Oisd STD-226
Oisd STD-226
Oisd STD-226
FIRST EDITION
AUGUST 2007
FOR RESTRICTED
CIRCULATION ONLY
No..
OISD-STD--226
FIRST EDITION
August2007
FOR RESTRICTED
CIRCULATION ONLY
No..
NOTE
Oil Industry Safety Directorate (OISD) publications are prepared for use in the oil and gas
industry under Ministry of Petroleum & Natural Gas, Govt. of India. These are the property of
Ministry of Petroleum & Natural Gas and shall not be reproduced or copied and loaned or
exhibited to others without written consent from OISD.
Though every effort has been made to assure the accuracy and reliability of the data contained in
these documents, OISD hereby expressly disclaims any liability or responsibility for loss or
damage resulting from their use.
These documents are intended only to supplement and not to replace the prevailing statutory
requirements.
iii
FOREWORD
Oil Industry in India is more than 100 years old. Over years, a variety of practices have been in
vogue because of collaboration / association with different foreign companies and governments.
Standardisation in design, operating and maintenance practices was hardly in existence at a
national level. This lack of uniformity, coupled with feed back from some serious accidents that
occurred in the recent past in India and abroad, emphasised the need for the industry to review
the existing state of art in designing, operating and maintaining oil and gas installations.
With this in view, the Ministry of Petroleum & Natural Gas in 1986 constituted a Safety Council
assisted by the Oil Industry Safety Directorate (OISD) staffed from within the industry in
formulating and implementing a series of self regulatory measures aimed at removing
obsolescence, standardizing and upgrading the existing standards to ensure safer operations.
Accordingly, OISD constituted a number of functional committees comprising of experts
nominated from the industry to draw up standards and guidelines on various subjects.
The present document on Cross-country Natural Gas Pipelines and City Gas pipeline were
prepared by the Functional Committee on Natural Gas Pipelines. This document is based on
the accumulated knowledge and experience of functional committee members and various
national and international codes and best practices. This document is meant to be used as
supplement and not as a replacement for existing codes and practices.
This standard in no way supersedes the statutory requirements of bodies like IBR, CCE, Factory
Inspectorate or any other Government Body which must be followed as applicable.
This document will be reviewed periodically for improvements based on the new experiences and
better understanding. Suggestions may be addressed to:
The Co-ordinator
Committee on Cross-country LPG Pipelines,
Oil Industry Safety Directorate
7th Floor, New Delhi House
27, Barakhamba Road
New Delhi-110 001
iv
MEMBERS
Sh. V. K. Khanna
Sh. J. P. Ojha
Sh. S. Sreenivasalu
Sh. S. P. Singh
MEMBER CO-ORDINATOR
SH. S. K. NANDY
In addition to the above, several other experts from the industry contributed in the preparation,
review and finalization of this document.
v
PART-1
STANDARD ON NATURAL GAS TRANSMISSION PIPELINES
CONTENTS
-----------------------------------------------------------------------------------------------------------CHAPTER DESCRIPTION
PAGE NO.
-----------------------------------------------------------------------------------------------------------1
INTRODUCTION
SCOPE
DEFINITIONS
DESIGN
10
15
8.
MATERIALS
17
CORROSION CONTROL
18
10
CONSTRUCTION
20
11
25
12
28
13
31
14
36
15
ABANDONMENT OF PIPELINE
36
16
MANAGEMENT OF CHANGE
37
17
DEFECT ASSESSMENT
37
18
REPAIR OF PIPELINE
37
19
REFERENCES
38-39
20.
ANNEXURES
40-43
vi
PART -II
S.NO.
DESCRIPTION
PAGE NO.
----------------------------------------------------------------------------------------------------------1.0
INTRODUCTION
45
2.0
SCOPE
45
3.0
DEFINITIONS
45
4.0
STATUTORY REGULATINS
46
5.0
47
6.0
LAYING OF PIPELINE
51
7.0
53
8.0
54
9.0
57
10.0
TRAINING
58
11.0
RECORDS
58
12.0
REFERENCES
59
ANNEXURES
I
II
III
IV.
60
61
V.
67
VI.
68
vii
PART-I
NATURAL GAS TRANSMISSION PIPELINES
1.0
INTRODUCTION
3.0
Authorized person
A person or representative of the
company trained and assigned to
carry out a specific job.
Cross country pipeline
Cross country pipeline means all
pipelines (including pipelines after
separator and / or processing plant
beyond isolation valves) and
facilities which are used for
transportation of Natural Gas from
one point to another except plant
piping within the limit of isolation
valves of the plant.
DEFINITIONS
Consumer
The organization or individual to
whom Natural Gas is delivered
through the cross country pipeline.
Cold Work
It is an activity which does not
produce sufficient heat to ignite a
flammable mixture (mixture of
flammable gas with an oxidizing
agent ) or a flammable substance.
SCOPE
This standard outlines the minimum
requirement for safety in design,
construction, inspection, testing,
commissioning,
operation,
maintenance,
modifications,
abandonment, corrosion protection,
safety of onshore natural gas cross
country
pipelines
including
associated facilities and installations
as outlined in Annexure-I.
Chief Controller
Means Chief
Explosives.
Controller
of
Competent Authority
Any person authorized by Central
Government , by notification in the
official Gazette, to perform the
functions
of
the
competent
authority under the PMP Act1962.
Competent Person :
A person recognized by the
concerned statutory authority for the
purpose in respect of which the
competency is required.
Design Factor
It is percentage factor of Specified
minimum strength of the material
considered for determining wall
thickness based on location class of
the pipeline.
Design Pressure
The maximum internal pressure
which the pipeline can be subjected
to as determined by design
procedure applicable to materials
and locations involved.
Delivery Station
Delivery station is the station on the
pipeline used for receipt of natural
gas and delivery to consumer(s) /
city gate station.
Hot work
It is an activity which involves
welding, burning, soldering, brazing,
sand blasting, chipping by spark
producing tools, use of power driven
tools, non flame proof electrical
work including other work which
can produce sufficient energy to
cause ignition where potential
flammable mixture (mixture of
flammable gas with an oxidizing
agent ) or a flammable substance
exists.
Onshore
Areas other than Offshore as defined
Offshore
Areas beyond the line of high water
along that portion of the coast that is
in direct contact with the open sea
and beyond the line marking the
seaward limit of inland coastal
waters.
Operating Company
The
organization owning and
operating Natural Gas cross country
pipeline system
for delivering
natural gas to various Consumer(s).
Shall
The word shall is used to indicate
that the provision is mandatory.
Should
The word should is used to indicate
that
the
provision
is
recommendatory as per sound
engineering practice.
Operating Pressure
It is the pressure corresponding to a
particular flow rate at which pipeline
is operated. Operating pressure is
less than or equal to MAOP.
