Usace Design Manual
Usace Design Manual
Usace Design Manual
US Army Corps
of Engineers
Mobile District
Design Manual
T A B L E
CHAPTERS
O F
C O N T E N T S
TITLES
REVISIONS SUMMARY
GENERAL INSTRUCTIONS
PRESENTATION OF DATA
SPECIFICATIONS
SITE DEVELOPMENT
GEOTECHNICAL
ARCHITECTURAL
10
INTERIOR DESIGN
11
STRUCTURAL
12
PLUMBING
13
14
15
16
17
18
COST ESTIMATING
19
ANTITERRORISM/FORCE PROTECTION
20
21
QUALITY MANAGEMENT
22
23
CHARRETTES
24
MILCON TRANSFORMATION
25
REVISIONS SUMMARY
1.
2.
3.
CHAPTER 1
GENERAL INSTRUCTIONS
INDEX
1.1
GENERAL
1.1.1 Purpose
1.1.2 Proponent
1.1.3 Military Construction (MILCON) Transformation
1.1.4 A-E Task Order (TO) Statement of Work (SOW)
1.1.5 Acronyms and Abbreviations
1.1.6 Discipline Coordination
1.2
APPLICABLE PUBLICATIONS
1.3
INSTRUCTIONS
1.3.1
Pre-design Conference
1.3.2
Quality Management
1.3.3
Studies, Renderings and Models
1.3.4
Charrette
1.3.5
Life, Health and Safety Standards
1.3.6
Design for the Physically Handicapped
1.3.7
Topographic Surveys, Basements and Utilities
1.3.8
Foundation Investigation
1.3.9
Environmental Regulatory Permits
1.3.10 Sustainable Design
1.3.11 Anti-Terrorism/Force Protection (AT/FP)
1.3.12 Lessons Learned
1.4
DEFINITIONS
1.4.1
Design Analysis
1.4.2
Drawings
1.4.3
Specifications
1.5
SUBMITTAL REQUIREMENTS
1.5.1
General
1.5.2
Project Definition (10-15%)
1.5.3
Concept Design (30-35%)
1.5.4
Value Engineering
1.5.5
Interim Design (50-65%)
1.5.6
Final Design (Unreviewed 100%)
1.5.7
Ready-To-Advertise (RTA) (Reviewed 100%)
EXHIBITS
1-1
1-1
CHAPTER 1
GENERAL INSTRUCTIONS
1.1
GENERAL
1.1.1
Purpose
Proponent
Designated Army MILCON and Army Base Realignment and Closure (BRAC)
2005 Act projects are subject to Army Transformation and supporting
U.S. Army Corps of Engineers (USACE) MILCON Transformation (MT)
procedures. These designated projects will be completed in cooperation
with USACE Centers of Standardization (CoS). CoS roles,
responsibilities and duties, and geographic district (GD) roles,
responsibilities and duties in MT designated projects are described in
Chapter 24 MILCON TRANSFORMATION.
1.1.4
(a) For A-E professional and technical services under A-E Indefinite
Delivery contracts with Mobile District or through capacity provided by
other organizations, the A-E Task Order (TO) Statement of Work (SOW)
will provide project specific execution criteria in conformance with
1-2
See Exhibit
1-3
1-4
NTP
Grade site bldg pad
Foundation
Under slab utilities
Slab on Grade
Structural fame
Roof framing-deck
Roofing
Exterior walls-windows
Bldg dry-in
B
X
C
X
X
X
X
1-5
D
X
X
X
X
X
X
X
X
X
X
E
X
X
X
X
X
X
X
X
X
X
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
Interior walls-framing
Permanent power
Wall finish
Prime paint
Mech/elect RI
Plumbing
Mech/elect above ceiling
Flooring (VCT-ceramic)
Doors-hardware
HVAC -ductwork-controls
Ceiling finish
Finish paint
Mech/Elect systems
Site work-utilities - paving
Carpet
QC system test (debugging)
QA system test (acceptance)
CQC inspection
HVAC Test and Balance
Landscaping-grassing
Prefinal Inspection
Commissioning-HVAC
Final/acceptance inspection BOD
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
1-6
Discipline Coordination
1-7
APPLICABLE PUBLICATIONS
INSTRUCTIONS
1.3.1
Pre-design Conference
1-8
Quality Management
An I-H Quality Control Plan (QCP) or A-E Quality Assurance Plan (QAP)
is required for all projects. See Chapter 21 QUALITY MANAGEMENT for
specific requirements.
1.3.3
Charrette
The most recent version of the International Building Code (IBC) will
be used as the basis of design of facilities unless specifically
exempted by the customer and documented. In addition, the most recent
version of NFPA 101 Life Safety Code and other NFPA Codes shall be
incorporated into the design as appropriate. UFC 1-200-01 will be used
by all designers as the basis for determination of code requirements.
(Changes mandated in use of codes in UFC 1-200-01 will be adjusted
based on use of the most recent IBC and NFPA codes until UFC 1-200-01
is updated.) The facilities, systems, and equipment design standards
of the Occupational Safety and Health Act, Code of Federal Regulations,
Title 29, Chapter XVII, Parts 1910 and 1926, as applicable, shall be
incorporated by the designer into all design and analyses. Other
customer-specific health and safety regulations will be determined
during the pre-design conference, and incorporated in the design
1-9
Foundation Investigation
1-10
(2)
Fees required.
Sustainable Design
Anti-Terrorism/Force Protection
Lessons Learned
1-11
1.4
DEFINITIONS
1.4.1
Design Analysis
Drawings
Specifications
SUBMITTAL REQUIREMENTS
1.5.1
General
1-12
plans and spec books are reserved for advertised solicitations only).
Submittals will not include the solicitation number on the drawings,
specs or covers. (Solicitation numbers on plans and spec books are
reserved for advertised solicitations only.)
1.5.2
Design Analysis:
Concept drawings.
(c)
(d)
(e)
(f)
1.5.4
Value Engineering
1-13
Transmittal letter.
(2)
Cover Sheet.
(3)
Table of Contents.
(4)
(5)
Study Methodology.
1-14
(e)
1-15
(f)
Identify Bid
1-16
Project Description:
1-17
Drawing/Specification Units
Topographic Survey
[The Government will furnish the A-E with the topographic survey for use in
preparation of the [design] [RFP].
[The A-E shall obtain all topographic surveys required to design the
project. The area to be mapped is approximately [??] acres (hectares).
The area shall be mapped at a scale of 1"= [??]'. The subsurface utilities
investigation shall be performed to a Quality Level [A] [B] [C] [D].] {PAE
shall coordinate with EN-DA (Civil/Site) and the survey section to
determine survey requirements, utility investigation quality level
required, and subsurface exploration methods.}
EXHIBIT 1-1 (Continued)
1-18
10.
Foundation Investigation
[Design-Bid-Build: The Government will furnish the A-E with the appropriate
subsurface data and a written report with foundation parameters to be used
in the design.]
[Design-Build: The Government will furnish the A-E with the appropriate
subsurface data and a written report with foundation parameters to be used
in the design. In the RFP it should be made explicitly clear that the D-B
Contractor is fully responsible for an acceptable foundation.]
[Design-Bid-Build: It is the AEs responsibility to obtain all subsurface
information and associated test data required for preparation of the
Geotechnical Report, the design and construction of the project in
accordance with the Design Manual. The AE shall be responsible for
obtaining all required drilling permits.]
[Design-Build: The A-E shall obtain all subsurface and associated test data
required for design of the project. The scope of the investigation will
include as a minimum the following [provide scope details] {PAE to
coordinate with EN-GG for requirements}. In the RFP it should be made
explicitly clear that the D-B Contractor is fully responsible for an
acceptable foundation.]
11.
{PAE
{PAE to determine in
1-19
TO SOW
Requirement
{Indicate
specific
requirement/s}
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
[X][1]
Architect-Engineer Services
Design Manual
Paragraph
and/or Chapter
Requirement
1.3.4, Chapter
23
Chapters 18 and
23
1.3.3(a)
Chapters 1, 2,
22 and 23
Chapters 1, 2,
22 and 23
Chapters 1, 2,
22 and 23
1.3.4, Chapter
23
Chapters 1, 2,
and 3
Chapters 1, 2,
and 3
Chapters 1, 2,
and 3
Chapters 1, 2,
and 3
Chapters 1, 2,
and 3
Chapters 1 and
20
1.5.4
Chapter 10
Chapter 10
1.3.3(b)(1)
1.3.3(b)(2)
1.3.7, Chapter
5
1.3.8, Chapter
6
Chapters 2 & 18
1.1.4(8)
[Reference]
1-20
14. The following actions or submittals are required from the A-E prior to
completion of the TO SOW negotiation.
Design Manual
TO SOW Requirement
TO SOW
Paragraph
Requirement
Requirement
{Indicate
specific
requirement/s}
X
1.1.4(b)
Pre-design Conference
X
1.3.1(b)
Pre-design Conference Minutes
X
1.1.4(f)(2)
Initial Progress Chart
X
1.1.4(f)(1)
Proposal
15. The following routine submittals are required from the A-E during
conduct of the TO SOW. Refer to the Design Manual for project specific
submittal requirements.
Design Manual
TO SOW Requirement
TO SOW
Paragraph
Requirement
Requirement
{Indicate
specific
requirement/s}
X
1.1.4(h)(1)
Updated Progress Chart
X
1.1.4(h)(2)
Payment Request
X
1.1.4(h)(3)
Final Payment Request
X
1.1.4(h)(4)
Change in personnel and revised SF 330 for
Government Approval
X
1.1.4(h)(5)
Needs List
X
21.3.2(c)
Quality Assurance Plan
16.
The
[
[
[
[
The
[
[
[
1-21
Duration
10 calendar days after TO award
[xx] calendar days after TO award
[xx] calendar days after TO award
[xx] calendar days after TO award
[xx] calendar days after TO award
[xx] calendar days after TO award
[xx] calendar days after TO award
4 calendar days prior to bid or
proposal opening
[xx] calendar days after TO award
[Other]
[The A-E shall provide its information to the Government, and the
Government will coordinate and mail the Final submittal package for
review.] [The Government will provide its information to the A-E, and the
A-E shall coordinate and mail the Final submittal package for review.]
19.
Period of Service.
[Since the A-E may be required to furnish advice during construction, all
work and services to be performed under this Task Order will be completed
by {enter date}.]
[All work including the submission of all required reports and data shall
be completed no later than [XXX] {enter time period} days after award of
this TO.]
20. Attachments:
[Design Submittal Mailing List]
[Submittal Evaluation Post Card]
[DD Form 1391]
[Other]
1-22
ABCDE F GH I J
AGENCY
A. U.S. ARMY ENGINEER DISTRICT, MOBILE
ATTN: CESAM-[PAE]
109 ST. JOSEPH STREET
MOBILE, ALABAMA 36628-0001
CHARRETTE
Design Narrative
Concept Site Plan
Schematic Floor Plans
Schematic Elevations
Parametric Cost Estimate
D. [RESIDENT ENGINEER]
E. [USER]
F. [COMMAND]
G. [AREA ENGINEER]
J. [INSTALLER]
H. [CONTRACTOR]
I. [CONTRACTING]
1-23
Design Analysis
Drawings (1/2 - Size Prints)
Cost Data Files (See Chapter 18)
Marked up Redlined Specifications
Final specifications
Permit Applications
Permit Documentation, P,S & DA Signed/sealed
Structural Interior Design
Furniture, Fixtures and Equipment
1-24
CHAPTER 2
PRESENTATION OF DATA
INDEX
2.1
GENERAL
2.1.1 Standards for Presentation of Data
2.1.2 Document Format and Guidelines
2.2
APPLICABLE PUBLICATIONS
2.2.1 Internet Addresses
2.3
SUBMITTAL REQUIREMENTS
2.3.1 Project Definition, Concept, & Interim Submittal
2.3.2 Final Submittal (Unreviewed 100%)
2.3.3 Ready-To-Advertise (RTA) (Reviewed 100%)
2.3.4 Computer Aided Language (CAL) File Creation and Submittals
2.3.5 Design-Build (D-B) Request for Proposal (RFP) Narrative
2.4
2.5
DRAWINGS
2.5.1 Computer Aided Design Drafting (CADD) Standards and Naming
Convention
2.5.2 Drawing Package Assemblage
2.5.3 Drawing Size, Title Blocks, Borders and CADD Code
2.5.4 Drawing Layout
2.5.5 Drawing Fonts and Scales
2.5.6 Drawing Standard Lines Styles and Widths
2.5.7 Location of Project Elements
2.5.8 For Information Only Drawings
2.5.9 Drawing Amendments and Change Orders Revisions
2.5.10 Computer Aided Design Drafting (CADD) Submittals
2.6
EXHIBITS
2-1
Submittal Evaluation Post Card
2-2
Example Project Definition Narratives and Design Analyses Format
2-3
Example RTA Report
2-4
Project Title Block
2-5
Sample Revision Block
2-6
Section & Detail Cross References
2-1
CHAPTER 2
PRESENTATION OF DATA
2.1 GENERAL
2.1.1 Standards for Presentation of Data
The guidelines, standards, and reference materials contained within this
Manual shall be used for preparation of all documents, unless otherwise
noted during the pre-design conference and in the SOW. The SOW for each
project is specific and may include additional requirements of the customer,
user, location, or installation.
2.1.2 Document Format and Guidelines
All documents presented shall be legible and clearly expressed. The
standard formats for many documents are described throughout this Manual.
Each and all required documents submitted should be adequately titled and
dated. The documents should show the stage of the submittal clearly marked
on the cover. Pages within any section or chapter of a document shall be
consecutively numbered, indexed, and cross-referenced so that specific
information can be easily located.
2.2 APPLICABLE PUBLICATIONS
ERDC/ITL TR-01-6
2-2
(c) RTA Cadd Files will not contain the use of Reference or Xref
Each drawing file must be free standing and independent.
(d) The PAE will furnish the A-E the Solicitation Number and
advertising date to be shown on each drawing. The Solicitation number and
advertising date shall be placed on each drawing after the Final Submittal
has been made and prior to RTA. A-E contract numbers will not be shown on
the drawings.
(e) See Chapter 3, SPECIFICATIONS, for the Ready-To-Advertise
specifications submittal requirements.
2.3.4 Computer Aided Language (CAL) File Creation and Submittals
See the following website for CAL files creation and downloads:
http://www.sam.usace.army.mil/en/guides/cadd/cals/cals.html
2-3
CAL files shall be half size plots of originals and may need to be rotated
90 degrees. For assistance, points of contact are listed on the web page
listed above.
2.3.5
2-4
2-5
2-6
2-7
I-1
I-2
General
Needs List
Foundation Conditions
II-1 Foundation Conditions
Site Development
III-1 Siting
III-2 Pavements
III-3 Grading and Storm Drainage
III-4 Fencing
III-5 Railroads
Landscaping, Irrigation, Planting and Turfing
IV-1 Landscaping, Irrigation, Planting and Turfing
Utilities
V-1 Water
V-2 Sanitary/Wastewater
V-3 Gas
V-4 Steam Distribution
V-5 Environmental Protection
V-6 Special Considerations
V-7 Fire Protection
Anti-Terrorism/Force Protection
VI-1 Anti-Terrorism/Force Protection
Architectural
VII-1 Architectural
VII-2 Interior Design
Structural
VIII-1 Structural
Mechanical
IX-1 Heating, Ventilation and Air Conditioning
IX-2 Plumbing
IX-3 Fire Suppression
IX-4 Special Considerations
IX-5 Special Mechanical Systems and Equipment
IX-6 Boiler Plants
IX-7 Air Pollution Control and Equipment
Electrical
X-1 Electrical
Electronics
XI-1 Electronic Systems
Communications
XII-1 Communications
Sustainable Design Development
XIII-1 Sustainable Design Development
Construction Coordination
XIV-1 Notes to the Resident Engineer
Cost Estimate
XV-1-Cost Estimate
2-8
Courier New, Size 10, black for all text and page
(b) No underlining.
(c) No bold lettering.
(d) Section titles shall not be all capitals.
(e) Margins:
Left
Right
Top
Bottom
1.25"
0.75"
1.0"
1.0"
2-9
bottom center.
TITLE.
<tab> (a)
Text.............
Text........
2-10
CADD ID No:
POOR (1) TO EXCELLENT (5)
RATING
N/A
COMMENTS:
EXHIBIT 2-1
2-11
Example
Chapter IX-1-Heating, Ventilation and Air Conditioning
(Level of Design) Design Submittal
Official Job Title
Installation, State
1.
2.
DESIGN REFERENCES.
a.
b.
TITLE.
<tab> (a)
<tab><tab>
(1)
3. TITLE. If you have only one paragraph associated with a section, do not
suspend the text below.
4.
SPECIFICATIONS.
a.
EXHIBIT 2-2
2-12
Example
RTA REPORT DESIGN SUBMISSION LEVEL
PROJECT TITLE
INSTALLATION, STATE
CADD CODE
SOLICITATION NUMBER (When available)
ADVERTISEMENT DATE (When available)
Date:
Preparer/Phone:
(Drawings and Specification listed below are examples)
CADD
NUMBER
SHT
REF.
TITLE OF DRAWINGS
X001E308.DWG
C001E308.DWG
C002E308.DWG
C003E308.DWG
C004E308.DWG
C005E308.DWG
C006E308.DWG
C007E308.DWG
X-001
C-001
C-002
C-003
C-004
C-005
C-006
C-007
Index of Drawings
Location and Vicinity Map
General Site Plan
South Site Removal Plan
North Site Removal Plan
Overall Site Layout
Overall Site Quantity/Distance Arcs
South Site Enlarged Site Plan
SPEC
NUMBER
TITLE OF SPECS
04 01 20
04 01 21
04 01 40
04 20 00.00 40
04 20 00
DESIGN
ANALYSIS
TITLE
MB06E308FVII-1.doc
Architectural
EXHIBIT 2-3
2-13
EXHIBIT 2-4
2-14
EXHIBIT 2-5
2-15
EXHIBIT 2-6
2-16
CHAPTER 3
SPECIFICATIONS
INDEX
3.1
GENERAL
3.1.1
3.1.2
3.1.3
3.1.4
3.2
OUTLINE SPECIFICATIONS
3.3
TECHNICAL SPECIFICATIONS
3.3.1
Generating Original Specifications
3.3.2
Tailoring and Coordination of Specifications
3.3.3
Tailoring Specification Shop Drawing Submittals
3.4
SPECIFICATION SUBMITTALS
3.4.1
Interim Submittal Specifications
3.4.2
100% Unreviewed Submittal Specifications
3.4.3
Ready-To-Advertise (RTA) Submittal Specifications
3.5
3.6
AIDS TO ADVERTISING
3.6.1
General
3.6.2
Aids Required with the 100% Unreviewed Final Design
Submittal
3.6.3
Aids Required with the Ready-to-Advertise (RTA) Submittal
3.7
EXHIBITS
3-1
Sample
3-2
Sample
3-3
Sample
3-4
Sample
3-5
Sample
3-6
Sample
3-7
Sample
Purpose
Automated Specifications
Scope
Quality of Work
Resume of Work
List of Drawings
Bidding Schedule
Explanation of Bid Items
Table of Contents
Submittal Register (SpecsIntact Automated)
Amendment Report
3-1
CHAPTER 3
SPECIFICATIONS
3.1
GENERAL
3.1.1
Purpose
Automated Specifications
3-2
Scope
Quality of Work
OUTLINE SPECIFICATIONS
The designer shall submit a list of specifications with the Concept design
analysis submittal. The list of specifications will support the various types
of construction intended and described in the design analysis, and provide a
description of any specifications which must be developed for the project.
Exhibit 2-1 provides an example of typical outline specification integration
into the design analysis.
3-3
3.3
TECHNICAL SPECIFICATIONS
3.3.1
o
o
o
o
o
o
o
o
Level 1 - 31 00 00 Earthwork
Level 2 31 41 00 Shoring
Level 3 31 41 16 Sheet Piling
Level 4 31 41 16.11
for activity or project specific use
for multiple contracts or alternate systems.
for very unique narrow scope UFGS (minimal)
Level 5 31 41 16.11 10 Designation for non-unified sections
10 Army
20 Navy
30 Air Force
40 NASA
50 90 other Future participating agencies
Sole source specifications are to be avoided. The use of trade names and
proprietary items and the drafting of a specification by adopting a
manufacturer's description of a particular article or procedures shall be
3-4
3-5
3.3.3
(a) The Shop Drawings typically listed in each UFGS specification are
intended to over the majority of circumstances for a variety of projects. Not
all Shop Drawings listed in the specification need to be included in every
project. During the editing of the Shop Drawing Submittal portion of each
specification, the designer should carefully consider which Shop Drawing
Submittals are actually required from an Engineering Verification and Quality
Control perspective. All submittals that are not absolutely necessary should
be deleted whether listed for "Government Approval" or "For Information Only".
(b) Submittals Requiring Government Approval. Shop Drawings and Product
Data Submittals requiring Government Approval should be limited to major
pieces of equipment or systems requiring review by the designer, color
selection, testing reports, etc. For each Submittal that requires Government
Approval, provide the desired reviewer designation "CD" for "Construction
Division" or "ED" for "Engineering Division." "ED" should be used for all
submittals that are an extension of Design. For example, a submittal that
requires Government Approval by Engineering should be listed as "G, ED". Note
the ", " between the "G" and "ED" which is required in order for the Automated
Submittal Register feature found in the SPECSINTACT software to function
properly. Recommendations for labeling Shop Drawing Submittals requiring
Government Approval are provided below. See UFGS specification Section 01 33
00 SUBMITTAL PROCEDURES for further information.
(1) Preconstruction submittals should be labeled "G, CD".
(2) Shop Drawings and Product Data Submittals for major pieces of
equipment or systems requiring review by the designer should be labeled "G,
ED".
(3) Submittals involving "Samples", or "Color" selection should be
labeled "G, CD" for coordination with the local BCE, DPW, or other
Installation office.
(4) Test Reports, Certificates, Operations and Maintenance Data
and Closeout Submittals should be labeled "G, CD".
(5) "For Information Only (FIO)" Submittals: For Shop Drawing
Submittals not requiring Government Approval, the "G" and "CD" or "ED"
designations after the Shop Drawing Title shall not be included.
3.4
SPECIFICATION SUBMITTALS
3.4.1
3-6
Following the 100% Unreviewed Final Submittal review, review comments will be
provided to the designer. The designer shall incorporate the comments into
the specifications and prepare the final specification utilizing the automated
specification techniques of SpecsIntact. The Ready-To-Advertise specification
shall be furnished in SpecsIntact standard generalized markup language (SGML)
format.
3.5
3.5.1
Standard Format
The designer shall utilize the SPECSINTACT UFGS MasterFormat 2004 files
downloaded from the Internet (http://specsintact.ksc.nasa.gov/) to prepare the
final specifications. The following must be used, when submitting hard
copies.
(a)
(b)
accepted.
Top Margin:
Bottom Margin:
Left-hand Margin:
Right-hand Margin:
1
1
1
1
inch
inch
inch
inch
(c)
(d)
(e)
(f)
(g)
Page numbering footers set to allow the computer to automatically
number the pages consecutively with the section number included when the
document is printed. (Example: 03 30 04 Page 1, 03 30 04 Page 2, 03 30 04 Page
3, etc.) The SPECSINTACT program will automatically generate this function.
(h)
Hard returns placed only at the required locations (i.e., at the
end of the paragraphs) to allow the text to word-wrap. Hard returns left
after each line in tables and forms to prevent word-wrapping and retain the
correct text format.
(i)
Sketches, drawings, or other attachments to be inserted at the end
of a specification section shall be scanned into and Adobe .PDF format.
(g)
Appendices to be placed in the rear of the specification set
should also be scanned into an Adobe .PDF format.
3.5.2
3-7
3.6
AIDS TO ADVERTISING
3.6.1
General
Resume of Work:
The designer shall furnish an estimate of the time to construct the project.
Consideration will be given to construction contractor procurement of
materials and any associated "lead" time, sequence of construction, phasing
requirements, anticipated climatic conditions to be encountered during
construction, etc. Rationale will be included to back up the designer's
estimated construction time.
3.6.3
All aids required with the RTA submittal must be furnished to the Mobile
District on CD-Rom. Acceptable formatting is limited to MS Word and Adobe
.PDF formats.
(a)
List of Drawings
Bidding Schedule
3-8
Table of Contents
An example is
(f)
Special Provisions Covering Unusual Situations, i.e., interface
problems, outages, security and/or safety requirements, storage area,
construction sequences and phasing requirement (if applicable), access to
site, early completion dates, etc.
Any questions concerning the above-listed submittals should be directed to ENDW for resolution.
3.7
Following the RTA submittal by the designer, the project will be advertised
for construction. During the advertisement period as discrepancies,
oversights, omissions, and other changes surface, the designer will be
required to prepare affected drawings and specifications for amendment.
Similar changes may also be required to be performed by the designer during
construction in the form of a Change Order. Amendments and Change Orders
shall be structured in the format specified below:
3.7.1
Specification Revisions
3-9
Example
RESUME OF WORK
The site of work is located in Okaloosa County, Florida, at Eglin Air Force
Base, and includes the following principal features and approximate
quantities:
(a)
Construction of a gymnasium containing approximately 10,000 square
feet of floor space, consisting of concrete floor slabs, concrete frame,
concrete frame, concrete masonry unit walls, open-web steel joists, steel deck
and built-up roofing. Interior work includes plumbing, heating, air
conditioning, and electrical work. Gymnasium to be furnished with
miscellaneous gymnasium equipment.
(b)
(c)
Water line - 400 feet of 3-inch pipe; 3-inch gate valve;
connection to existing 10-inch line.
(d)
(e)
(f)
(g)
(h)
Clearing and grubbing, including removal of portable wooden
bleachers (16' X 74') - 2.9 acres.
(i)
(j)
(k)
1-1/2 inch flexible pavement, including tack and prime coats and
7-1/2 inch stabilized aggregate base course - 700 square feet.
(l)
(m)
(n)
(o)
(p)
72 linear feet
200 linear feet
58 linear feet
Exhibit 3-1
3-10
Sample
List of Drawings
LATEST DATE
TITLE
A001YA20.DWG
February 2006
Index of Drawings
A101YA20.DWG
February 2006
Location/Vicinity Map
A301YA20.DWG
February 2006
Survey
A302YA20.DWG
February 2006
Site Plan
A303YA20.DWG
February 2006
A304YA20.DWG
February 2006
A305YA20.DWG
February 2006
Miscellaneous Details
A306YA20.DWG
February 2006
Miscellaneous Details
A307YA20.DWG
February 2006
Floor Plan
A308YA20.DWG
February 2006
Wall Sections
A309YA20.DWG
February 2006
Water Plan
Exhibit 3-2
3-11
Sample
Bidding Schedule
BIDDER'S NAME:______________________________________________________________
BIDDING SCHEDULE
____________________________________________________________________________
Item
Estimated
Unit
Estimated
No.
Description
Quantity
Unit
Price
Amount____
Base Bid
1.
1a.
1
7,900
Job
LF
XXX
__________
________
__________
__________
Job
____________
Warehouse Addition
2a.
Warehouse Addition
Prestressed Concrete Piles
1
850
LF
XXX
_________
__________
__________
Job
__________
3a.
1
300
LF
XXX
_________
__________
__________
Job
XXX
____________
Job
XXX
__________
5.
3-12
BIDDING SCHEDULE
____________________________________________________________________________
Item
Estimated
Unit
Estimated
No.
Description
Quantity
Unit
Price
Amount____
Bid Option No. 5
6.
Job
XXX
__________
Job
XXX
__________
Job
Pedestrian bridge
over canal
XXX
__________
__________
3-13
One contract only will be awarded on this Bid Schedule and award will be made
on the Base Bid and selected Options, in accordance with the paragraph entitled
Evaluation of Options (JUL 1990) in Section 00100: INSTRUCTIONS TO BIDDERS.
Award will be made according to the "Best Value" approach as defined in Section
00110: PERFORMANCE-PRICE TRADE-OFF BEST VALUE.
The Government may require the delivery of the numbered line items, identified
in the schedule as option items, in the quantity and at the price stated in the
schedule. Subject to the availability of funds, the Contracting Officer may
exercise the option(s) by written notice to the Contractor within 120 days of
Notice to Proceed.
NOTE NO. 5.
3-14
3-15
Sample
EXPLANATION OF BID ITEMS
GENERAL: This section comprises an explanation of the bid items identified in
the bid schedule. This section is a general scope of work for the bid items
described in the bidding schedule and is not intended to be all encompassing in
the descriptions. All work specified herein shall be accomplished in
accordance with the procedures prescribed in the technical provisions of the
specifications and the plans/details as shown on the contract drawings. Some
drawings are identified below to reference general locations and detail
information for various bid items, however other drawings, details and
specifications also apply. The Contractor shall bid each type of work under the
applicable bid item. Measurement for unit price payment will be made as
specified herein. Payment described for the various bid items will be full
compensation for all labor, materials, and equipment required to complete the
work. Compensation for any item of work described in the contract but not
listed in the bid schedule shall be included in the payment for the item of
work to which it is made subsidiary.
BASE BID
1. Payment under bid item no. 1 will constitute full compensation for
furnishing all materials, equipment, plant, tools, and all labor costs and
other associated incidentals necessary to complete the construction of the
Design Security Forces Facility project, in accordance with all drawings and
specifications, except as noted below. The entire courtyard area up to the
building and turn-around will be constructed of asphalt in the base bid. Base
bid also includes trees near the building, and limited trees around site, as
well as all grasses as shown on L-101, L-104 and L-105 and irrigation serving
these areas.
1a. Payment under bid item no. 1a will constitute full compensation for
furnishing all materials, equipment, plant, tools, and all labor costs and
other associated incidentals associated with testing, providing and placing
Security Forces Facility Prestressed Concrete Piles, which shall be measured
and paid at the contract unit price to the nearest 0.10 linear foot.
Measurement will be made from the tip of the pile to the top of the pile and
will not include any length of pile that is cut off and discarded.
BID OPTION NO. 1
2. Payment under bid item no. 2 will constitute full compensation for
furnishing all materials, equipment, plant, tools, and all labor costs and
other associated incidentals necessary to complete the construction of the
warehouse addition, except as noted in bid item 2a below.
2a. Payment under bid item no. 2a will constitute full compensation for
furnishing all materials, equipment, plant, tools, and all labor costs and
other associated incidentals associated with testing, providing and placing
Warehouse Addition Prestressed Concrete Piles, which shall be measured and
paid at the contract unit price to the nearest 0.10 linear foot.
Measurement
will be made from the tip of the pile to the top of the pile and will not
include any length of pile that is cut off and discarded.
3-16
3-17
Sample
W91278-06-R-0130
TABLE OF CONTENTS
BIDDING REQUIREMENTS
00100
00600
00700
00800
00 62 35
SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
Section
01 00 00
Section
02 41 00 DEMOLITION
02 42 00 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD
DIVISION 03 - CONCRETE
Section
03 11 14.00 10
03 15 13.00 10
03 30 04
03 45 01.00 10
WATERSTOPS
3-18
W91278-06-R-0130
Section
04 21 13.13 NONBEARING MASONRY VENEER/STEEL STUD WALLS
04 21 26
GLAZED STRUCTURAL CLAY TILE AND PREFACED CONCRETE MASONRY
UNITS
DIVISION 05 METALS
Section
05 05 23.00
05 12 00.00
05 21 00.00
05 30 00
05 70 00.00
10 WELDING, STRUCTURAL
40 STRUCTURAL STEEL
40 STEEL JOISTS
STEEL DECKS
40 ORNAMENTAL METAL
ROUGH CARPENTRY
FINISH CARPENTRY
11
11
14
34
44
51
62
71
DIVISION 09 - FINISHES
09
09
09
09
09
09
09
09
09
06
22
24
29
30
51
65
68
90
90
00
23
00
00
00
00
00
00
COLOR SCHEDULE
METAL SUPPORT ASSEMBLIES
STUCCO
GYPSUM BOARD
CERAMIC TILE, QUARRY TILE, AND PAVER TILE
ACOUSTICAL CEILINGS
RESILIENT FLOORING
CARPET
PAINTS AND COATINGS
3-19
14
14
21
44
51
01 EXTERIOR SIGNAGE
02 INTERIOR SIGNAGE
13.16 40 PLASTIC LAMINATE TOILET COMPARTMENTS
16.00 40 PORTABLE FIRE EXTINGUISHERS
00.00 40 LOCKERS
DIVISION 11 - EQUIPMENT
11 13 10 DOCK LEVELERS
DIVISION 12 FURNISHINGS
12 50 00 FURNITURE SYSTEMS
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19 PREENGINEERED METAL BUILDINGS
DIVISION 14 - CONVEYING EQUIPMENT
14 20 00 ELEVATORS, ELECTRIC
DIVISION 21 - FIRE SUPPRESSION
21 13 00.00 40 FIRE SPRINKLER SYSTEMS
21 13 24.00 10 AQUEOUS FILM-FORMING FOAM (AFFF) FIRE PROTECTION SYSTEM
21 30 00 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 14 29.00 40 SUMP PUMPS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 09 33.00 40 CONTROL SYSTEMS
23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT
DIVISION 26 ELECTRICAL
26
26
26
26
26
26
00
00
11
20
24
32
00.00
00.00
14.00
00
16.00
15.00
3-20
00
05
11
23
31
41
00
EARTHWORK
19
GEOTEXTILE
00
CLEARING AND GRUBBING
00.00 20 EXCAVATION AND FILL
16.19
TERMITE CONTROL BARRIER SYSTEM
16
METAL SHEET PILING
01
01
05
10
11
11
12
12
16
17
18
31
84
92
92
93
DIVISION 33 - UTILITIES
33
33
33
33
33
33
05
11
30
34
40
51
3-21
3-22
Sample
Submittal Register (SpecsIntact Automated)
Exhibit 3-6
3-23
Sample
AMENDMENT REPORT
Report for Amendment 0002:
FY-04 SOF Squad Ops / AC-130 Hurlburt Field, FL (MB02F312)
Hurlburt Field, FL
Solicitation No. W91278-03-R-0068
Date for Amendment: 10 Oct 2003
1. SPECIFICATIONS:
a. Add Revised Table of Contents. (Deleted Section 16755)
b. Add Revised Bid Schedule and Explanations.
c. Revise specification Section 06650 "Solid Polymer (Solid Surfacing)
Fabrications" as follows:
(1)Revise Paragraph 2.3.4 as follows:
2.3.5
Window stools and stage edge details shall be fabricated from 3/8 1/2 inch
thick solid surfacing, solid polymer material. Dimensions, edge shape, and
other details shall be determined during the design phase of the project.
d. Revise specification Section 08330 "Overhead Coiling Doors" as follows:
(1)Revise Paragraph 2.1.13 as follows:
2.1.13 Finish
Steel slats and hoods shall be hot-dip galvanized G90 in accordance with ASTM
A 653/A 653M, and shall be treated for paint adhesion and shall receive a
factory powder coat finish. The paint powder coat system shall withstand a
minimum of 1500 hours without blistering, bubbling, or rust. Surfaces other
than slats, hood, and faying surfaces shall be cleaned and treated to assure
maximum paint adherence and shall be given a factory dip or spray coat of rust
inhibitive metallic oxide or synthetic resin primer. Interior door surface
shall be painted to match the adjacent wall color. The exterior and interior
of the door shall be painted to match Devoe "Tortoise Shell" 2M54E (See ICI
Dulux Paints for discontinued Devoe formula).
e. Revise specification Section 09915 "Color Schedule" as follows:
(1)Revise Item c. of Paragraph 2.2.1.1 Exterior Trim as follows:
c.
3-24
2.
DRAWINGS:
LATEST
DATE
OCTOBER
OCTOBER
OCTOBER
OCTOBER
OCTOBER
OCTOBER
OCTOBER
2003
2003
2003
2003
2003
2003
2003
DRAWING TITLE
SITE PLAN = BASE BID - SHEET 1 OF 2
SITE DETAILS
FIRST FLOOR PLAN
SECOND FLOOR PLAN
ROOFING DETAILS AND WALL SECTIONS
DOOR SCHEDULE - SHEET 1 OF 2
FINISH SCHEDULE
LATEST
DATE
OCTOBER 2003
OCTOBER 2003
DRAWING TITLE
PLUMBING DETAILS - SHEET 1 OF 2
PLUMBING DETAILS - SHEET 2 OF 2
3-25
CHAPTER 4
SITE DEVELOPMENT
INDEX
4.1
GENERAL
4.1.1 Scope
4.1.2 Quality of Design
4.2
APPLICABLE PUBLICATIONS
4.3
4.4
4.5
4.6
FINAL
4.6.1
4.6.2
4.6.3
4.7
4.8
EXHIBITS
4-1
Sample, Tables A, B, and C
4-2
Figure I, Design Storm Index, 10 Years, 1-Hour Rainfall (Inches)
4-3
Figure II, Surface Runoff Coefficients and Figure III, Retardence
Coefficients
4-4
Figure IV, Infiltration Rates F and V
4-5
Figure VI, Rainfall Intensity I
4-6
Figure VII, Nomograph
4-7
Figure VIII, Nomograph
4-8
Figure IX, Hydraulic Elements Circular Conduits
4-9
Figure X, Roughness Coefficient n for Various Pipe, and Figure
XI, Head Loss Coefficients at Junctions
4-10 Sample, Plan - Design Example
4-11 Sample, Profile - Design Example
4-12 Table - Hydraulic Design For Culverts
4-1
4-13
4-14
4-15
4-16
Table
Table
Table
Storm
A - Blank Form
B - Blank Form
C - Blank Form
Drain Pipe and Structure Schedule
4-2
CHAPTER 4
SITE DEVELOPMENT
4.1
GENERAL
4.1.1
Scope
Quality of Design
APPLICABLE PUBLICATIONS
UFC
Unified Facilities Criteria (UFC) including UFC Series 3200: Civil/Geotechnical/Landscape Architecture shall be
utilized to provide planning, design, construction,
sustainment, restoration, and modernization for Department
of Defense (DOD) Projects.
AASHTO
USDOT
NPDES
4.3
The designer shall develop a narrative and conceptual site plan which
describe and present the conceptual site features based on the project
requirements. The narrative will discuss siting requirements and site
concerns including wetlands, installation restoration program (IRP)
sites, and soil and ground water contamination. The conceptual site
plan should be an efficient layout with emphasis given to user
requirements. The plan shall show building locations, parking areas,
roads, limits of paving and hardstands, and pedestrian access points.
The plan shall be developed so that a preliminary cost estimate can be
prepared.
4.4
4.4.1
4.4.1.1
General
Removals
Geometry
(a)
Storm Drainage
4-4
(b) Discuss the preliminary storm water design scheme and discuss
impacts on the existing storm drain systems.
(c) Provide selected design values to be used in the storm
drainage calculations such as surface runoff coefficient, retardance
coefficients, infiltration rate, and rainfall intensity based on a 10year, 25-year, and the 100-year storm frequency.
(d)
Grading
(d)
(a)
4-5
(a)
(b) Provide AASHTO design vehicle for which turning movements are
to be provided for and corresponding minimum turning radius.
(c)
(d)
(e)
(f)
(g)
(h)
Embankment slopes.
