Installation Instructions For MS 06.2005 PDF
Installation Instructions For MS 06.2005 PDF
2.
3.
4.
Put the M6 screws (inside scope of supply) through the holders at the
connections but dont tighten them.
5.
Put the small brass-made installation helps in the INC gaps at the overlay
part of the segments to ensure proper roundness.
If the shaft diameter variation is too high you maybe have to loosen all M6
screws. (Loosen only so far that the wheel can be justified with slight hits
from a plastic hammer.)
6.
7.
8.
9.
10.
11.
12.
13.
Tighten all tensioning and holding screws, so that the adjustment of the
wheel can not be changed by hand any more.
14.
Select the item CHECK TDC SENSOR in the PREMET main menu and
choose the option COUNT INC PULSE. Now slow-turn the engine and
check if 360 pulses where counted. If not, check the wheel for dirt, grease
or anything else that could block the laser beam inside the pick-up, remove
the dirt an start the test again.
15.
Pull the long silver cable with the connection box up to the cylinder station
and mount the connection box at a place not more than 10m away from
any indicator cock. (Please see also instruction Installation instruction for
MS-cable)
16.
Connect the PREMET to the connection box using the short silver cable
and repeat the test in step 14.
- running engine
- slow turning the gear
- to count the pulse signals by slow turning the gear
In order to check the MS-wheel sensor choose Count INC pulses and push ENTER.
Turn the engine slowly 1 rotation starting from the TDC position and ending again in
the same TDC -position.
The sensor should now record 360 pulses per one rotation.
CHECK TDC SENSOR
INC : XXX pulses
ESC
ENTER
In this instance, please check if any or some of the slots are not recordable (for
example they are covered or dirty inside) or if the flywheel was turned too wait
causing overlapping.