MS For Grounding and Cadwelding Work
MS For Grounding and Cadwelding Work
MS For Grounding and Cadwelding Work
Vietnam
08.Feb.2011
V.H.PHONG J.Y.JEONG
K.J.LIM
Revised incorporating the comment made by Owner via "Unifier System" on SB1053 dated 23.Jan.12
26.Dec.2011
V.H.PHONG J.Y.JEONG
K.J.LIM
For Information
Rev.
Date
Drawn
Checked
Approved
Details of Revision
Owner :
Contractor :
Project :
PC
Title :
T10206
UAS :
DD09
Unit :
PO
KKS :
BAU
Drawing No. :
T10206-DD09-POBAU__-14001
Page-No :
1
1 of 34
AES-VCM
INDEX
SI NO.
DESCRIPTION
PAGE NO.
1.0
PURPOSE
2.0
SCOPE
3.0
REFERENCE DOUCMENTS
4.0
5.0
RESPONSIBILITIS
6.0
7.0
8.0
QUALITY INSPECTION
13
9.0
EXHIBITS
13
10.0
14
11.0
15~16
12.0
Attachment
17~34
4~10
11~12
1. Storage Procedure
2. Exothermic Welding system
3. Material safety data sheet
Page 2
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
PURPOSE
1.0
The purpose of this Method Statement is to describe the methodology involved in excavation, installing earthing material
and backfilling works and to details out the steps to be taken in meeting the technical standards and EHS requirements of
Mong Duong II Coal Fired Power Plant.
2.0
SCOPE
The purpose of this method statement is to provide the minimum requirements for the
installation of
above ground Earthing and cad welding. This method statement defines the methods
and processes to be adopted in ensuring that activities regarding the work activities are
done in convenience and accordance to specification.
This documents also describes details of EHS Requirements, Equipments and Methodology Requirements
3.0
Reference Doucments
A. Issued For Construction Drawings
B. Approved Contract Quality Plan
C. Project EHSS Management Plan
4.0
.
.
.
.
.
.
Equipment and Tools to be used for Installation and Erection of Grounding (Earthing) and Cad Welding System.
prior to using any machineries / equipment at site ,it will be inspected and certified by qualified person.
periodic preventive Maintenance will by made on all equipment and machineries.
all operators and drivers are to be equipped with valid drivers license/operators license or permit from
concerned government agency.
only authorized drivers and operators are allowed to operate equipment and machinery
only authorized signalman will be assigned together with the driver or operator.
all lifting equipments as well as its accessories such as sling wire, nylon sling, shackles,
chain blocks crane hook and latch shall be inspected periodically.
- Truck 11ton
- Truck 1ton
- Forklift 7ton
- Welding Machine
Page 3
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
5.0
Responsibilities
.
.
.
.
.
.
6.0
It is overall responsibility of Project Manager to organize resources prior to perform construction activities
as per project specification in compliance with the quality, schedule and safety Requirement.
EHS Manager will ensure incoordination with Site Engineer that all measure/construction
taken shall be maintained till completion of job.
It is the responsibility of Construction Manager/Site Engineer that construction activites are executed
According to the relevant project specification in compliance with the quality, schedule and safety requirements.
Doosan will ensure that all works are performed safely according to the attachment.
The relevant Doosan supervisor will ensure that the work is carried out in accordance with this method
Statement and project specification.
The QC inspector will ensure that the work is executed according the requirements
of quality dossier are fulfilled.
Page 4
AES-VCM
6.5
6.6
Emergency Procedures
Sub-Contractor shall follow clients emergency procedure during the period of work and shall ensure that its staff
and personnel are fully familiar with the use and location of the essential emergency equipment such as BA, Fire
Extinguishers, fire exits, muster points and plant alarms.
- Actions In The Event of Plant Emergency.
1) General and Evacuation alarm.
2) All works must stop and switch off all welding machines and compressor.
3) All personnel must proceed to safe location upwind or across wind to muster stations
4) Use of breathing apparatus if necessary.
5) Sub-Contractor personnel who detected a fire , toxic, flammable or asphyxiating gas leak must initially ensure their own
safety and report immediately to key personnel about the incident.
6) Direct person to person or by messenger by proving pertinent information to the Fire Station.
(location, problem, name and staff position).
6.7
First Aid
1) Sub-Contractor shall use first aid provided by Doosan in the project site.