(a)
(b)
(c)
(d)
(e)
(f)
Pedestrian access
(g)
operation
4-6
4.4.1.9
(a)
(b)
(c)
4.4.1.10.
Railroads
(a)
(b)
Anticipated volume
(c)
Describe intended plan for the design of sediment and erosion control
for the project.
4.4.1.13
Outline Specifications
Additional Information
Concept Drawings
4-7
4.4.2.1.
(a)
(b)
4.4.2.2
(a) Show the overall site plan of planned work (Scale may be
determined by the designer to best fit project requirements).
(b) Annotate major items of work, significant removals, and or
phasing.
(c) Site topography with major existing features, buildings, and
or roads shall be presented with the new work.
4.4.2.5
4-8
plan.
(d) Show the proposed finished floor elevation and critical spot
elevations.
(e) Provide control monument data, list horizontal and vertical
data for each.
(f) Reflect existing utilities with the topography. If necessary
for clarity, show removals, relocations, and new work for utilities on
separate plans as directed herein.
(g) All contour intervals shall be 1-foot (25cm) interval, unless
otherwise approved.
4.4.2.7
Centerline Profile
Present the new and existing site features with all utilities
underground and overhead shown.
4.4.2.11
Present the site topographic survey. The scale shall match the geometric
layout and grading plan scales presented.
4-9
4.4.2.12
Specifications
Design Analysis
Update and expand the Concept Design Analysis to support the submittal
and include the following, as applicable:
4.5.1.1.
Pavement Design
4-10
Additional Information
Interim Drawings
(a) Update from 35% as necessary, provide graphic symbols for all
items used in plan assembly;
(b) Update from 35% as necessary, provide list of all
abbreviations used in plan assembly.
4.5.2.3
(a) Indicate all items of site work, which shall require removal
or relocation.
(b) Provide dimensioning for removal items such as pavements,
curbs, sidewalks, etc.
4.5.2.4
This sheet may be omitted for small projects where the complete site can
be presented on one geometric layout sheet(s). For larger projects,
update this sheet from the 35% to present the 65% design.
4.5.2.5
4-11
(a) Complete the geometric layout of all items of new work using
offset dimensions from existing structures or use coordinates for
locating new work. Coordinates shall be to the one-hundred of a foot.
work.
(d) Complete the legend to include all items and symbols shown on
the plans. Symbols should be consistent between successive drawings.
(e) Show on the plan the construction centerline, right-of-way
limits, and all critical topographical features such as fences,
buildings, streams, railroads, etc.
(f) Locate or make reference to monuments and benchmarks for
horizontal and vertical control.
(g) Provide layout survey information necessary for establishment
of the survey centerline, new structures, building column lines, runway
centerlines, etc, including coordinates or computed bearings, radii,
curve data, super-elevation requirements, pavement widening
requirements, point of intersection of centerlines, etc.
(h) When super-elevation is required, include in the plan a
diagrammatic profile of how the super-elevation is obtained and also
tables of shoulder slopes versus cross slopes for the super-elevated
section.
(i) Unless otherwise shown on the demolition and removal plan,
note on the plans the size and type of all existing structures and the
manner in which they are to be utilized, removed, or otherwise affected
by new work.
(j) If widening of the pavement is required in curves provide
sufficient data to facilitate the construction.
4.5.2.6
4-12
4.5.2.7
(a) Airfields: Update from the 35%: present the interim design
profile for runway and/or taxiway centerlines. Provide edge of pavement
profiles if applicable for milling and overlay projects. Show existing
ground line and interim new finish grade with percent new grades
indicated.
(b) Roads, Streets, & Parking Areas: Update from the 35%: present
the interim design profile for centerlines. Show existing ground line
and interim new finish grade with percent new grades indicated.
(c) Unless otherwise approved, use a vertical scale of 1 = 5 and
horizontal scale of 1-30 or as appropriate to terrain as approved.
Indicate and label beginning and ending tie points.
(d) Provide elevations at points where changes of grade occur.
(e) Indicate the lengths of vertical curves and present all
vertical curve data.
(f) Indicate the percentage of slope for all grade lines. Provide
special information pertaining to the profile and affecting the design
such as curb grades, gutter grades, drainage structure inverts and top
elevations, etc.
(g) Provide centerline grade elevations at each 50-foot
station.
(h) Show new and existing drainage structures on the profile.
4.5.2.8
4-13
(a) Concrete Joint Layout Plans: Provide a joint layout plan for
each concrete apron, hardstands, road, pavement, etc. Joint plan shall
clearly indicate the required joint type for all joints as well as
specific slabs which require reinforcement. The scale of layout plans
shall be enlarged to clearly show all details for layout and grading.
Typical scale shall be 1=10 or 1=20 or unless otherwise approved.
(b) Concrete Joint Grading Plans: Provide a joint grading plan
for all concrete pavements, aprons, hardstands, roads, etc. Grade for
each joint intersection shall be provided on the plan at the specific
joint. Only joints with grades, which can be linearly interpolated, may
be omitted. Sufficient grades must be provided to facilitate
calculation of all joints in the plan. Scale of grading plan shall be
in accordance with 4.5.2.10(a).
(c) Concrete joint details: Provide details of all joint types as
applicable to the project. Provide detail of joint sealant.
(d) Sidewalk joint layout: Provide details of sidewalk joints for
entrances at buildings, handicap ramps, and circular drives, etc, as
applicable.
4.5.2.11
4-14
(a) Update the preliminary new and existing site plan with all
utilities underground and overhead shown.
(b) Coordinate and resolve utility conflicts as necessary.
4.4.2.13
(a) Present the site topographic survey. The scale shall match
the geometric layout and grading plan scales presented.
(b) Present any special notes and locations of IRP sites,
wetlands, or other environmentally sensitive areas. Present any
archeological or culturally significant areas.
4.5.2.14 Preliminary Best Management Practices Plan (Erosion and
Sedimentation Control Plan)
(a) For all projects with land disturbance provide a Best
Management Practices Plan (Sediment and Erosion Control Plan). The plan
shall be prepared by a Professional Engineer registered in the State
where the project exist and shall also meet the minimum State specific
qualifications requirements as a Qualified Credentialed Professional
as defined by State specific regulations. The Plan shall present the
preliminary best management practices both temporary and permanent,
anticipated to control sedimentation and erosion throughout the life of
the project. Plans shall be in accordance with the specific State
adopted Best management Practices handbook(s) as referenced in the
specific State NPDES Construction Permit Program.
(b) Provide calculations in the design analysis for sizing
temporary and permanent sedimentation basins or ponds, ditches, ditch
liners, diversions, etc.
(c) Provide preliminary details for all erosion and sediment
control devices such as sediment traps, sediment ponds, slope
diversions, filter strips, seeding and grassing requirements,
structures, and maintenance schedules. Details shall be in accordance
with the specific State adopted Best management Practices handbook(s) as
referenced in the State NPDES Construction Permit Program.
(d) Provide erosion and sediment control phasing sequences.
4.4.2.15
Specifications
4-15
Advance design of all plan and details sheets to completion. Present the
complete design for layout, grading, materials, marking, demolition and
removal, drainage, erosion control, traffic control, and construction
phasing information with complete construction details. Resolve or
comply with comments from the previous reviews. The Final plan assembly
shall include, as a minimum the following completed plan sheets, as
applicable to the specific project.
Title Sheet and Index;
Project Location & Vicinity Map(s);
Project Symbols Legends and Abbreviations Sheet;
Demolition and Removal Plan.
General Site Overview Plan;
Geometric Layout Plan;
Grading and Storm Drain Plan;
Centerline Profile Sheet(s);
Storm Drain Profile Sheet(s);
Typical Sections Sheet(s);
Concrete Layout and Joint Plan(s);
Construction Detail(s) and enlargement Plan(s);
Composite Utility Plan(s);
Existing Site Topographical Survey and Utilities Plan;
Final Best Management Practices Plan (Erosion and Sedimentation
Control Plan);
Project Construction Phasing Plan.
4.6.1
4-16
Final Specifications
General
(a) For the design of other than airfield storm drainage systems,
the procedure that follows and, as appropriate, TM 5-820-4 shall be
utilized. Design compilation sheets, reference l.c., shall be used
during the design and included as a part of the design analysis. The
design analysis shall also include an overall drainage map depicting
individual drainage areas, assumed paths, and slopes of runoff used to
compute times of concentration, and the types of surface within the
individual areas.
(b) For projects located in the states that require storm water
permits, the designer shall perform the drainage design in accordance
with the state's criteria. The designer shall maintain a complete
record of the criteria and calculations.
4-17
4.8.3
Notes To Designer
(a) The "Procedure for Design of Storm Drainage Systems for Other
Than Airfields" was developed to consolidate and clarify design criteria
and procedures presented in TM 5-820-1 and TM 5-820-4, to facilitate
designs of other than airfield drainage systems, and to achieve design
consistency.
(b) This design procedure in no way relieves designers of their
responsibility to comply with the provisions and requirements of TM 5820-4.
(c) The storm runoff design procedure presented in Steps l through
l2 in 4.8.5 applies to both the closed storm drainage system and
individual culverts. The pipe sizing procedure presented in Steps l3
through l9 applies to closed storm drainage systems only. Individual
culverts shall be sized using procedures contained in TM 5-820-4.
4.8.4
(a) The criteria and procedures are for areas up to one square
mile, where only peak discharges are required for design, and ponding is
not permitted.
(b) The design storm shall be based on l0-year storm frequency
with no ponding. The designer will check the 100-year event through
the proposed system to insure no flooding or damage occurs.
(c) Minimum times of concentration, t, of l0 minutes for paved
areas and 20 minutes for grassed areas shall be used.
(d) Manholes or junction boxes shall be provided at points of
change in conduit grade or size, at junctions with laterals or branches,
and wherever entry for maintenance is required. Distance between points
of entry shall be not more than about 300 feet for conduits with
diameter smaller than 30 inches. Conduit alignment between entry points
shall be straight, except for 30 inches and larger sizes.
(e) Pipe discharge velocities must not be less than 2.5 fps to
provide for adequate pipe cleansing.
(f) Minimum pipe sizes shall be l2 inches for closed drainage
systems and l8 inches for individual culverts, unless unusual or special
design considerations warrant using smaller pipe.
(g) Storm drainage systems shall be constructed in accordance with
UFGS specifications section 33 40 01. The specifications contain
instructions and information that must be considered during design.
(h) Metal pipes will receive paved inverts when pipe velocities
exceed 6 fps.
(i) Plain Galvanized Steel pipes shall receive bituminous coating.
(j) Aluminized Steel, Type 2, will not require bituminous coating.
(k) Plastic pipes shall be HDPE Double wall.
4-18
4.8.5 Procedure For Design Of Storm Drainage Systems For Other Than
Airfields
Step 1 - Columns l through l4 of Table "A" of Exhibit 4-1 shows
data necessary for drain inlet design. The drainage area for each inlet
is calculated with respect to the paved, bare soil and turfed surface
conditions within the area. These areas are entered in Columns 2, 3,
and 4. The total drainage area for each inlet is then entered in Column
5. Surface runoff coefficients "C" are assigned from Figure II of
Exhibit 4-3 based on the predominant paved, bare soil, and turfed
surface conditions encountered in the overall drainage area and are
entered at the top of Columns 2, 3, and 4. Only under unusual
circumstances shall bare surface areas be considered in the drainage
calculations. The weighted coefficient "C" for inlet number 1 is
calculated as follows:
A
Step 2 - The actual length of runoff "L" for each inlet or design
is scaled from contour maps, etc., with respect to the paved, bare soil
and turfed surface conditions encountered. The sum of the individual
lengths involved is entered in Column 7. Considerations must be given
to the type of flow (sheet, channelized, ditch, swale, etc.), slopes,
(along the flow path), and surface retardence coefficients when
selecting the runoff length. Sheet flow is assumed to become
channelized flow on unpaved surfaces after a sheet flow distance of 200
feet. The selected length of runoff should represent a realistic path
of flow measured perpendicular to contours and one that shall provide
the maximum runoff flow time (time of concentration). The actual runoff
length "L" for inlet 1 drainage area was determined to be 260 feet. The
first 200 feet occurred with sheet flow on an average grass surface
sloping at 0.70%. The next 35' occurred with channelized flow on an
average grass surface sloping at 0.70%. The assumed surface retardence
"n" was 0.40 for sheet flow and 0.20 for channelized flow. The
remaining 25 feet of runoff occurred on an asphalt paved surface sloping
at 0.50% and having a retardence "n" of 0.02. Retardence "n" is the
term used to designate the resistances to sheet, channelized, and ditch
flow caused by various surface conditions such as vegetation, surface
and alignment in the path of flow. Retardence coefficients are assigned
from Figure III of Exhibit 4-3. The average retardence "n" for inlet
number 1 is calculated as follows:
L
4-19
=
=
=
=
=
4-20
4-21
shown in Figures VII may be used for the design of circular pipe having
respective "n" values of 0.012 and 0.024. On occasion when non-circular
pipe and/or pipe having other "n" values are required, they shall be
designed using the Manning's Equation. Hydraulic Design Series No. 3 of
"Design Charts for Open-Channel Flow" published by the U. S. Department
of Transportation, Federal Highway Administration (Reprinted 1979) is an
acceptable design aid that may be used to design for these special
conditions. Pipe roughness coefficients "n" for various pipe are shown
in Figure X of Exhibit 4.9.
Step 14 - The pipe roughness coefficient "n" is entered in the
appropriate space of the top of Table "C" of Exhibit 4-1. For this
example, an "n" value of 0.012 is being used.
Step 15 - Enter Figure VII of Exhibit 4-6 using the design
discharge from Column 32. Select a pipe size such that a line drawn from
the design discharge from Column 32 through the selected pipe size
intersects the slope and velocity lines at minimum values. Slopes for
the required pipe size should be held to a minimum consistent with
limitations imposed by cover requirements, proximity to other
structures, and interference with other utilities. Also, pipe sizes and
slopes should be selected such that flow velocities in successive pipes
remain fairly constant. To avoid ponding at intake points (inlet, catch
basins, etc.), pipe inverts and velocities must be established such to
maintain the kinetic energy line (velocity head V plus the entrance 2g
loss, head (K V2) at or below the top or gutter line elevation of the
intake structures. In most cases, providing minimum pipe cover shall
fulfill or exceed the velocity head plus entrance loss requirement.
Both conditions, however, must be checked to ensure that ponding shall
not occur.
In profile proceeding downstream, the crowns of pipes where sizes
progressively increase shall be matched. Crowns of incoming laterals
shall be matched to that of mainline. Additional lowering of an
outgoing pipe shall be required to compensate for head loss within the
junction structure.
Step 16 - For pipe 1-2, a Q of 3.3 cfs (from Column 32) is entered
into Figure VII of Exhibit 4-6. At a slope of 0.85%, a 12" pipe shall
handle the design discharge with a reasonable velocity. A line drawn
through the pipe size of 12" and a slope of 0.85%, intersects the
discharge line at 3.5 cfs and the velocity line at 4.6 fps. This
indicates the capacity of the pipe flowing full is 3.5 cfs at a velocity
of 4.6 fps. Enter the selected pipe size and slope into Columns 33 and
34, respectively. It is now necessary to determine the Velocity in the
pipe for the design Q of 3.3 cfs. Compute the ratio of the design
discharge (3.3 cfs) to the flowing full discharge (3.5 cfs) as follows:
Q Design = 3.3 = 0.94
Q Full
3.5
Enter the bottom of Figure IX of Exhibit 4-8 at 0.94 and project a
vertical line intersecting the "Capacity" curve. Continue the line
horizontally from this point intersecting the "Velocity" curve. The
partial full to full flow velocity ratio (Design/Full) is interpreted as
1.135 by projecting a vertical line from the "Velocity" curve to the
bottom of Figure IX of Exhibit 4-8. The partial full or Pipe 1-2 design
velocity (Design) is found to be (4.6) (1.135) = 5.2 fps and is entered
into Column 35.
4-22
4-23
Sample
Tables A, B, C
Exhibit 4-1
4-24
Figure I
Design Storm Index, 10 Years, 1-Hour Rainfall (Inches)
Exhibit 4-2
4-25
Figure II
Surface Runoff Coefficients
Figure III
Retardence Coefficients
Exhibit 4-3
4-26
Figure IV
Infiltration Rates F (Inches/Hour)
Figure V
Time of Concentration
Exhibit 4-4
4-27
Figure VI
Rainfall Intensity I
Exhibit 4-5
4-28
Figure VII
Nomograph
Exhibit 4-6
4-29
Figure VIII
Nomograph
Exhibit 4-7
4-30
Figure IX
Exhibit 4-8
4-31
Figure X
Roughness Coefficient n for Various Pipe
Figure XI
Head Loss Coefficients at Junctions
Exhibit 4-9
4-32
Sample
Plan Design Example
Exhibit 4-10
4-33
Sample
Plan Design Example
Exhibit 4-11
4-34
Table
Hydraulic Design for Culverts
Exhibit 4-12
4-35
Table A
Blank Form
Exhibit 4-13
4-36
Table B
Blank Form
Exhibit 4-14
4-37
Table C
Blank Form
Exhibit 4-15
4-38
Exhibit 4-16
4-39
CHAPTER 5
SURVEYING AND MAPPING
INDEX
5.1
GENERAL
5.2
APPLICABLE PUBLICATIONS
5.3
PROJECT DEFINITION
5.3.1 General Statement of Surveying and Mapping Services
5.3.2 Existing Horizontal and Vertical Site Control
5.4
5.5
5.6
EXHIBITS
5-1
Standard AutoCad Layers for Topographical Surveys
5-1
CHAPTER 5
5.1
GENERAL
This chapter presents general requirements for surveying and mapping and
the processing of the data that may be required for the work necessary
in the design and advance planning of assigned projects. All labor,
materials, and equipment necessary to perform site surveying and mapping
services are required. Adequate professional supervision and quality
control to assure the accuracy, quality, and completeness of the site
surveys is required. Work may be required anywhere within the boundaries
or assignments of the Mobile District in connection with the acquisition
of site surveys and preparation of maps.
5.2
APPLICABLE PUBLICATIONS
Mobile District, Manual of Instructions for
Geodesy, Cartography, Hydrography and
Photogrammetry
EM-385-1-1
ERDC/ITL TR-01-6
EM 1110-1-1000
Photogrammetric Manual
EM 1110-1-1003
EM 1110-1-1004
EM 1110-1-1005
Topographic Surveying
EM 1110-2-1003
Hydrographic Surveying
5-2
These include surveys in which the figure and size of the earth are
considered and is used for precise location of basic points suitable for
controlling other surveys. These include all orders of horizontal and
vertical control surveys, geodetic astronomy, gravity and magnetic
surveys in accordance with the Standards and Specifications for Geodetic
Control Networks published by the Federal Geodetic Control Committee.
Conventional, electronic instrumentation, inertial, satellite and other
survey methods, as applicable, may be utilized. This reference is
available at:
5-3
http://www.ngs.noaa.gov/FGCS/tech_pub/1984-stds-specs-geodeticcontrol-networks.htm
5.4.2
Quantity Surveys
Layout Surveys
These include surveys of channels, lakes, rivers, bays and open coastal
waters in support of engineering design, construction, operations and
maintenance include acquisition of hydrographic and surveying and
mapping data representing three dimensional spatial relationships on the
earth's surface. This data may be required for planning, cost
estimating, engineering, dredging, design, construction, sedimentation,
master planning, operations and as-built conditions. Conventional and
electronic instrumentation, and remote sensing, inertial, satellite,
side scan sonar, subbottom profiling, marine magnetometer, and other
surveying methods, as applicable, may be utilized.
5.4.7
Precise Surveys
Photogrammetric Services
5-4
include film negatives, film and glass positives, photo indexes, photo
enlargements, computations, scribecoats, compilation histories, and
mapping on stable base materials my be required.
5.4.10
Cartographic Surveying
5-5
Digital Data
A digital CADD file with the survey data is required in the latest
release of both MicroStation and AutoCAD. The designer shall store and
maintain a copy of all electronically created digital files (CD's, tapes
and disc) through the construction phase of the project. The CD's,
tapes and disc shall be made available to the government upon request
and shall be maintained with no additional cost to the Government.
5.4.15
(a) The list of standard Cadd layer names shown in Exhibit 5-1
shall be utilized for topographical surveys. Where strict adherence to
this naming standard is not possible, the layer names assigned shall
easily identify those elements placed on that particular layer, and
follow the same layer naming logic.
(b) The latest version of the AEC CADD Standards shall be used.
This standard can be located at:
https://tsc.wes.army.mil/products/standards/aec/.
5.5
5.5.1
Unless otherwise stated within the Scope of Work, all horizontal data
shall be referenced to NAD83 with a projection in the local state plane
coordinate system. Unless otherwise stated within the Scope of Work,
all vertical data shall be referenced to NAVD88. The use of a geoid
model to convert from ellipsoid heights to orthometric heights is
permissible only with the GEOID 03 model or a later version, unless a
different model is explicitly stated within the scope of work. The site
survey shall be accomplished with no less than third (3rd) order
accuracy and procedure. Assumed coordinates and vertical positions can
be used only with the Government's permission. CADD drawings shall
indicated what horizontal and vertical control datum were used for the
site surveys.
5.5.3
Survey Monuments
5-6
TYPE MARK
AND DATE
NORTHING
SPC w/zone
NAD83 (ft)
EASTING
SPC w/zone
NAD83 (ft)
ELEVATION
NAVD88
(ft)
21A-3B
345,123.34
1,234,456.00
234.56 FT.
21A-3C
REBAR
345,140.66
1,234,400.56
246.98 FT.
BB-3
REBAR
345,340.45
1,234,645.14
250.42 FT.
21A-3D
345,450.98
1,234,823.34
254.10 FT.
212-3
345,003.45
1,234,700.98
224.21 FT.
212-4
256,234.67
1,989,067.00
225.90 FT.
5.5.5
All personnel shall strictly observe the laws of the United States or
other governing body affecting operations at all sites. The personnel
shall comply with all applicable laws under which they are operating
including those concerning the inspection and operation of equipment and
the licensing of engineers, land surveyors, pilots, mechanics and other
personnel. It is further understood and agreed that the designer
assumes full responsibility for the safety of his employees, plant, and
materials.
5.5.6
Security Clearance
5-7
5-8
C-APRN-OTLN-DM
C-APRN-OTLN-EX
C-APRN-OTLN-NW
- Apron outline.
C-APRN-TXT-DM
C-APRN-TXT-EX
C-APRN-TXT-NW
- Apron text.
C-BLDG-OTLN-DM
C-BLDG-OTLN-EX
C-BLDG-OTLN-NW
C-BLDG-TXT-DM
C-BLDG-TXT-EX
C-BLDG-TXT-NW
C-CONTMJ-LINE-DM
C-CONTMJ-LINE-EX
C-CONTMJ-LINE-NW
C-CONTMJ-TEXT-DM
C-CONTMJ-TEXT-EX
C-CONTMJ-TEXT-NW
C-CONTMN-LINE-DM
C-CONTMN-LINE-EX
C-CONTMN-LINE-NW
C-CONTMN-TEXT-DM
C-CONTMN-TEXT-EX
C-CONTMN-TEXT-NW
5-9
C-ELEC-LINE-DM
C-ELEC-LINE-EX
C-ELEC-LINE-NW
C-ELEC-TXT-DM
C-ELEC-TXT-EX
C-ELEC-TXT-NW
C-FENC-LINE-DM
C-FENC-LINE-EX
C-FENC-LINE-NW
- Fence lines
C-FENC-TXT-DM
C-FENC-TXT-EX
C-FENC-TXT-NW
C-GAS-LINE-DM
C-GAS-LINE-EX
C-GAS-LINE-NW
C-GAS-TXT-DM
C-GAS-TXT-EX
C-GAS-TXT-NW
C-PAVE-JNT-DM
C-PAVE-JNT-EX
C-PAVE-JNT-NW
- Pavement Joints
C-PAVE-TXT-DM
C-PAVE-TXT-EX
C-PAVE-TXT-NW
C-PKNG-OTLN-DM
C-PKNG-OTLN-EX
C-PKNG-OTLN-NW
- Parking outline
C-PKNG-PVMK-DM
C-PKNG-PVMK-EX
C-PKNG-PVMK-NW
C-PKNG-TXT-DM
C-PKNG-TXT-EX
C-PKNG-TXT-NW
- Parking text.
C-RAIL-CNTL-DM
C-RAIL-CNTL-EX
C-RAIL-CNTL-NW
- Railroad centerlines.
C-RAIL-OTLN-DM
C-RAIL-OTLN-EX
C-RAIL-OTLN-NW
- Railroad outlines.
C-RAIL-TXT-DM
C-RAIL-TXT-EX
C-RAIL-TXT-NW
- Railroad text.
C-RIPR-OTLN-DM
C-RIPR-OTLN-EX
C-RIPR-OTLN-NW
- Riprap outline
- Gas lines
5-10
C-ROAD-CNTR-DM
C-ROAD-CNTR-EX
C-ROAD-CNTR-NW
- Road centerline.
C-ROAD-CURB-DM
C-ROAD-CURB-EX
C-ROAD-CURB-NW
- Road curbs
C-ROAD-GARD-DM
C-ROAD-GARD-EX
C-ROAD-GARD-NW
C-ROAD-OTLN-DM
C-ROAD-OTLN-EX
C-ROAD-OTLN-NW
- Road guardrails
C-ROAD-TXT-DM
C-ROAD-TXT-EX
C-ROAD-TXT-NW
- Road Text.
C-RUNW-CNTL-DM
C-RUNW-CNTL-EX
C-RUNW-CNTL-NW
- Runway centerlines.
C-RUNW-OTLN-DM
C-RUNW-OTLN-EX
C-RUNW-OTLN-NW
- Runway outline
C-RUNW-TXT-DM
C-RUNW-TXT-EX
C-RUNW-TXT-NW
- Runway Text
C-SIGN-OTLN-DM
C-SIGN-OTLN-EX
C-SIGN-OTLN-NW
- Signs
C-SIGN-TXT-DM
C-SIGN-TXT-EX
C-SIGN-TXT-NW
- Sign Text
C-SNSW-LINE-DM
C-SNSW-LINE-EX
C-SNSW-LINE-NW
C-SNSW-MNHL-DM
C-SNSW-MNHL-EX
C-SNSW-MNHL-NW
C-SNSW-TXT-DM
C-SNSW-TXT-EX
C-SNSW-TXT-NW
C-STEAM-LINE-DM
C-STEAM-LINE-EX
C-STEAM-LINE-NW
- Steam lines
C-STEAM-TXT-DM
C-STEAM-TXT-EX
C-STEAM-TXT-NW
- Road outline
5-11
C-STRM-HDWL-DM
C-STRM-HDWL-EX
C-STRM-HDWL-NW
C-STRM-LINE-DM
C-STRM-LINE-EX
C-STRM-LINE-NW
C-STRM-MNHL-DM
C-STRM-MNHL-EX
C-STRM-MNHL-NW
- Stormwater lines.
C-STRM-TXT-DM
C-STRM-TXT-EX
C-STRM-TXT-NW
- Stormwater text.
C-SURV-BND-LNS
C-SURV-BND-TXT
C-SURV-CNTL-PTS
C-SURV-CNTL-TXT
C-TAXI-CNTR-DM
C-TAXI-CNTR-EX
C-TAXI-CNTR-NW
- Taxiway centerlines.
C-TAXI-OTLN-DM
C-TAXI-OTLN-EX
C-TAXI-OTLN-NW
- Taxiway outlines.
C-TAXI-TXT-DM
C-TAXI-TXT-EX
C-TAXI-TXT-NW
- Taxiway text.
C-TOPO-BORE
C-TOPO-COOR
C-TOPO-GRID
C-TOPO-SPOT-DM
C-TOPO-SPOT-EX
C-TOPO-SPOT-NW
C-TOPO-TXT-DM
C-TOPO-TXT-EX
C-TOPO-TXT-NW
- Topographical text.
C-VEG-OTLN-DM
C-VEG-OTLN-EX
C-VEG-OTLN-NW
- Vegetation outline
C-VEG-TXT-DM
C-VEG-TXT-EX
C-VEG-TXT-NW
- Vegetation text.
C-WALK-OTLN-DM
C-WALK-OTLN-EX
C-WALK-OTLN-NW
- Walkways.
C-WALK-TXT-DM
C-WALK-TXT-EX
C-WALK-TXT-NW
- Walkway text.
- Stormwater manholes.
Survey
Survey
Survey
Survey
boundary lines.
boundary line text.
control points.
control text.
5-12
C-WATF-OTLN-DM
C-WATF-OTLN-EX
C-WATF-OTLN-NW
C-WATF-TXT-DM
C-WATF-TXT-EX
C-WATF-TXT-NW
C-WATR-HYDT-DM
C-WATR-HYDT-EX
C-WATR-HYDT-NW
- Water hydrants
C-WATR-LINE-DM
C-WATR-LINE-EX
C-WATR-LINE-NW
- Water lines.
C-WATR-TXT-DM
C-WATR-TXT-EX
C-WATR-TXT-NW
5-13
CHAPTER 6
GEOTECHNICAL
INDEX
6.1
GENERAL
6.2
APPLICABLE PUBLICATIONS
6.2.1 ASTM Specifications
6.2.2 Government Technical Publications
6.3
6.4
6.5
6.6
6.7
FINAL
6.7.1
6.7.2
6.7.3
6.7.4
6.8
EXHIBITS
6-1 Sample, Boring Log - General Notes
6-2 Sample, Boring Log - Soil Classification Legend
6-3 Sample, Boring Log - Rock Classification Legend
6-4 Boring Log - Abbreviations
6-5 Boring Log - ENG Form 1836
6-6 Boring Log - ENG Form 1836A
6-7 Geotechnical Report Checklists
6-8 Plans and Specifications Submittal Checklist
6-9 CSV Files for Boring Log and Laboratory Test Data
6-1
CHAPTER 6
GEOTECHNICAL
6.l GENERAL
This chapter outlines the content of subsurface investigations,
geotechnical design reports, geotechnical design analyses, and
geotechnical data for inclusion in design and contract documents. A
geotechnical design report is typically identified as a Foundation
Report for projects that include structures as primary features but may
otherwise be identified as a Subsurface Investigation Report. The term
Geotechnical Report is used synonymously for both types of reports
hereinafter. The geotechnical report shall be provided to all designers
for use in design and incorporated in the various submittal stages. As
soon as possible after locations of the primary features of the project
are identified, the Geotechnical and Dam Safety Section of Mobile
District (EN-GG) shall evaluate any existing subsurface data for the
site and identify the need for subsurface investigation at the site. ENGG, or the Architect-Engineer (A-E) if included in the statement of
work, shall plan and perform such geotechnical subsurface investigation
at the project site as required, and provide to the designer a
comprehensive Geotechnical Report as early in the design as practicable
but not later than the Interim Design (50-65%) submittal. This chapter
also lists the specific requirements of the submittal stages for
geotechnical design features.
6.2 APPLICABLE PUBLICATIONS
6.2.1 American Society for Testing and Materials (ASTM) Specifications
Many of the "Guide Specifications" reference ASTM specifications. Most
of the ASTM specifications that are usually referenced by geotechnical
specifications can be found in Volume 04.08 of ASTM. Listed below are
the most frequently used ASTM specifications.
C 117-95
C 136-84
D 420-87
D 421-85
D 422-63
D 653-90a
D 698-91
6-2
D 1140-54
D 1241
D 1452-80
D 1556-90
D 1557-91
D 1586-84
D 1587-83
D 2113-83
D 2167-84
Test Method for Density and Unit Weight of Soil InPlace by the Rubber Balloon Method (1990)
D 2216-90
D 2487-90
D 2488-90
D 2922-91
D 2937-83
D 3017-78
Test Method for Moisture Content of Soil and SoilAggregate in Place by Nuclear Methods (Shallow Depth)
D 3740-88
D 4043-91
D 4044-91
D 4318-84
D 4428/4428M-91
D 4718-87
6-3
D 4829-88
D 5299-99
G 57-78
EM 1110-1-1804
Geotechnical Investigations
EM 1110-1-1-1904
Settlement Analysis
EM 1110-1-1-1905
EM 1110-1-2908
Rock Foundations
EM 1110-2-1902
Slope Stability
EM 1110-2-1906
Laboratory Testing
EM 1110-2-1913
EM 1110-2-2906
TM 5-818-1
TM 5-818-5
6-4
TM 5-818-7
TM 5-818-8
TI 800-01
Design Criteria
TI-800-03
6-5
6-6
6-7
6-8
6-9
6-10
6-11
00
00
31
00
00
00
00.10 36
16
00.15 36
00.16 36
Earthwork
Earthwork
Soil Treatment for Subterranean Termite Control
Excavation, Filling and Backfilling for Buildings
Excavation, Trenching, and Backfilling for
Utilities Systems
6-12
6-13
Sample
Boring Log General Notes
Exhibit 6-1
6-14
Sample
Boring Log - Soil Classification Legend
Exhibit 6-2
6-15
Sample
Boring Log - Rock Classification Legend
Exhibit 6-3
6-16
Sample
Boring Log - Abbreviations
6-17
Sample
Boring Log - Abbreviations
6-18
Exhibit 6-5
6-19
Exhibit 6-6
6-20
6-21
6-22
Exhibit 6-8
6-23
CSV File Requirements for Boring Log and Laboratory Test Data
1. Data Format. Comma-separated-value (CSV) file format shall be used.
CSV file format is used by many spreadsheet and database software
applications and is used for importing and exporting to and from the
Borlog and Bordbs MDL (Microstation Development Language) applications.
In CSV format files, data fields for each spreadsheet row or database
record are written to a ASCII file as a single line with text fields
separated by commas.
There may be subtle but important differences in the way double-quote
characters and embedded comma characters in CSV files are used,
interpreted, and displayed by various software. Boring log and
laboratory test data shall be provided in CSV files with the following
characteristics::
a) Text data fields including embedded comma character(s) must be
enclosed with beginning and ending double-quote characters.
b) Data fields not including embedded comma character(s) may optionally
be enclosed with beginning and ending double-quote characters, but they
are not required.
c) Data fields including embedded double-quote character(s) must include
a contiguous pair of double-quote characters for each double-quote
character in the data field.
d) Numerical data must not include embedded comma characters. For
example the numerical value 100000 must appear as either ...,100000,...
or as ...,"100000",... when viewed with Notepad. It must not appear as
...,"100,000",... .
For example illustrating text with neither an embedded comma or an
embedded double-quote, the text data "BROWN LEAN CLAY (CL)" must appear
in the CSV file when viewed with Notepad as either ...,"BROWN LEAN CLAY
(CL)",... or as ...,BROWN LEAN CLAY (CL),... .
For example illustrating text with both an embedded comma and an
embedded double-quote, the text data "TAN POORLY GRADED GRAVEL (GP), 2"
MAX." must appear in the CSV file when viewed with Notepad as ...,"TAN
POORLY GRADED GRAVEL (GP), 2"" MAX.",... .
CSV files produced with the "Save As" command (specifying CSV as file
type) in Microsoft Excel software are compatible with these
requirements. Users producing CSV files for importing data into Borlog
should verify that their software is capable of producing CSV files with
meeting these requirements or should edit the CSV file data as required
after producing it.
CSV files for boring log and laboratory testing use keywords (as defined
in following paragraphs) that describe the content of the data that
follows the keyword. By convention if the keyword ends with a colon
character, the data associated with that keyword follows in the next
data field on the same line. If the keyword does not end with a colon
character, the keyword is a column heading and data associated with that
keyword follows in the same data field on the following lines.
2. File Name Conventions and Data Content for Boring Log Data. Six
types of Borlog CSV files can be used to import boring log data into
Borlog (.bor) format files. The files should be named according to the
conventions described in paragraphs 2.1 to 2.6 so as to be able to
easily identify the data content by the file name. The first line of
Exhibit 6-9 (Continued)
6-24
each type of CSV files when viewed in Notepad (or first row in
spreadsheet) must contain heading text that matches keywords that are
defined in the Borlog application. Valid heading keywords are listed
Table 2.1 to 2.6. The keywords are not case sensitive. For keywords
with units of length (northing, easting, and various depths and
elevations), the units of length can be specified by appending to the
base keyword ",ft" or ",ft_s" for U.S. survey feet, ",ft_i" for
international feet, or ",m" for meters (for example,
...,"Easting,m","Northing,m",...). The difference between U.S. survey
feet and international feet is significant only for northing and easting
boring location coordinates. Default units if units are not appended to
the base keyword are U.S. survey feet. Data columns with invalid heading
keywords are allowed but are not imported. The data corresponding to the
keywords must be placed in columns if viewed with spreadsheet.
Each line of data in CSV files (or a row in spreadsheet) is limited to a
maximum of 511 characters. The first heading keyword of all .csv files
(at cell A1 in spreadsheet) must be Boring. The second and third
keywords (cells B1 and C1 in spreadsheet) of all .csv files except
zzznnnnn-gen.csv must be "Top_D" and "Bot_D". All other keywords are
optional and, with a few exceptions, may appear in any sequence, but
generally should appear in the sequences indicated in the following in
the interest of consistency.
Data fields for which no data is available should be left blank except
where otherwise stated.
2.1 File gen.csv (or zzznnnnn-gen.csv if Borlog project ID zzznnnnn has
been defined, where zzz is a 3-character zone abbreviation and nnnnn is
a zero-filled 5-digit sequential number for subsurface investigations in
that zone) should contain data that is general; i.e., it contains
information about the boring that is not specific to any particular
depth, sample, or stratum. It should include the data with keyword
headings listed in Table 1.
If mm/dd/yy or mm-dd-yy formats are used for dates in the Date_Start and
Date_Compl data fields, years between 50 and 99 inclusive are assumed by
Borlog to be between 1950 and 1999 and years between 0 and 49 inclusive
are assumed to be between 2000 and 2049. Use of mm/dd/yyyy format is
recommended for dates to avoid any possibility of misinterpretation.
Depth zero is usually assumed to be at ground surface level at the
boring location; However, any depth datum may be used provided that the
same datum is consistently used for all depths recorded for the boring.
Levels below depth zero should be entered as positive depth values and
levels above depth zero should be entered as negative depth values.
