, power source) is bypassed or deliberately rendered inoperable].
Bypassed or inoperable status of any one multiplexing system can not render inoperable any
redundant portion of the protection system. Each multiplexing system is independent in each
division. Inoperable status in one division will cause the appropriate safe-state trips in that
division, but the other divisions will continue to operate normally. Faults in another division
simultaneously will indicate according to the previous discussion. The resulting safe-state trips will
7A-11
Rev. 0
ABWR
result in the required protective action. Thus, the requirements of Regulation Guide 1.47, Section
C.3, are satisfied.
During periodic surveillance, the system-level out-of-service indicators can be tested manually. This
satisfies the requirement of Regulation Guide 1.47, Section C.4.
NRC Request (15)Provide an explicit discussion of the susceptibility of the multiplexer systems
to electromagnetic interference.
Response (15)Each control station of the multiplexer system, either in the control room or in local
areas is electrically powered and contains solid-state logic and, therefore, is potentially susceptible
to the effects of EMI. However, the effects on the overall network are reduced because of the dual,
fiber optic, data transmission network that is used between stations. Fiber optics are not subject to
induced electrical currents, eliminate ground loops, and also do not radiate electrical noise. Thus,
the isolated and distributed nature of the system, which is also replicated in four divisions, tends to
reduce EMI effects.
Response (4) indicates several common techniques (shielding, grounding, etc.) used to minimize
EMI in the electrical control circuitry. Proper physical placement, especially for the Remote
Multiplexing Units, is essential to eliminate interference from high current or high voltage
switching devices.
Data checking software at the RMUs and in the control room at the Control Room Multiplexing
Units monitors data transmission to ensure that faults do not propagate into the safety protection
logic. Bad data transmission will cause a system alarm and, possibly, a system shutdown if the fault
does not clear within defined time constraints.
Response (4) also discusses various tests that the system will undergo to demonstrate immunity to
EMI.
7A-12
Optical characteristics
Rev. 0
ABWR
(2)
Optical characteristics are checked by an optical power meter and a hand-held light source to
determine the optical loss from one end of the fiber optic cable to the other. In an operational system,
an optical time domain reflectometer measures and displays optical loss along any continuous
optical fiber path. Any abrupt disruption in the optical path such as a splice or connector is seen as
a blip on the display. This technique is especially useful for troubleshooting long runs of cable such
as in the multiplexing system. Cable terminations are visually inspected under magnification to
determine if cracks and flaws have appeared in the optical fiber surfaces within the connector.
Transmission characteristics are tested by bit generation. This test method determines bit error rate
by generating a random stream of bits at the transmitter and verifying them at the receiver to
determine the reliability of the fiber optics. Data rate is set at the maximum throughput required by
the system. Proper transfer of analog signals is determined by analog-to-digital conversion of test
signals at the transmitting end, and monitoring of the digital-to-analog conversion at the receiving
end for linearity over the full scale range. Frequency of the test signals is set at the maximum
required by the system.
Maximum credible electrical faults applied at the outputs of isolation devices do not apply to fiber
optic systems. The maximum credible fault is cable breakage causing loss of signal transmission.
Faults cannot cause propagation of electrical voltages and currents into other electrical circuitry at
the transmitting or receiving ends. Conversely, electrical faults originating at the input to the fiber
optic transmitter can only damage the local circuitry and cause loss or corruption of data
transmission; damaging voltages and currents will not propagate to the receiving end.
NRC Request (2)Identify the data that will be used to verify that the maximum credible faults
applied during the test are the maximum voltage/current to which the device could be exposed, and
to define how the maximum voltage/current is determined.
Response (2)The response to Request (1) established that electrical faults are not credible at the
output of a fiber optic isolating device. Therefore, Request (2) is not relevant.
NRC Request (3)Identify the data that will be used to verify that the maximum credible fault is
applied to the output of the device in the transverse mode (between signal and return) and other
faults are considered (i.e., open and short circuits).
Response (3)The response to Request (1) established that electrical faults are not credible at the
output of a fiber optic isolating device. Open and short circuits of the fiber optic cable have no
electrical effect on the input side electrical circuitry.
NRC Request (4)Define the pass/fail acceptance criteria for each type of device.
Response (4)Since electrical faults at the outputs are not credible, acceptance tests for fiber optic
isolation devices need only verify optical characteristics and signal transmission characteristics as
defined in Response (1).
Design Response to Appendix B, ABWR LRB Instrumentation and Controls
7A-13
Rev. 0
ABWR
NRC Request (5)Provide a commitment that the isolation devices will comply with all
environmental qualification and seismic qualification requirements.
Response (5)Fiber optic isolation devices are expected to have less difficulty than previous
isolation devices in complying with all qualification requirements due to their small size, low mass,
and simple electronic interfaces. The basic materials and components, except for the fiber optic cable
itself, are the same as those used in existing, qualified isolation devices.
A major advantage of fiber optics is that signals can be transmitted long distances and around
curves through the isolating medium; thus, the physical, safety-class barrier required for separation
of Class 1E devices may be provided by just the cable length if the protective covering and any fill
materials of the cable are made properly flame-retardant. For short distances, the fiber optic cable
can be fed through a standard safety class structure.
Details of the type of cable, transmitter, and receiver combinations that will provide optimum
compliance with qualification requirements must await the guidance to be developed by the NRC
staff/EG&G studies (see Section 4).
NRC Request (6)Describe the measures taken to protect the safety systems from electrical
interference (i.e., electrostatic coupling, EMI, common mode, and crosstalk) that may be generated.
Response (6)Previous responses have described the specific measures that are employed to
minimize electrical interference. Fiber optic isolating devices do not require metallic shielding and
are immune from electrostatic coupling, EMI, common-mode effects, and crosstalk along their cable
length; they also do not radiate electrical interference. The electrical circuitry used to transmit and
receive the optical signals is susceptible to electrical interference in the same manner as other
circuitry, but the isolating effects of the fiber optic cable will reduce propagation of interference. The
local effects of EMI and other electrical noise are handled by standard filtering, shielding, and
grounding techniques.
See Reponse (4) of Section 7A.2 for tests that will be performed to verify the effectiveness of EMI
preventive measures for safety systems. Additional tests to determine the susceptibility of safety system
control equipment to electrostatic discharges shall be established using the test procedures included
in IEC Publication 801-2, Electromagnetic Compatibility for Industrial-Process Measurement and
Control Equipment, Part 2: Electrostatic Discharge Requirements. The test procedures of Paragraph
8 of this document shall be performed up to and including Severity Level 4, as defined in the
document.
NRC Request (7)Provide information to verify that the Class 1E isolation devices are powered
from a Class 1E power source(s).
Response (7)When using fiber optic devices as Class 1E isolation devices, only the input side of
the transmitting device and output side of the receiving device use electrical power. The low voltage
7A-14
Rev. 0
ABWR
power supplies for these devices use the same power source as the logic that drives the isolating device.
For ABWR safety systems, this power is:
(1)
Divisional 120V Vital AC (UPS)For Reactor Protection System (RPS) logic and Main
Steam Isolation Valve (MSIV) logic.
(2)
125V Plant DC Power SupplyFor ECCS logic and Leak Detection and Isolation
System (LDS) logic.
NRC Request (8)Provide a comparison of the design with the guidance in NUREG/CR3453/EGG-2444, Electronic Isolators Used in Safety Systems of U.S. Nuclear Power Plants,
March 1986.
Response (8)The isolating devices used for the ABWR are similar to the Group 1 types referred
to in the NUREG. They are of the long fiber optic cable design, so transmitting and receiving ends
are separated by a significant distance (typically several feet to several hundred feet). These types of
designs had the best isolating characteristics of the various isolators compared in the NUREG study.
Typically, the electrical-to-optical interfaces are part of the general logic processing equipment within
a channel and do not reside in separate isolator units. The fiber optic interfaces receive the
protection from EMI and surge currents designed into the logic equipment (for example, power
supply decoupling, shielding, filtering, single-point signal common connection to chassis ground,
and chassis ground connection to panel ground bus). The equipment will undergo EMI and surge
testing to the standards identified in the NUREG or equivalent.
The results of the NUREG tests show that the fiber optic type of isolators exhibited no or very little
effects from the major fault and lightning surge tests. Only surge and EMI tests applied to the
isolator power supplies caused damage to the isolator input side, mainly because of the output and
input supplies sharing a common, commercial AC power line. However, as noted in the NUREG
BWRs do not directly use a commercial power source. For the ABWR, RPS and ESF functions are
supplied from different plant power sources (120V Vital AC and 125 VDC, respectively). The low
voltage DC supplies fed from these sources are highly regulated and filtered. Thus, isolator circuitry
is isolated from most power source transients.
NRC Request (9)Provide a comparison of the design with the guidance in draft Regulatory
Guide EE502-4, Criteria for Electrical Isolation Devices Used in Safety Systems for Nuclear Power
Plants.
Response (9)(Draft RG EE502-4 was withdrawn by the NRC.)]*
7A-15
Rev. 0
ABWR
(2)
Regulatory Guide 1.152, Criteria for Programmable Digital Computer System Software
in Safety-Related Systems of Nuclear Power Plants, November 1985
(3)
(4)
(5)
IEEE-603, IEEE Standard Criteria for Safety Systems for Nuclear Power Generating
Stations
(2)
(3)
Regulatory Guide 1.153, Criteria for Power, Instrumentation and Control Portions of
Safety Systems
(4)
* Responses to Sections 7A.5 and 7A.6 above are grouped in various combinations, as appropriate,
in Subsection 7A.7
See section 7A.1(2) and 7A.1(1).
Responses to Sections 7A.5 and 7A.6 above are grouped in various combinations, as appropriate,
in Subsection 7A.7
7A-16
Rev. 0
ABWR
(5)
7A.7 Responses to Subsections 7A.5 & 7A.6; Computer Hardware and Software
Items 7A.5(1) and 7A.5(2)
Criteria and guidelines stated in ANSI/IEEE-ANS-7.4.3.2, as endorsed by Regulatory Guide
1.152, have been used as a basis for design procedures established for programmable digital
equipment.
All programmable digital equipment utilized for safety-related functions are qualified in accordance
with safety criteria and with the safety system design basis with which they interface.
Self-test or self-diagnostic features of this equipment, whether implemented in hardware or software,
are considered an integral part of the design, and, as such, are qualified to Class 1E standards.
A structured, engineered approach to the development of both hardware and software is
implemented to assure that the design proceeds along the lines of the requirement specifications and
has traceable documentation.
Verification and validation (V&V) includes the establishment of test and evaluation criteria, the
development of test and evaluation procedures, the testing of the integrated hardware and software,
and the installation of the hardware and software in the field.
In accordance with the step-by-step verification process, design reviews are performed at the system
functional and performance requirements specification/task analysis and allocation of functions
level, the hardware design and the software design level, the test and evaluation criteria and
procedures level, and the personnel requirements and operating/maintenance plan level. Such
reviews are conducted by knowledgeable and experienced system engineers, software engineers,
hardware engineers, etc., who are not directly responsible for the design, but who may be from the
same organization.
Figure 7A-2 illustrates the structure utilized for ABWR control and instrumentation system design
which incorporates subject guidelines.