Purging
It is the process of replacing the
atmospheric air within a container
(pipeline, vessels, filters etc) by an
inert substance in such a manner so
as to prevent the formation of
explosive mixture.
STATUTORY
ACTS
AND
REGULATIONS
Natural Gas pipeline and its
associated facilities are covered
under various regulations and
require specific approval from
concerned
authorities.
Various
regulations, interalia applicable are
as under:
i.
Petroleum and Natural Gas
Regulatory
Board
(PNGRB) Act2006.
ii. Policy for development of
Natural Gas Pipelines and
City or Local Natural gas
Distribution Netwroks.
iii. Guidelines
for
Environmental clearance of
new projects 1981
iv. The
Environment
(Protection ) Act -1986
v. Water ( Prevention &
Control of Pollution) Act
1974
vi. Air ( Prevention & Control
of Pollution) Act 1981
vii. The Petroleum and Mineral
Pipelines (Acquisition of
Right of Users in Land)
Act, 1962.
viii. Manufacture ,Storage &
Iimport
of
Hazardous
chemical Rules-1989
ix. National Highway Act,
1956
x. Railway Act , 1989
In addition all other statutory
approvals required for laying of
the pipelines across rail, road
and water body (canals/rivers
etc.) crossings and other utility
crossings as notified by local
authorities / State etc shall be
applicable.
5.0
operation, a programme of
condition
monitoring
and
maintenance
should
be
undertaken to ensure integrity is
maintained.
The selection of design for
pipeline system shall be based
on the following evaluation of
the properties and required flow
rate of the fluid to be
transported, together with the
environment in which the
pipeline is to be installed.
a) Gas composition including
hydrogen sulphide , oxygen
and water vapour content
b) Sweet or sour natural gas,
single or multiphase flow
conditions.
c) Operating pressures and
temperatures.
d) Type of Pipeline System
(Gathering/Transmission/Di
stribution/Service lines).
e) Location class through
which pipeline shall pass.
DESIGN
The pipelines shall be designed
in a manner that ensures
adequate public safety under all
conditions
likely
to
be
encountered during operating
conditions. All materials and
equipment shall be selected to
ensure safety and suitability for
the condition of use.
The initial integrity of the
pipeline is established through
proper design, material selection
and
sound
construction
practices. After the pipeline has
been commissioned and is in
5.1
Pipeline Design
Design of Natural Gas pipeline
shall be in accordance with
ASME B31.8
5.1.1
5.1.2
environmental parameters as
applicable, during all phases of
work from installation to
operation. Such calculations
shall include but not limited to
the following:
a) Buoyancy
control
and
stability analysis for pipeline
section to be installed in
areas
subjected
to
flooding/submergence,
b) Crossing analysis of rivers by
trenchless
techniques,
wherever soil data is
favorable for such operation,
c) Evaluation of potential for
earthquake occurrence along
pipeline route and carrying
out requisite seismic analysis
to ensure safety and integrity
of the pipeline system.
5.1.3
5.1.4
Design Temperature
Pipelines shall be designed for
the following temperature limits
(i) Above ground - Maximum :
65o C ; Minimum: (-) 29o C
(ii) Below ground- Maximum :
60o C ; Minimum: (-) 29o C
Design shall also consider the
temperature of natural gas
proposed to be transported
through the pipeline. When the
maximum design temperature
exceeds 120o C ( 250o F),
particular attention shall be given
to tensile properties of the
material to ensure that the
derating factor for temperature is
adequate as per Table-1 below.
Table -1
Gas Temperature in degree Celsius Temperature derating factor (T)
(Fahrenheit)
Less than 120 o C ( 250 o F)
1.000
120 o C ( 250 o F) to 149 o C ( 300 o F)
0.967
o
o
o
o
149 C ( 300 F) to177 C ( 350 F)
0.933
177 o C ( 350 o F) to 204 o C ( 400 o F)
0.900
o
o
o
o
204 C ( 400 F) to 230 C ( 450 F)
0.867
For intermediate gas temperatures, the derating factor is determined by interpolation.
5.2
Design of Components
P x D
2xSxFxExT
Where
t = Nominal wall thickness, in mm;
P= Internal design pressure, in N/mm2.
Table -2
4
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.40
In setting the values of the design factor, F, due consideration has been given and allowance
has been made for the various under thickness tolerances provided for in the pipe
specifications listed and approved for usage in this Code.
The pipe wall thickness less than 6.4 mm should not be used for cross country pipelines.
Pipe diameter 4 and above shall be used in cross country pipelines.
- Near concentration in Class 1 and 2 means places of public assembly (school, temple,
7
Corrosion
All underground and above ground
pipes and its components shall be
protected against corrosion inline
with para 9.0 of this standard.
5.2.5
5.3
Installation Layout
5.3.1 Location
The information on following
aspects are required to be
considered for finalising location
of pipeline compressor station, tapoff station , Intermediate pigging
station and SV stations.
(i) Location of tap-off facilities
with the pipeline system
compatible with zoning, land
use and land development.
(ii)
Environmental consideration
based on Environmental
Impact Assessment (EIA)
and Risk Analysis (RA)
study for the pipeline and
stations.
(v)
(vi)
Availability of electrical
power
movement
equipment.
ii.
iii.
iv.
v.
vi.
vii.
5.3.3
fighting
Separation Distances
Inter-distances for various station
facilities and utilities shall be as
per ANNEXURE - III.
5.3.5
Piping layout
Wherever possible, piping shall be
located above the ground. Piping
shall be designed considering skin
temperature of piping material
under empty conditions as 65 C or
the design temperature of pipeline,
whichever is higher. Buried piping
inside the terminal area shall have a
minimum depth of cover of 1.2 m.
Where buried pipes come out of the
ground, the underground coating on
the pipe will continue for a length
of at least 300 mm above ground.
Platforms and crossovers shall be
provided for ease of operation and
maintenance.
5.4
Protection of Facilities
5.4.1
5.4.2
5.4.3
5.4.4
fire
5.3.4
5.3.2 Layout
i.
of
a)
(1) Supervisory Control And Data
Acquisition (SCADA) System.
(2) Leak detection system with
provision for identification /
location of leak and isolation
of affected section.
(3) Facilities for controlled flaring.
(4) Accessories & kit for arresting
leak
5.5
SCADA REQUIREMENTS
PIPELINE
SYSTEM
COMPONENTS
6.1
Isolation Valves
Isolation valve shall be provided for
isolating sections of pipeline in order
to:
Location Class
1
2
3
4
&
b)
Mainline
Block
Valves
/
Sectionalizing Valves
Sectionalizing valves shall be
installed
where
required
for
operation and maintenance and
control of emergencies. Factors such
as topography of the location, ease
of operation and maintenance
including requirements for pressure
relief, security, proximity to
occupied buildings shall be taken
into consideration in deciding the
location of the valves. The
maximum distance between the
location of any two section isolation
valve stations shall be as given in
Table -3 below, based on the location
class and taking into consideration
factors like the terrain features,
requirement of safety and operation,
etc.