2) Horseplay is Fools Play :
- There have been some incidents or horseplay on the process plant and the people
involved have been pulled up and warned about their future conduct
- A process plant is not a place for this kind of childish behaviour and can have devastating consequences.
- All employees must ensure that their ACTS and OMISSIONS do not endanger any other person working on site.
They are also responsible for their own safety and must co-operate with the employer and SAFETY at all times.
- Sub-Contractor require that all personnel report UNSAFE ACTS and CONDITIONS. They are also expected to
suggest methods to improve the workplace.
Page 5
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
3)
Safety Awareness :
The underlying cause accidents, injuries and incidents is invariably a lack of Safety Awareness linked with
unsafe behaviour.
Safety awareness is;
Being alert to what you are doing and what is going on around you.
Identifying potential hazards and taking the appropriate precautions to minimise and eradicate the risk.
Something everyone has to learn if he or she is to stay injury free
Part of every employees job, Everyone should carry out a Self Assessment and use Total Observation to;
Think about how you have done similar jobs in the past.
Think about how you are doing or planning to do the job now.
Compare the two operations with how the job should be done safely.
Look at everything that is taking place around you and anything that could pose a hazard to you.
Look above, below, behind and inside. Use the questioning Attitude to ask.
Have any people been injured doing this particular job ?
What injuries could occur if the unexpected happens ?
On, what I am doing will it affect other people ?
Do I have the authority, have I been trained, am I capable of doing the job ?
Do I need to wear or am I wearing the correct Personnel Protective Equipment ?
Eye Injuries :
- There have been a few entries in the accident books that relate to injuries to the eyes.
- Most of these injuries could have been avoided if the operatives had been wearing
goggles as proposed to safety glasses
- With immediate effect, Sub-Contractor Management insists that all personnel working inside the Process Plant wear
Safety Goggles /Glass at all times.
- If the housekeeping at the worksite is poor or if there is a long standing dust hazard
operatives are encouraged to report the matter to their supervisor.
6.8
- Head Projection,
The Process Plant is a designated Hard Hat site so safety helmets must be worn in all
the plant area. You must change your helmet if it is damaged in any way.
- Body Protection.
Protective clothing that is the right size, suitable for the job and properly maintained
must be worn all time at the Process Plant. Overalls must be made from 100% cotton.
- Safety Footwear
Safety Footwear must be worn at all times in all plant areas. The most common type of safety footwear is the safety
boot or shoe. It is recommended that they are fitted with at least a 200 joule toe-cap.
Page 6
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
- Hearing Protection
Adequate hearing protection must be worn at all times in the designated high noise areas.
Audits are finding lots of people not wearing ear defends in the high noise areas. There are two types of ear defenders
available for use i.e muffs fitted to the helmet and ear plugs which fit inside the ear canal.
- Hand Protection
Personnel working on site are likely to be expose to a number of hazards i.e. thermal, mechanical, chemical and vibration.
Where there is a risk of contact with one or more of these hazards then the appropriate protective gloves must be worn.
- Good Housekeeping.
Poor housekeeping and untidy working is a MAJOR source of accidents and injuries.
Sub-contractor is expected to clean up and debris created and after every job. Stop work and tidy up if the work area
is becoming cluttered and ensure that you take time out at the end of every work period to do some housekeeping.
Persistent untidy workers cannot be tolerated.
Housekeeping audits are being conducted on a daily basis by both Sub-contractor and CLIENT management
and the auditors will be looking at the following area.
- Hose and cable discipline i.e. trailing hoses and cables that do not restrict access egress, passage ways or roadways.
- Oil and process spill. Any liquid should be contained in dams or soaked up with proprietary absorbent materials such
as Spillsorb or soak-up before disposal in the approved manner. Solids and dusts should be either dampened
down or vacuumed up as soon as possible.
- Insulation and scaffolding debris. This material should be removed as soon as possible and disposed of in the approved
area.
- Engineering and General Debris. To be removed as soon as possible and disposed of the approved area, meanwhile, it
must be stored in a tidy manner.
- Elevated platforms, stairways, and access ways free from debris and/or obstruction. Tools and equipment must be positioned
so that they cannot be fall onto people working below.