7A-17
Rev. 0
ABWR
The ABWR design of the Reactor Protection System utilizes microprocessor technology for logic
decisions based on analog input from various sensors. This philosophy is much the same as that of
GESSAR II and the Clinton BWR, except in those designs, solid-state CMOS accepted digital
signals from analog trip modules (ATM). In the ABWR design, the microprocessors perform the
functions of both the CMOS and the ATM.
The important distinction is that the ABWR uses a modern form of digital computer device (i.e.,
microprocessors) for the same reasons relays and solid-state devices were used in earlier designs (i.e.,
making simple logic decisions); not for making complex calculations for which protective action is
dependent.
Rev. 0
ABWR
scram. These are Class 1E sensors, but they are not shared with other protection systems and the
interface with the recirc system is naturally isolated via fiber-optic cable.
Another use for some of the protection shared signals involves the ATWS trip which activates the
Fine Motion Control Rod Drive (FMCRD) run-in and alternate rod insertion (ARI) as diverse
backup to hydraulic scram. However, this Class-1E-to-non-Class-1E isolated interface is a special
case for mitigation of ATWS and is not a control system interface.
The ABWR demonstrates strong multi-system diversity in its capability to shut down and cool the
reactor core. There are four distinct systems for controlling reactivity and four distinct systems for
cooling the core.
Reactor Shutdown Systems
(1)
The RPS failsafe (i.e., scram on loss of power or data communications) hydraulic
scram (Subsection 7.2.1.1.4).
(2)
(3)
The ATWS-mitigating rod run-in function utilizing fine-motion control rod drive
(Subsection 7.7.1.2.2).
(4)
(2)
(3)
(4)
The Remote Shutdown System (RSS) also provides an independent means of actuating core cooling
functions diverse from the plant main control room.
In summary, the ABWR design has incorporated defense-in-depth principles through maintaining
separation of control and protection functions even though sensors are shared within protection
systems. In addition, the shared sensors are designed within a full four division architecture with
two-out-of-four voting logic.
Diversity principles are incorporated at both the signal and system levels: (1) diverse parameters are
monitored to automatically initiate protective actions which are also manually controllable; and,
(2) multiple diverse systems are available to both shut down the reactor and to cool its core.
Design Response to Appendix B, ABWR LRB Instrumentation and Controls
7A-19
Rev. 0
ABWR
Rev. 0
ABWR
Div
Description
B21-F003A
AO CHECK VALVE
B21-F003B
AO CHECK VALVE
B21-F010A
SRV/ADS VALVE
B21-F010A
SRV/ADS VALVE
B21-F010A
SRV/ADS VALVE
B21-F010B
B21-F010C
SRV/ADS VALVE
B21-F010C
SRV/ADS VALVE
B21-F010D
B21-F010E
B21-F010F
SRV/ADS VALVE
B21-F010F
SRV/ADS VALVE
B21-F010G
B21-F010H
SRV/ADS VALVE
B21-F010H
SRV/ADS VALVE
B21-F010H
SRV/ADS VALVE
B21-F010J
B21-F010K
B21-F010L
SRV/ADS VALVE
B21-F010L
SRV/ADS VALVE
B21-F010L
SRV/ADS VALVE
B21-F010M
B21-F010N
SRV/ADS VALVE
B21-F010N
SRV/ADS VALVE
B21-F010P
B21-F010R
SRV/ADS VALVE
B21-F010R
SRV/ADS VALVE
B21-F010S
B21-F010T
SRV/ADS VALVE
B21-F010T
SRV/ADS VALVE
B21-F010U
B21-F011
MO GATE VALVE
B21-F012
MO GATE VALVE
B21-LT001A
LEVEL TRANSMITTER
B21-LT001B
LEVEL TRANSMITTER
B21-LT001C
LEVEL TRANSMITTER
Thi d
t d ith F
7A-21
M k
403
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-22
Device
Div
Description
B21-LT001D
LEVEL TRANSMITTER
B21-LT003A
LEVEL TRANSMITTER
B21-LT003B
LEVEL TRANSMITTER
B21-LT003C
LEVEL TRANSMITTER
B21-LT003D
LEVEL TRANSMITTER
B21-LT003E
LEVEL TRANSMITTER
B21-LT003F
LEVEL TRANSMITTER
B21-LT003G
LEVEL TRANSMITTER
B21-LT003H
LEVEL TRANSMITTER
B21-LT006A
LEVEL TRANSMITTER
B21-LT006B
LEVEL TRANSMITTER
B21-POSZ902A
POSITION SWITCH
B21-POSZ902B
POSITION SWITCH
B21-POSZ902C
POSITION SWITCH
B21-POSZ902D
POSITION SWITCH
B21-POSZ902E
POSITION SWITCH
B21-POSZ902F
POSITION SWITCH
B21-POSZ902G
POSITION SWITCH
B21-POSZ902H
POSITION SWITCH
B21-POSZ902J
POSITION SWITCH
B21-POSZ902K
POSITION SWITCH
B21-POSZ902L
POSITION SWITCH
B21-POSZ902M
POSITION SWITCH
B21-POSZ902N
POSITION SWITCH
B21-POSZ902P
POSITION SWITCH
B21-POSZ902R
POSITION SWITCH
B21-POSZ902S
POSITION SWITCH
B21-POSZ902T
POSITION SWITCH
B21-POSZ902U
POSITION SWITCH
B21-F010A
B21-F010B
B21-F010C
B21-F010D
B21-F010E
B21-F010F
B21-F010G
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
B21-F010H
B21-F010J
B21-F010K
B21-F010L
B21-F010M
B21-F010N
B21-F010P
B21-F010R
B21-F010S
B21-F010T
B21-F010U
B21-PT007A
PRESS TRANSMITTER
B21-PT007B
PRESS TRANSMITTER
B21-PT007C
PRESS TRANSMITTER
B21-PT007D
PRESS TRANSMITTER
B21-PT025A
PRESS TRANSMITTER
B21-PT025B
PRESS TRANSMITTER
B21-PT025C
PRESS TRANSMITTER
B21-PT025D
PRESS TRANSMITTER
B21-PT028A
PRESS TRANSMITTER
B21-PT028B
PRESS TRANSMITTER
B21-PT028C
PRESS TRANSMITTER
B21-PT028D
PRESS TRANSMITTER
B21-PT301A
PRESS TRANSMITTER
B21-PT301B
PRESS TRANSMITTER
B21-PT301C
PRESS TRANSMITTER
B21-PT301D
PRESS TRANSMITTER
B21-TE019A
TEMP ELEMENT
B21-TE019B
TEMP ELEMENT
B21-TE020A
TEMP ELEMENT
B21-TE020B
TEMP ELEMENT
B21-TE021A
TEMP ELEMENT
B21-TE021B
TEMP ELEMENT
B21-TE022A
TEMP ELEMENT
B21-TE022B
TEMP ELEMENT
B21-TE023A
TEMP ELEMENT
7A-23
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-24
Device
Div
Description
B21-TE023B
TEMP ELEMENT
B21-TE024A
TEMP ELEMENT
B21-TE024B
TEMP ELEMENT
C12-D005001
C12-D005001
C12-D005002
C12-D005002
C12-D005003
C12-D005003
C12-D005004
C12-D005004
C12-D005005
C12-D005005
C12-D005006
C12-D005006
C12-D005007
C12-D005007
C12-D005008
C12-D005008
C12-D005009
C12-D005009
C12-D005010
C12-D005010
C12-D005011
C12-D005011
C12-D005012
C12-D005012
C12-D005013
C12-D005013
C12-D005014
C12-D005014
C12-D005015
C12-D005015
C12-D005016
C12-D005016
C12-D005017
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
C12-D005017
C12-D005018
C12-D005018
C12-D005019
C12-D005019
C12-D005020
C12-D005020
C12-D005021
C12-D005021
C12-D005022
C12-D005022
C12-D005023
C12-D005023
C12-D005024
C12-D005024
C12-D005025
C12-D005025
C12-D005026
C12-D005026
C12-D005027
C12-D005027
C12-D005028
C12-D005028
C12-D005029
C12-D005029
C12-D005030
C12-D005030
C12-D005031
C12-D005031
C12-D005032
C12-D005032
C12-D005033
C12-D005033
C12-D005034
C12-D005034
C12-D005035
7A-25
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-26
Device
Div
Description
C12-D005035
C12-D005036
C12-D005036
C12-D005037
C12-D005037
C12-D005038
C12-D005038
C12-D005039
C12-D005039
C12-D005040
C12-D005040
C12-D005041
C12-D005041
C12-D005042
C12-D005042
C12-D005043
C12-D005043
C12-D005044
C12-D005044
C12-D005045
C12-D005045
C12-D005046
C12-D005046
C12-D005047
C12-D005047
C12-D005048
C12-D005048
C12-D005049
C12-D005049
C12-D005050
C12-D005050
C12-D005051
C12-D005051
C12-D005052
C12-D005052
C12-D005053
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
C12-D005053
C12-D005054
C12-D005054
C12-D005055
C12-D005055
C12-D005056
C12-D005056
C12-D005057
C12-D005057
C12-D005058
C12-D005058
C12-D005059
C12-D005059
C12-D005060
C12-D005060
C12-D005061
C12-D005061
C12-D005062
C12-D005062
C12-D005063
C12-D005063
C12-D005064
C12-D005064
C12-D005065
C12-D005065
C12-D005066
C12-D005066
C12-D005067
C12-D005067
C12-D005068
C12-D005068
C12-D005069
C12-D005069
C12-D005070
C12-D005070
C12-D005071
7A-27
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-28