Table - 3
Maximum Distance in km
32
24
16
8
Note : Based on the above location class no. of Block / Sectionalizing valves
to be installed shall be worked out. Valve spacing adjustments should not
exceed 10% of the applicable distances listed above (due to non availability of
land). However, the total number of valves as per the design requirement shall
remain same.
6.1.5
Sectionalizing
Valve(s) shall be
provided with blow down or vent
line
connection to isolate the
pipeline section and evacuate the
pipeline section in case of an
emergency and repair. The size and
capacity of the connections for
blowing down the line shall be such
that under emergency condition the
section of line can be vented as
rapidly as practicable.
Pigging Facilities
The pipelines shall be designed to
meet the requirements for pigging
considering the following:
a) location of the permanent pig
traps
or
connections
for
temporary pig traps;
b) access to the pig traps;
c) handling facilities;
d) isolation requirements necessary
for pig launching and receiving;
e) venting
and
draining
requirements
for
precommissioning and operation;
f) direction of pigging including bidirectional pigging;
6.2.4
6.3
Bends
The minimum radius of Cold Field
Bend shall be as per Table -4 below:
Table 4
Minimum Radius of Cold Field Bends
Nominal Pipe Size (inch)
21D
30 D
40 D
Insulating Joints
Insulating joints shall be provided to
electrically isolate the buried
pipeline from the above ground
pipeline. Insulating joints shall be
6.5
6.6
6.7
6.8
Check valves
Check Valves shall be installed to
provide automatic blockage of
reverse flow in the piping system,
within
the
station, wherever
required.
Flow/Pressure Control Valve
Design of control valves shall meet
the requirement of part I of API
550 / API-RP-553 , ISA ( Instrument
Society of America) S- 75.01 -75.03,
IEC -79 and IEC-529.
Branch Connections
Minimum size of any tapping from
the underground pipeline shall be of
50 mm nominal bore and shall be
provided with an isolation ball valve
located at a minimum distance of 50
mm from the pipeline. All branch
connections or side tap on the
piggable lines having branch line
diameter equal to or exceeding 40
percent of the main pipe diameter,
shall be provided with flow tees/bar
tees in order to enable smooth
passage of cleaning, gauging,
instrumented and other pigs. All
flow tees/bar tees shall comply with
the requirements of ASME B 16.9,
MSS-SP-75 or equivalent.
Metering facilities
Positive displacement meters ,
turbine meters or equivalent
measuring device and their proving
facilities shall be designed and
installed at all stations except
sectionalizing valve stations. Dry
gas filters shall be installed at the
upstream of the meters.
6.10
(ii)
6.11
6.13
designed
and
installed
and
maintained
to
ensure
safe
operations under both normal and
emergency situations.
6.14
COMPRESSOR STATION
6.14.1
Compressor Design
The compressor station shall be
designed in accordance with the
requirements of ASME B 31.8.
Centrifugal type process gas
compressors shall be designed in
accordance
with
API-617.
Reciprocating Compressors shall
be designed in accordance with
API-618 and other compressors
shall be designed in accordance
with API-11P.
Compressor station shall consist of
following:
ASME
Section VIII of the
Boiler and Pressure Vessel Code.
6.14.1.6
6.14.2
6.14.1.5
Instrument
System
and
Plant
(iii)
(iv)
(v)
(vi)
(vii)
Air
A
compressor
building/shed to house the
compressors.
Switchgear building for
electric power.
Power
generator
building/shed.
Workshop building.
Warehouse store.
Office building.
Control room building.
SAFETY
DEVICES
&
FEATURES
The safety system for compression
facilities and gas transportation
system shall consist of following:
7.1
7.2.1
7.2.2
7.2.3
7.2 4
7.3
Vent Lines
7.3.1
7.4.2
7.6
7.7
7.10
.
7.11
8.0
8.1
General
Materials for use in the pipeline
system shall comply with the design
requirements and be suitable for the
intended fabrication and / or
construction methods.
8.2
Steel Pipe
Line Pipe for use in Natural Gas
Pipeline System shall be Seamless,
Electric
Welded
(EW)
or
Longitudinal/Helical Submerged Arc
Welded (LSAW/HSAW) conforming
to Line Pipe Specification API 5L
(PSL-2) or equivalent.
Maximum
limits
on
Carbon
Equivalent for Steel line pipes shall be
as follows:
CE(Pcm) :
0.20
CE (IIW) :
0.40
Carbon Equivalent shall be calculated
based on the formula given below:
C + Si + Mn + Cu + Ni + Cr + Mo + V + 5B
30
20
20
60
20
15
10
If heat analysis indicate that boron content is less than 0.01%, then product analysis need
not include boron.
For Carbon content more than 0.12%,
CE = C +
Mn + (Cr + Mo +V) + Ni + Cu
15
CORROSION CONTROL
9.1
General
All above ground and buried
pipelines
shall
be adequately
protected against corrosion.
(a) Above ground pipes shall be
protected from atmospheric
corrosion by suitable coating or
paint. Above ground sections of
pipelines shall be electrically
isolated from the buried
pipeline sections. This will
however be, not applicable at
over ground pipe section in
suspension crossings and bridge
crossings along the mainline,
where the pipeline shall be
electrically continoius.
(b) Buried pipes likely to be
affected by external corrosion
should
be
protected
by
combination of anticorrosion
coatings
and
cathodic
protection.
For plant piping, depending upon the
requirement underground piping
should be protected by anti-
External Corrosion
Electric Interference
a)
b)
c)
d)
10.2
Excavation
In cultivable land and other areas
specifically designated, the top soil
on the pipeline trench top width shall
be excavated and stored separately.
This top soil shall be replaced in
original position after backfilling and
compacting the rest of the trench. The
width of trench shall be such that a
minimum clear distance of 200mm
for trench in normal soil and 300mm
for trench in rock is maintained
between edge of pipe and the trench
wall at the bottom of trench.
below:
Table 5
Minimum Cover Requirements for Pipelines
Sl No.
Locations
Minimum Cover
In Mtr
ii)
iii)
1.2
iv)
1.5
v)
2.5
vi)
1.5
vii)
1.5
viii)
1.2
ix)
1.7
i)
1.0
1.0
NOTES:
(i) The depth of cover shall be measured from the top of the pipe coating to the top of the
undisturbed surface of soil or the top of graded working strip, whichever is lower. The fill
material in the working strip shall not be considered in the depth of cover;
(ii) The cover shall be measured from the top of road or top of rail, as the case may be;
(iii) For river/watercourses that are prone to scour and erosion, adequate safe cover shall be
provided below the predicted scour profile expected during the life time of the pipeline;
(iv) When scour level is not known, an additional cover of at least 1 m shall be provided from
the existing bed of the river/water course except in case of rocky river bed;
(v) The minimum cover requirements shall be applicable for all Location Classes;
(vi) Whenever the above provisions of cover cannot be provided due to site constraints,
additional protection in form of casings, bridging, etc shall be provided.
