Project Management Process
Project Management Process
Process
1 | Page
Table of Contents
1. Introduction....................................................................................................... 2
2. Introduction to Project Management..................................................................2
3. Project Management Process.............................................................................3
3.1 Project Definition.......................................................................................... 3
3.1.1 Setting Objectives.................................................................................. 3
3.1.2 Project Scope.......................................................................................... 3
3.1.3 Project Stakeholders............................................................................... 4
3.1.4 Project Team........................................................................................... 5
3.2 Project Planning............................................................................................ 6
3.2.1 Project Tasks........................................................................................... 6
3.2.2 Project Scheduling..................................................................................7
3.2.3 Project Resources................................................................................... 8
3.2.4 Project Budget........................................................................................ 8
3.2.5 Project Risk Management.......................................................................9
3.2.6 Risk Matrix of Yorkshire House Food.....................................................11
3.2.7 Project Communication Plan.................................................................12
3.3 Project Execution........................................................................................ 13
3.3.1 Project Implementation and Controlling...............................................13
3.3.2 Project Monitoring................................................................................ 14
3.4 Project Closure............................................................................................ 15
4. Conclusion....................................................................................................... 16
References........................................................................................................... 17
Appendix A.......................................................................................................... 20
2 | Page
1. Introduction
Yorkshire House Foods (YHF) is currently looking to intensify its production capabilities by
constructing a new plant and overhauling existing one. Also, the company wants to bring
improvement in its existing services for the intention to move to the wholesale market. For
this purpose, a number of decisions have been made by the authorities and some new people
are hired at top positions in some key departments such as HR and production departments.
This meaningful report illustrates how the project manager of YHF will manage future
projects by following the project management process of defining, scoping, executing, and
finally closing the project.
SMART framework is often used to set underlying objectives for the projects. Also, it is used
to define Key Performance Indicators (KPI) for the project and organisation. The term is first
used by Doran (1981) to resolve management issues for his company. Table 1.1 illustrates the
typical values and meanings of SMART framework.
Table 1.1 SMART framework
Specific
Measurable
Attainable
Relevant
Timely
Yorkshire House Foods can use SMART framework for project goal-setting purpose in order
to address the key problems that the company is currently facing (Jensen et al., 2007) such as
lack of documented processes, poor planning, managing risks, inconsistency of products,
poor communication, and inadequate employee skills.
3.1.2 Project Scope
Defining project scope means to obtain necessary information required to initiate the project
in order to meet project stakeholders requirements (PMI, 2008). YHF can use project
management triangle to obtain primary information about the projects cost, time, and quality.
4 | Page
The project management triangle is often employed to demonstrate the ability of project
management team to organise projects resources, essentially cost and time, for the purpose to
achieve desired quality (ibid). Figure 1.1 depicts triangle constraints that YHF can manage to
achieve customer satisfaction by delivering optimal quality of food products.
In addition, in defining the projects scope it
Organisations sometimes ignore some stakeholders that can significantly contribute to the
project success. The YHF can apply DRUGS test to identify such stakeholders for any
specific project. The DRUGS framework is depicted in figure 1.3.
Figure 1.3 Identifying key stakeholders
The client YHF wishes to improve its quality of the products and also to bring improvement
in its customer service operations. In order to achieve these goals, it is inherent for the
company to develop effective team with excellent management, planning and control, and
skills and capabilities. For this purpose, YHF can employ Belbins nine team roles theory that
can help the organisation to identify behavioural strengths and weaknesses of the employees
at work (Belbin, 2012). The nine team roles of Belbin are illustrated in figure 2A in appendix
6 | Page
Belbin Roles
Managing Director
John Jones
Plant / Shaper
Project Manager
Aymen Omran
HR Manager
Janet Jackson
Resource Investigator
Production Manager
Gary Gowrie
Implementer
Support University
Shaper
From the past few decades, a number of tools and methods have been developed and
identified to organise project tasks. The project manager and management team usually use
these tools for task identification, task sequencing, time allocation, and resource allocation. In
task allocation, tasks are allocated to employees according to their skills, knowledge,
experience, and time availability. From a range of available tools and techniques, the project
manager of YHF can use Work Breakdown Structure (WBS) for task management as it lists
7 | Page
all interrelated project tasks and deliverables required by the project (Kliem and Ludin,
1998).