Device
Div
Description
C12-D005071
C12-D005072
C12-D005072
C12-D005073
C12-D005073
C12-D005074
C12-D005074
C12-D005075
C12-D005075
C12-D005076
C12-D005076
C12-D005077
C12-D005077
C12-D005078
C12-D005078
C12-D005079
C12-D005079
C12-D005080
C12-D005080
C12-D005081
C12-D005081
C12-D005082
C12-D005082
C12-D005083
C12-D005083
C12-D005084
C12-D005084
C12-D005085
C12-D005085
C12-D005086
C12-D005086
C12-D005087
C12-D005087
C12-D005088
C12-D005088
C12-D005089
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
C12-D005089
C12-D005090
C12-D005090
C12-D005091
C12-D005091
C12-D005092
C12-D005092
C12-D005093
C12-D005093
C12-D005094
C12-D005094
C12-D005095
C12-D005095
C12-D005096
C12-D005096
C12-D005097
C12-D005097
C12-D005098
C12-D005098
C12-D005099
C12-D005099
C12-D005100
C12-D005100
C12-D005101
C12-D005101
C12-D005102
C12-D005102
C12-D005103
C12-D005103
C12-D005104
C12-D005104
C12-D005105
C12-D005105
C12-D005106
C12-D005106
C12-D005107
7A-29
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-30
Device
Div
Description
C12-D005107
C12-D005108
C12-D005108
C12-D005109
C12-D005109
C12-D005110
C12-D005110
C12-D005111
C12-D005111
C12-D005112
C12-D005112
C12-D005113
C12-D005113
C12-D005114
C12-D005114
C12-D005115
C12-D005115
C12-D005116
C12-D005116
C12-D005117
C12-D005117
C12-D005118
C12-D005118
C12-D005119
C12-D005119
C12-D005120
C12-D005120
C12-D005121
C12-D005121
C12-D005122
C12-D005122
C12-D005123
C12-D005123
C12-D005124
C12-D005124
C12-D005125
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
C12-D005125
C12-D005126
C12-D005126
C12-D005127
C12-D005127
C12-D005128
C12-D005128
C12-D005129
C12-D005129
C12-D005130
C12-D005130
C12-D005131
C12-D005131
C12-D005132
C12-D005132
C12-D005133
C12-D005133
C12-D005134
C12-D005134
C12-D005135
C12-D005135
C12-D005136
C12-D005136
C12-D005137
C12-D005137
C12-D005138
C12-D005138
C12-D005139
C12-D005139
C12-D005140
C12-D005140
C12-D005141
C12-D005141
C12-D005142
C12-D005142
C12-D005143
7A-31
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-32
Device
Div
Description
C12-D005143
C12-D005144
C12-D005144
C12-D005145
C12-D005145
C12-D005146
C12-D005146
C12-D005147
C12-D005147
C12-D005148
C12-D005148
C12-D005149
C12-D005149
C12-D005150
C12-D005150
C12-D005151
C12-D005151
C12-D005152
C12-D005152
C12-D005153
C12-D005153
C12-D005154
C12-D005154
C12-D005155
C12-D005155
C12-D005156
C12-D005156
C12-D005157
C12-D005157
C12-D005158
C12-D005158
C12-D005159
C12-D005159
C12-D005160
C12-D005160
C12-D005161
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
C12-D005161
C12-D005162
C12-D005162
C12-D005163
C12-D005163
C12-D005164
C12-D005164
C12-D005165
C12-D005165
C12-D005166
C12-D005166
C12-D005167
C12-D005167
C12-D005168
C12-D005168
C12-D005169
C12-D005169
C12-D005170
C12-D005170
C12-D005171
C12-D005171
C12-D005172
C12-D005172
C12-D005173
C12-D005173
C12-D005174
C12-D005174
C12-D005175
C12-D005175
C12-D005176
C12-D005176
C12-D005177
C12-D005177
C12-D005178
C12-D005178
C12-D005179
7A-33
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-34
Device
Div
Description
C12-D005179
C12-D005180
C12-D005180
C12-D005181
C12-D005181
C12-D005182
C12-D005182
C12-D005183
C12-D005183
C12-D005184
C12-D005184
C12-D005185
C12-D005185
C12-D005186
C12-D005186
C12-D005187
C12-D005187
C12-D005188
C12-D005188
C12-D005189
C12-D005189
C12-D005190
C12-D005190
C12-D005191
C12-D005191
C12-D005192
C12-D005192
C12-D005193
C12-D005193
C12-D005194
C12-D005194
C12-D005195
C12-D005195
C12-D005196
C12-D005196
C12-D005197
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
C12-D005197
C12-D005198
C12-D005198
C12-D005199
C12-D005199
C12-D005200
C12-D005200
C12-D005201
C12-D005201
C12-D005202
C12-D005202
C12-D005203
C12-D005203
C12-D005204
C12-D005204
C12-D005205
C12-D005205
C12-F041
SO VALVE
C12-F042
SO VALVE
C12-F043
AO VALVE
C12-F044
AO VALVE
C12-F047
AO VALVE
C12-F048A
AO VALVE
C12-F048B
AO VALVE
C12-F049A
AO VALVE
C12-F049B
AO VALVE
C12-PT011A
PRESS TRANSMITTER
C12-PT011B
PRESS TRANSMITTER
C12-PT011C
PRESS TRANSMITTER
C12-PT011D
PRESS TRANSMITTER
E11-C001A
RHR PUMP
E11-C001B
RHR PUMP
E11-C001C
RHR PUMP
E11-C002A
E11-C002B
E11-C002C
7A-35
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-36
Device
Div
Description
E11-F001A
MO GATE VALVE
E11-F001B
MO GATE VALVE
E11-F001C
MO GATE VALVE
E11-F004A
MO GLOBE VALVE
E11-F004B
MO GLOBE VALVE
E11-F004C
MO GLOBE VALVE
E11-F005A
MO GATE VALVE
E11-F005B
MO GATE VALVE
E11-F005C
MO GATE VALVE
E11-F006A
AO CHECK VALVE
E11-F006B
AO CHECK VALVE
E11-F006C
AO CHECK VALVE
E11-F007B
E11-F007C
E11-F008A
MO GLOBE VALVE
E11-F008B
MO GLOBE VALVE
E11-F008C
MO GLOBE VALVE
E11-F009A
E11-F009B
E11-F009C
E11-F010A
MO GATE VALVE
E11-F010B
MO GATE VALVE
E11-F010C
MO GATE VALVE
E11-F011A
E11-F011B
E11-F011C
E11-F012A
MO GATE VALVE
E11-F012B
MO GATE VALVE
E11-F012C
MO GATE VALVE
E11-F013A
MO GLOBE VALVE
E11-F013B
MO GLOBE VALVE
E11-F013C
MO GLOBE VALVE
E11-F014B
MO GATE VALVE
E11-F014C
MO GATE VALVE
E11-F015B
MO GATE VALVE
E11-F015C
MO GATE VALVE
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
E11-F017B
MO GLOBE VALVE
E11-F017C
MO GLOBE VALVE
E11-F018B
MO GATE VALVE
E11-F018C
MO GATE VALVE
E11-F019B
MO GATE VALVE
E11-F019C
MO GATE VALVE
E11-F021A
MO GATE VALVE
E11-F021B
MO GATE VALVE
E11-F021C
MO GATE VALVE
E11-F029A
MO GATE VALVE
E11-F029B
MO GATE VALVE
E11-F029C
MO GATE VALVE
E11-F030A
MO GATE VALVE
E11-F030B
MO GATE VALVE
E11-F030C
MO GATE VALVE
E11-F031A
MO GLOBE VALVE
E11-F031B
MO GLOBE VALVE
E11-F031C
MO GLOBE VALVE
E11-F036A
AO GLOBE VALVE
E11-F036B
AO GLOBE VALVE
E11-F036C
AO GLOBE VALVE
E11-F043A
SO VALVE
E11-F043B
SO VALVE
E11-F043C
SO VALVE
E11-F044A
SO VALVE
E11-F044B
SO VALVE
E11-F044C
SO VALVE
E11-F045A
MO GLOBE VALVE
E11-F046A
MO GLOBE VALVE
E11-FT008A1
FLOW TRANSMITTER
E11-FT008A2
FLOW TRANSMITTER
E11-FT008B1
FLOW TRANSMITTER
E11-FT008B2
FLOW TRANSMITTER
E11-FT008C1
FLOW TRANSMITTER
E11-FT008C2
FLOW TRANSMITTER
E11-FT012B
FLOW TRANSMITTER
7A-37
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-38
Device
Div
Description
E11-FT015B
FLOW TRANSMITTER
E11-FT015C
FLOW TRANSMITTER
E11-POT303A
POSITION TRANSMITTER
E11-POT303B
POSITION TRANSMITTER
E11-POT303C
POSITION TRANSMITTER
E11-PT004A
PRESS TRANSMITTER
E11-PT004B
PRESS TRANSMITTER
E11-PT004C
PRESS TRANSMITTER
E11-PT004E
PRESS TRANSMITTER
E11-PT004F
PRESS TRANSMITTER
E11-PT004G
PRESS TRANSMITTER
E11-PT005A
PRESS TRANSMITTER
E11-PT005B
PRESS TRANSMITTER
E11-PT005C
PRESS TRANSMITTER
E11-PT009A
PRESS TRANSMITTER
E11-PT009B
PRESS TRANSMITTER
E11-PT009C
PRESS TRANSMITTER
E22-C001B
PUMP
E22-C001C
PUMP
E22-F001B
MO GATE VALVE
E22-F001C
MO GATE VALVE
E22-F003B
MO GATE VALVE
E22-F003C
MO GATE VALVE
E22-F004B
E22-F004C
E22-F005B
E22-F005C
E22-F006B
MO GATE VALVE
E22-F006C
MO GATE VALVE
E22-F008B
MO GLOBE VALVE
E22-F008C
MO GLOBE VALVE
E22-F009B
MO GLOBE VALVE
E22-F009C
MO GLOBE VALVE
E22-F010B
MO GATE VALVE
E22-F010C
MO GATE VALVE
E22-F019B
EQUALIZING VALVE
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
E22-F019C
EQUALIZING VALVE
E22-FT008B1
FLOW TRANSMITTER
E22-FT008B2
FLOW TRANSMITTER
E22-FT008C1
FLOW TRANSMITTER
E22-FT008C2
FLOW TRANSMITTER
E22-PT003B
PRESSURE TRANSMITTER
E22-PT003C
PRESSURE TRANSMITTER
E22-PT006B
PRESSURE TRANSMITTER
E22-PT006C
PRESSURE TRANSMITTER
E22-PT006F
PRESSURE TRANSMITTER
E22-PT006G
PRESSURE TRANSMITTER
E22-PT007B
PRESSURE TRANSMITTER
E22-PT007C
PRESSURE TRANSMITTER
E31-DPT006A
E31-DPT006B
E31-DPT006C