Page 7
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
Sub - Contractor
First Finder
Site Manager
Sub-contrator
Project Manager
Doosan
site Manager
AES-VCM
Safety Manager
Police Station
Sub - Contractor
Safety Manager
Doosan
Sub-contrator
Admin Manager
Labour Office
Safety Manager
AES-VCM
Social Security
Safety
Hospital
Page 8
Fire Dept,
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
Risk Assessment
A. Survey
1. Survey Instrument
Type of
Damage
Injury
BASE RISK
(without
controls)
L
Risk
Mitigating Control
RESIDUAL RISK
(with controls)
L
Risk
B. Erection Work
1. Preparation
2. Installation
Injury
Injury
Injury
Injury
Injury
Injury
Breaking
Injury
Burn
3. Welding
Injury
Burn
Note:
Burn
Burn
L (Low)
5 : Almost Certain
4 : Likely
3 : Probable
2 : Occational
1 : Unlikely
S (Serious)
4 : High
3 : Moderate
2 : Low
1 : Very Low
Risk
S : 10~15
M : 6~9
T : 3~5
A : 1~2
Page 9
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing hazards.
solutions that control, minimize or eliminating)
Task : Grounding Work(Electric Work)
Prepared by :
Reviewed by :
Approved by :
Original Dated :
Revised by:
Revision Date :
Revision : A
Goggles
Gloves
Face
Barricade
Lock out No
Needed YES
Tack out No
YES
Safety
YES
Long
Harness
YES
Shield
YES
Hearing
Sleeves
YES
Ground Fault
Protection
YES
Interrupter
Others:
B. Erection Work
1. Preparation
2. Installation
injure hand.
2.6 Underground live cables
3. Welding
3.2 Spark
Page 10
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
7.0
1.2 m
GL
1m
1.1 m
Earthing wire
1m
Excavation work for earthing wire
Page 11
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
3m
GL
1.1m
2m
3m
2m
7.4 Cad Welding Work
1) Qualified Cadwelder resume should be submitted to Onwer for review
2) Cadweld work process should be strictly followed the manufacture's instruction (Welding manual). Please see attachment.
3) In addition to project safety requirement, more safety precaution should be provided depend on the location and the
nature of the job, such as
- Fire bucket/extinguisher (if working near flammable materials)
- Heat resistant board.
4) Sample Cadweld should be done and tested by qualified welder and should be approved by Onwer's team
5) Cadweld material should not mix with different material.
6) The inspection must be carried out before backfilling the soil.
7) Test instrument should have valid calibration date prior to use
Instrument test certificate shouldbe enclosed with the report.
Page 12
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
8.0
Quality Inspection
The Site Inspection and Test plan (ITP) for this work summarizes various characteristics to be checked. the concerned
Site Engineer/Foreman will be responsible to ensure stage wise compliance for these operation and the Site QA/QC
Engineer/Inspector will carry-out quality control checks and report the inspection results
9.0
Exhibits
Exhibit A-INSPECTION & TEST REPORT FOR GROUND SYSTEM
(See sample Next Page)
Page 13
AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS
10.0
Installation
(4) Direct Worker (Incharge Foreman)
Page 14
AES-VCM
:
:
:
Earthing System
Ref. No.
Date :
CHECK ITEM
No
Inspection elements
Material Check
Excavation work
Earthing wire and Earthing Rod installed with designed depth and
location
Checked by : (Subcontractor)
Name & Signature
Position
Date
Page 15
Observed
Result
/ Remarks
AES-VCM
Name & Signature
Position
Date
AES-VCM
Testing Sheet
Project
:
Drawing No.
:
Specific Location :
Cadwelder Person :
Test Person
:
Test Equipment
:
Earthing System
Ref. No.
Date :
CHECK ITEM
No
Location
Earthing resistance
8
Checked by : (Subcontractor)DOOSAN Electrical Dept.
Name & Signature
Name & Signature
Position
Position
Date
Date
Page 16
Observed
Result
/ Remarks
STORAGE PROCEDURE
ITEM NAME :
1 OF 6
Rev. No.
0.0
Doc. No.
ENL-SP-0001
Storage Procedure
Title
()
PROJECT NAME :
PAGE
( )
MONG DUONG
CONDUIT & ACCESSORIES
EARTHING & LIGHTNING MATERIALS
0.0
2011.03.28
First Issue
Rev.
No.
DATE
()
DESCRIPTION
()
S.H.PARK
K.H.LEE
K.M.LEE
PREPARED
BY
REVIEWED
BY
APPROVED
BY
A4 ( 210 * 297 )
STORAGE PROCEDURE
PAGE
2 OF 6
Rev. No.
