PM 2010 Quick Reference Guide
PM 2010 Quick Reference Guide
To create a new blank project in Project, click the File tab. Click New, and then click Blank Project.
To create a new project from a template, click the File tab. Select a template from Templates
(local), Office Online Templates (Web), or Project Server Templates.
Click the File tab, and then click Info. On the right side of the Information page, select a date in the Start
Date box.
Click the Project tab. In the Properties group, click Change Working Time. Identify working and nonworking days and times for your project.
click the File tab. Click Save. In the File name box, type the project name.
If you are publishing the project to Microsoft Office Project Server 2010, type the name of the project and
include any values for custom fields that are required by your organization.
1. Enter tasks
Click the View tab. In the Task Views group, click Gantt Chart. In the Task Name field, enter tasks. Tasks
can also include summary tasks, milestones, and WBS items.
In Project 2010, you can now schedule tasks manually in addition to having Project automatically schedule
them. Select the scheduling method after you enter a new task by clicking one of the following in the Task
Mode column:
Manually scheduled With this method, Project won't move a task after it is created, even when
resources are assigned to it, or tasks get linked to it, or if the Project calendar changes. New tasks
are manually scheduled by default.
Auto scheduled Use this method when you want Project to schedule the task based on
dependencies, constraints, calendars, and other factors.
Note New tasks are manually scheduled by default. To make new tasks automatically scheduled by
default, click the Tasks tab. In the Schedule group, point to Task Mode, and in the list, click Auto Schedule.
3. Outline tasks
Create your task hierarchy, including tasks and milestones under summary tasks, which can represent
phases or other work divisions. Click the View tab. In the Task Views group, click Gantt Chart. Select a task
(or several tasks), and then in the Tasks group, click the Indent or Outdent button
Tip If you created a summary task with a duration, start date, or finish date, then the tasks that fall under
the summary task will not be rolled up to this summary task. They'll be independent of it. This is known as
top-down scheduling.
4. Enter durations
Click the Duration field for a task and enter a duration. For Project 2010, you can enter duration in two
different ways, depending on the scheduling method that is being used for the task.
Manually scheduled task Enter duration as either a number or as text. For example, you can
enter "Sometime after June," or "Two days after ship."
Auto scheduled task Enter duration as a number. For example, type 4d to indicate 4 days. To
specify a milestone without duration, type 0d. To indicate that a duration is an estimate, add a
question mark; for example, type 6d?
Note When using automatic scheduling, avoid entering start and finish dates for tasks. Instead, enter
duration and let Project 2010 automatically set these dates, which might change anyway as resources are
assigned to tasks.
5. Link tasks to show
relationships
Click the View tab. In the Task Views group, click Gantt Chart. Select the tasks that you want to link, and
then click the Link Tasks button
in the Tasks group, which is found under the Tasks tab. To change the
default finish-to-start dependency type, double-click the line between the tasks that you want to change,
and then select a task link from the Type list.
6. Create deliverables
After your project is underway, you might learn that other projects depend on your project as a
deliverable. Click the View tab. In the Task Views group, click Gantt Chart. On the Task tab, in the Insert
group, click Manage Deliverables and Dependencies
that is connected to Project Server 2010.
3 Assign resources
1. Add resources to your
project
Click the View tab. In the Resource Views group, click Resource Sheet
type the names of the resources you will use for this project.
If you are using Project Professional, you can add resources from the enterprise resource pool. Click the
Resources tab. In the Insert group, click Add Resources, and then click Build Team from Enterprise. This
feature requires Project Professional 2010 that is connected to Project Server 2010.
2. Assign resources to tasks
In the Gantt Chart view, select a task to which you want to assign a resource. On the Resources tab, in the
Assignments group, click Assign Resources
Tip Use the new Team Planner to drag and drop tasks around easily from one person to another within
your team, or back and forth in the schedule. Click the View tab. In the Resources group, click Team
Planner. You can even create new tasks on the Team Planner, or remove tasksby just dragging or
dropping.
3. Enter the work hours
resources spend on tasks
When scheduling tasks, project managers sometimes prefer to enter the amount of work (or the amount
of labor) needed to complete a task, rather than the duration for the task. Entering work reflects realworld scheduling.
To enter work hours for resources assigned to tasks, add the Work column to the Gantt Chart view. Right
click a column, and then click Insert Column. Type "Work", to select the Work column.
As soon as you assign resources to automatically scheduled tasks, Project 2010 determines how to
schedule the task based on the task type. (Manually scheduled tasks don't use task types.) Durations might
change as you assign resources to tasks.
Duration changes
Work changes
Duration changes
Duration changes
Units change
Duration changes
Units change
Work changes
Work changes
To set a default task type for the entire project, click the File tab, and then click Options. In the
Default task type box, select Fixed Units (the default), Fixed Duration, or Fixed Work.
To change the task type for an individual task, click the Task tab, and then in the Properties group,
click the Task Information button
. Click the Advanced tab, and then in the Task type box,
click the task type that you want to create.