E31-DPT006D
E31-DPT013A
E31-DPT013B
E31-DPT013C
E31-DPT013D
E31-DPT014A
E31-DPT014B
E31-DPT014C
E31-DPT014D
E31-DPT015A
E31-DPT015B
E31-DPT015C
E31-DPT015D
E31-DPT016A
E31-DPT016B
E31-DPT016C
E31-DPT016D
E31-DPT016E
E31-DPT016F
E31-DPT016G
7A-39
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-40
Device
Div
Description
E31-DPT016H
E31-DPT016J
E31-DPT016K
E31-DPT016L
E31-DPT016M
E31-DPT016N
E31-DPT016P
E31-DPT016R
E31-DPT016S
E31-F002
A O SOLENOID VALVE
E31-F003
A O SOLENOID VALVE
E31-F004
A O SOLENOID VALVE
E31-F005
A O SOLENOID VALVE
E31-PT007A
PRESS TRANSMITTER
E31-PT007D
PRESS TRANSMITTER
E31-TE005A
TEMP ELEMENT
E31-TE005B
TEMP ELEMENT
E31-TE005C
TEMP ELEMENT
E31-TE005D
TEMP ELEMENT
E31-TE008A
TEMP ELEMENT
E31-TE008B
TEMP ELEMENT
E31-TE008C
TEMP ELEMENT
E31-TE008D
TEMP ELEMENT
E31-TE008E
TEMP ELEMENT
E31-TE008F
TEMP ELEMENT
E31-TE008G
TEMP ELEMENT
E31-TE008H
TEMP ELEMENT
E31-TE008J
TEMP ELEMENT
E31-TE008K
TEMP ELEMENT
E31-TE008L
TEMP ELEMENT
E31-TE008M
TEMP ELEMENT
E31-TE009A
TEMP ELEMENT
E31-TE009B
TEMP ELEMENT
E31-TE009C
TEMP ELEMENT
E31-TE009D
TEMP ELEMENT
E31-TE009E
TEMP ELEMENT
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
E31-TE009F
TEMP ELEMENT
E31-TE009G
TEMP ELEMENT
E31-TE009H
TEMP ELEMENT
E31-TE009J
TEMP ELEMENT
E31-TE009K
TEMP ELEMENT
E31-TE009L
TEMP ELEMENT
E31-TE009M
TEMP ELEMENT
E31-TE010A
TEMP ELEMENT
E31-TE010B
TEMP ELEMENT
E31-TE010C
TEMP ELEMENT
E31-TE010D
TEMP ELEMENT
E31-TE011A
TEMP ELEMENT
E31-TE011B
TEMP ELEMENT
E31-TE011C
TEMP ELEMENT
E31-TE011D
TEMP ELEMENT
E31-TE012A
TEMP ELEMENT
E31-TE012B
TEMP ELEMENT
E31-TE012C
TEMP ELEMENT
E31-TE012D
TEMP ELEMENT
E31-TE018A
TEMP ELEMENT
E31-TE019A
TEMP ELEMENT
E31-TE020A
TEMP ELEMENT
E31-TE020B
TEMP ELEMENT
E31-TE020C
TEMP ELEMENT
E31-TE020D
TEMP ELEMENT
E31-TE021A
E31-TE021B
E31-TE021C
E31-TE021D
E31-TE022A
TEMP ELEMENT
E31-TE022B
TEMP ELEMENT
E31-TE022C
TEMP ELEMENT
E31-TE022D
TEMP ELEMENT
E31-TE023A
TEMP ELEMENT
E31-TE023B
TEMP ELEMENT
E31-TE023C
TEMP ELEMENT
7A-41
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-42
Device
Div
Description
E31-TE023D
TEMP ELEMENT
E31-TE024A
TEMP ELEMENT
E31-TE024B
TEMP ELEMENT
E31-TE024C
TEMP ELEMENT
E31-TE024D
TEMP ELEMENT
E31-TE025A
TEMP ELEMENT
E31-TE025B
TEMP ELEMENT
E31-TE025C
TEMP ELEMENT
E31-TE025D
TEMP ELEMENT
E31-TE026A
TEMP ELEMENT
E31-TE026B
TEMP ELEMENT
E31-TE026C
TEMP ELEMENT
E31-TE026D
TEMP ELEMENT
E31-TE027A
TEMP ELEMENT
E31-TE027B
TEMP ELEMENT
E31-TE027C
TEMP ELEMENT
E31-TE027D
TEMP ELEMENT
E31-TE028A
TEMP ELEMENT
E31-TE028B
TEMP ELEMENT
E31-TE028C
TEMP ELEMENT
E31-TE028D
TEMP ELEMENT
E31-TE029A
TEMP ELEMENT
E31-TE029B
TEMP ELEMENT
E31-TE029C
TEMP ELEMENT
E31-TE029D
TEMP ELEMENT
E31-TE031A
TEMP ELEMENT
E31-TE031E
TEMP ELEMENT
E31-TE031J
TEMP ELEMENT
E31-TE032A
TEMP ELEMENT
E31-TE032E
TEMP ELEMENT
E31-TE032J
TEMP ELEMENT
E31-TE033A
TEMP ELEMENT
E31-TE033E
TEMP ELEMENT
E31-TE033J
TEMP ELEMENT
E31-TE034A
TEMP ELEMENT
E31-TE034E
TEMP ELEMENT
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
E31-TE034J
TEMP ELEMENT
E51-C002
TURBINE
E51-C901
VACUUM PUMP
E51-C902
CONDENSATE PUMP
E51-F001
MO GATE VALVE
E51-F004
MO GATE VALVE
E51-F005
A0 CHECK VALVE
E51-F006
MO GATE VALVE
E51-F008
MO GLOBE VALVE
E51-F009
MO GLOBE VALVE
E51-F011
MO GLOBE VALVE
E51-F012
MO GLOBE VALVE
E51-F026
AO GLOBE VALVE
E51-F031
SO DIAPHRAM VALVE
E51-F032
SO DIAPHRAM VALVE
E51-F035
MO GATE VALVE
E51-F036
MO GATE VALVE
E51-F037
MO GLOBE VALVE
E51-F039
MO GATE VALVE
E51-F040
AO GLOBE VALVE
E51-F041
AO GLOBE VALVE
E51-F045
MO GLOBE VALVE
E51-F047
MO GATE VALVE
E51-F048
MO GLOBE VALVE
E51-F058
AO GLOBE VALVE
E51-FT007-1
FLOW TRANSMITTER
E51-FT007-2
FLOW TRANSMITTER
E51-LS011
LEVEL SWITCH
E51-POT901
POSITION TRANSMITTER
E51-POT902
POSITION TRANSMITTER
E51-PT001
PRESS TRANSMITTER
E51-PT002
PRESS TRANSMITTER
E51-PT005
PRESS TRANSMITTER
E51-PT008
PRESS TRANSMITTER
E51-PT009
PRESS TRANSMITTER
E51-PT013A
PRESS TRANSMITTER
7A-43
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-44
Device
Div
Description
E51-PT013E
PRESS TRANSMITTER
E51-PT014A
PRESS TRANSMITTER
E51-PT014B
PRESS TRANSMITTER
E51-PT014E
PRESS TRANSMITTER
E51-PT014F
PRESS TRANSMITTER
E51-SE997
SPEED ELEMENT
G31-F002
MO GATE VALVE
G31-F003
MO GATE VALVE
G31-F015
MO GLOBE VALVE
G31-F017
MO GATE VALVE
G51-F001
MO GATE VALVE
G51-F002
MO GATE VALVE
G51-F007
MO GATE VALVE
K11-C001A
K11-C001B
K11-C101A
K11-C101B
K11-C102A
K11-C102B
K11-C102C
K11-C102D
K11-C102E
K11-C102F
K11-C102G
K11-C102H
K11-C102I
K11-C102J
P13-LT001A
P13-LT001B
P13-LT001C
P13-LT001D
P21-C001A
PUMP
P21-C001B
PUMP
P21-C001C
PUMP
P21-C001E
PUMP
P21-C001F
PUMP
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
P21-C001D
PUMP
P21-DPS033A
P21-DPS033B
P21-DPS033C
P21-DPS034A
P21-DPS034B
P21-DPS034C
P21-E/P605A
E/P CONVERTER
P21-E/P605B
E/P CONVERTER
P21-E/P605C
E/P CONVERTER
P21-F004A
MO GATE VALVE
P21-F004B
MO GATE VALVE
P21-F004C
MO GATE VALVE
P21-F004D
MO GATE VALVE
P21-F004E
MO GATE VALVE
P21-F004F
MO GATE VALVE
P21-F004G
MO GATE VALVE
P21-F004H
MO GATE VALVE
P21-F004J
MO GATE VALVE
P21-F013A
MO GLOBE VALVE
P21-F013B
MO GLOBE VALVE
P21-F013C
MO GLOBE VALVE
P21-F018A
MO GLOBE VALVE
P21-F018B
MO GLOBE VALVE
P21-F018C
MO GLOBE VALVE
P21-F019A
AO GLOBE VALVE
P21-F019B
AO GLOBE VALVE
P21-F019C
AO GLOBE VALVE
P21-F025A
MO GLOBE VALVE
P21-F025B
MO GLOBE VALVE
P21-F025C
MO GLOBE VALVE
P21-F025E
MO GLOBE VALVE
P21-F025F
MO GLOBE VALVE
P21-F055A
MO GATE VALVE
P21-F055B
MO GATE VALVE
P21-F055C
MO GATE VALVE
7A-45
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-46
Device
Div
Description
P21-F055D
MO GATE VALVE
P21-F055E
MO GATE VALVE
P21-F055F
MO GATE VALVE
P21-F072A
AO VALVE
P21-F072B
AO VALVE
P21-F072C
AO VALVE
P21-F072D
AO VALVE
P21-F072E
AO VALVE
P21-F072F
AO VALVE
P21-F074A
MO GATE VALVE
P21-F074B
MO GATE VALVE
P21-F074C
MO GATE VALVE
P21-F075A
MO GATE VALVE
P21-F075B
MO GATE VALVE
P21-F080A
MO GATE VALVE
P21-F080B
MO GATE VALVE
P21-F081A
MO GATE VALVE
P21-F081B
MO GATE VALVE
P21-F082A
MO GATE VALVE
P21-F082B
MO GATE VALVE
P21-F082C
MO GATE VALVE
P21-F084A
P21-F084B
P21-F084C
P21-F195A
MO GATE VALVE
P21-F195B
MO GATE VALVE
P21-F196A
MO GATE VALVE
P21-F196B
MO GATE VALVE
P21-FT006A
FLOW TRANSMITTER
P21-FT006B
FLOW TRANSMITTER
P21-FT006C
FLOW TRANSMITTER
P21-FT008A
FLOW TRANSMITTER
P21-FT008B
FLOW TRANSMITTER
P21-FT008C
FLOW TRANSMITTER
P21-FT042A
FLOW TRANSMITTER
P21-FT042B
FLOW TRANSMITTER
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
P21-FT042C
FLOW TRANSMITTER
P21-LS015A
LEVEL SWITCH
P21-LS015B
LEVEL SWITCH
P21-LS015C
LEVEL SWITCH
P21-LT013A
LEVEL TRANSMITTER
P21-LT013B
LEVEL TRANSMITTER
P21-LT013C
LEVEL TRANSMITTER
P21-LT014A
LEVEL TRANSMITTER
P21-LT014B
LEVEL TRANSMITTER
P21-LT014C
LEVEL TRANSMITTER
P21-LT014D
LEVEL TRANSMITTER
P21-LT014E
LEVEL TRANSMITTER
P21-LT014F
LEVEL TRANSMITTER
P21-LT014G
LEVEL TRANSMITTER
P21-LT014H
LEVEL TRANSMITTER
P21-LT014J
LEVEL TRANSMITTER
P21-PT004A
PRESS TRANSMITTER
P21-PT004B
PRESS TRANSMITTER
P21-PT004C
PRESS TRANSMITTER
P21-TE005A
TEMP ELEMENT
P21-TE005B
TEMP ELEMENT
P21-TE005C
TEMP ELEMENT
P21-TE009A
TEMP ELEMENT
P21-TE009B
TEMP ELEMENT
P21-TE009C
TEMP ELEMENT
P24-F053
MO GATE VALVE
P24-F141
MO GATE VALVE
P24-F142
MO GATE VALVE
P25 F016A
P25-C001A
HECW PUMP
P25-C001B
HECW PUMP
P25-C001C
HECW PUMP
P25-C001E
HECW PUMP
P25-C001F
HECW PUMP
P25-D001A
REFRIGERATOR
P25-D001B
REFRIGERATOR
7A-47
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-48