Table 1: Borlog Heading Keywords, Descriptions and Variable Types for
Gen.csv File:
Boring - boring name, 12-character max. text
Easting - easting coordinate at boring location, numeric
Northing - northing coordinate at boring location, numeric
GS_E - ground surface elevation at boring location, numeric
GS_D - ground surface depth at boring location (usually zero), numeric
BOH_D - bottom of hole depth, numeric
GW_DI - initial groundwater depth, numeric (same as GW_DF if only one
reading made)
GW_DF - final groundwater depth, numeric
Exhibit 6-9 (Continued)
6-25
6-26
6-27
6-28
6-29
6-30
"Size,mm",Value,,,,,,,,,,,
.0031,69.6,,,,,,,,,,,,,,
.0043,38.4,,,,,,,,,,,,,,
3.3 Consolidation Tests. File T03.csv shall contain general and sample
identification data using keywords defined in Tables 7 and 8
respectively, and test data for consolidation tests. Keywords
specifically for consolidation tests include Initial void ratio: and
column heading keywords Load,tsf and Void Ratio. An example file
that includes both loading and unloading is shown below:
;Example CSV file for Consolidation Test
Organization:, USACE ERDC
Client:,USACE Mobile District
Project:,Fire Crash Station
Project Location:,"MacDill AFB, Florida"
Started:,11/07/2002
Completed:,11/21/2002
,,
Test Type:,Consolidation
Boring:,DF-1-02
Top_D:, 16.5
Bot_D:, 18.8
Sample:,TUBE 1
Initial void ratio:,1.20
,,
Load,tsf, Void Ratio
0.1,1.150
0.25,1.124
0.5,1.072
1,0.990
2,0.910
4,0.826
8,0.740
16,0.656
32,0.578
60,0.499
16,0.516
4,0.560
1,0.616
0.25,0.67
0.1,0.684
6-31
CHAPTER 7
LANDSCAPING, IRRIGATION, PLANTING AND TURFING
INDEX
7.1
GENERAL
7.1.1 Scope
7.2
APPLICABLE PUBLICATIONS
7.3
7.4
7.5
INTERM
7.5.1
7.5.2
7.5.3
7.6
7.7
7.8
TECHNICAL REQUIREMENTS
7.8.l Design Criteria
7.8.2 Site Investigation
7.8.3 Coordination
DESIGN (50-65%)
Design Analysis
Drawings
Specifications
7-1
CHAPTER 7
GENERAL
7.1.1
Scope
APPLICABLE PUBLICATIONS
Design Criteria
7.3
UFC 3-210-05FA
UFC 4-010-01
The project definition shall verify the minimum design requirements for the
work being performed in the landscape and irrigation plans. Specific
boundaries, limits of the work being performed, shall be delineated to
anticipate the level of development of the landscape and irrigation plans.
Each plan will in turn be used to determine a preliminary cost estimate for
the project. Specific use areas shall be located to determine the proper
landscape treatment for those areas, from both the standpoint of material
selection and functional use e.g. screening, canopy, color, enclosure etc.
and/or turf, it shall also be communicated in the project definition.
7.4
7.4.1
Design Analysis
proposed development and the rationale for proposed plant locations shall be
indicated. For the irrigation system, if applicable, the designers shall
determine whether irrigation water will be supplied via potable water,
shallow well, or grey water source, and describe the materials to be used in
the irrigation piping system, and the type of irrigation heads to be used in
various locations. The narrative shall also include a list of suggested
types and sizes of plant materials, which are to be used, based upon the
designated functional and visual criteria, and installation specific
planting lists. The concept cost estimate for landscaping, planting, and
turfing shall be based on quantities derived from generalized locations and
listed types and sizes of plant materials.
(b) The concept cost estimate for the landscape irrigation system
shall be coordinated with the conceptual landscaping, planting, and turfing
plan in order to estimate the type and quantity of irrigation heads and zone
control valves to be used, as well as estimated irrigation pipe sizes and
their linear feet of length, type of irrigation controller, and other system
appurtenances.
7.4.2
Drawings
The overall design approach shall depict factors, which affect existing site
features and influence subsequent design proposals. The concept drawings
shall be prepared at a scale, which corresponds with the site layout and
grading plans, and shall include reference coordinates, north arrows,
graphic scales, and appropriate legends.
7.5
7.5.1
Design Analysis
Drawings
(a) The interim design submittal shall expand the concept design by
development of an overall planting layout and shall include enlarged detail
plans of specific areas, as needed, to clarify requirements. The proposed
layout shall indicate shade trees, evergreen trees, flowering trees, shrub
masses, etc., according to designated functional and visual locations of
planting. A legend indicating sizes of plants recommended for each of the
above categories shall be included. The preliminary design drawings and all
subsequent plans shall indicate existing and proposed buildings, paved
areas, signs, light standards, transformers, dumpster areas, storm drainage
system, and other structures and utilities. If existing and proposed
contours cannot be clearly indicated graphically on the plan, overlay of the
drawings shall reveal that grades and elevations have been taken into
account. Grassing limits, seeded or sodded, shall be clearly described in
the contract documents.
(b) Irrigation systems are typically included in projects as a
performance specification with the actual design being performed by the
contractor. Therefore, irrigation system plans should clearly delineate all
required design information such as the limits of area to be irrigated;
zones where specific types of spray heads or bubblers are to be used;
locations for equipment such as for controllers, wells, tanks, etc., as
applicable; protective casings under pavements to facilitate installation
and/or future expansion; locations of existing piping and sprinkler heads
7-3
Specifications
7.6.1
Design Analysis
Specifications
Drawings
7-4
All final design drawings, specifications, and the design analysis and cost
estimate shall have incorporated comments from the preceding review before
submittal as Ready-to-Advertise.
7.8
TECHNICAL REQUIREMENTS
7.8.1
(a)
Design Criteria
Designer Qualifications
7-5
plants, shrubs, and grassing within the design boundaries. The system shall
be divided into zones and be automatically controlled. The sprinkler heads,
laterals, control valves, and other related irrigation system appurtenances
shall be in accordance with the requirements contained within this landscape
irrigation performance specification. Sprinkler performance such as
operating pressure, radius of throw, etc., shall be chosen as best fitted
for the intended area to be irrigated. Provide the sprinkler system as a
complete unit produced by a single acceptable manufacturer for all major
components including sprinkler heads, valves, controller, and other
accessories.
7.8.2
Site Investigation
Coordination
7-6
CHAPTER 8
WATER, WASTEWATER AND ENVIRONMENTAL PROTECTION
INDEX
8.1
GENERAL
8.1.1 Water Supply Systems
8.1.2 Wastewater Systems
8.1.3 National Environmental Protection Act (NEPA) Documentation
8.2
APPLICABLE PUBLICATIONS
8.3
8.4
8.5
8.6
8.7
8.8
TECHNICAL REQUIREMENTS
8.8.1 Standard Systems Criteria
8.8.2 Supplemental Design Criteria
EXHIBIT
8-1 Sample Environmental Permit Contact Sheet
8-1
CHAPTER 8
GENERAL
Wastewater Systems
In the event that the Government has prepared any NEPA Documentation,
i.e. Environmental Impact Statement (EIS), Environmental Assessment
(EA), or a Findings of No Significant Impact (FONSI), the designer shall
prepare the design so that it is entirely compatible with any and all
requirements of that NEPA Documentation.
8.2
APPLICABLE PUBLICATIONS
Unified Facilities Criteria (UFC)
UFC 3-230-02
UFC 3-230-03A
Water Supply
UFC 3-230-04A
Water Distribution
8-2
UFC 3-230-07A
UFC 3-230-08A
UFC 3-230-09A
UFC 3-230-10A
UFC 3-230-11A
UFC 3-230-12A
Water Desalination
UFC 3-230-13A
UFC 3-230-19N
UFC 3-240-02N
UFC 3-240-03N
UFC 3-240-04N
Wastewater Collection
UFC 3-240-06N
UFC 3-240-07FA
UFC 3-240-08FA
UFC 3-240-09FA
UFC 3-600-01
Design Criteria
TI 814-01
Water Supply
TI 814-03
Water Distribution
TI 814-10
Wastewater Collection
TM 5-809-10
TM 5-810-5
Plumbing
TM 5-8l3-l
TM 5-8l3-3
TM 5-8l3-4
TM 5-813-5
8-3
TM 5-8l3-7
TM 5-813-8
Water Desalination
TM 5-8l3-9
TL 1110-3-446
TL 1110-3-465
TL 1110-3-481
TL 1110-3-484
TL 1110-3-485
EM 11102-503
Wastewater Collection
TM 5-8l4-1
TM 5-8l4-2
TM 5-8l4-3
TM 5-8l4-5
Sanitary Landfill
TM 5-8l4-7
TM 5-8l4-8
TM 5-814-9
TL 1110-3-466
TL 1110-3-469
EM 1110-1-501
EM 11102-501
Military Handbook
MIL-HDBK-1005/7A
MIL-HDBK 1005/16
8-4
Handbook
MIL-HDBK 1005/17
NFPA 20
NFPA 22
NFPA 24
NFPA 291
NFPA 409
MOP 7
MOP 8
MOP FD-12
AWWA
8-5
Design Analysis
The narrative shall define the source of water for potable use and fire
protection. The narrative shall also describe any pretreatment,
treatment, and methods of wastewater disposal from the new facility.
8.3.2
The water and sanitary site plan shall show all existing water lines and
sanitary sewers. The new water lines for building service and fire flow
shall be shown from the point of connection to the existing water
distribution system. All necessary valves, fire hydrants, ground
storage tanks, pump stations, etc. shall be indicated. Building
connections for wastewater shall be shown from the building to the
existing sanitary sewer system or onsite treatment system. All
necessary septic tanks, grease traps, oil/water separators, treatment
plants, manholes, lift stations, force mains, etc. shall be shown. All
pipe sizes shall be indicated. At this stage or earlier, the designer
shall request a fire flow test(s) specifying exact hydrant locations
required to flow and where residual pressure is to be measured. Request
shall be furnished to COE project manager.
8.4
8.4.1
Design Analysis
Base all new designs on the most economical plan consistent with the
applicable criteria; i.e., Army Technical Manuals, Air Force Manuals,
etc. Include in the design analysis any assumptions made or source of
information if not included in manuals, guides, or instructions. The
design analysis shall be sufficiently complete to clearly show project
requirements and utility support capacity. Prepare outline
specifications as directed in Chapter 3, SPECIFICATIONS.
8.4.1.1
The source of the potable water supply for domestic and industrial use
and fire flow demand shall be identified in this submittal. If lawn
irrigation is required, the source of water for the irrigation system
shall also be identified in this submittal. Provide calculations
indicating available supply and pressure versus required supply and
pressure. If a pump, water storage tank, or any other peripheral
equipment is required, provide calculations to support the selected pump
size, storage tank volume, and sizes of peripheral equipment.
Individuals experienced in fire protection systems must accomplish
design of fire pumping stations. The designer shall determine in this
submittal whether a fire pump station with or without a ground storage
reservoir is required.
8.4.1.2
Service Lines
Service lines are the water lines connecting building piping to water
distribution lines. The analysis for service lines shall show service
line size, domestic demand, velocity and pressure drop between the water
distribution line and building.
8.4.1.3
8-6
Sanitary Sewers
New gravity sanitary sewers will be sized in this submittal. The design
analysis shall show wastewater flows, velocities, pipe sizes,
elevations, and pipe capacities. Where new sewage collection systems
are to be connected to the existing system, the existing sewage
collection system shall be checked to determine whether it has adequate
capacity for the additional flow. If the existing system does not have
sufficient capacity, it shall be revised to handle the increased flow.
The design analysis shall contain a narrative description with all
necessary calculations for new wastewater lift stations and force mains
showing flows, velocities, component capacities, head requirements,
detention periods, etc. The design analysis shall be prepared in
accordance with TI 814-10. A design analysis is required for onsite
sewage treatment and disposal systems (e.g. septic tank and tile field).
The feasibility of an onsite sewage treatment and disposal system where
buildings are remotely located and it is not economically possible to
connect to an existing wastewater collection system shall be determined.
Coordination shall be made with the appropriate county sanitarian to
determine soil percolation rates to use for sizing the tile fields.
Permits for septic tank and tile fields are not generally required for
Federal projects, but the criteria established by the local sanitary
authorities is typically employed unless an appropriate justification
can be cited.
8.4.1.5
Building Connections
Lift Station
Calculate the average and peak loadings for individual unit processes
including hydraulic, organic, solids, etc. Provide detailed
8-7
Drawings
The water and sanitary site plan shall be adequately detailed to show
new work and connections to the existing water distribution system and
wastewater collection system. The proposed designs shall include
sufficient details to obtain adequate concept cost estimates for all
items such as lift stations, septic tanks, oil separators, etc. The
invert elevations of all new and existing sanitary sewer lines and the
top and invert elevations of all new and existing manholes shall be
shown on concept plans. The water and sanitary site plans shall be on a
minimum scale of l" = 30'. The designer shall provide any additional
drawings other than those listed above which he considers necessary to
show the intent of design.
8.4.3
Environmental Permitting
The Interim Design Analysis shall include all items in the Concept
Design Analysis and any necessary updates or revisions. Provide
catalogue cuts, pump curves, and any other manufacturers information on
selected equipment.
8.5.2
Drawings
Water Supply
8-8
8.5.2.3
Provide a site plan showing all existing and new valves, fire hydrants,
manholes, pumping stations, laterals, meters, etc. Include sizes of all
water lines, sanitary sewers, and force mains. Invert and rim
elevations are required for all manholes. Provide profiles of gravity
sewers. Double lines are required for profile piping. Provide details
for connecting new lines to existing systems.
8.5.3
Specifications
8.6.1
Design Analysis
Drawings
8-9
Specifications
Environmental Protection
All final design drawings, specifications, and the design analysis and
cost estimate will have incorporated comments from the preceding reviews
before submittal as Ready-To-Advertise.
8-10
8.8
TECHNICAL REQUIREMENTS
8.8.1
8.8.1.1
Building Services
(a) Water Service Lines. Provide exterior water service line to all
new buildings from existing and/or new water distribution systems. Size
building water service line to meet the peak building demand as required
in the IPC. The pressure drop through the service line will not exceed
l0 psi or a velocity of 8 feet per second at the peak building demand.
Provide a gate valve or service stop near the connection point to the
distribution system. The designer shall insure that all state and local
cross connection requirements have been incorporated into the design.
(b) Building Connections (Sanitary). Building connections will be of
either the gravity type or the force main type as required by the
building site conditions. Gravity type sanitary sewers are preferable,
if feasible, and will be constructed of 6-inch minimum size pipe on an
appropriate slope to achieve a velocity (or equivalent) cleansing
velocity of two (2) feet per second. Where gravity type building
connections to a sanitary collection system are not possible, provide
pneumatic ejectors or sewage pumps in the building or a lift station
outside the building. The selection of pumps or ejectors will be based
on the economy of initial installation. A design analysis of gravity
sanitary sewers for building connections is not required if the same
slope for the building plumbing can be maintained to the street sewer.
However, if the slope cannot be maintained an analysis demonstrating
maximum achievable velocity during peak flow must be provided with the
proposed slope. Pipe diameter and slope must be shown on the drawings.
Duplex units will be provided where ejectors or pumps are required. The
capacity of each unit will be sufficient to handle the peak rates of
flow. Other design characteristics will conform to TI 814-10.
8.8.1.2
Fire Protection
8-11
less than 25 feet nor more than 50 feet from the face of the building,
which they are to serve. They may be of either the post indicator type,
or the rising stem and yoke type installed in a pit, as dictated by the
proposed construction provided for that area. Use post indicator valves
generally in grassed areas, and use the rising outside stem and yoke
type installed in underground pits in paved areas. Fire pumping
stations shall comply with UFC 3-600-01 and NFPA Codes 20, 24, and 409,
as appropriate, and shall be designed by persons experienced in design
of fire protection systems. The design of a fire pump or series of fire
pumps shall not exceed 1500 GPM each without approval of the Corps of
Engineers. Provide standby fire pumps where required by NFPA 409.
8.8.1.3
(a) Gravity Sewers. Where more than one building is involved, use
gravity sewers. Design is to conform to the applicable requirements of
TI 814-10. Size gravity sewers to discharge the expected peak rate of
flow. Design pipes to run not more than 80% full, except that
regardless of the design quantities, the minimum size of gravity sewers
is 8 inches. Gravity sewers shall normally be laid on a sufficient
slope to provide a velocity of at least 2.5 feet per second when the
pipe is flowing full and 2.0 feet per second at the average rate of
flow. Locate gravity sewers by the topography of the site to minimize
excavation.
(b) Force Mains and Sewage Lift Stations. Where more than one
building is involved, if gravity type sewers cannot be provided, sewage
pumps shall be installed in a sewage lift station constructed on the
lowest terrain in the vicinity. Since force mains do not require a
specific grade for satisfactory operation, they shall be constructed as
straight, short, and shallow as possible. Routings for force mains
shall generally follow existing right-of ways, roads, or utility
corridors. In the Mobile District, force mains are generally installed
a minimum of 30 inches below final grade. Force mains and sewage lift
stations shall conform to the applicable requirements of TI 814-10. The
capacity of the lift station shall be sufficient to handle peak rates of
sewage flow, determined in accordance with TI 814-10. Sewage pumps must
be designed to meet actual head conditions of the force main provided
for the lift station. The design point on the pump characteristic curve
shall be justified by plotting this curve against the system
head-capacity curve. The system head curve shall be obtained by
plotting the static lift plus the friction head at various flow rates.
Where pumps operate in parallel or series, combined curves shall be
provided. Intersection of characteristic curve with system head curve
shall be the design operating point. Where appropriate, grinder-type
pumps shall be considered.
(c) Septic Tank and Tile Field. Design septic tanks and tile fields
in accordance with Manual of Septic Tank Practice and applicable state
criteria. When state criteria is not relevant, then use design manual
EPA 625/1-80-012. Prefabricated septic tanks approved by the state or
local authority may be used providing the minimum wall thickness is 4
inches and calculations are provided for structural soundness.
(d) Oil/Water Separators. Oil/water separators shall be provided for
process wastewaters in accordance with ETL 1110-3-466 for Army projects
and as required by state and local regulators for Air Force projects.
Separators shall be of the prefabricated type or built in place.
Oil/water separators shall be designed to meet the effluent requirements
for pretreatment by the EPA and/or applicable State Agency. The effluent
from the oil/water separator shall be routed to a sanitary sewer or an
8-12
Treatment Plants
Seismic Provision
Fire protection using AFFF Systems shall comply with the requirements of
ETL 1110-3-481. Provide a means for containment of and disposal of AFFF
foam solution runoff through coordination with Government personnel and
the local environmental regulatory authority. Containment and disposal
must meet the requirements of the applicable State Agency, and shall be
a part of permitting requirements. Other options that can be approved
by the installation and state regulatory agencies should be presented as
economic alternatives before the 30% design is finalized.
8.8.2
8.8.2.1
(a) Water wells shall conform to AWWA Standard A-100; TI 814-01 and
applicable State Public Health Department criteria for public water
supplies. Specification for water wells shall be based current UFGS
specification provided.
(b) The designer through the Mobile District geologist (CESAM-EN-GG)
shall coordinate design of water wells.
(c) Vertical turbine pumps larger than 5 hp shall conform to AWWA
E-101 and the appropriate UFGS.
(d) Design of water treatment plants shall conform to TI 814-02 and
Mil-Handbooks as appropriate and any applicable State criteria for
public water supplies; and as a minimum the Recommended Standards for
Water Works (Ten States' Standards).
(e) Small isolated facilities shall utilize a hydro-pneumatic
pressure tank and, if appropriate, a ground storage reservoir as
discussed below. Small systems shall normally be located in a
protective building. Where permitted by the State, pitless well
adapters may be used. Use of well pits is prohibited.
8-13
(f) Supply and distribution piping shall comply with TI 814-03 and
appropriate UFCs and UFGS. Piping materials shall be based on UFGS
unless technical considerations require other methods.
(g) Water storage designs shall comply with UFC 3-600-01, TI 814-01,
and AWWA D100. Specifications shall be based on the appropriate UFGS.
(h) Hydraulic analyses shall normally be made using a value of C =
100 for the roughness co-efficient; however, consideration should be
given to the use of coefficients greater than 100 when specifying
concrete or plastic pipe. Changes in coefficients from new pipe to an
aged pipe should be considered to insure that excessive velocities are
not generated in new piping by using only coefficients for aged pipe.
(i) Fire hydrant branches shall not be less than 6 inches in
diameter, shall be as short in length as possible, and shall have a gate
valve and box.
(j) Locate water lines at least l0 feet horizontally from a sewer or
drain line. When required, a minimum horizontal separation of 6 feet
can be allowed, but the bottom of the water line must be at least 12
inches above the top of the sewer pipe, unless state regulations require
a more strict limitation.
(k) Where water lines must cross sewers they shall conform to the
requirements of TM 5-813-5, UFGS Guide Specifications for water lines,
and applicable state criteria.
(l) Water lines crossing railroads shall be installed in protective
casings conforming to the requirements of American Railway Engineering
Association (AREA), Volume 1. Design should specify method of
construction for each particular site (i.e., ut vs. jacking). The
designer shall obtain permits from the railroad authority, as required.
Permit application procedure and submittal should occur as soon as
practicable.
(m) Water lines located in airfield pavement shall conform to the
requirements of TM 5-813-5.
(n) Control valves shall be provided on distribution systems in
accordance with TM 5-813-5.
(o) Air release and vacuum relief valves shall be provided in
accordance with the requirements of TM 5-813-5.
(p) Fire hydrants shall be provided in accordance with the
requirements of TM 5-813-5;; NFPA 24, Outside Piping; and UFC 3-600-01.
Hydrants should not be located closer than 25 feet to a building and
should be located not more than 7 feet nor less than 6 feet from the
edge of a paved roadway surface. Residual pressures at fire hydrants
shall not be less than 20 psi when flowing at the desired rate.
(q) Thrust blocking shall be provided in accordance with TM 5-813-5;
ETL 1110-3-446 Revision of Thrust Block Criteria in TM 5-813-5, Appendix
C, and the UFGS water lines specification.
(r) Where the base distribution system is unable to provide the fire
flow demand at the required residual pressure, the designer shall
analyze the existing distribution system and provide pumping equipment
and ground storage tanks, if necessary. A complete design analysis is
required, including fire flow test data. Pumping stations shall conform
8-14
8-15
High-Water Level
(% of Total Tank
Capacity)
20-40
30-50
40-60
50-70
60-80
43
38
34
32
28
Withdrawal
(% of Total
Tank Capacity
33
28
24
22
18
8-16
400'
600'
(7)
8-17
inches.
used.
(2) Minimum size force mains where nonclog pumps are used is 4
Smaller pipe sizes can be considered when grinder pumps are
cover.
(5)
(6)
(7)
(8)
8-18
(3) Pump(s) trip in a single run mode and a multiple pump trip
with all pumps tripping at the same instance.
(4) Pump(s) start and stop at intermediate design flow; e.g.,
35 to 50 percent.
(5) Analysis of all pressure relief or reduction elements such
as air chambers, surge relief valves, by-pass, etc.
(6) All assumptions used to model the system shall be clearly
explained. In addition, any physical phenomenon anticipated to occur
shall be described so that Base operations personnel can be made fully
aware of these phenomenons and take any appropriate actions required.
8-19
SUBJECT:
PERMIT REQUIRED:
APPROVING AGENCY:
Permit to Construct
Central Florida District, FDER
(P.O.C.) Denise Judy or alt. Lee Miller
PROCESSING:
*30 days to review plus public notice period plus any time needed to
incorporate FDER changes*
SPECIAL REQUIREMENTS: Controls for this facility are TSS 20 mg/L, BOD
20 mg/L, and N-NO3 12 mg/L. Construction permit good for up to 6 months
after construction is finished. Can be extended during construction if
time expires for $50 per extension, up to 5 years.
Systems operating manual is required (Note: FDER says these
are usually disappointing, because they are normally only O &
and not process controlbut have allowed it to suffice). The
manual is required to be ready within the 6-month period that
construction permit is used to operate the plant.
manuals
M manuals
systems
the
EXHIBIT 8-1
8-20
CHAPTER 9
ARCHITECTURE
INDEX
9.1
GENERAL
9.1.1 Scope
9.1.2 Architectural Quality
9.2
APPLICABLE PUBLICATIONS
9.2.1 Building Code Compliance
9.2.2 Functional Criteria
9.2.3 Community Criteria
9.3
9.4
9.5
9.6
9.7
9.8
TECHNICAL REQUIREMENTS
9.8.1 Coordination
9.8.2 Site Work
9.8.3 Masonry
9.8.4 Miscellaneous Metals
9.8.5 Thermal and Moisture Protection
9.8.6 Roof Systems
9.8.7 Doors
9.8.8 Windows
9.8.9 Finishes
9.8.10 Equipment
9.8.11 Rooms and Spaces for Utilities
9.8.12 Floor Drains and Slopes
9-1
CHAPTER 9
ARCHITECTURE
9.1
GENERAL
9.1.1
Scope
Architectural Quality
APPLICABLE PUBLICATIONS
9-2
During this phase the designer must define the customer's requirements
and confirm that they can be met within the project's constraints. To
that end, a comprehensive interface with the customer is required
generally through a charrette or other previously approved data
gathering process. The primary purpose of the design process at this
stage is to gather any information from the customer that would be
necessary in the design of the facility.
9.3.1
Narrative
9.3.1.1
Provide a summary of the Basis of Design including, but not limited to,
the following:
a. State the building construction type and occupancy
classification appropriate to the model code(s) in use.
b.
c.
d.
e.
design.
Criteria
9-3
List the functional and technical criteria used to guide the design
work.
9.3.1.4
The designer shall state the assumptions and rationale behind all major
facility design decisions including, but not limited to, discussions of
the following:
a.
area.
c.
d.
b.
c.
Fenestration.
d.
Roof systems.
e.
f.
g.
Ceiling systems.
h.
Floor systems.
i.
9-4
j.
Drawings
This submittal consists of one or more single line schematic floor plans
which effectively indicate to the using agency that the function,
circulation, and life safety issues have been assessed and can be met by
the proposed design. At least one major elevation (preferably the front
elevation) for each submitted building is required. A site plan is
required to indicate the building orientation and circulation to the
building entrances. The site plan shall be coordinated with the
requirements of Chapter 4, titled SITE DEVELOPMENT.
9.4
9.4.1
General Considerations
Design Analysis
Drawings
9.4.3.1
When the main floor plans must be drawn in segments in order to comply
with the requirements for scale and sheet size, provide a composite
floor plan for each floor level. These plans shall show the following:
9-5
d.
Floor Plans
B.
c.
d.
level.
e.
f.
i.
j.
9.4.3.3
Roof Plan
b.
c.
d.
9-6
e.
f.
g.
9.4.3.4
Demolition Plans
Building Elevations
b.
Building masses.
b.
Structural system.
c.
d.
Finish ceilings.
e.
f.
Floor elevations.
g.
h.
Adjacent grades.
9-7
9.4.3.7
Structural system.
b.
c.
Ceiling systems.
d.
e.
Floor elevations.
f.
g.
9.4.3.8
Finish Schedules
Details
Type of occupancy.
b.
Type of construction.
c.
Fire/smoke compartments.
d.
e.
f.
Door labels.
g.
h.
k.
Exit lights.
9-8
9.4.4
Specifications
9.5.1
Design Analysis
The Design Analysis shall include all items in the Concept Design
Analysis narrative and any revisions made necessary by comments about
the Concept Design submittal. In addition verify site and building
signage requirements. See Chapter 10, INTERIOR DESIGN for interior
signage requirements.
9.5.2
Drawings
Building Plans
Schedules
Specifications
9-9
9.6
9.6.1
Design Analysis
The Final Design analysis narrative shall include all items in the
Interim Design analysis narrative and any revisions made necessary by
comments about the Interim Design submittal.
9.6.2
Drawings
Specifications
TECHNICAL REQUIREMENTS
Coordination
9-10
Site Work
9.8.2.1
Access to Entrances
Masonry
Concrete masonry units (CMU) for interior masonry walls and partitions
shall be not less than 6 inches in nominal thickness.
9.8.3.2
Where split face or fluted units are used, provide smooth face units
where concrete paving or flashing occurs, and where items are attached
to, or penetrate CMU wall surfaces.
9.8.3.3
Coursing
9-11
9.8.4
Miscellaneous Metals
9.8.5.1
Insulation
Vapor Barrier
Moisture Barrier
Roof Systems
9-12
(c) Vented ridge caps are not desirable due to potential leaks.
(d) Concealed, mechanically formed seams are preferred. Install
with fasteners permitting expansion/ contraction attached to the
structural deck (when present) through rigid insulation (when present)
or locking type seams (as opposed to snaplock type) for hurricane and
high wind areas.
(e) An independent roofing consultant shall be hired by the
roofing subcontractor for roofs over 10,000 square feet. The consultant
shall review and approve roofing shop drawings prior to submittal to the
government. The consultant shall be present to monitor the entire roof
installation. The consultant shall be certified by the roofing
manufacturer.
(f) Ensure that pressure treated wood blocking is designed and
shown in the drawings at roof edges.
(g) Roof penetration flashing, curbs, gutters, and flashing shall
be the product of the roofing manufacturer.
(h) All laps shall be in the direction of water flow.
(i) Full length, job fabricated panels are recommended.
Individual roof panels less than 50 feet in length with joints are not
permitted.
(j) Ensure that roof penetrations occur in the center of
individual roof panels rather than at edges.
(k) Roof edge gutters shall be installed with gutter hangars, and
shall not be attached directly to the roof membrane or fascia. The
front edge of the gutter shall be below the back edge at least 1 inch
below the roof edge
(l) If fascia and/or soffit panels are to match the roof system
color, ensure that different manufacturers provide matching colors.
Roof panels are not acceptable as fascia.
(m) Where rigid insulation is installed, ensure that its
compressive strength is compatible with the standing seam metal roof
system as recommended by the manufacturer.
9.8.6.2
Other Roofs
For other roof types comply with the National Roofing Contractors
Association standards.
9.8.6.3
Sheet Metal
In all cases sheet metal for various elements used throughout a building
shall be of the same basic metal. Atmospheric conditions shall be
considered in the selection of exposed sheet metal. Different types of
sheet metal that can cause accelerated corrosion (galvanic action) of
either one shall not be placed in direct contact. Sheet metal used on
roofs with concrete roof tiles shall not react with nor corrode
excessively due to the concrete.
9.8.6.4
9-13
When downspouts are required they shall not drain directly onto a walk
or platform. When downspouts must occur at walks or platforms they
shall pass through or under into underground drains or toward open
ground beyond. Downspouts draining onto open ground shall be diverted
using precast concrete splash blocks to prevent erosion. Use of
interior downspouts shall be avoided wherever design permits. The use
of scuppers should be maximized. Avoid built-in gutters behind fascia
or parapet due to expansion/contraction of metal and surrounding
material unless dictated by Installation requirements. All gutters
shall have leaf screens at locations susceptible to collection of leaves
and other wind blown debris.
9.8.7
Doors
Pedestrian Doors
Doors to Rooms
Exterior Doors
Special-Purpose Doors
Finish Hardware
(a) Carefully read the "Notes to Specifier" for the UFGS hardware
specification. Hardware shall be selected from BHMA and ANSI standards.
All cylinders shall have 7 pins. Provision of these items must conform
to individual requirements of the installation on which the project is
located.
(b) Floor mounted center door stops for door pairs shall not be
installed above floor level.
9-14
9.8.7.6
Return Air
Windows
(a) Window schedules and types shall be indicated in the drawings.
(b) Ensure that window types and locations are coordinated with
furniture placement to avoid blocking views.
9.8.9
Finishes
9.8.9.1
Ceramic Tile
Chair Rails
In rooms with movable furniture, ensure that chair rails are installed
at appropriate heights to protect wall finish.
9.8.9.5
Paint
Equipment
9-15
Floor drains and slopes, hose bibbs, and shower heads shall be shown on
the architectural drawings as well as on mechanical drawings, and shall
be closely coordinated. All floors in areas requiring drains shall be
sloped toward the drains.
9-16
CHAPTER 10
INTERIOR DESIGN
INDEX
10.1
GENERAL
10.1.1 Scope
10.1.2 Overview
10.1.3 Furniture, Fixtures and Equipment (FFE) Procurement
Criteria Review
10.1.4 Reviews and Revisions of Interior Design Projects
10.2
10.3
10.4
10.5
10.6
10-1
10.7
FURNITURE SYSTEMS
10.7.1 Furniture System Requirements During the Design Phase
10.7.2 Furniture Systems Requirements During the Construction
Phase
10.7.3 Editing FFE MS Excel Furniture Systems Workbook
10.7.4 Workstation Finish Sample Boards
10.7.5 Workstation Location Codes
10.7.6 Editing the MS Excel Manufacturer Worksheet
10.7.7 Editing Fabric and Finish Worksheet
10.7.8 Editing Typical Workstation Worksheets
10.7.9 Editing UFGS Section 12 50 00, Furniture Systems
10.8
10.9
10.10
10.11
EXHIBITS
10-1a
10-1b
10-1c
10-2a
10-2b
10-2c
10-2d
10-2e
10-2f
10-3a
10-3b
10-3c
10-4a
10-4b
10-4c
10-4d
10-4e
10-4f
10-4g
10-4h
10-5a
10-5b
10-6a
10-7a
10-8a
10-10a
10-11a
10-12
10-2
CHAPTER 10
INTERIOR DESIGN
10.1
GENERAL
10.1.1
Scope
Overview
The Mobile District has two categories for interior design services and
two primary project delivery processes to solicit for the design,
construction and outfitting of facilities. Exhibit 10-1a describes the
two categories for interior design services. Exhibit 10-1b describes the
two project delivery processes. The percentage level of design criteria
and presentation information for building related and furniture related
submittals vary within each project delivery process. However, 100%
building related and furniture related interior designs shall be
accomplished at the end of the project delivery process regardless of
which type of solicitation is used.
The most recent editions of references or publications at Project
Solicitation Issue Date (Advertise Date) will be referenced and
incorporated (as appropriate) in work prescribed by this manual.
10-3
Exhibit
10-1a
SID
FFE
Exhibit
10-1b
PPTO
D-B RFP
10-4
D-B contract. During the design phase after award of the D-B
contract, the D-B Contractor's interior design source will
respond to the D-B RFP SID/FFE instructions provided in Sections
01 10 10 and 01 10 12. When the design phase of the project is
complete, 100% SID/FFE submittals will be completed as well.
Reference Chapter 22 for specific instructions.
10.1.3
Review
Exhibit 10-1c
Review Questions
Attendees
10.1.4
10-5
Hard copy deliverables for both SID/FFE projects will use the same
presentation format for binders and color boards. The SID/FFE binders
become the book set envelope. The binders will hold the hard copy
SID/FFE color Boards and the digital project data (CD-ROM). Do not merge
the SID and FFE color samples together on the same board. Building related
finishes are packaged separately and stand alone from furniture related
finishes. Requirements for SID/FFE binders and color boards are shown in
Exhibits 10-2a and 10-2b.
Exhibit 10-2a
Size
Features
Project
Identification
10-6
Exhibit 10-2b
Size
Header
Footer
Samples
Photos of
Samples
10.2.2
Drawing
Standards
SID
Specifications
Specifications
Standards
10-7
10-8
Exhibit 10-2d
FFE
Composite
Furniture
Placement
Drawings
FFE
Specifications
10.2.3
10-9
The digital FFE data used to create the "electronic FFE binder" shall be
organized in a file structure to differentiate between Portable Document
Files (Adobe PDF), CADD files, and MS Excel files. The Master Adobe PDF
Folders can be linked together to facilitate easy viewing between Adobe
PDF SID electronic data submitted and coordinated through EN-DW and will
not appear in the FFE CD-ROM. The FFE file structure shall be as follows:
Exhibit 10-2e Final Electronic FFE Binder Folder/File Structure
PROJECT FOLDER
#1
FFE-PDF
#2
PLANS-PDF
#3
Color Boards
#4
MS Excel
Adobe PDF Read Only Image of the Hard Copy Color Boards.
Submitted @ Final Design
#5
CADD DRAWINGS
10.2.4
SID and FFE digital deliverables are to be developed and viewed using five
(5) computer software programs with no exceptions. The five software
programs relate to: (1) CADD drawings, (2) Unified Facility Guide
Specifications (UFGS), (3) FFE procurement data (other than drawings), (4)
viewing the SID/FFE Record Copy and (5) writing the digital data to CDs.
10-10
2.
UFGS
3.
FFE Procurement
Ordering data
(Other than
drawings)
4.
SID/FFE
Record Copy
Software Requirements
SID/FFE working CADD drawings shall be developed in
the latest version of AutoCAD (.dwg) or Microstation
(.dgn). Customer requirements will dictate which
software version to use. AutoCAD is the preferred
CADD program for developing FFE (furniture related)
drawings.
SID specifications will be edited using SpecsIntact
software. Contact the office of EN-DW to obtain
project specific software programs available for
downloading.
FFE Procurement Ordering data shall be developed in
the latest version of MS Excel (.xls). The required
18 editable working files are ready for copy and
downloading on the Mobile District Public FTP web
site. The Website address is
ftp://ftp.sam.usace.army.mil/pub. Open the folder
marked "INTERIOR DESIGN" for the editable FFE .xls
files and copy to your hard drive.
The SID/FFE digital record copy shall be developed and
viewed in the latest version of Adobe Acrobat
Read/Write portable document format (Adobe PDF).
Working CADD drawings are to be "printed" in black and
white (no color output) Adobe PDF format.
FFE MS Excel.xls files are to be "printed" in the
Adobe PDF format.
5.
CD's
and Jewel Box
10.3
10-11
10.3.1
There are four matrixes to use for SID projects. The project delivery
process used for the project solicitation will determine which SID matrix
to use. The Exhibit 10.3a list the project specific SID Matrixes. For D-B
specific instructions, see Chapter 22 DESIGN BUILD REQUEST FOR PROPOSAL
DEVELOPMENT for SID and FFE Design specific instructions.
Exhibit 10.3a
Project Delivery
Process
PPTO
Exhibit 10.3b
Reference Chapter 22
D-B RFP
Exhibit 10.3c
Reference Chapter 22
D-B RFP
Exhibit 10.3g
Reference Chapter 22
D-B RFP After Award
Exhibit 10.8a
Coordination of the
FFE
10-12
10.3.2
SID PPTO projects will require 100% of the SID to be developed by one
interior design source. During the project development process, the
project interior designer will be required to write the SID CD-ROM. The
CD will be submitted in the front pocket of the SID binder at each
submittal phase. These preliminary contract documents will be submitted in
the Adobe PDF Read Only format.
When the project is complete and Ready-To-Advertise (RTA) all the contract
drawings and specifications, including SID drawings and specification,
will be sent to the Mobile District. The Districts project support
section, EN-DW, will write the final RTA Project CD-ROM. The project
interior designer will be required to obtain copies of the RTA CD-ROM from
EN-DW and include it in the front pocket of the SID Binder before the
final SID binders are distributed.
EXHIBIT
10.3b
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
DESCRIPTION
10%15%
S-2
10-13
30%35%
S-3
50%65%
S-4
100%
RTA
S-5
S-6
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
10-14
10.4
FFE Deliverables
There are four matrixes to use when a FFE is part of the overall project
delivery process. The project delivery process used for project
development will determine which FFE matrix to use. Exhibit 10.4a lists
he project delivery process and corresponding FFE Matrix to use.
Exhibit 10-4a
Project Delivery
Process
PPTO
Matrix
Exhibit 10.4b
Reference Chapter 22
D-B RFP
Matrix
Exhibit 10.4c
10-15
Reference Chapter 22
D-B RFP
Matrix
Exhibit 22-4
Reference Chapter 22
D-B
After Award
Matrix
Exhibit 10.5a
Note:
FFE INSTALLED BY THE
USER GROUP
Note:
FFE INSTALLED BY THE
CONSTRUCTION
CONTRACTOR
EXHIBT
10-4b
ITEM
10%15%
S-2
30%S-3
50%65%
S-5
100%
RTA
X
x
X
S-6
35%S-4
*
1.
2.
3.
X
X
X
X
3A.
**
10-16
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
13A.
14.
15.
16.
17.
17A.
18.
19.
19A.
20.
21.
21A.
22.
23.
23A.
24.
25.
26.