(vii) Soft soil/sand padding of minimum 150 mm thickness to be provided around the pipe where
gravel or hard soil is encountered. In case of rocky areas rock-shield along with 150 mm of
soft soil / sand padding around the pipe should be provided.
In case the pipeline is to be laid through populated area (which otherwise could not be
avoided), additional protective measures to be provided be by way of providing higher wall
thickness pipe or laying at a greater depth or by providing casing pipe.
10.4 Crossing of Utilities
any existing underground pipeline,
cable, drain or other services, the
10.4.1 When a buried pipeline has to cross
pipeline shall be laid at least 300
Location
10.6.5
10.7
Welding
and
Acceptance Criteria
Inspection
Welding Inspection
Dents
Hydrotesting of Pipeline
a)
b)
c)
All
sections
including
previously hydrostatically tested
one vis--vis road/rail and river
crossings shall be retested along
with
completed
mainline
sections.
11.2
g)
h)
Pressure Requirement
11.8
Commissioning
11.8.1
A proper commissioning
procedure shall be prepared for
removal of air from the system and
to prevent intermixing of air and the
hydrocarbons.
11.7
Documentation
Following records should be made:
(i)A complete pipe book including
hydrotesting data and location
of leaks or failures and
description of repair action
taken.
(ii) As built drawings like Route
(iii)
(iv)
(v)
(vi)
i) Temporary
modifications
required at the stations for
commissioning
have
been
completed in all respect.
j) Commissioning
check
list
prepared and ensured availability
of all materials tools , tackles and
consumable.
k) Fire fighting facilities shall be
kept ready.
l) Caution boards shall be displayed
while venting in progress.
m) Complete removal of moisture
shall be ensured.
n) Trained and experience personnel
are deployed to carry out
commissioning.
11.8.3
supervised
by
authorized
personnel.
(iv) Venting shall be controlled at
the pig-receiving end so that
proper
backpressure
is
maintained to control pig train
speed of 3 to 4 km /hr. The
desired portion of the pipeline
shall be commissioned in this
manner. The pipeline system
shall subsequently be slowly
pressurized up to its operating
conditions.
12.0
OPERATION
&
MAINTENANCE
A
detailed
operation
and
maintenance procedure for control
system and safety interlocks shall be
developed .
12.1
Operating Procedures
A comprehensive operating manual
shall be developed which shall
interalia include following:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
System Description
Operation set points
Initial start up
Normal operations
Normal shut down procedure
Temporary operations
Execution of emergency shut
down in a safe & timely
manner
(viii) Emergency shut down
(ix) Conditions
under
which
emergency
shutdown
is
required
(x) Emergency operations
12.2
12.3
Maintenance Procedure
A detailed maintenance procedure
shall be developed for entire pipeline
system
considering
the
recommendations given by the
original equipment manufacturer
keeping in mind the local conditions.
To facilitate the maintenance
services to be rendered in a planned
manner, a preventive maintenance
schedule covering necessary work to
be done, mentioning the periodicity
i.e daily, weekly, monthly, half
yearly and yearly schedule shall be
worked out and adhered to. This
should also include procedures for
repair by clamping, removal and
replacement of pipe / hot tapping
and stoppling etc. Adherence to
work permit system inline with
OISD-STD-105 shall be followed.
pipeline.
(b) Line Walk by the official of the
company at least twice in a
year shall be carried out before
and after the monsoon.
(c) The operating company shall
analyze the existing pipeline
for new anticipated external
loads, when the pipeline is to
be crossed by a new road or
railroad.
The
operating
company
shall
install
mechanical
reinforcement,
structural
protection,
or
suitable pipe, in case the
design parameters considered
are exceeding in order to
ensure redistribution of the
external loads acting on the
pipeline.
(d) Villagres / public along the
right of away shall be
adequately made aware of the
possible consequence of gas
leaks and this shall be included
as a part of regular audit.
12.3.3 Pigging
Pigging operation shall be carried
out for all pigable pipelines at least
once in a year for we gas and once
in 3 years for dry gas. Records of
quantity and quality of deposits (pig
residue) collected after pigging
shall be chemically examined.
Depending upon the out come of
the chemical analysis and review
pigging
frequency
shall
be
increased.
12.3.4
Intelligent Pigging
Intelligent pigging survey ( IPS)
shall be carried out once in 10 years
and this data shall be compared
with the data collected during
electronic geometric piging / caliper
pigging before commissioning to
asses the health of the pipeline. In
(b)
(c)
that
polarisation
potential is not more
negative than (-) 1.2
volts with respect to
copper/copper sulphate
half cells..
iii) Instant pipe to soil OFF
potential readings at test lead
points of entire pipeline shall
be taken once in a year. For
the purpose of logging the
instant OFF PSP, care shall
be taken to minimize the
effect of polarization decay.,
by logging the reading within
the first 1 or 2 seconds of
simultaneous switching of all
Cathodic protection station
affecting that section of the
pipeline. The PSP survey
results shall be plotted
graphically to identify and
locate cathodic holidays.
iv) Current consumption data
should be taken at the test
stations
where
current
measurement facility exist.
B) Cathodic protection rectifiers shall
be inspected once in two months.
C) All protective devices shall be
inspected once in two months.
D) Interference bonds shall be
inspected once a year.
12.3.6 Coating Survey
Pearson Survey / Direct Current
Voltage gradient (DCVG) /
Continuous Potential Logging
(CPL) survey / Current Attenuation
Test ( CAT) shall be carried out
once in 5 years. Insulating joints
and couplings shall be inspected
once in a year.
12.3. 7 Internal Corrosion Monitoring
Following monitoring techniques
should be used in the pipelines for
internal
corrosion monitoring.
a) Corrosion coupons
b) Corrosion
monitoring
equipment based on Electric
resistance
(ER)
technique,
electrochemical noise (ECN)
technique, & Linear polarisation
(LPR) technique
c) Iron count analyses
d) chemical analysis of pig residue
for other parameters
e) UT measurement at critical
locations
f) Intelligent pigging of pipeline in
line with para 12.3.4 above.
12.3.8
12.3.9
Inspection
of
Pumps,
Compressors,
Control
and
Protective Equipment
Periodic inspection and maintenance
shall be carried out for control and
protective equipment including
pressure limiting devices, regulators,
controllers, relief valves and other
safety devices in accordance with
OEM and following OISD standards
Pumps
:
OISD-STD-119,
Compressors : OISD-STD-120,
Pressure Limiting Devices: OISDSTD-132.