Device
Div
Description
P25-D001C
REFRIGERATOR
P25-D001E
REFRIGERATOR
P25-D001F
REFRIGERATOR
P25-DPT007A
P25-DPT007B
P25-DPT007C
P25-F005B
P25-F005C
P25-F012A
P25-F012B
P25-F012C
P25-F016B
P25-F016C
P25-F022A
P25-F022B
P25-F022C
P25-FIS003A
P25-FIS003B
P25-FIS003C
P25-FIS003E
P25-FIS003F
P25-TE005A
TEMP ELEMENT
P25-TE005B
TEMP ELEMENT
P25-TE005C
TEMP ELEMENT
P41-C001A
RSW PUMP
P41-C001B
RSW PUMP
P41-C001C
RSW PUMP
P41-C001D
RSW PUMP
P41-C001E
RSW PUMP
P41-C001F
RSW PUMP
P41-DPI004A
P41-DPI004B
P41-DPI004C
P41-DPI004D
P41-DPI004E
P41-DPI004F
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
P41-DPS004A
P41-DPS004B
P41-DPS004C
P41-DPS004D
P41-DPS004E
P41-DPS004F
P41-DPT004A
P41-DPT004B
P41-DPT004C
P41-DPT004D
P41-DPT004E
P41-DPT004F
P41-F003A
MO BUTTERFLY VLV
P41-F003B
MO BUTTERFLY VLV
P41-F003C
MO BUTTERFLY VLV
P41-F003D
MO BUTTERFLY VLV
P41-F003E
MO BUTTERFLY VLV
P41-F003F
MO BUTTERFLY VLV
P41-F004A
MO BUTTERFLY VLV
P41-F004B
MO BUTTERFLY VLV
P41-F004C
MO BUTTERFLY VLV
P41-F004D
MO BUTTERFLY VLV
P41-F004E
MO BUTTERFLY VLV
P41-F004F
MO BUTTERFLY VLV
P41-F005A
MO BUTTERFLY VLV
P41-F005B
MO BUTTERFLY VLV
P41-F005C
MO BUTTERFLY VLV
P41-F005D
MO BUTTERFLY VLV
P41-F005E
MO BUTTERFLY VLV
P41-F005F
MO BUTTERFLY VLV
P41-F005G
MO BUTTERFLY VLV
P41-F005H
MO BUTTERFLY VLV
P41-F005J
MO BUTTERFLY VLV
P41-F006A
MO BUTTERFLY VLV
P41-F006B
MO BUTTERFLY VLV
P41-F006C
MO BUTTERFLY VLV
7A-49
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-50
Device
Div
Description
P41-F006D
MO BUTTERFLY VLV
P41-F006E
MO BUTTERFLY VLV
P41-F006F
MO BUTTERFLY VLV
P41-F009A
AO GLOBE VALVE
P41-F009B
AO GLOBE VALVE
P41-F009C
AO GLOBE VALVE
P41-F009D
AO GLOBE VALVE
P41-F009E
AO GLOBE VALVE
P41-F009F
AO GLOBE VALVE
P41-F009G
AO GLOBE VALVE
P41-F009H
AO GLOBE VALVE
P41-F009J
AO GLOBE VALVE
P41-F011A
AO GLOBE VALVE
P41-F011B
AO GLOBE VALVE
P41-F011C
AO GLOBE VALVE
P41-F011D
AO GLOBE VALVE
P41-F011E
AO GLOBE VALVE
P41-F011F
AO GLOBE VALVE
P41-F011G
MO BUTTERFLY VLV
P41-F011H
MO BUTTERFLY VLV
P41-F011J
MO BUTTERFLY VLV
P41-F013A
MO BUTTERFLY VLV
P41-F013B
MO BUTTERFLY VLV
P41-F013C
MO BUTTERFLY VLV
P41-F013D
MO BUTTERFLY VLV
P41-F013E
MO BUTTERFLY VLV
P41-F013F
MO BUTTERFLY VLV
P41-F014A
MO BUTTERFLY VLV
P41-F014B
MO BUTTERFLY VLV
P41-F014C
MO BUTTERFLY VLV
P41-F015A
MO BUTTERFLY VLV
P41-F015B
MO BUTTERFLY VLV
P41-F015C
MO BUTTERFLY VLV
P41-PT003A
PRESS TRANSMITTER
P41-PT003B
PRESS TRANSMITTER
P41-PT003C
PRESS TRANSMITTER
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
P51-F276
MO GLOBE VALVE
P54-F003A
MO GLOBE VALVE
P54-F003B
MO GLOBE VALVE
P54-F007A
MO GLOBE VALVE
P54-F007B
MO GLOBE VALVE
P54-F012A
MO GLOBE VALVE
P54-F012B
MO GLOBE VALVE
P54-F200
MO GLOBE VALVE
P54-PIS001A
P54-PIS001B
P54-PT002A
PRESS TRANSMITTER
P54-PT002B
PRESS TRANSMITTER
P54-PT005
PRESS TRANSMITTER
R42-P005A
R42-P005B
R42-P005C
R42-P005D
R42-P006A
R42-P006B
R42-P006C
R42-P006D
7A-51
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-52
Device
Div
Description
R42-P007A
R42-P007B
R42-P007C
R42-P007D
R42-P008A
1,2
R42-P008B
1,3
R43-C201A
COMPRESSOR
R43-C201B
COMPRESSOR
R43-C201C
COMPRESSOR
R43-C202A
COMPRESSOR
R43-C202B
COMPRESSOR
R43-C202C
COMPRESSOR
R43-C401A
R43-C401B
R43-C401C
R43-DPS091A
R43-DPS091B
R43-DPS091C
R43-J001A
DIESEL GENERATOR
R43-J001B
DIESEL GENERATOR
R43-J001C
DIESEL GENERATOR
R43-LIS191A
R43-LIS191B
R43-LIS191C
R43-LS142A
LEVEL SWITCH
R43-LS142B
LEVEL SWITCH
R43-LS142C
LEVEL SWITCH
R43-LS395A
LEVEL SWITCH
R43-LS395B
LEVEL SWITCH
R43-LS395C
LEVEL SWITCH
R43-P001A
R43-P001B
R43-P001C
R43-P002A
R43-P002B
R43-P002C
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
R43-P003A
R43-P003B
R43-P003C
R46-J002A1
R46-J002B1
R46-J002C1
R46-J002D1
R46-P001A
VITAL CVCF A
R46-P001B
VITAL CVCF B
R46-P001C
VITAL CVCF C
R46-P001D
VITAL CVCF D
T22-B001B
T22-B001C
T22-C001B
T22-C001C
T22-C002B
T22-C002C
T22-D001B
T22-D001C
T22-DPT003
T22-DPT007
T22-DPT008
T22-DPT012
T22-DPT017
T22-DPT021A
T22-DPT021B
T22-DPT021C
T22-DPT021D
T22-DPT022
T22-DPT027
T22-DPT103
T22-DPT107
T22-DPT108
T22-F002B
MO BUTTERFLY VALVE
T22-F002C
MO BUTTERFLY VALVE
T22-F004B
MO BUTTERFLY VALVE
7A-53
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-54
Device
Div
Description
T22-F004C
MO BUTTERFLY VALVE
T22-F005B
MO BUTTERFLY VALVE
T22-F005C
MO BUTTERFLY VALVE
T22-FT018B
FLOW TRANSMITTER
T22-FT018C
FLOW TRANSMITTER
T22-H001C1
T22-H001C2
T22-H001C3
T22-H001C4
T22-H001B1
T22-H001B2
T22-H001B3
T22-H001B4
T22-LS004B
LEVEL SWITCH
T22-LS004C
LEVEL SWITCH
T22-LS029C
LEVEL SWITCH
T22-LS029B
LEVEL SWITCH
T22-ME011B
MOISTURE ELEMENT
T22-ME011C
MOISTURE ELEMENT
T22-ME012B
MOISTURE ELEMENT
T22-ME012C
MOISTURE ELEMENT
T22-MT011B
MOISTURE TRANSMITTER
T22-MT011C
MOISTURE TRANSMITTER
T22-MT012B
MOISTURE TRANSMITTER
T22-MT012C
MOISTURE TRANSMITTER
T22-POE001B
POSITION ELEMENT
T22-POE001C
POSITION ELEMENT
T22-TE002B
TEMP ELEMENT
T22-TE002C
TEMP ELEMENT
T22-TE010B
TEMP ELEMENT
T22-TE010C
TEMP ELEMENT
T22-TE013B
TEMP ELEMENT
T22-TE013C
TEMP ELEMENT
T22-TE014B
TEMP ELEMENT
T22-TE014C
TEMP ELEMENT
T22-TE016B
TEMP ELEMENT
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
T22-TE016C
TEMP ELEMENT
T22-TS005B
TEMP SWITCH
T22-TS005C
TEMP SWITCH
T22-TS009B
TEMP SWITCH
T22-TS009C
TEMP SWITCH
T22-TS013B
TEMP SWITCH
T22-TS013C
TEMP SWITCH
T22-TS015B
TEMP ELEMENT
T22-TS015C
TEMP ELEMENT
T31-F001
AO VALVE
T31-F002
AO VALVE
T31-F003
AO VALVE
T31-F004
AO VALVE
T31-F005
AO VALVE
T31-F006
AO VALVE
T31-F007
AO VALVE
T31-F008
AO VALVE
T31-F009
AO VALVE
T31-F010
AO VALVE
T31-F011
AO VALVE
T31-F025
AO VALVE
T31-F039
AO VALVE
T31-F040
AO VALVE
T31-F041
AO VALVE
T31-F044A-H
POSITION SWITCH
T31-F044A-H
POSITION SWITCH
T31-F731
SO VALVE
T31-F733A
SO VALVE
T31-F733B
SO VALVE
T31-F735A
SO VALVE
T31-F735B
SO VALVE
T31-F735C
SO VALVE
T31-F735D
SO VALVE
T31-F737A
SO VALVE
T31-F737B
SO VALVE
T31-F739A
SO VALVE
7A-55
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-56
Device
Div
Description
T31-F739B
SO VALVE
T31-F739C
SO VALVE
T31-F739D
SO VALVE
T31-F741A
SO VALVE
T31-F741B
SO VALVE
T31-F741C
SO VALVE
T31-F741D
SO VALVE
T31-F743A
SO VALVE
T31-F743B
SO VALVE
T31-F745A
SO VALVE
T31-F745B
SO VALVE
T31-F801A
SO VALVE
T31-F801B
SO VALVE
T31-F803A
SO VALVE
T31-F803B
SO VALVE
T31-F805A
SO VALVE
T31-F805B
SO VALVE
T31-LT058A
LEVEL TRANSMITTER
T31-LT058B
LEVEL TRANSMITTER
T31-LT058C
LEVEL TRANSMITTER
T31-LT058D
LEVEL TRANSMITTER
T31-LT059A
LEVEL TRANSMITTER
T31-LT059B
LEVEL TRANSMITTER
T31-LT100A
LEVEL TRANSMITTER
T31-LT100B
LEVEL TRANSMITTER
T49-C001B
BLOWER
T49-C001C
BLOWER
T49-D002B
HEATER
T49-D002C
HEATER
T49-F001B
MO GATE VALVE
T49-F001C
MO GATE VALVE
T49-F002A
AO GATE VALVE
T49-F002A
AO GATE VALVE
T49-F002E
AO GATE VALVE
T49-F002E
AO GATE VALVE
T49-F003B
MO GLOBE VALVE
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
T49-F003C
MO GLOBE VALVE
T49-F004B
MO GLOBE VALVE
T49-F004C
MO GLOBE VALVE
T49-F006A
AO GATE VALVE
T49-F006A
AO GATE VALVE
T49-F006E
AO GATE VALVE
T49-F006E
AO GATE VALVE
T49-F007B
MO GATE VALVE
T49-F007C
MO GATE VALVE
T49-F008B
MO GATE VALVE
T49-F008C
MO GATE VALVE
T49-F009B
T49-F009C
T49-F010B
MO GLOBE VALVE
T49-F010C
MO GLOBE VALVE
T49-F013B
T49-F013C
T49-F014B
T49-F014C
T49-FT002B
FLOW TRANSMITTER
T49-FT002C
FLOW TRANSMITTER
T49-FT004B
FLOW TRANSMITTER
T49-FT004C
FLOW TRANSMITTER
T49-PT003B
PRESS TRANSMITTER
T49-PT003C
PRESS TRANSMITTER
T49-TE001B
TEMP ELEMENT
T49-TE001C
TEMP ELEMENT
T49-TE005B
TEMP ELEMENT
T49-TE005C