0.0
Doc. No.
ENL-SP-0001
- Contents ( ) 1. Scope ( )
2. Purpose ( )
3. Storage ( )
Attachment 1 ( 1 : ) - 5 page
Attachment 1 ( 1 : ) - 6 page
A4 ( 210 * 297 )
STORAGE PROCEDURE
PAGE
3 OF 6
Rev. No.
0.0
Doc. No.
ENL-SP-0001
1. Scope ( )
This procedure shall be applied to storage methods of electric conduit, grounding and lightning products.
, .
2. Purpose ( )
This procedures describes storage methods to prevent supplied equipment and materials from corrosion,
chemical damage or any effect of deteriorating quality.
,
.
3. Storage ( )
Every product shall be classified into indoor or outdoor storage and stored according to detailed storage
method based on its material and characteristics of use structure.
( Outdoor storage refers to that with canopy or equivalent to prevent exposure to the rainwater. )
For the concerned storage, perform the sorage method on the basis of contents on Attachment 1.
, ,
.
( . )
, 1 .
3.1
3.2
Shall be stored and handled considering packing volume and frequency of carry-in/out.
.
3.3 Keep clean in the storage area and do not store the products under tough corrosive environments.
, .
A4 ( 210 * 297 )
STORAGE PROCEDURE
PAGE
4 OF 6
Rev. No.
0.0
Doc. No.
ENL-SP-0001
3.4 Thinner, paints and other inflammable hazrdous materials shall be stored on the separately designated
place , and avoid the storage place around fire and explosion hazrds scattered.
, ,
.
3.5 Every threaded products shall be treated with anticorrosive process first to prevent corrosion on the
thread, and the related products shall be stored on dry place without moisture so as to prevent
re-corrosion.
,
.
3.6 Those products packed within carton box may be stacked to the extent that the lower box shall not
be sunken, but periodic checkup is required.
box box box
.
A4 ( 210 * 297 )
PAGE
5 OF 6
Rev. No.
0.0
Doc. No.
ENL-SP-0001
Class
Indoor
Outdoor
As original Material
Steel
Electro-Galvanizing
Carbon steel
Hot-Dip Galvanized
Zinc Alloy
Electro-Galvanizing
As original Material
As original Material
Chromate Plating
Nickel Plating
Bronze
As original Material
SUS304
As original Material
SUS316
As original Material
As original Material
Tinned Coating
Hot-Dip Galvanized
Aluminum
As original Material
PVC
As original Material
Concrete
As original Material
Graphite Compressive
As original Material
Inflammable
As original Material
Adhesives
As original Material
paint/Thinner
As original Material
STORAGE PROCEDURE
ATTACHMENT 1.
Materials
Brass
Copper
Cast Iron
Plating Specification
Storage Class
A
B
C
D
E
Materials vulnerable to oxidation (rust) that shall be stored indoor and avoided storage under
high humid area as possible.
Hot dip galvanized products available for outdoor storage ( However, white rust shall not be
regarded as quality defect. )
Products without deterioration from oxidation (rust), available for outdoor storage.
Products without deterioration from oxidation (rust). However, as their deflection may occur,
excessive stacking shall be avoided.
Inflammable materials or other explosive materials that shall be isolated indoor and avoid
the storage place around fire and explosion hazrds scattered.
ENL-Q-004 Rev 1
1.0
0
SAMSUNG E&L CO
CO.,LTD
LTD
A4 ( 210 * 297 )
PAGE
6 OF 6
Rev. No.
0.0
Doc. No.
ENL-SP-0001
(SUS304)
(SUS316)
PVC
STORAGE PROCEDURE
ATTACHMENT 1.
() , .
. (, . )
() .
D
E
() ,
.
,
.