13.1
12.4
(ii)
(ii)
(iii)
(iv)
(v)
Centrifugal
fire water
pumps shall be installed to
meet the designed fire
water flow rate and head.
Pump shall have flooded
suction.
Motor driven Jockey pump
(not more than 10 M3 / Hr
of water flow) shall be
installed to maintain the
fire network pressure at 7.0
Kg/Cm2 at farthest end of
the network.
The fire water pumps
including the stand by
pumps shall preferably be
diesel
driven.
Where
electric supply is reliable
50% of the pumps may be
motor driven.
A minimum of 50% stand
by pump(s) (minimum one
no) of the same type,
capacity and head as the
main pumps shall be
provided.
The fire water pumps shall
be provided with automatic
starting facilities.
points.
(x) The deluge valve shall be
located at 15 mtrs. from the
risk being protected. A fire
wall shall be provided for
the protection of the deluge
valve and for operating
personnel.
(xi) Fire Hydrants/ monitors
shall be located at a
minimum distance of 15
mtrs from the hazardous
facility / equipment. Case
of buildings this distance
shall not be less than 2 mtr
and not more than 15 mtr
from the face of building.
Provisions of hydrants
within the building shall be
provided in accordance
with IS:3844.
(xii) At least one hydrant post
shall be provided for every
30 mtr of external wall
measurement or perimeter
of the battery limit.
Monitors shall be placed at
45 mtr interval.
13.1.7
Medium
System
Velocity
Sprinkler
13.2
13.3
MATERIAL SPECIFICATIONS
All material used in fire water system
using fresh water shall be of the type
indicated below
a) Pipes
- Carbon Steel (CS) IS:
3589 / IS :1239 / IS : 1978 or
Composite materials as per API
15 LR / API 15 HR or its
equivalent shall be used.
In case saline / brackish water /
treated effluent water is used , the
fire water main of steel pipes
shall be, internally cement mortar
lined or glass reinforced epoxy
13.5
HOSES,
NOZZLES
AND
ACCESSORIES .
(i) Minimum 2 Nos. or 25% spare
hoses shall be stored.
(ii) In addition to the nozzles
provided in the hose boxes there
shall be 1 set of spare nozzles
for each category viz- Jet
Nozzle with branch pipes, Fog
Nozzle, Universal Nozzle, water
curtain Nozzle and spray
Nozzle.
(iii) The following accessories /
first aid items shall be provided
in
each
compressor,
intermediate
and
terminal
delivery stations.
(a) Fire hoses 2nos / per
hose box / per hydrant
point- Minimum 10 nos.
(b) Safety helmets-1 no./person
(min 10 nos.).
(c) Stretcher with blanket- 2
Nos.
(d) First aid box- 1 nos.
(e) Rubber hand gloves for
electrical purpose- 2 nos.
(f) Low temperature rubber
hand gloves - 4 pairs.
(g) Fire proximity suit- 1 no.
(h) Resuciator - 1 No.
(i) Red / green flags 2 nos. in
each colour
(j) Self contained breathing
apparatus with one spare
cylinder (cap 30 min) 1 set
13.7
13.8
13.9
Communication System
(i) Communication system like
telephone / PA or paging,
walkie-talkie, optical fibre cable
based communication system
shall be provided.
(ii) All intermediate stations
including IP stations / Repeater
station shall be provided with
proven communication system.
Security at unmanned station
shall be trained to deal with
communication and emergency
handling.
13.10
Emergency Plan
A mutual aid scheme for the fire
fighting and emergency rescue
operation shall be
made
involving local industries , local
govt. agencies. Mock drill
involving all mutual partners
shall be conducted at least once
in a year. The emergency plan
shall be prepared based on the
following:
a)
b)
c)
d)
e)
f)
Risk scenarios
Flow balance
Organisation structure
Emergency Trainings
Responsibility
14.0
PIPELINE INTEGRITY
MANAGEMENT (PIM)
14.1
A
comprehensive
manual
containing program & practices
shall be developed for existing
pipeline / after construction of
the new pipeline to manage
pipeline integrity taking into
consideration
consequence
classification / category
of
pipeline, and risk involved in
each segment of the pipeline.
14.5
14.6
14.2
The
integrity
management
program framework shall take
into consideration continual /
periodic assessment & an
evaluation process as to its
effectiveness of the current
health of the pipeline & to
prevent any failure in future.
14.3
14.4
(b)
(c)
(d)
(e)
14.7
15.0
15.1
ABANDONMENT OF PIPELINE
A pipeline system that is no longer
required for transportation of gas
shall be taken out of service with all
hazardous fluids removed from the
system.
In
case a operating
company decides to abandon full or
part of the pipeline system
permanently or temporarily after
obtaining necessary approval from
the statutory authority (if required),
it shall prepare a detailed plan
considering the following. Large
scale venting of natural gas shall be
avoided. It shall be ensured that
most of the natural gas contained in
the system shall be utilized by
consumer.
(i) Pipeline section and facilities
shall be disconnected from all
source of supply of gas.
(ii) Pipeline system and facilities
to be abandoned shall be
purged with nitrogen gas or
inert materials and ends hall be
sealed. If the facilities are
purged with air, it shall be
ensured
that
combustible
mixture is not present in the
system
15.2
Decommissioning
Plans and procedures shall be
developed for safe decommissioning ,
dismantling, demolition, and disposal
of the pipeline and shall include the
following.
(i) Maintenance of the facility shall
continue till full dismantling of
facilities have been completed.
(ii) Cathodic protection system shall
be maintained with periodic
inspection.
(iii)
Environmental
impact
assessment.
18.3
REFERENCES
This standard shall be read in conjunction with the following standards, codes and
publications:
(i)
(ii)
(iii)
(iv)
(v)
ASME B31.8
API -617
API- 618
API- 11P
API 1102
(vi)
(vii)
API 1104
API 1107
API 1110
(x)
API 500C
(xi)
API- 5L
(xii) API- 6D
(xiii) ASME Section VIII
(xiv)
(xv)
ASME Section IX
MSS-SP-50
(xvi)
MSS-SP-69
(xvii) NACE-RP-01-69
(xviii) NACE-RP-01-75
(xix) ISA S-75.01
(xx) ISA S-75.02
(xxi) IEC 79
(xxii) IEC 529
(xxiii) OISD-STD-105
(xxiv) OISD-STD-118
(xxv) OISD-STD-120
(xxvi) OISD-STD-128
(xxvii) OISD-STD-130
(xxviii) OISD-STD-132
(xxix) OISD-STD-137
(xxx) OISD-STD-141
(xxxi) OISD-STD-142
(xxxii) OISD-RP-149
(xxxiii) OISD-STD-153
(xxxiv) OISD-GDN-178
(xxxv) OISD-STD-195
Annexure -1
ANNEXURE -II
DETERMINATION OF LOCATION CLASS
C-1 Population density index along the pipeline route shall be determined as follows:
As zone, 400 m wide, shall be considered along the pipeline route with the pipeline in the
centre-line of this zone. Then the entire route of the pipeline shall be divided into lengths of
1600 m such that the individual lengths will include the maximum number of dwellings intended
for human occupancy. The number of such dwellings which are intended of human occupancy
within each 1600 m zone shall be counted and reported along with other survey data.