You can use Project 2010 to help you understand how changes to one task can affect the rest of the
project. Click the Task tab, and then in the Schedule group, click Inspect Task. A pane opens on the left
showing the factors that affect the scheduling of the selected task.
Tip You can also see task scheduling information (such as scheduling mode, duration, and start and stop
times) quickly by hovering the mouse over the task's Gantt bar.
After your project plan is solidly in place for the finish date, budget, and scope, you can submit the plan for
approval. Once it has been approved, save the baseline plan. Click the Project tab, in the Schedule group,
click Set Baseline.
Click the View tab, and then click the Gantt Chart button. Click the Format tab, and then in the Bar Styles
group, click Baseline. the baseline information is shown as the lower of the two Gantt bars for each task.
Click the View tab. In the Task Views group, click Gantt Chart (or any view that includes columns). Point to
Tables, and then select Variance. This table includes fields for baseline and variance start and finish.
Updating the progress of your project is the only way to make sure
it stays on track as work is performed. The focus at this point is on
managing changes, updating the schedule, tracking progress, and
communicating project information.
5 Update progress
1. Manage changes
Managing changes involves modifying durations, dates, dependencies, resource assignments, or tasks
based on requested changes or new information. Keep the current fields up to date and compare them to
the baseline.
Its best to decide on a single method for tracking progress. You can enter percentage complete, actual
durations
start and finish dates, actual and remaining durations, or actual and remaining work.
Click the Task tab, and select the task for which you want to enter actual progress. In the Tasks group,
select the amount of progress done on the task
If you want to enter actual and remaining work hours or costs, use the tracking table. Click the View tab. In
the Data group, point Table, and then click Tracking. Enter progress data in the Act. Work or Act. Cost
fields for the task.
You can also use the tracking table to enter percent complete, actual start and finish dates, and actual and
remaining duration.
Project 2010 has some old views and some new views to help you see project information and report it to
others on your team or organization. Click the View tab. In either the Task Views group or the Resource
Views group, select the view you want to use. There are many views, but the most useful ones include:
Team planner view Move tasks easily from one person to another within your team, or back and
forth in the schedule. You can create new tasks in the team planner or remove tasksjust by
dragging them.
Timeline view Place tasks, subtasks, or milestones onto a single timeline at the top of most views.
You can copy the timeline into Word, PowerPoint, Excel, or Outlook. You can instantly create
attractive project reports this way. Click the Timeline check box to see how the timeline works.
Gantt Chart view View project tasks in a combination view, with columns on one side and bars
along a timeline on the other side.
Calendar view See project information in a familiar monthly or weekly calendar format that can
be printed.
2. Add a column
Adding columns to a view is one of the easiest ways to create the view that meets your needs.
Click the View tab. In either the Task Views group or the Resource Views group, select the view you want
to use. Right click on a column header to the left of where you want to insert a new column, and then click
Insert column. Type the name of the column you want to insert.
Tip You can also insert a custom column as easily as a built-in column. For example, if you want a column
called "Deliveries", type that name when you insert a new column. If you want the new column to contain
only numbers (to specify the number of deliveries), then right click the column down-arrow, point to Data
Type, and select the type of data that the column should contain.
3. Customize a view
Customizing views beyond adding columns has been made considerably easier in Project 2010. Whether
its the Team Planner, Timeline, or classic Gantt Chart, all formatting options are available on the Format
tab.
Select the view you want to customize, and then on the Format tab click the type of view element you
want to change, such as the bar styles on the Gantt Chart, callout text on the Timeline, or the gridlines and
timescales of any views.
Tip If you want to filter, sort, or group tasks prior to printing, Click the View tab, and then in the Data
group, click the Sort, Filter, or Group options.
Set up the current view the way that you want it to look when printed. Click the File tab, and then click
Print. A preview of the view will be printed appears on the right.
Tip Click in the preview part of the view to see the actual size of the view as it will be printed.
5. Generate a report
Click the Project tab, and then in the Reports group, click one of the following:
Visual Reports Use visual reports to see your projects data as a PivotTable report in Excel 2010 or
a PivotDiagram view in Visio Professional 2010.
Reports Use basic reports to see your project's data in tabular reports that don't require Excel or
Visio. These basic reports are collected in categories for easy selecting and printing.
Compare Projects Use a compare projects report to view a report that displays changes in the
current project compared to another project.
Just because your project is almost finished doesnt mean that your
work is done. You still need to resolve any final project details and
obtain customer acceptance of final deliverables. Conduct a
lessons learned session, recording information about areas for
improvement and best practices. Make any final updates to the
project plan. Finally, archive the project plan according to your
organizations guidelines.
Click the Project tab. In the Reports group, click Visual Reports to see your projects data as a PivotTable
report in Excel 2010 or a PivotDiagram view in Visio Professional 2010.
You can also view basic reports that dont require Excel or Visio. Click the Project tab, and in the Reports
group, click Reports. Double-click a report category, and then double-click the predefined report. Enter any
requested information. A preview of the report appears. To print the report, click Print.
2. Save a project as a
template
After completing a project, you should leverage what youve learned in the project by making it a template
for future projects. Click the File tab, click Save As, and then in the Save As Type box, click Template.