27.
27A.
28.
29.
30.
31.
**
32.
32.
34.
**
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
50%65%
S-5
100%
RTA
X
X
X
X
X
X
X
X
X
50%65%
S-5
100%
RTA
X
X
X
X
X
X
X
X
X
10%15%
S-2
30%S-3
35%S-4
X
X
10%15%
S-2
30%S-3
S-6
S-6
35%S-4
X
Title Section Page-MARKED FOR INFORMATION
ONLY-NOT FOR SHOP DRAWING APPROVAL
X
36.
SID Material, Finish and Color Boards Adobe
PDF
37.
X
FFE Fabric and Finish Color Boards Adobe PDF
* Note if Artworks and Interior Signage are part of the FFE provide record copy and working
drawings in digital separate folders.
35.
**
10-17
10%15%
30%S-3
50%65%
100%
RTA
S-2
S-5
S-6
35%S-4
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
52.
53.
54.
55.
**
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
10%15%
S-2
30%S-3
50%65%
S-5
100%
RTA
S-6
35%S-4
56.
10-18
Editing the Ms Excel Workbooks and Worksheets will begin with instructions
for editing files 08-Accessories.xls through 17-Window Treatments.xls
10-19
and end with instructions for editing files 00-Project Title Page.xls
through 07-Manufacturer List.xls.
Default Page Set-up and hyperlinks for all Ms Excel Worksheets are follows:
The first worksheet tab within each workbook file shall always be the
hyperlinked Table of Contents Link. This hyperlink feature will
facilitate easy access and navigation to all other workbook files
within the master project folder during the development of the FFE. The
integrity of these hyperlinks is to remain at all times.
When workbook files are deleted from the master project Folder, edit
10-20
The second worksheet tab within each workbook file shall always be the
Section Title Page. Exhibit 10-4f illustrates the "Section Title
Page".
Edit the footer on all "Section Tile Page" worksheets to indicate the
Project Name and Location. Verify the correct "Section Title" is in the
header. Do not put dates or location codes in the "headers and
footers".
Edit the Section Title Page to provide a generic list of items
specified in each section. For example the list under the general
category of "Section 8-Accessories" may read: Artwork, Artificial
Plants, Clocks, Coat Racks and Wastebaskets.
Edit the "Section Title Page" for the range of location codes used
within this section. For example if 32 accessory type items are being
specified in Section 8-Accessories then the range of location codes
would read: A-1 thru A-32.
Exhibit 10-4f
10-21
10.4.7
The third worksheet tab within a workbook shall always start the
Illustrated Order Forms (IOF). Each IFO is identified on a worksheet
tab with the new simplified alphanumeric Location Code.
Exhibit 10-4g illustrates the Location Codes tabs and stacked
horizontally for easy navigation.
There are only 10 "alpha codes" that can be used in developing the FFE.
However there are infinite "number codes" to use. Before assigning an
alphanumeric location code to an item, determine the FFE category
workbook the item is to be in. When the category and workbook is
determined, using the workbook's unique alpha code, assign the item an
"alphanumeric" location code.
Location Codes are not in alphabetical order. Codes are selected,
ordered and stacked for easy editing of the Master MS Excel Director.
10.4.8
A=
V=
C=
D=
F=
T=
S=
E=
B=
W=
Accessories
Audio Visual and Presentation support furnishings
Seating (All Kinds)
Desks (All Kinds of free standing units)
Files and Storage (All Kinds)
Tables (All Kinds)
Furniture Systems (Panels, components, & worksurfaces)
Equipment
Bedding, dormitory room furniture, Sheets, Mattress
Window Treatments not included in the SID such as draperies.
10.4.9
Editing the IOF worksheet is a two-step process. The first step is the
page set-up. The second step is the actual development of the item
specific ordering information. The following instructions will provide
general guidance developing IOF worksheets and page set-ups:
The new simplified Location Codes are provided in the editable MS excel
files obtained from the Mobile District.
10-22
Edit the header/footer of each IOF with the Section Number and Name
and the Project Name and Project Location. Dates are not required.
Formulas for adding and multiplying cost and quantities can be used for
quick calculations within a IFO worksheet only and can remain in
individual IOFs at RTA.
10.4.10
The designer is to edit the IOF by completing all sections. The goal is
the use of only one page, 8-1/2 x 11 with portrait orientation and
shown in Exhibit 10-4g. An exception is allowed if additional sheets
are needed for detail specifications. The additional pages are to be
ordered down then over in the page set.
Each IOF worksheet is a stand-alone document and provides
comprehensive ordering information including the following:
10-23
File 14-Furniture Systems.xls workbook will not follow the format of the
other furniture item and equipment workbooks. Paragraphs 10.4.5 Furniture
Systems and 10.4 SID/FFE Drawing and Specification Requirements will
discuss in detail developing projects that include Furniture Systems.
10.4.12
The Project Title Page is found in the file 00-Project Title.xls Edit
the project specific information as indicated in Exhibits 10-2a and 10-2b.
This worksheet will also be printed and used as the FFE binder cover insert
as well as the digital title page for the Master FFE Adobe PDF Folder,
which will be discussed later. Editing the header and footer in this
workbook is not required. Design Firms may insert their companys logo in
the title page as well as project specific User and command logos.
10.4.13
10-24
10.4.14
Title
71-I
Office Furniture
71-II
10-25
71-II-H
Packaged Furniture
71-II-K
71-III
71-III-E
Miscellaneous Furniture
72-I-A
Floor Coverings
72-II
Furnishings
10.4.14.4
The FAR mandates that all commercial items (furniture and related services)
acquisitions use and document two separate and distinct criteria to reach a
best value determination before commercial items can be purchased. The
two criteria are: (1) market research and (2) price reasonableness. Though
these two determinations may both consider the same information obtained
during market research, they are separate and distinct from each other.
The documentation of price reasonableness is required for all contract
awards. The Best Value Statement for all FFE packages will document both
criteria. In addition, the FFE Best Value Statement will also document
the market research and price reasonableness of UNICORs products as well.
Although the Department of Defense is not mandated to obtain a UNICOR
waiver or required to buy from UNICOR, it is a requirement that UNICOR
products be considered when developing a FFE package.
The Best Value Statement is to list the Location Code, then the three
required vendors considered for the item, the price of the three considered
and a brief statement why the selected item was the best value to the
government.
For Example:
The Best Value Statement workbook may also be expanded to include any
Scope of Work documents required to procure from the FSS 71-II-H Packaged
Furniture or FSS 71-II-K Comprehensive Furniture Management Services
contracts
10.4.15
10-26
from UNICOR. The UNICOR Workbook has been completed. It contains all the
statements and DoD documentation required by a Contracting Official to
determination that the FFE meets the FAR.
No additional editing is
needed.
If the FFE is being developed for another Federal Agency or Department
other than the DoD, a paper copy of the UNICOR wavier is to be scanned and
inserted as an image into this workbook. Edit the UNICOR Waiver Worksheet
to document:
The FFE Narrative worksheets are found in the file 04-FFE Narrative. The
FFE narrative will provide a comprehensive discussion and design analysis
as to how FFE items are integrated and function with the SID. Edit the FFE
narrative worksheet using:
A "portrait"-down and over orientation
Letter size 8-1/2 x 11
No gridlines
Do not import any other word document programs into this Workbook.
The FFE Narrative is intended to:
10.4.17
10.4.18
Name
Address
Phone/Fax
E-mail
Job Function of those associated with the FFE project.
Editing the Location Codes and Cost Estimate Workbook
10-27
10-28
After the MS Excel FFE workbooks are edited to meet project and submittal
level requirements, each workbook is to be "printed" in Adobe PDF format
and compiled into Sub-Folder #1 which is the Record Copy FFE. The
creation of the Record Copy FFE is a two-step process. The first step is
to print or transposed all the Ms Excel working files into Adobe PDF
files. Exhibit 10-5a illustrates the files names and stacking order.
Creating the FFE Adobe PDF files is quick and easy. To print the Ms Excel
FFE working files into the Adobe PDF file, print one entire workbook at a
time by simply highlighting the required worksheet tabs then print in a
.PDF output. The file name will be the same with one exception. The file
extension will be .PDF. Not all the worksheets in a workbook will be
printed. Do not print to the PDF file the Table of Contents Link
worksheet tab. The Link worksheet tab is used only in the FFE working
files within the MS Excel Master Sub-Folder #4 for navigation purposes.
Typical tabs titles printed in files 08 through 17 are:
10-29
Workbooks with the digital file names 00-Project Title Page.xls through
07-Manufacturer List.xls will require the workbook specific tabs to be
printed. Do not print the Table of Contents Link in these workbooks.
After the digital workbook pages have been inserted into the Sub-Folder #1
using Adobe Acrobat Writer program, begin adding bookmarks to identify each
"Section Title Page" and provide the number of pages within each Section.
Exhibit 10-5b illustrates this requirement. For example, in Exhibit 10-5b
the Section Title page "SID FFE Narratives has (2) pages within that
section. The page numbers within the each section are noted in parentheses
( #).
10.5.2
Add IOF bookmarks as a sub-tile under the Section Title bookmarks. Edit
the bookmarks using the simple alphanumeric location code used to identify
the furniture item. If two or more sheets are required for an IOF add the
number of sheets in (#) like the Section Title pages.
10-30
10.5.3
10-31
After all the FPP drawings have been set for full view, bookmarked and
titled, create individual room placement views under each Sheet title.
This is done by "zooming-in" on the individual furnished rooms and
inserting a bookmark for that one room. Edit Room Placement Plan
bookmarks with the room number only. If the customer requires a hard copy
of the room plan, instruct them to use the crop and print feature in the
Acrobat program to obtain the hard copy.
Exhibit 10-6a illustrates the
Composite FPP with individual room bookmarks.
FURNITURE SYSTEMS
10-32
one would find in a hard walled office. Workstation designs and layouts
are required to fully coordinate with the life safety plan, audio and
visual alarms and the fire suppression system to ensure the building
within the building supports life safety.
Workstation solutions for projects are not only to be designed for project
specific requirements but are required to address the inevitable office
reconfiguration. Workstations need to be selected for their best value
features, durability, flexibility, and ease of reconfiguration.
Workstations are to offer limited interruption of the PVD when
reconfiguration occurs and are to be easily adaptable to incorporate new
technology.
Workstations are to provide ergonomic features such as adjustable height
work surfaces, fully articulating keyboards with parallel and changeable
mouse pads, and paper management and storage tools to support tasking.
All computer hard drives are to be mounted under the worksurfaces. A
suitable, ergonomically designed task chair is to be selected and
specified for each workstation. To the fullest extent possible, avoid
placing an occupied workstation next to common use area such as semiprivate conference spaces, copy areas or food preparation areas.
When considering the scope of work involved developing a furniture systems
design and cost estimate and when considering the project delivery process
of fast track- Design Build, new design requirements have been developed
to ensure furniture systems designs and installation efforts are
reasonably distributed throughout the design and construction process.
These new requirements shall be applied to PPTO and D-B RFP projects alike
to ensure the SID/FFE submittal process for all projects are consistent.
10.7.1
During the Design Phase of an PPTO or D-B RFP project provide the following
design and procurement information:
Workstation finishes,
Coded workstation layouts plans
Workstation product lists
PVD requirements per typical workstation
Cost estimates
Edited UFGS Section 12 50 00 FURNITURE SYSTEMS
10.7.2
During the construction phase of the project furniture systems vendors and
the construction contractor is to provide as a single shop drawing the
following submittal information:
Detailed drawings, panel plans, PVD plans,
Bill of materials
Elevations or isometrics of typical workstations
Note: These requirements are based on submittal requirements listed in the
UFGS 12 50 00 Furniture Systems.
10.7.3 Editing FFE Ms Excel Furniture Systems Workbook
The following instructions will provide guidance for the development of
the FFE MS Excel file 14-Furniture Systems.xls to meet Design Phase
10-33
10.7.5
10.7.6
Block 1 Locations Codes: List all the location codes used. If only
one manufacturer is supplying two or three types of systems, the
location codes should be keyed to the ordering information make the
distinction.
Block 2 thru 6: Edit to include all the required ordering information
and GSA contracting information.
Block 7: Special Instructions.
Block 8: List the types by Location Code and in [brackets] list the
room numbers where they are used.
Block 9: Indicate the total quantity of each typical.
Block 10: Indicate the cost of a single workstation type.
Block 11: Indicate the extended cost.
Block 12: Indicate the total cost for all types.
Block 13: Add additional costs for design, installation etc.
Blocks 14-16: Cost may vary depending on the FFE procurement strategy
agreed to during the Criteria Review meeting.
Block 17: Indicate the Grand Total for Workstation design and
installation.
10-34
10.7.8
Worksheets
Worksheet Tabs: Edit the sheet tabs using the typicals location
code.
Block 1: Indicate the Location Code.
Block 2: Workstation dimensions/square footage requirements.
Block 3: List of product and PVD requirements.
Note: When the UFGS 12 50 00 is used but not included in the set of
building related contract drawings and specifications published by the
Districts EN-DW, submit the specification as part of the Master FFE Adobe
Acrobat file. Print the SpecsIntact file to an Adobe PDF file and insert
into the Master FFE Binder directly behind the last typical location code
for furniture systems. Provide a Bookmark indicating it is the Furniture
Systems Specification.
10-35
10-36
The 100% FFE is to be completed by the D-B Contractor's Design Team and
ready for government procurement at the time building construction begins.
The FFE needs to be fully coordinated with the other engineering
disciplines to ensure PVD connection requirements are met as well as the
architectural layout and building related finishes.
10.8.3
D-B
D-B
D-B
D-B
Pre-Definition Conference
50% Design Phase
95% Design Phase
Final Design Phase.
Pre-Definition Conference
After the Pre-Definition Conference, the D-B Contractor will submit the
formal 50%, 100% Un-reviewed and Final Design Package. The Contractor
shall submit 5 complete sets of the 100% SID/FFE package.
10-37
EXHIBIT 10-8a SID/FFE D-B Contractor Deliverables After Award of the D-B
Contract
ITEM
1.
*
**
2.
*
3.
*
4.
5.
6.
7.
8.
**
9.
**
10.
**
11.
**
12.
**
13.
**
14.
**
10.9
100%
UnReviewed
Final
Design
Phase
Final
Design
FULL
PROJEC
T
CRITER
IA
X
X
X
X
X
X
X
X
X
X
X
The following commonly used terms and definitions are associated with
SID/FFE design development process. The terms may not be used in this
10-38
10-39
10-40
When non-price related factors are used, these factors are documented as
market research. In making a best value determination, the
Contracting Official uses price and market research assessments.
COM - CUSTOMERS OWN MATERIAL- Manufacturers have standard fabric
offerings that meet testing standards, aesthetics qualities and color
trends. A custom or special order fabric which is not part of a standard
offering is called Customers Own Material (COM). Typical COM adds
extra cost and coordination issues to the order. COM is discouraged.
DESIGN-BUILD (D-B) - The term Design-Build has many meaning. For the
purposes of this chapter of the Design Manual the term Design Build will
be a method of contracting in which a single entity takes responsibility
for both design and construction of a facility. Performance requirements
are outlined using the RFP format. See also RFP.
ENVIRONMENTAL PRODUCTS GUIDE - A GSA catalog for supply items.
can be obtained by contacting:
GSA CENTRALIZED MAILING LIST SERVICE (7CAFL)
P.O. BOX 6477
FT. WORTH, TX 76115
(817) 334-5215
This guide
10-41
UNICOR - The trade name for the Federal Prison Industries (FPI) Inc., a
wholly owned government corporation established in 1934. UNICOR provides
a variety of products and services to the Federal Government. All
furniture systems workstations and conventional furniture requires a
waiver. All waivers are to be requested at 35% design. Web site for FPI
is www.unicor.gov. The waiver requests are sent to FPI on this web site.
Space Planning Terms
Assignment Drawings - Single-line architectural drawings, which
incorporate graphic and statistical information broken down by tenant or
organization.
Base Building Drawings - Scaled architectural drawings indicating the
building shell and accurately representing all architectural and
structural elements. They shall include but not be limited to exterior
building elements, and permanent interior partitions, core areas, columns
and convectors. Numerical identification of all columns, stairwells and
elevators, toilets, doors, etc., shall be included.
Bay - The space in a building bounded by four columns. 20,25 and 30 foot
bays are common.
Blocking, Stacking and Zoning - The first step in space planning.
Arranging all organizational units by floor and within a floor to fit in
the building. Determined by adjacency requirements, square footage and
10-42
special space needs. Zoning diagrams show public, semi-private and secure
spaces by floor or within the facility.
Building Core - Includes elevators, stairs, restrooms, mechanical rooms,
shafts, and electrical closets.
Circulation & Layout factors - In accordance with the AR-405-70, the
circulation factor is a percentage of the net square footage allocation
per person. The AR-405-70 space allocations for open offices include both
the net square footage for an assigned workstation footprint and the net
square footage of circulation required to access the assigned workstation.
Net square footage allocations for private offices do not include the
necessary square footage allowance to move
Color Boards - Boards displaying samples of the materials to be used in
the project. There are color boards for SID building related materials
and color boards for FFE furniture related materials.
Design Charrette Phase - The second part of the on-site effort is to
produce a responsive schematic project solution based on the documentation
of the Requirement Analysis Charrette. See Requirement Analysis
Charrette.
Ergonomic - The science or study of human proportions and actions as
related to the immediate human environment such as an employees
workstation.
Footprints & Typical - The footprint is an outline of the space required
for a workstation and a typical is an example type of workstation that is
used repeatedly throughout the project with no variation.
FPP - Furniture Placement Plan drawings usually provided in the FFE
package that show all the furniture and equipment needed to outfit the
facility.
FURNITURE SYSTEMS - Furniture systems refer to workstation cubicles that
are either desk based, panel based or frame and tile based. All types are
under the same GSA Contract Furniture Systems Workstations are O&M
funded only and never MILCON. If included in the construction contract
and funded with O&M dollars, the workstations may be purchased and
installed in the construction contract.
The interior designer will coordinate the workstation plans with the
building and building systems and provide the plans and specifications in
the contact documents for bids if the General Contractor will purchase and
install the workstations and connect the workstations to the building's
electrical, data, voice, and local area network (LAN) systems. Reference
UFGS Section 12 50 00 Furniture Systems. Layout plans for workstations
purchased and installed by the User are to be fully coordinated with the
building's systems and workstation layouts are included in the contract
plans for "information only."
PVD - Power, Voice and Data
Electrical and Electronic systems that must
be coordinated with the FPP. Each workstation must be assessed for the
type of equipment that will be used and ensure the correct number of
electrical and data outlet devices and circuits are specified.
These requirements are to be coordinated with the Electrical Drawings.
10-43
Requirement Analysis (RA) Charrette Phase - The first part of the on-site
effort to systematically collect and analyze the customer and project
requirements. Information is typically gathered through the use of project
specific questionnaires typically alphanumeric and proceeds to the
schematic design such as a bubble diagram and the blocking and stacking
plans.
Turnkey - Specific to Mobile District
When a single contractor is hired
to provide all services related to implement the SID and FFE packages.
Typically the FFE is procured by the Government and installed by the
General Construction Contractor. The coordination and installation of
furniture deliveries and placement efforts are typically and option to the
building related contract.
Workstation Standard - Development of a personal workspace, which includes
all necessary storage, and furnishings for a specific job function.
10.10
been established,
establish preliminary
costs have been developed
the facility and the
10-44
Orders under the MPT, currently $2,500-place with any schedule contractor: this form is not required.
Orders over the MPT, but under the Maximum Order (MO)-Review GSA Advantage or at least 3 GSA vendors price lists
Orders over the MO, review additional price lists/use GSA Advantage and seek a price reduction.
REQUISITION OR MIPR NUMBER______________________________________________________
Review at least three sources under the Federal Supply Schedule and list the contractors names and prices below. Submit justification if
fewer than three sources were considered. You may attach the pricing or contractors quotes. It is important to have installation, design and
other services pricing included as separate line items in each quote. Please indicate the selected contractor by placeing a check or X by the
Contractor Name.
Location Code
1. Contractor
Product $
Installation$
Design $
Other Services$ Total$
2. Contractor
Product $
Installation$
Design $
Other Services$ Total$
3. Contractor
Product $
Installation$
Design $
Other Services$ Total$
Yes or No (circle one)
Was the requirement in excess of the MO? If yes, reiveiw additional sources/GSA Advantage!
Under the Federal Supply Schedule and list below (attach if desired)
Location Code
1. Contractor
2. Contractor
Product $
Product $
Installation$
Installation$
Design $
Design $
Other Services$
Other Services$
Total$
Total$
Indicate the factors, other than price, considered in your best value decision:
__Special Features
__Warranty Consideration
___Delivery Time
__Past Performance/Experience
__Comfort/suitability of the item
__Technical Qualifications
__Trade-In Considerations
__Compatibility with existing furniture
__Probable life of the item selected compared with that of a comparable item
__Environmental considerations-ie. Recycled content, naturally renewable ingredients, bio
based content, energy efficiency, (See Executive Order 13101)
__Other (specify)
When ordering through the NFC, please include this checksheet with your
order. Please ensure that all the information is complete. Fax order to
703-305-6032 or call 703-305-7003 for more information. Please include
all the information, requested below in case additional information is
required. Orders over $100,000.00 require a written Acquisition Plan,
which will require extra information and time for the NFC to complete the
order issuance.
Signature:
Title
Phone Number
Email
Note: This form does not apply to services.
10-45
Date
(b) COMPETITION REQUIREMENT- If the Secretary determines that a Federal Prison Industries
product is not comparable in price, quality, or time of delivery to products available from
the private sector that best meet the Department's needs in terms of price, quality, and time
of delivery, the Secretary shall use competitive procedures for the procurement of the
product or shall make an individual purchase under a multiple award contract. In conducting
such a competition or making such a purchase, the Secretary shall consider a timely offer
from Federal Prison Industries.'; and
(c) IMPLEMENTATION BY SECRETARY OF DEFENSE- The Secretary of Defense shall ensure that-(1) the Department of Defense does not purchase a Federal Prison Industries product or
service unless a contracting officer of the Department determines that the product or service
is comparable to products or services available from the private sector that best meet the
10-46
10-47
CHAPTER
11
STRUCTURAL
INDEX
11.1
GENERAL
11.1.1 Scope
11.2
APPLICABLE PUBLICATIONS
11.3
11.4
CONCEPT
11.4.1
11.4.2
11.4.3
DESIGN (30-35%)
Structural System Selection Analysis
Design Analysis
Drawings
11.5
INTERIM
11.5.1
11.5.2
11.5.3
DESIGN (50-65%)
Design Analysis
Specifications
Drawings
11.6
11.7
11.8
TECHNICAL REQUIREMENTS
11.8.1 General
11.8.2 Design Loads
11.8.3 Foundations
11.8.4 Structural Steel
11.8.5 Steel Joists
11.8.6 Pre-engineered Metal Buildings
11.8.7 Cold-Formed Steel
11.8.8 Steel Roof and Floor Deck
11.8.9 Concrete
11.8.10 Precast Architectural Concrete
11.8.11 Masonry Construction
11.8.12 Antiterrorism/Force Protection (AT/FP)
11.8.13 Required Standard Details
11-1
CHAPTER 11
STRUCTURAL
11
GENERAL
11.1
Scope
APPLICABLE PUBLICATIONS
American Association of State Highway Traffic Officials (AASHTO)
HB-17
315R
318
530
SDPWS
360
North American Specification for the Design of ColdFormed Steel Structural Members, including
Supplement
General
Header
Lateral
Truss
WSD
24
IRC
MNL 120
Mnl-122
No. 30
11.3
UFC 1-200-01
UFC 3-310-01
At the Project Definition phase, the designer must define the specific
project requirements and confirm that they can be met within the project
constraints. This is normally done through a charrette or other data
gathering process. The structural engineer shall also coordinate with
the architect at this phase to insure that the architectural floor plan
and other architectural features of the project can be framed and
constructed economically.
11-3
11.4.1
Design Analysis
References
List all references used in the Concept design including UFC, industry
standards, and project specific criteria provided at the Charrette or
pre-design meeting.
11.4.2.2
Design Loads
11-4
Lateral Stability
Fire Resistance
Structural Calculations
Drawings
Sufficient framing plans are required for roof, floors, and foundations,
as applicable, to indicate layout of principal members. Typical
sections shall be furnished through roof, floors, and foundations
indicating materials and type of construction proposed. Drawings will
contain a set of general notes indicating design live, wind, and seismic
loading, references used in the structural design, and applicable
material strengths.
11.5
11.5.1
Design Analysis
The interim design analysis shall include all items presented in the
concept design analysis and any revisions necessitated by review
comments on the Concept Submittal. Calculations shall be included for
all principal members, including the structure foundations. Structural
design issues related to AT/FP and Progressive Collapse will be
presented in the design analysis along with structural calculations
related to these issues.
11.5.2
Specifications
Drawings
Drawings for this submittal will include roof and floor framing plans,
as applicable. All principal members will be shown on the plans. A
foundation plan will also be furnished showing main footings and grade
11-5
beams where applicable. Where beam, column, and footing schedules are
used, they will be filled in sufficiently to indicate principal member
sizes. Typical bar bending diagrams shall be included if applicable.
Typical sections will be furnished for principal roof, floor, and
foundation conditions. Slab-on-grade crack control joint locations
shall be indicated on plans and appropriate joint details shall be
provided. Formed concrete slab construction joint locations shall be
indicated on plans and appropriate joint details shall be provided.
Masonry wall control joint locations shall be shown on the structural
and architectural plans. Wall joints shall be carefully coordinated
between the structural and architectural plans. Masonry walls supported
directly by thickened slabs shall insure that the slab crack control
joints are located directly below the wall crack control joint. Typical
applicable masonry construction details shall be provided. Comments
made on the Concept Submittal shall be incorporated into the drawings
for this submittal. The general notes will be developed to reflect the
interim level of design.
11.6
11.6.1
Design Analysis
The Final design analysis shall include all items in the concept and
interim design analyses and any revisions necessitated by review
comments on the Concept and Interim Design submittals. Complete
calculations for all structural members shall be included. Any
calculation changes required by comments on the Interim and Concept
Design submittals must be incorporated.
11.6.2
Specifications
Drawings
11.7.1
Design Analysis
Specifications
Drawings
TECHNICAL REQUIREMENTS
11.8.1
General
Design Loads
Load assumptions shall be in accordance with IBC and UFC 1-200-01 with
the following modifications.
11.8.2.1
The design requirements of ASCE 7-05 will be used, except for one and
two family housing. Local building code requirements do not apply and
will not be used. Wind-load criteria to be used for one and two family
housing shall be as set forth in IRC. Family housing projects located
near coastal areas of the Gulf of Mexico and the Atlantic Ocean shall
comply with the design requirements of SSTD 10-99.
11.8.2.2
(a) Family Housing. Seismic criteria used for one and two family
housing shall be in accordance with the IRC.
(b) Bridges. Seismic criteria used for bridges shall be as set
forth in the AASHTO HB-17 Standard Specification.
(c) All Other Structures. Seismic criteria used for structures
other than family housing and bridges shall be in accordance with the
IBC as modified by UFC 1-200-01.
11.8.3
Foundations
11-7
Structural Steel
Steel Joists
11.8.7
Cold-Formed Steel
Where steel roof and floor deck is used, the required section modulus
and moments of inertia shall be shown on the drawings. The type and
quantity of decking connectors to be used to resist computed wind uplift
and shear diaphragm forces shall be clearly detailed on the final plans.
Steel deck diaphragms shall be designed in accordance with the SDI
Diaphragm Manual. All decking shall have a minimum galvanized coating
conforming to ASTM A653, G60. Steel roof deck material shall have a
minimum thickness of 0.0295 inch (22 gage); non-composite steel form
decking shall have a minimum thickness of 0.0179 inch (26 gage);
composite steel form deck shall have a minimum thickness of 0.0295 inch
(22 gage). When the underside surface of large areas of steel decking
is exposed to view and indicated to be finish painted, the underside
surface of the steel decking will be specified to be factory cleaned and
factory primed with a finish paint compatible primer.
11.8.9
the IBC
Concrete
(a) Concrete design and detailing shall be in accordance with
except as indicated below:
Masonry Construction
11-10
Antiterrorism/Force Protection
11-11
CHAPTER 12
PLUMBING
INDEX
12.1
GENERAL
12.1.1
12.2
APPLICABLE PUBLICATIONS
12.3
12.4
12.5
12.6
12.7
12.8
TECHNICAL REQUIREMENTS
12.8.1
General Considerations
12.8.2
Plumbing Considerations
12.8.3
Seismic Protection
Scope
12-1
CHAPTER 12
PLUMBING
12.1
GENERAL
12.1.1
Scope
APPLICABLE PUBLICATIONS
IPC
UFC 3-420-01
Design: Plumbing
12.3.1
General Considerations
During the Project Definition design phase the designer shall define
the customer's requirements and confirm that they can be met within the
project's constraints. To that end, a comprehensive interface with the
customer is required generally through a charrette or other previously
approved data gathering process. The primary purpose of the design
process at this stage is to gather any information from the customer
that would be necessary in the design of the facility. Also, the
design preferences of the customer should be obtained for compliance if
possible.
The general plumbing system type along with a rough order-of-magnitude
estimate of major equipment sizes will be provided during this phase
for use in preparing the cost estimate and sizing the required
mechanical spaces.
12.3.2
Narrative
The narrative shall include, but not be limited to, the following items
as applicable:
12-2
(e)
12.4
12.4.1
General Considerations
Design Analysis
The Concept Design Analysis shall include but not be limited to the
following items as applicable:
(a) List all references used in the Concept Design including
Government design documents, industry standards, criteria given to the
designer at the pre-design meeting, etc.
(b) Provide justification and a brief description of the types of
plumbing fixtures, piping materials, and equipment proposed for use.
12-3
12.4.3
Specifications
Drawings
The Concept Design drawings should include, but not be limited to, the
following items as applicable:
(a) Indicate locations and general arrangement of plumbing fixtures
and major equipment.
(b) Indicate location and extent of any demolition that will be
required concerning the plumbing system.
12.5
Design Analysis
The Interim Design Analysis shall include all items in the Concept
Design Analysis and any necessary revisions. In addition, the
following specific items shall be included when applicable: Provide
detailed calculations for the sizing of the following systems: domestic
hot water, domestic cold water, waste and vent, natural and LP gases,
vacuum, compressed air, distilled or deionized water, medical gases,
and other specialty systems. Identify and address any security
requirements.
12.5.2
Specifications
Drawings
The Interim Drawings should show all information given on the Concept
Drawings but in greater detail. In addition, the Interim Drawings
should include, but not be limited to, the following items as
applicable:
(a) Include plan and isometric riser diagrams of all areas including
hot water, cold water, waste, and vent piping as applicable. Piping
layouts and risers should also include natural gas (and meter as
required), LP gas, vacuum systems, compressed air systems, distilled or
deionized water, medical gases, and other specialty systems as
applicable.
12-4
12.6.1
Design Analysis
The Final Design Analysis shall include all of the information required
in the Interim Submittal in its final form, and incorporate or answer
all review comments.
12.6.2
Specifications
Drawings
(b)
(c)
12.7
TECHNICAL REQUIREMENTS
12.8.1
General Considerations
12.8.2
Plumbing Considerations
(a) Piping System. Piping materials and sizes shall comply with the
recommendations in the IPC and UFC 3-420-01. Flow velocities in water
pipe shall not exceed 10 feet per second. All piping shall be sloped
to permit complete drainage and shall be properly supported with
allowances for expansion and contraction. Expansion loops or expansion
joints and anchor points shall be shown on plumbing drawings. Piping
subject to freezing shall be suitably protected.
(b) Wall Hydrants and Lawn Faucets. The maximum spacing between
wall hydrants or between lawn faucets around the perimeter of a
building is 200 feet. Add 5 gpm for each hydrant or faucet to building
load for sizing water main.
(c) Floor Drains. Floor drains shall be provided in all boiler and
mechanical equipment rooms and adjacent to each indoor emergency deluge
shower. Provide trap primers for all floor drains unless specified
otherwise. Floor drains are not allowed in rooms used as plenums.
(d) Backflow Prevention. The water distribution system shall be
protected against the flow of water or other liquids into the distributing pipes from any unintended source or sources. Refer to the IPC
for requirements on all systems.
(e) Domestic Hot Water. In the design of any buildings in which
water closets and showers are installed, the designer shall exercise
the necessary precautions to prevent personnel from being scalded while
taking showers due to simultaneous operation of water closets equipped
with flush valves.
(1) Domestic Hot Water Temperature. Domestic hot water supply
maximum temperatures at the point of use will be as follows for the
indicated facilities or areas unless higher temperatures are required
for sanitizing or special processes:
a. In all latrines, heads, and toilet facilities without showers
or tubs, the actual measured temperature of hot water delivered to the
user shall not exceed 130 F.
b. In all latrines, heads, and toilet facilities with showers or
tubs, the actual measured temperature of hot water delivered to the
user shall not exceed 120 F.
c. In buildings such as bachelor officer quarters (BOQ) and
bachelor enlisted quarters (BEQ) where there may be toilet facilities
both with and without showers or tubs, where there is both heavy and
frequent use of the bathing facilities, where there is a common hot
water supply system, the delivered temperature of 120 F may be used for
all facilities.
d. In buildings such as administrative, where showers are
provided only in a few special cases, such as for the commanding
officer and duty officer, the delivered water temperature shall not
exceed 120 F. The same condition shall prevail in laboratory and
special buildings where showers are provided for emergency or
exceptional use, or where the number of users or frequency of use is
12-6
low.
(2) It is recognized that in some older buildings or in some
unusual cases it may be necessary to do more than reset existing
temperature controllers. In some cases, added storage tanks,
temperature blending equipment, or separate lines might be required.
(f) Sump Pumps. Sump pumps will be provided in areas that do not
have a way for gravity drainage.
(g) Compressed Air. Unless requirements are stated in specific
instructions, compressed air system and compressor sizes will be determined by the designer from analysis of equipment layout and/or
coordination with the customer's requirements. Design shall be in
accordance with UFC 3-420-02FA.
(h) Equipment Schedules. Each set of drawings for a project or
building shall include one or more fixture schedules that will
designate the symbols, P numbers, outfit numbers, description, and
sizes of connections.
(i) Plumbing shall not traverse over or under electrical panels or
switchboards.
12.8.3
Seismic Protection
12-7
CHAPTER 13
HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
INDEX
13.1
GENERAL
13.1.1 Scope
13.2
APPLICABLE PUBLICATIONS
13.3
13.4
13.5
CONCEPT
13.5.1
13.5.2
13.5.3
DESIGN (30-35%)
General Considerations
Design Analysis
Drawings
13.6
INTERIM
13.6.1
13.6.2
13.6.3
DESIGN (50-65%)
Design Analysis
Drawings
Specifications
13.7
13.8
13.9
TECHNICAL REQUIREMENTS
13.9.1 General Considerations
13.9.2 HVAC Design Considerations
l3.9.3 Seismic Protection
13-1
CHAPTER 13
GENERAL
13.1.1
Scope
APPLICABLE PUBLICATIONS
Energy Policy Act of 2005 (EPACT 05) (Public Law 109-58)
IMC
IFGC
IPC
UFC 3-410-01FA
UFC 3-400-01
ENERGY CONSERVATION
13-2
Narrative
The narrative shall include, but not be limited to, the following items
as applicable:
(a) List all references used in the Design charrette Narrative
including Government design documents, industry standards, safety
manuals, and criteria given to designer at the Charrette or predesign
meeting.
(b) Explain the purpose and proposed type of the environmental
system (i.e., personnel comfort, process or computer cooling, freeze
protection or otherwise.
(c) List manditory and prescriptive HVAC features to be included in
the design as required by ASHRAE 90.1 and UFC 3-400-01 in order to
provide an energy efficient facility.
(d) State the design conditions including indoor and outdoor
temperatures, relative humidities for summer and winter conditions,
filtration and ventilation requirements, personnel loads, special
equipment loads, etc.
(e) State the proposed building characteristics including 'U'
Factors of walls, floors, roofs, windows, etc., orientation of the
building, latitude and longitude of location, and any special
conditions that would have an impact on HVAC design.
(f) List the major equipment and give the sizes in general order-ofmagnitude.
(g) Briefly describe the proposed control system type.
Base Criteria.
See Specific
(h) Discuss requirements for natural gas, fuel oil, and water flow
meters.
(i)
13-3
13.5
13.5.1
General Considerations
Design Analysis
The Concept Design Analysis shall include, but not be limited to, the
following items as applicable:
(a) List all references used in the Concept Design including
Government design documents, industry standards, safety manuals,
criteria given to the designer at the predesign meeting, etc.
(b) Explain the purpose of the environmental system (i.e., personnel
comfort, process or computer cooling, freeze protection or otherwise).
(c) List manditory and prescriptive HVAC features to be included in
the design as required by ASHRAE 90.1, UFC 3-400-01 and EPACT 05 in
order to provide an energy efficient facility.
13-4
Drawings
The Concept Design Drawings should include, but not be limited to,
single-line layouts of heating and air conditioning systems showing
equipment and contemplated zoning for each building. Drawings shall
indentify rooms and be sufficiently complete to show the location,
arrangement, approximate capacities of all major items of equipment,
and space allocated for servicing and maintenance. Include the
following items:
(a) Single-line layouts of HVAC systems with preliminary
representative duct sizes of main runs and air quantities. This
includes exhaust systems and makeup air systems. Representative
sections of ducts in congested areas should be shown double line.
(b) Show required maintenance space for all major equipment,
preferably with dashed lines.
(c)
13-5
13.6
Design Analysis
The Interim Design Analysis shall include all items in the Concept
Design Analysis and any necessary revisions. In addition, the
following specific items shall be included when applicable:
(a) Provide detailed calculations for the following: heating loads,
cooling loads, equipment sizing, etc. Computer calculations shall
include printout of input data as well as output.
(b) Equipment selection: Equipment selection shall be based on not
less than three manufacturers whose equipment meets project requirements for each item. The design analysis shall include catalog
cuts of all major equipment (e.g., air handlers, coils, chillers,
condensing units, boilers, pumps, fans, unit heaters, heat exchangers,
etc.) used as the basis of the design indicating manufacturer, model
number, dimensions, capacities, and electrical requirements. The
project design is not complete until the designer is assured that there
is sufficient physical space in areas where equipment is to be located
to install and to maintain the selected equipment.
(c) Include any other information or calculations to verify that the
design complies with applicable criteria codes or standards and is
satisfactory for intended purposes.
(d) Major unforeseen costs and any changes from Concept Submittal
shall be referenced and the impact on energy efficiency shall be
indicated. Justification for departures, if any, from the original
design recommendations shall be provided.
(e) Explanatory notes shall be included in the design analysis
covering all rationale for design which would not be obvious to an
engineer reviewing the analysis. Methods of air conditioning and
controls for air conditioning systems shall generally be confined to
those in common use in the industry.
(f) Specifications: The outline specifications previously submitted
for concept phase shall be revised, updated, further developed and
resubmitted in accordance with Chapter 3 SPECIFICATIONS.