TEMP ELEMENT
T49-TE006B-1
TEMP ELEMENT
T49-TE006C-1
TEMP ELEMENT
T49-TE007B-1
TEMP ELEMENT
T49-TE007C-1
TEMP ELEMENT
T49-TE008B-1
TEMP ELEMENT
T49-TE008C-1
TEMP ELEMENT
T49-TE009B-1
TEMP ELEMENT
7A-57
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-58
Device
Div
Description
T49-TE009C-1
TEMP ELEMENT
T49-TE010B-1
TEMP ELEMENT
T49-TE010C-1
TEMP ELEMENT
T49-TE011B-1
TEMP ELEMENT
T49-TE011C-1
TEMP ELEMENT
T53-TE001A
TEMPERATURE ELEMENT
T53-TE001C
TEMPERATURE ELEMENT
T53-TE001E
TEMPERATURE ELEMENT
T53-TE001G
TEMPERATURE ELEMENT
T53-TE001J
TEMPERATURE ELEMENT
T53-TE001L
TEMPERATURE ELEMENT
T53-TE001N
TEMPERATURE ELEMENT
T53-TE001R
TEMPERATURE ELEMENT
T53-TE002B
TEMPERATURE ELEMENT
T53-TE002D
TEMPERATURE ELEMENT
T53-TE002F
TEMPERATURE ELEMENT
T53-TE002H
TEMPERATURE ELEMENT
T53-TE002K
TEMPERATURE ELEMENT
T53-TE002M
TEMPERATURE ELEMENT
T53-TE002P
TEMPERATURE ELEMENT
T53-TE002S
TEMPERATURE ELEMENT
T53-TE003B
TEMPERATURE ELEMENT
T53-TE003D
TEMPERATURE ELEMENT
T53-TE003F
TEMPERATURE ELEMENT
T53-TE003H
TEMPERATURE ELEMENT
T53-TE003K
TEMPERATURE ELEMENT
T53-TE003M
TEMPERATURE ELEMENT
T53-TE003P
TEMPERATURE ELEMENT
T53-TE003S
TEMPERATURE ELEMENT
T53-TE004A
TEMPERATURE ELEMENT
T53-TE004C
TEMPERATURE ELEMENT
T53-TE004E
TEMPERATURE ELEMENT
T53-TE004G
TEMPERATURE ELEMENT
T53-TE004J
TEMPERATURE ELEMENT
T53-TE004L
TEMPERATURE ELEMENT
T53-TE004N
TEMPERATURE ELEMENT
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
T53-TE004R
TEMPERATURE ELEMENT
T53-TE005A
TEMPERATURE ELEMENT
T53-TE005C
TEMPERATURE ELEMENT
T53-TE005E
TEMPERATURE ELEMENT
T53-TE005G
TEMPERATURE ELEMENT
T53-TE005J
TEMPERATURE ELEMENT
T53-TE005L
TEMPERATURE ELEMENT
T53-TE005N
TEMPERATURE ELEMENT
T53-TE005R
TEMPERATURE ELEMENT
T53-TE006B
TEMPERATURE ELEMENT
T53-TE006D
TEMPERATURE ELEMENT
T53-TE006F
TEMPERATURE ELEMENT
T53-TE006H
TEMPERATURE ELEMENT
T53-TE006K
TEMPERATURE ELEMENT
T53-TE006M
TEMPERATURE ELEMENT
T53-TE006P
TEMPERATURE ELEMENT
T53-TE006S
TEMPERATURE ELEMENT
T53-TE007B
TEMPERATURE ELEMENT
T53-TE007D
TEMPERATURE ELEMENT
T53-TE007F
TEMPERATURE ELEMENT
T53-TE007H
TEMPERATURE ELEMENT
T53-TE007K
TEMPERATURE ELEMENT
T53-TE007M
TEMPERATURE ELEMENT
T53-TE007P
TEMPERATURE ELEMENT
T53-TE007S
TEMPERATURE ELEMENT
T53-TE008A
TEMPERATURE ELEMENT
T53-TE008C
TEMPERATURE ELEMENT
T53-TE008E
TEMPERATURE ELEMENT
T53-TE008G
TEMPERATURE ELEMENT
T53-TE008J
TEMPERATURE ELEMENT
T53-TE008L
TEMPERATURE ELEMENT
T53-TE008N
TEMPERATURE ELEMENT
T53-TE008R
TEMPERATURE ELEMENT
U41-C201A
U41-C201E
U41-C202A
7A-59
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
7A-60
Device
Div
Description
U41-C202E
U41-C203A
U41-C203E
U41-C204B
U41-C204F
U41-C205B
U41-C205F
U41-C206B
U41-C206F
U41-C207C
U41-C207G
U41-C208C
U41-C208G
U41-C209C
U41-C209G
U41-C601B
U41-C601F
U41-C602B
U41-C602F
U41-C603B
U41-C603F
U41-C604A
U41-C604E
U41-C605A
EM EQ EX FAN(A) ZONE(A)
U41-C605E
EM EQ EX FAN(B) ZONE(A)
U41-C606B
U41-C606F
U41-C607B
EM EQ EX FAN(A) ZONE(B)
U41-C607F
EM EQ EX FAN(B) ZONE(B)
U41-C608C
U41-C608G
U41-C609C
EM EQ EX FAN(A) ZONE(C)
U41-C609G
EM EQ EX FAN(B) ZONE(C)
U41-C621C
U41-C621G
U41-C622C
U41-C622G
Rev. 0
ABWR
Table 7A-1 List of Equipment Interface with Essential MUX Signals (Continued)
Device
Div
Description
U41-C623C
U41-C623G
U41-D101
U41-D102
U41-D103
U41-D104
U41-D105
U41-D106
U41-D107
U41-D108
U41-D109
U41-D110
U41-D111
U41-D112
U41-D113
U41-D114
U41-F001A
U41-F001B
U41-F002A
U41-F002B
U41-F003A
MO VALVE
U41-F003B
MO VALVE
U41-F003C
MO VALVE
U41-F004A
MO VALVE
U41-F004B
MO VALVE
U41-F004C
MO VALVE
U41-F005A
MO VALVE
U41-F005B
MO VALVE
U41-F005C
MO VALVE
U41-TE052
TEMP ELEMENT
U41-TE056
TEMP ELEMENT
U41-TE060
TEMP ELEMENT
U41-TE103B
TEMP ELEMENT
U41-TE103C
TEMP ELEMENT
7A-61
ABWR
7A-62
LOCAL AREA
CONTROL ROOM
TO SAFETY
SYSTEM
EQUIPMENT
ACTUATORS
REMOTE
MULTIPLEXING UNITS
RMU
Div. I
Essential
Multiplexing
System
(EMS)
Isolated trips
from DTMs in
other divisions
RPS / MSIV
DTM
see Note 7
TLU
SETPOINT
COMPARISON
RMU
TRIP OUTPUTS TO
PILOT VALVE SOLENOIDS
3/4
MANUAL
CONTROLS
RPS
LOAD
DRIVER
HI =
bypassed
4
LDS / ECCS
DTM
SETPOINT
COMPARISON
Pressure
Level
Flow
Temperature
Contact Closures
see Note 5
SLU
2/4 TRIP DECISION
1/N TRIP SELECTION
INTERLOCK LOGIC
SHARED
SENSORS
MANUAL
CONTROLS
RMU
Self-test
link
(typical)
TEST
STIMULI
ESF
ECCS trips
RCIC
RHR A
ADS A
LDS trips
RCIC
RHR A
CUW
PCV ISOL.
Hardwired
MSIV
LOAD
DRIVER
Bypass status
and interlocks
to and from
other divisions
FEEDBACK OF
TEST RESULTS
SURVEILLANCE TEST
UNIT FOR OFF-LINE
MAINTENANCE
Div. III
RPS
MANUAL
SCRAM
BYPASS
CONTROL
HI = bypassed
RMU
POWER
SOURCE
OLU
Isolated trips to
TLUs in other
divisions
Div. IV Div. I
Div. II
RPS / MSIV
trip I
bypass I
trip II
bypass II
trip III
bypass III
trip IV
bypass IV
trip I
bypass I
trip II
bypass II
trip III
bypass III
trip IV
bypass IV
2/4
Rev. 0
SSLC
EMS
Channel-of-sensors bypass
Division-out-of-service bypass
Glossary:
DTM
ESF
OLU
PMCS RMU
SLU
TLU
Notes:
1. THIS SIMPLIFIED DIAGRAM SHOWS THE BASIC
ARRANGEMENT OF THE ABWR SHARED SENSOR,
TIME-MULTIPLEXED, PLANT PROTECTION
SYSTEM, USING STORED-PROGRAM COMPUTERS
TO DETERMINE THE DECISION FOR SAFETY
ACTION.
2. Essential Multiplexing System , which is independent of
SSLC, is shown for REFERENCE ONLY and
represents one possible configuration. As an example,
a bi-directional, dual redundant ring is ilustrated.
This system can automatically reconfigure after a
node or cable failure to maintain availability of
remaining functions.
3. RMUs shown are typical; actual quantity of RMUs
and number of inputs and outputs per RMU will be
determined during detailed design stage.
4. DTM, SLU and TLU functions shown are performed
by microprocessors under software program control;
the exact number and location of these functions will
be determined during further detailed design. The
functions shown represent the minimum separation of
tasks between RPS and ESF to ensure independence
and high system availability.
5. To provide fault-tolerance, the LDS/ECCS SLU may
be made redundant (for example, dual with 2/2 voting
or triple with 2/3 voting) to prevent inadvertent ECCS
initiation.
6. RPS and MSIV outputs are shown hardwired to the
load drivers due to time constraints for trip action.
7. "3/4" coincidence trip is "fail-safe 2/4"; i.e., two or
more normally high inputs must trip low for the
normally high output to trip low. Three or more high
inputs maintain a high output.
Rev. 0
ABWR
PERFORMANCE
OBJECTIVES
APPLICABLE
CODES
INTERFACE
STANDARDS
REQUIREMENTS AND NUC REGS
CUSTOMER
REQUIREMENTS
ASSUMPTIONS
AND
CONSTRAINTS
REVIEW AND
DOCUMENTATION
FUNCTION
ALLOCATION
ALLOCATE FUNCTIONS/
TASK ANALYSIS
COMPONENT A
DESIGN
REVIEW
COMPONENT B
ESTABLISH
TEST AND
EVALUATION
CRITERIA
ESTABLISH
DEVELOP
PERSONNEL
OPERATING
PROCEDURES REQUIREMENTS
TECHNICIAN
INTERFACES
COMPONENT C
DEVELOP
TEST AND
EVALUATION
PROCEDURES
COMPONENT D
HARDWARE
DESIGN
DESIGN
REVIEW
COMPONENT F
SOFTWARE
DESIGN
DESIGN
REVIEW
DESIGN
REVIEW
STATIC REVIEW
PART TASK EVALUATIONS
COMPONENT E
INTEGRATED
HARDWARE/SOFTWARE
V&V ACTIVITY
USES ITERATIVE
IMPLEMENTATION
DYNAMIC REVIEW
FIELD
INSTALLATION AND
VALIDATION TESTS
SYSTEM OPERATIONAL
7A-63 /64
Rev. 1
ABWR
the organization and responsibilities for development of the software design; the
procedures to be used in the software development; the interrelationships between
software design activities; and the methods for conducting software safety
analyses.