ENL-Q-004 Rev 1
1.0
0
SAMSUNG E&L CO
CO.,LTD
LTD
A4 ( 210 * 297 )
HEALTH
1
FLAMMABILITY
0
PHYSICAL HAZARD 0
SUPERWELD
2 = MODERATE
3 = HIGH
4 = EXTREME
TRANSPORTATION INFORMATION
PROPER SHIPPING NAME: Not Regulated
HAZARD CLASS / PKG GRP: Not regulated
IDENTIFICATION NUMBER: None
Page 1 of 3
MANUFACTURER'S NAME
34-6622-03 Rev. A
EMERGENCY TELEPHONE NUMBER
Superweld
(031) 542-8381
Pochun-Si, Kyungki-Do
CAS #
%
(OPTIONAL)
OSHA PEL
PPM
MG/M3
ACGIH TWA
PPM
MG/M3
SARA
RQ
TITLE III
LBS
1317-39-1
65~75
Copper (a,b)
7440-50-8
10~20
1.0
1.0
Yes
7429-90-5
10~20
15
10
Yes
1317-61-9
1~3
10
Mixture
1~3
Calcium Silicon
Yes
9600
(a) A "Yes" in the SARA TITLE III column in Section 2 indicates a toxic chemical subject to annual reporting requirements of Section 313 of the Emergency
Planning and Community Right-To-Know Act of 1986 and of 40 CFR 372.
(b) The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) has notification requirements for releases or spills to the
environment of the Reportable Quantity (RQ for this mixture > 24000 lbs) or greater amounts, if < 4 diameter, according to 40 CFR 302.
(c) The exposure limits of this product, when allowed to enter the environment as dust particulate, are covered under the rules of 29 CFR 1910.1000, Table Z 3, "All inert or nuisance dusts, whether mineral, inorganic or organic."
Remove contaminated clothing; wash affected area with soap and water;
launder contaminated clothing before reuse; if irritation persists, seek medical
attention.
Remove contact lenses. Flush eyes with clear running water for 15 minutes
while holding eyelids open; if irritation persists, seek medical attention.
INGESTION: May cause gastric distress, stomach pains, vomiting and diarrhea.
Give two glasses of water for dilution; induce vomiting as directed by medical
personnel; never give anything by mouth to an unconscious person; seek
medical attention.
CARCINOGENICITY
NTP?
No
IARC MONOGRAPHS? No
OSHA REGULATED? No
California Prop 65, Safe Drinking Water and Toxic Enforcement Act of 1986 - there are no reportable chemicals present known to the state to cause cancer or
reproductive toxicity.
MEDICAL CONDITIONS GENERALLY AGGRAVATED BY EXPOSURE: Preexisting skin, eye, or respiratory disorders may become aggravated through
prolonged exposure.
Page 2 of 3
34-6622-03 Rev. A
Date:
NFPA RATING
FLAMMABLE LIMITS
Not applicable
None
EXTINGUISHING MEDIA
Use dry sand, graphite, dolomite, sodium chloride, water spray or chemical foam.
SPECIAL FIRE FIGHTING PROCEDURES
Firefighters must wear full facepiece self - contained breathing apparatus in positive pressure mode.
UNUSUAL FIRE AND EXPLOSION HAZARDS: Thermoweld copper base welding/joining materials are exothermic mixtures, which when reacted, produce hot
molten materials with temperatures in excess of 4000 F and a localized release of smoke. The materials are not explosive, ignition temperatures are in excess of
850 F for starting material and 1750 F for base material. They are not shock sensitive, nor are they subject to spontaneous ignition. Should the material be
accidentally ignited, the immediate and direct application of large volumes of water will effectively retard the spread of fire and control it. Large amounts of dense,
dusty smoke will be liberated during an accidental fire.
RESPIRATORY PROTECTION (SPECIFY TYPE): NIOSH approved respirator designed to remove airborne particulate present in excess of maximum allowable
concentrations due to secondary operations such as mixing, spraying, sanding, buffing, etc. Refer to 29 CFR 1910.134 or European Standard EN 149 for
regulations.
VENTILATION
LOCAL EXHAUST:
Recommended
SPECIAL: None
MECHANICAL (GENERAL):
Yes
OTHER: None
UNSTABLE:
STABLE:
MAY OCCUR:
WILL NOT OCCUR:
Non Toxic
Page 2 of 3
Contaminated packaging :
Empty containers can be land filled when in compliance with local regulations
4.1
II
SECTION 15 - INSTRUCTIONS
None
SECTION 16 - MISCELLANEOUS
Recommended Use :
Further Information :
Please ensure that it is passed to the appropriate person(s) in your company , who are capable of acting on the infirmation.
The information given in this safety data sheet is based on current knowledge and experience and is intended to describe the products in
terms of their health and safety requirements. it should not therefore be construed as guaranteeing specific properties.
This data is based on our present knowledge. however it shall not constitute a guarantee for any specigic product features and shall not
establish a legally valid contractual relationship.