13.6.2
Drawings
The Interim Drawings should show all information given on the Concept
Drawings but in greater detail. In addition, the Interim Drawings
should include, but not be limited to, the following items as
applicable:
(a) Show all duct work and piping, with sizes and flow rates, where
necessary for balancing purposes. Indicate the duct work pressures in
13-6
(2) All duct and fittings in congested areas and mechanical rooms
shall be drawn to scale using double-line layouts. In a VAV system,
ducts between the air handling unit (AHU) and variable air volume (VAV)
boxes shall be double-lined and ducts downstream of the VAV boxes may
be single lined.
(3) All equipment shall be outlined to scale, and maintenance or
removal space shall be indicated by dashed lines.
(d) Show new exterior chilled water, dual temperature water, or
steam distribution systems from central energy plants in plan and
profile. Show all other exterior piping in plan.
(e) The final form of all equipment schedules shall be shown with
preliminary equipment data filled in.
13.6.3
Specifications
Design Analysis
The Final Design Analysis shall include all of the information required
in the Interim Submittal in its final form and the information listed
below when applicable:
(a) Include flow diagrams with all quantities for both air and water
sides of complex HVAC systems for balancing purposes (including all
kitchens with commercial hood systems.)
13-7
(b) Major unforeseen costs and any changes from Interim or Concept
Submittals shall be referenced and impact on energy and economic
studies shall be indicated. Justification for departures, if any,
shall be provided.
(c) The designer shall review the prepared plans and specifications
and determine that they are in accordance with this manual and all
other criteria and instructions furnished by USACE. It will be the
responsibility of the designer to coordinate the HVAC systems with the
other trades involved in the building design and to eliminate
interference between HVAC equipment and other components of the
building.
13.7.2
Specifications
Drawings
(b)
(c)
(d)
(e)
Specifications
13-8
13.9
TECHNICAL REQUIREMENTS
13.9.1
General Considerations
Insure UFC 3-
Water Chillers
13-9
13-10
Ventilation.
Heating
55-65 degrees F
13-11
40 degrees F
13-12
(q) Controls. Most bases have in place Direct Digital Control (DDC)
systems. The designer shall contact the base to insure the new
controls are equal to or can seamlessly interface with the existing
system.
13.9.3
Seismic Protection
13-13
CHAPTER 14
FIRE SUPPRESSION SYSTEM
INDEX
14.1
GENERAL
14.1.1
14.2
APPLICABLE PUBLICATIONS
14.3
14.4
14.5
14.6
14.7
14.8
TECHNICAL REQUIREMENTS
14.8.1
General Considerations
14.8.2
Fire Suppresion System
l4.8.3
Seismic Protection
Scope
14-1
CHAPTER 14
GENERAL
14.1.1
Scope
This Chapter provides guidance for preparation and development of the fire
suppression systems. Specific design submittal requirements in this
chapter supplement the requirements in Chapter 1 GENERAL INSTRUCTIONS. All
required documents, including drawings and design analysis, shall be in
accordance with Chapter 2 PRESENTATION OF DATA.
14.2
APPLICABLE PUBLICATIONS.
Unified Facilities Criteria (UFC)
UFC 3-600-01
UFC 3-610
UFC 3-310-03A
14.3.1
General Considerations
During this phase the designer must define the customer's requirements and
confirm that they can be met within the project's constraints. To that
end, a comprehensive interface with the customer is required generally
through a charrette or other previously approved data gathering process.
The primary purpose of the design process at this stage is to gather any
information from the customer that would be necessary in the design of the
facility.
The general fire suppression system type and purpose along with a roughorder-of-magnitude estimate of major equipment sizes will be provided at
the Design Charrette Phase for use in preparing of cost estimate and sizing
the required mechanical spaces. The possibility of a fire pump requirement
shall be determined as early as possible to insure that the associated
costs are included in the earliest estimate.
14.3.2
Narrative
14-2
The narrative shall include, but not be limited to, the following items as
applicable:
(a) List all references used in the Design Charrette Narrative
including Government design documents, industry standards, safety manuals,
criteria given to designer at the Charrette or predesign meeting.
(b) Explain the proposed type of the fire suppression system and if a
fire pump and/or storage tank is needed.
14.4
(c)
(d)
14.4.1
General Considerations
Design Analysis
The Concept Design Analysis shall include, but not be limited to, the
following items as applicable:
(a) List all references used in the Concept Design including
Government design documents, industry standards, criteria given to the
designer at the predesign meeting, etc.
(b)
(c)
Fire zone
(2)
(3)
Specifications
Drawings
The Concept Design Drawings should include, but not be limited to, the
following items as applicable:
(a) The location and rating of any fire-resistive construction such
as occupancy separations, area separations, exterior walls, shaft
enclosures, corridors, stair enclosures, exit passageways, etc.
(b) The location and coverage of any fire suppression systems (e.g.,
sprinkler risers, standpipes, etc.).
(c)
Design Analysis
Specifications
Drawings
The Interim Drawings should show all information given on the Concept
Drawings but in greater detail. In addition, the Interim Drawings should
include, but not be limited to, the following items as applicable:
(a)
revisions.
(b) Prepare a schedule describing the system with the following
information: fire hazard and occupancy classifications, building
construction type, GPM/square foot sprinkler density, area of operation,
hose stream allowances and other as required.
(c) Provide drawings showing a rough layout of the main piping
involved in the sprinkler system if applicable.
14.6
The Final Design Analysis shall include all of the information required in
the Interim submittal in its final form and incorporation of, or answers
to, all comments received concerning the Interim Submittal.
14.6.2
Specifications
Drawings
14.7
(a)
(b)
(c)
TECHNICAL REQUIREMENTS
General Considerations
Seismic Protection
14-6
14-7
CHAPTER 15
OTHER MECHANICAL SYSTEMS AND EQUIPMENT
INDEX
15.1
GENERAL
15.2
APPLICABLE PUBLICATIONS
15.3
15.4
15.5
15.6
15.7
15.8
TECHNICAL REQUIREMENTS
15.8.1
POL Facilities
15.8.2
Engine-Generators
15.8.3
Cranes and Hoists
15.8.4
Storage Tanks For Petroleum, Oils, and Lubricants
15.8.5
Central Energy Plants and Energy Distribution
15.8.6
Elevators
15.8.7
Other Mechanical Systems
15-1
CHAPTER 15
GENERAL
15.2
(c)
(d)
Storage Tanks
(e)
(f)
Elevators
(g)
APPLICABLE PUBLICATIONS
International Building Code (IBC)
Unified Facilities Criteria (UFC)
UFC 3-460-01
UFC 3-400-01
General Criteria
ASME
ANSI
AWS
API
15-2
NFPA
CMAA No. 74
Elevators
ASME A17.1
15.3.1
General Considerations
During this design phase the designer must define the customer's
requirements and confirm that they can be met within the project's
constraints. To that end, a comprehensive interface with the customer
is required generally through a charrette or other previously approved
data gathering process. The primary purpose of the design process at
this stage is to gather any information from the customer that would be
necessary in the design of the facility. Also, the design preferences
of the customer should be obtained for compliance if possible.
The general mechanical system types and purpose along with a roughorder-of-magnitude of major equipment sizes will be estimated at the
Design charrette phase for the purpose parametric cost estimate and
required mechanical spaces.
15.3.2
Narrative
The narrative shall include, but not be limited to, the following items
as applicable:
(a) List all references used in the Design Charrette Narrative
including Government design documents, industry standards, safety
manuals, criteria given to designer at the charrette, predesign
meeting, etc.
(b)
(c)
(d)
(e)
15-3
15.4.1
Design Analysis
Phasing.
Drawings
Specifications
15-4
15.5.1
Design Analysis
The Interim Design Analysis shall include all items in the Concept
Design Analysis and any necessary revisions. In addition, the
following specific items shall be included when applicable:
(a)
(b)
Drawings
These diagrams shall show all of the information given on the Concept
drawings, but in greater detail. The diagrams shall include equipment
capacities and power requirements, all piping sizes with flow rates
indicated, all valves, piping specialties, instrumentation, and control
devices.
15.5.2.2
Layouts and details of the final version of the proposed system showing
location, arrangement, capacity and space requirements of all equipment
plus size, elevations, supports, product identification and direction
of flow for all piping.
15.5.2.3
Equipment
The drawings shall include space for rating data in tabular form for
all items of equipment, with space reserved for designating the
manufacturer and the model number, in anticipation of as-built
drawings. Preliminary rating data shall be inserted in the equipment
schedules at this stage. Equipment schedules shall be completed when
final rating data are established but not later than the Final Review
submission.
15.5.3
Specifications
15-5
TECHNICAL REQUIREMENTS
15.8.l
POL Facilities
Engine-Generators
15-6
15.8.3.1
Hoists
(b)
(c)
The
Special hoists and cranes that are not monorail or overhead traveling
type shall be treated as special designs. Design requirements for
these special cranes shall be requested through Project Management to
the appropriate technical section at or before the predesign
conference.
15.8.3.4
Hoists and cranes must be coordinated with the heating and ventilating
systems. If infrared heating is used in the area where the crane is
located, provide a shield for the top of the crane to protect it from
the infrared heaters.
15.8.4
Aboveground Tanks
15-7
Underground Tanks
Elevators
15-8
CHAPTER 16
ELECTRICAL AND ELECTRONIC SYSTEMS
INDEX
16.1
GENERAL
16.1.1
16.1.2
16.2
APPLICABLE PUBLICATIONS
16.2.1
Other Publications and Code Compliance
16.2.2
Guide Specifications
16.3
16.4
Scope
Design Submittals
16.5
16.6
16.7
16.8
TECHNICAL REQUIREMENTS
16.8.1
Metering
16.8.2
Salvageable Material
16.8.3
Special Items
16.8.4
Design Criteria for Nonlinear Loads
16.8.5
Telecommunication/Data Systems
16.8.6
Fire Detection and Alarm System
16.8.7
Mass Notification System
16.8.8
Special Grounding Systems
16.8.9
Public Address Systems
16.8.10 Intrusion Detection Systems
16.8.11 Leak Detection for Underground Storage Tanks
16.8.12 Lightning Protection System
16.8.13 Hospital Systems
16.8.14 Cable Television Systems (CATV)
16.8.15 Closed Circuit Television Security (CCTV) System
16-1
16.9
16.10
GENERATORS
POST/BASE SPECIFIC CRITERIA
EXHIBITS
16-1 Panel Schedule
16-2 Lighting Fixture Schedule
16-3 Intrusion Detection System Riser Diagram
16-4 Typical Telephone System Riser Diagram
16-5 Fire Alarm Riser Diagram
16-6 Typical Public Address System Riser Diagram
16-7 Design Review Checklist
16-2
CHAPTER 16
GENERAL
16.1.1
Scope
Design Submittals
(a) The following submittal guidelines have been developed for the most
common projects such as a building or buildings and minor exterior electrical
design. Projects which require extensive exterior electrical work and projects
with complicated or highly-technical interior electrical work will have special
submittal requirements developed for that project.
(b) The requirements shall be defined, developed and agreed upon at the
predesign conference and will become part of the contract.
(c) Design submittals will be reviewed for general compliance with
criteria. Some detailed checks will be made. Complete and independent checking
of the design should be accomplished by the designer. The designer is fully
responsible for the design. The design should be complete and accurate. It
should be thoroughly checked for errors, conflicts (both within and between
disciplines), and proprietary requirements. No proprietary restrictions may be
included in the contract unless specifically authorized.
16.2
APPLICABLE PUBLICATIONS
American National Standard Institute (ANSI)
IEEE-C2
ISA 55.2
NFPA 70E
NFPA 72
NFPA 90A
NFPA 101
NFPA 170
NFPA 730
NFPA 780
MIL-HDBK 1190
MIL-HDBK 1191
MIL-HDBK 1012/3
UFC 3-520-01
UFC 3-530-01AN
UFC 3-550-03FA
UFC 3-600-01
UFC 4-021-01
UFC 4-010-01
Design Guide
IFC
IBC
TIA/EIA-568-B.2
TIA/EIA-568-B.3
TIA/EIA-569-B
ETL 98-7
ER 1110-345-700
ETL 1110-3-403
In addition to the codes and standards listed above, all electrical work shall
comply with the applicable requirements of the latest edition of the standards
of the National Electrical Manufacturer's Association (NEMA); Insulated Power
Cable Engineer's Association (IPCEA); and all applicable federal, state, city,
and local codes, regulations, ordinances, publications and manuals. All new
manufactured equipment shall be listed by the Underwriter's Laboratory (UL) or
16-5
Guide Specifications.
The Project Definition narrative shall include the requirements stated below
and shall include all data and any calculations if required to support design
decisions and estimates at this stage of design. The analysis shall
incorporate specific criteria furnished and conference minutes for all systems
considered. The analysis shall include the following:
16.3.1
(e) Clearly define and completely indicate any and all hazardous areas
with the applicable class, group, division, and suitable operating temperature
as defined in the National Electrical Code. Do not attempt to design around
the hazardous areas in lieu of designating the areas. State source of
criteria, such as Safety Officer or other recognized official. Include
documentation of the source of the criteria.
(f) Indicate if a lightning protection system will be required; if none,
so state. (Reference TM 5-811-3 and NFPA 780).
(g) Provide brief description of the grounding system to be installed.
If a counterpoise, grid, electromagnetic interference (EMI) shielding
requirements, etc., is to be utilized, state standards to be used.
(h) List UFGS that will be used. The designer shall obtain the
appropriate guide specifications and use them for design guidance.
(i) Provide a firm statement that no brand names or proprietary items
will be used in final plans and specifications.
(j) Provide a statement identifying the sustainable design features to
be incorporated. See Chapter 20 SUSTAINABLE DESIGN AND DEVELOPMENT (SDD) for
specifics.
16.3.3 Exterior Electronic System Design Analysis Narrative
(a) Provide a statement describing the extent of any exterior work such
as telephone lines, duct banks, etc., outside of 5 feet from the building line.
Provide brief description of the standards of design.
(b) List Unified Facilities Guide Specifications that will be used. The
designer shall obtain the appropriate guide specifications and use them for
design guidance.
16.3.4
Telecommunication/Data Systems
(2)
(3)
(4)
(5)
Security Systems
(6)
(7)
(c)
Code) and indicate the type of equipment proposed for use in such areas.
(d) List Unified Facilities Guide Specifications that will be used. The
designer shall obtain the appropriate guide specifications and use them for
design guidance.
16.4 CONCEPT DESIGN (30%-35%)
The Concept Design Analysis shall include the requirements stated below and
shall include all data and calculations to support design decisions and
estimates at this stage of design. The analysis shall incorporate specific
criteria furnished and conference minutes of all systems considered. The
analysis shall include the following:
16.4.1
(a) Provide a statement describing the extent of any exterior work such
as telephone lines, duct banks, etc., outside of 5 feet from the building line.
(b)
16.4.3
(2) Lighting intensity for each room. (State the design basis such
as Illumination Engineering Society (IES), Definitive Drawings, etc.)
(3) Type of fixture, either by Standard Drawing Number or, if not
applicable, include three (3) manufacturers' catalog cut sheets of each fixture
type.
(c) State type of wiring system, such as rigid or intermediate conduit,
electrical metallic tubing, nonmetallic sheathed cable, etc., and location of
proposed use.
(d) Provide a paragraph describing special items of design, such as
equipment, receptacles, handicapped and seismic requirements, etc.; include
description and location. Reference pertinent NEMA or any recognized standards
to identify type receptacles selected.
(e) Clearly define and completely indicate any and all hazardous areas
with the applicable class, group, division, zone, and suitable operating
temperature as defined in the National Electrical Code. Do not attempt to
design around the hazardous areas in lieu of designating the areas. State
source of criteria, such as Safety Officer or other recognized official.
Include documentation of the source of the criteria.
(f) Describe basic characteristics of panelboards, protective devices,
switchgear, motor control centers or other major equipment to be provided.
Short circuit and voltage drop calculations must be included to the service.
Indicate equipment interrupting rating and short circuit withstand current, and
include the source of this information. Evidence shall be included to support
that the equipment is manufactured or can be manufactured and supplied by at
least three reliable manufacturers and that the space is adequate for the
equipment having the greatest dimensions.
(g)
Telecommunication/Data Systems
(2)
(3)
(4)
(5)
(6)
Security Systems
(7)
Drawings (30%-35%)
16.4.5.1
Exterior Electrical
(a) Existing and new electrical primary lines both overhead and
underground shall be properly identified.
(b) Show removals and relocations, if any.
separate drawing(s).
If extensive, provide
Guying calculations
same.
Interior Electrical
(a)
(b)
(b) Show the proposed riser diagrams for all systems. Sizes of conduit,
wires, cables, panels, etc., need not be included at the 30%-35% design.
(See EXHIBITS 16-3, 16-4, 16-5, and 16-6)
(c) Provide a complete symbol legend for all devices or equipment shown on
the plans.
(d) It may be necessary for the designer to provide a recommended layout
for telephone, LAN, mass notification and cable television (CATV) on floor
plans.
16.5
16.5.1
Design Analysis
16-11
Drawings (50%-65%)
16.5.2.1
General
16-13
Exterior Electrical
All exterior electrical shall be completed in plan with poles and other
pertinent components detailed. Details shall include transformer's location,
type of construction, kVA, impedance, voltage, phase, and type, size and number
of conductors. If manholes or handholes are required for underground, utilize
typical manhole from UFC 3-550-03FA. Manholes and/or handholes shall be
detailed on final drawings.
16.5.2.3
Interior Electrical
Electronic Systems
All exterior plans should be completed.
(d) Provide riser diagrams for fire detection and alarm system,
intrusion detection system, public address system, telephone system, mass
notification system, etc. Risers should show the location of the various
components and interconnections with other systems such as HVAC panel
connections to fire alarm panels, etc. (See EXHIBITS 16-3, 16-4, 16-5 and 166)
(e) Show location of all devices (fire alarm, mass notification,
communications, etc.) and equipment for electronic systems on the floor plans.
Show location of devices to be interconnected; e.g., show duct-mounted smoke
detectors, hood fire-suppression system contacts for fire alarm system input,
etc. Location of all devices shall conform to NFPA 72 and UFC 3-600-01, ADAAG
(ADA Accessibility Guideline; www.access-board.gov) and/or UFAS.
16-14
Specifications
Additional Criteria
Design Analysis
Drawings
The final drawings are an extension of the approved 50%-60% drawings and shall
incorporate the 50%-60% comments.
(a) All details for final package shall be on the drawings (pole
details, fixture details, etc.). Congested areas where there can be
interference with various electrical systems, cable trays, piping, ducts, etc.,
shall be thoroughly detailed by expanded scale drawings.
(b) Thoroughly check the drawings for discrepancies, for compatibility
between drawings and specifications, and for compatibility between disciplines.
Check the following, as a minimum, but DO NOT LIMIT CHECKING TO THESE ITEMS:
(1) Verify compatibility between electrical, electronic systems,
and other disciplines (equipment locations, reflected ceiling plans, motor
voltage and across the line as reduced voltage starters and horsepower, NEMA
16-15
schedule.
(4)
(5)
(6)
(7)
(11) Ensure that the proper receptacle types(s) are provided for
the specific special purpose equipment that will be used in the facility.
Obtain equipment list and requirements from user.
16.6.3
Specifications
short circuit study and coordination curves for the equipment to be furnished.
The study and curves shall be approved prior to approval of shop drawings for
the equipment. The study shall not be provided for projects having
nonadjustable protective devices for which coordination is not possible (e.g.
standard molded case breakers). Projects that are served by a transformer 750
kVA or less do not require a study. Certain facilities where the loss or power
would be critical shall also require the study.
(g) If the design is predominately exterior overhead or underground with
a small amount of information required that is contained in the interior
electrical specification, the design specifications may include excerpts from
the interior specifications in either the overhead or underground
specifications and the title changes to "Electrical".
This procedure must
have prior approval.
16.7 READY-TO-ADVERTISE (REVIEWED 100%)
(a) The comments generated during the Final Review shall be answered or
incorporated into the completed design analysis (not amended sheets),
specifications, and drawings before they are submitted as Ready-to-Advertise.
(b) The analysis shall be complete and shall support the requirements of
the project.
(c) The drawings and specifications shall be complete and thoroughly
checked. Where additions to existing electronic systems are made, the designer
shall have verified that the existing system is expandable and can accommodate
the additions. This verification shall include an on-site survey of the system
and contacts with the manufacturer to ensure that the expansion modules, etc.,
are available. Information on manufacturer, model number, etc., of the
existing electronic equipment shall be included in the plans and
specifications. This is typical of expansions made to fire alarm and public
address systems.
16.8
TECHNICAL REQUIREMENTS
16.8.1
Metering. Metering shall be provided for both Army and Air Force
projects as required by UFC 3-520-01.
16.8.2
Salvageable Material
The
Removals
Where indicated, existing equipment and material shall be removed and shall
remain the property of the Government. Salvageable equipment and materials
shall be delivered to the Contracting Officers Representative for storage on
the premises as directed. Materials and debris considered unsalvageable by the
Contracting Officers Representative shall be disposed of as directed.
16.8.2.2
Removed materials with the exception of poles shall be reused if they are in
good condition and they meet the requirements of this section of the
specifications. Removed wood poles shall not be reinstalled. (Removed
materials not incorporated in the new work shall be delivered to storage and
disposed of as directed by the Contracting Officers Representative.)
16-17
16.8.3
Special Items
(a) The design of the electrical distribution (both normal and emergency
power) shall consider the effects that harmonics from non-linear loads can
produce on the system. Harmonics from non-linear loads can affect the sizes of
the neutral conductor, panelboards, phase conductors and emergency generators.
Design for facilities having nonlinear loads shall be in accordance with ETL
1110-3-403. Per the requirements of paragraphs 4c and 4g, the use of 75 degree
C (minimum) conductors is required and must be shown as such on the drawings.
Eight-wire branch circuits within the building which serve nonlinear loads
shall be 3#12, 3#10 N., 1#12 GND., and 1#12 Isolated GND. Feeders serving
panelboards with nonlinear loads shall have the neutral conductor ampacity
based on at least 1.73 the ampacity of the phase conductors. The simplest way
to accomplish this is a double ampacity neutral or parallel neutrals in sizes
allowed by the National Electrical Code.
(b) "K" rated transformers shall be used where the associated panelboards
are feeding a large quantity of non-linear loads. Special attention shall be
given to the harmonics produced by variable speed and variable frequency drive
units for control of HVAC equipment.
16-19
Telecommunication/Data Systems
General Design
building and should be clear of any decorative wall, sidewalks, parking areas,
etc., with a clear, planned route to the service connection point (pole,
manhole, etc.). Provide ductbank sleeves under roads, walks, etc. to
facilitate unobstructed access for the installation of cables. Outside of the
building, the conduit should be capped and the location marked for future
installation of cable by telephone company. All underground conduits should be
a minimum of thirty (30) inches below grade and concrete encased.
(e) When involved with a large complex or building (i.e., multibuilding
complex, etc.), make a determination as early as possible the equipment
required for telephone and LAN service. Communication equipment installations
require special considerations (e.g., space, additional HVAC, vented exhaust
systems for batteries, rated walls, hazardous area, etc.). Often, the plans
for communication equipment may not be stated in the specific project document.
State any requirement or anticipated plans for communication equipment in the
concept design analysis along with all data justifying this need.
(f) When communication outlets are installed in prewired workstations,
the cable shall be a continuous run from the outlet to the connector block at
the backboard.
(g) The designer shall insure that the communication system design
complies with the Uniform Federal Accessibility Standards (UFAS) and/or ADAAG,
and all state and local laws and standards for buildings and facilities
requiring accessibility and usability for physically handicapped people. These
instructions cover such items as the height of payphones, These requirements
may require that power outlets be provided next to telephones for TDD devices.
(h) Provide show telephone jack in each Elevator Equipment Room. Add a
note on title drawing stating that The Contractor shall obtain the elevator
response telephone number from the base via the Contracting Officers
Representative.
(i) Check with the base Communications Officer for requirements
associated with providing a Local Area Network (LAN) connection to the
mechanical heating, ventilating and air conditioning (HVAC) direct digital
controls (DDC). Coordinate with the Mechanical designer.
(j) Include provisions for under floor routing of microphone and other
types or cables in video teleconference rooms, courtrooms and similar areas.
(k) Local area networks shall be included for all projects as required.
The basic criteria will be obtained from the user for inclusion in the project.
All LAN outlets installed in prewired workstations shall be wired continuously
from the outlet to the backboard, multitap, etc. depending on the type of
system installed.
16.8.6
The fire detection and alarm system shall comply with the following design
guidance where applicable.
(a) System shall conform to the NFPA Codes and ADA and/or UFAS
Requirements.
(b) Do not show wire or conduit size, or the quantity of conductors in
the circuits, as they will vary with different manufacturers and shall be
required by the specifications to be included in the shop drawings. One
exception to this requirement is the AC power circuit to the fire alarm
equipment.
16-21
Use NFPA
(d) Provide a riser diagram showing the control panel, annunciator panel
(if required), all zones, radio transmitter (if required), battery cabinet and
interfaces to other systems (HVAC, sprinkler, hood dry chemical, etc.).
(e) Primary power shall be provided from a lockable breaker in
electrical panel nearest to the originating point of the power and lighting
service (208Y/120 Volts). Backup power shall be provided by batteries and
charger.
(f) The fire alarm system must report to a Central Station. if required,
(which will send an alarm signal to the local fire station) via transceiver,
transmitter connected to telephone lines or existing fire reporting system.
Conduit and wire in building to be included in design. The Contractor does not
normally supply the central station receiver module; however, any equipment
supplied must be fully compatible with the central station equipment. The make
and model number of control station equipment must be determined for inclusion
in the specifications.
(g) The specific project Criteria shall be followed for specific
requirements. All ambiguities or conflicts should be clarified early in the
design.
16.8.7
16.8.8.1
General
Qualifications
(a) The specifications and drawings shall completely reflect all of the
design requirements. The specifications shall require field tests (in the
construction phase), witnessed by the Contracting Officers Representative, to
determine the effectiveness of the grounding system.
(b) The design must include drawings showing existing construction.
Verification of the validity of any existing drawings and/or any other data
furnished by the Government shall be the responsibility of the engineering
services firm.
(c) The designer shall provide a cost estimate for the grounding system.
This will include all construction and testing cost reflected to installation
of the grounding system. The estimate shall be a detailed estimate, showing
equipment, labor, excavation, etc.
(e)
16.8.9
16.8.11.1
General
Leak detection must be provided for underground storage tanks and piping which
will contain petroleum products or the hazardous materials as required by
local, state, or federal regulation. The leak detection provisions shall
16-24
Guidance
16.8.12.1
Minimum Scope
Additional Scope
For building types not in the above description, a risk assessment shall be
performed using the guides in TM 5-8ll-3 and NFPA 780 to determine the risk of
loss due to lightning.
16.8.12.3
Master Label
For buildings and facilities with a strong risk potential, furnish and install
equipment, accessories, and material necessary for a complete "Master" labeled
lightning protection system to protect all building components. The system
shall comply with all the requirements of TM 5-8ll-3 and AMC-R 385-100, as well
as the National Fire Protection Association (NFPA 780), the Underwriter's
Laboratories, Inc., (UL 96A), and the Lightning Protection Institute (LPI 165).
All cables, air terminals, and accessories shall be copper. All connections
and splices shall be exothermic weld type.
16.8.12.4
Minimum Requirements
Certification Delivery
Before the lightning protection system is accepted, the contractor shall obtain
and deliver to the supervising architect, the "Master Label" of the
Underwriters Laboratories, Inc., or an equivalent certification.
16.8.13
Hospital Systems
Hospital systems are very special designs, and specific requirements should be
provided for each project. Hospital systems include Nurse Call, Central
Dictation, Patient Monitoring, Radio and Public Address, CATV or MATV, Radio
Paging Telephone, etc.
16.8.14
The CATV shall be a prewired system or a conduit system only for projects
according to the criteria given. A two-inch (2") empty entrance conduit shall
16-25
be installed for all projects for future installation of service cable by Using
Agency. Provide a 3/4-inch plywood backboard with sufficient space for the
distribution cable terminations, amplifiers, and splitters. The systems shall
include cables from the backboard to each outlet, connectors on outlet plates
and sufficient spare cable at backboard for future connection to splitters.
All empty conduits shall have pull wires. Specifications will be included in
Section ELECTRICAL WORK, INTERIOR.
16.8.15
The video security system, where required, shall be integrated into the overall
function of the facility. The designer shall design a complete closed circuit
television security (CCTV) system and shall have a minimum of 3 years
experience in similar installations. Placement of cameras must be carefully
considered in order to avoid dead zones. Conduit and wiring shall be installed
for the system and a camera shall be installed at all entrance and exit areas.
The location of the camera shall be suitable for monitoring people movement
when entering or leaving the building and an emergency circuit shall provide
power for each camera location. Conduit, wiring, cameras, etc., shall also be
installed in all parking lots, loading docks, and computer areas to provide
monitoring.
(a) Cameras shall be of the fixed or pan-tilt-zoom type as required for
each specific location. Camera components shall include cameras, lenses, fixed
and remote-control camera accessories, camera housing, and environmental
options. Cameras shall be housed in proper enclosures for the environment in
which they are to operate (e.g., defrosters, heaters, weatherproof enclosures,
corrosion resistant or vandalproof enclosures, etc.).
(b) All cameras shall be monitored/controlled at the facilities central
control station. Monitors shall be event driven. Monitor components shall
include monitors and monitor mounts. A VCR shall be provided where required,
to record unauthorized access (control by guard). A 120 volt single duplex
receptacle (emergency power) shall be provided immediately adjacent to all CCTV
camera locations.
(c) CCTV cameras shall be provided to monitor entry and exiting from the
loading dock areas. CCTV monitors (in addition to that at the central console
for the loading dock areas), shall be provided in the loading dock office to
provide identification of delivery vehicles prior to opening the loading dock
doors.
16.9
GENERATORS
When generators are a part of a project, show power circuits to the battery
charger, block heater, and any other associated piece of equipment requiring an
external power source. Also show empty conduits for controls, annunciators,
etc.
16.10 POST/BASE SPECFIC CRITERIA
In addition to the requirements stated hereinbefore, criteria specific to a
particular installation shall also be incorporated. This criteria is in many
instances more restrictive that this document and must be obtained and used
from the beginning of each project.
16-26
DESCRIPTION
CONNECTED KVA:
CONNECTED AMPS
DEMAND KVA:
DEMAND AMPS:
xxxY/xxx VOLTS
VA B
VA C
3 PHASE
EXHIBIT 16-1
16-27
NO
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
EXHIBIT 16-2
16-28
EXHIBIT 16-3
16-29
EXHIBIT 16-4
16-30
EXHIBIT 16-5
16-31
EXHIBIT 16-6
16-32
Main transformer
Check to insure that the primary and secondary
voltages/connections are shown.
Check to see if the impedance is shown or covered in the
specifications.
Primary
Insure that the size and voltage rating of the cable is
shown.
Insure that the size is adequate for the transformer size.
Insure that fused cutouts or fused primary switch is shown.
Service
Insure that the service entrance conductors are sized for the
demand load or the transformer secondary current as a
maximum.
Insure that the grounding electrode conductor is in
accordance with NEC Article 250.
Service Equipment
Insure that the main breaker and interrupting ratings are
shown (verify interrupting rating with short circuit
calculations; verify the continuous current rating with
demand load calculations).
Insure that the main bus rating is shown (size should agree
with the demand load calculations as a minimum).
Insure that Ground Fault Protection is shown if required be
the National Electrical Code. See also additional
requirements from UFC 3-520-01.
Insure that 15%-25% spare breakers are shown.
EXHIBIT 16-7 (Continued)
16-33
Subpanels
Insure that the feeders are sized per the demand load
calculations (as a minimum; can be sized to match the rating
of the panel)
Insure that the panel main breaker (if not MLO) is sized for
the panel rating. Insure that the interrupting rating is
shown and verified by short circuit calculations.
Insure that the panel trim (flush vs. surface) is shown.
Insure that a oversized neutral is shown when required for
nonlinear loads (ETL 1110-3-403)
Insure that 15%-25% spare breakers are shown.
o 208Y/120 Volt Panels
Insure that the required main breaker is shown. Check to
insure that it is sized at the demand load as a minimum or
the panel rating as a maximum. Insure that the interrupting
rating is shown and verified by short circuit calculations.
Insure that an oversized neutral is show when required for
nonlinear loads (ETL 1110-3-403).
Insure that 15%-25% spare breakers are shown.
o 480Y/277 Volt dry type transformers
Insure that these are sized by demand load calculations.
Indicate the K-Factor ratings on the drawings and in the
specifications.
Insure that the grounding electrode conductor is shown in
accordance with Article 250of the National Electrical Code.
Insure that the primary and secondary connections are shown.
Insure that the impedance is shown.
Floor Plans
o Compare the electrical plans (lighting, power, and systems) with
the architectural to insure that these agree.
o Compare these plans with the mechanical plans to insure that power
is provided to mechanical equipment and it its the correct size as
shown in the mechanical equipment schedule(s).
Lighting Plans
o Coordinate the lighting fixture layout with the HVAC plans to
insure that fixtures and registers do not conflict in location.
o Insure that lighting switches are shown on the correct side of the
door swing and that they are not located in sidelights or other
glass.
o Insure that a fixture schedule is included. Use the new 40-06-06
for details and EI 16E500 for the schedule.
o Insure that fixtures chosen are compatible with ceiling types
specified on the architectural plans.
o Insure that boundaries of any hazardous classified location and
identification of this location(s) are shown clearly.
o If dimming ballasts are required, insure that they are shown in the
details and/or schedule.
Power Plans
o Verify that there is power to each piece of HVAC equipment (size
for the sizes shown in mechanical equipment schedules.
o Insure that GFI is provided where required by the National
Electrical Code
o Insure that the chiller circuit is sized in accordance with
manufacturers data and that the data is included in the design
analysis.
EXHIBIT 16-7 (Continued)
16-34
o
o
o
Insure that receptacles are located at the TBB, LAN backboard and
at DDC controls.
Insure that there is at least one outlet on every wall.
Panel Schedules:
Panel name
MLO or Main Breaker
AIC rating shown
Size of branch breaker and description shown
Oversize neutral shown where required
Surface or flush trim shown
Voltage rating and main bus rating is shown
Spare breakers shown
Insure that standard sizes are shown (100 Amps < use 30
poles; 225 Amps < use 42 poles)
Indicate any 2 section panels (state if they are feed-through
or double lugs)
Insure that boundaries of any hazardous classified location and
identification of this location(s) are shown clearly.
Duct detectors
Coordinate with the mechanical engineer
Over 2000 CFM, provide on supply.
Over 15000 CFM and multistory building, provide on
return.
Provide remote test station as required by NFPA 72.
Show detectors on floor plans and in the riser.
Notification Appliances
Audible Appliances
Locate to provide sufficient sound level
o 15 dB above ambient
o 5 dB above maximum 60 second sound level
o Double the distance loses 6 dB
o Lose 25 dB through walls
o Lose 10 dB through doors
o UFGS states that bells/horns have 85 dBA at 10
feet
o Provide devices on every floor
o Provide devices in noisy areas (e.g. mechanical
rooms, etc.)
o Devices shall have a temporal sound pattern in
accordance with NFPA 72
Visual Appliances
o Space in accordance with NFPA 72 and ADAAG.
Control Panel
Where connecting to an existing system, insure that the
existing and new systems are compatible.
For conventional systems, use the following zones:
Fire suppression system
Hazardous areas
Flow switches
Tamper switches
Other supervisory devices
Firemans elevator service
Attic detectors
Pull station
Kitchen equipment
Notification appliances
Automatic door release
Power shutdown to data processing equipment
AHU shutdown
Provide manual override for AHU shutdown testing
NFPA 72 lists maximum number if devices fir a zone.
Annunciator: use a graphic annunciator if one is required.
Specify transceiver to be compatible with the base/post
system
Riser
Power
Diagram
Show FACP
Show power supply
Show signaling method
Show annunciator
Show all zones
supply
Provide primary source from light and power system
(208Y/120 volts) per NFPA 72.
Secondary source is primarily batteries. Size per NFPA
72 requirements. PROVIDE A SEPARATE BATTERY CABINET.
Power all devices from the FACP
Wiring
All wiring is to be Class A, Style D
When connecting to an existing system, insure
compatibility, Do not connect a 4-wire system to a 2wire system.
Sprinkler System Supervision
Coordinate with the Mechanical/fire protection
engineer.
Flow switches
Tamper switches
Pressure switches (on all systems)
Telephone
o Coordinate that receptacles are located at the TBB
o Verify that phone outlets are located as desired by the user
o Provide telephone outlets at the DDC panel location
o Verify that the telephone room complies with EIA/TIA standards
o Insure that CAT 5 circuits have not exceeded the 90-meter limit in
length.
Site Plan
o Verify that the electrical site plan agrees with the civil site
plan
o Coordinate with the landscaping plans to avoid conflicts between
electrical equipment (transformers, lighting fixtures, etc.) and
planting materials
o Coordinate with the mechanical plans to avoid conflicts in location
between transformers and chillers, etc.
o Verify the lighting layout meets design lighting level prescribed
in IES and the TI; support with calculations
o Verify that required details are shown; these include pole details,
pad details, manhole/handhole details, duct bank sections, etc.
o Coordinate with other utilities (water, sewer, gas, storm sewer,
etc.) to identify any conflicts and to insure that required code
(IEEE C2 and NFPA 70) clearances are obtained
EXHIBIT 16-7 (Continued)
16-37
o
o
o
o
o
Miscellaneous Drawings
o Verify that all symbols are included in the legend (use Triservice
standard symbols)
o Verify that enlarged plans of electrical and/or mechanical rooms
are included if necessary
o Insure that the size of large items of equipment can be provided by
at least three manufacturers
o Verify that NFPA 70 clearances have been obtained
Miscellaneous
o Insure that Customer Specific Criteria has been incorporated
o Insure that all design techniques for nonlinear loads have been
incorporated
Design Analysis
o Calculations included
Demand load analysis
Lighting Calculations
Zonal cavity for interior
Exterior
Short circuit calculations
Voltage drop calculations
o Coordination study provided (as required in the design manual)
o Arc Flash Hazard Analysis has be performed and results presented
o Design narrative
o Interior, exterior narratives
o Catalog cuts
Lessons Learned
o Verify that all applicable lessons learned from the district
database have been incorporated (at each design/review submittal).
CHAPTER 17
CORROSION CONTROL AND CATHODIC PROTECTION SYSTEMS
INDEX
17.1
GENERAL
17.1.1 Scope
17.1.2 Design Submittals
17.2
APPLICABLE PUBLICATIONS
17.3
17.4
CONCEPT
17.4.1
17.4.2
17.4.3
17.4.4
17.4.5
DESIGN (30-35%)
General Considerations
Drawings
Removal of Demolition
Specifications
Additional Criteria/Information
17.5
INTERIM
17.5.1
17.5.2
17.5.3
17.5.4
DESIGN (50-65%)
Design Analysis
Drawings
Specifications
Additional Criteria
17.6
17.7
17.8
TECHNICAL REQUIREMENTS
17.8.1 Salvageable Material
17.8.2 Special Items
17.8.3 Corrosion Control and Cathodic Protection
17.8.4 Other Electronic Systems
17-i
CHAPTER 17
GENERAL
17.1.1
Scope
Design Submittals
(a) The following submittal guidelines have been developed for the
most common projects such as cathodic protection design for the protection
of new buried metallic piping to building(s) and utility facilities that
might be constructed in support of those new buildings such as water tanks,
fuel tanks, sewage lift stations, etc. Projects, which require extensive,
unusual, or complicated cathodic protection work, will have special
submittal requirements developed for that project.