Within the defined scope and content of the Software Management Plan, accepted
methods and procedures for the above activities are presented in the following
documents:
(i)
[IEEE 730, Standard for Software Quality Assurance Plans, Section 3.4;
(ii)
(vi) IEEE 1012, Standard for Software Verification and Validation Plans,
Section 3.5;
(vii) IEEE 830, Guide to Software Requirements Specifications, Section 5;
(viii) IEEE 1042, Guide to Software Configuration Management.]*
Note that within the set of documents listed above, differences may exist regarding
specific methods and criteria applicable to the Software Management Plan. In
situations where such differences exist, all of the methods and criteria presented
within those documents are considered to be equally appropriate and valid and,
therefore, any of the above listed documents may be selected as the basis for elements
of the SMP.
Thi d
t d ith F
7B-1
M k
403
Rev. 0
ABWR
(b)
(ii)
identify in the coding and test of the developed software, those software
modules which are safety-critical;
(v)
(vi)
Planning
(ii)
Design Definition
Software Coding
(v)
Integration
(vi)
Validation
the Planning phase design activities, which shall address the following system
design requirements and software development plans:
(i)
(ii)
7B-2
(iv)
(v)
(vi)
Rev. 0
ABWR
(e)
the Design Definition phase design activities, which shall address the development
of the following implementing equipment design and configuration requirements:
(i)
equipment schematic;
(ii)
(f)
(iv)
(v)
(vi)
the Software Design phase, which shall address the design of the software
architecture and program structure elements, and the definition of software
module functions:
(i)
(ii)
the Software Coding phase, which shall address the following software coding and
testing activities of individual software modules:
(i)
(ii)
the Integration phase, which shall address the following equipment testing
activities that evaluates the performance of the software when installed in
hardware prototypical of that defined in the Design Definition phase:
(i)
(ii)
7B-3
Rev. 1
ABWR
(i)
the Validation phase, which comprises the development and implementation of the
following documented test plans and procedures:
(i)
(ii)
(j)
(iv)
(v)
(vi)
the Change Control phase, which begins with the completion of validation testing,
and addresses changes to previously validated software and the implementation of
the established software change control procedures.
(ii)
(v)
(vi)
designate and control software revision status. Such methods shall require
that software code listings present direct indication of the software code
revision status.
Within the defined scope and content of the Configuration Management Plan,
accepted methods and procedures for the above activities are presented in the
following documents:
(i)
(ii)
Rev. 1
ABWR
methods for, and the sequencing of, reviews to evaluate the compliance of software
design activities with the requirements of the CMP;
(c)
(d)
(e)
methods for tracking error rates during software development, such as the use of
software metrics;
(f)
(ii)
7B-5
Rev. 0
ABWR
(c)
that the use of commercial software and commercial development tools for safetyrelated applications is a controlled and documented procedure.
(d)
(e)
that for safety-related software, verification reviews and validation testing are to
be conducted by personnel who are knowledgeable in the technologies and methods
used in the design, but who did not develop the software design to be reviewed and
tested.
(f)
(g)
that validation testing shall be conducted per a documented test plan and
procedure.
(h)
(i)
the products which shall result from the baseline reviews conducted at each phase
of the software development life-cycle; and that the defined products of the baseline
Rev. 0
ABWR
reviews and the V&V Plan shall be documented and maintained under
configuration management.
(j)
(k)
that the software development is not complete until the specified verification and
validation activities are complete and design documentation is consistent with the
developed software.]*
7B-7/8
Rev. 0
ABWR
Thi d
t d ith F
M k
403
7C-1
Rev. 0
ABWR
Manual scram and isolation by the operator in the main control room in
response to diverse parameter indications.
(b)
Core makeup water capability from the diverse feedwater, CRD, and
condensate systems.
(c)
7C-2
(a)
(b)
(c)
Microprocessors with minimal instruction sets and a simple operating system are
used. The lost computing power is not needed and the limited instructions
minimize inadvertent programming and operational errors. This aids in
verification and validation and further enhances reliability.
(d)
The highest quality, high precision components are used to gain reliability.
Designs with these components minimize manual calibration, simplify reliability
analysis, and maximize surveillance intervals.
(e)
(f)
Rev. 0
ABWR
(h)
Modules have one entry and one exit point and are written using a limited
number of program constructs, as specified by [DOD-STD-2167]*
(i)
Program code for each safety system resides in independent modules which
perform setpoint comparison, voting, and interlock logic
(ii)
(iii) Fixed message formats are used for plant sensor data, equipment activation
data and diagnostic data. Thus, corrupted messages are readily detected by
error-detecting software in each digital instrument.
(j)
(k)
A full-scope operating system is not used. The operating system for each instrument
is a small, real-time kernel customized to perform only the required scheduling
functions
(l)
(m)
(n)
The most important factor, however, in implementing reliable software is the quality of
the design and requirements specifications. These documents are also controlled under
the formal V&V program.
7C-3
Rev. 0
ABWR
(b)
(c)
(d)
Simplifies verification
(ii)
A strong V&V program can reduce the probability of common mode failure to a very low level
because the simple modules used in each division, although identical in some cases, can be
thoroughly tested during the validation process. In addition to software V&V, however, SSLC
contains several system level and functional level defenses against common mode failure, as follows:
(1)
Operational defenses
(i)
(ii)
(b)
(iv)
(v)
Functional Defenses
(i)
(ii)
(iii) Separation and independence protect against global effects (EMI, thermal,
etc.)
7C-4
Rev. 0
ABWR
The functional program logic in the SSLC controllers also provides protection against common
mode failures, as follows:
(1)
Interlock logic for ESF pumps and valves varies in each division
(ii)
Each division has different quantities and types of inputs and outputs
(iii) Redundant sensors have data messages with unique identifications and
time-tags in each division
(b)
Modules that are identical are simple functions such as setpoint comparison and
2-out-of-4 voting that can be readily verified
(c)
Multiplexing and other data transmission functions use standard, open protocols
that are verified to industry standards and are also qualified to Class 1E
standards
Due to this extensive diversity that exists at the protection system and plant levels, the use of
hardware and software diversity among the redundant channels of the protection system was not
considered practical for the following reasons:
(1)
Diverse software is more error prone during development and does not guarantee that the
resulting system will be error-free
(2)
Diverse hardware and software increases V&V and system integration costs
(3)
(4)
Maintenance and surveillance require more time and attention because the diverse
equipment may perform differently
(5)
System revision costs are prohibitive because of additional V&V and documentation
(6)
7C-5
Rev. 0
ABWR
therefore, did not need to be considered further in the licensing process [see reference
7C-6(1)]. These analyses considered the defined SSLC configuration (e.g., 2-out-of-4
safety system logic and segmentation of functions performed with the multiple
microprocessors of a safety division), system functions (e.g., automated self-test), and
qualification of the equipment to the applicable standards (e.g., hardware qualification
and software verification and validation (V&V).
During this initial period of ABWR design certification activities, the NRC staff was
striving internally to define the methods that they should use to review and evaluate the
acceptability of broad scope digital-based safety systems such as those which are
incorporated into the ABWR design. Although the staff had some experience in
reviewing and licensing individual systems and components that used advanced digital
technologies (e.g., GEs NUMAC family of products), they had no experience in the
review of broad scope integrated digital systems such as the SSLC design. In addition,
the staffs past practice for the review of digital-based equipment was to review the actual
implemented equipment hardware and software. For the ABWR design certification,
the scope of their review specifically excluded the review of any particular
implementation of equipment and, as a consequence, the NRC staff had no precedents
to guide them in their review of ABWR licensing submittals regarding digital safety
systems.
With the issuance of NRC paper SECY 91-292 (September 16, 1991), the staff indicated
that they would require some type of I&C diversity in those plants that chose to
implement broad scope digital systems in safety-related applications. The formal
rationale presented by the staff indicated that the incorporation of such I&C diversity
would provide additional defense-in-depth and that such an approach was already
being taken in other countries (e.g., France).
OCTOBER, 1991
The NRC staff contracted with Lawrence Livermore National Laboratory (LLNL) to
perform a worst-case common-mode failure (CMF) analysis of ABWR digital safety
systems. LLNL defined worst-case to be an undetected, simultaneous, 4-division
failure such that all safety actions are inhibited at the time that these actions are
required by the coincident occurrence of a design basis event (accident or transient).
The methodology to be used would be based on NUREG-0493 (1979).
MARCH, 1992
LLNL provided their first results to the NRC in March of 1992. Based upon the LLNL
work, the staff formulated a position which included the requirement that a set of
safety grade displays and manual controls, independent of the computer system(s) and
located in the main control room, shall be provided for system-level actuation and
monitoring of critical safety function parameters... and that the displays and manual
7C-6
Rev. 0
ABWR
The analyses presented in Chapter 15 of Tier 2 would be re-done with the modeling
assumption that a worst-case postulated CMF of the digital safety systems would be
considered concurrently with each of the individual design basis events.
The analyses could take credit for non-safety controls and instrumentation if that
equipment was independent of the postulated CMF in the digital safety systems.
The analyses could take credit for operator actions at the RSS after one hour, but
prior to that one hour period, all operator actions would be limited to those which
could be performed in the main control room, using equipment that was
independent of the postulated CMF.
JUNE, 1992
GE completed the evaluations and provided the results to the NRC staff. The
evaluations took credit for the control room operation of the feedwater system and CRD
hydraulic system to maintain RPV water level, and the use of a small set of hardwired
displays and controls in the main control room for the purpose of the scram and
containment isolation functions, which need to be accomplished in a relatively short
time (i.e., at least within the first hour of the postulated event scenarios considered). To
demonstrate that at least one hour of operation from only the control room was
achievable, three of the most limiting scenarios were evaluated in detail, and the
analyses were terminated after two hours of the scenario had been evaluated. The
results of those evaluations (which were performed using the SAFR computer code)
showed that even in the case where all operator actions are confined to just the control
Defense Against Common-Mode Failure in Safety-Related, Software-Based I&C Systems
7C-7
Rev. 0
ABWR
room, the fuel peak clad temperature (PCT) could be maintained at less than 1204 C
such that no additional hardwired functions beyond the small set considered in the
analyses were needed. That small set of hardwired control and display functions was
as follows:
CONTROLS
CUW line inboard isolation valve manual initiation (for CUW LOCA outside the
primary containment)
RCIC steamline inboard isolation valve manual initiation (for RCIC steam line
break outside the primary containment)
DISPLAYS
Drywell pressure
MSIV status
Also in June of 1992, top GENE management met with the NRC commissioners and
presented GEs position that the ABWR design already included adequate diversity and
that the NRC staffs approach to requiring significant hardwired functions in the main
control room was not technically justified.
SEPTEMBER, 1992
In a letter to the chairman of the NRC [see reference 7C-6(3)], the Advisory Committee
on Reactor Safeguards (ACRS) rejected the NRC staffs position regarding the
requirement for hardwired backup for the digital safety systems in the main control
room (MCR). The ACRS position, which was consistent with the position that had been
taken by GE and others in the nuclear industry, was that there are many potentially
acceptable methods of implementing diversity that could be used to mitigate postulated
7C-8
Rev. 0
ABWR
CMF of digital safety systems, and, thus, the NRC staff position which specifically
required hardwired functions in the MCR was not technically justified.
