01 - Adv Issues in Cap Budgeting
01 - Adv Issues in Cap Budgeting
01 - Adv Issues in Cap Budgeting
100
100
80
8,000
crores
Rs.
Rs.
Rs. Crore
D
E
DER
1.25 =C14/C6
Gain to existing
shareholders due to project
10 =NPV
25 Rs. Crore
(0.15) Rs.
=c20*(Value - Price)
=C23 - C27
=C30/C4
Period
0
1
2
3
4
NPV
IRR
15.00%
15.00%
(Rs. Crore)
CF-A
CF-B
(10.0) (100.0)
3.5
30.0
4.5
35.0
6.0
45.0
7.5
55.0
4.68
33.66%
Period
0
1
2
3
4
NPV
IRR
15.00%
15.00%
(Rs. Crore)
CF-A
CF-B
(100.0)
###
50.0
30.0
40.0
33.0
32.0
45.0
30.0
55.0
11.92
21.41%
A
B
C
D
E
F
G
25
40
5
100
50
70
35
10
20
5
25
15
20
20
Given the information above, how should the firm select the projects,
and which projects should it select?
To resolve this, we compute the PI of each project, and find the rank of each.
Project
A
B
C
D
E
F
G
PI
Rank_PI
0.40
0.50
1.00
0.25
0.30
0.29
0.57
4
3
1
7
5
6
2
Example - 3B: Using the Profitability Index to Choose Projects - with Project Dependence
Since B has to be undertaken, we exclude B's project cost (Rs. 40 crore).
We also reduce the constraints by Rs. 40 crore.
We redraw the list as follows:
Constraint = Rs. 60 crore
Project
Initial Invt. NPV
PI
Rank_PI Cum_Invt
(Rs. Crore) (Rs. Cr.)
(Rs. Crore)
C
G
A
E
F
D
5
35
25
50
70
100
5
20
10
15
20
25
1.00
0.57
0.40
0.30
0.29
0.25
1
2
3
4
5
6
5
40
65
Period
0
1
2
3
4
WACC
(Rs. Million)
CF
(1,000)
300
400
500
600
IRR =
15%
24.89%
The IRR above is based on the assumption that cash flows of years
1, 2 and 3 respectively are re-invested at the same rate (IRR).
MIRR is computed on the basis that intermediate cash flows are
re-invested at the cost of capital. This is worked out below.
Period
Cash Flows
Investment
(1,000)
1
300
-20
-8
-8
-8
-8
-8
-30
-3
-3
-3
-3
-3
Vendor-1
(PV)
1
2
3
4
5
NPV
Vendor-2
(PV)
(7.27)
(6.61)
(6.01)
(5.46)
(4.97)
(2.73)
(2.48)
(2.25)
(2.05)
(1.86)
(50.33)
(41.37)
15%
Project A
-100
40
40
40
40
40
12%
Project B
-150
35
35
35
35
35
35
35
35
35
35
34.65
5
47.76
10
10.29
8.45
34.65
( 1 ( 1+ r )n )
ZOOM TO 145%
2
400
(Rs. Million)
3
4
500
600
PV at Cost of Capital
600.00
575.00
529.00
456.26
PV_at_COC
(Terminal Value)
2,160.26
r
n
( 1+ r )
50
7
50
7
10
8
6
4
2
15
10
5
0
25
30
35
40
45
-5
-10
-15
Pay-Off-Long Put Option
Pay-Off-
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
-7
-7
-7
-7
-7
-7
-7
-7
-6
-5
-4
-3
-2
-1
0
1
2
3
4
5
6
7
8
7
7
7
7
7
7
7
7
6
5
4
3
2
1
0
-1
-2
-3
-4
-5
-6
-7
-8
10
8
6
4
2
0
-2 35
-4
-6
-8
-10
40
45
50
55
60
65
35
40
45
50
55
60
55
60
65
70
Cause
Debt limit imposed by outside agreement
Number of firms
10
Percent of total
10.6%
3.2%
65
69.1%
2
14
2.1%
14.9%
TOTAL
94
---
Source: Damodaran, Applied Corporate Finance, 3/e, Wiley-India Edition (2011: John Wiley & Sons Inc.; Reprint 2012 by Wil
Theory
A business uncovers
a good investment
opportunity.
Practice
A business believes,
given the underlying
uncertainty, that it
has a good project.
Source of Rationing
Uncertainty about
true value of
projects may cause
rationing.
2. Information
revelation
The business
conveys information
about the project to
financial markets.
The business
attempts to convey
information to
financial markets.
Difficulty in
conveying
information to
markets may cause
rationing.
3. Market response
Financial markets
believe the firm;
i.e., the information
is conveyed
credibly.
Financial markets
may not believe the
announcement.
4. Market efficiency
The securities
issued by the
business (stocks and
bonds) are fairly
priced.
The securities
issued by the
business may not be
correctly priced.
With underpriced
securities, firms will
be unwilling to raise
funds for projects.
5. Flotation costs
(or Transaction costs)
1. Project discovery
Source: Damodaran, Applied Corporate Finance, 3/e, Wiley-India Edition (2011: John Wiley & Sons Inc.; Reprint 2012 by Wil
pp. 263