C-2 Areas shall be classified based on guidelines as given below:
a) Class 1 Location A class 1 location is any 1 600 m section that has 10 or
fewer dwellings intended for human occupancy;
b) Class 2 Location A class 2 Location is any 1 600 m section that has more
than 10 but less than 46 dwellings intended for human occupancy;
c) Class 3 Location A class 3 Location is any 1 600 m section that has 46 or
more dwellings intended for human occupancy except when a Class 4 Location
prevails; and
d) Class 4 Location A class 4 Location include areas where multi-storey
buildings are prevalent, and where traffic is heavy or dense and where there may be
numerous other utilities underground. Multi-storey means four or more floors above
ground, including the ground floor and irrespective of depth of basement or number of
floors of basement.
C-3 In addition to the criteria contained in C-2 a) to d), while classifying areas, additional
consideration must be given to possibilities of increase in concentration of population along the
pipeline route such as may be caused by the presence of schools, hospitals, recreational areas of
an organized character, places of assembly, places of worship, etc. If one or more of these
facilities are present, the area shall be classified as a Class 3 location.
C-4 Notwithstanding the above, while determining class location of an area due consideration
shall be given to the possibility of future development of the area during the design life of the
pipeline. If it appears likely that future development may cause a change in the location class,
this shall be taken into consideration while determining its class location.
C-5 : When cluster of building intended for human occupancy indicates that a basic 1.6 km
should be identified as a location class 2 or 3, the location class 2 or location class 3 may be
terminated at 220 mtr from the nearest building in the cluster.
ANNEXURE- III
S.No.
1
2
3
4
5
6
7
8
9
10
From / To
Small Compressor /
Pump
House
Main Compressor House
Scraper Launcher
Scraper Receiver
Control Room / Office building
/ Store
Fire Pump House / Fire water
storage tanks
Water Spray Deluge Valve
Cold Flare
Compound wall
Elect Sub station,
1
-
2
15
3
15
4
15
5
16
6
60
7
15
8
15
9
30
10
15
15
15
15
16
15
15
16
15
x
16
15
x
16
16
16
16
-
60
30
30
30
15
15
15
15
15
15
15
30
30
15
15
30
30
30
30
-
60
60
30
30
30
60
12
15
15
30
15
15
15
30
30
15
15
15
30
15
15
15
30
15
30
30
-
60
12
-
15
15
15
15
30
15
15
15
30
15
-
ANNEXURE IV.
TO CONSUMERS/
DOWNSTREAM P/L
GAS FROM PRODUCER/
UPSTREAM PIPELINE
FILTER
SEPARATOR
TO DISPOSAL
CONDENSATE TANK
STARTING GAS
CONDITIONING
UNIT
FUEL GAS
CONDITIONING
UNIT (GTG)
FUEL GAS
CONDITIONING
UNIT (GTG)
FUEL GAS
METERING
SYSTEM
GT GENERATOR
GT
POWER
COMPRESSOR
EXHAUST
AFTER COOLER
PART -II
CITY GAS DISTRIBUTION NETWORKS
1.0
INTRODUCTION
a. Consumer
Meter
(CM)
for
Commercial & Industrial Consumers
DEFINITIONS
a. Authorised Person: A person
trained and assigned to carry out a
specific job by the owner or PNG
Distribution Company.
b. Active Regulator: Regulator in PRI
that normally controls the outlet
pressure
are
SCOPE
This standard lays down the
minimum safety requirements for
PNG Distribution in cities/towns. It
covers the equipment, pipelines,
accessories etc. installed between
Up-Stream Inlet Isolation Valve of
City Gate Station (CGS) and;
p. Shall
:
Indicates
requirement.
mandatory
s. Service
Regulator:
Regulator
installed on a gas service line to
control the pressure of the gas
delivered to customer.
4.0
STATUTORY REGULATIONS
It is necessary to comply with
statutory regulations such as State
Pollution Board, Factories Act,
Indian Explosives Act, IE Rules,
Municipal Authorities etc as
applicable and requisite approvals
shall be obtained from the relevant
competent authorities for the PNG
46
distribution system.
5.0
5.1
PRESSURE
REGULATING
STATIONS (CGS & PRI)
5.1.1
5.1.3
ISOLATION OF CGS
Quick acting isolation valves shall
be provided at CGS for emergency
isolation purpose.
5.2
5.2.1
STEEL PIPING
e.
5.2.2
5.2.3
Nominal
outside
dia, mm
Dn
16
20
25
32
40
50
63
75
90
110
125
140
160
180
200
SDR
13.6
2.3
2.3
2.3
2.3
3.0
3.7
4.7
5.5
6.6
8.1
9.2
10.3
11.8
13.3
14.7
SDR
11
3.0
3.0
3.0
3.0
3.7
4.6
5.8
6.8
8.2
10
11.4
12.7
14.6
16.4
18.2
of
STRATEGIC VALVES
SDR
9
3.0
3.0
3.0
3.6
4.5
5.6
7.1
8.4
10.1
12.3
14
15.7
17.9
20.1
22.4
5.3
CONSUMER INSTALLATIONS
48
5.5
5.4
iii.
b. Close
proximity
to
unstable
structures or where construction
could lead to damage to pipeline.
a) Name of
company
PNG
distribution
PROXIMITY TO PROPERTIES
The minimum distance between steel
pipelines, having operating pressure
of 4 barg or more and the normally
occupied buildings shall be 2 meters.
g. Landfill sites.
h. Steel piping should avoid;
i.
ii.
5.7
PNG ODOURISATION
e.
i. Four numbers 10
FIRE PROTECTION
FACILITIES
DCP
DCP
Foam
kg
CO2
MCC / ELECTRIC
INSTALLATION
Following fire extinguishers shall be
provided:
kg
5.8
a. One no. 10
kg DCP
50
c. Sand Buckets
5.9
6.0
FOOTPATH
ROAD
LAYING OF PIPELINE
TELECOM
ELEC
(HV)
CABLE
PNG
WATER
51
250 mm=
500 mm=
500 mm=
Rocky Areas
1. 0
Road Crossings
1. 2
Railroad Crossings
1. 7
1. 0
NOTE :
(i)
(ii)
250 mm =
(iii)
(iv)
500 mm=
DEPTH OF COVER
Minimum depths of cover for buried
pipelines shall be as per the table
given below;
Location
Industrial, Commercial
and Residential Areas
Min.