OCTOBER, 1992
The staff modified its position on hardwired functions [see reference 7C-6(4)] and
acknowledged that other methods (including diverse digital equipment) could be used
to satisfy their requirement for mitigating postulated CMF of digital safety systems.
DECEMBER, 1992
The staff released the draft Final Safety Evaluation Report (FSER) on the ABWR. In that
document, the staff presented their new list of diverse MCR displays and controls
required for the ABWR. That list was essentially the same as the list developed by GE
(see above) with one exception: The staff still required diverse HPCF manual initiation
and flow indication in the MCR. In addition, the staff required that the feedwater system
(FWS) be designed and tested to demonstrate high reliability. The rationale that the
staff presented for requiring these additional diverse functions and capabilities was that,
although the analyses submitted by GE in June 1992 had frequently taken credit for the
operation of the FWS, the staff felt uncomfortable with placing such reliance on that
system because past experience with single channel analog feedwater control system
performance in U.S. plants had not been good.
JANUARY, 1993
In a meeting with the NRC staff, GE discussed the staff position presented in their draft
FSER. GE argued that since the ABWR had incorporated a triplicated fault-tolerant
architecture for the feedwater control system (FWCS), the reliability of feedwater
control was significantly improved over past single-channel analog systems. The staff
countered that, if GE was going to take credit for the feedwater system in the I&C
common-mode failure analyses, they would then require that the FWCS be essentially
designed and tested as though it were a safety-related system. In addition, the staff would
still require that at least one division of HPCF manual initiation be provided in the MCR
as redundant backup to the feedwater system.
During the January 1993 discussions, GE provided the staff with the results of new
analyses that had been performed with the additional modeling assumption that the
FWCS was assumed to have failed concurrent with the postulated initiating design basis
event and the postulated worst-case CMF of the digital safety systems. In those analyses,
only the operation of the CRD hydraulic system and the condensate system from the
MCR were considered for the first two hours of the event. The results were still less than
the 1204C PCT limit. These analyses were used to demonstrate that even if the FWCS
was assumed to have failed, there would still be adequate capability in the MCR (without
hardwired manual HPCF initiation) to support operator actions to maintain the reactor
Defense Against Common-Mode Failure in Safety-Related, Software-Based I&C Systems
7C-9
Rev. 0
ABWR
in a safe condition and provide sufficient time for an operator to move to the remote
shutdown system to initiate core make-up systems from that location. The staff accepted
these arguments and agreed that the requirements they had proposed regarding FWCS
reliability and HPCF manual initiation capability could be deleted. However, the staff
requested that three additional design basis events be evaluated using the same type of
modeling assumptions, including the postulated concurrent failure of the FWCS.
Together with the previous analyses, these additional evaluations would comprise a
bounding set of Chapter 15 events regarding the consequences of common mode
failure on the digital protection system.
FEBRUARY, 1993
GE submitted to the staff the results of the three additional analyses [see reference 7C6(5)]. All results were again less than the defined 1204C PCT limit.
MARCH, 1993
The staff contacted GE to discuss some questions they had regarding the analyses
previously provided by GE. The analyses included consideration of actions that would
be taken by the operators in the MCR during the postulated events. These operator
actions were defined based upon the ABWR Emergency Procedure Guidelines; the
timing of these assumed operator actions was supported by operator performance test
data from training simulators. The question raised by the Human Factors Branch of the
NRC staff was basically: How sensitive are the results of the GE analyses to the timing
of the assumed operator actions? More specifically, as an example, GEs analyses
modeled that the operator would initiate condensate system operation within 5 minutes
after the RPV water level dropped below level 2. The NRC staffs question was: After
how much longer would the analysis results still be acceptable? GE agreed to reperform the three most limiting analyses with the objective of trying to determine how
long the operator could wait to take his first action. With the time margin for operator
action quantified, and assuming this margin was sufficient, the staff agreed that the issue
of I&C diversity would finally be closed with GEs incorporation of the small set of MCR
displays and controls presented above.
These final analyses were performed using the TRAC computer code. TRAC was used
instead of the SAFR code employed in the previous analyses because the additional
modeling assumption of a delayed operator action time causes a longer period of
operation with a depressed RPV water level; the TRAC code was considered to do a
better job of modeling these conditions. Note that the SAFR code is an approved Level
2 code for the performance of Design Basis LOCA analyses in which the ECCS initiates
automatically and the period of core uncovery nominally lasts no longer than about 100
seconds. However, in these special analyses, the period of core uncovery would last for
1000 seconds or more and, therefore, were beyond the scope of the existing SAFR code
7C-10
Rev. 0
ABWR
qualification. During the conduct of these evaluations using the TRAC code, it was
determined that the previous analytical results obtained with the SAFR code were not
correct and were non-conservative. Upon realization that the previous results were
invalid, the entire set of six events previously analyzed in June 1992 were re-analyzed.
The results of these TRAC analyses showed that the CRD hydraulic system and
condensate system alone were not adequate to maintain the core within the 1204 C
limit under the conditions postulated in those analyses. In order to maintain the core
within the 1204C limit for these postulated event scenarios, it was necessary to take
credit for operation of one division of HPCF [see reference 7C-6(6)].
MAY, 1993
GE advised the staff that manual control of HPCF Loop C (Division III) and the display
of HPCF Loop C flow would be added to the list presented above of hardwired displays
and controls provided in the MCR. (Manual control of HPCF Loop B (Division II), with
local display, is already provided at the RSS.)
JUNE, 1993
As of the week of June 7, 1993, the staff indicated that, with the addition of the
hardwired HPCF manual control in the MCR, the issue of I&C diversity would be closed,
pending the staffs final review of the results of the analyses that were re-done to
incorporate manual HPCF initiation. Within the U.S. licensing material, manual HPCF
Loop C initiation will be presented as a manual switch hardwired to a programmable
logic controller (PLC) device that is independent of Safety System Logic and Control
(SSLC) and the Essential Multiplexing System (EMS). SSLC and EMS will continue to
provide the automatic software-based initiation logic for HPCF Loop C [see reference
7C-6(7)].
The SSLC design also uses hardwired control switches to perform manual system start
of the other systems in ECCS. However, these switches are hardwired only from the
operators control station to the microprocessor logic in SSLC, where EMS then
provides the transmission path for control signals from SSLC to the actuated devices.
Control switch signals for individual control of pumps and valves are multiplexed from
the operators control station to SSLC and then through EMS as stated above.
JULY, 1993
The final NRC staff position on I&C diversity is stated in NRC document SECY-93-087,
Section II.Q. This position has been approved by the NRC commissioners, with minor
changes, in item 18 of a staff requirements memorandum (SRM), dated July 15, 1993.
GEs design for safety-related I&C, as described in the above chronology and discussed
in detail in the following section, fully meets the staff requirements.
7C-11
Rev. 0
ABWR
(2)
(3)
(b)
(c)
(d)
(e)
ATWS mitigation [Alternate Rod Insertion (ARI) and FMCRD run-in, ADS
inhibit, automatic Standby Liquid Control System initiation and feedwater
runback] (hardwired and diverse digital system)
Defense-in-depth configuration:
(a)
(b)
Control systems are independent of RPS and ESF in separate triplicated processing
network using diverse hardware and software from the Essential Multiplexing
System network
Equipment diversity
(a)
7C-12
Output logic units use discrete gate logic and provide trip seal-in and reset,
division bypass, and manual trip functions
Rev. 0
ABWR
(b)
The operator is provided with a set of diverse displays separate from those supplied
through the safety-related, software-based logic. The displays listed below provide
independent confirmation of the status of major process parameters:
(i)
(ii)
(v)
(vi)
(d)
CUW line inboard isolation valve manual initiation (for CUW LOCA
outside the primary containment)
(ii)
RCIC steam line inboard isolation valve manual initiation (for RCIC
steam line break outside the primary containment)
(ii)
(iii) Manual open/close valve control of condensate storage pool suction valve
F001
(iv)
(2)
(3)
7C-13
Rev. 0
ABWR
(4)
(v)
If the protection system is disabled because of common mode failure, the operator is expected to enter
the emergency operating procedures at the appropriate points as determined by the indications on
the hardwired backup displays and manipulate the control functions described above.
Additional diversity is available at the plant level even if SSLC is disabled because of common mode
failure. The same common mode failure would not be expected to affect the feedwater control system,
which, although not safety-related, is operated by a highly reliable, triplicated fault-tolerant control
system that is diverse in both hardware and software from the safety systems. Similarly, makeup
water is also available from CRD purge flow and condensate pumps. These additional sources of
water will generally mitigate all Chapter 15 events, as discussed in the analyses described in section
7C.4 above; however, a channel of manually-initiated HPCF, as shown in item (4) above, has been
added to meet worst-case conditions.]*
7C.6 References
(1)
(2)
(3)
(4)
(5)
(6)
(7)
ABWR
DIV. I
DIV. II
SENSORS
SENSORS
DIV. III
LT
PT
003
025
RMU
RMU
RMU
RMU
CMU
DTM
ANN, PMCS
PT
FT
025
009
C
RMU
RMU
RMU
CMU
DTM
ANN, PMCS
DIV. IV
LT
003
RMU
SENSORS
SENSORS
RMU
RPV
LEVEL
LI
DTM
ANN, PMCS
RMU
RPV
LEVEL
LI
603
DRYWELL
PRESSURE
PI
G
DRYWELL
PRESSURE
625
625
RMU
RMU
CMU
F
PI
025
H
CMU
603
PT
LT
003
B
FI
ANN, PMCS
DTM
LI
RPV
LEVEL
603
PI
H
DRYWELL
PRESSURE
625
D
HPCF C
FLOW
609
C
Bypass
Bypass
Bypass
SLU X 2
SLU X 2
2/4
ANN, PMCS
CMU
ANN, PMCS
Manual
Controls
CMU
RMU
SLU X 2
2/4
Manual
Controls
RMU
RMU
To Actuating Devices:
- Motor Control Centers
- Switchgear
- Solenoids
- Contactors
HPCF C
Manual
Start
Interlocks
HPCF C
Logic
2/2
Manual
Isolate
CUW Inboard
Containment
Isolation Valve
MO-F002
R G hardwired
HPCF C
Start
HPCF C
Backup
Start
To Actuating Devices:
- Motor Control Centers
- Switchgear
Start pump C001C
- Solenoids
Open injection valve F003C
- Contactors
Close test return valve F008C
Close test bypass valve F009C
Auto open CSP valve F001C
Start diesel generator C
7C-15 /16
FIGURE 7C 1 IMPLEMENTATION OF ADDITIONAL DIVERSITY IN SSLC TO MITIGATE EFFECTS OF COMMON MODE FAILURES
Figure 7C-1 Implementation of Additional Diversity in SSLC to Mitigate Effects of Common-Mode Failures
To Actuating Devices:
- Motor Control Centers
- Switchgear
RCIC
- Solenoids
Steam Supply Line
- Contactors
Inboard Isolation Valve
MO-F035
R G hardwired
AutoIsolate
HPCF C
Reset
RMU
AutoBypass
2/2
Manual
Isolate
PBS
CMU
AutoBypass
2/2
PBS
CMU
RMU
AutoBypass
AutoIsolate
2/4
Manual
Controls
ANN, PMCS
CMU
RMU
Rev. 0