(b) The requirements shall be defined, developed and agreed upon at
the pre-design conference and will become part of the contract.
(c) Design submittals will be reviewed for general compliance with
criteria. Some detailed checks will be made. The designer should
accomplish complete and independent checking of the design. The designer
is fully responsible for the design. The design should be complete and
accurate. It should be thoroughly checked for errors, conflicts (both
within and between disciplines), and proprietary requirements. No
proprietary restrictions may be included in the contract unless
specifically authorized.
17-1
17.2
APPLICABLE PUBLICATIONS
National Fire Protection Association (NFPA)
NFPA 70
NACE RP0177
NACE RP0187
NACE RP0188
NACE RP0193
NACE RP0274
NACE RP0285
NACE RP0286
NACE RP0388
NACE RP0572
Design:
UFC 3-570-02N
UFC 3-570-06
UFC 3-570-07
Design Criteria
Corrosion Control
17-2
Safety Manual
17.3
UFGS 26 42 14.00 10
UFGS 26 42 15.00 10
UFGS 26 42 17.00 10
Project Definition shall include the requirements stated below and shall
include all data and calculations to support design decisions and estimates
at this stage of design. The analysis shall incorporate specific criteria
furnished and conference minutes of all systems considered. The analysis
shall include the following:
17.3.1
Design Analysis
17-3
17-4
alternatives.
(e) Define any hazardous areas (as defined in the National
Electrical Code) and indicate the type of any cathodic protection equipment
proposed for use in such areas.
(f)
17.4
17.4.1
Design Analysis
The Concept Design analysis shall include the requirements stated below and
shall include all data and calculations to support design decisions and
estimates at this stage of design. The analysis shall incorporate specific
criteria furnished and conference minutes of all systems considered. The
analysis shall include the following:
(a) Provide the name of the licensed Corrosion Engineer, certified
NACE Cathodic Protection Specialist, or certified NACE Corrosion
Specialist.
(b) New or supplemental CP shall be compatible to the existing CP
systems (if operational) and other adjacent structures or components. It
is the responsibility of the Corrosion Expert, as defined in this
chapter, to verify, during the pre-design cathodic protection survey, the
operability of existing cathodic protection systems located adjacent to or
in the vicinity of the new metallic structures requiring cathodic
protection. All variables that may compromise the operation of the new
cathodic protection system, such as interference and grounding to existing
structures, etc., must be considered in the design. The design shall
require remedial actions that will mitigate all interference, grounding,
and other undesirable effects to enable the new CP system to afford the
required potentials. New systems will be compatible with installation wide
systems to allow ease of repair and maintenance. New metallic pipelines or
other metallic structures which are to be connected to existing metallic
pipelines or other existing structures shall be electrically isolated by
the installation of isolation flanges between the new and old metallic
structures, regardless if the existing metallic structure is cathodically
protected or not. That is, new cathodic protection systems must be
independent and isolated from existing cathodic protection systems and
designed such that the new CP system provides the specified protective
potentials to the new metallic structure. Any variation from the
installation of isolation flanges between new and old pipelines, such as
expansions of existing cathodic protection systems to accommodate new pipe
extensions, must be submitted to and approved by the Mobile District,
Engineering Division CP Specialist. Expansions of existing CP systems to
new pipelines or other metallic structures requiring cathodic protection
must be supported by CP field survey data, including potential surveys of
existing pipelines under cathodic protection, existing isolation flange
tests, existing coating integrity tests, etc. All these tests, as well as
other tests that might be necessary in order to support the design, must be
conducted by the Corrosion Expert and results and procedures included in
the Design Analysis. Where additions or alterations to existing CP systems
are to be recommended, verification and substantiation that the systems are
operational, expandable, and can accommodate the additions or alterations
are mandatory. Provide a description of all proposed additions and
alterations to each system. Information on manufacturer, model number,
etc., of the existing cathodic protection equipment shall be included in
17-5
(2)
(3)
(4)
Drawings
Removal or Demolition
Specifications
Additional Criteria/Information
17-6
17.5
Design Analysis
Drawings
17.5.2.1
General
Specifications
Additional Criteria
17-7
Design Analysis
Drawings
The final drawings are an extension of the approved 50%-60% drawings and
shall incorporate the Concept Design submittal review comments.
(a)
drawings.
(2)
(3)
(4)
Rectifier locations.
(5)
(6)
(7)
Specifications
17-8
(a)
(a) The comments generated during the Final design submittal review
shall be incorporated into the design analysis (not amended sheets),
specifications, and drawings before they are submitted as Ready-toAdvertise.
(b) The analysis shall be complete and shall support the requirements
of the project.
(c) The drawings and specifications shall be complete and thoroughly
checked. Where additions to existing cathodic protection systems are made,
the designer must follow the guidance included in previous submittals
described in this chapter.
17.8
TECHNICAL REQUIREMENTS
17.8.1
Salvageable Material
Removals
Existing materials shall be reused if they are in good condition and they
meet the requirements of this section of the specifications.
17.8.2
Special Items
17-9
17-10
17.8.3.1
Coating Requirements
17-11
17-12
17-13
Criteria of Protection
17-14
17.8.4.1
Leak detection must be provided for underground storage tanks and piping
which will contain petroleum products or the hazardous materials as
required by local, state, or federal regulation. The leak detection
requirements are discussed in Chapter 16 ELECTRICAL AND ELECTRONIC SYSTEMS.
17.8.4.2
Grounding Systems
17-15
17-16
CHAPTER 18
COST ESTIMATING
INDEX
18.1
GENERAL
18.2
APPLICABLE PUBLICATIONS
18.3
GENERAL INSTRUCTIONS
18.4
DELIVERABLES
18.5
ESTIMATOR QUALIFICATIONS
18.6
METHODS OF ESTIMATING
18.6.1
General
18.6.2
PACES (Parametric Cost Engineering System)
18.6.3
MCACES 2nd Generation (MII)
18.6.4
Manual
18.6.5
Excel Spreadsheet
18.7
SUBMITTAL
18.7.1
18.7.2
18.7.3
18.7.4
18.7.5
18.7.6
REQUIREMENTS
General
Cost Control
Format
Cost Breakdown
Resubmittal and/or Support
Bid Exceeds Estimate
18.8
TECHNICAL
18.8.1
18.8.2
18.8.3
18.8.4
18.8.5
18.8.6
18.8.7
18.8.8
18.8.9
18.8.10
18.8.11
18.8.12
18.8.13
18.8.14
18.8.15
18.8.16
REQUIREMENTS
General
Quantity Survey
Material Pricing
Labor
Construction Equipment
Subcontract Work
Mobilization and Demobilization Costs
Indirect Costs
Profit
Bond
Contract Modification Estimates
Current Working Estimate (CWE)
Quality Assurance
Supplemental Information
Clarification
DD Form 1391
18.9
SCOPE
18.10
18-1
18.11
18.10.5
18.10.6
TECHNICAL
18.11.1
18.11.2
18.11.3
18.11.4
18.11.5
18.11.6
18.11.7
EXHIBITS
18-1 Field Indirect Costs
18-2 Weighted Guideline Method for Derivation of Profit Factor
18-3 Technical Quality Control Checklist
18-4 Creating a New Project Checklist
18-5 Print Submittal Reports Checklist
18-6 Contingencies and Supervision & Administration
18-2
CHAPTER 18
COST ESTIMATES
18.l
GENERAL
APPLICABLE PUBLICATIONS
Unified Facilities Criteria (UFC)
UFC 1-300-08 series
Cost Engineering
ER 1110-2-1302
ER 1110-3-1300
ER 1110-3-1301
GENERAL INSTRUCTIONS
DELIVERABLES
18-4
the Internet (See Paragraph 18.3 above). Access to each cost estimate
and its contents shall be limited to those persons whose duties require
knowledge of the cost estimate.
(b) Estimate. (Required for all submittals, number of copies
specified in Appendix A, A-E Design Contracts). For manually-prepared,
the complete detail and required summaries; for MII, all material
printed out in accordance with the Project Template, in reduced size
(8-1/2x11), landscape, and suitably-bound. MCACES 2nd Generation
(MII) guidance can be obtained from the Mobile District Cost Engineering
Branch. All electronically prepared cost estimates can be e-mailed or
ftped to the Mobile District Cost Engineering Branch. The Ready-ToAdvertise (RTA) cost estimate that is submitted to the Government shall
be accompanied by a letter of transmittal, which includes the following
statement: To the best of my knowledge the confidential nature of this
estimate has been maintained. This statement should be signed, dated
and maintained until the official markings have been removed. A-E RTA
estimates shall include all amendments that might occur during the
advertising period.
(c) Bid Schedule. (Required for all submittals.) Prepare in a
format in accordance with instructions in Chapter 3 SPECIFICATIONS.
During design, Bid Schedules frequently change as selected features may
need to be covered under separate bid items. The final Bid Schedule
will be as directed or approved by the Government.
(d) AF Form 1178. (Required for all submittals on Air Force
Projects only), properly filled out in accordance with the instructions
below. A blank AF Form 1178 can be downloaded off the Internet (See
Paragraph 18.3 above).
completed.
18-5
ESTIMATOR QUALIFICATIONS
METHODS OF ESTIMATING
18.6.1
General
18-6
Under the MCACES 2nd Generation (MII) procedure, the estimate shall be
prepared as explained in the Statement of Work-Cost Estimating Criteria.
Further detailed instructions and specific information will be provided
separately as necessary by the Mobile District Cost Engineering Branch.
18.6.4
Manual
Excel Spreadsheet
SUBMITTAL REQUIREMENTS
18.7.1
General
Cost Control
18-7
Format
18.7.3.1
General
18-8
Military Projects
HTRW Projects
HTRW Environmental Restoration Projects shall use the HTRW WBS. The
HTRW WBS provides the framework for preparing cost estimates, modeling
development, and collecting historical data for all remediation
projects. The WBS consists of a numbering and title system that details
the work to four levels of the WBS to organize the HTRW estimate. As a
minimum, all estimates shall be prepared to the fourth level followed by
detail. The quantity take-off shall be prepared following the WBS to
the same level. In no case shall the WBS title descriptions be changed
for levels one through four. Levels five and six are optional. New
titles for work not covered in the WBS may be added under numbers 90
through 99. Maintaining this rigid structure for the first four levels
will allow systematic collection of historical HTRW costs. Any vertical
building construction required within the HTRW project shall be a
separate estimate from the environmental work and shall follow the
Military WBS. HTRW projects will likely have two distinct phase;
construction of a treatment facility and operation and maintenance of
the facility over a period of time that may range from months to years.
Construction and operating wage rates, escalation rates, and other cost
18-9
Bid Schedule
Contractor Type
Cost Breakdown
18.7.4.1
General
Costs must be broken down into priceable elements. All cost and
quantities in the estimate must be supported. Unsupported lump sum
pricing is not acceptable at any stage of design. The level of
breakdown must be commensurate with detail available from the design
documents.
18.7.4.2
18-10
The Interim Design Submittal Cost Estimate shall be prepared in task-bytask detail to accurately reflect the scope of work shown in the
submittal. This cost estimate provides good cost control prior to final
design.
18.7.4.5
Ready-to-Advertise (100%)
(a) After all bids are received and they are significantly higher
than the Government Estimate to be determined unreasonable, there is a
possibility that one or more bidders will protest the reasonableness of
the Government Estimate. In addition, the designer/cost consultant
Final Bid Price Estimate may not be within 15 percent of the low
responsive bid at bid opening time. If this occurs, the designer has a
major role in reviewing the Government Estimate and evaluating the
Government's position. The designer/cost consultant will promptly
conduct an independent review of the Government estimate at no
18-11
TECHNICAL REQUIREMENTS
18.8.1
General
Quantity Survey
18-12
Material Pricing
18-13
Labor
18.8.4.1
Wages
Labor costs in the estimate must be based on rates that include basic
wages, overtime and holiday premium payments, and Contractor's
contributions for fringe benefits such as health and welfare, holiday
and vacation pay, pension fund, apprentice training, etc. Estimated
rates should be those which the contractor will be expected to pay when
the project is actually constructed and must consider prevailing rates
actually being paid in the project area as well as minimum rates which
will be included in the contract in accordance with the requirements of
the Davis-Bacon Act. Information on wages may be available from various
sources, such as Corps field offices, Mobile District Cost Engineering
Branch, contractors in the project area, etc. Ultimately, the designer
is responsible for all wage rates used in the cost estimate.
18.8.4.2
Unit Costs
18.8.4.2.1
General
PACES
PACES does not use specific project location wage rates to develop unit
costs, but uses location modifiers to adjust material, labor, and
construction equipment costs based on the location of the project.
However, PACES scope and cost can be exported to MCACES 2nd Generation
MII where specify line items can be adjusted.
18.8.4.2.3 MCACES 2nd Generation (MII)
For MII estimates, labor unit cost is a function of the crew unit cost
and the value for crew daily output included for each task. The
18-14
The contractor's cost for Social Security taxes (FICA), Federal and
State Unemployment Insurance, Workmen's Compensation and Employer's
Liability Insurance and any other social benefits must be included in
the estimate as a percentage of the labor costs. Guide for Estimating
Payroll Taxes & Insurance can be downloaded off the Internet (See
Paragraph 18.3 above).
18.8.5
Construction Equipment
Subcontract Work
18-15
Indirect Costs
18.8.8.1
General
Profit
The estimate shall include appropriate allowances for profit. For the
prime Contractor and for subcontractors whose work is a significant
portion of the project, rates for profit allowance will be determined by
18-16
Bond
Quality Assurance
Supplemental Information
Clarification
18-17
18.8.16
DD Form 1391
SCOPE
18.10.2
18.10.2.1
General
Labor Rates
Sample Projects
18-18
Sample Projects are provided for review of the required format for the
Civil, HTRW and Military type of estimates prepared by the U.S. Army
Corps of Engineers.
18.10.4
Templates
Templates shown below are used to start the respective project. For
Military Estimates the Project Template Military v2.mlp(depending on
the WBS specified) is to be used to create the estimate format. For
Civil Estimates use a User template defined by the estimators
requirements. Both templates are required to be used with applicable
Cost Book, Equipment, Labor and User Cost Book Libraries.
18.10.5
Training
MII training is available through Project Time & Cost, 2727 Paces Ferry
Road, Suite 1-1200, Atlanta, GA 30339, and telephone number (770) 4449799.
18.11
Estimate Format
18-19
are for the interior of the building (5-foot line outside the building)
and system 16 Selective Building Demolition fall under Primary
Facilities. Systems 17 through 20 are exterior systems and fall under
Support Facilities.
18.11.2
18-20
Project
Scope - Primary/Support/Additive Alternate/Option
Bid Item Primary Facilities
System (WBS)
Subsystem
Assembly Categories, Bid Item Supporting Facilities
Assembly
Detail
(1) Project (Level 1). All cost of the Primary and Support
Facilities are accumulated to obtain a total project cost. This shall
include all construction cost as well as Government-Furnished materials
and items furnished through other than construction funds, i.e.
information systems. Escalation, Construction contingency and
Supervision & Administration (S&A) or Supervision, Inspection & Overhead
(SIOH) Costs are added at this level.
(2) Scope - Primary/Support/Additive Alternate/Options
(Level 2). Divides the project into Primary Facilities, Support
Facilities, Category E Equipment and Government-Furnished Equipment
based on DD Form 1391 format for the project. Additive Alternates or
Options shall also be located at this level if required.
(3) Bid Items - Primary Facilities (Level 3). Individual
Facilities under Primary Facilities will be all individual
building/major construction features. Individual Facilities under the
Support Facilities shall be eight categories under Support Facilities of
the DD Form 1391.
(4) System (Level 4). Under Primary Facilities the
interior Military WBS System 01 through 15 and System 16 are titled at
this level. If there are multiple Primary Facilities, each one shall be
broken down by the 01 through 16 Systems. Under Support Facilities the
Military WBS Systems 17 through 20 are broken down under the appropriate
eight categories defined by DD Form 1391.
(5) Subsystem (Level 5). This level contains the Subsystem
titles from the Military WBS for the above Systems. If there are
subsystems in the project not identified by the Military WBS, they shall
be identified using 90 through 99 under the appropriate System.
(6) Assembly Category, Bid Item - Supporting Facilities
(Level 6). This level contains the Assembly Category titles from the
Military WBS for the Subsystems above. If there are Assembly Categories
in the project not identified by the Military WBS, they shall be
identified using 90 through 99 under the appropriate subsystem. In
addition, this level contains the Bid Items for the Supporting
Facilities.
(7) Assemblies (Level 7). Assembly Titles shall be created
at this level following the definitions contained in the WBS.
(8) Detail (Level 8). Individual Cost Items are located at
this lowest level in the cost estimate and reports at this level are
referred to as Detail Reports. These are the basic work tasks
18-21
Project
Scope - Primary/Support/Additive Alternate/Option
Bid Item Both Primary and Supporting Facilities
Systems (CSI or Trades Structure)
Optional
Optional
Optional
Optional
Note: Detail can be at either optional level.
(1) Project Level (Level 0). All cost of the Primary and
Support Facilities are accumulated to obtain a total project cost. This
shall include all construction cost as well as Government-Furnished
materials and items furnished through other than construction funds,
i.e. information systems. Escalation, Construction contingency and
Supervision & Administration (S&A) or Supervision, Inspection & Overhead
(SIOH) Costs are added at this level.
(2) Scope - Primary/Support/Additive Alternate/Options
(Level 1). Divides the project into Primary Facilities, Support
Facilities, Category E Equipment, and Government-Furnished Equipment
based on the DD Form 1391 format for the project. Additive Alternates
or Options shall also be located at this level if required.
(3) Bid Item - Both Primary & Supporting Facilities (Level
2). Individual Facilities under Primary Facilities will be all
individual building/major construction features. Individual Facilities
under the Support Facilities shall be items such as: Exterior
Electrical Distribution, Water Supply System, Sanitary Sewer System,
Site Improvements, Parking Lot, Landscaping, etc.
(4) System. Under this title show the Construction
Specification Index (CSI) items, such as: Concrete Moisture Protection,
Finishes, Specialties, etc. or Trades, such as Asbestos removal,
Plumbing, Insulation, Controls, Test & Balance, etc. or a combination of
both. The major features of the project should be shown at this level.
(5) Optional levels. These levels could be used to further
define the project features. Detail can be at level 4, 5, 6 or 7.
18.11.3
All sheets of the cost estimate and quantity take-off shall be clearly
marked as to the design stage (concept, preliminary, final, etc.) the
cost estimate represents. The design stage identity shall be entered on
the cover page of the estimate.
18.11.4
18-22
Profit
18.11.6.1
The settings for reports within MII should be displayed in the Other
Options with specific settings. This would apply to all previously
created reports.
18.11.6.2
To change the rounding options for a previously created report, open the
report using the report icon from the tool bar, or select the open
option from the report menu. The report can also be selected from the
list of opened reports. After selecting the appropriate report, select
the show options button to display sections.
18.11.7
Required Services
18-23
18-24
2.
Engineering Personnel
Project Engineer
Office Engineer
Quality Control Engineers
Surveyor and Surveymen
Draftsmen
3.
Office Staff
Office Manager
Payroll Clerk
Clerk-Typists
Purchasing Agent
Janitor
4.
Miscellaneous Staff
Safety Engineer, Nurse, First-Aid Attendant
Warehousemen
Clerks
Security Personnel
5.
Job Expenses
Office Facilities
Shops, Warehouses, and Yards
Laboratory and Testing Expense and Facilities
Night Lighting Work Area
Construction and Maintenance of Access and Haul Roads
Office and Engineering Supplies and Equipment
Water, Power, Telephone, Radios, Sanitary Facilities
Project Sign and Bulletin Board
Vehicles and Transportation Expenses
Travel, Subsistence, Housing, etc. for Key Personnel
Permits, Easements and Rights-of-Way
Builders Risk Insurance
Environmental Protection, Dust Control, and Restoration
Progress Schedules and Reports
Job Cleanup
EXHIBIT 18-1
18-25
RATE
20 x
15 x
15 x
15 x
5 x
5 x
25 x
WEIGHT(.03-.12)
=
=
=
=
=
=
=
TOTAL
=
VALUE
_____
_____
_
_____
_____
_____
_____
_____
EXPLANATION OF WEIGHTS:
Degree of Risk. Weight within range of .03 for slight risk to
.12 for highest risk. Consider lump sum items riskier than unit price
items. Also, consider nature and location of work, amount
subcontracted, ratio of labor to total cost and whether work has already
been accomplished.
Relative Difficulty. Weight within range of .12 for most
difficult and complex to .03 for simplest work.
Size of Job.
Size of Job
$
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
900,000
1,000,000
100,000
200,000
$100,000
200,000
300,000
400,000
500,000
600,000
700,000
800.000
900,000
1,000,000
100,000
200,000
300,000
0.120
0.119
0.117
0.116
0.114
0.113
0.111
0.110
0.109
0.107
0.106
0.104
0.103
Size of Job
600,000
700,000
800,000
900,000
3,000,000
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
Factor
700,000
800,000
900,000
3,000,000
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
900,000
0.083
0.081
0.080
0.079
0.077
0.076
0.074
0.073
0.071
0.070
0.069
0.067
0.066
18-26
Size of Job
300,000
400,000
400,000
500,000
500,000
600,000
600,000
700,000
700,000
800,000
800,000
900,000
900,000
2,000,000
2,000,000
100,000
100,000
200,000
200,000
300,000
300,000
400,000
400,000
500,000
500,000
600,000
Factor
0.101
0.100
0.099
0.097
0.096
0.094
0.093
0.091
0.090
0.089
0.087
0.086
0.084
Period of Performance.
Size of Job
900,000
4,000,000
4,000,000
100,000
100,000
200,000
200,000
300,000
300,000
400,000
400,000
500,000
500,000
600,000
600,000
700,000
700,000
800,000
800,000
900,000
900,000
5,000,000
5,000,000
10,000,000
OVER
10,000,000
Factor
OVER
23 TO
22 TO
21 TO
20 TO
19 TO
18 TO
17 TO
16 TO
15 TO
14 TO
13 TO
24
24
23
22
21
20
19
18
17
16
15
14
MONTHS
MONTHS
MONTHS
MONTHS
MONTHS
MONTHS
MONTHS
MONTHS
MONTHS
MONTHS
MONTHS
MONTHS
Note:
extension.
Factor
0.064
0.063
0.061
0.060
0.059
0.057
0.056
0.054
0.053
0.051
0.050
0.040
0.030
0.120
0.116
0.112
0.109
0.105
0.101
0.098
0.094
0.090
0.086
0.082
0.079
12
11
10
9
8
7
6
5
4
3
2
1
TO
TO
TO
TO
TO
TO
TO
TO
TO
TO
TO
TO
13 MONTHS
0.075
12 MONTHS
0.071
11 MONTHS
0.068
10 MONTHS
0.064
9 MONTHS
0.060
8 MONTHS
0.056
7 MONTHS
0.052
6 MONTHS
0.049
5 MONTHS
0.045
4 MONTHS
0.041
3 MONTHS
0.037
2 MONTHS
0.034
UNDER 30 DAYS
0.030
OR
TO
TO
TO
TO
TO
TO
TO
--
MORE
80%
70%
60%
50%
40%
30%
20%
--
0.030
0.042
0.055
0.068
0.080
0.092
0.105
0.118
0.120
EXHIBIT 18-2 (End)
18-27
[
] A complete detailed cost estimate?
[
] All supporting backup?
[
] All applicable design documents (plans, specifications,
design analysis, etc.)?
[
] Annotated Comments?
[
] Has cost estimate been approved by the Chief, Cost Engineering
Branch?
[
[
] Is the Sign-thru Cover Sheet for the Government Estimate that
discloses the overall project cost estimate stamped FOR OFFICIAL USE
ONLY?
[
] Has the Project Manager been notified of the estimated price
verses the available funds?
CONTRACT REQUIREMENTS (A-E/COST CONSULTANT ONLY)
[
[
] Has the Cost Estimate been submitted in the required number of
copies, suitably-bound, in landscape?
[
BID SCHEDULE
[
] Does the Bidding Schedule contain Bid items for the following
work features, if applicable?
[
] Each Building to the 5 ft line?
[
] Major site features (e.g. Sanitary Sewer System, Exterior
Electrical Distribution, Parking Lot, etc.)?
[
] Design Costs?
[
] Asbestos Abatement?
[
] Unit Cost Items (e.g. Rock Excavation, Unclassified
Excavation, etc.)?
[
] Pre-Wired Work Stations?
EXHIBIT 18-3 (Continued)
18-28
[
[
[
[
]
]
]
]
FORMAT
[
[
] Were the correct Cost Libraries used in preparing the cost
estimate?
[
] Is the cost estimate in the required Work Breakdown Structure
(WBS) to Level 4 (Subsystem)?
[
] Is the cost estimate structured according to the type contractor
most likely to bid as prime?
[
] Has a sufficient number of subcontractors been developed for the
project?
[
] Is a majority of the work selected to be done by the prime
contractor or subcontractor(s) according to normal construction
practice?
[
] Does the cost estimate include escalation, construction
contingency and SIOH?
[
] Is the cost estimate so structured to be directly comparable to
the project Bid Schedule?
[
[
] Is the cost estimate within the Construction Cost Limitation
(CCL)?
[
] If the cost estimate is more than the CCL, have Additive
Alternates or Options been identified that bring the Base Bid within the
CCL?
[
[
] Has the cost estimate been compared to the previous cost
estimate?
[
] If the cost estimate has changed more than 5% (+ or -) from the
previous cost estimate, has reasons why been documented?
[
18-29
[
] Have specialty construction tasks (e.g. scaffolding, noise & dust
control, phasing, etc.) been included in the cost estimate?
[
MAGNITUDE OF DETAIL
[
] Is the Level of detail commensurate with detail available from
the design documents?
[
BACKUP
[
] Has all Backup (Quantity Takeoff, Quantity Derivations and
Quotations) been furnished?
[
] Is all Backup traceable to the line item task in the cost
estimate that it supports?
[
Did the reviewer spot check critical cost items and quantities?
[
] Does quotation used include all applicable costs (e.g.
manufacturer/supplier, location, person contacted, telephone number,
date, freight to job site, etc.)?
[
Does the wage rates reflect the local prevailing wage rates?
EXHIBIT 18-3 (Continued)
18-30
[
] Does the total wage rate shown include basic wage rate, fringes,
OT, payroll taxes & insurance, etc.?
[
] Do the labor productivities used consider project conditions,
labor availability, market conditions, etc.?
DIRECT COST - CONSTRUCTION EQUIPMENT
[
] Has Construction Equipment Cost for major items been included in
the cost estimate?
[
[
] Has any construction equipment been included using rental
rates?
SUBCONTRACTED WORK
[
[
] Is all major subcontractor work detailed?
maybe unit priced.
Note:
Minor work
[
] Does the project contain any work that is normally done by a 2nd
Tier
Subcontractor Work (e.g. Controls, Test & Balance, Insulation, etc.)?
[
] Were subcontractor quotes obtained to verify the reasonableness
of the of the estimate for the subcontractor work?
[
[
] Has the Prime Contractor Field overhead been prorated to all Bid
Items proportionally to the direct costs?
[
] Have those items in the specification Special Clauses that are
normally considered Field Overhead Items been incorporated into the
cost estimate?
[
[
] Has Mobilization/Demobilization costs been included in the cost
estimate?
[
] Do overhead salaries shown include an allowance for payroll taxes
& insurance?
[
[
] Is Prime Contractor Home Office Expense included in the cost
estimate?
[
18-31
PROFIT
[
[
] Was Profit for the Prime Contractor determined using the
Weighted Guideline Method?
[
] Were the fixed cost (Size of Job, Period of Performance, Amount
of Subcontracting) portion of the Weighted Guideline Method done
correctly?
[
] Were the judgmental factors (Degree of risk, Relative Difficulty
of Work, Contractors Investment, Assistance by Government) reasonable?
BONDS
[
COST ESCALATION
[
[
] Were all construction costs escalated to the Midpoint of
Construction? Note: Army - Escalate from Midpoint of Estimate to
Midpoint of Construction, AF - Escalate from Date of Submittal to
Midpoint of Construction.
[
CONSTRUCTION CONTINGENCY
[
] Was a Construction Contingency percentage shown in the cost
estimate?
[
MODIFICATIONS
[
[
] Has adequate information been received to reflect actual
contractor rates?
[
Has the original scope and changed scope been clearly defined?
[
] Does the estimate include costs and time for the impact on the
unchanged work?
EXHIBIT 18-3 (Continued)
18-32
DREDGING
[
[
] Does the narrative document the decisions and selections made
within CEDEP?
[
] Has effective working time been calculated considering lost time,
weather delays, etc.?
[
] Have estimate results been compared against historic information
and reconciled if necessary?
[
] Has the estimate been compared against data from similar
projects?
[
] Have production rates been calculated considering pumping rate,
travel time, line size, navigational delays, etc.?
[
] Have environmental requirements (beach and offshore) been
included?
[
] Does the estimate reflect correct environmental windows for the
project area?
18-33
[
] The Project Template has been copied to new six characters ID for
this project.
[
] The New Project has now been selected, and name of project
edited.
[
[
] The required Assembly Titles for all Primary and Support
Facilities have been
created and detailed items entered into the Assemblies.
[
] All System, Subsystem, and Assembly Category Titles not required
in this project
have been deleted and the Project has been Packed.
[
] All subcontractors not required in this project have been
deleted.
EXHIBIT 18-4
18-34
[
] Prime Profit has been calculated by the Weighted guideline
Method.
[
[
] Prime and Subcontractors have been assigned at the appropriate
locations within the project.
[
] Any Subcontractors not applicable to this project have been
deleted.
[
[
] Estimate Status (35%, 60%, 95% etc.) has been entered in the
Report Title field or the Print Selected Reports Window.
[
EXHIBIT 18-5
18-35
AIR FORCE
CONTINGENCIES
NEW WORK
5%
5%
10%
10%
ADDITIONS/ALTERATIONS
10%
5%-IF ADDITION
IS LARGEST
10%-IF ALTERATION
IS LARGEST
S&A (SIOH)
NEW WORK
6.0% (CONUS)
6.5% (OCONUS)
6.0%
6.0% (CONUS)
6.5% (OCONUS)
6.0%
INSTALLATION SUPPORT
8.0% (CONUS)
8.5% (OCONUS)
N/A
EXHIBIT 18-6
18-36
CHAPTER 19
ANTITERRORISM/FORCE PROTECTION (AT/FP)
INDEX
19.1
GENERAL
19.1.1
19.2
APPLICABLE PUBLICATIONS
19.3
19.4
19.5
19.6
19.7
19.8
TECHNICAL REQUIREMENTS
19.8.1
General Considerations
19.8.2
Site
19.8.3
Architectural
19.8.4
Structural
19.8.5
Mechanical
19.8.6
Electrical
Scope
19-1
CHAPTER 19
ANTITERRORISM/FORCE PROTECTION
19.1
GENERAL
19.1.1
Scope
APPLICABLE PUBLICATIONS
Unified Facilities Criteria (UFC)
19.3
UFC 1-200-01
UFC 4-010-01
UFC 4-010-02
UFC 4-023-03
19.3.1
General Considerations
AT/FP design shall be integrated into the overall facility design from
the beginning of the project. At the Project Definition phase the
designer shall investigate the AT/FP measures required for the project.
The designer shall determine if the setback distances required for
conventional construction can be provided within the project
constraints or if further analysis and building hardening is likely to
be required. In addition, any building elements requiring special
design, such as mail rooms, equipment enclosures, progressive collapse,
etc. shall be noted for use in preparing the cost estimate.
19.3.2
Narrative
The Project Definition narrative shall include, but not be limited to,
the following items as applicable:
(a) List all antiterrorism/force protection references used in
the Project Definition design including Government design documents,
industry standards, and criteria given to the designer at the charrette
or predesign meeting.
19-2
19.4.1
General Considerations
Design Analysis
19-3
19.5
Design Analysis
Design Analysis
Specifications
TECHNICAL REQUIREMENTS
19.8.1
General Considerations
19-4
integrated into the overall facility design from the beginning of the
project through coordination of all disciplines. Antiterrorism/force
protection requirements shall be met in the most effective and
economical method. These methods include maximizing standoff
distances, preventing building collapse, minimizing hazardous flying
debris, providing effective building layout, limiting airborne
contamination, providing mass notification, and facilitating future
upgrades. Antiterrorism/force protection requirements shall be
coordinated with all other applicable DoD building and design criteria
and policies. Where other criteria mandates more stringent
requirements, the provisions of those criteria will be followed.
19.8.2
Site
Landscape Architecture
Architectural
19-5
Structural
Mechanical
(a) Outdoor air intakes must be at least 10 feet above the ground
for new buildings and as close as possible to 10 feet above the ground
for existing buildings.
(b) There must be an emergency shutoff switch in the HVAC control
system that can immediately shut down air distribution throughout the
building.
(c) Chillers (and all major mechanical equipment) should be
located outside the unobstructed space, at least 33 feet from the
building. If they are located within the unobstructed spaces and have
19-6
Electrical
19-7
CHAPTER 20
SUSTAINABLE DESIGN AND DEVELOPMENT (SDD)
INDEX
20.1
GENERAL
20.1.1
20.2
APPLICABLE PUBLICATIONS
20.3
SDD CRITERIA
20.3.1
Army
20.3.2
Air Force
20.3.3
Other Customers
20.3.4
Registration
20.4
20.5
20.6
20.7
20.8
Scope
20-1
CHAPTER 20
GENERAL
20.1.1
Scope
APPLICABLE PUBLICATIONS
Army
ECB 2003-20
Engineering and Construction Bulletin (ECB) 200320, Sustainable Project Rating Tool (SPiRiT)
ECB 2006-2
SDD CRITERIA
Army
(a) SPiRiT will be used for designated FY07 Army projects documenting
a Gold rating level. Designated Army projects may require use of the
USGBC Leadership in Energy and Environmental Design - New Construction
20-2
(LEED-NC) rating tool. For FY08, all Army Military Construction Army
(MCA) vertical climate-controlled facilities will be capable of
achieving certification using LEED-NC documenting a Silver rating level
unless exempt. At present registration and certification are not
required. However, projects designed to be certifiable at LEED Silver
will be subject to substantiation by the U.S. Army Corps of Engineers
(USACE) headquarters.
(b) Army MILCON Transformation (MT) designated projects developed for
Design-Build acquisition are required to use the Model Request for
Proposal (RFP). See Chapter 24 MILCON TRANSFORMATION. The Model RFP
contains specific requirements for Army SDD for those designated
projects.
20.3.2
Air Force
Other Customers
SDD rating, rating system, and design development for other military
services or customers will be determined by the Mobile District Project
Manager (PM) prior to the pre-design meeting and issuance of the SOW.
20.3.4
Registration
Submit the appropriate SDD rating tool and supporting narrative as part
of the Design Analysis. The narrative shall be developed in a
paragraph format matching the rating tool structure. For each point or
points in the rating tool, provide a brief description in the narrative
of the feature and how the point/s will be achieved. Briefly describe
future operation and maintenance requirements for selected features.
For features considered but not incorporated briefly describe the
feature and reason/s for non-selection. For each point to be achieved,
include a brief description of specific actions required of the
Resident Engineer and Contractor during construction.
20.5
20.5.1
Design Analysis
(a) Provide the SDD rating tool and narrative required at Project
Definition.
(b) For each anticipated achievable point or points that requires
production of a document, calculation to measure achievement of goals,
20-3
20.6.1
Design Analysis
The Design Analysis shall include all items in the Concept Design
Analysis narrative and any revisions made necessary by comments about
the Concept Design submittal. For USGBC registered projects, continue
development of the LEED letter templates, and submit as part of the
narrative.
20.6.2
Specifications
Drawings
20.7.1
Design Analysis
The Final Design analysis narrative shall include all items in the
Interim Design analysis narrative and any revisions made necessary by
comments about the Interim Design submittal. For USGBC registered
projects, complete the LEED letter templates, and submit as part of the
narrative.
20.7.2
Drawings
Specifications
20-4
20-5
CHAPTER 21
QUALITY MANAGEMENT
INDEX
21.1
GENERAL
21.1
Scope
21.2
APPLICABLE PUBLICATIONS
21.3
DEFINITIONS
21.3.1 Quality Control Plan (QCP)
21.3.2 Quality Assurance Plan (QAP)
21.3.3 Mobile District Project Manager (PM)
21.3.4 Mobile District Project Architect Engineer (PAE)
21.4
PROCEDURES
21.3.1 Pre-Design Conference
21.3.2 QCP and QAP Preparation
21.3.3 Project Management Plan (PMP)
21.3.4 Designer Project Visits
21.3.5 Design Budget
21.3.6 Installation Criteria
21.3.7 Design Schedule
21.3.8 Value Engineering (VE)
21.3.9 Design Submittal Review and Independent Technical Review
(ITR)
21.3.10 ITR Certification
21.3.11 Lessons Learned
21.3.12 Bidability, Constructability, Operability, and
Environmental (BCOE) Review Certification
21.3.13 Project Files and Document Management
21.3.14 As-Built Drawings
EXHIBITS
21-1
In-House Design Quality Control Plan Format
21-1
CHAPTER 21
QUALITY MANAGEMENT
21.1
GENERAL
21.1.1
Scope
APPLIABLE PUBLICATIONS
Army Regulation (AR)
AR 5-1
Total Army Quality Management
Engineer Regulation (ER)
ER 11-1-321
Value Engineering
ER 415-1-11
ER 415-1-13
ER 1110-1-12
Quality Management
ER 1110-1-8159
ER 1110-1-8158
ER 1110-2-112
ER 1110-2-1150
ER 1110-3-111
Lost Design
ER 1110-345-100
21-2
DEFINITIONS
21.3.1
The QCP is a written plan that defines how quality management will be
executed for I-H products. The QCP is prepared by the PAE in
coordination with the PDT.
21.3.2
PROCEDURES
21.3.1
Pre-design Conference
21-3
Project specific QCP and QAP procedures will be included in the PMP
prepared by the PM in coordination with the PDT.
21.3.4
21-4
Public Works, and USACE Resident Engineer at, or responsible for, the
installation prior to the visit.
21.3.5
Design Budget
DrChecks
21-5
251-694-3743
251-690-3106
251-690-2672
[email protected]
[email protected]
[email protected]
21-6
ITR Certification
Lessons Learned
(a) The Design Quality Lessons Learned module of DrChecks has been
mandated for use in compiling lessons learned. Procedures for use of
DrChecks for lessons learned, and any future certification
requirements, will be announced when updated lessons learned are
compiled and procedures finalized.
(b) Certification and use of the current lessons learned listing at
the following website is suspended.
http://www.sam.usace.army.mil/leslrn/llhome.asp
The database of lessons learned at the website have been evaluated as
no longer applicable, incorporated in this Manual, incorporated as
changes to the guide specifications, or incorporated in installation
criteria where appropriate.