Cover in
meter
1. 0
1. 5
Drainage ditches at
roadways and railroads
1. 0
52
LAYING OF PE PIPE
During installation of PE piping,
care shall be taken to prevent
damage to piping and components.
Gouge , cuts, scratches, kinks /
buckle or other form of damage shall
be removed by cutting out and
replacing the damage portion as a
cylinder.
6.5
BACK FILLING
Back filling shall be performed in a
manner to provide firm support
around the pipe. Material used for
back filling shall be free from rock,
pieces of pavement, stones or any
other material which can damage the
pipeline.
6.6
6.7
of
fire
fighting
c. Availability
facilities
of
communication
SERVICE LINE
e. Warning Signs
d. Availability
of
inspected
&
calibrated testing equipment /
instruments
7.2
TESTING OF INSTALLATIONS
7.2.1
Strengt
h Test
Pr.
(bar)
0.3
i.
ii.
iii.
iv.
Duration
Hydro.(H)/
Pneu. (P)
2.0
P
30 min
P
30 min
3.0
1.5 DP
H (4hrs)
H
4hrs
H
4 hrs
b. TEST DURATION
The duration of pneumatic testing of
service line and internal installation
shall not be less than 30 minutes.
8.0
8.1
PNEUMATIC TESTING
55
Type
General
Inspection
Freq.
Daily
Once a
month
Safety
Audit
Once a
year
Electrical
Audit
Once a
year
Agency
Operating
personnel
Engineering
in-charge of
PNG mktg.
Company
Authorised
Person (s) /
Agency
Licensed
Electrical
Agency
8.3
q. Equipment
appurtenances,
protection devices associated with
the PNG system as incorporated in
the design shall be tested,
maintained, repaired and replaced as
recommended by the manufacturer.
MODIFICATIONS
PIPELINES
TO
LIVE
8.4.1
PRESSURE CONNECTIONS
a. Metallic Pipelines:
Connection should be made to live
metallic pipeline by direct drilling
and tapping using proprietary fittings
and no gas to atmosphere drilling
equipment (hot tapping). Hot
tapping
procedures
for
steel
pipelines At annexure V.
Only fused connections shall be
made to PE mains using compatible
polymeric material and as per
applicable code.
v.
Major failure
fittings
Civil emergencies
ii.
iv.
i.
b. PE Mains:
9.0
iii.
equipment/
a.
PNG.
i.
ii.
iii.
b.
Familiarization
with
operational procedures & practices.
c.
Commissioning
of
facilities and equipment..
d.
Hands on experience
operation of equipment..
on
e.
Routine
checks
maintenance activities of
facilities.
and
the
f.
Knowledge of emergency
and manual shut down systems.
g.
new
iv.
h.
Safety
regulations
accident prevention.
v.
i.
10.0 TRAINING
10.1
Hazardous characteristics of
j.
Housekeeping
k.
First aid.
l.
Emergency plan/drills
and
11.0
RECORDS
The PNG distribution company shall
maintain
following
records/
documents:
REFERENCE S
59
60
Annexure-I
Steel
INLET
FROM
SUPPLIER
Mains
PRI Combined
Meter
PE/ Steel
PE/ Steel/
Copper
Mains
City Gate
Station
(CGS)
PRI Industrial
Appliances (Domestic,
Comm.& Industrial
Service
Meter
Industrial Appliances
PE/ Steel
PE/ Steel
Mains
service
Steel
Mains
PRI
Residential/
Commercial
Meter
PE/ Steel
Mains
Steel
Mains
PE/ Steel/
Copper
Dom./ Comm.
Appliances
Service
Compressed
Natural Gas
Dispensing
Station
NOTE : Compressed Natural Gas Dispensing Station is not covered under the scope of this standard
Standard on Natural Gas Transmission Pipelines and City gas distribution networks
Annexure-II
Filter
PSV
Isolation
Valve
INLET
Stand by
Odourant
Injection
Stand by
STAND BY
STREAM
OUTLET
Meter
NRV
Slam-Shut Valve
Active/ Monitor Regulators
Creep Valve
Annexure-III
Creep
Valve
Standard on Natural Gas Transmission Pipelines and City gas distribution networks
NRV
Slam Shut
Valve
INLET
Isolation
Valve
Filter
Active/ Monitor
Regulators
Outlet
Stand-by Stream
ANNEXURE - IV
1. Recommended specification of GI pipes used for domestic gas piping above ground up to the isolation valve after the meter
Pipes shall be conforming to IS: 1239 (Part-1) 1990. The manufacturer shall have a valid license to use ISI Monogram for manufacturing of
pipes in accordance with the requirements of IS: 1239 (Part-I) 1990.
63
Standard on Natural Gas Transmission Pipelines and City gas distribution networks
NOMINAL
BORE
GRADE
O.D. mm
max.
Min.
THICKNESS mm
NOMINAL
WEIGHT
Kg / mtr
15 mm
25 mm
50 mm
80 mm
HEAVY
(C CLASS)
HEAVY
(C CLASS)
HEAVY
(C CLASS)
HEAVY
(C CLASS)
21.8
21.0
34.2
33.3
60.8
59.7
89.5
88.0
3.2
4.0
4.5
4.8
1.44
2.93
6.19
9.90
Note:
Maximum tolerance on thickness (-)10%, Tolerance on weight for single tube 10% and for quantities per load of 10 tonnes, 7.5%.
Pipes shall be designed to withstand a test pressure of 5 MPa (50 Kgf / cm 2), maintained for at least 3 second without showing any kind
of defects.
Eddy Current test may be done in place of hydrostatic test as per the procedure given in Annex - C of IS: 1239 (Part-1) - 1990.
All Galvanised Tubes shall be Zinc coated by hot dip galvanising in accordance with IS: 4736-1986 & its relevant parts.
Minimum mass of zinc coating determined as per IS: 6745-1972 shall be 400 gms / m2.
The zinc coating on external and internal surfaces shall be adherent, smooth and free from such imperfections as flux, ash & dross
inclusions, bare patches, black spots, pimples, lumpiness, runs, rust stains, bulky white deposits and blisters.
Rejection and acceptance for these defects shall be as per Appendix-A of IS: 2629-1985
The galvanised coating when determined on a 100 mm long test piece in accordance with IS: 2633 - 1986 shall withstand 4, one minute dips.
The adherence of zinc coating on tubes above 50 mm nominal bore, shall be determined by the pivoted hammer test given in IS : 2629 1985.
Each pipe shall be legibly and durably marked at intervals of not more than one metre with the following information (i) Manufacturers name
or trade mark, (ii) Class of Pipe HEAVY, (iii) Indian Standard mark ISI, (iv) Batch No. of Production, if any.