The activities or tasks in WBS can be listed in top-down sequence which supports project
manager and team to distribute project tasks into different levels where each sub-level
describes more detailed information on specific task. Figure 3A in appendix A illustrates an
example of a WBS consisting of six sub-levels where first four levels supply inherent
information on project planning, scheduling, monitoring, and management tasks and last two
levels provide more detail information and processes. In employing WBS for task
management, the client (YHF) must know that WBS is useful in showing particular tasks at
different levels. However, it sometimes fails to include other interconnected tasks such as
project procurement, administration, and implementation (ibid).
3.2.2 Project Scheduling
The projects can be scheduled effectively by building main structures, developing resource
list, and adding finishing touches as shown in figure 1.4.
Figure 1.4 Project scheduling
The project manager in YHF can schedule project activities using Gantt chart as it is a
popular planning tool for representing task starting and ending times up in a row. The Gantt
chart can be developed using several programs such as MS Project and MS Excel and can be
updated accordingly as the project progresses (Greer, 2003). However, in developing the
Gantt chart, the project manager of YHF must keep in mind its underlying limitations such as
lack of demonstrating clear dependencies between tasks (Aguilar and Ruth, 2004) and lack of
8 | Page
communication medium during project execution phase (Mawdesley et al, 1997). The Gantt
chart for YHF project is developed and shown in Section III.
3.2.3 Project Resources
In making a budget plan for the project, the project manager of YHF can estimate how the
company will perform financially during the project. In addition, the manager will decide
projects funding and project costs including labour costs, material cost, overhead costs,
contingency costs, contract costs, and wages. The manager will also decide on which
budgeting technique he will use for preparing project plan. In this regard, four budgeting
techniques such as analogous technique, top-down method, bottom-down method, or
parametric-estimate method can be considered (Florin, 2011).
In the given scenario, it is useful for YHF to prepare budget using either analogous technique
or parametric estimate. In using the analogous technique, the manager can consider the actual
costs of the former project to estimate the costs of the present project. However, this
technique is only feasible if both projects are common in nature. On the other hand, while
9 | Page
making budget using a parametric-estimate, the project manager will estimate costs using
cost accounting information such as cost allocation methods or process costing tools that
contains each products cost.
The top-down budgeting technique can be employed if there is a need to estimate the costs
for each project process. In the opinion of Taylor (2007), the top-down technique is not
suitable for food industry as the project manager requires to investigate each project activity
more closely when estimating costs. In contrast to top-down method, the bottom-up technique
takes into account the costs of project inputs such as project resources in order to estimate the
total project budget. This method is useful when the costs of inputs are fixed. Thus, this
method cannot be employed by the YHF.
3.2.5 Project Risk Management
Risk identification
Risk assessment
Risk response
3.2.5.1 Risk Identification
The process of risk management starts with identifying various risks associated with the
project. In the food industry, risks occur from several sources such as health and safety
compliance, chemical risks, fire and explosion hazards, microbiological risks, and cleaning
hazardous material like bleach and lubricant (Potter and Hotchkiss, 1998; Brown and
Stringer, 2002; Lelieveld, 2003). Furthermore, some severe health risks of processed foods
are identified by SixWise.com which includes: obesity, diabetes, cancer, and other unknown
effects.
Turner (1999) believes that risks must be identified at the early stages of the project.
However, different opinion came from Chapman (2001) who emphasized the identification of
risks by applying risk management processes during the execution phase. This means that
risk identification is an ongoing process that ends with the accomplishment of the project.
Therefore, the project manager of YHF must identify risks at early stages of the project by
following six necessary steps such as realising the presence of uncertainty, developing initial
checklist, identifying risk emerging circumstances, risk mapping, logical risk classification
10 | P a g e
scheme, and summary sheet for risk classification (Bartlett, 2004). The list of risk
identification tools recommended by a number of researchers is available in table 1.3 that
client (YHF) can use to identify risks.
Figure 1.3 Risk identification and assessment tools
The identifying possible risks, the client (YHF) can analyse and evaluate each risks chances
of occurrence and its influence on the project as a whole. This assessment can be qualitative
or quantitative (Burtonshaw-Gunn, 2009). The risks can be analysed or evaluated
qualitatively by giving priority to each risk on the basis of its possibility of occurrence its and
11 | P a g e
influence on the project. On the contrary, quantitative risk analysis can be conducted
throughout the lifecycle of the project. The possible risk assessment tools suggested by
various researchers are included in table 1.3 that client (YHF) can use to analyse and evaluate
risks.