21.3.12 Bidability, Constructability, Operability, and
Environmental (BCOE) Review Certification
A BCOE review will be conducted by the executing Construction or
Operations Division field office on all D-B-B and D-B projects. The
BCOE review will be conducted at the Final (100% Unreviewed) submittal
phase. EN-DW will provide the design documents to Construction
Division. Comments will be entered in DrChecks. Designers will
resolve the comments and annotate them in DrChecks for back check.
After the PAE verifies that all comments have been annotated and
resolved to the satisfaction of the BCOE reviewers, the PAE shall
request that EN-DW create the BCOE certification letter. This letter
will have annotated BCOE comments attached. The BCOE certification
letter and attachments will then be sent from EN-DW to the Chief,
Design Branch, Mobile District Engineering Division for signature.
After signing, the BCOE certification letter will be forwarded to the
responsible Resident Engineer for signature. The certification letter
should reach the Resident Engineer on, or near, the day the project is
to be advertised. After signing, the Resident Engineer will forward
the letter to Contracting Division (CT) and copy furnished to EN-DW and
the PM.
21.3.13
21-7
21.3.14
As-Built Drawings
21-8
(NAME OF PROJECT)
(LOCATION OF PROJECT)
(DATE)
21-9
3.
a.
Project:
b.
Location:
c.
CADD ID:
d.
Programmed amount:
e.
References:
4.
b.
c.
d.
Responsibilities:
21-10
Control Plan (QCP) in the Project Management Plan (PMP) for the
project.
c. Project Architect Engineer (PAE): The PAE is responsible for
writing the QCP, scheduling, and documenting Quality Control
milestones, and for insuring these events follow established
procedures. The PAE will also lead QC conferences and insure design
and review teams comply with the QC Plan.
d. Design Review Team (Senior Technical Leaders) (DRT): The DRT is
responsible for providing the Independent Technical Review (ITR) and is
comprised of the Senior Technical Leaders in each discipline of
Engineering Division. The Senior Technical Leaders are as follows:
(REVIEW AND EDIT AS REQUIRED)
EN-DA Architectural
Bill Thomas
(251) 694-4089
EN-DA Structural
Don Smith
(251) 690-3489
EN-DE Mechanical
Clay Thames
(251) 690-2671
EN-DE Electrical
Larry Covert
(251) 694-3737
EN-DA Site Development
Randy Goff
(251) 690-2788
EN-GE Environmental/Utilities Joe Findley
(251) 694-4012
EN-GG Geotechnical
Mike McKown
(251) 690-2681
5.
Design Tools:
Estimating Tools:
Management Tools:
21-11
Procedures:
21-12
21-13
CHAPTER 22
DESIGN-BUILD (D-B) REQUEST FOR PROPOSAL (RFP) DEVELOPMENT
INDEX
22.1
GENERAL
22.1.1
22.2
APPLICABLE PUBLICATIONS
22.3
D-B APPROACHES
22.3.1
Army MT D-B RFP
22.3.2
D-B RFP Development for Other Than Army Customers
22.4
22.5
22.6
Scope
22.7
22.8
EXHIBITS
22-1 Color Schedule for D-B RFP Section 01 10 10
22-2 Preliminary Room Finish Schedule
22-3 Sample Section 01 10 10 Design Requirements
22-4 Sample Section 01 10 12 Design After Award
22-1
CHAPTER 22
GENERAL
22.1.1
Scope
APPLICABLE PUBLICATIONS
D-B APPROACHES
22.3.1
MT D-B RFP
Projects acquired through this D-B acquisition method shall follow the
requirements of the publications listed above under USACE Model RFP.
Any requests for deviation from the requirements stated in those
publications and current contract clauses shall be directed to the
Mobile District Project Manager (PM) for forwarding to USACE for final
determination. Deviations will only be granted by USACE. The USACE
intent is to ensure consistency across MT Model RFP projects. Facility
type (product line) requirements are being developed in specific
22-2
(a) USACE intent is to use the Model RFP to gain industry solutions
for the product lines. Beginning in Fiscal Year (FY) 08, COSs will
take these solutions and develop Army standard design adaptbuild/continuous build designs approaching an 80% solution (within the
area foot print of the product line). These designs are intended to be
acquired through regional indefinite delivery-indefinite quantity
contracts (IDIQ). For these projects, use of the Model RFP will end.
(b) Specific start dates for this adapt-build/continuous build
program for each product line is not set at the time this manual is
published. It is anticipated that the Model RFP will continue to be
used beyond FY08 for some product lines. For Army projects, the Mobile
District PM will determine the approach to be used prior to the
acquisition strategy meeting and pre-design meeting.
22.3.2
22.4.1
Site Work
22-3
22.4.1.1
Mandatory Requirements
The following are requirements and criteria that shall be included (as
applicable) in the RFP for every project regardless of the level of RFP
development:
(a) Provide a general overview of major site features planned, such
as building orientation, drainage patterns, parking provisions, traffic
circulation, provisions for the handicapped, security requirements,
etc.
(b) Provide a discussion of wetlands, as defined by Federal and/or
State criteria, historically significant areas, or areas with
endangered species of wildlife within the project site area.
(c) Provide discussion of items requiring removal or relocation,
method and location of the disposition of waste or salvage materials
and demolition phasing requirements.
(d) Provide discussion of the geometric layout of the project
facilities. Discuss orientation of building relative to existing site
features. Required offsets, site constrictions, site limitations and
impacts of new construction on existing facilities shall also be
discussed.
(e) Provide discussion of storm drain design scheme and the impacts
on the existing storm drain systems. Include minimum and maximum flow
velocities, pipe materials, slopes, distance between inlets, minimum
pipe size, types of structures, retention/detention requirements,
outfall end treatment, etc. Describe intended plan for the design of
sediment and erosion control for the project through implementation of
current Best Management Practices during construction.
(f) Provide selected design values to be used in the storm drainage
calculations such as surface runoff coefficient, retardance coefficients, infiltration rate, and rainfall intensity based on a 10-year,
25-year, and the 100-year storm frequency.
(g) Discuss existing site features affecting grading such as
buildings, streets, curbs, walks, fences, water courses, ponds,
elevation of high ground water, rock outcrop, etc. Discuss minimum and
maximum slopes to be used in the design for embankments, ditches,
pipes, etc.
(h) Provide specific design values for pavement thickness including
the number, type, and maximum weights of vehicles, traffic category,
class of road or street, and resulting design index. Flexible pavement
thickness shall be based on the design index and established subgrade
CBR. Minimum required thickness of base and pavement shall be 7-1/2
inches. Rigid Pavement thickness shall based on a 28-day flexural
strength concrete of 650 psi and the established modulus of subgrade
reaction. Minimum required thickness of nonreinforced concrete pavement
shall be 6-inches.
(i) Provide discussion of roads and streets to include listing of
traffic volumes and vehicle types, project design speed, maximum degree
22-4
Specific Requirements
Geotechnical
22-5
22.4.3.1
Mandatory Requirements
(a) Consult with the local user and Installation personnel to define
the extent of landscaping requirements, to determine appropriate plant
materials, and Installation grounds maintenance capabilities.
22.4.3.2
Specific Requirements
22.4.4.1
Environmental
22-6
22.4.4.1.1
Mandatory Requirements
Specific Requirements
22-7
(1) Include all elements of paragraphs 22. 4.3.2 (a) & (b)
Mandatory Requirements
(a) The water and wastewater systems shall be designed and specified
to the latest industry standards, codes, and Government regulations.
The RFP shall ensure high quality, energy efficient equipment and
systems with minimum maintenance. Design documents shall be submitted
and reviewed prior to commencing work on any treatment system.
22.4.4.2.2
Specific Requirements
22-8
22.4.4.3.1
Mandatory Requirements
22-9
Specific Requirements
22-10
22.4.4.4.1
Mandatory Requirements
22-11
performance data if the plant has been in operation long enough to have
established accurate data.
22.4.4.4.2
Specific Requirements
22-12
Mandatory Requirements
(a) The large sewage pump station and related ancillary appurtenances
shall be designed and specified to the latest industry standards,
codes, and Government regulations. The RFP shall ensure high quality,
energy efficient equipment and systems with minimum maintenance.
Design documents shall be submitted and reviewed prior to commencing
work on any wastewater treatment plant design-build project.
(b) The design-build RFP guidance shall comply with all applicable
Federal, State, and local codes, laws, and regulations. Any delays
resulting from failure to comply with these laws and regulations shall
be the responsibility of the D-B Contractor.
(c) The RFP shall include guidance that leads to the development of
important design factors that must be considered during the initial
planning and design stages of a large sewage pump station project.
These basic design factors include the following: site improvements,
structures, screening, and flow monitoring devices, pumping units, pump
drives, system controls and instrumentation, mechanical and electrical
components, interior piping, underground force mains, valves, and
appurtenances. The contractor shall address each topic at a level of
detail commensurate with the scope of work and tasks at hand. Topics
or issues which are not identified, but which the contractor considers
necessary, shall be identified and discussed after those items have
formally been identified.
(d) The design contractor must provide an engineered system
of sewers and pump stations, complete with all appurtenant facilities,
sufficient in size and capacity to collect and convey the required
wastewater flows to an acceptable point of discharge. The system must
be practicable, economically feasible, and all components must be
located to minimize the costs of installation, operation, and
maintenance. Sewers and appurtenances must be structurally sound, and
must protect the environment from pollution caused by leakage or
overflows.
22.4.4.5.2
Specific Requirements
22-13
Architectural
22.4.5.1
Mandatory Requirements
22-14
Specific Requirements
Interior Design
22.4.6.1
Mandatory Requirements
(a) The Structural Interior Design (SID) and the Furniture Fixtures
and Equipment Package (FFE) - formally known as the Comprehensive
Interior Design (CID) for the D-B RFP project delivery process requires
the project interior designer to edit two sections of the D-B RFP
solicitation. See Chapter 10 INTERIOR DESIGN.
(b) Coordination of interior design information with the
architectural and engineering disciplines is critical and necessary to
ensure no overlapping or conflicting criteria occurs in the D-B RFP.
(c) When developing the SID design criteria in a D-B RFP title the
paragraph Interior Design. Narratives within this paragraph should
discuss the following objectives.
(d) Exhibit 22-1 Color Schedule provides guidance for the sequence of
paragraphs for Structural Interior Design. The project interior
designer, project architect and other engineering disciplines that
address finishes are to fully coordinate the SID selections and
placement of materials, color, textures and patterns with the customer
to ensure complete customer satisfaction. Compare and coordinate all
SID information with the architectural and engineering design criteria
to eliminate conflicts and/or redundant design criteria. Ensure that
all exposed building related materials and fixtures requiring finishes
are addressed.
22-15
(e) When edited UFGS are part of the D-B RFP solicitation the
interior designer is to complete to the fullest extend possible UFGS
Section 09 06 90 Color Schedule and supporting UFGS.
(f) When UFGS are not provided in the D-B RFP, list the UFGS by
Section number and title and require the D-B Contractor to edit them
during the design phase after award. Establish minimum quality and
performance characteristics in a modified Color Schedule by adding
quality minimums and included it in the Structural Interior Design
criteria D-B RFP Section 01 10 10 Design Criteria. (For example, add
the minimum face weight, yarn type and carpet construction method in
the Carpet paragraph to establish a basis for quality such as Carpet,
CPT-1: 32 oz, tufted, graphic pattern, 100% solution dyed nylon;
Manufacturer Shaw, Style number 6087, Color 800 Blue).
(g) A preliminary Room Finish Schedule is be provided in the D-B
RFP Section 01 10 10 Structural Interior Design criteria and used in
combination with the Color Schedule to further define the SID in the
D-B RFP. Providing a preliminary Room Finish Schedule in a graphic
form is more efficient than using narrative. The Room Finish
Schedule shall be edited to establish minimum finishes for each room
type within the facility.
The Room Finish Schedule may be a table
similar to Exhibit 22-2 or it may be a typical schedule drawing. If a
drawing is used, verify drawings are permitted as part of the D-B RFP
solicitation package.
To establish minimum finish requirements
indicate floor, wall base, walls and ceiling finishes if a table is
used. The Color Schedule may be used to include specific details
needed to establish additional minimum finishes for casework, interior
signage, crown moldings, tile patterns and other details.
(h) SID materials, finishes and colors not discussed or required in
the D-B RFP Section 01 10 10 Structural Interior Design criteria may
not be provided by the Construction Contractor during the construction
phase of the project without additional funds and a "change order".
Therefore, it is important that a edited version of the UFGS Section 09
06 90 Color Schedule and UFGS list be included in the RFP design
criteria to ensure as much information about the quality, material,
finish and color of interior finishes is provided in the solicitation.
Project interior designers are to edit this schedule fully to ensure
the SID is fully integrated in the D-B RFP solicitation.
22.4.6.2
Specific Requirements
22-16
ITEM
1.
*
**
1.
**
1.a
**
1.b
**
1.c
**
2.
**
3.
**
22-17
PARTIAL
PROJECT
CRITERIA
35%-50%
FULL
PROJECT
CRITERIA
100%
X
4.
**
(d) For FFE requirements, a standard clause may be used in the RFP
Section 01 10 10 Design Criteria requiring the FFE package to be
developed after award of the contract under the base bid. If the
project specific FFE is required select and include one clause below,
and include this information in the narrative. Determine how the
furniture will be purchased and installed and provide the narrative to
indicate this process. Regardless of how the FFE is purchased and
installed, the FFE will be designed under the base bid contract. The
designer may modify the clauses to meet project specific requirements.
FFE-RFP Section 01 10 10 Design Criteria Matrix Summary
** Digital Data Presentation
ITEM
Standard clauses to use in
NOMINAL
PARTIAL
FULL
the
PROJECT
PROJECT
PROJECT
RFP
CRITERIA CRITERIA CRITERIA
"Section 01 10 10- Design
10%-30%
100%
35%-50%
Criteria
X
x.1 The FFE has been fully
STANDARD
developed and ready for
CLAUSE
procurement. The Contractor
**
is to coordinate building
changes with the USER and the
FFE package. All changes must
be coordinated with the User.
The User will be responsible
for updating the FFE based on
building related changes.
X
X
X.1 The Contractor shall be
STANDARD
responsible for the FFE
CLAUSE
requirement analysis survey
**
to determine the furniture
needs of the User. The
Contractor will develop the
FFE package in accordance
with the Mobile District
Design Manual Chapter 10
INTERIOR DESIGN. The
Government will provide the
brand name(s) of furniture to
use in the FFE package after
award of the D-B contract.
Furniture selected and
specified shall have a
current GSA contract or be
from UNICOR.
(d) The standard clause used in the D-B RFP Section 01 10 12 Design
After Award is a "bridge" clause because is involves both the SID and
FFE instructions to the D-B Construction Contractor. Some modification
to this clause may be needed to meet project specific requirements.
22-18
For example, if a FFE is not required, then revise the standard clause
by deleting the FFE submittal requirements.
ITEM
STANDARD
CLAUSE
22.4.7 Structural
22.4.7.1
Mandatory Requirements
Specific Requirements
22-19
Plumbing
Specific Requirements
22-20
22.4.9.1
Mandatory Requirements
(a) The HVAC systems shall be designed and specified to the latest
industry standards, codes, and Government regulations. The RFP shall
ensure high quality, energy efficient HVAC equipment and systems with
minimum maintenance. Design documents shall be submitted and reviewed
prior to commencing work on the HVAC system.
22.4.9.2 Specific Requirements
(a) Nominal Project Criteria
(1) Include a paragraph describing the HVAC system, any major
features such as central equipment and any special HVAC requirements
such as clean rooms, kitchens, humidity control, DDC Control System
type, etc.
(b) Partial Project Criteria
(1) Include a paragraph describing the HVAC system, any major
features such as central equipment and any special HVAC requirements
such as clean rooms, kitchens, humidity control, DDC Control System
type, etc.
(2) Describe the duct and pipe materials, and insulation to be
used on all plumbing systems.
(3) Include an outline of the specifications to be edited.
(c) Full Project Criteria
(1) Final Plumbing Plans (See Chapter 13 HEATING, VENTILATING,
AND AIR CONDITIONING.)
(2) Final Specifications (See Chapter 13 HEATING, VENTILATING,
AND AIR CONDITIONING.)
22.4.10
22.4.10.1
Mandatory Requirements
Type of construction.
Height and area limitation.
Building separation.
Fire resistive construction.
22-21
Specific Requirements
22.4.11.1
Mandatory Requirements
Specific Requirements
22-22
22.4.12.1
Mandatory Requirements
(a) All criteria that is not listed in the RFP will not normally be a
part of the RFP. Any specific UFC, TM, TI, MIL HDBK, etc. that is
required to be used shall be referenced as mandatory. A link to a web
site where the specific criteria can be obtained shall be provided.
22.4.12.1
Specific Requirements
22-23
Mandatory Requirements
22-24
(d) Require in the RFP that the D-B Contractor provide training for
each cathodic protection system.
(e) Codes and Standards. In addition to ETL 1110-3-474, referenced
above, the RFP must require the Design-Build contractor to comply with
all other relative corrosion control and cathodic protection system
requirements as contained in all of the criteria documents referenced
in this Chapter, as well as Codes and Standards, which may not be
included in this Chapter, but are relative to the locality.
(f) Require in the RFP, that all new metallic components that are
connected to existing metallic piping systems or other existing
metallic structures shall be electrically isolated from those existing
structures by the installation of an isolation flange, dielectric
union, or isolation valve. This requirement is mandatory regardless if
the existing piping system or other structure that is being connected
to currently has a cathodic protection system in place, even if the
existing system is operational.
(g) Special Cathodic Protection Requirements (e.g., conflicts with
grounding systems; structure interference considerations; structure
isolation considerations; coating requirements; special installation
problems, such as location of ground beds in conjunction with rock
formations; etc.).
(h) Require in the RFP, that only the latest Corps of Engineers
edition of the UFGS cathodic protection system specifications be
utilized in the contractors cathodic protection design. These
specifications must be utilized even if other portions of the RFP
design documents allow the use of specifications other than UFGS
specifications.
22.4.13.2
Specific Requirements
22-25
Antiterrorism/Force Protection
22.4.14.1
Mandatory Requirements
22-26
Specific Requirements
22.4.15.1
Mandatory Requirements
Specific Requirements
(a) During this phase the designer must define the customer's
requirements and confirm that they can be met within the project's
22-27
Model RFP
Criteria Drawings
Specifications
22-28
comply with the RFP and can be evaluated against the other proposals.
Requirements shall reflect the evaluation factors and agree with the
Project Criteria Approach. Evaluation will be performed by a government
Source Selection Evaluation Board (SSEB) and will be based on
evaluation of technical factors and price to select the "Best Value".
(d) Section 01 10 10 Design Requirements. Exhibit 22-3 outlines RFP
information requirements in a sample Section 01 10 10 Design
Requirements. Designers are required to use this format when
developing Section 01 10 10. This outline and content of the exhibit
will be modified to suit specific project requirements. Bracketed [ ]
items will be edited or completed to suit project specific
requirements. Items not bracketed shall be incorporated in the RFP
when appropriate to the project.
(e) Section 01 10 12 Design After Award. Exhibit 22-4 outlines RFP
information requirements in a sample Section 01 01 12 Design After
Award. Designers are required to use this format and list of typical
topics shown in the exhibit when developing Section 01 10 12. This
outline will be modified for project specific requirements. Bracketed
[ ] items will be edited or completed to suit project specific
requirements. Items not bracketed shall be incorporated in the RFP
when appropriate to the project.
(f) UFGS
(1) When edited UFGS are part of the D-B RFP solicitation
designers are to complete them to the fullest extent in SpecsIntact
possible ensuring consistency with Section 01 10 10 and 01 10 12
requiring that the D-B Contractor complete the editing in SpecsIntact
during design after award.
(2) When edited UFGS are not provided in the D-B RFP but
required to be issued by the D-B Contractor, list the UFGS by section
number and title, and require the D-B Contractor to edit them in
SpecsIntact during design after award.
(g) Nationally recognized and industry accepted commercial
specifications other than SpecsIntact may be used in the preparation of
technical specifications in the RFP. Government standards (ETLs,
ECs, ERs, etc.) may be required in preparing the RFP, but may not be
included by reference in the commercial specifications. These
Government standards shall be extracted from the applicable standards
and included in the RFP design and specification criteria, or the
standards shall be included as an appendix to the RFP. When technical
specifications are prepared in commercial specification format, the A-E
will require that edited specifications be submitted by the D-B
Contractor during design after award.
22.7
The Final Design shall include all items in the Interim Design
submittal advanced to a Final Design level, and any answers or
revisions made necessary by comments about the Interim Design
submittal.
22-29
The RTA submittal shall include all items in the Final Design submittal
and any answers or revisions made necessary by comments about the Final
Design submittal.
22-30
Color Schedule
This section covers only the color of the exterior and interior
materials and products that areas exposed to view in the finished
construction. The word color as used herein includes surface color,
pattern and texture. Requirement for quality and method of
installation are covered in other appropriate sections of the
specifications. Specific locations where the various materials are
required or items not designated for color in this RFP shall be
determined after the award of the Design-Build Contract.
The color schedule lists the colors, patterns, and textures required
for exterior and interior finishes, including both factory applied and
field applied colors.
x.x.2 Reference to Manufacturers Color
Where color is shown as being specific to one manufacturer, an
equivalent color by another manufacturer may be submitted as a
deviation and acceptance is required. Manufacturers and materials
specified are not intended to limit the selection of equal color from
other manufacturers.
x.x.3 Exterior Walls
Exterior wall colors shall apply to exterior wall surfaces including
recesses at entrances and projecting vestibules. Conduit shall be
painted to closely match the adjacent surfaces color. Wall color shall
be provided to match the colors listed as follows:
Brick: [___]
Mortar: [___]
Paint: [___]
Concrete Masonry Units (Integrally Colored): [___]
Metal Wall Panels, Hardware, and Associated Trim: [___]
Insulation and Finish System: [___]
Precast Concrete: [___]
Glass and Glazing: [___]
x.x.4 Exterior Trim and Miscellaneous Finishes
Exterior trim shall be provided to match the colors listed below.
Doors and Door Frames: [___]
Windows (million, sash. Trim, and sill): [___]
Wood Stain: [___]
Fascia: [___]
Downspouts, Gutter, Louvers, and Flashings: [___]
Handrails: [___]
Soffits and Ceilings: [___]
Signage: [___]
Overhangs: [___]
Caulking and Sealants: [___]
Stamped Concrete: [___]
Exhibit 22-1 (Continued)
22-31
[% of colors]
[Match roof color]
22-32
access panels, and piping and conduit adjacent to wall surfaces unless
other wise specified. Items not specified in other paragraphs shall be
painted to match adjacent wall surface. Wall materials shall be
provided to match the color listed below.
Paint: [___]
Vinyl Wall Covering: [___]
Fabric Wall Covering: [___]
Ceramic Tile: [___]
Ceramic Tile Grout: [___]
Acoustical Wall Covering: [___]
Brick: [___]
Metal Liner Panels: [___]
Glazed Structural Units: [___]
Prefaced Concrete Masonry Units:
Mortar: [___]
Columns: [___]
[___]
[___]
[___]
22-33
22-34
FLOOR
BASE
WALLS
CEILINGS
REMARKS
Exhibit 22-2
22-35
SECTION 01 10 10
DESIGN REQUIREMENTS
TABLE OF CONTENTS
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
DESCRIPTION OF FACILITY..........................................x
DESIGN REQUIREMENTS..............................................x
GENERAL REQUIREMENTS AND DEFINITIONS.............................x
PERMIT REQUIREMENTS..............................................x
ANTI-TERRORISM FORCE PROTECTION REQUIREMENTS.....................x
SITEWORK.........................................................x
NARRATIVES ON AREAS AND FUNCTIONAL REQUIREMENTS..................x
ARCHITECTURAL DESIGN.............................................x
INTERIOR DESIGN..................................................x
STRUCTURAL DESIGN...............................................xx
HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)...............xx
PLUMBING........................................................xx
FIRE SUPPRESSION................................................xx
ELECTRICAL SYSTEMS..............................................xx
ELECTRONIC SYSTEMS..............................................xx
CORROSION CONTROL AND CATHODIC PROTECTION.......................xx
ENVIRONMENTAL CONSIDERATIONS....................................xx
22-36
SECTION 01 10 10
DESIGN REQUIREMENTS
1.
DESCRIPTION OF FACILITY
1.1 The Contractor shall design and construct the FY-0X [Project Name]
at [Project Location] to result in a complete and usable facility based
on Design Requirements and Technical Specifications contained within
this solicitation.
1.2 This project is required to provide a [project description
including facility type/s, intended occupancy, building code
construction type, customer designation, user designation, gross square
footage, any phasing requirements, basis of design service standard
or standard design, general demolition requirements, general site work
requirements]. The Contractor shall design and construct these
facilities in accordance with the design requirements and technical
criteria established in this document.
1.2.1 Base Bid. The Base Bid includes design and construction of all
work required for the [Project Name, facility type/s] and all required
site work, landscaping, and utility systems. [The Base Bid includes
demolition of existing site features as shown on the site plans or
required for construction of the Base Bid.] [The Base Bid includes the
design of all Bid Options.]
[1.2.2 Bid Option Number 1 includes [general description]. [Provide
additional sub paragraphs as necessary to describe any additional bid
options.]
1.3
Sustainable Design
DESIGN REQUIREMENTS
22-37
O&M
22-38
3.1
22-39
Summarize intent.]
Definitions of Terms
PERMIT REQUIREMENTS
22-40
5.1
[Define requirements.]
5.6.2 Demonstrate that the design of each different size and type of
window or glazed door system, and their connection to the structure
meets the minimum antiterrorism standards contained herein shall be
submitted to the government for approval. Demonstration shall be by
either Design Analysis or Standard Airblast Test results, as described
below:
[5.6.2.1 Design analysis prepared and signed by a registered
professional engineer. The design analysis shall include calculations
verifying the structural performance of each window or glazed door
system proposed for use, under the given loads. The window components
and anchorage devices to the structure, as determined by the design
analysis, shall be reflected in the shop drawings.]
Exhibit 22-3 (Continued)
22-41
SITEWORK
6.3.1 The criteria site geometry plan presents the general geometric
layout for the site and facilit[y/ies]. The Contractor shall design
the [drainage, sidewalks, landscaping, site grading, privately owned
vehicle (POV) parking, concrete curbs and gutters, miscellaneous
building access pavement areas, and utilities (including fire hydrants,
irrigation and area lighting) for the [Project Name]].
6.3.2 Pavement and Parking Areas. [Define anticipated vehicle types
influencing site and pavement design, performance requirements for
asphalt and concrete pavements, and structures, use of PCASE, pavement
widths, base course aggregate, etc.]
6.3.2.1 Parking areas shall be provided in the parking layout as
generally indicated in the criteria site drawing[s]. [Define the
number of handicap spaces and type, POV parking spaces, parking for
larger vehicles or equipment, and motorcycle spaces.] [Define
performance requirements including codes and standards, pavement
widths, emergency vehicle access, efficiency and safety, lighting,
accessibility including sidewalks in moving from parking areas to
facilities, drainage, curb and bumper types, and signs and pavement
markings]
Exhibit 22-3 (Continued)
22-42
Facility Sign.
Define requirements.]
Define any requirements for bike racks,
6.4.6
[Define requirements.]
[Define requirements.]
Define
22-43
Site/Topographic Survey.
Soil Treatment.
[Define requirements.]
6.8
[6.8.3.1
6.8.5
6.9
[Define requirements.]
Define requirements.]
[Define requirements.]
Earthwork
6.9.1
Material Classification.
6.9.2
Borrow Material.
6.9.3
Disposal Areas.
[Define requirements.]
[Define requirements.]
[Define requirements.]
Utilities
22-44
Electric
Telephone, Telegraph, Television, Police, and Fire
Communications
Water Systems
Sewer Systems
Gas, Dangerous Materials
Blue:
Green:
Yellow:
[6.10.5
6.10.6
Metering.
Define requirements.]
6.10.6.1
Wastewater.
6.10.6.3
Existing Wastewater.
6.10.6.4
Wastewater Piping.
6.10.6.5
[Define requirements.]
6.10.6.6
Connections to Manholes.
[Define requirements.]
6.10.7
Water Supply.
6.10.7.1
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define requirements.]
Existing Water.
[Define requirements.]
Exhibit 22-3 (Continued)
22-45
Piping.
6.10.7.4
6.10.7.5
Meters.
[Define requirements.]
6.10.7.6
Valves.
[Define requirements.]
6.10.7.7
6.10.7.8
Backflow Preventer.
6.10.8
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define requirements.]
6.10.8.1
Fire Hydrants.
6.10.8.2
[6.10.8.3
6.10.9
Fire Pump.
Water Permit.
[Define requirements.]
[Define requirements.]
[Define requirements.]
Define requirements.]
[Define requirements.]
7.1 The paragraphs in this section are included to aid the Contractor
in understanding the requirements all the functional areas within the
[Project Name]. To aid in the design, the net square footage totals
shown on the criteria drawings, and general functional requirements
given below shall be fully coordinated. All materials and equipment
are Contractor Furnished and Contractor Installed (CFCI) unless
otherwise indicated. General types of furnishings and equipment for
each room are shown in the concept drawings to assist in establishing
anticipated individual room areas.
[7.2 Room Name, Room Number. Describe requirements including but not
limited to function, operating requirements, dimensional requirements,
ceiling heights, furnishings and built in components establishing room
size and organization, equipment and accessory requirements, any
construction requirements for security, acoustics, and accessibility,
finish materials in coordination with paragraph 9 below, and electrical
or electronics requirements.]
8.
ARCHITECTURAL DESIGN
Exhibit 22-3 (Continued)
22-46
8.5.1
Exterior
8.5.1.1
Walls.
[Define requirements.]
Exterior Doors.
[Define requirements.]
8.5.1.4
[Define requirements.]
Interior
Flooring.
Doors.
8.5.2.5
Windows.
22-47
Cabinetry.
8.5.2.9
Equipment.
[8.5.2.10 Other.
categories.]
INTERIOR DESIGN
9.1 Structural Interior Design (SID). The SID includes the selection
and sampling of all applied finishes to complete the building exterior
and interior architectural features.
9.1.1 Design Requirements. The Contractor shall use this criteria and
the drawings for the development of the SID exterior and interior
finishes, materials, and colors. The SID submittals shall run
concurrent with the architectural submittal. The Contractor shall
update the color boards and the UFGS to reflect any of the Government
comments or discontinued manufacturer colors indicated. The SID
finishes accepted at the Final design phase (defined in Section 01 10
12) shall be the SID finishes installed during the construction phase
of the project.
9.1.2 SID Room Finish Narrative. Each interior space shall be
finished in accordance with this narrative. This narrative provides
initial guidance only. As the design becomes more defined after award
of the contract, the Contractor shall provide a comprehensive room
finish schedule, signage schedule, edited UFGS 09 06 90 Color Schedule
and associated guide specifications to define all aspects of the SID.
[9.1.2.1 Primary Facility Name if more than one building in the
project.]
9.1.2.1.1 [Room Name/Interior Space Name][and Room Number].
requirements.]
[9.1.2.1.2 [Room Name/Interior Space Name][and Room Number].
requirements for all additional rooms/spaces.]
[Define
[Define
[Define
The Contractor
22-48
submit a signage plan that shows the placement of all interior and
exterior signage used in the project including [building directory,
room identification plaques, work station plaques, emergency egress
plaques, restroom signs, directional information signs].
9.1.2.3.1 [Room Name/Interior Space Name][and Room Number].
requirements for room/space types.]
[Define
9.1.2.4 Color Schedule. Product and color are shown as being specific
to one manufacturer to establish design intent. An equivalent product
and color by another manufacturer may be submitted for approval.
Manufacturers and materials specified are not intended to limit the
selection of equivalent products and colors from other manufacturers.
9.1.2.4.1
Define
Define
Define
Define
22-49
ceiling finishes.]
9.1.2.4.5
Define
22-50
STRUCTURAL DESIGN
Codes and References.
22-51
free areas.]
10.2.3 Variations from level or from slopes specified for roof decks,
floors, ceilings, beam soffits, lintels, sills, horizontal grooves, or
other conspicuous lines shall be as follows: [define requirements].
10.2.4 Where raised or depressed floors are provided, structural slab
elevations shall be adjusted so that all finished floor levels are the
same.
10.2.5 A minimum safety factor of 1.5 shall be provided against
uplift, sliding, overturning, or flotation.
[10.2.6 Wood shall not be used for any structural members. Plywood
shall not be used for wall sheathing or structural roof sheathing, or
floor decking. Tilt-up panels shall not be used. Pre-engineered metal
buildings shall not be used.]
10.3
Design Loads
10.3.1 Design dead, live, and wind loads, and load combinations shall
be in accordance with the [IBC], unless specified otherwise herein.
10.3.2 Live loads, not given, shall be in accordance with Appendix B
of UFC 3-310-01. The following floor areas shall be designed using the
stated loads, as a minimum:
[Room Type
[All additional Room Types
XX psf]
XX psf]
10.3.3 Wind loads shall be based on a [XXX] miles/hr Basic Wind Speed,
Building Occupancy Category [XX], and Exposure Category [X] as
described in UFC 3-310-01. Wind loads shall be computed and applied in
accordance with the [IBC]. All parts of all structures shall be
designed for the specified wind velocity and shall be tied together to
provide an integrated resistance to high wind effects.
10.3.4 Seismic loads shall be in accordance with UFC 3-310-01,
Building Occupancy Category [XX], and Seismic Use Group [X]. The short
period spectral acceleration value (Ss) shall be taken as [XX]g and the
one second period spectral acceleration value (S1) shall be taken as
[XX]g, for a [X]% probability of exceedance in [XX] years. Seismic
Site Classification [X] shall be used. Seismic loads shall be computed
and applied in accordance with the [IBC].
10.4
Concrete
[Define
[Define requirements.]
22-52
Wire Mesh
Reinforcement
Slab Thickness
150 psf
250 psf
400 psf
4 inches
5 inches
6 inches
[Define
10.4.7
The flatness of the floors shall be carefully controlled and
the tolerances shall be measured by the straightedge system as
specified in paragraph 4.5.7 of ACI 117/117R, using a 10 foot
straightedge, within 72 hours after floor slab installation and before
shores and/or forms are removed. The listed tolerances shall be met at
any and every location at which the straightedge can be placed.
Bullfloated
Straightedged
Float Finish
Trowel Finish
1/2 inch
5/16 inch
3/16 inch
3/16 inch
Steel
10.5.2.1
10.5.3
Joists.
10.5.4
Braced frames.
10.5.5
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define requirements if used.]
[Define requirements if used.]
22-53
[Define
Metal Deck
10.6.1
Form deck.
10.6.2
Masonry
10.7.1
Horizontal reinforcement.
[Define requirements.]
22-54
follows.
a.
b.
c.
d.
e.
f.
22-55
[XX] F DB
[XX] F WB ([XXX.X]%)
[XXXX]
Cooling
Indoor Design Temperature
Outdoor Design Dry Bulb Temperature
Outdoor Design Wet Bulb Temperature
11.2.1 The following table indicates the minimum thermal value for
building composite sections. Minimum insulation values were taken from
ASHRAE 90.1-2001.
Wall U Value
Roof U Value
11.2.2
[0.XXX] BTU/hr*ft2*F
[0.XXX] BTU/hr*ft2*F
Load Calculations.
[Define requirements.]
[Define
11.2.4
Mechanical Equipment.
[Define requirements.]
11.2.5
11.2.6
11.2.7
11.2.8
[Define requirements.]
11.2.9
Exhaust System(s.
[Define requirements.]
11.2.11
Piping systems.
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define
11.2.13
[Define requirements.]
11.2.14
stacks.
Controls.
[Define
[Define requirements.]
Specifications.
22-56
PLUMBING
Codes and References.
[Define requirements.]
12.2.1
12.2.1.1
[Define requirements.]
[Define requirements.]
12.2.2
12.2.3
Gas Connections.
12.2.4
Plumbing Fixtures.
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define
Define requirements.]
[1
As required
MATERIALS
As required
SCHEDULE/RATING
STANDARD
As required
22-57
MATERIALS
As required
SCHEDULE/RATING
As required
STANDARD
As required
As required
MATERIALS
SCHEDULE/RATING
As required
STANDARD
As required
FIRE SUPPRESSION
Codes and References.
General.
Equipment
13.3.1
[13.3.2
13.3
[Define requirements.]
[Define requirements.]]
Design.
22-58
Drawings.
ELECTRICAL SYSTEMS
Codes and References.
14.2.2
Distribution System.
[Define requirements.]
Transformers.
[Define requirements.]
Exterior Lighting.
[Define requirements.]
Electrical Interior.
[Define requirements.]
14.3.1
Service Entrance/Equipment.
[Define requirements.]
14.3.2
Voltage Characteristics.
14.3.3
Panel Locations.
[Define requirements.]
14.3.4
Branch Circuits.
[Define requirements.]
[Define requirements.]
22-59
14.3.4.1
Separate Circuits.
[Define requirements.]
14.3.5
Exterior Outlets/Lights.
14.3.6
Lighting Fixtures.
[Define requirements.]
14.3.7
Bathroom Switches.
[Define requirements.]
14.4
Lightning Protection.
[Define requirements.]
[Define requirements.]
ELECTRONIC SYSTEMS
Codes and References.
15.3
[Define requirements.]
15.3.1
15.3.2
[Define requirements.]
[Define requirements.]
Maintenance Manuals.
[Define requirements.]
15.4.1
Qualifications.
15.4.2
15.5
Cable Television.
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define
15.6
15.7
[Define requirements.]
[Define requirements.]
[Define requirements.]
22-60
General.
[Define requirements.]
16.3
16.4
16.5
Criteria of Protection.
16.6
Coating.
16.7
System Design.
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define requirements.]
ENVIRONMENTAL CONSIDERATIONS
Codes and References.
Environmental Protection.
[Define requirements.]
17.3
17.4
17.5
Hazardous Materials.
17.6
17.7
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define requirements.]
[Define requirements.]
22-61
SECTION 01 10 12
DESIGN AFTER AWARD
1. DESIGN RESPONSIBILITY
The Contractor shall furnish and be responsible for a complete set of
design documents as called for in specification section 01 10 10 DESIGN
REQUIREMENTS, and Section 00 10 00, ADDITIONAL SPECIAL CONTRACT
REQUIREMENTS and as called for hereinafter. Information provided below
is intended to supplement the Mobile District Design Manual
requirements. The Design Manual is available on the internet at:
http://www.sam.usace.army.mil/en/guides/DesMan/desman.htm
2.
DESIGN SUBMITTAL
TECHNICAL SPECIFICATIONS
22-62
[2.1.2 Fast Tracking: The contractor may at his option, "fast track"
the design and construction of site work, exterior utilities, and the
building foundation. These items may be initially designed to the 100%
Unreviewed stage, and submitted with the 50% Design Submittal. The
slab including all utilities. An Intermediate Backcheck Submittal
shall be provided for Fast-Tracked items for review and approval by the
Government, so that a Partial Notice To Proceed (NTP) can be issued to
the contractor for that portion of the work.]