2. Recommended specification of copper pipes used for domestic gas piping inside the residence up to the isolation valve after the
meter
64
Standard on Natural Gas Transmission Pipelines and City gas distribution networks
For a copper service in domestic natural gas installations, materials supplied shall be in accordance with BS EN 1057:1996, it has replaced
the copper tube standard BS 2871 Part 1. BS EN 1057 ensures the quality of the copper product by specifying the pipe in terms of its
chemical composition, mechanical properties (tensile strength, hardness, elongation etc.), dimension and tolerance, surface quality, freedom
from defects and suitability for pipe bending.
Copper pipe work shall be jointed by soldering or brazing, using mechanical compression or capillary type fittings. Fittings for use in joining
copper tube shall be as per BS EN 1254 Parts 1 and 2. Fittings for capillary soldering and brazing are specified in Part 1 and compression
fittings are specified in Part 2.
Soft soldering utilises filler metals with melting points at temperatures up to 450C. Filler metals shall be as per BS EN 29453:1994 - Soft
solder alloys - Chemical compositions and forms. Solders for use with copper tube and fittings generally melt within the temperature range
180C to 250C. Compression fittings shall be comply with BS 864 Part 2 or BS 2051 Part 1.
For capillary fittings:
Height limit for copper risers: Although there is no specific guidance regarding maximum height of copper risers, IGE/UP/2 only allows the
use of steel for risers above heights of 15 meter. Thus, unless local information is available to the contrary, 15-meter maximum height shall
be considered safe due to weight and mechanical strength of material.
General guidance in BS 6891 also states that copper pipe work is not acceptable inside a protected shaft. Requirements for ventilation and
fire stopping shall apply to ducts conveying copper pipe work. For an external copper riser system, protection against lightning conductors
shall be considered.
Last but not least, a copper gas line shall never be used as a ground for an electrical system.
65
Standard on Natural Gas Transmission Pipelines and City gas distribution networks
3. Recommended specification of rubber hose used for connecting the Gas Stove after the isolation valve to the Gas Stove.
Rubber hose shall be conforming to IS: 9573 Type IV. The hose shall consist of lining, reinforcement and cover.
The Hose should not be exposed to internal or external temperature exceeding the recommended limits, as high heat conditions can cause
an adverse effect on the hose by degrading the Elastomer and thereby reducing fitting retention.
The hose size must be capable of handling the required flow volume. Using the smaller than required diameter of hose for a given volume of
flow would, result in excessive fluid turbulence, pressure drop, heat generation and tube damage.
The hose should not be bend or flex beyond the specified parameter (refer, Table 1 Dimensions and Bend radii for Rubber Hoses, IS: 9573),
as this would put excessive stress on the reinforcement and severely reduce the ability of the hose to withstand pressure.
Hoses in service should be checked every year, for leakage, kinking, corrosion, abrasion or any other signs of wear and damage. Any hose
worn or damaged must be removed from service and replaced immediately
4. Recommended specification of the domestic gas burner.
The gas stove shall be manufactured and checked in accordance to IS: 4246, IS: 11480 and IS: 5116. The following tests are conducted, (i)
strength testing, (ii) thermal efficiency, (iii) combustion, (iv) gas soundness test, (v) floor wall & ceiling temperature measurement (vi) gas
consumption test.
The jet nozzle of the gas burner shall be designed for a standard length of 11mm, with a tolerance of 0.2mm. The bore at the bottom of the
hose is of 2.38 mm diameter (tolerance +0.1, -0.15). The hole on the top of jet is of diameter 1.25 mm or 1.10 mm (tolerance +0.02, -0.01)
based on the capacity. (Refer fig. 1 & 2)
66
Standard on Natural Gas Transmission Pipelines and City gas distribution networks
67
Standard on Natural Gas Transmission Pipelines and City gas distribution networks
Annexure - V
Details of the online procedures for Steel pipelines where hydro testing is not recommended. Hot tapping
Procedure for Hot tapping on pipelines in-service shall comply to IS: 15679 : 2006. Hot tapping is the technique of attaching a mechanical or
welded branch fitting to piping or equipment in service, and creating an opening in that pipeline by drilling or cutting a portion of the piping
within the attached fitting.
Hot tapping shall be performed when it is not feasible, or impractical to take the piping out of service, or to purge or clean it by conventional
methods. A hot tap connection can often be safely made without interfering with the process operation.
Prior to conducting hot tapping, a written plan shall be prepared which includes the following,
Connection design
Hot tap procedure
Detailed written welding procedure
Health, safety, fire protection, emergency response, and other appropriate procedures & instructions.
Additional information when developing a written plan may be obtained from Section IX of the ASME Boiler and Pressure Vessel Code for
qualification of welders and the fundamental ASME Code welding procedure to be employed.
Note: Section IX does not cover the condition encountered while welding on in service piping containing flammable and combustible liquids.
Refer to API Recommended Practice 1107 for qualification of welders and the welding procedures to be employed when welding on inservice flammable and combustible liquid piping.
The tightness of bolts, packing, packing nuts and any by-pass line shall be checked to avoid any possible leakage. The test pressure should
be atleast equal to the operating pressure of the line or vessel to be tapped. But it shall not exceed the present internal pressure by more
than approximately 10%, in order to avoid possible internal collapse of the pipe or vessel wall.
68
Standard on Natural Gas Transmission Pipelines and City gas distribution networks
Annexure - VI
Details of the online procedures for PE pipelines where hydro testing / pneumatic testing is not recommended. EF Jointing
MDPE pipeline is constructed by joining together lenghts of PE pipe. The PE pipes can be joined by a variety of joining techniques like
electrofusion couplings, butt fusion and mechanical jointing. However, the most preferable method shall be electrofusion jointing. Smaller
service pipes or spur lines can be taken off the live PE main by tapping tees to the top of the pipes using the EF jointing method.
PE fittings used for EF jointing shall be made as per ISO 8085, Part 3 Polyethylene fittings for use with polyethylene pipes for the supply of
gaseous fuels Electrofusion fittings
The Electrofusion jointing shall be carried out as per ISO DTR 10839 Recommended practice for laying of PE pipes . Electrofusion type of
jointing shall be applied to pipe / fittings of same Outside Diameter and Wall Thickness. The surface of the pipe shall be scrapped to ensure
that it is free from Burrs and oxide layer at the pipe ends to be welded. Pipe ends shall be free from grease or other dirt & the degreasing
shall be done by Isopropyl Alcohol.
The End faces of pipe to be welded shall be at right angle to pipe axis. Gap between pipe-pipe or pipe-fittings or fittings-fittings shall not be
more than 0.3 mm for all sizes after planing.
The Electrofusion jointing shall be carried out using standard EF jointing machines. During the Electrofusion welding process ,the frequency
& voltage of generator supplying power shall not outside the prescribed range of the EF machines. The use of Top-loading clamp is a must
during the entire heating cooling cycle. The heating & cooling time for each joint shall be fed into the EF machine either by bar code readers
or manually.
69