3.2.5.3 Risk response
Once the possible risks are identified and analysed, then the next step is to adopt an
appropriate approach to mitigate the impact of risks. This process is called risk response. The
client (YHF) can adopt different risk response strategies recommended by several
researchers. These strategies are: risk response, risk acceptance, risk transfer, and risk
mitigation (Chapman, 2001; PMI, 2010). Risk response strategy refers to the modifications in
the project plans so that risks can become unrelated. However, risks can be accepted if they
emerge due to natural disasters or unforeseen events. On the other side, risk transfer indicates
the strategy of transferring the risk impact to other party i.e. insurance company whereas risk
mitigation strategy can be adopted to minimise the influence or chances of occurrence of
common risks.
3.2.6 Risk Matrix of Yorkshire House Food
The project manager of Yorkshire House Food can take into account risk probability matrix to
identify and analyse the risks. A sample risk matrix is shown in figure A4 in appendix A.
Moreover, table 1.4 illustrates the summary of identified risks and their importance for YHF
along with the managers who will undertake each risk.
Table 1.4 Risk log of YHF
Risk
Prob.
Impact
Manager
Activity
High
High
Gary
Gowrie
High
Medium
Gary
Gowrie
Mediu
m
High
Janet
Jackson
12 | P a g e
Project communication is very important for corresponding with all stakeholders. The figure
5A in appendix A shows how communication surrounds different activities. The typical
project communication plan of YHF should involve all stakeholders. Table 1.5 demonstrates a
proposed project communication plan of YHF.
Table 1.5 Project communication plan of YHF
What
Initial meeting
Who
All stakeholders
Purpose
Information collection for project
When
December 12
Project initiation
John Jones
04 Feb 2013
Project planning
Project Manager
01 January 13
Risk management
Project Manager
Throughout
the project
Reporting /
Coordination
Project Manager
Throughout
the project
Team meetings
All stakeholders
Throughout
the project
Production
matters
Gary Gowrie
February 13
to
December 13
Resources
management
Janet Jackson
November 13
to
April 14
Post project
review
John Jones
practically put into practice (Jeffery et al., 2010, p. 75). Project execution phase consists of
following process:
The project manager of YHF can implement plans developed in previous phases using
following triple constraint (Greer, 2003; Levin, 2012).
For the purpose to develop effective control over the project costs and activities, YHF project
manager needs to ensure that the actual costs of activities are allied or close to the planned
project costs. This can be ensured by continuously scrutinizing the graphs of accumulated
costs. An example of such a graph is illustrated in figure 1.6 where planned (baseline), actual
costs, and value completed are compared with each other.
Figure 1.6 Cost comparison graph
In the implementation phase, the project manager of YHF can control the entire activities of
the project by ensuring that activities or tasks mentioned in WBS are correctly and timely
accomplished (Greer, 2003). Figure 1.5 clearly illustrates the way how the clients project
14 | P a g e
manager can manage and control the projects scope and time using WBS to confirm that
actual results are allied with required results.
Figure 1.5 Project implementation and controlling
The project manager of client (YHF) can collect, record, and report primary information to
monitor projects performance and then pass this information to stakeholders. According to
Taylor (2007), project manager needs to monitor inputs and outputs of the projects where
input are time, cost, quality, and 5Ms of resources i.e. Money, Materials, Methods,
Manpower, and Machinery whereas the outputs are project actual cost, progress, job start and
completion times, and design changes. It is best practice for the clients project manager to
use the Milestone Trend Analysis (MTA) technique for monitoring purpose. The MTA
technique points out the projects present status in terms of its scope (Levin, 2012). An
example of MTA is stated in figure 1.7.
15 | P a g e
16 | P a g e
4. Conclusion
It is concluded from the above discussion that the client YHF can manage projects by
following a project management process framework proposed by PMBOK (PMI, 2010). This
framework mainly comprised of four stages: project definition, project scope, project
execution, and project closure. The project manager of YHF can employ a number of tools
and methods at different stages to effectively manage the projects including an analysis of
project risks.
17 | P a g e
References
Aguilar, S. and Ruth, S. (2004). Business Process Modelling: Review and Framework. International
Journal of Production Economics, 90, pp. 129-149
Bartlett, J. (2004). Project Risk Analysis and Management Guide. 2nd edition, APM Publishing
Limited
Belbin, M. R. (2012). Team Roles at Work. 2nd edition, Routledge
Biafore, B. and Stover, T. (2012). Your project management coach: Best practices for managing
projects in the real World. John Wiley & Sons
Brown, M. and Stringer, M. (2002). Microbiological risk assessment in food processing. Woodhead
Publishing
Burtonshaw-Gunn, S. A. (2009). Risk and financial management in construction. Gower Publishing
Ltd.