2.2
PERMITTING
DESIGN SCHEDULE
PROGRESS CHARTS
22-63
INTERIOR DESIGN
6.3.1.1 The design of the FFE shall be concurrent with the building
related design and fully coordinated with the building systems design
for power, voice, data and mechanical devices such as thermostats, fire
protection devices, fire pull boxes, sprinkler heads, etc. The
Contractor will be responsible for insuring all the building systems
devices are correctly placed so that the FFE is fully coordinated for
access. The CID shall also be fully coordinated with the Customers
equipment requirements.
6.3.1.2 Contractors Interior Designer shall be required to conduct
in-depth customer interviews to determine the actual and specific
requirements of the FFE. Based on customer in-put, the FFE shall
include space planning with comprehensive furniture placement plans,
selection of all furniture and furnishings with all associated fabrics
and finishes and development of illustrated furniture order forms to
Exhibit 22-4 (Continued)
22-64
22-65
a GSA contract have no basis for determining quality and cost and will
be not acceptable for this project. The following best value
determination checklist shall be edited and used to evaluate a GSA
contract source and shall be submitted in the FFE package to justify
the FFE selections.
BEST VALUE DETERMINATION CHECKLIST
(a) Special features, which are required in effective program
performance that are not provided by a comparable item.
(b) Trade-in considerations
(c) Probable life of the item selected as compared with a
comparable item
(d) Warranty considerations
(e) Maintenance availability
(f) Past performance (i.e. experience)
(g) Environmental and energy efficiency considerations
(h) Comfort/suitability of the item
(i) Delivery time
(j) Administrative costs
(k) Training needed or provided
(l) Technical qualifications
(m) Compatibility with existing furniture/product/technology
(circle one)
(n) Other specify):___________________________________________
6.3.7
Compliance Verification
After acceptance of the FFE package, the Contractor shall submit a FFE
Implementation Schedule with set benchmark dates for the procurement
and installation of the FFE. The Contractor shall fully coordinate the
construction schedule with the FFE Implementation Schedule.
6.3.9
50% SUBMITTAL
Exhibit 22-4 (Continued)
22-66
6.4.1
22-67
6.4.4
Environmental
Landscape
Architectural Design
The Contractor shall submit five (5) complete sets of the initial
SID[/FFE] package. All SID[/FFE] proposals shall be reviewed and
approved by the Government. The Government shall return the SID[/FFE]
packages to the Contractor after the review for updating and
incorporating review comments. Each submittal will follow this method
of review until the Government approves the completed SID[/FFE]
package. The Submittals shall be side marked and distributed as
follows: 1. EN-DA Mobile District Office; 2. CD-[XX] 3. [Installation]
4. [User] and 5. [Installation] Contracting.
6.8.9
a.
Structural
Provide drawings, narrative, and design analysis to include
Exhibit 22-4 (Continued)
22-68
Plumbing
22-69
layouts and risers should also include natural gas (and meter as
required), and other specialty systems as applicable.
j. Include equipment and fixture schedules with descriptions,
capacities, locations, connection sizes and other information as
required.
k. Include marked up UFGS specifications of materials and methods.
6.8.11
22-70
i.
6.8.12
(2) 50% Drawings: The drawings shall show all information given
on the concept drawings but in greater detail. The drawings should
include, but not be limited to, the following items as applicable:
(a) Show all ductwork and piping, with sizes and flow rates,
where necessary for balancing purposes. Indicate the ductwork pressures
in accordance with SMACNA standards. Include all accessories and
appurtenances.
(b) Show elementary ladder diagrams and temperature control
schematics indicating remote sensors, panel mounted controllers, and
thermostats.
(c) Show layout and details of the final version of all HVAC
systems. The location, arrangement, capacity, and space requirements
of all equipment shall be indicated. Selected zones of air
distribution shall be sufficiently completed to indicate the solution
of the design for the remainder of the system and the precautions taken
Exhibit 22-4 (Continued)
22-71
Electrical Systems
6.8.13.1
22-72
22-73
Electronic Systems
22-74
6.8.14.1
22-75
Anti-terrorism/Force Protection
Sustainable Design
Using [SPiRiT] [the LEED-NC v 2.2 Rating System], the Contractor shall
submit a sustainable design narrative that includes a "Summary
Table" of points earned at this phase of the project. The narrative
supporting the point shown in the "Summary Table" shall briefly
describe the feature used to obtain the point and how the point is or
will be earned. For each point earned that requires calculations
and documentation provide this information to the level of design at
this phase. Provide references to drawings and specifications for
location of applicable features.
6.9
6.9.1
22-76
Irrigation System
Environmental
Landscape Work
Architectural Design
Exhibit 22-4 (Continued)
22-77
The Contractor shall submit five (5) complete sets of the approved and
final SID[/FFE] package. Once the Contractor has submitted the
SID[/FFE] and the Government has approved the submittal, all materials,
finishes, colors, textures and pattern submitted and approved for this
project are then considered as part of the contract and the Contractor
shall furnish and install all approved SID finishes and items. No
deviations will be considered once the SID[/FFE] has been approved.
6.9.7
Structural
Fire Protection
Plumbing
Electrical Systems
6.9.11.1
22-78
Antiterrorism/Force Protection:
Sustainable Design:
Exhibit 22-4 (Continued)
22-79
FINAL SUBMITTAL
The documents which the Contractor shall submit to the Government for
each submittal are listed and generally described below.
8.
MAILING OF SUBMITTALS
d. Mobile District
Commander
U.S. Army Engineer District, Mobile
ATTN: [Individual, organization]
109 St. Joseph Street
Mobile, AL 36628-0001
[telephone number]
22-80
8.2
SUBMITTAL DISTRIBUTION
[Customer]
# Items
50% Submittal
1 Design Anal.
1 Drawings
1
Specifications
[Installation
Engineering
Office]
10 Design Anal.
10 Drawings
10
Specifications
3 Permit Appl.
3 SID/FFE
Binder
Mobile
District
Resident
Office
2 Design Anal
2 Drawings
2
Specifications
2 Permit Appl.
1 SID/FFE
Binder
Mobile
District
7 Design Anal.
7 Drawings
7
Specifications
2 Permit Appl.
1 SID/FFE
Binder
9.
# Items
100% Unreviewed
1 Design Anal.
1 drawings
1 Specifications
1 Ann. Comments
1 Framed
Rendering
10 Design Anal.
10 Drawings
10 Specifications
10 Ann. Comments
3 Permit Docum.
3 SID/FFE Binder
2 Framed
Renderings
8 Rendering
Photos
2 Design Anal
2 Drawings
2 Specifications
2 Ann. Comments
2 Permit Docum.
1 SID/FFE Binder
# Items
Final Submittal
1 Design Anal.
1 Drawings
1 Specifications
1 Ann. Comments
7 Design Anal.
7 Drawings
7 Specifications
7 Ann. Comments
2 Permit Docum.
1 SID/FFE Binder
1 Lessons Learned
4 Rendering
Photos
7
7
1
7
7
2
1
1
1
1
2
10 Design Anal.
10 Drawings
10 Specifications
10 Ann. Comments
3 Permit Docum.
3 SID/FFE Binder
1 CD Rom containing Plans,
Specs, and Design
Analysis
2
2
2
2
2
1
1
Design Anal
Drawings
Specifications
Ann. Comments
Permit Documents.
SID/FFE Binder
CD Rom containing Plans,
Specs, and Design
Analysis
Design Anal.
Drawings
Drawings Full Size
Specifications
Ann. Comments
Permit Documents.
SID/FFE Binder
Lessons Learned
Drawing Full Size
Original Specifications
CD Rom containing Plans,
Specs, and Design
Analysis.
SUBMITTAL REVIEWS
22-81
22-82
10.
DESIGN ANALYSIS
11.1 Media and Format. The design analysis shall be presented on 81/2" x 11" paper except that larger sheets may be used when required
for graphs or other special calculation forms. All sheets (including
oversized sheets, and hand calculations) shall be submitted in Adobe
PDF format. The original material may be computer generated,
typewritten, hand lettered, handwritten, or a combination thereof,
provided it is legible. Side margins shall be 1-inch minimum to permit
side binding and head to head printing. Bottom margins shall be 1-1/4
inches, with page numbers centered 1-inch from the bottom.
11.2 Organization. The several parts and sheets of the design
analysis shall be given a sequential binding number and bound under a
cover indicating the name of the facility and project number, if
applicable. The title page shall carry the designation of the
submittal being made. The complete design analysis presented for final
review with the final drawings and specifications shall carry the
designation "FINAL DESIGN ANALYSIS" on the title page.
11.3 Design Calculations. Design calculations are a part of the
design analysis. When they are voluminous, they shall be bound
separately from the narrative part of the design analysis. The design
calculations shall be presented in a clean and legible form
incorporating a title page and index for each volume. A table of
contents, which shall be an index of the indices, shall be furnished
when there is more than one volume. The source of loading conditions,
supplementary sketches, graphs, formulae, and references shall be
identified. Assumptions and conclusions shall be explained.
Calculation sheets shall carry the names or initials of the computer
and the checker and the dates of calculations and checking. No portion
of the calculations shall be computed and checked by the same person.
11.4 Automatic Data Processing Systems (ADPS): When ADPS are used to
perform design calculations, the design analysis shall include
descriptions of the computer programs used and copies of the ADPS input
data and output summaries. When the computer output is large. It may
be divided into volumes at logical division points. Each set of
computer printouts shall be preceded by an index and by a description
of the computation performed. If several sets of computations are
submitted, they shall be accompanied by a general table of contents in
addition to the individual indices. Preparation of the descriptions
which must accompany each set of ADPS printouts shall include the
following:
Exhibit 22-4 (Continued)
22-83
c.
DRAWINGS
The building drawings shall consist of 1/8" scale minimum floor plans.
Elevations shall be drawn to a 1/8" scale minimum. The scale of other
visual information shall be as required. Building wall sections shall
be drawn at a minimum of 1/4" scale. The site and exterior utility
drawings shall use a minimum scale of 1"=30' unless otherwise
indicated. Additionally, the overall site plan for this project shall
be on one drawing sheet. Minimum text size on half size drawings is
1/8".
13.
SPECIFICATIONS
22-84
http://www.wbdg.org/ccb/
The specifications shall be detailed enough such that another product
meeting the specification could be substituted and it would not
adversely impact the project. All marked-out or redlined text shall be
deleted and all inserted text shall be typed at the 100% unreviewed and
final submittals.
14.
SUBMITTAL REGISTER
DESIGNER OF RECORD
22-85
CHAPTER 23
CHARRETTES
INDEX
23.1 GENERAL
23.2 APPLICABLE PUBLICATIONS
23.3 DEFINITIONS
23.3.1
Planning Charrette
23.3.2
Design Charrette
23.3.3
Level of Design
23.4 PROCEDURES
23.4.1
Documentation of Failure to Conduct Design Charrette
23.4.2
Pre-Charrette Installation Visit
23.4.3
Questionnaire Preparation, Submittal and Return
23.4.4
Charrette Conduct
EXHIBITS
23-1 Sample Questionnaire
23-2 Charrette Checklist
23-3 Checklist for Parametric Cost Estimates
23-4 Sample Charrette Report
23-1
CHAPTER 23
CHARRETTES
1.1
GENERAL
1.1.1
This chapter applies to planning and design charrettes
conducted by in-house and A-E personnel in support of Mobile District
Army and Air Force customers. Charrettes conducted for other customers
may vary in detail but will follow the general guidelines established
in this chapter.
1.1.2
Planning charrettes are critical activities essential to the
scope definition and programming at adequate funding levels of planned
facilities.
1.1.3
Design charrettes similarly are critical to confirm scope and
funding authorization at design start. Within the constraints of
design funding and time, the importance of the conduct of design
charrettes will be emphasized with customers and users.
1.2
APPLICABLE PUBLICATIONS
1.2.1
Army
1.2.1.1
ECB 2003-8, DD Form 1391 Preparation Planning Charrette
Process, 11 April 2003 at
http://www.wbdg.org/ccb/ARMYCOE/COEECB/ecb_2003_8.pdf.
1.2.1.2
ECB 2002-13, Design Charrette Guidance for Army Military
Construction (MILCON) Programs, 6 September 2004 at
http://www.wbdg.org/ccb/ARMYCOE/COEECB/ecb_2002_13.pdf.
1.2.1.3
For Army efforts conducted as part of MILCON Transformation,
see Chapter 24.
1.2.2
Air Force
1.2.2.1
The United States Air Force Project Managers Guide for
Design and Construction, 1 June 2000, chapters 1, 2 and 4 at
http://www.wbdg.org/ccb/AF/AFDG/pmguide.pdf.
1.3
DEFINITIONS
1.3.1
Planning Charrette
23-2
Design Charrette
Level of Design
PROCEDURES
1.4.1
Pre-Charrette Activities
1.4.2.1
23-3
The questionnaire will be developed with design team input based on the
type facility to be programmed or designed. The questionnaire will be
provided to the PM for submittal to the designated installation POC.
Questionnaire responses will be distributed to the design team prior to
conduct of the charrette. A sample questionnaire is at Enclosure 23-1.
1.4.2.3
Charrette Agenda
23-4
Post-Charrette Activities
23-5
g.
2. Organizational Information:
a. In the space provided below, draw or describe your organizational structure as it will look
when you move into the new facility (i.e., sketch and fill in your organization chart - what
subordinate elements will work for yours, and who your organization will work for). Or, attach an
organization chart or diagram highlighting where your organization is.
b. Organization: List the staff your organization will require when you move into the new
facility. Show staff requirements by position, shift, and type office space required (describe
physical type of room, i.e., single/enclosed office, shared/enclosed office, systems furniture office,
shop, etc.)
Exhibit 23-1 (Continued)
23-6
Organization:
____________________________________________________________________
Position/Title/Rank
Office Type
_____________________
________________
3. Facility Requirements:
a. Space Requirements: List the types of work areas, offices, etc. that your organization will
need in the facility. (Please coordinate this table with the preceding organizational chart.)
Space / Room
Name
Number of
Personnel
Area Req'd
(Room Size)
______________________
_________
__________
Remarks/Special
Equipment Needs
___________________________
b. Internal Space Organization: In the space provided below, sketch or describe how your
organization should be arranged in the new facilities (i.e., which offices should be located where,
and special physical separations between spaces - doors, sound barriers, security, etc.). If other
organization(s) will be housed in the new facility, please indicate how your organization should be
arranged in relation to the tenant organization(s) using the facility.
4. Other space requirements:
a. Will your organization need a dedicated conference area?
(Circle one.)
Yes
No
Yes
No
Number of
Personnel
______________________
_________
__________
____________________________
Indicate the type of special doors required to support your operations (other than 3'x7' personnel
doors). Use the following codes in the table below.
23-7
SOH
GOH
COH
DD
VD
SAD
Door Type
________
Location
From
To
__________ __________
Size
Special Requirements
__________
_____________________________
d. Will your organization require that any walls around operating areas limit sound
transmission (open storage, SCIF, counseling, etc.)? Please describe what you will need and
locations. Does your organization have a security person we can talk to when we have
questions?
_____________________________________________________________________________
e. Assuming most rooms will have a 9' ceiling height, are there any spaces in your
organization that will require a higher ceiling height? Please describe your needs below.
_____________________________________________________________________________
f. If the complex is designed with two floors, can any of your organization's spaces be
located on the second floor? Please describe any special needs related to splitting your
organization on two floors (i.e., service elevator, proximity to stairs, etc.)
_____________________________________________________________________________
5. Furnishings/Equipment Requirements: The following section will be used to determine
physical elements of the new facilities needed to support your organization and its operations.
g. Equipment Requirements. Please identify any equipment needs, and anticipated sources
of the equipment (i.e., copiers, kitchen unit, audio-visual equipment, etc.) for your organization.
Procurement codes are: GF/GI (government furnished, government installed), GF/CI (government
furnished, contractor installed).
Space / Room Equipment Type
Name
Quantity
Procurement
Method
Remarks
___________
_______
__________
___________________
_________________
h. Identify any existing equipment your organization will want moved to the new facility (i.e.,
radios, power converters, etc.). Describe who should relocate and install the equipment if it is to
be moved (i.e. Government or Contractor).
_____________________________________________________________________________
i. Identify any new equipment that your organization will require for the new facility. Please
identify the funding source for the new equipment.
_____________________________________________________________________________
Exhibit 23-1 (Continued)
23-8
j. Indicate any new furnishings that your organization will require for the new facility.
Please identify the funding source for the new equipment.
_____________________________________________________________________________
5. Civil/Site and Utility Requirements:
a. Demolition: Please identify any demolition requirements.
b. External Space Organization. In the space below, graphically describe your vision of how
your new facility should be located on the proposed site. (Please consider access to the facility
by vehicles and supply trucks, installation of the LMPTT, parking areas, landscaping
requirements, etc.)
c. Indicate special exterior site requirements for your organization (amount of parking for
occupants, visitors, military vehicles; large commercial vehicles; exterior utiltity requirements i.e., hydrants; vehicle turning radius requirements; exterior access to interior activities; etc.)
_____________________________________________________________________________
6. Structural Requirements:
a. Please describe any special floor loading requirements in your organization (i.e., map
storage, safes, vehicle servicing, fork lift operation, parking, etc.).
_____________________________________________________________________________
7. Mechanical Requirements:
a. Heating, Ventilating and Air Conditioning Requirements. Please describe HVAC needs to
support your organization's operations (i.e., special temperature or humidity considerations, after
hours operations, zoning requirements, etc.).
_____________________________________________________________________________
b. Plumbing Requirements. Please describe any special plumbing needs (i.e., eye wash
stations, floor drain requirements, special sinks, compressed air, or natural gas requirements,
etc.).
_____________________________________________________________________________
c. Fire Protection Requirements. Please describe any special Fire Protection needs. (i.e.
type of sprinkler system, need for a fire pump, etc.)
_____________________________________________________________________________
d. Special Mechanical Equipment. Please identify any special mechanical equipment (i.e.
cranes, monorails, vehicle exhaust system, dust collection system, etc.)
_____________________________________________________________________________
23-9
8. Electrical Requirements:
a. Electrical Service Requirements. Please describe any special power or lighting
requirements (i.e., service, transformers or uninterrupted power supply, dedicated circuits,
emergency generators or back-up power, special lighting, indirect office lighting, digital clocks,
etc.).
_____________________________________________________________________________
9. Electronics/Communications Requirements:
a. In the table below, list rooms or spaces that will require communications support.
Space / Room Name
Telephone
# Jacks
Req'd
_________________ ________
LAN
# Drops
Req'd
Tempest
Requirement
Other Needs
(i.e. Intercoms, Closed
Circuit Monitors, etc.)
_______
__________
_________________________
b. Please list any rooms / spaces that will require raised access flooring.
_____________________________________________________________________________
c.
_____________________________________________________________________________
10. Environmental Requirements:
a. Does your organization handle or use any type of hazardous material? Please identify
the materials, where they will be used or stored, and any special needs in the areas they will be
used (i.e., special ventilation, safety needs such as eye washes, requirements for resistant
finishes on the floor/walls/ceiling, special sinks or equipment, waste removal requirements, etc.)
_____________________________________________________________________________
b. Identify any known Wetland or IRP Sites in the vicinity of the proposed site.
_____________________________________________________________________________
11. Miscellaneous Requirements:
a. In the space below, please describe any Miscellaneous need(s) not covered so far in the
questionnaire. Also, provide any comments about how you believe the new facilities should be
designed that would improve your ability to perform your missions.
_____________________________________________________________________________
Thanks for taking the time to complete this questionnaire. Your information will help the
designers begin to understand your needs for the new facility.
23-10
Charrette Checklist.
Determine whether preliminary meeting can be held at installation.
If yes, coordinate funding with PM, develop agenda, identify and
coordinate with participants, conduct meeting. Discuss items in
paragraph 1.4.2.1.
If no, work through PM to talk by phone/email to MACOM, customer and
user representatives to discuss resolve items in paragraph 1.4.2.1.
Identify and meet with design team to set requirements for
successful charrette, provide background and available information,
determine additional information requirements, develop questionnaire,
discuss charrette agenda, discuss charrette budget.
Prepare and submit questionnaire for return prior to conduct of
charrette.
Establish charrette document management system: CADD Code,
ProjectWise set-up.
Formalize budget and submit to PM.
Funds available and set up in P2.
Notify design team of charge numbers and individual budgets.
Receive and distribute questionnaire returns to design team.
Design team meeting set travel requirements, coordinate
transportation, identify rental car requirements. Review product
requirements. Review questionnaire returns. Discuss format for
conduct of charrette who facilitates, takes notes, use of digital
projector to display acquired information/wall cards. Formalize
agenda. Share cell phone numbers.
Initiate TDY orders and overtime requests.
Establish hotel location and coordinate reservations.
Coordinate with installation: verify command/installation/customer
participant names and positions, charrette location, work hours,
communications and computer access, printer/plotter access, agenda for
interviews/out-brief.
Identify tools to take to charrette: digital projector, lap tops,
memory sticks, butcher paper, 5x7 index cards, felt tips, tape,
tracing paper, scales, digital cameras, colored pencils/markers for
presentations, etc.
Ensure digital tools work and work together.
23-11
Make revisions.
Submit final
23-12
23-13
Sewer
Distance to connect
Size & type of piping
Lift stations
Capacity
Number of manholes
Size & type of piping
Pavements
Thickness & area of asphalt paving
Thickness & area of concrete paving
Thickness of base material
Site Improvements
Quantity of excavation and fill
Amount of clearing and grubbing,
Landscaping
Fencing
Demolition & Relocations:
Square footage and type of buildings to be removed
HTRW:
Amount of asbestos and lead based paint abatement
Contaminated soils
Underground tanks removals
23-14
Page
2
2.1
PROJECT DESCRIPTION
General Description
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
LIST OF TABLES
Table 1
Table 2
CONSTRUCTION SCHEDULE
PHOTOS
APPENDIX A DRAWINGS
C-100 Location and Vicinity Maps
C-101 Site Plan
A-101 Floor Plan
APPENDIX B
Programming Charrette Participants (names, roles,
telephone number, email address)
APPENDIX C
Supporting Documentation
Design Instruction
DD Form 1391
LEED (or SPiRiT) Assessment Checklist
Exhibit 23-4 (Continued)
23-15
INTRODUCTION
Purpose
Charrette conduct
2
PROJECT DESCRIPTION
GENERAL DESCRIPTION
Project overview
Summary project statistics
Table 1.
3
Project Statistics
3.1
Level/points summary
Certifiable or certification
3.2
SITE DEVELOPMENT
General.
Site Layout.
Grading.
POV Parking Area.
GOV Parking Area.
Anti-terrorism/Force Protection.
Storm Drainage.
Demolition and Removals.
Clearing and Grubbing.
Erosion control and dust control.
3.3
LANDSCAPING
3.4
UTILITIES
General.
Water Distribution.
Sanitary Sewer.
Natural Gas.
3.5
SPACE REQUIREMENTS
General.
Design considerations.
Functional/narrative description of required spaces.
Table 2. Listing of all the functional spaces identified during the
charrette and the net square footage allocated for the space.
23-16
3.6
ARCHITECTURAL
General
Criteria
Life Safety Analysis
Building Component Definition
3.7
General.
SID
FFE
3.8
STRUCTURAL
General.
Criteria.
Design Loads.
3.9
MECHANICAL
General.
Heating, Ventilation, and Air Conditioning.
Plumbing.
Fire Protection.
3.10
ELECTRICAL
General.
Primary Power.
Services.
Metering.
Lighting.
Receptacles.
Hazardous Areas.
Lightning Protection.
Emergency Generator.
3.11
ELECTRONICS
Outside Plant.
Telephone System.
LAN System.
Fire Alarm System.
Mass Notification System.
Public Address (PA) System.
Antennas.
Cable Television System.
Closed Circuit Television (CCTV) System.
Intrusion Detection.
Entry Control System.
Cathodic Protection.
3.12
ENVIRONMENTAL
Exhibit 23-4 (Continued)
23-17
3.13
CONSTRUCTION SCHEDULE
PHOTOS
APPENDICES
23-18
CHAPTER 24
MILCON TRANSFORMATION (MT)
INDEX
24.1
GENERAL
24.2
APPLICABILITY
24.3
APPLICABLE PUBLICATIONS
24.3.1
Planning Charrette
24.3.2
Design Charrette
24.3.3
Level of Design
24.4
DEFINITIONS
24.4.1
Army Standard
24.4.2
Army Standard Design
24.5
PROGRAM PROCEDURES
24.5.1
Implementation
24.5.2
Program Responsibilities
24.6
PROCEDURES
24.6.1
COS Definitions
24.6.2
Workload
24.6.3
Army Standard
24.6.4
Army Standard Design (if warranted)
24.6.5
Program Certification
24.6.6
Project Definition and Design Development
24.6.7
Design/Construction Execution
24.6.8
Life-cycle Design Sustainment
24-1
CHAPTER 24
GENERAL
APPLICABILITY
APPLICABLE PUBLICATIONS
Army Regulation (AR) 415-15, Army Military Construction Program
Development and Execution
Engineering Regulation (ER) 5-1-11, USACE Business Process
ER 5-1-10, Corps-Wide Areas of Work Responsibility (AOR)
ER 1110-1-8158, Corps-Wide Centers of Expertise Program
ER 1110-3-113, Department of the Army Facilities Standardization
Program
United States Army Corps of Engineers (USACE), Operations Order
2006-16, FY07 MILCON/BRAC Execution OPORD, Annex U
Realignment/Establishment of Centers of Standardization
USACE, US Army COS Program, Program Management Plan (PgMP) and
Appendix, Mobile District COS Management Plan
CEMP-M/CERM-P Memorandum, 26 March 2003, subject: Clarification of
USACE Policy on Planning and Design (P&D), Construction Supervision
24-2
DEFINITIONS
24.4.1
Army Standard
PROGRAM PROCEDURES
24.5.1
Implementation
This program is being implemented over a three year period through FY08
with all COS at initial operational capability in FY08.
24.5.2
Program Responsibilities
(a) Each COS serves within the Department of the Army as the definer
of Army Standards and Army Standard Designs. The COS develops, maintains,
and provides Army Standard technical criteria or the Army Standard Design
for each designated facility type. A waiver system has been implemented
that requires COS evaluation and USACE approval of deviations from either
the Army Standard or Army Standard Design. Each COS will receive funding
for development and maintenance of their respective facility type Army
Standard or standard design from USACE. Each COS participates on a COS
Management Board for development of policy and processes; assuring
consistent application of the program; and monitoring execution.
(b) Geographic Districts (GD) are defined as the executing district
responsible for MT project site design, construction, project reporting,
and contract close out. A COS may be a GD. The GD maintains the Project
Manager function. It is anticipated that the GD will receive MT project
funding (design and construction funds), and distribute an appropriate
share to each COS with facility type responsibilities on that specific
project. (In some cases, several COSs and facility types may be involved
on one project, and the GD is responsible for integrating these multiple
building activities in one project.)
24.5.2.1
Facility Types
24-3
24-4
MT Model RFP
MT Adapt-Build
MT Acquisition
24-5
24.5.2.5
It is the USACE intent that BIM be used in the submittal of Contractordeveloped MT designated construction documents, and preparation of
future adapt-build Army Standard Designs. In FY08, contractor MT
submissions will be required to be submitted in BIM format. BIM
submissions prior to that year are voluntary. A USACE BIM standard is
being developed by the Engineering Research and Development Center
(ERDC).
24.5.2.6
PROCEDURES
COS Definitions
4-Star Headquarters
24-6
Workload
Mobile District has been granted access in the PAX system to view
future MILCON and BRAC projects related to COS responsibilities. It is
a mutual responsibility of the COS and GD to initiate discussions on
projects requiring COS involvement for MT projects.
24.6.3
Army Standard
24.6.3.1
Develop functional (building, site, furniture, furnishings)
and technical requirements of the Standard Design for the assigned
facility type.
24.6.3.2
As applicable, develop land area adjacencies, site plans or
layouts in support of area development or real property master plans.
24.6.3.3
Conduct studies, analyses or assessments directed by the
Facility Design Team (FDT) (including Department of the Army (DA),
Assistant Chief of Staff for Installation Management (ACSIM), and USACE
representation) during the development of Army Standards.
24.6.3.4
24.6.3.4.1
Work in conjunction with the FDT co-chairs to arrive at
Army Standards for FDT staffing leading to review and approval of the
Army Standard by ACSIM.
24-7
24.6.3.4.2
When life-cycle investment requirements are identified,
conduct analyses and implement innovations to mitigate or reduce
implementation cost. Where mitigation by market analyses,
constructability, or other engineering factors (for similar functions
or facilities in private sector or other areas of Government) cannot
achieve design cost impacts, identify courses of action or alternatives
for consideration by the FDT.
24.6.3.5
Ensure consideration and inclusion of appropriate
sustainable design considerations to consistently and successfully
achieve sustainable design objectives.
24.6.3.6
Analyze installation design guides for locations where a
standard design will be constructed and develop information on
architectural theme, colors, exterior/interior signage, furniture, and
landscape materials. Determine proper application of preferences in
the development of Army Standards as substantiated by the approved IDG.
24.6.3.7
Consider safety features (e.g. fall protection tie-off
points) that may be included in the Army Standard to enhance the safe
operation and maintenance of the facility. Perform a Facility Systems
Safety Assessment on the design if the risks merit it.
24.6.3.8
Prepare cost estimates for the facilities. Provide market
surveys or analyses to ascertain appropriate unit cost consistent with
the functional requirements and operational objectives of the standard
design. Develop rationales and recommend unit cost changes to the
USACE Program Coordinator (PC) for the Army Facilities Standardization
Program (HQUSACE/CECW-CE-D)
24.6.4
24.6.4.1
Develop the standard design of the building to an 80%
solution including regional climate and structural requirements. The
80% solution will be predicated on Army Standard criteria, and will be
developed in consultation with the FDT. It may be developed using
contract or district resources. This requirement is to be phased into
the program as discussed below.
24.6.4.1.1
FY-08 program: Develop a basic floor plan for use in a
design build Request for Proposals (RFP). Where a standard design has
already been completed with little or no changes expected, this
standard design will be developed to the 80% solution and utilized in
an adapt build contract to the maximum extent possible.
24.6.4.1.2
FY-09 program: Incorporate best designs from the FY-07
model RFP packages and proceed further toward the 80% solution.
24.6.4.2
24.6.4.3
Develop template DD1391s for use in identifying, defining,
and validating facility requirements and assessing potential facility
impacts associated with materiel fielding. This requirement requires
coordination with the HQUSACE (CRST), CEMP-DA.
24-8
24.6.4.4
Coordinate with the Technology Standards Group (TSG) (TSG
reports to DAIM-FDF) or technology evaluation teams for identification
and incorporation of technology standards and criteria as appropriate.
24.6.4.5
Coordinate with USACE Communities of Practice (COPs) as
necessary for technical support.
24.6.4.6
Develop and maintain the Army Standard Design in BIM. Attend
BIM meetings and training designed to foster implementation of BIM
deployment.
24.6.4.6.1
Identify COS BIM team to facilitate BIM usage for
planning, design, construction and O&M of facilities and grounds.
24.6.4.6.2
Maintain COS/district expertise in BIM to perform QA of AE prepared electronic files and insure conformance with BIM-CADD
standards, policies and procedures including data base, file and naming
conventions, and defined file data sets.
24.6.4.6.3
Designate COS facility type BIM manager to act as
technical subject matter expert (SME) leading activities including
establishment, distribution and retrieval of BIM data, files,
libraries.
24.6.4.6.4
Provide technical assistance during A-E scope negotiations
regarding BIM requirements and deliverables.
24.6.5
Program Certification
24.6.5.1
Participate in planning charrettes to ensure consistent
implementation and compliance with Army standards and standard designs.
(Geographic districts will lead the planning charrette).
24.6.5.2.
Assist OACSIM/DAIM-FDC in review of DD1391/ENG 3086 scope
and cost for consistent implementation and compliance with Army
standard.
24.6.5.3
Ensure use of template DD1391s (when available) as basis for
developing project scope and cost.
24.6.5.4
Ensure that the DD1391 documents include only customer
preferences (as substantiated by the approved IDG) that have been
reviewed and approved in accordance with the established approval or
waiver requirements.
24.6.5.5
When a waiver request to an Army standard is submitted,
ensure geographic district and IMA region affected by the waiver are
aware of the waiver process and are advised that the project
development will be held in abeyance pending AFSC approval. Ensure
concurrent notification to OACSIM/DAIM-FDC, HQIMA and HQUSACE of
pending waiver submission in order to expedite review process.
24.6.5.6
When a waiver to an Army standard design is approved by
HQUSACE, ensure DD1391 is properly annotated and notification of scope
and cost waiver results are provided to OACSIM/DAIM-FDC.
24.6.6
24-9
24.6.6.1
Support the execution district PM as an integral member of
project development team.
24.6.6.2
Provide building and interior design and contracting
services to the GD. (HQUSACE will identify the mandatory use of the
COS in the design directive)
24.6.6.3
Review and approve user requests prior to the inclusion in
the adapt-build design (or MT Model RFP).
24.6.6.4
Identify and advise IMA garrison when a waiver to either the
Army Standard or Standard design is.
24.6.6.4.1
For Army Standards, review of waivers shall include scope
and cost implications, assessment, and recommendation of CONCURRENCE or
NON-CONCURRENCE to USACE. Analyses, assessment, and staff/coordination
of waivers to Army Standards shall be completed in accordance with the
Army Facilities Standardization Program charter dated 24 May 2006. All
projects requiring waiver to Army Standards will be held in abeyance
pending ACSIM approval.
24.6.6.4.2
For Army Standard Designs, determine technical and
functional implications of waiver requests and determine potential
implication to Army standards. Coordinate potential impacts with FDT
and where no Army Standard implication exists, recommend CONCURRENCE or
NON-CONCURRENCE to PC AFSP (HQUSACE/CECW-CE-D). Analyses, assessment,
and staffing/coordination of waivers to Army Standard Designs shall be
completed in accordance with the Army Facilities Standardization
Program charter dated 24 May 2006.
24.6.6.4.3
USACE (when applicable) will coordinate waivers to Army
Standard Designs with the Program Coordinator for Readiness and
Modernization Support (PC RMS) (HQUSACE/CEMP-DA) for any implications
on Army strategic objectives, priorities, or plans prior to approval
and notification to the Army Facilities Standardization Committee
(AFSC).
24.6.7
Design/Construction Execution
24.6.7.1
Ensure consistent implementation and compliance with Army
Standards and Standard Designs.
24.6.7.2
Participate in design charrettes to ensure the Army Standard
and Army Standard Design intent is maintained through design
development. (Geographic districts will lead the design charrette)
24.6.7.3
24.6.7.3.1
Integration of projects where more than one COS is
involved to ensure commonality of engineering support systems and
aesthetic expressions.
24.6.7.3.2
Geotechnical investigation and report. (Facility
foundation design is by COS.)
24.6.7.3.3
24-10
24.6.7.3.4
Environmental permitting requirements or any other
permitting requirements specific to the building execution. (The
geographic execution district will obtain permits.)
24.6.7.3.5
LEED points and strategies needed in the site development
in relation to the facility.
24.6.7.4
Develop site specific standard design for contract or
prepare an RFP package to reflect approved IDG architectural theme,
colors, exterior/interior signage, furniture, and plant materials.
24.6.7.5
Execute the following compliance checks and conformance
reviews for projects:
24.6.7.5.1
Conformance with RFP document as modified by the awarded
Contractor proposal
24.6.7.5.2
24.6.7.5.3
Functional adjacencies
24.6.7.5.4
AT/FP
24.6.7.5.5
24.6.7.5.6
24.6.7.5.7
Structural Interior Design (SID) and FF&E (furniturerelated interior design) layout compliance [The term Comprehensive
Interior Design (CID) is used to describe the provision of both
building-related and furniture-related interior design.]
24.6.7.5.8
Seismic strategies
24.6.7.5.9
24.6.7.5.10
Utilities interface
24.6.7.5.11
Communications
24.6.7.5.12
24.6.7.6
Perform/review VE analysis on projects as needed or
requested.
24.6.7.7
Coordinate field technical assistance necessary (RFIs,
claims, modifications, EDC) for the facilities.
24.6.7.7.1
approved
24.6.7.7.2
Ensure
communicated to the
implement a process
provide feedback to
24-11
24.6.8
24.6.8.1
Attend selected construction and post occupancy evaluations
to obtain user feedback and lessons learned. COS leads; include the
GD, and invite IMA, ACSIM, and HQDA proponents.
24.6.8.2
Maintain lessons learned in Dr Checks as required. Maintain
historical database of standard design use by FY, PN and location.
24.6.8.3
Explore, adopt, and implement new technologies (processes,
materials, equipment, and methods) that support standards and improve
facility management.
24.6.8.4
Maintain market surveys or analyses to ensure unit cost
stays abreast of technology and constructability.
24.6.8.5
Adjust template DD Forms 1391 (where applicable) based on
execution lessons learned, trends, and actual project execution.
24.6.8.6
currency.
24.6.8.7
Consolidate lessons learned from project development and
execution. Assess lessons learned for trends or programmatic
adjustments to policies, processes, procedures, or standards and
criteria to improve program implementation and project execution. Apply
lessons learned to the Army Standard or Army Standard Design.
24.6.8.8
Maintain currency with applicable specifications, codes, and
industry standards
24.6.8.9
designs
24.6.8.10
When applicable and directed, conduct independent
compliance assessments of projects to monitor effectiveness of Army
Standard and Army Standard Design policies, directives, processes, and
procedures.
24.6.8.11
Maintain coordination with related technical (i.e., US Army
Safety Center) and functional activities (i.e., US Army Aeronautical
Services Agency for aviation facility types).
24-12
CHAPTER 25
ACRONYMS AND ABBREVIATIONS
AASHTO
ABA
ACI
ADA
ADEM
A-E
A/E/C
AF
AFF
AFFF
AF&PA
AFI
AFM
AHU
AISC
AISI
AMCR
ANSI
API
AR
ARC
ASCE
ASHRAE
ASME
ASTM
AT/FP
AWS
BCE
BEQ
BICSI
BMP
BOQ
BRAC
C
CADD
CATV
CCB
CCTV
cfm
CFR
cfs
cm
c.m.
CMAA
CMU
COM
COR
CoS
CP
CSV
25-1
CWE
D-B
D-B-B
DD
DDC
DM
DOD
DPW
EIA
EC
EM
EMCS
EMI
EN-DA
EN-DW
ENG
EN-GG
EPA
ER
ETL
F
FAR
FFE
FPP
fps
FSC
FSN
FSS
FY
GD
gpm
GSA
HAG
HAP
HTW
HVAC
IBC
ICC
IEEE
IES
IFC
IFGC
I-H
IMC
IMCOM
IOF
IPC
IPCEA
IRC
IRP
ISA
JOC
LAN
LEED
MACOM
MBMA
25-2
MCA
MCASES
MCP
MILCON
MIL-HDBK
MO
MS
MT
MWPCA
NACE
NEMA
NFPA
NOR
NPDES
O&M
OMA
PACES
PAE
PCASE
PCI
PDF
PIV
PM
PPTO
psi
PVC
PVD
QCP
RA
RFP
RFQ
RTA
SABER
SDI
SID
SIOH
SGML
SMACNA
SOW
SPiRiT
TIA
TI
TL
TM
TRACE
UFC
UG
UL
UMCS
USDOT
UFAS
UFGS
USACE
VAV
WAN
25-3