Carayannis, E. G., Kwak, Y-H, Anbari, F. T. (2005). The story of managing projects: An
interdisciplinary approach. Greenwood Publishing Group
Chapman, R. J. (2001). The controlling influences on effective risk identification and assessment for
project design management. International Journal of Project Management, 19(3), pp. 147-160.
Chapman, R. J. (2011). Simple Tools and Techniques for Enterprise Risk Management. 2nd edition,
John Wiley & Sons
Cooper, D. F., Grey, S., Raymond, G. and Walker, P. (2004). Project Risk Management Guidelines:
Managing Risk in Large Projects and Complex Procurements. John Wiley & Sons
Conrow, E. H. (2003). Effective Risk Management: Some Keys to Success. 2 nd edition, AIAA
Crundwell, F. K. (2008). Finance for engineers: Evaluation and funding of capital projects. Springer
Doran, G. T. (1981). There is a S.M.A.R.T. way to write management's goals and objectives.
Management Review, 70(11), pp. 35-36.
Edwards, P. and Bowen, P. (2005). Risk Management in Project Organisations. New South Publishing
Field, M., Keller, L. and Keller, L. S. (1998). Project Management. Cengage Learning EMEA
Florin, B. (2011). Bottom-up/Top-down Budgeting. The 6th International Scientific Conference,
Romania, December 02 March 2011.
Greer, M. (2003). Project Management. Jaico Publishing House
18 | P a g e
Harrison, F. L. and Lock, D. (2004). Advanced Project Management: A structured approach. 4th
edition, Gower Publishing Ltd
Haughan, G. T. (2008). Work Breakdown Structures for projects, programs, and enterprises.
Management Concepts
Heldman, K. (2005). Project Manager's Spotlight on Risk Management. John Wiley & Sons
Jeffery, A. H., George, H. F. and Valacich, J. S. (2010). Modern Systems Analysis and Design. 6th
edition, Pearson Education India
Jensen, D., McMullen, T. and Stark, M. (2007). The manager's guide to rewards: What you need to
know to get the best for--and from--your employees. AMACOM Division American
Management Association
Khknen, K. and Artto, K. A. (1997). Managing Risks in Projects: Proceedings of the Ipma
Symposium on Project Management. Taylor & Francis
Kendrick, T. (2009). Identifying and Managing Project Risk: Essential Tools for Failure-Proofing
your Project. 2nd edition, AMACOM Division American Management Association
Kliem, R.L. and Ludin, I.S. (1998). Project Management Practitioners Handbook. AMACOM Books
Lelieveld, H. L. M. (2003). Hygiene in food processing: Principles and practice. Woodhead
Publishing
Mawdesley, M., Askwe, W. and OReilly, M. (1997). Planning and Controlling Construction
Projects: The Best Laid Plans. England: Addison Wesley Longman
Meyer, P. J. (2003). What would you do if you knew you couldnt fail? Creating S.M.A.R.T. Goals.
Meyer Resource Group, Incorporated, The. ISBN 978-0-89811-304-4
Molenaar, K. R., Anderson, S. D. and Schexnayder, C. J. (2010). Guidebook on Risk Analysis Tools
and Management Practices to Control Transportation Project Costs. Transportation Research
Board
Newell, M. W. and Grachina, M. N. (2003). The Project Management Question and Answer Book.
AMACOM Division American Management Association
PMI (2008). A Guide to the Project Management Body of Knowledge (PMBOK Guide) 4 th Edition.
Project Management Institute, ISBN 978-1-933890-51-7
PMI (2010). A Guide to the Project Management Body of Knowledge (PMBOK), p.27-35
Potter, N. N., Hotchkiss, J. H. (1998). Food science. 5th edition, Springer
Sachs, I. (2011). Performance-driven IT Management: Five practical steps to business success.
Government Institutes
19 | P a g e
SixWise.com (n.d.). All the Health Risks of Processed Foods -- In Just a Few Quick, Convenient
Bites. [online]. Available from: http://www.sixwise.com/newsletters/05/10/19/all-the-healthrisks-of-processed-foods----in-just-a-few-quick-convenient-bites.htm (Accessed: 06 November
2012)
Taylor, J. (2007). Project scheduling and cost control: Planning, monitoring and controlling the
baseline. J. Ross Publishing
Turner, J. R. (1999). The handbook of project based management: improving the processes for
achieving strategic objectives, 2nd Edition, London: McGraw Hill
Wells, G. L. (1996). Hazard Identification and Risk Assessment. IChemE
20 | P a g e
Appendix A
Figure A1 Project management procedure
21 | P a g e
22 | P a g e
23 | P a g e